0% found this document useful (0 votes)
32 views1 page

Dyliacco Gantt Chart 12 13 23

The document outlines the scope of works for a proposed 2-storey residence and basement including general requirements, earthworks, concreting works, rebar and steel works, formworks, metal works and roofing, and masonry works. It provides details on each item, estimated weights, amounts, and projected monthly progress over a 16 month period.

Uploaded by

docwit10
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
32 views1 page

Dyliacco Gantt Chart 12 13 23

The document outlines the scope of works for a proposed 2-storey residence and basement including general requirements, earthworks, concreting works, rebar and steel works, formworks, metal works and roofing, and masonry works. It provides details on each item, estimated weights, amounts, and projected monthly progress over a 16 month period.

Uploaded by

docwit10
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 1

PROJECT Proposed 2-Storey Residence + Basement

LOCATION Venare, Calamba Laguna


OWNERMr. & Mrs Ray Dy-Liacco
DATE Dec 14,2023

ITEM Scope of Works WEIGHT AMOUNT Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10 Month 11 Month 12 Month 13 Month 14 Month 15 Month 16
NO. % 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

I. GENERAL REQUIREMENTS 2.00% 170,000.00 100


City Hall Building Permit /Electrical/Plumbing/ Occupancy Permit/ by Owner %
1 Meralco dep/ Permit Taxes
2 Village Bonds,Construction Bonds, Water meter by Owner
3 Temporary Facilities/Site Preparation 0.59% 50,000.00
4 Temporary Power Supply/Water Supply 0.35% 30,000.00

5 Mobilization/Demobilization 0.59% 50,000.00

0.35% 30,000.00
6 As-built Plan 95%
7 Site Clearing 0.12% 10,000.00

II. EARTHWORKS 5.13% 436,085.00

1 Excavation 3.14% 267,200.00

2 Backfill 0.28% 24,135.00

3 Grading & Compaction 0.32% 27,000.00


90%
4 Soil Poisoning (initial 1 application only) 0.09% 7,500.00

5 Hauling of Debris 0.94% 80,000.00

6 2" Thick Gravel Bedding 0.24% 20,250.00

7 Layout & Staking 0.12% 10,000.00

11.48% 976,164.75
III. CONCRETING WORKS 85%
1 Slab on grade 1.84% 156,444.75

2 Suspended Slab 2.18% 185,625.00

3 Footing 1.83% 155,331.00

4 Column Pedestal 0.70% 59,400.00

5 Concrete Column 1.42% 120,285.00


6 Footing tie beam 0.55% 46,332.00
152,732.25
80%
7 Concrete Floor Beam 1.80%
8 Lintel Beam 0.28% 24,131.25

9 Roof Beam 0.68% 57,469.50

10 Wall Footing 0.22% 18,414.00

IV. REBAR & STEEL WORKS 16.88% 1,434,867.48 75%


1 Slab on grade 0.67% 56,652.75

2 Suspended Slab 1.65% 140,057.78

3 Footing 0.74% 62,592.75

4 Column Pedestal 1.23% 104,722.20

5 Column 5.80% 492,864.08


70%
6 Footing tie beam 0.64% 54,515.09

7 Floor Beam 4.43% 376,313.85

8 Lintel Beam 0.10% 8,761.50

9 Roof Beam 1.15% 98,010.00

10 Wall Footing 0.10% 8,787.49

11 tie wires 0.37% 31,590.00 65%


V. FORMWORKS 2.73% 231,842.00

1 Suspended Slab (steeldecking ) 1.46% 124,020.00


2 Footing 0.62% 52,780.00
3 Column 0.26% 22,040.00
60%
4 Footing tie beam 0.25% 20,880.00
5 Lintel Beam 0.08% 6,467.00
6 Wall Footing 0.07% 5,655.00
VI. METAL WORKS & ROOF 2.07% 176,044.05
A. STRUCTURAL STEEL WORKS
1 Steel Trusses Roof Framing 2.07% 176,044.05
55%
B. ROOFING WORKS 0.00%
Stone coated metal roofing,fascia ,accs., insulation w/o gutter by Others 0.00%
VII. MASONRY WORKS 21.54% 1,830,908.95
1 125 mm CHB 9.16% 778,410.00
2 100mm CHB 2.95% 250,574.85
10 mm rebars 1.10% 93,174.10 50%
3
4 Plastering 6.67% 567,000.00

5 Concrete topping 1.67% 141,750.00

VIII. ARCHITECTURAL FINISHES 13.85% 1,177,452.20

A. FLOOR FINISHES
1 Floor Tiling OSM 1.15% 97,796.00
45%
B. WALL FINISHES
1 Wall tiling OSM 0.89% 75,591.00
C. CEILING FINISHES

1 10mm thk Standard Core Gypsum Board (flat ceiling layout) 3.96% 336,376.80

2 PVC ceiling on metal furring (exterior,eaves, lanai, terrace, garage) by Others


D. PAINTING WORKS
168,188.40
40%
1 Flat Latex Paint Finish (gypsum ceiling) 1.98%
3 Latex Wall Paint Finish 5.56% 472,500.00

4 Matte Varnish Finish (on wood jambs) 0.32% 27,000.00

IX. DOORS & WINDOWS 0.54% 45,700.00

A. Doors / Jambs
35%
1 Door ,Jamb installation OSM 0.39% 33,500.00
4 upvc framed sliding door with clear glass by Others
B. Windows
1 Upvc framed windows with clear glass by Others
C. Hardware
30%
1 Locksets OSM 0.11% 9,000.00

2 Hinges OSM 0.04% 3,200.00

X. SPECIALTIES

1 Mirror: (on toilet & bath) by Others

2 Bedroom Closet (local carpentry works - 3/4" marine plywd))


by Others

by Others
3 Kit Cab w/ tile counter top (carpentry works - 3/4" marine plywd) 25%
4 Wood Stair steps on concrete frame w/ steel,glass railings by Others
5 Balcony railings by Others
XI. THERMAL & MOISTURE PROTECTION

A. WATERPROOFING WORKS
1 Toilets & terrace by Others
2 Basement wall earth support by Others
20%
XII. ELECTRICAL WORKS 3.91% 332,500.00

A. WIRES THHN 1.41% 120,000.00

B. CONDUITS & FITTINGS OSM 1.06% 90,000.00

C. BOXES OSM 0.26% 22,500.00

D. MISC 0.18% 15,000.00

E ELECTRICAL DEVICES (switches,c.o.,plates) by Others 0.18% 15,000.00


15%
F LIGHTING FIXTURES by Others 0.29% 25,000.00

G PANEL BOARD & BREAKERS by Others 0.29% 25,000.00

H Auxillary (cctv,catv,tel,net,intercom)OSM wires by Others 0.24% 20,000.00

XIII. PLUMBING WORKS 5.01% 425,900.00

A. SEWER & SANITARY SYSTEM 1.94% 165,000.00


10%
B. COLD WATER SYSTEM PPR 2.65% 225,000.00

C. Catch basin cover, Area & Floor drains OSM 0.06% 5,000.00

D. PLUMBING FIXTURES OSM 0.36% 30,900.00

XIV. MECHANICAL WORKS 0.09% 15,000.00

1 Window-type air-conditioning units (incl drain) by Others


2 Exhaust fans,Water heaters OSM
5%
3 Pumps, tanks, motors, Stainless Cistern tank OSM 0.18% 15,000.00

XV. RETAINING WALL 3.59% 305,401.67

Rear, Left & Right side chb fence @ 2mt ht (painted) 3.59% 305,401.67

XVI. FENCE 4.32% 367,420.05

Rear, Left & Right side chb fence @ 2mt ht (painted) 4.32% 367,420.05 0%

Contingencies,OH/Profit 6.85% 582,051.12


:
100.00% 8,500,000.00

You might also like