Method-Statement For Structure Assembly and Erection
Method-Statement For Structure Assembly and Erection
Page :1/9
Owner
NILANCHAL ISPAT NIGAM LIMITED
VENDOR
Project
NILANCHAL ISPAT NIGAM LIMITED CDCP STRUCTURE REVIVAL WORK
Prepared
Approved
ERECTION METHOD STATEMENT
FOR
CDCP STRUCTURE ERECTION
Department MECHANICAL
W.O.NO-3800000024
1
JOB No.
Page :2/10
CONTENTS
1. INTRODUCTION
1.1 OBJECTIVE
1.2 SCOPE
2. WORK CONDITION
2.3 SCHEDULE
3. WORK METHODOLOGY
4. QUALITY REQUIREMENTS
5. SAFETY ANALYSIS
pg. 2
JOB No.
Page :3/10
1. INTRODUCTION
1.1 Objective:
The purpose of this work procedure is to detail for the Erection of Structure, that shall be
followed during the execution of the project.
1.2 Scope:
The procedure covers all activities related to Erection of Structure that shall be carried out
while the execution of the project.
2. WORK CONDITION:
To under stand the scope of work and decide in how many lifts the columns & Beams are
to be positioned. This will give us a fair under standing of the total height that is to be
achieved while erecting the structure.
Manpower Utilization:
pg. 3
JOB No.
Page :4/10
3. WORK METHODOLOGY:
Prepare the Temporary arrangement for changing the sling after erection.
Arrg. of Temp. Platforms where ever reqd.
Approval of Method Statement YES
NO
Further Process
pg. 4
JOB No.
Page :5/10
3.2.1.2. Checking the verticality of column and center to center distance between
the columns.
3.2.1.4. Tightening of base plate bolt and release for grouting as per specification
3.2.1.6. Temporary Erection loads or permanent loads shall not be placed on any
incomplete portions of the structures being erected.
3.2.1.7. Temporary arrangements like providing working platforms / Man lift etc. on
the columns to facilitate guiding and positioning of the structures and for
removing of the slings.
3.2.2.1 All the structural erection activities shall be carried out after the approval /
clearance of the foundations by the customer representatives.
3.2.2.3. The civil foundations for the structural shall be checked for any defects. If
there is any defect the same shall be repaired before the erection of the
structural into the foundation. The top of the concrete level shall be as per
drawing limits and the same shall be recorded.
3.2.2.4. The size of the bolts, number of nuts, height of the bolt shall be checked prior
to erection.
The condition of the foundation bolt shall be checked before the commencement of the erection.
3.2.3.1 Crane of suitable capacity along with all the necessary accessories shall be
employed for the erection purpose. It shall be ensured that the crane used
shall be in possession of all the safety requirements as emphasized.
pg. 5
JOB No.
Page :6/10
3.2.3.2 To ensure having the valid crane load test certificate at site. The location of
crane and trailer positioning shall be clearly identified, prior to receiving the
structural material at site.
3.2.3.4 The Latest revision drawing for the structure that is to be erected shall be made
available at site for ready references.
3.2.3.5 The tools and tackles will be checked for the availability of the required quantity as
per checklist.
3.2.3.6 The valid test certificates for the rigging equipment, tools and tackles shall be ensured
for the lifting requirements.
3.2.3.7 It shall be ensured that the necessary permits from Safety Engineer, Customer and
Consultant for erection are obtained prior to the commencement of the works.
3.2.3.8. Ensure the back filling / compaction is done and the area is workable as well as
approachable for working.
3.2.4.1 All the transportation/maneuvering & lifting operation shall be carried out under the
sole control of the designated Execution Engineer / Supervisor.
3.2.4.2 Pre assembly of columns and tie beams to make the H-frames in segments to
achieve the safe erection are done at the ground level. The same shall be lifted with
the suitable crane and installed over the foundations.
3.2.4.3 Ensure horizontal bracings are erected to make box in each level before next level of
column erection.
3.2.4.4 After the positioning of all the structural elements, including vertical and horizontal
bracings, the final connection shall be carried out by Bolting / welding.
3.2.4.5 If any alterations are to be carried out, then prior approval to be sought from the
Customer / Consultant before taking up the work.
3.2.4.6 After the final positioning, bolting and welding (if required) is completed, the
Structure shall be offered for Inspection to QA/QC department/Consultant
representatives.
Quality requirements are to be written down prior to the starting of the job in the
quality plan. The same should get approved by all concerned. Ensuring that all the
quality requirements are adhered is the responsibility of the QA/QC Engineer.
pg. 6
JOB No.
Page :7/10
pg. 7
JOB No.
Page :8/10
8
JOB No.
Page :9/10
ensured
9
JOB No.
Page :10/10
-Fire hazard
- Safety
- Protection Shed/cover is Engineer /
to be provided for welding Electrical
machine. Position the engineer
welding machines at a
elevated position to avoid - Safety
coming in contact with Engineer.
water.
- Cable condition is to
be checked &Leather
hand gloves to be used
-Area is to be cordoned
off
-Proper warning board is
to be displayed
10
JOB No.
Page :11/10
-Condition of regulator,
hose & torch to be
checked
-Stone lighter is to be
used
-Fire extinguisher is to be
kept ready
11