Weekly Activity Plan
Weekly Activity Plan
Week of March 24
14 Internal Partition Works- Single Side 12 days
35 Supply & Installation Fire Alarm & Fire Fighting Works 40 days
37 Supply & Instllation of Ducting Works 30 days
41 Coring Works For the Slab 5 days
Week of March 31
14 Internal Partition Works- Single Side 12 days
35 Supply & Installation Fire Alarm & Fire Fighting Works 40 days
37 Supply & Instllation of Ducting Works 30 days
41 Coring Works For the Slab 5 days
12 Supply & Installation of 20cm thick Block Wall with Lintel & Plastering 18 days
24 Drainage Piping Works 10 days
25 Hot & Cold Water Piping Woks 8 days
29 Conduiting Works 10 days
Week of April 7
35 Supply & Installation Fire Alarm & Fire Fighting Works 40 days
37 Supply & Instllation of Ducting Works 30 days
12 Supply & Installation of 20cm thick Block Wall with Lintel & Plastering 18 days
24 Drainage Piping Works 10 days
25 Hot & Cold Water Piping Woks 8 days
29 Conduiting Works 10 days
13 Supply and installation of 100 mm Mortar & 50mm thick polystrene for whole floor 12 days
15 Supply & Installation of Rockwool inside the Partition 6 days
26 Supply & Installation of necessary Plumbing Services 3 days
16 Internal Partition Works - Double Side 15 days
30 Supply & Installation of PDB 5 days
Week of April 14
35 Supply & Installation Fire Alarm & Fire Fighting Works 40 days
37 Supply & Instllation of Ducting Works 30 days
12 Supply & Installation of 20cm thick Block Wall with Lintel & Plastering 18 days
13 Supply and installation of 100 mm Mortar & 50mm thick polystrene for whole floor 12 days
15 Supply & Installation of Rockwool inside the Partition 6 days
16 Internal Partition Works - Double Side 15 days
30 Supply & Installation of PDB 5 days
38 Supply & Installation Of FCU 15 days
20 Joint Filling Works On Gypsum Wall 10 days
Page 1
Unstarted Tasks as of Thu 3/21/24
&BMC ONCOLOGY TOWER
Week of April 21
35 Supply & Installation Fire Alarm & Fire Fighting Works 40 days
37 Supply & Instllation of Ducting Works 30 days
13 Supply and installation of 100 mm Mortar & 50mm thick polystrene for whole floor 12 days
16 Internal Partition Works - Double Side 15 days
38 Supply & Installation Of FCU 15 days
20 Joint Filling Works On Gypsum Wall 10 days
31 Cable Pulling Works 10 days
17 Supply and fix water proofing and screed to match finish level in floor area 5 days
Week of April 28
35 Supply & Installation Fire Alarm & Fire Fighting Works 40 days
38 Supply & Installation Of FCU 15 days
17 Supply and fix water proofing and screed to match finish level in floor area 5 days
22 Supply and fix Wall Tiles 5 days
Week of May 5
35 Supply & Installation Fire Alarm & Fire Fighting Works 40 days
22 Supply and fix Wall Tiles 5 days
45 Floor Tiles Installation Works 10 days
18 False Ceiling Installation 12 days
21 Ceiling Painting Works 10 days
Week of May 12
45 Floor Tiles Installation Works 10 days
18 False Ceiling Installation 12 days
21 Ceiling Painting Works 10 days
43 Supply & Installation of Self leveing to floor to receive vinyl flooring 5 days
Week of May 19
43 Supply & Installation of Self leveing to floor to receive vinyl flooring 5 days
19 Wall Painting Works 8 days
32 Installation of Lights 10 days
44 Vinyl flooring Installation Works 10 days
10 Supply & Installation of ELV Systems 30 days
33 Installation of Sockets 10 days
27 Supply & Installation of Sanitary Fittings 4 days
48 Supply & Installation of Counters & Cabinets 20 days
Page 2
Unstarted Tasks as of Thu 3/21/24
&BMC ONCOLOGY TOWER
Week of June 2
10 Supply & Installation of ELV Systems 30 days
48 Supply & Installation of Counters & Cabinets 20 days
47 Supply & Installation of Doors 10 days
50 Supply & Installation of Access Control System 15 days
Week of June 9
10 Supply & Installation of ELV Systems 30 days
48 Supply & Installation of Counters & Cabinets 20 days
50 Supply & Installation of Access Control System 15 days
Week of June 16
10 Supply & Installation of ELV Systems 30 days
50 Supply & Installation of Access Control System 15 days
55 Submission to ADCD 1 day
57 ADMCC Inspection & Approval 5 days
Week of June 23
57 ADMCC Inspection & Approval 5 days
56 ADCD Inspection 1 day
Week of June 30
58 Submission to ADM 1 day
Week of July 7
59 ADM Inspection 1 day
60 Building Completion from ADM 1 day
61 As Build Drawings & Documents to Client for DOH Submission 1 day