Advice Note - AN8 - CEMP Planning Guidance Note v2 January 2022
Advice Note - AN8 - CEMP Planning Guidance Note v2 January 2022
AN8
Construction
Environmental
Management Plans
(CEMP)
PLANNING ADVICE NOTE 8: CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLANS
(CEMP)
ANNI
NG ADVICE NOTE 5: DOMESTIC WIND TURBI
Overview
This advice note provides information to applicants and developers regarding Construction Environmental
Management Plans (CEMP). This document provides technical guidance relating to the general aspects that
should be considered within a CEMP. The production of a CEMP is the responsibility of the applicant/developer
and the onus is on them to ensure that it is specific to their project and suitable in scope.
A CEMP helps to ensure that construction work considers aspects of environmental protection within the
context of compliance with local legislation and minimisation of the impacts on humans and the environment. A
CEMP allows a proactive approach in controlling potentially polluting activities to prevent adverse public health
impacts, nuisance and hazards to the natural and human environment. A CEMP is however not intended to
safeguard private interests from construction activities.
This CEMP guidance document applies to the following projects which are likely to require a CEMP;
• Any project requiring an Environmental Impact Assessment (EIA) or screening opinion under schedules 1 & 2
of the Land Planning and Development (Environmental Impact Assessment) Ordinance, 2007
• Significant industrial facilities that e.g. contain manufacturing processes
• Larger residential and commercial development projects (e.g. housing development of 20+ units of
accommodation, office development of more than 1,000sq m)
• Any other project deemed by the Development & Planning Authority as presenting an environmental risk
warranting a CEMP
A CEMP ensures that environmental impacts identified during previously performed environmental studies (e.g.
an Environment Impact Assessment (EIA)) or during the scoping phase, will be properly managed and that
controls will be put in place to reduce the impacts of the development on the natural and human environment
during construction. If no EIA was completed for the project, then the CEMP should detail the extent to which
environmental effects, impacts, and risks exist and will be mitigated during the construction phase.
Where a CEMP is required by the Development & Planning Authority (‘the Authority’), a specific condition to this
effect and outlining what the CEMP must cover will be imposed on the planning permission that is granted for
the proposed development. The requirement for a CEMP may also be referred to in a Development Framework,
where one has been adopted by the Authority as Supplementary Planning Guidance. The applicant for the
proposed project is responsible for the CEMP although they may use a consultant or contractor to develop the
document. It is, however, important to note that consulting companies must ensure that each CEMP is specific
to the specific project site and the proposed activities.
Planning Advice Note AN8: Construction Environmental Management Plans (CEMP)_v2_January 2022 2
When the CEMP is complete, it must be submitted to the Authority for approval before construction works
begin, in accordance with the relevant condition of the planning permission. The Authority will consult with
other States of Guernsey services (e.g. the Office of Environmental Health and Pollution Regulation (OEHPR),
Traffic & Highway Services, Health and Safety Executive etc.) for comments on the submitted CEMP therefore
sufficient time should be allowed for this between submitting the document and scheduled start of works.
A CEMP is a public document and, once approved by the Authority, it will be made available to other parties on
request. The effect of a development on the public (e.g. occupants of domestic residences and workplaces) is a
key consideration of the CEMP but public consultation is not a requirement of the submission and responsibility
remains with the Authority to determine the suitability of the CEMP. A CEMP is not intended to safeguard
private interests from construction activities. Applicants/developers are, however, encouraged to engage with
parties that are likely to be affected by their development and to provide information regarding the project and
how it’s impact will be managed.
Following submission of a CEMP, the Authority will review the CEMP to verify that it is complete and that it
meets all of the necessary requirements. The Authority may seek clarification or revisions to the CEMP from the
applicant/developer for the proposed project. Following approval of the CEMP, the Authority will contact the
applicant/developer to confirm that construction activities can commence at the project site.
The content of a CEMP will vary by project as the size and scope of construction projects differ, as do site-
specific considerations. Table 1 provides recommended CEMP content areas and an overview of the individual
CEMP sections. Your CEMP must include, at a minimum, consideration of all of the sections listed in Table 1.
Planning Advice Note AN8: Construction Environmental Management Plans (CEMP)_v2_January 2022 3
Additional Guidance
When writing a CEMP, reference is likely to be necessary to technical guidance beyond this advice note.
Guidance documents of use include, but are not limited to;
It should be noted that technical guidance documents are subject to review and amendment and an
applicant/developer should ensure that they are using the most recent document as a reference point.
Further Information
The Island Development Plan (November 2016) contains relevant planning policies which may have a bearing on
the preparation of a CEMP. In particular, reference should be made to the general policies of the Plan (which are
prefixed ‘GP’) and to the Annexes to the Plan. The Island Development Plan can be downloaded from the States
of Guernsey website at https://gov.gg/planningpolicy.
This note is issued by the Authority to assist understanding of the provisions of the current planning
legislation. It represents the Authority’s interpretation of certain provisions of the legislation and is not
intended to be exhaustive or a substitute for the full text of the legislation copies of which are available
from the Greffe. Electronic copies are also available at www.guernseylegalresources.gg. Substantive
queries concerning the legislation should be addressed to the Authority by email at [email protected] .
The Authority does not accept any liability for loss or expense arising out of the provision of, or reliance
on, any advice given. You are recommended to seek advice from an independent professional advisor
where appropriate.
Planning Advice Note AN8: Construction Environmental Management Plans (CEMP)_v2_January 2022 4