Walsh Processed Presentation 2 LR
Walsh Processed Presentation 2 LR
esbnetworks.ie
Impact of increased electrification of Household load on Network
esbnetworks.ie
Expected Energy consumption growth of 228% in Ireland to meet Net Zero
esbnetworks.ie
Growth in Installed Generation associated with increased Energy Consumption is 380%
esbnetworks.ie
Growth in Renewable Generation, especially Offshore Wind
esbnetworks.ie
Simplified Line Diagram of Transmission and Distribution Networks
esbnetworks.ie
What drove 20kV Conversion program in early 2000’s?
Consequently, if major refurbishment is Answer is that for less than 10% more, the network could be
required with massive asset replacement, the rebuilt as 20kV or refurbished at 10kV for future conversion
question is whether the existing network to 20kV – the major difference being that actual 20kV
should be rebuilt exactly as before, as this
Conversion requires substantial work in HV/MV Substations.
would mean no extra capacity?
esbnetworks.ie
Why 20kV? - Higher voltages carry significantly higher power but at little extra cost.
Volt Drop which is usually a limiting criteria in rural networks is halved when voltage is doubled
Load = 1MVA so I10 = 1MVA /(√3*10kV) = 58A ; I20 = 1MVA /(√3*20kV) = 29A ; V20/V10 = (29A x R)/(58AxR) =1/2
Loss Ratio = (I102 R / I202 R) = (I102 /I202) = (V10 /R)2 / (V20 /R)2 = 10kV2/20kV2 = ¼
ESB operates an isolated Neutral system at 10kV, so insulators rated for 17.5kV. Earthing the neutral for 20kVmeans that
existing insulators do not need replacement except in coastal areas ( 8-30km from coastline).
XLPE 10kV Cables could be operated at 20kV, but not paper cables, hence conversion in Urban areas slower
esbnetworks.ie
Practical Benefits from conversion from 10kV to 20kV:
Allows major new loads to be accommodated on existing networks (at 20kV rather than 38kV)
Much better standby capability between networks due to less volt drop at higher power
Lower costs per kVA served as costs of 20kV construction very similar to 10kV, but much higher
capacity
Existing 38kV Stations have longer reach so fewer new 38kV Stations needed
Load will accumulate at fewer 38kV Stations and facilitate their conversion to 110kV
20kV Equipment is standard and better than 38kV generally, as 38kV is now a non-standard voltage
and at the bottom of range for sub-transmission equipment
Plan to gradually replace 38kV/MV with 110kV/MV over time (25 years)
esbnetworks.ie
ESB’s Networks – DSO, DAO & TAO in Southern Ireland
Connected MAN
esbnetworks.ie
Approximate Network Component Volumes and MVA Capacity
esbnetworks.ie
Conversion of 10kV Line to 20kV
esbnetworks.ie
Conversion of 10kV Line to 20kV using Interface Transformer
esbnetworks.ie
Interface Transformer (IFT) : 3 – 5MVA, 10/20kV Step Up
esbnetworks.ie
38kV Station Conversion Options
38kV Station with multiple 10kV and 20kV outlets 38kV Station with one 20kV feeder.
One half bar at 10kV, one at 20kV, with IFT for Bar remains at 10kV but Step-Up IFT provides
coupling. 20kV supply to feeder.
esbnetworks.ie
Contractors were a third of the total workforce, from 20 countries incl .Australia,
South Africa and Turkey, as well as Eastern Europe
esbnetworks.ie
Volumes of work very high – Labour and Materials critical
esbnetworks.ie
Map of MV Status in 2022 – 20kV is Red, 10kV Blue – 50% converted
esbnetworks.ie
Where do we go from here?
esbnetworks.ie
Using Three Winding 110/38/MV Transformers for 38kV Conversion?
Stn A Stn B
MV Traditional 110/38kV Stn.
MV
38/20kV 38/10kV
Consider uprating from 38kV to 110kV? – standardise voltages further by eliminating 38kV over time.
However, in lightly loaded areas 38kV will persist for many years.
Possibly use 110/38/MV transformers instead of 110/MV, so that whilst dense loads can be fed locally
at MV, the remaining 38kV System can be reinforced and provide value for many years, easing
workload and providing greater cost effectiveness.
esbnetworks.ie
Existing ESB 38kV Monopole for 150AAAC with Braced Portal Poleset
(instead of Pylon) for Angle < 25°
esbnetworks.ie
Low Profile 132kV Single Pole Line in UK, with inset of existing ESB 38kV headgear
esbnetworks.ie
Conclusions
Very high levels of growth in the next decade will require very significant increases in Long Term Grid capacity
Grid capacity is limited by circuit capacity which is used to feed downstream Substations
Load will be too large to be managed – peaks will simply shift to become peaks at other times
Generation will seek to ‘sink’ power into load when wind is blowing – so Generators will look for Network to be sized to
match generation, whereas Networks usually look to minimise load to match Network capacity and minimise Investment.
However, Voltage Uprating is a fast, proven methodology, that uses existing, publicly accepted, circuit routes and stations,
and which can double or treble power available at least cost and effort, by also making use of reinforced existing assets.
[email protected]
28 www.esbnetworks.ie