This document provides a method statement review checklist for testing and commissioning of a fire detection and alarm system for a project. It lists 10 items to be reviewed including equipment details, design drawings, safety measures, commissioning equipment, and competency lists. Comments are also provided on coordination with other disciplines and cause and effect matrices.

Uploaded by

Jaya Krishna
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
181 views

Method Statement For Testing & Commissioning of Fire Detection

This document provides a method statement review checklist for testing and commissioning of a fire detection and alarm system for a project. It lists 10 items to be reviewed including equipment details, design drawings, safety measures, commissioning equipment, and competency lists. Comments are also provided on coordination with other disciplines and cause and effect matrices.

Uploaded by

Jaya Krishna
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 38

.

fc^fclV&l co:»(
Cox Hewlett & BaileyWoodland 2 ? FEB 2020
POBox7013CloistersSquareWA6850 RCA PROJECT OFH^i- - OMAA
360MurrayStreetPerthWA6000Australia Signature:.
T + 61893223644 F + 61 8 9322 1664 www. cox. com. au

ARCHITECTSADVICE Advice Number: OAAM-AA-09628


Project Oman Across Ages Museum

Job 614020
number

Proprietor RoyalCourtAffairs
Contractor SPML - OSCO Joint Venture
File no.
Sheet 1 Of Date 27/02/2020

The Contractor shall comply with directions described without variation to the Contract sum and without
adjustment to the time for Substantial Completion. Should the Contractor consider that compliance with
these directions involves a variation to the Contract Sum or an adjustment to the time of Substantial
Completion of the works, he/she shall inform the Resident Engineer (RCA) and obtain written approval
before executing the work

SUBJECT: Method Statement for Testing & Commissioning of Fire Detection & Alarm System (FDAS)
DOCUMENT REFERENCE- OAAM/SPOS/DT/MEP3/001701
REQUIREDBY DATE- N/A

Name r
David Kirwan Resident
Signed

Copies to - RCA, MIL


'^^/il ^^'^Jc^^'

-^- S^O^: ^LST l^lbU ^ppy&VtlJL/Co^V^V^jrv^f '

Cox Architecture Pty Ltd ACN 002 535 891


S>kc^~o/Y' 0^1^} ^-.OZ^ ,
NominatedArchitects:Steve WoodlandNo. 1965, Greg Hewlett No. 1029.

Page 1 f 1
REFER TO COMMENTS ENCLOSED

ARUL VEERAPPAN

10-12-2019
Method Statement Review Checklist- REV-1

Date 05/03/2020
Project OAAM
Contract No. 09628
Service Fire Detection & Alarm System (FDAS)

Contractor
Initial Check CommissioningEngineer
Item Method Statement Review Checklist Yes No Yes No Comments
-Attached or refer to the system detail and
1 Equipment/ systems briefdetails including designparameters * design parameters need to be attached for
andrelative drawings/schematic - FDASintegrated system needto be listed
andseparateinspectionneedto bedone.
2 Designdrawings/shop drawingsandMASreferenceonly * Incorporate the MAS for the
(copy to be made available at sit as per RCA specification) equipment during commissionmg
3 ApprovedRCAandupdatedinternationalCommissioningcode *
reference.

4 DetailedSafetymeasuresandsafetydevicesto betakenduring *

commissioning
5 CalibratedCommissioningequipmentdetails *

6 Contractor and supplier commissioningengineer/technician * Providethe list ofcommissioning


competency list with CV . engineer and technician with CV
-The list provided without reading
7 Pre -commissioning certificate template includes initial * -For each PDAS must have individual pre-
function test template commission check list and then for all the
integration PDAS
Commissioning requests report and this should include
8 contractor, site RCA project, RCA Consultant (if applicable)/ * -The cover list ofTesting and commissioning
Approved Commissioning RCA Commissioning Engineers and need to be sign offby those.
Commissioning leader, (commissioning agent ) if available
9 Factoryfunctiontest certificate(ifapplicable) *
without reference and not attachment
Reference of site approved material/ equipment installation
10 request. *
Provide reference or attachment for instant
^ installation check and cable check.
^ }/^f/^ ^Y)^" ^c^j^/y^^r, ^r-/-

~^
'x^ ^^ 5
DOCUMENT REVIEW SHEET
Project Name: Oman Museum Across Ages, Nizwa, Sultanate of Oman Project Number 1661
Doc Ref: 1661-TEN-OAAM-MST-012 Issue Date 26.02.2020

System: Fire Detection Alarm System Document Reference: OAAM-MEP3-MS-EL-0018/ R0

Category Method Statement for Testing & commissioning of External Fire Hydrant

Reviewed By: Yuvaraj M Approved By: Rathnakara A


Sr. Fire Engineer Principal Fire Engineer

Review Findings

Tenable Fire Engineering had reviewed the MST (refer category) and our observations are as follows:

a) Pl. refer Lead/ sub-consultant comments.


b) Attach individual pre-commissioning check list & commissioning check list for the devices and equipments
c) Cause & Effect to be attached (Approved)

Required Action

Review Status
☐ Approved ☐ Approved with Comments ☒ Not Approved

☐ Attachments

Issued by:

Yuvaraj M
Sr. Fire Engineer
P.O Box 250, PC 118, Muscat, Sultanate of Oman; T: +968 24693056, F: +968 24693057, E: [email protected], www.tenablefec.com
COMMENTS: (OAAM-SPOS-DT-MEP3-001701 MST for T&C of FDAS)
01. MEP3 Contractor shall ensure the coordination with all adjacent disciplines & other NSC's are
completed prior to the commencement of any installation, T&C works.
MEP3 Contractor shall be responsible for rectifying any co-ordination errors where coordination has
not been carried out.

02. The Contractor shall ensure the and installations shall comply in accordance with project
requirement and demonstrated to the end user. FDAS interface(s) with various third party systems
For example - but not limited to:
1) Sprinkler system,
2) ASD,
3) Lighting Control System,
4) Fire fighters emergency telephone,
5) Fire pumps,
6) Security Access Control System,
7) Fire doors/access controlled egress doors,
8) HVAC, PA/Voice, BMS systems
9) Lift,
10) Any other systems mentioned in the project Specifications (Exhibition specialist equipment)

03. Fire alarm Cause & Effect Matrix shall be submitted for approval prior to T&C procedure.
CONTRACTOR DOCUMENT REVIEW
(B) NO EXCEPTION TAKEN.
(A) NO EXCEPTION TAKEN. COMPLY WITH COMMENTS.
WORK MAY PROCEED.
(C) NO EXCEPTION TAKEN
EXCEPT CLOUDED AREAS. (D) REVISE AND RESUBMIT.
RESUBMIT CLOUDED AREAS. WORK NOT TO PROCEED.

Aurecon Australasia Pty Ltd


ABN 54 005 139 873
BY: Arul Veerappan
DATE: 19-12-2019
PROJECT No: 247055
DATE RECEIVED: 10-12-2019
This review is only for general conformance with the
design concept of the project and general compliance
with the information given in the contract documents.
Any action shown is subject to the requirements of
the contract documents. This review does not relieve
the Contractor of their Contractual obligations nor of
their responsibilities of ensuring the work is complete,
accurate and correct. Any amendment does not
constitute an order of authority for a price variation to
the contract.
all
* Ensure all battery charging & recharging operation shall be automatic.
* Ensure the selected battery are as per standby & alarm power calculations. Ensure system control panel will be capable
of displaying the type of trouble condition
(open, short, device missing, failed).
Should a device fail it will not hinder the
operation of other system devices.

* These procedures
must allow the
complete panel to be
tested automatically
by the activation of
dedicated keys on
the keyboard.

Ensure that testing procedure, whilst testing all zones and functions, must not activate any ancillary
equipment such as air conditioning shutdown, direct Authority alarm, magnetic door holders etc.
This section includes ASD or not.
Contractor to confirm.

Heat Detectors:

The detectors shall be tested


in place to ensure Heat entry
into the sensing chamber and
an alarm response as per
NFPA 72 National Fire Table.

Ensure the evacuate


* Any Detector that fails the testing methods outlined in this document should be signal/message after 120
cleaned and retested. If the sensor fails after cleaning, it must be replaced. sec delay as per spec.

MEP3
contractor to
ensure the
notification on
BMS system
due to
activation of
MCP or
detector etc.,