Method Statement For Testing & Commissioning of Fire Detection
Method Statement For Testing & Commissioning of Fire Detection
fc^fclV&l co:»(
Cox Hewlett & BaileyWoodland 2 ? FEB 2020
POBox7013CloistersSquareWA6850 RCA PROJECT OFH^i- - OMAA
360MurrayStreetPerthWA6000Australia Signature:.
T + 61893223644 F + 61 8 9322 1664 www. cox. com. au
Job 614020
number
Proprietor RoyalCourtAffairs
Contractor SPML - OSCO Joint Venture
File no.
Sheet 1 Of Date 27/02/2020
The Contractor shall comply with directions described without variation to the Contract sum and without
adjustment to the time for Substantial Completion. Should the Contractor consider that compliance with
these directions involves a variation to the Contract Sum or an adjustment to the time of Substantial
Completion of the works, he/she shall inform the Resident Engineer (RCA) and obtain written approval
before executing the work
SUBJECT: Method Statement for Testing & Commissioning of Fire Detection & Alarm System (FDAS)
DOCUMENT REFERENCE- OAAM/SPOS/DT/MEP3/001701
REQUIREDBY DATE- N/A
Name r
David Kirwan Resident
Signed
Page 1 f 1
REFER TO COMMENTS ENCLOSED
ARUL VEERAPPAN
10-12-2019
Method Statement Review Checklist- REV-1
Date 05/03/2020
Project OAAM
Contract No. 09628
Service Fire Detection & Alarm System (FDAS)
Contractor
Initial Check CommissioningEngineer
Item Method Statement Review Checklist Yes No Yes No Comments
-Attached or refer to the system detail and
1 Equipment/ systems briefdetails including designparameters * design parameters need to be attached for
andrelative drawings/schematic - FDASintegrated system needto be listed
andseparateinspectionneedto bedone.
2 Designdrawings/shop drawingsandMASreferenceonly * Incorporate the MAS for the
(copy to be made available at sit as per RCA specification) equipment during commissionmg
3 ApprovedRCAandupdatedinternationalCommissioningcode *
reference.
4 DetailedSafetymeasuresandsafetydevicesto betakenduring *
commissioning
5 CalibratedCommissioningequipmentdetails *
~^
'x^ ^^ 5
DOCUMENT REVIEW SHEET
Project Name: Oman Museum Across Ages, Nizwa, Sultanate of Oman Project Number 1661
Doc Ref: 1661-TEN-OAAM-MST-012 Issue Date 26.02.2020
Category Method Statement for Testing & commissioning of External Fire Hydrant
Review Findings
Tenable Fire Engineering had reviewed the MST (refer category) and our observations are as follows:
Required Action
Review Status
☐ Approved ☐ Approved with Comments ☒ Not Approved
☐ Attachments
Issued by:
Yuvaraj M
Sr. Fire Engineer
P.O Box 250, PC 118, Muscat, Sultanate of Oman; T: +968 24693056, F: +968 24693057, E: [email protected], www.tenablefec.com
COMMENTS: (OAAM-SPOS-DT-MEP3-001701 MST for T&C of FDAS)
01. MEP3 Contractor shall ensure the coordination with all adjacent disciplines & other NSC's are
completed prior to the commencement of any installation, T&C works.
MEP3 Contractor shall be responsible for rectifying any co-ordination errors where coordination has
not been carried out.
02. The Contractor shall ensure the and installations shall comply in accordance with project
requirement and demonstrated to the end user. FDAS interface(s) with various third party systems
For example - but not limited to:
1) Sprinkler system,
2) ASD,
3) Lighting Control System,
4) Fire fighters emergency telephone,
5) Fire pumps,
6) Security Access Control System,
7) Fire doors/access controlled egress doors,
8) HVAC, PA/Voice, BMS systems
9) Lift,
10) Any other systems mentioned in the project Specifications (Exhibition specialist equipment)
03. Fire alarm Cause & Effect Matrix shall be submitted for approval prior to T&C procedure.
CONTRACTOR DOCUMENT REVIEW
(B) NO EXCEPTION TAKEN.
(A) NO EXCEPTION TAKEN. COMPLY WITH COMMENTS.
WORK MAY PROCEED.
(C) NO EXCEPTION TAKEN
EXCEPT CLOUDED AREAS. (D) REVISE AND RESUBMIT.
RESUBMIT CLOUDED AREAS. WORK NOT TO PROCEED.
* These procedures
must allow the
complete panel to be
tested automatically
by the activation of
dedicated keys on
the keyboard.
Ensure that testing procedure, whilst testing all zones and functions, must not activate any ancillary
equipment such as air conditioning shutdown, direct Authority alarm, magnetic door holders etc.
This section includes ASD or not.
Contractor to confirm.
Heat Detectors:
MEP3
contractor to
ensure the
notification on
BMS system
due to
activation of
MCP or
detector etc.,