F-YLFCCS-QC-10-023 HAND-OVER FORM REQUEST
F-YLFCCS-QC-10-023 HAND-OVER FORM REQUEST
FORM NO. :
F-CMGSI-QC-10-023
HAND-OVER FORM REQUEST
CONTRACTOR : _____________________________________________________________________________________________________________
NAME/POSITION : ________________________________________________________________
REQUEST NO. :_________________________
AREA (Pls. enclose key plan) : INSPECTION TYPE: INSPECTION DATE/TIME: INSPECTION CLOSE OUT DATE:
Preliminary
Final
NOTE : ALL SIGNATORIES SHOULD PRINT THEIR NAME AND SIGN TO IDENTIFY EACH SPECIMEN
The A&E Representatives certify to the CMG Representative that inspections were conducted by the subcontractor and verified by te CONTRACTOR'S-Project Engineers, and that the
(Pass/Fail) recommendations reflect the findings from those inspections.
AREA CLEANLINESS
SURFACE DEFECTS
COMPLETENESS
ARCHITECTURAL
CIVIL/STRUCTURAL
ELECTRICAL
WATER PROOFING
FDAS
MECHANICAL
SANITARY/PLUMBING
FIRE PROTECTION
SAFETY
OTHERS
ATTACHMENTS: Keyplan Inspection Checklist Test Reports (IF APPLICABLE) Material/s Inspection (IF APPLICABLE)
For Follow-up
Do Not Proceed
Others _________________
NOTED : THIS FORM MUST BE SUBMITTED TO THE CMGSI TEAM, DULY ACCOMPLISHED AND SIGNED BY THE CORRESPONDING CONTRACTOR'S PERSONNEL-IN-
CHARGE AT LEAST 24 HOURS BEFORE THE ACTUAL INSPECTION AND/OR INSTALLATION.
MANILA NEW OFFICE
Contract No.:ANNEX
NOTE : ALL SIGNATORIES SHOULD PRINT THEIR NAME AND SIGN TO IDENTIFY EACH SPECIMEN
AREA (Pls. enclose key plan) LEVEL INSPECTION DATE/TIME INSPECTION CLOSE OUT DATE
The A&E Representatives certify to the CQC Representative that inspections were conducted by the subcontractor and verified by te MDC-Project Engineers, and that the
(Pass/Fail) recommendations reflect the findings from those inspections.
ARCHITECTURAL
CIVIL/STRUCTURAL
ELECTRICAL
TELECOM
FDAS
BMS
FE/BR
MECHANICAL
SANITARY/PLUMBING
FIRE PROTECTION
RED LINING
OTHERS
ATTACHMENTS: Keyplan Inspection Checklist Test Reports (IF APPLICABLE) Material/s Inspection (IF APPLICABLE)
For Follow-up
Do Not Proceed
Others _________________
JOEL C. DOMINGO
Site Superintendent MDC - CQC Manager
RODELITO J. OCAMPO
MDC - CQC Representative MDC - Project Manager
NOTED : THIS FORM MUST BE SUBMITTED TO THE CQC TEAM, DULY ACCOMPLISHED AND SIGNED BY THE CORRESPONDING CONTRACTOR'S PERSONNEL-
IN-CHARGE AT LEAST 24 HOURS BEFORE THE ACTUAL INSPECTION AND/OR INSTALLATION.
NOTE : ALL SIGNATORIES SHOULD PRINT THEIR NAME AND SIGN TO IDENTIFY EACH SPECIMEN
AREA (Pls. enclose key plan) LEVEL INSPECTION DATE/TIME INSPECTION CLOSE OUT DATE
The A&E Representatives certify to the CQC Representative that inspections were conducted by the subcontractor and verified by te MDC-Project Engineers, and that the
(Pass/Fail) recommendations reflect the findings from those inspections.
ARCHITECTURAL
CIVIL/STRUCTURAL
ELECTRICAL
TELECOM
FDAS
BMS
FE/BR
MECHANICAL
SANITARY/PLUMBING
FIRE PROTECTION
OTHERS
ATTACHMENTS: Keyplan Inspection Checklist Test Reports (IF APPLICABLE) Material/s Inspection (IF APPLICABLE)
For Follow-up
Do Not Proceed
Others _________________
JOEL C. DOMINGO
Site Superintendent MDC - CQC Manager
RODELITO J. OCAMPO
MDC - CQC Representative MDC - Project Manager
NOTED : THIS FORM MUST BE SUBMITTED TO THE CQC TEAM, DULY ACCOMPLISHED AND SIGNED BY THE CORRESPONDING CONTRACTOR'S PERSONNEL-
IN-CHARGE AT LEAST 24 HOURS BEFORE THE ACTUAL INSPECTION AND/OR INSTALLATION.
DEFINABLE FEATURE OF WORK INSPECTION DATE/TIME INSPECTION CLOSE OUT INSPECTION TYPE
Preliminary
Final
The A&E Representatives certify to the CQC Representative that inspections were conducted by the subcontractor and verified by te MDC-Project Engineers, and that the (Pass/Fail)
recommendations reflect the findings from those inspections.
OTHERS
REMARKS : ACTION
For Follow-up
Proceed to Succeeding Work
Do Not
Proceed Others
_______________
JOEL C. DOMINGO
SITE SUPERINTENDENT CQC MANAGER
RODELITO J. OCAMPO
MDC CQC REPRESENTATIVE PROJECT MANAGER
NOTE : This form must be submitted to The CQC TEAM, duly accomplished and signed by the corresponding
Contractor's Personnel-in-charge at least 24 hours before actual installation.
F-MNOX-CQC-07-009 REV-0
REQUEST FOR INSPECTION/INSTALLATION