Fitout Schedule
Fitout Schedule
As of 13/12/2023
Months Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24 Jul-24 Aug-24 Sep-24
Weeks 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 5
Stage/Phase Description Duration (Wks) Start Finish
1 Design 18
Project Kick Off 1-Dec-23 1-Dec-23
Appointment of Architect 8-Dec-23 8-Dec-23
Appointment of other Consultants (QS, GC&MEP, T&C) 3 8-Dec-23 29-Dec-23
Test Fit & Review 1 11-Dec-23 18-Dec-23
2 Procurement
2A Design Services Procurement
Tender Preparation 2 4-Dec-23 18-Dec-23
Calling Tender 1 18-Dec-23 25-Dec-23
Tender Evaluation, Approval & Award 1 25-Dec-23 1-Jan-24 Award of Consultancy
3A Construction 17
Mobilisation 2 8-Apr-24 22-Apr-24 RI Inspection
Fit Out Works 14 15-Apr-24 22-Jul-24 FSC Approval
RI Inspection and FSC Approval 2 22-Jul-24 5-Aug-24
Stage 1 Sever Room Inspections (Room Readiness) 17-Jun-24 Stage 1 Server Room Handover
Stage 2 Sever Room Inspections (Final Cleaning & Server Rack Install) 15-Jul-24 Stage 2 Server Room Handover