Fitout Schedule

The document outlines a master programme schedule for interior fit out works for AMK2 Levels 2 and 4. It includes timelines for design, procurement, construction and handover activities over a period of around 8 months from December 2023 to August 2024. Key milestones include design approvals from Apple, tender evaluations and awards, delivery of long lead equipment, construction works and server room handovers.

Uploaded by

idaryllee
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
194 views

Fitout Schedule

The document outlines a master programme schedule for interior fit out works for AMK2 Levels 2 and 4. It includes timelines for design, procurement, construction and handover activities over a period of around 8 months from December 2023 to August 2024. Key milestones include design approvals from Apple, tender evaluations and awards, delivery of long lead equipment, construction works and server room handovers.

Uploaded by

idaryllee
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

AMK2 Levels 2 and 4 Interior Fit Out Master Programme

As of 13/12/2023
Months Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24 Jul-24 Aug-24 Sep-24
Weeks 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 5
Stage/Phase Description Duration (Wks) Start Finish

1 Design 18
Project Kick Off 1-Dec-23 1-Dec-23
Appointment of Architect 8-Dec-23 8-Dec-23
Appointment of other Consultants (QS, GC&MEP, T&C) 3 8-Dec-23 29-Dec-23
Test Fit & Review 1 11-Dec-23 18-Dec-23

Concept Design 3 18-Dec-23 8-Jan-24


High Level Ballpark Estimate (QS) 1 1-Jan-24 8-Jan-24 Apple Target Sign off on CD
Apple Review RE&D + BU W2 Jan 2024
Schematic Design 4 15-Jan-24 12-Feb-24
Cost Plan (QS) 50% 1 5-Feb-24 12-Feb-24 Apple Target Sign off on SD
Apple Review RE&D + BU W2 Feb 24
Detailed Design 3 12-Feb-24 4-Mar-24
Cost Plan (QS) 100% 1 26-Feb-24 4-Mar-24 Apple Target Sign off on DD
Apple Review RE&D + BU W1 Mar 2024 Sufficient detail for
SCDF BP Submission
Tender and Construction Documentation 2 4-Mar-24 18-Mar-24
Pre Tender Estimate (QS) 1 18-Mar-24 25-Mar-24
Target NOA from SCDF
Authority Submission (Kenyon) 6 26-Feb-24 8-Apr-24

2 Procurement
2A Design Services Procurement
Tender Preparation 2 4-Dec-23 18-Dec-23
Calling Tender 1 18-Dec-23 25-Dec-23
Tender Evaluation, Approval & Award 1 25-Dec-23 1-Jan-24 Award of Consultancy

2B Apple Direct Procurement Items

2B-1 Main Contractor Tender Package 4 19-Feb-24 18-Mar-24


Apple Procurement Review 2 11-Mar-24 25-Mar-24
Calling Tender 1 25-Mar-24 1-Apr-24
Tender Evaluation 1 1-Apr-24 8-Apr-24 Award of Work Package
Approval & Award 1 8-Apr-24 15-Apr-24

2B-2 FFE / System Furniture


System Partition / Fabric Soft Cell Ceiling Panels / Carpet Tiles
Tender Preparation 2 11-Mar-24 25-Mar-24
Calling Tender 1 25-Mar-24 1-Apr-24
Tender Evaluation, Approval & Award 1 1-Apr-24 8-Apr-24
Delivery Lead Time 12 8-Apr-24 1-Jul-24

Workstations / Manager Desks / Conference Tables / Loose Furniture


Tender Preparation 2 11-Mar-24 25-Mar-24
Calling Tender 1 25-Mar-24 1-Apr-24
Tender Evaluation, Approval & Award 1 1-Apr-24 8-Apr-24
Delivery Lead Time 12 8-Apr-24 1-Jul-24

2C Long Lead Equipment & Items


IS&T Equipment Lead Time 20 1-Jan-24 20-May-24
WAP & Server Installation & Cabling 7 17-Jun-24 5-Aug-24

GS Equipment Lead Time 20 1-Jan-24 20-May-24


Card Reader & CCTV & Server Installation & Cabling 6 24-Jun-24 5-Aug-24 WAP Instllation to
follow ceiling closure Handover of LAN room to GS &
AV Equipment Lead Time 20 1-Jan-24 20-May-24 IST for rack install
AV Equipment 3 1-Jul-24 22-Jul-24

3A Construction 17
Mobilisation 2 8-Apr-24 22-Apr-24 RI Inspection
Fit Out Works 14 15-Apr-24 22-Jul-24 FSC Approval
RI Inspection and FSC Approval 2 22-Jul-24 5-Aug-24
Stage 1 Sever Room Inspections (Room Readiness) 17-Jun-24 Stage 1 Server Room Handover
Stage 2 Sever Room Inspections (Final Cleaning & Server Rack Install) 15-Jul-24 Stage 2 Server Room Handover

3B Testing & Commisioning, Tests & Defects Rectification 5


T&C 2 22-Jul-24 5-Aug-24
Tests (IAQ & Portable Water) 2 22-Jul-24 5-Aug-24
Early User Inspections 4 8-Jul-24 5-Aug-24
Defects Retifications 4 15-Jul-24 12-Aug-24 Major Defects Rectification

4 Completion, Handover & Closeout 3 `


Final Handover Inspection 2 22-Jul-24 5-Aug-24 Final Handover
Handover 1 5-Aug-24 12-Aug-24