0% found this document useful (0 votes)
173 views17 pages

Bill of Quantities

Uploaded by

Jhet Bonode
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
173 views17 pages

Bill of Quantities

Uploaded by

Jhet Bonode
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 17

DETAILED COST ESTIMATE

Project Title: FARM TO MARKET ROAD

Location:
Barangay Municipality

DERIVATION FOR THE UNIT COST OF AGGREGATE BASE COARSE


QUANTITIES: 86.54 cu.m

EQUIPMENT COST
EQUIPMENT RENTAL COST
Description Unit Daily Rate Duration (days) Amount
Backhoe - 1.00- - 922.00- - 1.00- - 922.00-
Loader - 1.00- - 1,733.00- - 2.00- - 3,466.00-
Dumptruck - 4.00- - 1,420.00- - 1.50- - 8,520.00-
Total Item Material Cost = ( 12,908.00)

ITEM 102: ROADWAY EXCAVATION

Quantity = - 172.80- cu.m


Utilizing 0.25 cu.m capacity backhoe
Productivity Output = - 120.00- cu.m./day
Planned no. of Equipment = - 1.00-
Duration = 1.44 days say - 1.50-

1. EXCAVATION
a.) Labor Cost
No. of Days
Manpower No. Rate/day Total Amount
Reqd
Operator - 2.00- - 501.38- - 1.50- - 1,504.14-
Total Labor Cost for the Item = - 1,504.14-

b. Equipment Rental
Equipment No. Rate/day No. of Days Req'd Total Amount
Backhoe(0.25 cu.m capacity) - 1.00- - 922.00- - 1.50- - 1,383.00-
Truck (For Mobilizing the Backhoe to
- 1.00- - 1,017.90- - 1.50- - 1,526.85-
Project Site)
Total Equipment Cost for the Item - 2,909.85-

2. EQUIPMENT RENTAL
No of trucks to be utilized = 4 trucks
Capacity per truck = 2.5 cu.m/truck
No of days required = - 5.76- days; say 6 days

No. of Days
Equipment No. Rate/day Total Amount
Reqd
Backhoe (0.28cu.m capacity) - 1.00- - 922.00- - 6.00- - 5,532.00-
Dumptruck (2.5cu.m capacity) - 4.00- - 1,420.00- - 6.00- - 34,080.00-
Total Equipment Cost for the Items = - 39,612.00-

Direct Cost: - 44,025.99- Php


Indirect cost:
OCM (12%) = - 5,283.12- Php
CP/MU(8%) = - 3,522.08- Php
VAT(5%) = - 2,201.30- Php
Total Cost = - 55,032.49- Php
Unit Cost = 318.4750434 Php/cu.m

Item 103: EXCAVATION FOR STRUCTURE (GROUTED RIPRAP)


Quantity: - 47.54- cu.m

Productivity Output = - 1.00- cu.m/man-day


Planned no. of Manpower = - 6.00-
Duration = - 7.92- days say - 8.00- days
a.) Labor Cost
No. of Days
Manpower No. Rate/day Total Amount
Reqd
Unskilled - 6.00- - 386.41- - 8.00- - 18,547.68-
Total Labor Cost for the Item = - 18,547.68-

Direct Cost: - 18,547.68- Php


Indirect cost:
OCM (12%) = - 2,225.72- Php
CP/MU(8%) = - 1,483.81- Php
VAT(5%) = - 927.38- Php
Total Cost = - 23,184.60- Php
Unit Cost = - 487.69- Php/cu.m

Item 104: EMBANKMENT


Quantity: - 70.00- cu.m
*NOTE: Filling materials from item 102
Productivity Output = - 2.00- cu.m/day
Planned no. of Manpower = - 6.00-
Duration = - 5.83- days say - 6.00- days
a.) Labor Cost
No. of Days
Manpower No. Rate/day Total Amount
Reqd
Foreman - 1.00- - 694.77- - 6.00- - 4,168.62-
Skilled - 2.00- - 501.38- - 6.00- - 6,016.56-
Unskilled - 4.00- - 386.41- - 6.00- - 9,273.84-
Total Labor Cost for the Item = - 19,459.02-
b.) Equipment Rental Cost
No. of Days
Equipment No. Rate/day Total Amount
Reqd
Walk Behind Vibratory Plate Compactor - 2.00- - 123.00- - 6.00- - 1,476.00-
Total Equipment Cost for the Item = - 1,476.00-

Direct Cost: - 20,935.02- Php


Indirect cost:
OCM (12%) = - 2,512.20- Php
CP/MU(8%) = - 1,674.80- Php
VAT(5%) = - 1,046.75- Php
Total Cost = - 26,168.78- Php
Unit Cost = - 373.84- Php/cu.m

Item 105: SUBGRADE PREPARATION


Quantity: - 721.20- cu.m
*NOTE: Preparation shall be done manually
Productivity Output = - 2.00- cu.m/day
Planned no. of Manpower = - 6.00-
Duration = - 60.10- days say - 60.50- days
a.) Labor Cost
No. of Days
Manpower No. Rate/day Total Amount
Reqd
Unskilled - 6.00- - 386.41- - 60.50- - 140,266.83-
Total Labor Cost for the Item = - 140,266.83-
b.) Equipment Rental Cost
No. of Days
Equipment No. Rate/day Total Amount
Reqd
Walk Behind Vibratory Plate Compactor - 2.00- - 123.00- - 60.50- - 14,883.00-
Pick up Vehicle (For Mobilizing the plate
- 1.00- - 1,017.90- - 60.50- - 61,582.95-
compactors to Project Site)
Total Equipment Cost for the Item = - 76,465.95-

Direct Cost: - 76,465.95- Php


Indirect cost:
OCM (12%) = - 9,175.91- Php
CP/MU(8%) = - 6,117.28- Php
VAT(5%) = - 3,823.30- Php
Total Cost = - 95,582.44- Php
Unit Cost = - 132.53- Php/cu.m

Item 201: AGGREGATE BASE COARSE (75mm Thick)


Quantity: - 82.94- cu.m

a.) Material Cost


Description Unit Quantity Unit Cost Total Cost
Selected Borrow Base Coarse cu.m - 82.94- - 397.49- - 32,967.03-
Total Material Cost for the Item = - 32,967.03-

b.) Spreading and Compacting


b.1) Spreading Manually
Productivity Output = - 4.98- cu.m/day
Planned no. of Manpower = - 6.00-
Duration = - 2.78- days say - 3.00- days

Labor Cost
No. of Days
Manpower No. Rate/day Total Amount
Reqd
Unskilled - 6.00- - 386.41- - 3.00- - 6,955.38-
Total Labor Cost for the Item = - 6,955.38-

b.2) Compaction
*Using 12Hp Vibratory Plate Compactor
Productivity Output = - 18.00- cu.m/day
Planned no. of Manpower = - 2.00-
Duration = - 2.30- days say - 2.50- days

Labor Cost
No. of Days
Manpower No. Rate/day Total Amount
Reqd
Unskilled - 2.00- - 386.41- - 2.50- - 1,932.05-
Total Labor Cost for the Item = - 1,932.05-

Equipment Rental Cost


No. of Days
Equipment No. Rate/day Total Amount
Reqd
Motorized Road Grader - 1.00- - 2,173.00- - 2.50- - 5,432.50-
Vibratory Roller - 1.00- - 1,846.00- - 2.50- - 4,615.00-
Water Tank (16000L capacity) - 1.00- - 2,450.00- - 2.50- - 6,125.00-
Total Equipment Cost for the Items = - 16,172.50-

Direct Cost - 58,026.96- Php


Indirect cost:
OCM (12%) = - 6,963.23- Php
CP/MU(8%) = - 4,642.16- Php
VAT(5%) = - 2,901.35- Php
Total Cost = - 72,533.69- Php
Unit Cost = - 874.55- Php/cu.m

Item 311: 150MM THICK PORTLAND CEMENT CONCRETE PAVEMENT


Thickness = - 0.15- m Material Factors:
Road Width = - 3.35- m Class for concrete
Quantity = - 0.50- sq.m cement sand gravel
A
- 9.00- - 0.50- - 0.80-

a.) Material Cost


Pick-up Cost
Description Unit Quantity
Unit Cost Total Cost
1"Ø Gravel (FOB to SP Site) cu.m - 0.40- - 781.59- - 314.20-
Sand (FOB to SP Site) cu.m - 0.25- - 730.31- - 183.49-
- pcs 2" x 6' x 8' Lumber (FOB to SP Site) bdft - 20.00- - 882.34- - 17,646.80-
- pcs 2 x 6 x 10 Lumber (FOB to SP Site) bdft - 20.00- - 882.34- - 17,646.80-
- pcs 2 x 6 x 12Lumber (FOB to SP Site) bdft - 20.00- - 882.34- - 17,646.80-
Portland Cement bags - 192.00- - 255.85- - 49,123.20-
16mmØ Reinforcing Steel Bars (form pins &
pcs - 13.00- - 38.40- - 499.20-
construction joints dowels)
Blown Asphalt x 20kgs (expansion joint filler) bags - 2.00- - 3,325.00- - 6,650.00-
20 Liters - Empty Plastic Container pcs - 10.00- - 138.00- - 1,380.00-
Sack Canvas ( 2.4m x 25m) roll - 1.00- - 1,700.00- - 1,700.00-
200 Liters -Plastic Empty Drums pcs - 1.00- - 1,500.00- - 1,500.00-
Hacksaw Handle pcs - 2.00- - 104.86- - 209.72-
Hacksaw Blade pcs - 5.00- - 60.00- - 300.00-
3" CWNail kgs - 10.00- - 69.05- - 690.50-
Total Material Cost for the Items = - 115,490.71-

b.) Labor Cost


b.1) Formworks
Quantity = - 192.00- li.m
b.1.1) Form Setting
Labor Productivity Output = - 36.00- li.m/gang
Planned no. of gang = - 2.00- gang
Duration = - 2.67- days; say - 3.00- days
b.1.1) Form Removal
Labor Productivity Output = - 72.00- li.m/gang
Planned no. of gang = - 2.00- gang
Duration = - 1.33- days; say - 2.50- days

Form Setting & Removal


No. of Days
Manpower No. Rate/day Total Amount
Reqd
Foreman - 1.00- - 694.77- - 5.50- - 3,821.24-
Skilled - 2.00- - 501.38- - 5.50- - 5,515.18-
Unskilled - 4.00- - 386.41- - 5.50- - 8,501.02-
Total Labor Cost for the Item = - 17,837.44-

b.2) Concrete Works


Quantity = - 192.00- bags cement
*Utilizing 1-bagger Portable Concrete Mixer
Planned no. of 1-bagger Conc. Mixer = - 1.00- unit
Output = - 60.00- bags/day
Duration = - 3.20- days; say - 3.50- days

No. of Days
Manpower No. Rate/day Total Amount
Reqd
Foreman - 1.00- - 694.77- - 3.50- - 2,431.70-
Skilled - 3.00- - 501.38- - 3.50- - 5,264.49-
Unskilled - 12.00- - 386.41- - 3.50- - 16,229.22-
Total Labor Cost for the Item = - 23,925.41-

c.) Equipment Rental Cost


No. of Days
Manpower No. Rate/day Total Amount
Reqd
Transit Mixer ( 5 cu.m.) - 1.00- - 1,318.00- - 3.50- - 4,613.00-
Concrete Vibrator - 1.00- - 91.25- - 3.50- - 319.38-
Batching Plant (30 cu.m.) - 1.00- - 1,759.50- - 3.50- - 6,158.25-
Payloader (1.50 cu.m.), LX80-2C - 1.00- - 1,733.00- - 3.50- - 6,065.50-
Concrete Screeder (5.5 Hp) - 1.00- - 545.00- - 3.50- - 1,907.50-
Water Truck (16000 L) - 1.00- - 2,450.00- - 3.50- - 8,575.00-
Concrete Saw, Blade φ 14" (7.5 Hp) - 1.00- - 32.63- - 3.50- - 114.21-
Bar Cutter, Single Phase - 1.00- - 219.75- - 3.50- - 769.13-
Minor Tools (5% of Labor Cost) - - - - 1,196.27-
Total Equipment Cost for the Item = - 29,718.23-

Direct Cost: - 187,187.77- Php


Indirect cost:
OCM (12%) = - 22,462.53- Php
CP/MU(8%) = - 14,975.02- Php
VAT(5%) = - 9,359.39- Php
Total Cost = - 233,984.72- Php
Unit Cost = - 609.34- Php/ cu.m

Item 404: REINFORCING STEEL BARS


Quantity = - 825.00- kgs.

a.) Material Cost


Pick-up Cost
Description Unit Quantity
Unit Cost Total Cost
16mm dia x 6m RSB pcs - 523.00- - 38.40- - 20,083.20-
Hacksaw Handle pcs - 2.00- - 104.86- - 209.72-
Hacksaw Blade pcs - 5.00- - 60.00- - 300.00-
#16 GI Tie Wire kgs - 69.28- - 781.59- - 54,148.56-
Total Material Cost for the Items = - 74,741.48-

b.) Labor Cost


Productivity Output = - 2.00- kgs/gang-day
Planned no. of Gang = - 1.00- - 2.00- Steelman/gang
- 3.00- Laborers/gang
Duration = - 412.50- days say - 422.50- days

No. of Days
Manpower No. Rate/day Total Amount
Reqd
Foreman - 1.00- - 694.77- - 422.50- - 293,540.33-
Skilled - 2.00- - 501.38- - 422.50- - 423,666.10-
Unskilled - 3.00- - 386.41- - 422.50- - 489,774.68-
Total Labor Cost for the Item = - 913,440.78-

Direct Cost: - 988,182.25- Php


Indirect cost:
OCM (12%) = - 118,581.87- Php
CP/MU(8%) = - 79,054.58- Php
VAT(5%) = - 49,409.11- Php
Total Cost = - 1,235,227.81- Php
Unit Cost = - 1,497.25- Php/kg

Item 405: STRUCTURAL CONCRETE CLASS "A"


Quantity = - 9.30- cu.m Material Factors:
Class for concrete
cement sand gravel
A
- 9.00- - 0.50- - 0.80-

a.) Material Cost


Pick-up Cost
Description Unit Quantity
Unit Cost Total Cost
Portland Cement bags - 83.70- - 255.85- - 21,414.65-
1" Ø Gravel cu.m - 7.44- - 781.59- - 5,815.03-
Sand cu.m - 4.65- - 730.31- - 3,395.94-
Mixing Board
4 - 2 x 3 x 8 Lumber bdft - 16.00- - 37.02- - 592.32-
2 - 1 x 8 x 8 Lumber bags - 10.67- - 37.02- - 395.00-
2 - 1 x 8 x 12 Lumber pcs - 16.00- - 37.02- - 592.32-
2 - 1 x 12 x 12 Lumber bags - 24.00- - 37.02- - 888.48-
3" Common Wire Nail kgs - 2.00- - 69.05- - 138.10-
Concrete Pouring Pail (Rubberize Plastic) pcs - 10.00- - 60.00- - 600.00-
Total Material Cost for the Items = - 33,831.84-

b.) Labor Cost


Productivity Output = - 2.00- cu.m/gang-day
Planned no. of Gang = - 1.00- - 2.00- Skilled/gang
Duration = - 4.65- days say - 5.00- days

No. of Days
Manpower No. Rate/day Total Amount
Reqd
Foreman - 1.00- - 694.77- - 5.00- - 3,473.85-
Skilled - 2.00- - 501.38- - 5.00- - 5,013.80-
Unskilled - 10.00- - 386.41- - 5.00- - 19,320.50-
Total Labor Cost for the Item = - 24,334.30-

Direct Cost: - 58,166.14- Php


Indirect cost:
OCM (12%) = - 6,979.94- Php
CP/MU(8%) = - 4,653.29- Php
VAT(5%) = - 2,908.31- Php
Total Cost = - 72,707.67- Php
Unit Cost = - 7,818.03- Php/cu.m

Item 505: GROUTED RIPRAP


Quantity = - 180.60- cu.m Material Factors:
Class for concrete
cement sand
A
- 3.00- - 0.30-

a.) Material Cost


Pick-up Cost
Description Unit Quantity
Unit Cost Total Cost
Boulders cu.m - 180.60- - 872.96- - 157,656.58-
Portland Cement bags - 541.80- - 255.85- - 138,619.53-
Sand (FOB to SP Site) cu.m - 54.18- - 730.31- - 39,568.20-
3" Φ PVC Pipe pcs - 30.00- - 462.71- - 13,881.30-
Total Material Cost for the Item = - 349,725.60-

b.) Labor Cost


b.1) Laying of Boulders and Grouting
Productivity Output = - 9.00- cu.m/gang-day
Planned no. of Gang = - 3.00- - 3.00- Skilled/gang
- 6.00- Laborers/gang
Duration = - 6.69- days say - 7.00- days

No. of Days
Manpower No. Rate/day Total Amount
Reqd
Foreman - 1.00- - 694.77- - 7.00- - 4,863.39-
Skilled - 9.00- - 501.38- - 7.00- - 31,586.94-
Unskilled - 18.00- - 386.41- - 7.00- - 48,687.66-
Total Labor Cost for the Item = - 80,274.60-

c.) Equipment Rental Cost


No. of Days
Manpower No. Rate/day Total Amount
Reqd
One Bagger Mixer - 1.00- - 172.00- - 7.00- - 1,204.00-
Water Truck (16000 L) - 1.00- - 2,450.00- - 7.00- - 17,150.00-
Minor Tools (5% of Labor Cost) - - - - - - 4,013.73-
Total Equipment Cost for the Item = - 22,367.73-

Direct Cost: - 452,367.93- Php


Indirect cost:
OCM (12%) = - 54,284.15- Php
CP/MU(8%) = - 36,189.43- Php
VAT(5%) = - 22,618.40- Php
Total Cost = - 565,459.91- Php
Unit Cost = - 3,131.01- Php/cu.m

Item 600: CONCRETE CURB AND GUTTER


Length = - 192.00- li.m Material Factors:
Quantity = - 38.40- cu.m Class for concrete
cement sand gravel
A
- 9.00- - 0.50- - 0.80-

a.) Material Cost


Pick-up Cost
Description Unit Quantity
Unit Cost Total Cost
Portland Cement bags - 345.60- - 255.85- - 88,421.76-
1" Ø Gravel (FOB to SP Site) cu.m - 30.72- - 781.59- - 24,010.44-
Sand (FOB to SP Site) cu.m - 19.20- - 730.31- - 14,021.95-
12mmØ Reinforcing Steel Bars (PCCP to Curb an
pcs - 192.00- - 38.40- - 7,372.80-
Gutter joint dowels)
14 - 1 x 14 x 12' Good Lumber bdft - 196.00- - 37.02- - 7,255.92-
14 - 1 x 10 x 12' Good Lumber bdft - 140.00- - 37.02- - 5,182.80-
10 - 2 x 2 x 8 Good Lumber bdft - 26.67- - 37.02- - 987.32-
2" CWNail kgs - 5.00- - 69.05- - 345.25-
Total Material Cost for the Item = - 147,598.25-

b.) Labor Cost


b.1) Laying of Boulders and Grouting
Productivity Output = - 9.00- cu.m/gang-day
Planned no. of Manpower = - 3.00-
Duration = - 1.42- days say - 7.00- days

No. of Days
Manpower No. Rate/day Total Amount
Reqd
Foreman - 1.00- - 694.77- - 7.00- - 4,863.39-
Skilled - 2.00- - 501.38- - 7.00- - 7,019.32-
Unskilled - 10.00- - 386.41- - 7.00- - 27,048.70-
Total Labor Cost for the Item = - 34,068.02-

c.) Equipment Rental Cost


No. of Days
Manpower No. Rate/day Total Amount
Reqd
1-Bagger Conc. Mixer - 1.00- - 172.00- - 7.00- - 1,204.00-
Total Equipment Cost for the Item = - 1,204.00-

d.) Water provision and servicing of cement from bodega to SP site


No. of Days
Equipment No. Rate/day Total Amount
Reqd
Water Truck (16000 L) - 1.00- - 2,450.00- - 7.00- - 17,150.00-
Elf Truck (Fully Operated) - 1.00- - 1,420.00- - 7.00- - 9,940.00-
Total Equipment Cost for the Item = - 27,090.00-

Direct Cost: - 62,362.02- Php


Indirect cost:
OCM (12%) = - 7,483.44- Php
CP/MU(8%) = - 4,988.96- Php
VAT(5%) = - 3,118.10- Php
Total Cost = - 77,952.53- Php
Unit Cost = - 2,030.01- Php/cu.m

Prepared by: Checked by:

LOPEZ, MARVIN J. ENGR. ELIZABETH LUMIOAN


Student/ BSCE-4A Instructor
BILL OF QUANTITIES

PROJECT TITLE: FARM TO MARKET ROAD


LOCATION:

ITEM NO. ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL


102 ROADWAY EXCAVATION ( 172.80) cu.m 318.48 - 55,033.34-
103 EXCAVATION FOR STRUCTURE (GROUTED RIPRAP) ( 47.54) cu.m ( 487.69) - 23,184.78-
104 EMBANKMENT ( 70.00) cu.m ( 373.84) - 26,168.80-
105 SUBGRADE PREPARATION ( 721.20) cu.m ( 132.53) - 95,580.64-
201 AGGREGATE BASE COARSE (75mm Thick) ( 82.94) cu.m ( 874.55) - 72,535.18-
311 150MM THICK PCC PAVEMENT ( 0.50) sq.m ( 609.34) - 304.67-
404 REINFORCING STEEL BARS ( 825.00) kgs. ( 1,497.25) - 1,235,231.25-
405 STRUCTURAL CONCRETE CLASS "A" ( 9.30) cu.m ( 7,818.03) - 72,707.68-
505 GROUTED RIPRAP ( 180.60) cu.m ( 3,131.01) - 565,460.41-
600 CONCRETE CURB AND GUTTER ( 38.40) cu.m ( 2,030.01) - 77,952.38-
TOTAL PROJECT COST (Php) - 2,224,159.13-

Prepared by: Checked by:

LOPEZ, MARVIN J. ENGR. ELIZABETH LUMIOAN


Student/ BSCE-4A Instructor
DPWH PHILCON
FLYWHEEL
DESCRIPTION MODEL CAPACITY RENTAL RATE
HORSEPOWER CAR – Concreting Works Materials Prices
Earthmoving Equipment FORMWORKS AND SCAFFOLDS – CORDILLERA ADMINISTRATIVE REGION
Bulldozer D6H SERIES II PSDS/DD 165 3,379.00
AMOUNT
MATERIALS DESCRIPTION UNIT
Bulldozer w/ Ripper D6H SERIES II PSDS/DD 165 3,885.85 (PhP)
Payloader LX80-2C 1.50 m3/1.95 vd3 110 1,733.00 Concrete Nails Assorted kg 102.36
Motorized Road Grader G710A 140 2,173.00 Common Nails Assorted kg 69.05
Road Grader w/ Scarifier G710A 140 2,824.90 Formed Oil L 18.84
Compaction Equipment GI Pipe Schedule 40 Dia (19mm) pc 453.17
Pneumatic Tire Roller 9-WHL, 9.00X20, 4PR 10mt 107 561 GI Pipe Schedule 40 Dia (25.4mm) pc 669.94
Vibratory Roller SD100DC 10mt 125 1,846.00 GI Pipe Schedule 40 Dia (38mm) pc 1,089.93
Tandem Steel Roller CC421 10.10 mt 123.4 1,652.00 GI Pipe Schedule 40 Dia (50.8mm) pc 1,423.98
Plate Compactor 400-500 Gasoline Engine 5 123 GI Tie Wire #12 kg 70.81
Lifting Equipment GI Tie Wire #16 kg 69.28
Crawler Crane All Models 36-40 mt 190 1,902.00 Lumber Coco bd.ft. 20.04
Truck Mounted Crane All Models 31-35 mt 238 1,861.00 Lumber Good bd.ft. 37.02
Truck Mounted Crane All Models 41-45 mt 246 2,606.00 Metal Deck sq.m. 971.99
Excavating Equipment Plyboard (0.019m x 1.2m x 2.44m) pc 809.12
Backhoe SE 130 LC-2 0.80 m3/1.04 vd3 99 1,537.00 Plyboard (0.025m x 1.2m x 2.44m) pc 1,027.78
Backhoe w/ Breaker SE 130 LC-2 0.80 m3/1.04 vd3 99 1,998.10 Plywood Marine (0.00625m x 1.2m x 2.44m) pc 399.51
Backhoe, Wheel Mounted PW60N-1 0.28 m3/0.37 vd3 50 922 Plywood Marine (0.0125m x 1.2m x 2.44m) pc 741.31
Foundation Equipment Plywood Marine (0.019m x 1.2m x 2.44m) pc 1,102.64
Vibro Hammer DPD600T Hydraulic Pile Driver 60 ton 201 2,123.00 Plywood Ordinary (0.0065m x 1.4 x 2.44m) pc 340.27
Asphalting Equipment Plywood Ordinary (0.0125m x 1.4 x 2.44m) pc 628.35
Asphalt Distributor ROSC0/5 ton 3000 USG 100 936 Plywood Ordinary (0.019m x 1.4 x 2.44m) pc 1,011.98
Asphalt Paver NF220BIIVDM 80 1,833.00
Concreting Equipment Just to clarify, the aggregates’ prices listed below are from the quarry, additional costs for hauling distances and other extra charges are not included.
Concrete Screeder Wacker Truss Screed 5.5 545
Concrete Paver COMMANDER III, FOUR-TRACK 0 6,765.00 CEMENT AND REINFORCING BARS – CORDILLERA ADMINISTRATIVE REGION
One Bagger Mixer 4-6 ft3/min 0 172
AMOUNT
MATERIALS DESCRIPTION UNIT
Transit Mixer All Models 5-6 vd3 175 1,318.00 (PhP)
Hauling Equipment Fine Aggregate cu.m. 730.31
Dump Truck All Models 12 vd3 290 1,420.00 Gravel G1 cu.m. 781.59
Cargo/Service Truck All Models 2-5 mt 160 783 Gravel G1-1/2 cu.m. 893.67
Boom Truck All Models 2-5 mt 160 1,017.90 Gravel G2 cu.m. 882.34
Cargo/Service Truck All Models 9-10 mt 270 1,212.00 Gravel G2-1/2 cu.m. 872.96
Water Truck/Pump All Makes 16000 L 360 2,450.00 Gravel G3/4 cu.m. 867.42
Water Truck/Pump All Makes 1000 L 360 1,065.00 Natural Gravel cu.m. 678.28
Air Equipment Hydraulic Cement bag 231.98
Air Compressor All Models 356-450 cfrn 130 965 Portland Cement bag 255.85
Air Compressor All Models 161-185 dm 69 502 Pozzolan Cement bag 219.52
Air Compressor All Models 15-35 dm 20 205 Reinforcing Steel Bars Plain Grade 40 kg 38.4
Diamond Drill CP-8 201.25 Reinforcing Steel Bars Plain Grade 60 kg 41.09
Jackhammer 150 Reinforcing Steel Bars Deformed Grade 40 kg 38.54
Pneumatic Drilling Machine 170 Reinforcing Steel Bars Deformed Grade 60 kg 39.1
Pumping Equipment Rust Converter/ Remover Gal 538.92
Water Pump, 100mm suction dia. 16 266.25
Shop Equipment
Welding Machine electric driven/DC output 391
Welding Machine Gas/Diesel Driven 48 371
Special Support System
Chainsaw 75.36
Miscellaneous Equipment
Concrete Vibrator 91.25
Concrete Saw 32.63
Bar Cutter 219.75
Bar Bender 351.5
Plants
Asphalt Concrete PLant 4286.63
Concrete Batch Plant 1759.5
Others
Power Broom, Towered Type 130.54
Hydroseeding Machine 952
Applicator Machine 93.75
Kneading Machine 187.5
Drop Hammer 200
Cutting Outfit 45.45
Steel Wheel w/ Nylon Rope 300
Improvised Bamboo w/ Bucket 200
Asphalt Kettle/Drum 10
FLYWHEEL
DESCRIPTION MODEL CAPACITY RENTAL RATE
HORSEPOWER

Earthmoving Equipment
Bulldozer D6H SERIES II PSDS/DD 165 3,379.00
Bulldozer w/ Ripper D6H SERIES II PSDS/DD 165 3,885.85
Payloader LX80-2C 1.50 m3/1.95 vd3 110 1,733.00
Motorized Road Grader G710A 140 2,173.00
Road Grader w/ Scarifier G710A 140 2,824.90
Compaction Equipment
Pneumatic Tire Roller 9-WHL, 9.00X20, 4PR 10mt 107 561
Vibratory Roller SD100DC 10mt 125 1,846.00
Tandem Steel Roller CC421 10.10 mt 123.4 1,652.00
Plate Compactor 400-500 Gasoline Engine 5 123
Lifting Equipment
Crawler Crane All Models 36-40 mt 190 1,902.00
Truck Mounted Crane All Models 31-35 mt 238 1,861.00
Truck Mounted Crane All Models 41-45 mt 246 2,606.00
Excavating Equipment
Backhoe SE 130 LC-2 0.80 m3/1.04 vd3 99 1,537.00
Backhoe w/ Breaker SE 130 LC-2 0.80 m3/1.04 vd3 99 1,998.10
Backhoe, Wheel Mounted PW60N-1 0.28 m3/0.37 vd3 50 922
Foundation Equipment
Vibro Hammer DPD600T Hydraulic Pile Driver 60 ton 201 2,123.00
Asphalting Equipment
Asphalt Distributor ROSC0/5 ton 3000 USG 100 936
Asphalt Paver NF220BIIVDM 80 1,833.00
Concreting Equipment
Concrete Screeder Wacker Truss Screed 5.5 545
Concrete Paver COMMANDER III, FOUR-TRACK 0 6,765.00
One Bagger Mixer 4-6 ft3/min 0 172
Transit Mixer All Models 5-6 vd3 175 1,318.00
Hauling Equipment
Dump Truck All Models 12 vd3 290 1,420.00
Cargo/Service Truck All Models 2-5 mt 160 783
Boom Truck All Models 2-5 mt 160 1,017.90
Cargo/Service Truck All Models 9-10 mt 270 1,212.00
Water Truck/Pump All Makes 16000 L 360 2,450.00
Water Truck/Pump All Makes 1000 L 360 1,065.00
Air Equipment
Air Compressor All Models 356-450 cfrn 130 965
Air Compressor All Models 161-185 dm 69 502
Air Compressor All Models 15-35 dm 20 205
Diamond Drill CP-8 201.25
Jackhammer 150
Pneumatic Drilling Machine 170
Pumping Equipment
Water Pump, 100mm suction dia. 16 266.25
Shop Equipment
Welding Machine electric driven/DC output 391
Welding Machine Gas/Diesel Driven 48 371
Special Support System
Chainsaw 75.36
Miscellaneous Equipment
Concrete Vibrator 91.25
Concrete Saw 32.63
Bar Cutter 219.75
Bar Bender 351.5
Plants
Asphalt Concrete PLant 4286.63
Concrete Batch Plant 1759.5
Others
Power Broom, Towered Type 130.54
Hydroseeding Machine 952
Applicator Machine 93.75
Kneading Machine 187.5
Drop Hammer 200
Cutting Outfit 45.45
Steel Wheel w/ Nylon Rope 300
Improvised Bamboo w/ Bucket 200
Asphalt Kettle/Drum 10

Screen LS 20,000.00
1 sets of screen 15,000.00

hydroseeding machine 952


Chain Block 500 75.36 region
Lowbed Trailer with Prime Mover: 2290
Drilling Outfit, with drilling machine, derick, etc. (PhP 653.25) region
Grouting Machine (Air-driven) (PhP 350.00) region
Generator, 201 - 250 KW, 251 - 313 KVA 740
Generator Set (1401-1500 KW) 2737 region-guiiset project
Cap. of 1 Dump Truck (5 Tons/5cu.m.) 5000kg mini dumptruck Note: The roadway to the Project site from the National road
is very narrow with width of 2.5-3mts. And average steep grade
of 15% to 18% thus we utilized 5 tons/5 cu.m. capacity
dump trucks from materials source to the project site.
FLYWHEEL
DESCRIPTION MODEL CAPACITY RENTAL RATE
HORSEPOWER
FLYWHEEL
DESCRIPTION MODEL CAPACITY RENTAL RATE
HORSEPOWER
FLYWHEEL
DESCRIPTION MODEL CAPACITY RENTAL RATE
HORSEPOWER
FLYWHEEL
DESCRIPTION MODEL CAPACITY RENTAL RATE
HORSEPOWER
FLYWHEEL
DESCRIPTION MODEL CAPACITY RENTAL RATE
HORSEPOWER
FLYWHEEL
DESCRIPTION MODEL CAPACITY RENTAL RATE
HORSEPOWER

You might also like