Gantt

The document outlines a project plan using a Gantt chart format. It details 31 tasks across 6 phases of planning, requirements analysis, system design, software development, testing, and deployment from December 2023 through February 2024.

Uploaded by

thenura1979
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
20 views

Gantt

The document outlines a project plan using a Gantt chart format. It details 31 tasks across 6 phases of planning, requirements analysis, system design, software development, testing, and deployment from December 2023 through February 2024.

Uploaded by

thenura1979
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Gantt

Jan 01,2024 Feb 01,2024


ID WBS Task Start Finish Duration
2023-12-04 2023-12-11 2023-12-18 2023-12-25 2024-01-01 2024-01-08 2024-01-15 2024-01-22 2024-01-29 2024-02-05 2024-02-12 2024-02-19 2024-02-26

1 1 Planning project 2023-12-04 2023-12-15 10 Workdays

Initiate document
2 1.1 2023-12-04 2023-12-05 2 Workdays
creation
project charter
3 1.2 2023-12-04 2023-12-12 7 Workdays
development
stakeholder
4 1.3 identification and 2023-12-05 2023-12-08 4 Workdays
management plan

5 1.4 Risk assessment 2023-12-07 2023-12-12 4 Workdays

Resource allocation
6 1.5 2023-12-12 2023-12-14 3 Workdays
and Create Team

7 1.6 Kick off meeting 2023-12-15 2023-12-15 1 Workday

8 2 Requirement Analysis 2023-12-15 2023-12-26 8 Workdays

Requirement
9 2.1 2023-12-15 2023-12-26 8 Workdays
gathering

create functional and


10 2.2 non-functional 2023-12-21 2023-12-22 2 Workdays
requirements

requirement validation
11 2.3 2023-12-21 2023-12-26 4 Workdays
and verification

create and finalize


12 2.4 2023-12-15 2023-12-26 8 Workdays
SRS

13 3 System Design 2023-12-26 2024-01-05 9 Workdays

14 3.1 Architectural Design 2023-12-26 2023-12-29 4 Workdays

15 3.2 UI/UX design 2023-12-29 2024-01-05 6 Workdays

System security
16 3.3 2023-12-29 2024-01-05 6 Workdays
Design

17 4 Software Development 2024-01-05 2024-02-09 26 Workdays

18 4.1 Frontend development 2024-01-05 2024-01-23 13 Workdays

Backend
19 4.2 2024-01-09 2024-02-07 22 Workdays
Development

20 4.3 Intergration 2024-02-05 2024-02-09 5 Workdays

Code reviews and


21 4.4 2024-01-05 2024-02-08 25 Workdays
refactoring

22 5 Testing 2023-12-26 2024-02-14 37 Workdays

Develop detailed test


23 5.1 plan 2023-12-26 2024-02-12 35 Workdays

E xecute
24 5.2 comprehensive testing 2024-02-01 2024-02-07 5 Workdays

Implement security
25 5.3 vulnerability 2024-02-02 2024-02-07 4 Workdays
assessments
Facilitate user
26 5.4 Acceptance testing 2024-02-07 2024-02-14 6 Workdays
with stakeholders

27 6 Deployment 2024-02-14 2024-02-27 10 Workdays

Configure production
28 6.1 environment 2024-02-14 2024-02-20 5 Workdays

launch system in
29 6.2 production 2024-02-19 2024-02-22 4 Workdays
environment

Create and deliver


30 6.3 final documentation 2024-02-14 2024-02-26 9 Workdays

Host official project


31 6.4 closure with 2024-02-27 2024-02-27 1 Workday
stakeholders