Method Statement MV Cable
Method Statement MV Cable
METHOD STATEMENT
FOR
AT
Prepared
by: Reviewed Reviewed Reviewed
Approved
by: by: Date of
Rev. Date Description Electrica by: by:
QA/QC Safety Project Approval
l Consultant
Manager Manager Manager
Engineer
12-03-24 Installation, of
01 MV Cable
1| P a g e
CONSTRUCTION OF AL-URUBAH PARK
Low & Medium Voltage Cable Installation,
Testing & Termination
Table of Contents
1.0 INTRODUCTION............................................................................................................
2.0 PURPOSE & SCOPE OF WORK..................................................................................
3.0 DEFINITIONS:................................................................................................................
4.0 STANDARD AND REFERENCES:...............................................................................
4.1 References.........................................................................................................................
5.0 RESPONSIBILITIES......................................................................................................
5.1 Project Manager (PM).....................................................................................................
5.2 Construction Manager (CM):.........................................................................................
5.3 QA/QC Manager (QA/QC Manager):...........................................................................
5.4 Project HSE Manager:....................................................................................................
5.5 Site Engineer:...................................................................................................................
5.6 Site Foreman:...................................................................................................................
5.7 Land Surveyor:................................................................................................................
5.8 Quality Control Engineer:...............................................................................................
5.9 Supervisor/Safety Officer:...............................................................................................
5.10 Document Controller (DC):..........................................................................................
6.0 Resources:.........................................................................................................................
6.1 Equipment & Tools:.........................................................................................................
6.2 Manpower:........................................................................................................................
7.0 PROCEDURE/WORK METHODOLOGY:.................................................................
8.0 SAFETY MEASUREMENT...........................................................................................
9.0 RISK ASSESSMENT.......................................................................................................
2| P a g e
CONSTRUCTION OF AL-URUBAH PARK
Low & Medium Voltage Cable Installation,
Testing & Termination
1.0 INTRODUCTION
The purpose of this method statement is to specify the detailed requirements and
procedures carried out for installation o Medium voltage cable instal at Al Urubah
Park, as per the project Specification and Approved Drawings
This Method Statement highlights the work sequence intended for installation of
Underground Low & Medium voltage cable installation, testing & termination at
Al Urubah Park.
3.0 DEFINITIONS:
The following references and relevant standards which have been listed in the project
specification shall be used when carrying out the Works.
4.1 References
- Project Specification; Section 26 0513
- IFC Drawings. GR-03-CP001-LIT-ELE-DWG-CN-35001 & GR-03-
CP001-LIT-ELE-DWG-CN-35020
3| P a g e
CONSTRUCTION OF AL-URUBAH PARK
Low & Medium Voltage Cable Installation,
Testing & Termination
5.0 RESPONSIBILITIES
4| P a g e
CONSTRUCTION OF AL-URUBAH PARK
Low & Medium Voltage Cable Installation,
Testing & Termination
with quality, schedule and sequence requirements. Coordinates regularly with
the Safety Officers/Supervisors to ensure any and all safety situations are
promptly addressed and fully remedied. He shall also be responsible for
coordinating inspection requests to Quality Control Engineer to ensure that all
relevant inspections are completed and approved, he also takes corrective
action if any portion of work has not been performed correctly. Report directly
to the Construction Manager.
5| P a g e
CONSTRUCTION OF AL-URUBAH PARK
Low & Medium Voltage Cable Installation,
Testing & Termination
6.0 RESOURCES:
6.2 Manpower:
Site Electrical Engineer
Electrical QC Engineer
Safety Officer
Electrical Supervisor
Electricians
Electrician Helper
Labors
A. Pre-Installation:
1. Coordinate with other trades to avoid any crossing of utilities without minimum
required clearance
2. Identify all structures, obstructions and existing facilities within the work area.
6| P a g e
CONSTRUCTION OF AL-URUBAH PARK
Low & Medium Voltage Cable Installation,
Testing & Termination
3. Place sign boards such as “DEEP EXCAVATION” “MEN AT WORK”, “DANGER” and
other warning boards to indicate the excavation work.
4. Barricade the area, provide basic need for facilities & hygiene for people viz. shelter,
toilet, drinking water.
5. Check the area of excavation to find out any underground facilities using
appropriate detective equipment, such as cable detector, metal detector etc.
6. Ensure necessary shop drawings, tools, materials, equipment and manpower
required for the work to be on site.
7. Coordinate with Safety Officer regarding the risks associated to the activity.
8. Mandatory PPE for all workers on field.
9. Inspect the cable route to ensure compliance to the IFC & shop drawings.
10. Inspect the cable trench depth and width upon completion of excavation to ensure
compliance to the project specification.
11. Inspect the size of the cables to ensure compliance to the IFC & shop drawings.
12. QC Inspector shall be responsible for Quality Inspection.
B. Installation:
1. Excavation area shall be surveyed and marked for the lines and levels by surveyor as
per approved shop drawings.
2. The area of excavation shall be cordoned off using safety barricade.
3. The trench shall be excavated up to the required depth and width from the existing
ground level as per drawings.
4. As per the site requirements the dump trucks shall be readily available at site for
disposing of the excavated materials.
5. Dry sand bedding shall be carried out for a thickness as per project specification at
the bottom of the trench prior to the installation of cables.
6. Proper housekeeping shall be carried out and all unwanted debris shall be disposed
from the site.
7. Suitable inspection request notice for trench excavation shall be submitted in
advance.
8. Prior to commence the cable pulling the trench shall be maintained clean.
9. Cable rollers shall be placed if required on the cable route.
7| P a g e
CONSTRUCTION OF AL-URUBAH PARK
Low & Medium Voltage Cable Installation,
Testing & Termination
10. The cable drums shall be un-packed and cable shall be fixed to the winch, if used,
by means of a cable sock or gripper.
11. Cable laying shall generally start from one end of the route length or at any
suitable point if required.
12. In case of cable lengths which are more than one drum length, all cables which can
be laid from original position shall be completed. And then the cable pulling set-up
shall be re-positioned to the next location, from where the next length shall be
pulled.
13. Ensure the cable pulling lubricant shall be applied during cable pulling.
14. Bending radius of cables shall comply with cable manufacturer’s recommendation.
15. Unless the lengths exceed the maximum drum, lengths joints shall be avoided.
Joint markers indicating joint positions shall be provided above grade.
16. Prior to cut the cable, both ends must be inspected to ensure sufficient available
length for proper dressing and end termination.
17. The open ends shall be sealed till termination.
18. Cable identification tags shall be installed as per specification after the cable
pulling.
19. After completion the laying of all cables in the same route the cables shall be
dressed and tied.
20. Inspection for laying of cables shall be carried out by QC Inspector.
21. As-Built markup drawings certified by Contractor’s Supervisor and Engineer shall
be prepared.
22. Dry sand cover shall be installed on top of the cable as per relevant drawing.
23. Cable testing shall be performed wherever possible, prior to backfilling on Medium
Voltage cable only.
24. Empty cable drums shall be transported back to stores.
25. Cable markers shall be installed above grade to indicate the cable route in directly
buried trenches as per specification.
26. The excavated area will be backfilled using dune sand free from stones, rocks etc.
8| P a g e
CONSTRUCTION OF AL-URUBAH PARK
Low & Medium Voltage Cable Installation,
Testing & Termination
• All personnel involved in the mentioned activity shall be inducted on the safety,
health and environmental issues associated with the work.
• Only skill personnel shall be allowed to handle/operate the Equipment.
• Appropriate safety sign board, barriers and lighting and other safeguards shall be
provided as required by nature and location of the works. All operations shall be
carried out in accordance with safety requirements.
• All field personnel will use PPE (Personal Protective Equipment) safety
requirements like safety shoes, helmets, cover all, goggles etc. as required.
• All the safe practices shall be adopted during work activities.
• Good housekeeping around trees/ shrubs protection/relocation areas shall be
maintained and proper access to the working area shall be displayed by signboard.
• Ensure the area of working is properly illuminated, and provide access lighting.
• The Contractor shall take all measures reasonably required by any public or
concerned authority for the support and full protection of the utilities during the
progress of the Works, and shall construct and provide to the satisfaction of the
authority concerned, all works necessary for the prevention of damage or
interruption or delay.
• Conduct risk assessment for excavation for cable work and alert the team of
hazards through toolbox talks.
• Educate workers on how the hazards can be prevented and provide an action plan
for emergencies.
9| P a g e
CONSTRUCTION OF AL-URUBAH PARK
Low & Medium Voltage Cable Installation,
Testing & Termination
Risk Matrix
1| P a g e