0% found this document useful (0 votes)
48 views12 pages

Construction Management Workshop

Uploaded by

Chavan Creates
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
48 views12 pages

Construction Management Workshop

Uploaded by

Chavan Creates
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 12

CONSTRUCTION

MANAGEMENT WORKSHOP

COURSE CODE -17ECVP301


Team members :-

Name Roll no Usn no

Koduri Suchitra 158 01fe20bcv061

Manjunath Y B 159 01fe20bcv062

Nandala c 161 01fe20bcv064

Ajay L 162 01fe20bcv065

Srujana M u 165 01fe20bcv068


Problem statement 1
Your company has just won a contract for the construction of a shopping mall. The blockwise area distribution is listed below.

Total 7 blocks with interconnected pathways. 3 stories of underground parking.

Block no The area in square Feet

1 16000

2 18000

3 16000

4 16000

5 14000

6 18000

7 20000
The preliminary estimate of the project depicts about 12000 m3 of concrete.

The 7 blocks will be built on an 8-acre land (existing ground drawing (AUTOCAD) will be provided). You will be receiving mobilization amount in
the next 1 week. Use the drawing provided, as the basis for your site layout. The following pointers should help you to complete this assignment.

1. Conduct a detailed study of all the paperwork required by the local governing body and RERA, contact the Architect, Structural Engineer and
MEP Engineer to get the required permissions.

2. The layout should provide provision to stay of all skilled and unskilled labor. The Government of India has certain guidelines if the number of
labors on a site crosses a certain limit. These guidelines must be followed.

a. Check whether the concrete quantity justify setting up our own concrete plant or RMC will suffice. If the concrete plant is to be set
up, figure out potential vendors to supply the raw materials. Pay attention to the location of the plant as concrete must be supplied to
all corners of the site. Figure out the conveying systems.

b. Separate lots for carpenters and fabricators with material storage must be supplied.

c. The electrical and water requirements for the site and the labor camp must be provided.

d. Civil Engineering site office and sales office must be provided.

e. There are 2 gates for entrance and exit of this site.

f. Material testing lab and store must be set up.

3. Determine the probable number of working days for the completion of this project.
Minutes of meeting
Date : 17th,sept ,2022.

Time :11.33 pm.

Location: civil quadrangle .

Present members :All members were present .

Agenda :

Discussions
Pictures of Meeting
Rare
What is RERA?

As per the Real Estate (Regulation & Development) Act, 2016 – Real Estate Regulatory Authority (RERA) would regulate
and promote the real estate sector. The RERA will –

• Ensure the sale of land or building or a project in an efficient and transparent manner

• Protect the interests of consumers/buyers

• Establish an Appellate Tribunal mechanism to ensure speedy redressal of disputes

• Covers both residential and commercial projects.


Provisions under RERA:

1. All new projects are required to be registered with the regulating authority if not registered then 10% of the project cost as a penalty will be applicable.

2. As per the new act, developers cannot collect more than 10% of the value of the project in advance.

3. In case of any structural or other defects found within 5 years by the buyers, developers have to bear the responsibility of repairs.

4. Developers have to put aside 70% of project funds in a dedicated escrow account linked to the project and cannot be used for other projects.

5. Norms on the size of projects to be registered with RERA has been made 500 sq.m instead of 1000 sq m earlier.

6. Properties have to be sold on carpet area but not on Super Area.

7. Developers have to post details like the project plan, layout plan, approvals, land title status, details of promoters, contractors, architects, and date of completion on the RERA website.

8. Any violation of an order by the RERA Appellate Tribunal will invite jail term of 3 years.

9. Developers will be held accountable for details furnished; they will have to ensure that false promises are not made to buyers.
Advantages of RERA:

• Right to Information about the Property. This is in favour of the buyers.

• Standardized carpet area.

• Builders will be held responsible for any defect/fault in the construction.

• Grievances will be addressed and solved quickly.

• Builders won’t be able to delay the projects.

• Foreign investors would be attracted due to transparency


Disadvantages of RERA:

Some of the disadvantages are for Developers:

• Developers cannot use this fund in other projects hence new projects cannot be taken up on account of fund of previous
projects.

• Regulation requires approvals and permissions which may result in delay of starting/finishing of projects.

• Loss of interest of builders in Real estate projects due to strict regulations and reduced profit.

• Real estate has good employability potentials, but due to RERA developers are discouraged hence employment opportunities are
lost.

• Real estate involves use of construction materials which are means of source of earning to many small and large scale groups but
due to RERA the number of new projects are reduced hence demand of materials is reduced therefore, it has effect on economy
and employment both .

You might also like