0% found this document useful (0 votes)
60 views7 pages

Project Title: Construction of 2-Storey Residential Building

Uploaded by

Khrister Vergara
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
60 views7 pages

Project Title: Construction of 2-Storey Residential Building

Uploaded by

Khrister Vergara
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 7

Project Title: Construction of 2- Storey Residential Building

Activity Work Description Duration Precidence


A Preliminary site survey and assessment 3
B Development of design and achitectural plans 3 A
C Obtaining necessary permits 2 B
D Preparing the construction site for work activities 4 C
E Setting up temporary on-site facilities 3 C
F Procurement of materials and equipment 5 D, E
Mobilization of construction equipment and
G 5 F
materials

Foundation and Groundwork


H Excavation for foundation 6 G
I Setting up temporary shoring and support structures 3 H
J Pouring and curing the foundation footings 4 I
K Constructing of foundation walls 4 J
L Installing foundation drainage system 2 J
M Backfilling around foundation walls 4 K, L
N Compacting and leveling the ground floor 4 M

Ground Floor Construction


O Construction of columns 8 N
P Framing of ground floor 6 O
Q Installation of electrical and plumbing lines 2 O
R Concreting of ground floor slab 6 P, Q
S Installation of exterior walls 10 R
T Installation of interior walls 6 R
U Construction of beams 12 S, T
V Construction of stairs 6 U
W Installation of floor slab support 6 V

Second Floor Construction


X Framing of floor slab 6 W
Y Installation of electrical and plumbing lines 2 W
Z Concreting of ground floor slab 6 X, Y
A' Installation of exterior walls 10 Z
B' Installation of interior walls 6 Z
C' Construction of roof beams 12 A', B'
D' Erecting roof trusses 4 C'
E' Installtion of roof insulation foam 2 D'
F' Installation of roofing material 3 E'

Ground Floor Construction Phase 2


G' Exterior Plastering 5 F'
H' Interior Plastering 4 F'
I' Installation of ceiling 6 G, H'
J' Taping, sanding wall for smooth finish 4 I'
K' Painting walls and ceiling 10 J'
L' Installation of doors and windows 3 K'
M' Installing flooring tiles 8 L'
N' Installing cabinets 2 M'
O' Installation of bathroom and kitchen fixtures 2 M'
P' Septic tank excavation 4 N', O'
Q' Installation of septic tank walls 2 P'
R' Installation of septic tank plumbing lines 1 Q'
S' Concreting of septic tank 2 R'
Connecting plumbing fixtures to main water and
T' 2 S'
sewage system
U' Installation of lighting and power fixtures 4 T'
V' Installation of exterior claddings 6 U'

Second Floor Construction Phase 2


W' Exterior Plastering 5 F
X' Interior Plastering 4 F
Y' Installation of ceiling 6 W', X'
Z' Taping, sanding wall for smooth finish 4 Y'
A" Painting walls and ceiling 10 Z'
B" Installation of doors and windows 3 A"
C" Installing flooring tiles 8 B"
D" Installing cabinets 2 C"
E" Installation of bathroom fixtures 2 C"
Connecting plumbing fixtures to main water and
F" 2 D", E"
sewage system
G" Installation of lighting and power fixtures 4 F"
H" Installation of exterior claddings 6 G"

Post- Construction
I" Cleaning interior and exterior spaces 6 H"
J" Conducting final inspection 2 I"
K" Finishing final details 4 I"
L" Obtaining occupancy permit 2 J", K"
M" Handing over keys and documents to the owner 1 L"
Project Title: Construction of 2- Storey Residential Building

Activity Work Description Duration


A Preliminary site survey and assessment 3
B Development of design and achitectural plans 3
C Obtaining necessary permits 2
D Preparing the construction site for work activities 4
E Setting up temporary on-site facilities 3
F Procurement of materials and equipment 5
G Mobilization of construction equipment and materials 5

Foundation and Groundwork


H Excavation for foundation 6
I Setting up temporary shoring and support structures 3
J Pouring and curing the foundation footings 4
K Constructing of foundation walls 4
L Installing foundation drainage system 2
M Backfilling around foundation walls 4
N Compacting and leveling the ground floor 4

Ground Floor Construction


O Construction of columns 8
P Framing of ground floor 6
Q Installation of electrical and plumbing lines 2
R Concreting of ground floor slab 6
S Installation of exterior walls 10
T Installation of interior walls 6
U Construction of beams 12
V Construction of stairs 6
W Installation of floor slab support 6

Second Floor Construction


X Framing of floor slab 6
Y Installation of electrical and plumbing lines 2
Z Concreting of ground floor slab 6
A' Installation of exterior walls 10
B' Installation of interior walls 6
C' Construction of roof beams 12
D' Erecting roof trusses 4
E' Installtion of roof insulation foam 2
F' Installation of roofing material 3

Ground Floor Construction Phase 2


G' Exterior Plastering 5
H' Interior Plastering 4
I' Installation of ceiling 6
J' Taping, sanding wall for smooth finish 4
K' Painting walls and ceiling 10
L' Installation of doors and windows 3
M' Installing flooring tiles 8
N' Installing cabinets 2
O' Installation of bathroom and kitchen fixtures 2
P' Septic tank excavation 4
Q' Installation of septic tank walls 2
R' Installation of septic tank plumbing lines 1
S' Concreting of septic tank 2
Connecting plumbing fixtures to main water and
T' 2
sewage system
U' Installation of lighting and power fixtures 4
V' Installation of exterior claddings 6

Second Floor Construction Phase 2


W' Exterior Plastering 5
X' Interior Plastering 4
Y' Installation of ceiling 6
Z' Taping, sanding wall for smooth finish 4
A" Painting walls and ceiling 10
B" Installation of doors and windows 3
C" Installing flooring tiles 8
D" Installing cabinets 2
E" Installation of bathroom fixtures 2
Connecting plumbing fixtures to main water and
F" 2
sewage system
G" Installation of lighting and power fixtures 4
H" Installation of exterior claddings 6

Post- Construction
I" Cleaning interior and exterior spaces 6
J" Conducting final inspection 2
K" Finishing final details 4
L" Obtaining occupancy permit 2
M" Handing over keys and documents to the owner 1
Project Title: Construction of 2-Storey Residential Building

Start Finish Float Critical


Activity Duration
ES EF LS LF Total Free Activity
A 3 0 0 3 3 0 0 *
B 3 3 3 6 6 0 0 *
C 1 6 6 8 8 0 1
D 4 8 8 12 12 0 -4
E 3 8 9 11 12 -1 1
F 5 12 12 17 17 0 0 *
G 5 17 17 22 22 0 0 *
H 6 22 22 28 28 0 0 *
I 3 28 28 31 31 0 0 *
J 4 31 31 35 35 0 0 *
K 4 35 35 39 39 0 -4
L 2 35 37 37 39 -2 2
M 4 39 39 43 43 0 0 *
N 4 43 43 47 47 0 0 *
O 8 47 47 55 55 0 0 *
P 6 55 55 61 61 0 -6
Q 2 55 59 57 61 -4 4
R 6 61 61 67 67 0 0 *
S 10 67 67 77 77 0 -10
T 6 67 71 73 77 -4 4
U 12 77 77 89 89 0 0 *
V 6 89 89 95 95 0 0 *
W 6 95 95 101 101 0 0 *
X 6 101 101 107 107 0 -6
Y 2 101 105 103 107 -4 4
Z 6 107 107 113 113 0 0 *
A' 10 113 113 123 123 0 -10
B' 6 113 117 119 123 -4 4
C' 12 123 123 135 135 0 0 *
D' 4 135 135 139 139 0 0 *
E' 2 139 139 141 141 0 0 *
F' 3 141 141 144 144 0 0 *
G' 5 144 144 149 149 0 -5
H' 4 144 145 148 149 -1 1
I' 6 149 149 155 155 0 0 *
J' 4 155 155 159 159 0 0 *
K' 10 159 159 169 169 0 0 *
L' 3 169 169 172 172 0 0 *
M' 8 172 172 180 180 0 0 *
N' 2 180 180 182 182 0 -2
O' 2 180 180 182 182 0 0 *
P' 4 182 182 186 186 0 0 *
Q' 2 186 186 188 188 0 0 *
R' 1 188 188 189 189 0 0 *
S' 2 189 189 191 191 0 0 *
T' 2 191 191 193 193 0 0 *
U' 4 193 193 197 197 0 0 *
V' 6 197 197 203 203 0 -59
W' 5 144 153 149 158 -9 -5
X' 4 144 154 150 158 -10 1
Y' 6 149 156 155 164 -7 0
Z' 4 155 164 159 168 -9 0
A" 10 159 168 169 178 -9 0
B" 3 169 178 172 181 -9 0
C" 8 172 181 180 189 -9 0
D" 2 180 189 182 191 -9 -2
E" 2 180 189 182 191 -9 0
F" 2 182 191 184 193 -9 0
G" 4 184 193 188 197 -9 0
H" 6 188 197 194 203 -9 9
I" 6 203 203 209 209 0 0 *
J" 2 209 211 211 213 -2 -2
K" 4 209 209 213 213 0 0 *
L" 2 213 213 215 215 0 0 *
M" 1 215 215 216 216 0 0 *
Project Title: Construction of 2-Storey Residential Building
Critical Path

Legend:

Acitivity
Duration

A B F G H I J M N O R U
3 3 5 5 6 3 4 4 4 8 6 12

M' L' K' J' I' F' E' D' C' Z W V


8 3 10 4 6 3 2 4 12 6 6 6

O' P' Q' R' S' T' U' I" K" L" M"
2 4 2 1 2 2 4 6 4 2 1

Total = 163 days