Admin Completion Progress Report
Admin Completion Progress Report
AN EDU-TOURISM PROJECT
Contract Amt: Php 12,258,555
Contractor: KARKONZ BUILDERS AND CONSULTANCY
Date Started: April 2, 2022
The actual work accomplishment by Karkonz Builders and Consultancy as of April 30, 2022 is equivalent to 0.32% as opposed to
Therefore the Contractor has a slippage of 2.43% to date.
- 0.00%
assy. 19,809.56 19,809.56 22,922.03 0.19%
- 0.00%
no. 2,980.58 2,980.58 3,448.89 0.03%
- 0.00%
m 1,523.81 76,190.50 88,161.54 0.72%
- 0.00%
m 665.60 9,984.01 11,552.69 0.09%
- 0.00%
640.00 3,840.00 4,443.34 0.04%
m - 0.00%
323.05 8,076.28 9,345.22 0.08%
m - 0.00%
set 4,788.43 4,788.43 5,540.79 0.05%
- 0.00%
nos. 1,645.72 14,811.49 17,138.67 0.14%
- 0.00%
nos. 908.19 1,816.38 2,101.77 0.02%
- 0.00%
59,712.73 293,932.48 340,115.08 2.77% 0.00% -
s equivalent to 0.32% as opposed to 2.75% planned construction progress based on the submitted construction work schedule.
Recommending Approval:
Value of Work
To Date %Weight
Completed
Total
Total Amount w/ OCM,Profit, Construction
Labor VAT Cost
0.95% 4049.91920743 0.03% 369,050.00 57,985.05 427,035.05
0.00% - 0.00%
0.00% - 0.00%
10.00% 1,619.97 0.01%
10.00% 2,429.95 0.02%
15.11% 35370.0829933 0.29% 202,334.14 31,790.69 234,124.83
50.00% 7,575.38 0.06%
50.00% 13,060.99 0.11%
10.00% 8,597.79 0.07%
10.00% 6,135.93 0.05%
0.00% - 0.00%
0.00% 0 0.00% 2,876,600.86 451,970.88 3,328,571.74
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
0.00% 0 0.00% 491,114.95 77,163.87 568,278.82
- 0.00%
- 0.00%
0.00% 0 0.00% 435,905.19 68,489.32 504,394.51
- 0.00%
- 0.00%
- 0.00%
- 0.00%
0.00% 0 0.00% 368,247.92 57,859.03 426,106.95
- 0.00%
- 0.00%
0.00% 0 0.00% 1,121,706.06 176,242.20 1,297,948.26
- 0.00% 1 929,484.62 146,040.41 1,075,525.03
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00% 192,221.43 30,201.79 222,423.22
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
0.00% 0 0.00% 200,451.91 31,494.96 231,946.87
- 0.00%
- 0.00%
0.00% 0 0.00% 1,654,429.19 259,943.54 1,914,372.73
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
0.00% 0 0.00% 941,849.00 147,983.10 1,089,832.10
0.00 0.00% 1 264,475.35 41,554.31 306,029.66
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00% 293,932.48 46,182.60 340,115.08
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00% 74,538.81 11,711.52 86,250.33
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00% 245,836.06 38,625.71 284,461.77
- 0.00%
- 0.00%
- 0.00%
- 0.00% 48,803.45 7,667.99 56,471.44
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00% 4,754.30 746.99 5,501.29
- 0.00% 9,508.59 1,493.99 11,002.58
0.00% 0 0.00% 195,982.61 30,792.74 226,775.35
- 0.00%
- 0.00%
0.00% 0 0.00% 573,826.52 90,159.49 663,986.01
- 0.00%
- 0.00%
- 0.00%
- 0.00%
- 0.00%
0.00% 0 0.00% 1,162,526.72 182,655.93 1,345,182.65
- 0.00%
- 0.00%
- 0.00%
39,420.00 0.32% 10,594,025.07 1,664,530.82 12,258,555.89
1,664,530.82
Approved:
0.16
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
Name of Project: CULTURAL HERITAGE AND EDUCATIONAL RESEARCH CENTER: Location: New Site, ISAT U Main Campus, La Paz, Iloilo City Project Progress/Accomplishment Ending May 31,2021
AN EDU-TOURISM PROJECT Original Contract Duration: 300 CD
Contract Amt: Php 12,258,555.88
Approved Extension: Relative This Value of Work
Previous To Date %Weight
Contractor: KARKONZ BUILDERS AND CONSULTANCY Orig. Date of Completion: January 26,2022 Value Report Completed
Date Started: April 2, 2022
Rev. Date of Completion:
Total Direct Total
Item No. Scope of Work Quantity Unit Unit Price Cost (Matls & Construction %Weight
Labor) Cost
1.0 GENERAL REQUIREMENTS 1 lot 369,050.00 369,050.00 427,035.05 3.48% 0.03% 4,049.92 6.24% 6.27% 26778.6443594 0.22%
Permits (Building and Occupancy Permits Processing & Fire 1.00 lot 320,050.00 320,050.00
1.1 Code Fees, Sign and Seal, As-Built Plans, 370,336.18 3.02% - 5.00% 5.00% 18,516.81 0.15%
1.2 Material Testing 1.00 lot 14,000.00 14,000.00 16,199.68 0.13% - 1.00% 1.00% 162.00 0.00%
1.3 Water and Electricity 1.00 lot 14,000.00 14,000.00 16,199.68 0.13% 10.00% 1,619.97 10.00% 20.00% 3,239.94 0.03%
1.4 Health and Safety Requirements (PPE, Uniform and Signages) 1.00 lot 21,000.00 21,000.00 24,299.52 0.20% 10.00% 2,429.95 10.00% 20.00% 4,859.90 0.04%
2.0 SITEWORK 1 lot 37,731.46 202,334.10 234,124.83 1.91% 0.29% 35,370.08 30.28% 30.57% 71576.5275614 0.58%
2.1 Temporary Facilities (Enclosure and Bodega) 1.00 lot 13,093.50 13,093.50 15,150.75 0.12% 50.00% 7,575.38 50.00% 100.00% 15,150.75 0.12%
2.2 Mobilization/Demob, Clearing and Layout 1.00 lot 22,575.00 22,575.00 26,121.98 0.21% 50.00% 13,060.99 25.00% 75.00% 19,591.49 0.16%
2.3 Excavation & Backfilling and 235.10 cu.m. 316.05 74,303.36 85,977.90 0.70% 10.00% 8,597.79 15.00% 25.00% 21,494.47 0.18%
2.4 Gravel/Boulder Fill 34.25 cu.m. 1,548.25 53,027.56 61,359.25 0.50% 10.00% 6,135.93 15.00% 25.00% 15,339.81 0.13%
2.5 Termite Proofing 198.00 sq.m. 198.66 39,334.68 45,514.95 0.37% - 0.00% 0.00% - 0.00%
3.0 CONCRETE WORKS 79,825.20 2,876,600.86 3,328,571.74 27.15% 0.00% - 1.99% 1.99% 66250.458287 0.54%
3.1 Foundation - Footing & Tie Beams,4000 psi 57.38 cu.m. 9,978.15 572,546.25 662,504.58 5.40% - 10.00% 10.00% 66,250.46 0.54%
3.2 Columns from footing to roof beams; planted columns 49.78 cu.m. 9,978.15 496,712.31 574,755.63 4.69% - 0.00% 0.00% - 0.00%
3.3 2nd Floor Beams and Slabs 71.63 cu.m. 9,978.15 714,734.88 827,033.87 6.75% - 0.00% 0.00% - 0.00%
3.4 Mezzanine Floor Beams and Slabs 12.23 cu.m. 9,978.15 122,032.77 141,206.54 1.15% - 0.00% 0.00% - 0.00%
3.5 3rd Floor Beams and Slabs, Parapets and Conc. Gutters 53.40 cu.m. 9,978.15 532,833.21 616,551.84 5.03% - 0.00% 0.00% - 0.00%
3.6 Roof Beam Framing (3rd Floor) 5.92 cu.m. 9,978.15 59,070.65 68,351.81 0.56% - 0.00% 0.00% - 0.00%
3.7 Stairs 10.00 cu.m. 9,978.15 99,781.50 115,459.15 0.94% - 0.00% 0.00% - 0.00%
3.8 Ground Floor Slab and Paved Areas 27.95 cu.m. 9,978.15 278,889.29 322,708.31 2.63% - 0.00% 0.00% - 0.00%
4.0 MASONRY WORK 1,128.75 491,114.95 568,278.82 4.64% 0.00% - 0.00% 0.00% 0 0.00%
4.1 6" CHB 488.20 sq.m. 586.95 286,547.52 331,569.81 2.70% - 0.00% - 0.00%
4.2 4" CHB 377.57 sq.m. 541.80 204,567.43 236,709.01 1.93% - 0.00% - 0.00%
5.0 METAL WORKS 115,159.59 435,905.19 504,394.51 4.11% 0.00% - 0.00% 0.00% 0 0.00%
5.1 Roof Framing 297 sq.m. 1,083.60 321,829.20 372,394.93 3.04% - 0.00% - 0.00%
5.2 Stair Handrails and Railings 1 lot 46,910.85 46,910.85 54,281.47 0.44% - 0.00% - 0.00%
5.3 Ramp Railings 1 lot 26,593.35 26,593.35 30,771.69 0.25% - 0.00% - 0.00%
5.4 Stainless Steel Signage 1 lot 40,571.79 40,571.79 46,946.42 0.38% - 0.00% - 0.00%
6.0 MOISTURE AND THERMAL PROTECTION 1,715.70 368,247.92 426,106.95 3.48% 0.00% - 0.00% 0.00% 0 0.00%
6.1 Metal Roofing and Insulation 252.45 sq.m. 1,264.20 319,147.29 369,291.64 3.01% - 0.00% - 0.00%
6.2 Waterproofing 108.75 sq.m. 451.50 49,100.63 56,815.30 0.46% - 0.00% - 0.00%
7.0 DOORS, WINDOWS & GLAZING 706,535.17 1,121,706.06 1,297,948.26 10.59% 0.00% - 0.00% 0.00% 0 0.00%
7.1 Windows and Glass 641,970.68 929,484.63 1,075,525.05 8.77% 0.00% - - 0.00%
- 0.00% - 0.00%
The actual work accomplishment by Karkonz Builders and Consultancy as of May 31, 2022 is equivalent to 1.34% as opposed to 9.66% planned construction progress based on the submitted construction work schedule.
Therefore the Contractor has a slippage of 8.32% to date.
Ar. NICOLE C. MARAÑON Engr. JOSE L. VIRGULA, JR. Engr. ALBERT Z. JANAPON Dr. GABRIEL M. SALISTRE, JR. Dr. RAUL F. MUYONG
Project Supervising Architect Project Supervising Engineer Director, PDAS VP AF University President
Total
Total Amount w/ OCM,Profit, Construction
Labor VAT Cost ohpt dc final unit cost
369,050.00 57,985.05 427,035.05 427,035.05 57,985.05 369,050.00 369,050.00 100.00% 369,050.00 427,035.05 1.00
573,826.52 90,159.49 663,986.01 663,986.01 90,159.49 573,826.52 573,826.52 100.00% 573,826.52 663,986.01 1.00
83,797.50 14.60% 83,797.50 96,963.74
57,486.33 10.02% 57,486.33 66,518.57
178,182.04 31.05% 178,182.04 206,177.96
96,711.30 16.85% 96,711.30 111,906.56
157,649.35 27.47% 157,649.35 182,419.18
1,162,526.72 182,655.93 1,345,182.65 1,345,182.65 182,655.94 1,162,526.71 1,162,526.71 100.00% 1,162,526.71 1,345,182.65 1.00
300,203.25 25.82% 300,203.25 347,371.12
216,690.20 18.64% 216,690.20 250,736.52
645,633.26 55.54% 645,633.26 747,075.02
10,594,025.07 1,664,530.82 12,258,555.89
1,664,530.82
0.16
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
Name of Project: CULTURAL HERITAGE AND EDUCATIONAL RESEARCH CENTER: Location: New Site, ISAT U Main Campus, La Paz, Iloilo City Project Progress/Accomplishment Ending June 30,2022
AN EDU-TOURISM PROJECT Original Contract Duration: 300 CD
Contract Amt: Php 12,258,555.88
Approved Extension: Relative This Value of Work
Previous To Date %Weight
Contractor: KARKONZ BUILDERS AND CONSULTANCY Orig. Date of Completion: January 26,2022 Value Report Completed
Date Started: April 2, 2022
Rev. Date of Completion:
Total Direct Total
Item No. Scope of Work Quantity Unit Unit Price Cost (Matls & Construction %Weight
Labor) Cost
1.0 GENERAL REQUIREMENTS 1 lot 369,050.00 369,050.00 427,035.05 3.48% 0.22% 26,778.64 11.49% 11.71% 49,993.36 0.41%
Permits (Building and Occupancy Permits Processing & Fire 1.00 lot 320,050.00 320,050.00
1.1 Code Fees, Sign and Seal, As-Built Plans, 370,336.18 3.02% 5.00% 18,516.81 5.00% 10.00% 37,033.62 0.30%
1.2 Material Testing 1.00 lot 14,000.00 14,000.00 16,199.68 0.13% 1.00% 162.00 4.00% 5.00% 809.98 0.01%
1.3 Water and Electricity 1.00 lot 14,000.00 14,000.00 16,199.68 0.13% 20.00% 3,239.94 10.00% 30.00% 4,859.90 0.04%
1.4 Health and Safety Requirements (PPE, Uniform and Signages) 1.00 lot 21,000.00 21,000.00 24,299.52 0.20% 20.00% 4,859.90 10.00% 30.00% 7,289.85 0.06%
2.0 SITEWORK 1 lot 37,731.46 202,334.10 234,124.83 1.91% 0.58% 71,576.53 39.43% 40.01% 93,677.10 0.76%
2.1 Temporary Facilities (Enclosure and Bodega) 1.00 lot 13,093.50 13,093.50 15,150.75 0.12% 100.00% 15,150.75 0.00% 100.00% 15,150.75 0.12%
2.2 Mobilization/Demob, Clearing and Layout 1.00 lot 22,575.00 22,575.00 26,121.98 0.21% 75.00% 19,591.49 0.00% 75.00% 19,591.49 0.16%
2.3 Excavation & Backfilling and 235.10 cu.m. 316.05 74,303.36 85,977.90 0.70% 25.00% 21,494.47 15.00% 40.00% 34,391.16 0.28%
2.4 Gravel/Boulder Fill 34.25 cu.m. 1,548.25 53,027.56 61,359.25 0.50% 25.00% 15,339.81 15.00% 40.00% 24,543.70 0.20%
2.5 Termite Proofing 198.00 sq.m. 198.66 39,334.68 45,514.95 0.37% - 0.00% 0.00% - 0.00%
3.0 CONCRETE WORKS 79,825.20 2,876,600.86 3,328,571.74 27.15% 0.54% 66,250.46 6.77% 7.31% 243,371.72 1.99%
3.1 Foundation - Footing & Tie Beams,4000 psi 57.38 cu.m. 9,978.15 572,546.25 662,504.58 5.40% 10.00% 66,250.46 25.00% 35.00% 231,876.60 1.89%
3.2 Columns from footing to roof beams; planted columns 49.78 cu.m. 9,978.15 496,712.31 574,755.63 4.69% - 2.00% 2.00% 11,495.11 0.09%
3.3 2nd Floor Beams and Slabs 71.63 cu.m. 9,978.15 714,734.88 827,033.87 6.75% - 0.00% 0.00% - 0.00%
3.4 Mezzanine Floor Beams and Slabs 12.23 cu.m. 9,978.15 122,032.77 141,206.54 1.15% - 0.00% 0.00% - 0.00%
3.5 3rd Floor Beams and Slabs, Parapets and Conc. Gutters 53.40 cu.m. 9,978.15 532,833.21 616,551.84 5.03% - 0.00% 0.00% - 0.00%
3.6 Roof Beam Framing (3rd Floor) 5.92 cu.m. 9,978.15 59,070.65 68,351.81 0.56% - 0.00% 0.00% - 0.00%
3.7 Stairs 10.00 cu.m. 9,978.15 99,781.50 115,459.15 0.94% - 0.00% 0.00% - 0.00%
3.8 Ground Floor Slab and Paved Areas 27.95 cu.m. 9,978.15 278,889.29 322,708.31 2.63% - 0.00% 0.00% - 0.00%
4.0 MASONRY WORK 1,128.75 491,114.95 568,278.82 4.64% 0.00% - 0.00% 0.00% - 0.00%
4.1 6" CHB 488.20 sq.m. 586.95 286,547.52 331,569.81 2.70% - 0.00% - 0.00%
4.2 4" CHB 377.57 sq.m. 541.80 204,567.43 236,709.01 1.93% - 0.00% - 0.00%
5.0 METAL WORKS 115,159.59 435,905.19 504,394.51 4.11% 0.00% - 0.00% 0.00% - 0.00%
5.1 Roof Framing 297 sq.m. 1,083.60 321,829.20 372,394.93 3.04% - 0.00% - 0.00%
5.2 Stair Handrails and Railings 1 lot 46,910.85 46,910.85 54,281.47 0.44% - 0.00% - 0.00%
5.3 Ramp Railings 1 lot 26,593.35 26,593.35 30,771.69 0.25% - 0.00% - 0.00%
5.4 Stainless Steel Signage 1 lot 40,571.79 40,571.79 46,946.42 0.38% - 0.00% - 0.00%
6.0 MOISTURE AND THERMAL PROTECTION 1,715.70 368,247.92 426,106.95 3.48% 0.00% - 0.00% 0.00% - 0.00%
6.1 Metal Roofing and Insulation 252.45 sq.m. 1,264.20 319,147.29 369,291.64 3.01% - 0.00% - 0.00%
6.2 Waterproofing 108.75 sq.m. 451.50 49,100.63 56,815.30 0.46% - 0.00% - 0.00%
7.0 DOORS, WINDOWS & GLAZING 706,535.17 1,121,706.06 1,297,948.26 10.59% 0.00% - 0.00% 0.00% - 0.00%
7.1 Windows and Glass 641,970.68 929,484.63 1,075,525.05 8.77% 0.00% - - 0.00%
- 0.00% - 0.00%
Ar. NICOLE C. MARAÑON Engr. JOSE L. VIRGULA, JR. Engr. ALBERT Z. JANAPON Dr. GABRIEL M. SALISTRE, JR. Dr. RAUL F. MUYONG
Project Supervising Architect Project Supervising Engineer Director, PDAS VP AF University President
Total
Total Amount w/ OCM,Profit, Construction
Labor VAT Cost ohpt dc final unit cost
369,050.00 57,985.05 427,035.05 427,035.05 57,985.05 369,050.00 369,050.00 100.00% 369,050.00 427,035.05 1.00
573,826.52 90,159.49 663,986.01 663,986.01 90,159.49 573,826.52 573,826.52 100.00% 573,826.52 663,986.01 1.00
83,797.50 14.60% 83,797.50 96,963.74
57,486.33 10.02% 57,486.33 66,518.57
178,182.04 31.05% 178,182.04 206,177.96
96,711.30 16.85% 96,711.30 111,906.56
157,649.35 27.47% 157,649.35 182,419.18
1,162,526.72 182,655.93 1,345,182.65 1,345,182.65 182,655.94 1,162,526.71 1,162,526.71 100.00% 1,162,526.71 1,345,182.65 1.00
300,203.25 25.82% 300,203.25 347,371.12
216,690.20 18.64% 216,690.20 250,736.52
645,633.26 55.54% 645,633.26 747,075.02
10,594,025.07 1,664,530.82 12,258,555.89
1,664,530.82
0.16
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
Name of Project: CULTURAL HERITAGE AND EDUCATIONAL RESEARCH CENTER: Location: New Site, ISAT U Main Campus, La Paz, Iloilo City Project Progress/Accomplishment Ending July 31,2022
AN EDU-TOURISM PROJECT Original Contract Duration: 300 CD
Contract Amt: Php 12,258,555.88
Approved Extension: Relative This Value of Work
Previous To Date %Weight
Contractor: KARKONZ BUILDERS AND CONSULTANCY Orig. Date of Completion: January 26,2022 Value Report Completed
Date Started: April 2, 2022
Rev. Date of Completion:
Total Direct Total
Item No. Scope of Work Quantity Unit Unit Price Cost (Matls & Construction %Weight
Labor) Cost
1.0 GENERAL REQUIREMENTS 1 lot 369,050.00 369,050.00 427,035.05 3.48% 0.41% 49,993.36 16.30% 16.71% 71,345.11 0.58%
Permits (Building and Occupancy Permits Processing & Fire 1.00 lot 320,050.00 320,050.00
1.1 Code Fees, Sign and Seal, As-Built Plans, 370,336.18 3.02% 10.00% 37,033.62 5.00% 15.00% 55,550.43 0.45%
1.2 Material Testing 1.00 lot 14,000.00 14,000.00 16,199.68 0.13% 5.00% 809.98 5.00% 10.00% 1,619.97 0.01%
1.3 Water and Electricity 1.00 lot 14,000.00 14,000.00 16,199.68 0.13% 30.00% 4,859.90 5.00% 35.00% 5,669.89 0.05%
1.4 Health and Safety Requirements (PPE, Uniform and Signages) 1.00 lot 21,000.00 21,000.00 24,299.52 0.20% 30.00% 7,289.85 5.00% 35.00% 8,504.83 0.07%
2.0 SITEWORK 1 lot 37,731.46 202,334.10 234,124.83 1.91% 0.76% 93,677.10 45.54% 46.30% 108,410.82 0.88%
2.1 Temporary Facilities (Enclosure and Bodega) 1.00 lot 13,093.50 13,093.50 15,150.75 0.12% 100.00% 15,150.75 0.00% 100.00% 15,150.75 0.12%
2.2 Mobilization/Demob, Clearing and Layout 1.00 lot 22,575.00 22,575.00 26,121.98 0.21% 75.00% 19,591.49 0.00% 75.00% 19,591.49 0.16%
2.3 Excavation & Backfilling and 235.10 cu.m. 316.05 74,303.36 85,977.90 0.70% 40.00% 34,391.16 10.00% 50.00% 42,988.95 0.35%
2.4 Gravel/Boulder Fill 34.25 cu.m. 1,548.25 53,027.56 61,359.25 0.50% 40.00% 24,543.70 10.00% 50.00% 30,679.63 0.25%
2.5 Termite Proofing 198.00 sq.m. 198.66 39,334.68 45,514.95 0.37% 0.00% - 0.00% 0.00% - 0.00%
3.0 CONCRETE WORKS 79,825.20 2,876,600.86 3,328,571.74 27.15% 1.99% 243,371.72 7.06% 9.05% 301,242.15 2.46%
3.1 Foundation - Footing & Tie Beams,4000 psi 57.38 cu.m. 9,978.15 572,546.25 662,504.58 5.40% 35.00% 231,876.60 7.00% 42.00% 278,251.92 2.27%
3.2 Columns from footing to roof beams; planted columns 49.78 cu.m. 9,978.15 496,712.31 574,755.63 4.69% 2.00% 11,495.11 2.00% 4.00% 22,990.23 0.19%
3.3 2nd Floor Beams and Slabs 71.63 cu.m. 9,978.15 714,734.88 827,033.87 6.75% - 0.00% 0.00% - 0.00%
3.4 Mezzanine Floor Beams and Slabs 12.23 cu.m. 9,978.15 122,032.77 141,206.54 1.15% - 0.00% 0.00% - 0.00%
3.5 3rd Floor Beams and Slabs, Parapets and Conc. Gutters 53.40 cu.m. 9,978.15 532,833.21 616,551.84 5.03% - 0.00% 0.00% - 0.00%
3.6 Roof Beam Framing (3rd Floor) 5.92 cu.m. 9,978.15 59,070.65 68,351.81 0.56% - 0.00% 0.00% - 0.00%
3.7 Stairs 10.00 cu.m. 9,978.15 99,781.50 115,459.15 0.94% - 0.00% 0.00% - 0.00%
3.8 Ground Floor Slab and Paved Areas 27.95 cu.m. 9,978.15 278,889.29 322,708.31 2.63% - 0.00% 0.00% - 0.00%
4.0 MASONRY WORK 1,128.75 491,114.95 568,278.82 4.64% 0.00% - 0.00% 0.00% - 0.00%
4.1 6" CHB 488.20 sq.m. 586.95 286,547.52 331,569.81 2.70% - 0.00% - 0.00%
4.2 4" CHB 377.57 sq.m. 541.80 204,567.43 236,709.01 1.93% - 0.00% - 0.00%
5.0 METAL WORKS 115,159.59 435,905.19 504,394.51 4.11% 0.00% - 0.00% 0.00% - 0.00%
5.1 Roof Framing 297 sq.m. 1,083.60 321,829.20 372,394.93 3.04% - 0.00% - 0.00%
5.2 Stair Handrails and Railings 1 lot 46,910.85 46,910.85 54,281.47 0.44% - 0.00% - 0.00%
5.3 Ramp Railings 1 lot 26,593.35 26,593.35 30,771.69 0.25% - 0.00% - 0.00%
5.4 Stainless Steel Signage 1 lot 40,571.79 40,571.79 46,946.42 0.38% - 0.00% - 0.00%
6.0 MOISTURE AND THERMAL PROTECTION 1,715.70 368,247.92 426,106.95 3.48% 0.00% - 0.00% 0.00% - 0.00%
6.1 Metal Roofing and Insulation 252.45 sq.m. 1,264.20 319,147.29 369,291.64 3.01% - 0.00% - 0.00%
6.2 Waterproofing 108.75 sq.m. 451.50 49,100.63 56,815.30 0.46% - 0.00% - 0.00%
7.0 DOORS, WINDOWS & GLAZING 706,535.17 1,121,706.06 1,297,948.26 10.59% 0.00% - 0.00% 0.00% - 0.00%
7.1 Windows and Glass 641,970.68 929,484.63 1,075,525.05 8.77% 0.00% - - 0.00%
- 0.00% - 0.00%
Ar. NICOLE C. MARAÑON Engr. JOSE L. VIRGULA, JR. Engr. ALBERT Z. JANAPON Dr. GABRIEL M. SALISTRE, JR. Dr. RAUL F. MUYONG
Project Supervising Architect Project Supervising Engineer Director, PDAS VP AF University President
Total
Total Amount w/ OCM,Profit, Construction
Labor VAT Cost ohpt dc final unit cost
369,050.00 57,985.05 427,035.05 427,035.05 57,985.05 369,050.00 369,050.00 100.00% 369,050.00 427,035.05 1.00
573,826.52 90,159.49 663,986.01 663,986.01 90,159.49 573,826.52 573,826.52 100.00% 573,826.52 663,986.01 1.00
83,797.50 14.60% 83,797.50 96,963.74
57,486.33 10.02% 57,486.33 66,518.57
178,182.04 31.05% 178,182.04 206,177.96
96,711.30 16.85% 96,711.30 111,906.56
157,649.35 27.47% 157,649.35 182,419.18
1,162,526.72 182,655.93 1,345,182.65 1,345,182.65 182,655.94 1,162,526.71 1,162,526.71 100.00% 1,162,526.71 1,345,182.65 1.00
300,203.25 25.82% 300,203.25 347,371.12
216,690.20 18.64% 216,690.20 250,736.52
645,633.26 55.54% 645,633.26 747,075.02
10,594,025.07 1,664,530.82 12,258,555.89
1,664,530.82
0.16
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
Name of Project: CULTURAL HERITAGE AND EDUCATIONAL RESEARCH CENTER: Location: New Site, ISAT U Main Campus, La Paz, Iloilo City Project Progress/Accomplishment Ending August 31,2022
AN EDU-TOURISM PROJECT Original Contract Duration: 300 CD
Contract Amt: Php 12,258,555.88
Approved Extension: Relative This Value of Work
Previous To Date %Weight
Contractor: KARKONZ BUILDERS AND CONSULTANCY Orig. Date of Completion: January 26,2022 Value Report Completed
Date Started: April 2, 2022
Rev. Date of Completion:
Total Direct Total
Item No. Scope of Work Quantity Unit Unit Price Cost (Matls & Construction %Weight
Labor) Cost
1.0 GENERAL REQUIREMENTS 1 lot 369,050.00 369,050.00 427,035.05 3.48% 0.58% 71,345.11 61.57% 62.15% 265,423.03 2.17%
Permits (Building and Occupancy Permits Processing & Fire 1.00 lot 320,050.00 320,050.00
1.1 Code Fees, Sign and Seal, As-Built Plans, 370,336.18 3.02% 15.00% 55,550.43 50.00% 65.00% 240,718.52 1.96%
1.2 Material Testing 1.00 lot 14,000.00 14,000.00 16,199.68 0.13% 10.00% 1,619.97 30.00% 40.00% 6,479.87 0.05%
1.3 Water and Electricity 1.00 lot 14,000.00 14,000.00 16,199.68 0.13% 35.00% 5,669.89 10.00% 45.00% 7,289.85 0.06%
1.4 Health and Safety Requirements (PPE, Uniform and Signages) 1.00 lot 21,000.00 21,000.00 24,299.52 0.20% 35.00% 8,504.83 10.00% 45.00% 10,934.78 0.09%
2.0 SITEWORK 1 lot 37,731.46 202,334.10 234,124.83 1.91% 0.88% 108,410.82 61.15% 62.04% 145,245.10 1.18%
2.1 Temporary Facilities (Enclosure and Bodega) 1.00 lot 13,093.50 13,093.50 15,150.75 0.12% 100.00% 15,150.75 0.00% 100.00% 15,150.75 0.12%
2.2 Mobilization/Demob, Clearing and Layout 1.00 lot 22,575.00 22,575.00 26,121.98 0.21% 75.00% 19,591.49 0.00% 75.00% 19,591.49 0.16%
2.3 Excavation & Backfilling and 235.10 cu.m. 316.05 74,303.36 85,977.90 0.70% 50.00% 42,988.95 25.00% 75.00% 64,483.42 0.53%
2.4 Gravel/Boulder Fill 34.25 cu.m. 1,548.25 53,027.56 61,359.25 0.50% 50.00% 30,679.63 25.00% 75.00% 46,019.44 0.38%
2.5 Termite Proofing 198.00 sq.m. 198.66 39,334.68 45,514.95 0.37% 0.00% - 0.00% 0.00% - 0.00%
3.0 CONCRETE WORKS 79,825.20 2,876,600.86 3,328,571.74 27.15% 2.46% 301,242.15 10.18% 12.64% 420,580.72 3.43%
3.1 Foundation - Footing & Tie Beams,4000 psi 57.38 cu.m. 9,978.15 572,546.25 662,504.58 5.40% 42.00% 278,251.92 5.00% 47.00% 311,377.15 2.54%
3.2 Columns from footing to roof beams; planted columns 49.78 cu.m. 9,978.15 496,712.31 574,755.63 4.69% 4.00% 22,990.23 15.00% 19.00% 109,203.57 0.89%
3.3 2nd Floor Beams and Slabs 71.63 cu.m. 9,978.15 714,734.88 827,033.87 6.75% 0.00% - 0.00% 0.00% - 0.00%
3.4 Mezzanine Floor Beams and Slabs 12.23 cu.m. 9,978.15 122,032.77 141,206.54 1.15% 0.00% - 0.00% 0.00% - 0.00%
3.5 3rd Floor Beams and Slabs, Parapets and Conc. Gutters 53.40 cu.m. 9,978.15 532,833.21 616,551.84 5.03% 0.00% - 0.00% 0.00% - 0.00%
3.6 Roof Beam Framing (3rd Floor) 5.92 cu.m. 9,978.15 59,070.65 68,351.81 0.56% 0.00% - 0.00% 0.00% - 0.00%
3.7 Stairs 10.00 cu.m. 9,978.15 99,781.50 115,459.15 0.94% 0.00% - 0.00% 0.00% - 0.00%
3.8 Ground Floor Slab and Paved Areas 27.95 cu.m. 9,978.15 278,889.29 322,708.31 2.63% 0.00% - 0.00% 0.00% - 0.00%
4.0 MASONRY WORK 1,128.75 491,114.95 568,278.82 4.64% 0.00% - 2.00% 2.00% 11,365.58 0.09%
4.1 6" CHB 488.20 sq.m. 586.95 286,547.52 331,569.81 2.70% - 2.00% 2.00% 6,631.40 0.05%
4.2 4" CHB 377.57 sq.m. 541.80 204,567.43 236,709.01 1.93% - 2.00% 2.00% 4,734.18 0.04%
5.0 METAL WORKS 115,159.59 435,905.19 504,394.51 4.11% 0.00% - 0.00% 0.00% - 0.00%
5.1 Roof Framing 297 sq.m. 1,083.60 321,829.20 372,394.93 3.04% - 0.00% - 0.00%
5.2 Stair Handrails and Railings 1 lot 46,910.85 46,910.85 54,281.47 0.44% - 0.00% - 0.00%
5.3 Ramp Railings 1 lot 26,593.35 26,593.35 30,771.69 0.25% - 0.00% - 0.00%
5.4 Stainless Steel Signage 1 lot 40,571.79 40,571.79 46,946.42 0.38% - 0.00% - 0.00%
6.0 MOISTURE AND THERMAL PROTECTION 1,715.70 368,247.92 426,106.95 3.48% 0.00% - 0.00% 0.00% - 0.00%
6.1 Metal Roofing and Insulation 252.45 sq.m. 1,264.20 319,147.29 369,291.64 3.01% - 0.00% - 0.00%
6.2 Waterproofing 108.75 sq.m. 451.50 49,100.63 56,815.30 0.46% - 0.00% - 0.00%
7.0 DOORS, WINDOWS & GLAZING 706,535.17 1,121,706.06 1,297,948.26 10.59% 0.00% - 0.00% 0.00% - 0.00%
7.1 Windows and Glass 641,970.68 929,484.63 1,075,525.05 8.77% 0.00% - - 0.00%
- 0.00% - 0.00%
Ar. NICOLE C. MARAÑON Engr. JOSE L. VIRGULA, JR. Engr. ALBERT Z. JANAPON Dr. GABRIEL M. SALISTRE, JR. Dr. RAUL F. MUYONG
Project Supervising Architect Project Supervising Engineer Director, PDAS VP AF University President
Total
Total Amount w/ OCM,Profit, Construction
Labor VAT Cost ohpt dc final unit cost
369,050.00 57,985.05 427,035.05 427,035.05 57,985.05 369,050.00 369,050.00 100.00% 369,050.00 427,035.05 1.00
573,826.52 90,159.49 663,986.01 663,986.01 90,159.49 573,826.52 573,826.52 100.00% 573,826.52 663,986.01 1.00
83,797.50 14.60% 83,797.50 96,963.74
57,486.33 10.02% 57,486.33 66,518.57
178,182.04 31.05% 178,182.04 206,177.96
96,711.30 16.85% 96,711.30 111,906.56
157,649.35 27.47% 157,649.35 182,419.18
1,162,526.72 182,655.93 1,345,182.65 1,345,182.65 182,655.94 1,162,526.71 1,162,526.71 100.00% 1,162,526.71 1,345,182.65 1.00
300,203.25 25.82% 300,203.25 347,371.12
216,690.20 18.64% 216,690.20 250,736.52
645,633.26 55.54% 645,633.26 747,075.02
10,594,025.07 1,664,530.82 12,258,555.89
1,664,530.82
0.16
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
Name of Project: CULTURAL HERITAGE AND EDUCATIONAL RESEARCH CENTER: Location: New Site, ISAT U Main Campus, La Paz, Iloilo City Project Progress/Accomplishment Ending September 30,2022
AN EDU-TOURISM PROJECT Original Contract Duration: 300 CD
Contract Amt: Php 12,258,555.88
Approved Extension: Relative This Value of Work
Previous To Date %Weight
Contractor: KARKONZ BUILDERS AND CONSULTANCY Orig. Date of Completion: January 26,2022 Value Report Completed
Date Started: April 2, 2022
Rev. Date of Completion:
Total Direct Total
Item No. Scope of Work Quantity Unit Unit Price Cost (Matls & Construction %Weight
Labor) Cost
1.0 GENERAL REQUIREMENTS 1 lot 369,050.00 369,050.00 427,035.05 3.48% 2.17% 265,423.03 60.65% 62.82% 268,257.97 2.19%
Permits (Building and Occupancy Permits Processing & Fire 1.00 lot 320,050.00 320,050.00
1.1 Code Fees, Sign and Seal, As-Built Plans, 370,336.18 3.02% 65.00% 240,718.52 0.00% 65.00% 240,718.52 1.96%
1.2 Material Testing 1.00 lot 14,000.00 14,000.00 16,199.68 0.13% 40.00% 6,479.87 5.00% 45.00% 7,289.85 0.06%
1.3 Water and Electricity 1.00 lot 14,000.00 14,000.00 16,199.68 0.13% 45.00% 7,289.85 5.00% 50.00% 8,099.84 0.07%
1.4 Health and Safety Requirements (PPE, Uniform and Signages) 1.00 lot 21,000.00 21,000.00 24,299.52 0.20% 45.00% 10,934.78 5.00% 50.00% 12,149.76 0.10%
2.0 SITEWORK 1 lot 37,731.46 202,334.10 234,124.83 1.91% 1.18% 145,245.10 62.22% 63.40% 148,438.03 1.21%
2.1 Temporary Facilities (Enclosure and Bodega) 1.00 lot 13,093.50 13,093.50 15,150.75 0.12% 100.00% 15,150.75 0.00% 100.00% 15,150.75 0.12%
2.2 Mobilization/Demob, Clearing and Layout 1.00 lot 22,575.00 22,575.00 26,121.98 0.21% 75.00% 19,591.49 0.00% 75.00% 19,591.49 0.16%
2.3 Excavation & Backfilling and 235.10 cu.m. 316.05 74,303.36 85,977.90 0.70% 75.00% 64,483.42 3.00% 78.00% 67,062.76 0.55%
2.4 Gravel/Boulder Fill 34.25 cu.m. 1,548.25 53,027.56 61,359.25 0.50% 75.00% 46,019.44 1.00% 76.00% 46,633.03 0.38%
2.5 Termite Proofing 198.00 sq.m. 198.66 39,334.68 45,514.95 0.37% 0.00% - 0.00% 0.00% - 0.00%
3.0 CONCRETE WORKS 79,825.20 2,876,600.86 3,328,571.74 27.15% 3.43% 420,580.72 11.63% 15.06% 501,222.01 4.09%
3.1 Foundation - Footing & Tie Beams,4000 psi 57.38 cu.m. 9,978.15 572,546.25 662,504.58 5.40% 47.00% 311,377.15 1.00% 48.00% 318,002.20 2.59%
3.2 Columns from footing to roof beams; planted columns 49.78 cu.m. 9,978.15 496,712.31 574,755.63 4.69% 19.00% 109,203.57 10.00% 29.00% 166,679.13 1.36%
3.3 2nd Floor Beams and Slabs 71.63 cu.m. 9,978.15 714,734.88 827,033.87 6.75% 0.00% - 2.00% 2.00% 16,540.68 0.13%
3.4 Mezzanine Floor Beams and Slabs 12.23 cu.m. 9,978.15 122,032.77 141,206.54 1.15% 0.00% - 0.00% 0.00% - 0.00%
3.5 3rd Floor Beams and Slabs, Parapets and Conc. Gutters 53.40 cu.m. 9,978.15 532,833.21 616,551.84 5.03% 0.00% - 0.00% 0.00% - 0.00%
3.6 Roof Beam Framing (3rd Floor) 5.92 cu.m. 9,978.15 59,070.65 68,351.81 0.56% 0.00% - 0.00% 0.00% - 0.00%
3.7 Stairs 10.00 cu.m. 9,978.15 99,781.50 115,459.15 0.94% 0.00% - 0.00% 0.00% - 0.00%
3.8 Ground Floor Slab and Paved Areas 27.95 cu.m. 9,978.15 278,889.29 322,708.31 2.63% 0.00% - 0.00% 0.00% - 0.00%
4.0 MASONRY WORK 1,128.75 491,114.95 568,278.82 4.64% 0.09% 11,365.58 9.91% 10.00% 56,827.88 0.46%
4.1 6" CHB 488.20 sq.m. 586.95 286,547.52 331,569.81 2.70% 2.00% 6,631.40 8.00% 10.00% 33,156.98 0.27%
4.2 4" CHB 377.57 sq.m. 541.80 204,567.43 236,709.01 1.93% 2.00% 4,734.18 8.00% 10.00% 23,670.90 0.19%
5.0 METAL WORKS 115,159.59 435,905.19 504,394.51 4.11% 0.00% - 0.00% 0.00% - 0.00%
5.1 Roof Framing 297 sq.m. 1,083.60 321,829.20 372,394.93 3.04% - 0.00% - 0.00%
5.2 Stair Handrails and Railings 1 lot 46,910.85 46,910.85 54,281.47 0.44% - 0.00% - 0.00%
5.3 Ramp Railings 1 lot 26,593.35 26,593.35 30,771.69 0.25% - 0.00% - 0.00%
5.4 Stainless Steel Signage 1 lot 40,571.79 40,571.79 46,946.42 0.38% - 0.00% - 0.00%
6.0 MOISTURE AND THERMAL PROTECTION 1,715.70 368,247.92 426,106.95 3.48% 0.00% - 0.00% 0.00% - 0.00%
6.1 Metal Roofing and Insulation 252.45 sq.m. 1,264.20 319,147.29 369,291.64 3.01% - 0.00% - 0.00%
6.2 Waterproofing 108.75 sq.m. 451.50 49,100.63 56,815.30 0.46% - 0.00% - 0.00%
7.0 DOORS, WINDOWS & GLAZING 706,535.17 1,121,706.06 1,297,948.26 10.59% 0.00% - 0.00% 0.00% - 0.00%
7.1 Windows and Glass 641,970.68 929,484.63 1,075,525.05 8.77% 0.00% - - 0.00%
- 0.00% - 0.00%
Ar. NICOLE C. MARAÑON Engr. JOSE L. VIRGULA, JR. Engr. ALBERT Z. JANAPON Dr. GABRIEL M. SALISTRE, JR. Dr. RAUL F. MUYONG
Project Supervising Architect Project Supervising Engineer Director, PDAS VP AF University President
Total
Total Amount w/ OCM,Profit, Construction
Labor VAT Cost ohpt dc final unit cost
369,050.00 57,985.05 427,035.05 427,035.05 57,985.05 369,050.00 369,050.00 100.00% 369,050.00 427,035.05 1.00
573,826.52 90,159.49 663,986.01 663,986.01 90,159.49 573,826.52 573,826.52 100.00% 573,826.52 663,986.01 1.00
83,797.50 14.60% 83,797.50 96,963.74
57,486.33 10.02% 57,486.33 66,518.57
178,182.04 31.05% 178,182.04 206,177.96
96,711.30 16.85% 96,711.30 111,906.56
157,649.35 27.47% 157,649.35 182,419.18
1,162,526.72 182,655.93 1,345,182.65 1,345,182.65 182,655.94 1,162,526.71 1,162,526.71 100.00% 1,162,526.71 1,345,182.65 1.00
300,203.25 25.82% 300,203.25 347,371.12
216,690.20 18.64% 216,690.20 250,736.52
645,633.26 55.54% 645,633.26 747,075.02
10,594,025.07 1,664,530.82 12,258,555.89
1,664,530.82
0.16
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
Name of Project: CULTURAL HERITAGE AND EDUCATIONAL RESEARCH CENTER: Location: New Site, ISAT U Main Campus, La Paz, Iloilo City Project Progress/Accomplishment Ending October 31,2022
AN EDU-TOURISM PROJECT Original Contract Duration: 300 CD
Contract Amt: Php 12,258,555.88
Approved Extension: Relative This Value of Work
Previous To Date %Weight
Contractor: KARKONZ BUILDERS AND CONSULTANCY Orig. Date of Completion: January 26,2022 Value Report Completed
Date Started: April 2, 2022
Rev. Date of Completion:
Total Direct Total
Item No. Scope of Work Quantity Unit Unit Price Cost (Matls & Construction %Weight
Labor) Cost
1.0 GENERAL REQUIREMENTS 1 lot 369,050.00 369,050.00 427,035.05 3.48% 2.19% 268,257.97 66.20% 68.39% 292,039.67 2.38%
Permits (Building and Occupancy Permits Processing & Fire 1.00 lot 320,050.00 320,050.00
1.1 Code Fees, Sign and Seal, As-Built Plans, 370,336.18 3.02% 65.00% 240,718.52 5.00% 70.00% 259,235.33 2.11%
1.2 Material Testing 1.00 lot 14,000.00 14,000.00 16,199.68 0.13% 45.00% 7,289.85 20.00% 65.00% 10,529.79 0.09%
1.3 Water and Electricity 1.00 lot 14,000.00 14,000.00 16,199.68 0.13% 50.00% 8,099.84 5.00% 55.00% 8,909.82 0.07%
1.4 Health and Safety Requirements (PPE, Uniform and Signages) 1.00 lot 21,000.00 21,000.00 24,299.52 0.20% 50.00% 12,149.76 5.00% 55.00% 13,364.73 0.11%
2.0 SITEWORK 1 lot 37,731.46 202,334.10 234,124.83 1.91% 1.21% 148,438.03 70.27% 71.48% 167,345.68 1.37%
2.1 Temporary Facilities (Enclosure and Bodega) 1.00 lot 13,093.50 13,093.50 15,150.75 0.12% 100.00% 15,150.75 0.00% 100.00% 15,150.75 0.12%
2.2 Mobilization/Demob, Clearing and Layout 1.00 lot 22,575.00 22,575.00 26,121.98 0.21% 75.00% 19,591.49 0.00% 75.00% 19,591.49 0.16%
2.3 Excavation & Backfilling and 235.10 cu.m. 316.05 74,303.36 85,977.90 0.70% 78.00% 67,062.76 12.00% 90.00% 77,380.11 0.63%
2.4 Gravel/Boulder Fill 34.25 cu.m. 1,548.25 53,027.56 61,359.25 0.50% 76.00% 46,633.03 14.00% 90.00% 55,223.33 0.45%
2.5 Termite Proofing 198.00 sq.m. 198.66 39,334.68 45,514.95 0.37% 0.00% - 0.00% 0.00% - 0.00%
3.0 CONCRETE WORKS 79,825.20 2,876,600.86 3,328,571.74 27.15% 4.09% 501,222.01 23.15% 27.23% 906,512.48 7.39%
3.1 Foundation - Footing & Tie Beams,4000 psi 57.38 cu.m. 9,978.15 572,546.25 662,504.58 5.40% 48.00% 318,002.20 24.00% 72.00% 477,003.30 3.89%
3.2 Columns from footing to roof beams; planted columns 49.78 cu.m. 9,978.15 496,712.31 574,755.63 4.69% 29.00% 166,679.13 4.00% 33.00% 189,669.36 1.55%
3.3 2nd Floor Beams and Slabs 71.63 cu.m. 9,978.15 714,734.88 827,033.87 6.75% 2.00% 16,540.68 27.00% 29.00% 239,839.82 1.96%
3.4 Mezzanine Floor Beams and Slabs 12.23 cu.m. 9,978.15 122,032.77 141,206.54 1.15% 0.00% - 0.00% 0.00% - 0.00%
3.5 3rd Floor Beams and Slabs, Parapets and Conc. Gutters 53.40 cu.m. 9,978.15 532,833.21 616,551.84 5.03% 0.00% - 0.00% 0.00% - 0.00%
3.6 Roof Beam Framing (3rd Floor) 5.92 cu.m. 9,978.15 59,070.65 68,351.81 0.56% 0.00% - 0.00% 0.00% - 0.00%
3.7 Stairs 10.00 cu.m. 9,978.15 99,781.50 115,459.15 0.94% 0.00% - 0.00% 0.00% - 0.00%
3.8 Ground Floor Slab and Paved Areas 27.95 cu.m. 9,978.15 278,889.29 322,708.31 2.63% 0.00% - 0.00% 0.00% - 0.00%
4.0 MASONRY WORK 1,128.75 491,114.95 568,278.82 4.64% 0.46% 56,827.88 18.03% 18.50% 105,118.29 0.86%
4.1 6" CHB 488.20 sq.m. 586.95 286,547.52 331,569.81 2.70% 10.00% 33,156.98 1.00% 11.00% 36,472.68 0.30%
4.2 4" CHB 377.57 sq.m. 541.80 204,567.43 236,709.01 1.93% 10.00% 23,670.90 19.00% 29.00% 68,645.61 0.56%
5.0 METAL WORKS 115,159.59 435,905.19 504,394.51 4.11% 0.00% - 0.00% 0.00% - 0.00%
5.1 Roof Framing 297 sq.m. 1,083.60 321,829.20 372,394.93 3.04% - 0.00% - 0.00%
5.2 Stair Handrails and Railings 1 lot 46,910.85 46,910.85 54,281.47 0.44% - 0.00% - 0.00%
5.3 Ramp Railings 1 lot 26,593.35 26,593.35 30,771.69 0.25% - 0.00% - 0.00%
5.4 Stainless Steel Signage 1 lot 40,571.79 40,571.79 46,946.42 0.38% - 0.00% - 0.00%
6.0 MOISTURE AND THERMAL PROTECTION 1,715.70 368,247.92 426,106.95 3.48% 0.00% - 0.00% 0.00% - 0.00%
6.1 Metal Roofing and Insulation 252.45 sq.m. 1,264.20 319,147.29 369,291.64 3.01% - 0.00% - 0.00%
6.2 Waterproofing 108.75 sq.m. 451.50 49,100.63 56,815.30 0.46% - 0.00% - 0.00%
7.0 DOORS, WINDOWS & GLAZING 706,535.17 1,121,706.06 1,297,948.26 10.59% 0.00% - 0.00% 0.00% - 0.00%
7.1 Windows and Glass 641,970.68 929,484.63 1,075,525.05 8.77% 0.00% - - 0.00%
- 0.00% - 0.00%
Ar. NICOLE C. MARAÑON Engr. JOSE L. VIRGULA, JR. Engr. ALBERT Z. JANAPON Dr. GABRIEL M. SALISTRE, JR. Dr. RAUL F. MUYONG
Project Supervising Architect Project Supervising Engineer Director, PDAS VP AF University President
Total
Total Amount w/ OCM,Profit, Construction
Labor VAT Cost ohpt dc final unit cost
369,050.00 57,985.05 427,035.05 427,035.05 57,985.05 369,050.00 369,050.00 100.00% 369,050.00 427,035.05 1.00
573,826.52 90,159.49 663,986.01 663,986.01 90,159.49 573,826.52 573,826.52 100.00% 573,826.52 663,986.01 1.00
83,797.50 14.60% 83,797.50 96,963.74
57,486.33 10.02% 57,486.33 66,518.57
178,182.04 31.05% 178,182.04 206,177.96
96,711.30 16.85% 96,711.30 111,906.56
157,649.35 27.47% 157,649.35 182,419.18
1,162,526.72 182,655.93 1,345,182.65 1,345,182.65 182,655.94 1,162,526.71 1,162,526.71 100.00% 1,162,526.71 1,345,182.65 1.00
300,203.25 25.82% 300,203.25 347,371.12
216,690.20 18.64% 216,690.20 250,736.52
645,633.26 55.54% 645,633.26 747,075.02
10,594,025.07 1,664,530.82 12,258,555.89
1,664,530.82
0.16
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
Name of Project: CULTURAL HERITAGE AND EDUCATIONAL RESEARCH CENTER: Location: New Site, ISAT U Main Campus, La Paz, Iloilo City Project Progress/Accomplishment Ending November 30,2022
AN EDU-TOURISM PROJECT Original Contract Duration: 300 CD
Contract Amt: Php 12,258,555.88
Approved Extension: This Value of Work
Previous Relative Value To Date %Weight
Contractor: KARKONZ BUILDERS AND CONSULTANCY Orig. Date of Completion: January 26,2022 Report Completed
Date Started: April 2, 2022
Rev. Date of Completion:
Total Direct Total
Item No. Scope of Work Quantity Unit Unit Price Cost (Matls & Construction %Weight
Labor) Cost
1.0 GENERAL REQUIREMENTS 1 lot 369,050.00 369,050.00 427,035.05 3.48% 2.38% 292,039.67 71.01% 73.39% 313,391.43 2.56%
Permits (Building and Occupancy Permits Processing & Fire 1.00 lot 320,050.00 320,050.00
1.1 Code Fees, Sign and Seal, As-Built Plans, 370,336.18 3.02% 70.00% 259,235.33 5.00% 75.00% 277,752.14 2.27%
1.2 Material Testing 1.00 lot 14,000.00 14,000.00 16,199.68 0.13% 65.00% 10,529.79 5.00% 70.00% 11,339.77 0.09%
1.3 Water and Electricity 1.00 lot 14,000.00 14,000.00 16,199.68 0.13% 55.00% 8,909.82 5.00% 60.00% 9,719.81 0.08%
1.4 Health and Safety Requirements (PPE, Uniform and Signages) 1.00 lot 21,000.00 21,000.00 24,299.52 0.20% 55.00% 13,364.73 5.00% 60.00% 14,579.71 0.12%
2.0 SITEWORK 1 lot 37,731.46 202,334.10 234,124.83 1.91% 1.37% 167,345.68 72.47% 73.84% 172,871.76 1.41%
2.1 Temporary Facilities (Enclosure and Bodega) 1.00 lot 13,093.50 13,093.50 15,150.75 0.12% 100.00% 15,150.75 0.00% 100.00% 15,150.75 0.12%
2.2 Mobilization/Demob, Clearing and Layout 1.00 lot 22,575.00 22,575.00 26,121.98 0.21% 75.00% 19,591.49 0.00% 75.00% 19,591.49 0.16%
2.3 Excavation & Backfilling and 235.10 cu.m. 316.05 74,303.36 85,977.90 0.70% 90.00% 77,380.11 5.00% 95.00% 81,679.00 0.67%
2.4 Gravel/Boulder Fill 34.25 cu.m. 1,548.25 53,027.56 61,359.25 0.50% 90.00% 55,223.33 2.00% 92.00% 56,450.51 0.46%
2.5 Termite Proofing 198.00 sq.m. 198.66 39,334.68 45,514.95 0.37% 0.00% - 0.00% 0.00% - 0.00%
3.0 CONCRETE WORKS 79,825.20 2,876,600.86 3,328,571.74 27.15% 7.39% 906,512.48 25.26% 32.65% 1,086,924.32 8.87%
3.1 Foundation - Footing & Tie Beams,4000 psi 57.38 cu.m. 9,978.15 572,546.25 662,504.58 5.40% 72.00% 477,003.30 23.00% 95.00% 629,379.35 5.13%
3.2 Columns from footing to roof beams; planted columns 49.78 cu.m. 9,978.15 496,712.31 574,755.63 4.69% 33.00% 189,669.36 2.00% 35.00% 201,164.47 1.64%
3.3 2nd Floor Beams and Slabs 71.63 cu.m. 9,978.15 714,734.88 827,033.87 6.75% 29.00% 239,839.82 2.00% 31.00% 256,380.50 2.09%
3.4 Mezzanine Floor Beams and Slabs 12.23 cu.m. 9,978.15 122,032.77 141,206.54 1.15% 0.00% - 0.00% 0.00% - 0.00%
3.5 3rd Floor Beams and Slabs, Parapets and Conc. Gutters 53.40 cu.m. 9,978.15 532,833.21 616,551.84 5.03% 0.00% - 0.00% 0.00% - 0.00%
3.6 Roof Beam Framing (3rd Floor) 5.92 cu.m. 9,978.15 59,070.65 68,351.81 0.56% 0.00% - 0.00% 0.00% - 0.00%
3.7 Stairs 10.00 cu.m. 9,978.15 99,781.50 115,459.15 0.94% 0.00% - 0.00% 0.00% - 0.00%
3.8 Ground Floor Slab and Paved Areas 27.95 cu.m. 9,978.15 278,889.29 322,708.31 2.63% 0.00% - 0.00% 0.00% - 0.00%
4.0 MASONRY WORK 1,128.75 491,114.95 568,278.82 4.64% 0.86% 105,118.29 19.22% 20.08% 114,116.78 0.93%
4.1 6" CHB 488.20 sq.m. 586.95 286,547.52 331,569.81 2.70% 11.00% 36,472.68 2.00% 13.00% 43,104.07 0.35%
4.2 4" CHB 377.57 sq.m. 541.80 204,567.43 236,709.01 1.93% 29.00% 68,645.61 1.00% 30.00% 71,012.70 0.58%
5.0 METAL WORKS 115,159.59 435,905.19 504,394.51 4.11% 0.00% - 0.00% 0.00% - 0.00%
5.1 Roof Framing 297 sq.m. 1,083.60 321,829.20 372,394.93 3.04% - 0.00% - 0.00%
5.2 Stair Handrails and Railings 1 lot 46,910.85 46,910.85 54,281.47 0.44% - 0.00% - 0.00%
5.3 Ramp Railings 1 lot 26,593.35 26,593.35 30,771.69 0.25% - 0.00% - 0.00%
5.4 Stainless Steel Signage 1 lot 40,571.79 40,571.79 46,946.42 0.38% - 0.00% - 0.00%
6.0 MOISTURE AND THERMAL PROTECTION 1,715.70 368,247.92 426,106.95 3.48% 0.00% - 0.00% 0.00% - 0.00%
6.1 Metal Roofing and Insulation 252.45 sq.m. 1,264.20 319,147.29 369,291.64 3.01% - 0.00% - 0.00%
6.2 Waterproofing 108.75 sq.m. 451.50 49,100.63 56,815.30 0.46% - 0.00% - 0.00%
7.0 DOORS, WINDOWS & GLAZING 706,535.17 1,121,706.06 1,297,948.26 10.59% 0.00% - 0.00% 0.00% - 0.00%
7.1 Windows and Glass 641,970.68 929,484.63 1,075,525.05 8.77% 0.00% - - 0.00%
- 0.00% - 0.00%
Ar. NICOLE C. MARAÑON Engr. JOSE L. VIRGULA, JR. Engr. ALBERT Z. JANAPON Dr. GABRIEL M. SALISTRE, JR. Dr. RAUL F. MUYONG
Project Supervising Architect Project Supervising Engineer Director, PDAS VP AF University President
Total
Total Amount w/ OCM,Profit, Construction
Labor VAT Cost ohpt dc final unit cost
369,050.00 57,985.05 427,035.05 427,035.05 57,985.05 369,050.00 369,050.00 100.00% 369,050.00 427,035.05 1.00
573,826.52 90,159.49 663,986.01 663,986.01 90,159.49 573,826.52 573,826.52 100.00% 573,826.52 663,986.01 1.00
83,797.50 14.60% 83,797.50 96,963.74
57,486.33 10.02% 57,486.33 66,518.57
178,182.04 31.05% 178,182.04 206,177.96
96,711.30 16.85% 96,711.30 111,906.56
157,649.35 27.47% 157,649.35 182,419.18
1,162,526.72 182,655.93 1,345,182.65 1,345,182.65 182,655.94 1,162,526.71 1,162,526.71 100.00% 1,162,526.71 1,345,182.65 1.00
300,203.25 25.82% 300,203.25 347,371.12
216,690.20 18.64% 216,690.20 250,736.52
645,633.26 55.54% 645,633.26 747,075.02
10,594,025.07 1,664,530.82 12,258,555.89
1,664,530.82
0.16
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
1.00 TRUE
Name of Project: CULTURAL HERITAGE AND EDUCATIONAL RESEARCH CENTER: Location: New Site, ISAT U Main Campus, La Paz, Iloilo City Project Progress/Accomplishment Ending December 30,2022
AN EDU-TOURISM PROJECT Original Contract Duration: 300 CD
Contract Amt: Php 12,258,555.88
Approved Extension: This Value of Work
Previous Relative Value To Date %Weight
Contractor: KARKONZ BUILDERS AND CONSULTANCY Orig. Date of Completion: January 26,2022 Report Completed
Date Started: April 2, 2022
Rev. Date of Completion:
Total Direct Total
Item No. Scope of Work Quantity Unit Unit Price Cost (Matls & Construction %Weight
Labor) Cost
1.0 GENERAL REQUIREMENTS 1 lot 369,050.00 369,050.00 427,035.05 3.48% 2.56% 313,391.43 72.16% 74.72% 319,061.31 2.60%
Permits (Building and Occupancy Permits Processing & Fire 1.00 lot 320,050.00 320,050.00
1.1 Code Fees, Sign and Seal, As-Built Plans, 370,336.18 3.02% 75.00% 277,752.14 0.00% 75.00% 277,752.14 2.27%
1.2 Material Testing 1.00 lot 14,000.00 14,000.00 16,199.68 0.13% 70.00% 11,339.77 10.00% 80.00% 12,959.74 0.11%
1.3 Water and Electricity 1.00 lot 14,000.00 14,000.00 16,199.68 0.13% 60.00% 9,719.81 10.00% 70.00% 11,339.77 0.09%
1.4 Health and Safety Requirements (PPE, Uniform and Signages) 1.00 lot 21,000.00 21,000.00 24,299.52 0.20% 60.00% 14,579.71 10.00% 70.00% 17,009.66 0.14%
2.0 SITEWORK 1 lot 37,731.46 202,334.10 234,124.83 1.91% 1.41% 172,871.76 76.36% 77.77% 182,079.39 1.49%
2.1 Temporary Facilities (Enclosure and Bodega) 1.00 lot 13,093.50 13,093.50 15,150.75 0.12% 100.00% 15,150.75 0.00% 100.00% 15,150.75 0.12%
2.2 Mobilization/Demob, Clearing and Layout 1.00 lot 22,575.00 22,575.00 26,121.98 0.21% 75.00% 19,591.49 0.00% 75.00% 19,591.49 0.16%
2.3 Excavation & Backfilling and 235.10 cu.m. 316.05 74,303.36 85,977.90 0.70% 95.00% 81,679.00 5.00% 100.00% 85,977.90 0.70%
2.4 Gravel/Boulder Fill 34.25 cu.m. 1,548.25 53,027.56 61,359.25 0.50% 92.00% 56,450.51 8.00% 100.00% 61,359.25 0.50%
2.5 Termite Proofing 198.00 sq.m. 198.66 39,334.68 45,514.95 0.37% 0.00% - 0.00% 0.00% - 0.00%
3.0 CONCRETE WORKS 79,825.20 2,876,600.86 3,328,571.74 27.15% 8.87% 1,086,924.32 44.02% 52.89% 1,760,375.59 14.36%
3.1 Foundation - Footing & Tie Beams,4000 psi 57.38 cu.m. 9,978.15 572,546.25 662,504.58 5.40% 95.00% 629,379.35 5.00% 100.00% 662,504.58 5.40%
3.2 Columns from footing to roof beams; planted columns 49.78 cu.m. 9,978.15 496,712.31 574,755.63 4.69% 35.00% 201,164.47 15.00% 50.00% 287,377.82 2.34%
3.3 2nd Floor Beams and Slabs 71.63 cu.m. 9,978.15 714,734.88 827,033.87 6.75% 31.00% 256,380.50 67.00% 98.00% 810,493.19 6.61%
3.4 Mezzanine Floor Beams and Slabs 12.23 cu.m. 9,978.15 122,032.77 141,206.54 1.15% 0.00% - 0.00% 0.00% - 0.00%
3.5 3rd Floor Beams and Slabs, Parapets and Conc. Gutters 53.40 cu.m. 9,978.15 532,833.21 616,551.84 5.03% 0.00% - 0.00% 0.00% - 0.00%
3.6 Roof Beam Framing (3rd Floor) 5.92 cu.m. 9,978.15 59,070.65 68,351.81 0.56% 0.00% - 0.00% 0.00% - 0.00%
3.7 Stairs 10.00 cu.m. 9,978.15 99,781.50 115,459.15 0.94% 0.00% - 0.00% 0.00% - 0.00%
3.8 Ground Floor Slab and Paved Areas 27.95 cu.m. 9,978.15 278,889.29 322,708.31 2.63% 0.00% - 0.00% 0.00% - 0.00%
4.0 MASONRY WORK 1,128.75 491,114.95 568,278.82 4.64% 0.93% 114,116.78 29.90% 30.83% 175,217.83 1.43%
4.1 6" CHB 488.20 sq.m. 586.95 286,547.52 331,569.81 2.70% 13.00% 43,104.07 17.00% 30.00% 99,470.94 0.81%
4.2 4" CHB 377.57 sq.m. 541.80 204,567.43 236,709.01 1.93% 30.00% 71,012.70 2.00% 32.00% 75,746.88 0.62%
5.0 METAL WORKS 115,159.59 435,905.19 504,394.51 4.11% 0.00% - 0.74% 0.74% 3,723.95 0.03%
5.1 Roof Framing 297 sq.m. 1,083.60 321,829.20 372,394.93 3.04% - 1.00% 1.00% 3,723.95 0.03%
5.2 Stair Handrails and Railings 1 lot 46,910.85 46,910.85 54,281.47 0.44% - 0.00% - 0.00%
5.3 Ramp Railings 1 lot 26,593.35 26,593.35 30,771.69 0.25% - 0.00% - 0.00%
5.4 Stainless Steel Signage 1 lot 40,571.79 40,571.79 46,946.42 0.38% - 0.00% - 0.00%
6.0 MOISTURE AND THERMAL PROTECTION 1,715.70 368,247.92 426,106.95 3.48% 0.00% - 0.00% 0.00% - 0.00%
6.1 Metal Roofing and Insulation 252.45 sq.m. 1,264.20 319,147.29 369,291.64 3.01% - 0.00% - 0.00%
6.2 Waterproofing 108.75 sq.m. 451.50 49,100.63 56,815.30 0.46% - 0.00% - 0.00%
7.0 DOORS, WINDOWS & GLAZING 706,535.17 1,121,706.06 1,297,948.26 10.59% 0.00% - 0.00% 0.00% - 0.00%
7.1 Windows and Glass 641,970.68 929,484.63 1,075,525.05 8.77% 0.00% - - 0.00%
- 0.00% - 0.00%
The actual work accomplishment by Karkonz Builders and Consultancy as of December 30, 2022 is equivalent to 20.55% as opposed to 58.79% planned construction progress based on the submitted construction work schedule.
Therefore the Contractor has a slippage of 38.24% to date.
Ar. NICOLE C. MARAÑON Engr. JOSE L. VIRGULA, JR. Engr. ALBERT Z. JANAPON Dr. GABRIEL M. SALISTRE, JR. Dr. RAUL F. MUYONG
Project Supervising Architect Project Supervising Engineer Director, PDAS VP AF University President
Total
Total Amount w/ OCM,Profit, Construction
Labor VAT Cost ohpt dc final unit cost
369,050.00 57,985.05 427,035.05 427,035.05 57,985.05 369,050.00 369,050.00 100.00% 369,050.00 427,035.05 1.00 1.00 TRUE
573,826.52 90,159.49 663,986.01 663,986.01 90,159.49 573,826.52 573,826.52 100.00% 573,826.52 663,986.01 1.00 1.00 TRUE
83,797.50 14.60% 83,797.50 96,963.74
57,486.33 10.02% 57,486.33 66,518.57
178,182.04 31.05% 178,182.04 206,177.96
96,711.30 16.85% 96,711.30 111,906.56
157,649.35 27.47% 157,649.35 182,419.18
1,162,526.72 182,655.93 1,345,182.65 1,345,182.65 182,655.94 1,162,526.71 1,162,526.71 100.00% 1,162,526.71 1,345,182.65 1.00 1.00 TRUE
300,203.25 25.82% 300,203.25 347,371.12
216,690.20 18.64% 216,690.20 250,736.52
645,633.26 55.54% 645,633.26 747,075.02
10,594,025.07 1,664,530.82 12,258,555.89
1,664,530.82
0.16
Republic of the Philippines
Iloilo Science and Technology University
Burgos St., La Paz, Iloilo City, 5000 Philippines
Trunkline: (+6333) 320-7190 | Telefax: (+6333) 329-4274
https://www.isatu.edu.ph/
[email protected]/
Wood Plastic Composite (WPC) fluted indoor panel 5 pcs. ₱ 1,000.00 7,000.00
(15mm x 150mm x 2900) 8,890.00 0.99% 100.00% 100.00% 8,890.00
600mmØ Stainless steel ISAT U Logo 1 unit ₱ 10,000.00 14,000.00 17,780.00 1.98% 0.00% 0.00% -
timber Wood framings 1" x 2" x 10' S4S (assorted) 6 unit ₱ 3,000.00 25,200.00 32,004.00 3.56% 90.00% 90.00% 28,803.60
consumables 1 lot ₱ 10,000.00 14,000.00 17,780.00 1.98% 90.00% 50.00% 8,890.00
materials not included but necessary needed 1 lot ₱ 10,000.00 14,000.00 17,780.00 1.98% 90.00% 50.00% 8,890.00
TOTAL BUILDING CONSTRUCTION COST 898,424.67 100.00% 648,221.84
The actual work accomplishment by C SQUARE, ENGINEERING, CONSTRUCTION & SUPPLY as of April 14, 2024 is equivalent to 72.15% as opposed to 87.35% planned construction progress based on the submitted construction work schedule.
The works and materials used are in accordance with plans and specifications. Furthermore, the accomplishment for this period is recommended for approval and payment.
AR. NOWELL RON A. ARS ENGR. JOSE L. VIRGULA JR. SAMMY A. DAITAO, Ph. D.-TM RUSS ALLEN B. NAPUD, DIT GABRIEL M. SALISTRE JR., PEE, DIT
Project Development Offic Construction Supervising Engr. OIC, Director PDAS VP of Admin and Finance University President
Conforme:
%Weight
7.77%
4.24%
0.71%
2.83%
7.25%
1.66%
0.51%
0.89%
0.24%
1.66%
1.39%
0.36%
0.32%
0.23%
30.13%
8.71%
3.36%
0.69%
0.15%
0.08%
0.05%
0.95%
0.19%
1.19%
0.99%
0.11%
0.99%
0.56%
8.55%
1.78%
1.78%
6.39%
1.28%
1.25%
0.49%
0.32%
0.03%
0.05%
0.05%
0.36%
0.17%
0.90%
0.49%
0.99%
8.04%
2.08%
0.79%
0.11%
0.08%
0.05%
0.05%
0.28%
0.04%
0.59%
1.98%
1.98%
12.56%
2.08%
0.69%
0.79%
0.06%
0.04%
1.90%
0.03%
0.17%
0.10%
0.10%
0.11%
0.32%
0.99%
0.00%
3.21%
0.99%
0.99%
72.15%