Lecture 12
Lecture 12
Output Rate Capacity: For single product or homogenous products (units/ month)
Aggregate Unit of Capacity: Common unit of output measure (tons/hour, sales/ month)
For services, output measures are difficult to be assessed. So, input rate capacity is used,
like no. of beds available, available seat miles in airlines
Capacity Cushion: Additional amount of production capacity added onto the expected
demand
WAYS TO MEASURE CAPACITY
Actual output
Efficiency =
Effective capacity
Actual output
Utilization =
Design capacity
EFFICIENCY AND UTILIZATION
Design capacity = 50 trucks/day
Effective capacity = 40 trucks/day
Actual output = 36 units/day
Year
1 2 3 4 5
Product A
Bottles (000s) 60 100 150 200 250
Plastic Bags 100 200 300 400 500
Product B
Bottles (000s) 75 85 95 97 98
Plastic Bags 200 400 600 650 680
CALCULATE EQUIPMENT & LABOR REQUIREMENTS
Currently, three machines that can package up to 150,000 bottles each/ year are
available. Each machine requires two operators and can produce bottles for product A
as well as B. Currently, six bottle machine operators are available.
Also, five machines that can package up to 2,50,000 plastic bags each /year are
available. Each machine requires three operators and can produce plastic bags for
product A as well as B. Currently, twenty bag machine operators are available.
FOR YEAR 1
Year
1 2 3 4 5
Bottles (000s) 135 185 245 297 348
Plastic Bags 300 600 900 1050 1180
Total available capacity for bottle packaging = 3 machines* 15000 each=4,50,000/ year
Total available capacity for plastic machine= 5 machines* 250,000 each=1250,000/ year
No. of operators required =1.2 plastic packaging machine* 3 operator =3.6 operators
YEAR ON YEAR ANALYSIS
Year
1 2 3 4 5
Bottle Operation
Percentage capacity utilized 30 41 54 66 77
Machine requirement .9 1.23 1.62 1.98 2.31
Labor requirement 1.8 2.46 3.24 3.96 4.62
Plastic Bag Operation
Percentage capacity utilized 24
Machine requirement 1.2
Labor requirement 3.6
Do nothing 0 0
DECISION PROBLEM: UNDER CERTAINTY
The best of these worst numbers is $200,000, so the pessimist would build a small facility.
UNDER UNCERTAINTY : MAXIMAX CRITERIA
Maximax:
An alternative’s best payoff ($000) is the highest number in its row of the payoff matrix, or
The best of these best numbers is $800,000, so the optimist would build a large facility.
UNDER UNCERTAINTY : LAPLACE CRITERIA
Laplace:
With two events, we assign each a probability of 0.5. Thus, the weighted payoffs ($000) are
Do nothing 0 0
The best of these weighted payoffs is $480,000, so the realist would build a large facility.
UNDER UNCERTAINTY : MINIMAX REGRET
MINIMAX REGRET:
If demand turns out to be low, the best alternative is a small facility and its regret is 0 (or 200 − 200). If a
large facility is built when demand turns out to be low, the regret is 40 (or 200 − 160).
The column on the right shows the worst regret for each alternative. To minimize the maximum regret,
pick a large facility. The biggest regret is associated with having only a small facility and high demand.