Practical Training Report - 'Aina Nabihah Binti Mohd Zainal Fithri - 2020621602
Practical Training Report - 'Aina Nabihah Binti Mohd Zainal Fithri - 2020621602
SHAH ALAM
INTERNSHIP REPORT
DATE OF SUBMISSION :
GROUP : AP224 7B
PREPARED BY:
(2020621602)
DECLARATION
I declare that the work in this industrial training report was carried out following the regulations
of University Technology MARA. It is original and is the result of my work unless otherwise
indicated or acknowledged as referenced work. This industrial training report has not been
submitted to any other academic institution or non-academic institution for any degree or
qualification.
This industrial training report may be made available from the university library and may be
Signature of Student :
LIST OF ABBREVIATIONS................................................................................................................ v
i
7.0 APPENDICES .............................................................................................................................. 30
ii
LIST OF FIGURES
Figure 1 Google Earth from above side of Perintis Konsult Sdn Bhd 1
Figure 4 Email regarding adjustment for Sanitary Fitting and Wares from 6
architect
iii
LIST OF TABLES
iv
LIST OF ABBREVIATIONS
VO Variation order
PP Progress Payment
BQ Bills of Quantities
SO Superintendent officer
v
1.0 INTRODUCTION
1.1 Goal
comprehensive services for building and civil engineering projects. The firm excels in
management, and value engineering. With a primary focus on controlling costs and
minimizing risks, Perintis Konsult is dedicated to playing a positive and creative role in
realizing the objectives of its clients. The company consistently seeks self-motivated,
passionate, and dynamic individuals with unique skill sets, inviting them to showcase their
1.2 Location
Figure 1: Google Earth from above side of Perintis Konsult Sdn Bhd
PERINTIS KONSULT SDN BHD is located at Pusat Perniagaan Bukit Raja, Seksyen 7, 40000,
1
2.0 AGENCY IDENTIFICATION
Sr Nor
Afidah Binti
Ahmad
(Director)
Sr Jefri Bin
Masood
(Director)
Pn.
Cik Nurin
Pn. Nora Noramalina
Batrisyia Encik Firdaus
(Human Sufandi
(Quantity (Technician)
Resource) (Quantity
Surveyor)
Surveyor)
Perintis Konsult Sdn Bhd began operations starting from 2006 by offering critical services
in controlling costs, minimize any risks and providing positive and creative role in realising
the client’s objectives. PERINTIS KONSULT SDN. BHD. is a company registered with
Suruhanjaya Syarikat Malaysia and is issued with the registration number 735379-P for
its business operation. Perintis Konsult Sdn Bhd company is located at Seksyen 7 Shah
2
Alam while the existing location was in Subang Jaya, Selangor. The brief Company Profile
200601015627 (735379-P)
Ehsan
E-mail [email protected]
3
3.0 AREA OF STUDY 1: PRE-CONSTRUCTION
3.1 INTRODUCTION
The pre-construction stage is a crucial phase in the construction industry that involves
planning, preparation, and coordination before the actual construction work begins.
Successful completion of pre-construction tasks is essential for ensuring that the project
In my capacity at Perintis Konsult Sdn Bhd, I need to prepare a taking off and Bills of Quantities
(BQ) based on the revised drawing for a project named ‘Cadangan Membina dan Menyiapkan
Fasa 2A, 56-unit Rumah teres dua Tingkat yang mengandungi: a) Jenis A 20’x70’: Lot Tengah
– 48-unit, Jenis C 24’x70’: Lot Tepi – 8 Unit. The measurement process requires for all element
that consist of Piling Works, Building Works, External Works and Infrastructure works due to
variation order in design scope and specifications. In order to complete the taking-off process
for the calculation, all the calculated data were keyed in Excel application and saved in Perintis
Konsult Server and transferring the quantity into BuildSpace software in order to proceed for
BQ preparation.
Project Information
Project Name Cadangan Membina dan Menyiapkan Fasa 2A, 56-unit Rumah teres
Jorak, Daerah Muar, Johor Darul Takzim untuk Tetuan Sime Darby
4
Figure 3: Front page of Tender Document Commercial Proposal
The construction of this project involving many parties that consist of Developer of the project,
Architect, Civil & Structural Engineer, M & E Engineer, Quantity Surveyor and Landscape
Civil & Structural Engineer Jurutera Perunding Kamarul Saiful Sdn. Bhd.
5
3.2 CRITICAL ISSUE
Area to be critically assessed during the taking-off process is after the latest drawing was
issued, there were numerous changes in specifications and a lack of detailed information in
the drawing, leading to many assumptions that had to be made during the calculations.
There is variation order in drawing layout, specifications, and design due to employer’s
requirements which require the remeasurement of the building thus few changes need to do
in terms of quantity of length in the BQ, and the description in BQ needs to be adjusted
Figure 4: Email regarding adjustment for Sanitary Fitting and Wares from architect
6
Figure 5: Schedule of revised Sanitary fittings and wares
In this project, the cost estimation was influenced by the choice of brands and specifications.
In the pre-construction phase, the design team was required to submit a detailed report,
including the estimated cost, to Sime Darby Property (PAGOH) Sdn Bhd. During the cost
estimation process, it became evident that the developed cost exceeded the client's budget.
Consequently, Sime Darby Property rejected the initial design proposed by Perunding Alam
Bina Architect in the initial stage. The client provided feedback on the proposed brands during
a meeting. Subsequently, the design team engaged in discussions with Sime Darby and
reached an agreement to revise the specifications and brands outlined in the tender document.
The Variation order will lead to cost implications that involve Modifications to the initial contract
This will impact both the project's timeline and overall cost which is opposite to the client’s
7
3.3 METHODOLOGY TO SOLVE THE ISSUE
Issue: Variation order in terms of material and specification as per requested by the client
price.
In a situation where there are numerous variation orders during the pre-construction phase,
and the client wishes to maintain the original project cost, it's essential to find a balance
between accommodating client requests and managing project budget constraints. Here are
Negotiating with a client to change the brand of a material while maintaining the same quality
and specifications at a more reasonable price requires a strategic and thoughtful approach.
The first step in this negotiation process is a thorough understanding of the client's original
requirements and expectations for the material. This involves gaining insight into the specific
quality standards, specifications, and any unique features that the client deems necessary for
the project.
Once these requirements are clear, the next step is to conduct comprehensive research to
identify alternative brands that offer materials meeting or exceeding the original specifications.
8
It's crucial to ensure that the proposed material not only maintains the desired quality but
Having identified a suitable alternative, the negotiation process involves presenting a well-
structured proposal to the client. This proposal should highlight the features and benefits of
the new brand, emphasizing how it aligns with the client's needs and expectations. A key focus
during negotiations should be the cost-benefit analysis, demonstrating the significant cost
savings associated with the alternative brand without compromising on quality or performance.
To make the negotiation more tangible, providing samples of the alternative material for the
client to evaluate can be highly effective. Additionally, sharing testimonials or case studies
from other projects that have successfully implemented the proposed material can build
Throughout the negotiation process, it's essential to emphasize the long-term savings
associated with adopting the more reasonably priced material. This could include reduced
maintenance costs, extended lifespan, or other factors contributing to overall project savings.
The negotiation should be conducted with transparency, openly communicating the reasons
behind the proposed change and addressing any concerns the client may have.
Negotiations may involve discussions on adjusting contractual terms and conditions that could
schedules, warranties, and any other relevant aspects of the agreement. The goal is to
documentation should be a formal amendment to the contract, clearly outlining the revised
terms, including the change in material brand. Both parties should review and sign off on the
updated terms to ensure a mutual understanding and commitment to the negotiated changes.
This thorough and collaborative negotiation approach aims to secure a win-win outcome,
9
Option 2: Negotiation with Supppliers
Negotiating with suppliers and conducting a thorough comparison among various options
offering the same brand and specifications, as requested by the client at a reasonable price,
communicating the client's project requirements, quality standards, and budget constraints.
Effective negotiation seeks to create a mutually beneficial agreement that aligns with the
client's objectives.
During negotiations, price becomes a focal point. Suppliers may be willing to provide
discounts, volume incentives, and potential cost-saving measures forms an integral part of
these discussions. Equally important is the negotiation of terms and conditions, encompassing
payment schedules, delivery timelines, quality assurances, and any additional services that
Flexibility and customization are crucial negotiation elements. Suppliers willing to tailor their
offerings to better suit the client's unique project needs contribute to a more efficient and
streamlined procurement process. Building long-term relationships with suppliers is not only
beneficial for the current project but lays the groundwork for future collaborations, fostering a
key factors. Pricing structures are dissected to understand the breakdown of costs and any
hidden fees. Delivery timelines are scrutinized to ensure they align with project schedules.
Quality and specifications are closely examined, potentially involving the assessment of
product samples and certifications to guarantee compliance with industry standards. The
reputation and reliability of suppliers are weighed through client reviews, testimonials, and
10
The comparison also delves into value-added services that differentiate suppliers. Extended
warranties, technical support, or additional services beyond the basic requirements contribute
to the overall project value. The contractual terms proposed by each supplier are scrutinized
to ensure they align with the client's expectations. Clear terms regarding payment schedules,
return policies, and dispute resolution mechanisms are crucial for a transparent and successful
collaboration.
In conclusion, the negotiation with suppliers and the subsequent comparison process are
integral to securing the best value for the client's project. Balancing cost considerations with
quality and reliability ensures that the chosen supplier meets the client's expectations and
Determining the best option between negotiating with the client and negotiating with suppliers
hinges on various factors, each offering distinct advantages. Option 1, negotiating directly with
change in the material brand. The negotiation strategy involves thorough research to identify
alternative brands that not only meet but potentially exceed the specified standards,
comprehensive cost-benefit analysis, tangible samples for evaluation, and testimonials from
negotiation process.
This approach also emphasizes the long-term savings associated with adopting the more
reasonably priced material, such as reduced maintenance costs and extended lifespan.
Negotiations may extend to adjusting contractual terms impacted by the change, ensuring
collaborative solutions that benefit both parties. The agreement reached is formalized through
11
a documented contract amendment, securing a win-win outcome that aligns with the client's
multiple suppliers to find the most cost-effective solution. This option involves clear
communication with potential suppliers, highlighting the client's project requirements, quality
standards, and budget constraints. Negotiations with suppliers focus on competitive pricing,
potential discounts, and additional services, fostering flexibility and customization tailored to
the client's unique needs. The approach aims to establish long-term relationships that extend
structures, assessing delivery timelines, examining quality and specifications, and evaluating
the reputation and reliability of suppliers. The comparison also explores value-added services
that differentiate suppliers, contributing to the overall project value. Attention to contractual
terms ensures alignment with the client's expectations, emphasizing transparency and
successful collaboration.
In conclusion, although option 2 is the best option comparing with those two, it depends on
the project specifics and priorities. Option 1, negotiating with the client, emphasizes a
personalized and client-centric approach, while Option 2, negotiating with suppliers, provides
may involve a combination of both options, starting with client negotiations to understand
options. Ultimately, the goal is to achieve a balance between cost considerations, quality, and
12
4.0 AREA OF STUDY 2: POST CONTRACT AND COST CONTROL
4.1 INTRODUCTION
cost control, with a particular focus on the preparation and processing of payment claims,
specifically interim payments, for the Cadangan Membina Dan Menyiapkan Sebuah Muzium
Setem Negeri Selangor project in Daerah Petaling, Shah Alam, Selangor Darul Ehsan. This
the intricacies of the project's financial dynamics, contractual obligations, and industry
standards. I actively participate in the preparation of interim payment claims, ensuring that
they accurately reflect completed work, materials used, and associated costs in alignment with
As a trainee, I engage in the verification process, collaborating with various stakeholders such
address any discrepancies or queries during the evaluation of payment claims. This hands-on
experience not only enhances my technical skills in quantity surveying but also provides
insights into the practical aspects of post-contract cost control, a vital aspect of project
13
4.1.1 PROJECT’S BACKGROUND
Project Information
Contractor Class G7
14
4.2 CRITICAL ISSUE
The Cadangan Membina Dan Menyiapkan Sebuah Muzium Setem Negeri Selangor project in
Daerah Petaling, Shah Alam, Selangor Darul Ehsan involves several critical issues that
15
Figure 7: Summary of Ringkasan Arahan perubahan kerja
Firstly, the increase in earthwork quantity is due to errors in the original land survey plan used
during the tender process, resulting in changes in ground levels. This has also affected the
positioning of the 'Handicap Ramp' and the 'Retaining Wall' near the 'Bus Stop'. This additional
work has increased the project cost, which initially was RM491,661.70 as stated in the original
RM33,394.66 to be added to the original contract for this project. It is a significant concern as
this could entail the need for thorough assessment and planning to manage the increased
workload effectively. The earthwork quantity directly impacts the project's timeline, budget, and
16
overall construction logistics, necessitating careful coordination to ensure a smooth and
efficient execution.
The rearrangement of pantry space, meeting rooms, and stores represents another critical
issue. This involves strategic planning to optimize the functionality and efficiency of these
spaces within the museum. Addressing this issue requires a meticulous approach to space
utilization, considering the specific requirements of each area and ensuring that the
signboards, a prayer room (Musolla), roofed motorcycle parking, bus parking area, bus stop,
disabled (OKU) parking, refuse bin, and handicap ramp, introduces a multifaceted challenge.
Each element requires careful planning, adherence to safety standards, and compliance with
the project's success and requires effective communication and collaboration among
stakeholders.
Lastly, the replacement from Glass fibre Reinforced Concrete (GRC) Coping to Reinforced
Concrete Coping introduces a technical consideration. This change may have implications for
the project's design, structural integrity, and material requirements. Addressing this issue
transition while maintaining the project's overall quality and adherence to specifications.
In summary, the critical issues identified in the Cadangan Membina Dan Menyiapkan Sebuah
Muzium Setem Negeri Selangor project underscore the importance of careful planning,
17
Figure 8: The application of EOT No. 5
The latest issue in regards of Extension of time No. 5, the contractor has applied again for
delay of extension of time due to the scope of works. Unfortunately, the application was being
rejected. The request for a fifth time extension, specifically regarding the delay in completing
the water supply pipeline, cannot be considered due to the contractor's delayed project
planning, which is an error on the part of the contractor itself. Additionally, the pipeline work is
not on the critical path, which may not cause delays in other works. Many other tasks, such
as infrastructure work involving earthworks, roadwork, drainage, and so on, are still pending
completion.
18
Figure 9: EOT application review no 5.
Based on figure 9 shows the review of EOT No 5 applications by the Director of Perintis
19
4.3 METHODOLOGY TO SOLVE THE ISSUE
contractor.
the contractor.
Based on current issues that happen during the construction of the project, the contractor
keeps on repeating the same mistake which causes to issue the next extension of time. Then
The decision of a Superintending Officer (SO) to accept an application for an extension of time
by a contractor can be influenced by various factors. Here are some common reasons:
1. Contractual Entitlement:
If the contract between the parties explicitly allows for extensions of time under certain
conditions, the SO may accept the application in accordance with the terms and
beyond the contractor's control, such as adverse weather conditions, force majeure
3. Compensable Delays:
If the delay is compensable under the terms of the contract, meaning the contractor is
entitled to additional time due to specific compensable events, the SO may approve
the extension.
20
4. Evidence of Justification:
The contractor needs to provide clear and documented evidence justifying the need
for an extension. This could include detailed explanations, reports, and any relevant
The SO may consider whether the delayed activities are on the critical path of the
project. If the delay does not impact critical activities and does not cause a cascading
effect on other project milestones, the SO may be more inclined to accept the
extension.
6. Mitigation Efforts:
The SO may evaluate whether the contractor has taken reasonable steps to mitigate
the delay and has implemented measures to minimize its impact on the project
timeline.
The SO may consider the contractor's overall cooperation, communication, and good
faith efforts to resolve issues and meet project deadlines. A history of collaboration and
If the contractor follows the proper procedures outlined in the contract for requesting
If granting the extension does not cause undue prejudice to the employer or the project
It's important for the contractor to clearly communicate the reasons for the extension, provide
necessary documentation, and engage in a collaborative process with the SO. The decision
21
to accept or reject an extension request is typically based on a careful evaluation of the specific
Rejecting the application for an Extension of Time (EOT) and terminating the contractor is a
serious decision that is typically based on specific circumstances and breaches of contract.
Here are some reasons why an application for EOT might be rejected, leading to termination:
If the contractor fails to provide sufficient and justifiable reasons for the delay in the
project, the application for an EOT may be rejected. Lack of clear documentation,
evidence, or reasonable explanations could lead to scepticism about the validity of the
request.
failing to meet project milestones, quality standards, or safety requirements, the client
or project owner may reject the EOT application and terminate the contract.
If the contract specifies a maximum allowable extension of time, and the requested
extension exceeds these limits without proper justification, the application may be
rejected. The client might consider it a failure to adhere to the agreed-upon terms.
If the contractor fails to follow the proper procedures outlined in the contract for
requesting an extension, including notifying the relevant parties within the specified
22
Suppose the contractor has not taken reasonable steps to mitigate the impact of delays
or has not implemented measures to minimize the consequences. In that case, the
6. Repeated Delays:
If the project has experienced multiple delays, and the contractor has not demonstrated
a consistent effort to address and rectify these delays, the client may decide to reject
the EOT application and terminate the contract due to concerns about project
completion.
7. Financial Instability:
If the contractor is facing financial difficulties, unable to secure necessary funds, or has
failed to pay subcontractors and suppliers, the client may reject the EOT application
and terminate the contract due to concerns about the contractor's ability to complete
the project.
8. Safety Violations:
Persistent and serious safety violations that put workers, the public, or the project at
risk may lead to the rejection of an EOT application and termination, as safety is a
23
Best option: Rejecting the application of EOT and terminate the contractor.
• The remaining construction works for the TNB compact substation have been taken
• The pipe work is not on the critical path that could cause delays in other works.
• Other infrastructure works such as earthworks, road and drainage works, and arrow
• For the submission of QT 6a, the contractor needs to complete the building and sub-
24
Delay in the installation of aluminium composite panels
• Referring to the chronological percentage of facade works, the contractor should have
no obstacles in carrying out panel installation work as scheduled, even though there
the contractor to the architect indicates that the panel size is different from the contract.
However, the difference is not significant and does not contribute to the delay.
KSSB/2261/18/SSA/37 dated October 7, 2022, and the contractor has confirmed that
25
Figure 11: Notice for termination of the contractor
JKR Selangor has issued the Notice for termination purposes due to repeated delays and got
26
5.0 CONCLUSION
phase, cost-related issues take center stage, with a strong emphasis on achieving value for
money. Strategic planning during this stage is crucial to ensure that the construction project
remains within the client's budget, meeting their specific building requirements. This is
particularly relevant to the first highlighted issue, involving changes in brand and
specifications.
project effectively. This is exemplified in the instance where the cost estimation for the project
was directly impacted by the choice of brands and specifications. Initially, the design team
presented a detailed report, but the client expressed dissatisfaction and rejected the initial
design. Subsequently, discussions with Sime Darby Property led to a collaborative decision to
revise the specifications and opt for materials with lower costs, ensuring they still aligned with
the design requirements. This approach proves to be more efficient, striking a balance that not
only meets the client's needs but also prevents unexpected cost overruns, thus maintaining
overall cost-effectiveness.
For area 2, rejecting the application of EOT and terminate the contractor is crucial whenever
the contractor repeated delays of works and fails to provide reasonable justifications to the
SO. This is to prevent any circumstances that will lead to postponement of construction
completion date. The mistakes made by the contractor can no longer be considered due to
the fact that they have made the same mistakes over and over until they received a warning
letter from JKR Selangor. Therefore, retendering process will be implemented after the
27
6.0 LESSON LEARNT
Lesson Learned
in ensuring the success of construction projects. During the initial phase, where cost-related
issues are paramount, the lesson learned is that a strategic focus on achieving value for
money is crucial. The identified issue involving changes in brand and specifications
emphasizes the need for careful consideration during the planning stage. This signifies that
comprehensive planning not only addresses immediate cost concerns but also aligns with the
In the first highlighted area of pre-construction, the lesson learned revolves around adaptability
and collaboration. The rejection of the initial design by the client prompted a reassessment of
specifications and opt for more cost-effective materials demonstrates the importance of
flexibility and teamwork. This adaptive approach proves to be more efficient, striking a balance
that not only satisfies the client's needs but also safeguards against unforeseen cost overruns,
In the second highlighted area, the rejection of the application for an extension of time (EOT)
and the subsequent termination of the contractor highlight the significance of proactive project
management. The lesson learned here is the need for decisive action when faced with
repeated delays and inadequate justifications. It emphasizes that delays, if not promptly
addressed, can lead to potential postponement of the construction completion date, impacting
Self-Assessment
In assessing our practices and protocols, it becomes evident that continuous improvement is
integral to project success. The rejection of the initial design and subsequent adjustments
indicate a need for ongoing self-assessment. It is crucial to evaluate the efficiency of our
28
planning processes, ensuring they are adaptable to changing circumstances and client
feedback.
The self-assessment also highlights the importance of robust project management. The need
for rejecting EOT applications and terminating contracts underscores the necessity for clear
warning signs, such as the receipt of a warning letter from JKR Selangor, should prompt
environment and maintaining open lines of communication. This ensures that challenges are
framework for continuous improvement, ensuring that future construction projects are better
29
7.0 APPENDICES
30
Figure 14: Muzeum Setem Site
31