Construction Management
Construction Management
CONSTRUCTION ENGINEERING
Applied Mathematics
CONSTRUCTION ENGINEERING
Applied Mathematics
15. A soil weighs 1261 kg/LCM, 1665 kg/BCM and 2100 22. Calculate the required weight (kg) of cement and water
kg/CCM. What equivalent BCM contained in 600,000 LCM of per cubic meter of concrete.
this soil? A. 632 B. 555
C. 530 D. 587
16. Find the base width and height of a triangular spoil bank 23. Calculate required the weight (kg) of fine aggregates per
containing 76.5 BCM if the pile length is 9.14 m, the soil's cubic meter of concrete.
angle of repose is 37°, and its swell is 25%. A. 611 B. 745
C. 562 D. 452
Production on Heavy Equipments 24. Calculate the required weight (kg) of coarse aggregates
Production is commonly measured as volume per unit time per cubic meter of concrete.
(LCM/hr) A. 904 B. 1490
𝑷𝒓𝒐𝒅𝒖𝒄𝒕𝒊𝒐𝒏 = 𝑪 𝒙 𝑺 𝒙 𝑽 𝒙 𝑩 𝒙 𝑬 C. 1222 D. 1124
Where:
Situation: A concrete mix has the following composition.
C- cycles/hr S- Swing depth factor Cement 34 bags, 40kg/bag, Gs=3.15
V-heaped bucket volume B- Bucket fill factor Fine Aggregate 3000kg (dry basis), Gs=2.67
E- efficiency 1.15% moisture absorption
𝑻𝒐𝒕𝒂𝒍 𝑹𝒆𝒔𝒊𝒔𝒕𝒂𝒏𝒄𝒆 = 𝑹𝑹 + 𝑮𝑹 Coarse Aggregate 6000kg (dry basis), Gs=2.64
𝑹𝒆𝒔𝒊𝒔𝒕𝒂𝒏𝒄𝒆 = 𝑹𝒆𝒔𝒊𝒔𝒕𝒂𝒏𝒄𝒆 𝑭𝒂𝒄𝒕𝒐𝒓 𝒙 𝑾𝒆𝒊𝒈𝒉𝒕 2.0% moisture absorption
𝒌𝒈
𝑹𝑹𝑭 ( ) = 𝟐𝟎 + 𝟔 ∗ (𝒑𝒆𝒏𝒆𝒕𝒓𝒂𝒕𝒊𝒐𝒏 𝒊𝒏 𝒄𝒎. ) Water 600 liters
𝒕
20. Which of the following most nearly gives the volume
𝒍𝒃𝒔
𝑹𝑹𝑭 ( ) = 𝟒𝟎 + 𝟑𝟎 ∗ (𝒑𝒆𝒏𝒆𝒕𝒓𝒂𝒕𝒊𝒐𝒏 𝒊𝒏 𝒊𝒏. ) occupied by fine aggregate?
𝒕 A. 1.12 cu.m B. 1.86 cu.m
𝒌𝒈 𝒍𝒃𝒔
𝑮𝑹𝑭( ) = 𝟏𝟎 𝒙 𝑮𝒓𝒂𝒅𝒆(%) 𝑮𝑹𝑭( ) = 𝟐𝟎 𝒙 𝑮𝒓𝒂𝒅𝒆(%) C. 2.27 cu.m D. 1.57 cu.m
𝒕 𝒕 21. Which of the following most nearly gives the volume
𝒌𝒈 𝒍𝒃𝒔
𝑻𝒐𝒕𝒂𝒍 𝑹𝒆𝒔𝒊𝒔𝒕𝒂𝒏𝒄𝒆 ( , ) occupied by water?
𝒕 𝒕
𝑬𝒇𝒇. 𝑮𝒓𝒂𝒅𝒆 = A. 0.48 cu.m C. 0.54 cu.m
𝒌𝒈 𝒍𝒃𝒔
𝟏𝟎 𝒇𝒐𝒓 , 𝟐𝟎 𝒇𝒐𝒓 B. 0.60 cu.m D. 0.58 cu.m
𝒕 𝒕
17. Estimate the production in loose cubic meter per hour for 22. Which of the following most nearly gives the volume of
medium-weight clamshell excavating loose earth. Heaped concrete yield?
bucket capacity is 0.75 m3. A. 4.68 cu.m C. 5.21 cu.m
The soil is common earth with a bucket fill factor of 0.95. B. 4.37 cu.m D. 4.93 cu.m
Estimated cycle time is 40 s. Job efficiency is estimated at 50
min/h. Situation: Bill of guantity is to be prepared for a
guardhouse 3.6 m in height with one door opening only and
18. Find the expected production in loose cubic meter (LCM) a height of 2.1 m as shown. Assume density of steel equal to
per hour of a small hydraulic excavator. Heaped bucket 7860 kg/m3. CHB is 200 mm x 400 mm and 150 mm thick.
capacity is 0.57 m. The material is sand and gravel with a
bucket fill factor of 0.95. Job efficiency is 50 min/h. Average
depth of cut is 4.3 m. Maximum depth of cut is 6.1 m and
average swing is 90.
Situation:
A wheel tractor-scraper weighing 91 t is being operated on a
haul road with a tire penetration of 5 cm. The scraper is
ascending a slope of 5%.
19. What is the total resistance?
20. What is the effective grade?
CONSTRUCTION ENGINEERING
Applied Mathematics
C. 0.63 D. 0.75
31. Which of the following most nearly gives the total weight
of 12 mm bars?
A. 67 kg C. 76 kg
B. 49 kg D. 58 kg