Project Scope Report - NRE23-0021 Hazeldean BESS Connection
Project Scope Report - NRE23-0021 Hazeldean BESS Connection
Portfolio Management
Document Control
Change Record
Related Documents
Document Purpose
The purpose of this Project Scope Report is to define the business (functional) requirements that
the project is intended to deliver. These functional requirements are subject to Powerlink’s design
and construction standards and prevailing asset strategies, which will be detailed in documentation
produced during the detailed scoping and estimating undertaken by DTS (or OSD), i.e. it is not
intended for this document to provide a detailed scope of works that is directly suitable for
estimating.
Project Contacts
Project Details
Enervest Pty Ltd have submitted a connection enquiry under Chapter 5 of the NER
“Rules” for the establishment of Hazeldean BESS, a 800MW Battery Energy Storage
System with a proposed connection point approximately 60km South West of Tarong
Substation.
Briefly, the project consists of the establishment of a new 275kV switchyard cut in to
existing feeder F832 between Tarong and South Pine Substations, with the inclusion of
code compliant type one metering.
The project involves a combination of Transmission Network, IUSA and DCA works to
establish the proposed connection. Only the Transmission Network and IUSA components
will be detailed and estimated under the connection enquiry response.
The objective of this project is to establish the required assets required to facilitate the
proposed customer connection by 31 December 2025.
2. Project Drawings
H018 Tarong
Substation
South Pine
Substation
Existing 275kV
Feeder 832
NOTE: Transmission line cut-in provided as indicative location only and may differentiate
based on Design advice
New Country
Creek
Substation
(IUSA)
H002 South
Hazeldean Hazeldean
Pine
BESS BESS
Substation
NOTE: Line diagram and orientation provided as indicative connections only – Design to update
based upon SME input
3. Deliverables
The following deliverables must be provided in response to this Project Scope Report:
4. Project Scope
The following scope presents a functional overview of the desired outcomes of the project.
The proposed solution presented in the estimate must be developed with reference to the
remaining sections of this Project Scope Report, in particular Section 5 Special
Considerations.
Briefly, the project consists of the establishment of a new cut-in substation to facilitate the
connection of a new BESS facility onto the 275kV network between Tarong and South Pine
Substations with the inclusion of code compliant type 1 metering.
The works associated with this connection enquiry shall be broken into the following portions
to align with section 5 of the NER.
Design, procure, construct and commission all works deemed “cut-in works” under
chapter 5 of the NER. These works have been identified as non-contestable and must
be carried out by the relevant TNSP. These works do not form part of the threshold
calculation for IUSA.
Design, procure, construct and commission a cut-in into the existing 275kV feeder 832
between Tarong and South Pine Substations, between structures 1051-STR-7360 and
1051-STR-7362.
• String the new line deviations into the new substation, including OHEW/OPGW,
terminating at the appropriate landing beams. Powerlink shall provide the connection
hardware including droppers;
• The transmission line cut-in conductor should be sized to match the existing feeder
configuration/rating; and
• Feeder 832 has no OPGW, allowance must be made to retrofit OPGW along the
entire length of the feeder ~126km. Carry out a review of the existing structures
including earth peaks and include any upgrades necessary to facilitate the new
fibres. One path to be terminated in a lockable fibre optic canister on the leg of the
first structure outside of the substation and spliced to an underground fibre to
provide opto isolation.
Design, procure, construct and commission all IUSA secondary systems and
telecommunications works excluded from contestability under chapter 5 of the NER.
These works have been identified as non-contestable and must be carried out by the
relevant TNSP, however the estimated value of these works is included as part of the
threshold calculation for IUSA contestability.
Establish the appropriate secondary systems required for the new 275kV switchyard to
be located adjacent to the existing Powerlink easement on land acquired by the party
responsible for the contestable IUSA, taking into consideration the following
requirements:
• Powerlink requires a parcel of land with appropriate land tenure and access
rights to be provided by the party awarded the contestable IUSA, of a suitable
size to house the required secondary systems and communications
infrastructure (size to be determined by Design);
• Installation of redundant 125VDC supply systems and 50VDC supply systems (for
telecommunications equipment) in accordance with ASM-SPE-A3369893 DC
Supplies Specification;
• Carry out all required interface testing / SAT of the integration between the
contestable IUSA and the non-contestable IUSA.
The works deemed contestable under chapter 5 of the NER to establish a new 275kV
switchyard adjacent to the existing Powerlink easement including the acquisition of the
required land parcel. The contestable IUSA includes all site infrastructure and primary
plant associated with the substation switchyard.
Design, procure, construct and commission a 275kV switchyard adjacent to the existing
Powerlink easement within lot 13 on plan SP294647at 4439 Esk-Kilcoy Road,
Hazeldean;
• The cost of the acquisition of a free-hold parcel of land to the required size
suitable for the contestable and non-contestable IUSA scope has been
excluded from the enquiry response and will need to be considered separately.
Note: Size to be determined during design;
• Establish three (3) diameter circuit breaker and a half layout substation, to
facilitate the connection of the following bays;
o Four 275kV feeder bays to the proposed BESS including Point On Wave
(POW) functionality on the HV CBs;
Note: The proposed configuration to be set out to limit the impact of generator
caused outages/ events to the existing network;
o The main and alternate supplies are to be provided via two sets of bus
EMVTs through an AC changeover board; and
• Provision of all secondary cabling between the switchyard and the termination
racks associated with the control building.
These works are 100% contestable non-regulated works and are installed for customer
connection purposes. These works are not to be included in the statutory response to
the connection enquiry.
The proposed substation site is located within lot 13 on plan SP294647 at 4439 Esk-
Kilcoy Road, Hazeldean. The contestable IUSA Owner will be responsible for all
planning, environmental and cultural heritage approvals for the contestable IUSA
works.
The proponent will be responsible for all planning, environmental and cultural heritage
approvals for the DCA works.
Powerlink will be responsible for all planning, environmental and cultural heritage
approvals associated with the transmission line cut in works.
• The substation platform, substation access road and associated bulk earthworks
are to be provided by the contestable IUSA Owner satisfactory to Powerlink’s
requirements;
• Contestable IUSA Owner to install suitable conduit and / or trenching between the
landing gantry to the control building along redundant paths for the connection of
the OPGW / fibre;
• Contestable IUSA Owner to establish all secondary systems cabling between the
primary plant and the termination rack located external to the control building, with
the cable specification and design to meet Powerlink standard;
• The requirement and scope for any anti-islanding / runback schemes will be
determined upon application; and
• The DCA substation will be located adjacent to the IUSA substation and hence
earth-grid will be bonded.
5. Project Timing
The anticipated date by which the project will be approved is 28 October 2023.
The expected site access date (SAD), when the site is available for Powerlink construction
works to commence, is 3 months after notice to proceed / approval.
The latest date for the commissioning of the new assets included in this scope is 31
December 2025.
6. Special Considerations
Not applicable.
All required asset management and business information systems, including SPF drawing
and configuration records, Nexus, SAP, bay and circuit ratings shall be revised in
accordance with activities associated with this project.
Unless otherwise advised Deepesh Poudel will be the Project Sponsor for this project.
The Project Sponsor must be included in any discussions with any other areas of Network
& Business Development.
Garry Burke will provide the primary customer interface with Enervest. The Project
Sponsor should be kept informed of any discussions with the customer.
8. Asset Ownership
All the works detailed in this project will be Powerlink Queensland assets.
The asset boundary with the generator will be dependent upon the scope awarded to
Powerlink.
If Powerlink responsible for the non-contestable scope only: the primary asset boundary
will be the attachment points at the IUSA gantries for the regulated feeders. If awarded the
contestable IUSA, the primary asset boundary will be the attachment points at the IUSA
gantries for the customer feeders.
The secondary asset boundary between contestable IUSA and contestable IUSA will be
the termination rack for all secondary cables.
The telecommunications asset boundary between the non-contestable IUSA and DCA will
be the redundant fibre interface communication pits located at the Country Creek Substation
fence.
Operational issues that should be considered as part of the scope and estimate include:
10. Options
Not applicable
Not applicable
No related projects