Statistic of Complete Documents

The document provides a progress report for the feasibility study of the Hai Ha Thermal Power Plant project. It includes sections on project justification, construction site selection, fuel supply, environmental impact assessment, economic analysis, and engineering drawings. The report indicates the estimated completion dates for open tasks and lists the completed sections.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
25 views

Statistic of Complete Documents

The document provides a progress report for the feasibility study of the Hai Ha Thermal Power Plant project. It includes sections on project justification, construction site selection, fuel supply, environmental impact assessment, economic analysis, and engineering drawings. The report indicates the estimated completion dates for open tasks and lists the completed sections.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Estimated

NAME Condition time of


completion
FEASIBILITY STUDY REPORT DESCRIPTION
VOL 1: FEASIBITLITY STUDY REPORT
DESCRIPTION
C.1 Overview 14/08/2020
C.2 The justification for the need for project investment Completed
C.3 Construction site of Hai Ha Thermal Power Plant Completed
Selection of technological solutions and unit
C.4 Completed
capacity of Hai Ha 1 Thermal Power Plant
C.5 Supply fuel and raw materials to the plant Completed
C.6 Selection of technical options Completed
C.7 Connect the plant to the national electricity system 10/08/2020
C.8 Land clearance, compensation, and resettlement 07/08/2020
C.9 Organization of construction and project progress Completed
C.10 Environmental impact assessment 12/08/2020
C.11 Plant management and operation Completed
C.12 Total investment 10/08/2020
C.13 Economic - Financial Analysis 10/08/2020
C.14 Conclusions and recommendations 14/08/2020
VOL 2: LEGAL DOCUMENTS AND
SPECIALIZATION REPORTS
PART I: LEGAL DOCUMENTS
Approval for supplementation and adjustment
1 Completed
of electricity development planning
2 Document to ensure coal supply for the project
3 Agreement on construction power supply
4 Agreement on construction water supply
Required
5 EIA approval document of MONRE
Owner
Agreement with NPT on connection to the
6 support
national electricity system
Agreement of stack position and height with
7
QP
8 Other documents (if any)
PART II: SPECIALIZATION REPORT
PECC1 RESPONSIBILITY
1 Geological survey report Completed
2 Topographic survey report 12/08/2020
3 Meteorological survey report Completed
4 Fire protection report 10/08/2020
Report on compensation, land acquisition and
5 10/08/2020
resettlement
Report on transporting super-weight super-
6 10/08/2020
sized equipment
7 Report of coal port and shipping route 12/08/2020
8 Coal supply report Completed
Estimated
NAME Condition time of
completion
9 Report the connection to the national grid 12/08/2020
10 Environmental impact assessment report 12/08/2020
11 Fresh water supply report Completed
12 Report handling and reuse of ash Completed
BASIC DESIGN
VOL 1: BASIC DESIGN DESCRIPTION
C.1 Overview 14/08/2020
C.2 Natural conditions of the project area Completed
C.3 Basis of design 10/08/2020
C.4 Technology design solutions Completed
Basic design of electrical parts, C&I and
C.5 Completed
communications
C.6 Construction part design solutions 12/08/2020
C.7 Environmental protection solutions 12/08/2020
VOL 2: CALCULATION APPENDICES
Appendix Appendix for heat balance
Completed
01
Appendix The calculated input figures 10/08/2020
02
Appendix The main equipment of the unit 10/08/2020
03
Appendix Calculating the coal supply system
Completed
04
Appendix Calculating DO oil supply system
Completed
05
Appendix Calculation of limestone transport system
Completed
06
Appendix Calculation of water supply and wastewater
Completed
07
Appendix Calculate water balance
Completed
08
Appendix Calculation of ash removal system
Completed
09
Appendix Calculation of fire protection system
Completed
10
Appendix Calculation of environmental parameters 12/08/2020
11
Calculating the load capacity of pile types
Appendix Calculating the Turbine Space
12 Calculation of the central control house
Chimney Calculation
VOL 3: TOTAL INVESTMENT & FINANCIAL
ECONOMIC ANALYSIS
Appendix Tính toán tổng mức đầu tư
Estimated
NAME Condition time of
completion
01
Appendix Bảng tính phân tích Kinh tế - Tài
02 chính
VOL 4: DRAWINGS
PART I: GENERAL 5/5 Completed
Phần II: Phần công nghệ 27/37 14/08/2020
Phần III: Phần điện 15/15 Completed
Phần IV: Phần đo lường - điều khiển 2/2 Completed
Phần VI: Phần xây dựng 233/254 14/08/2020