ITP Boiler Installation
ITP Boiler Installation
: BBL/ITP-020
PT. TRUBA ALAM MANUNGGAL ENGINEERING
SFECO GROUP Revision : 0
INSPECTION & TEST PLAN ( ITP ) Date : March 20, 2009
PT PLN (Persero)
PLTU 3 BANGKA BELITUNG 2 x 30 MW Project no. : 2B0801
BOILER
REFERENCE VERIFYING INSPECTION ACTIVITIES
NO DESCRIPTION & ACTIVITIES CHECK LIST
DOCUMENT DOCUMENT SUBCON TAME PLN
1.0 DOCUMENT REVIEW
1.1 Technical Specification
1.1.1 Review Client's approved technical Specification. Construction Execution Plan Approved Tech. Spec. R R -
1.1.2 Finalize deviation, Amendments or Queries. Technical Spec./Code
1.2 The below procedure, specific requirement shall be check to compliance with specification or generate new
procedure if required
1.2.1 Material receiving, handling and storage procedure Construction Execution Plan Approved Procedure R R -
1.2.2 Installation , inspection and testing procedure Technical Spec./Code
1.2.3 Mechanical acceptance procedure, etc. Drawing
BOILER
REFERENCE VERIFYING INSPECTION ACTIVITIES
NO DESCRIPTION & ACTIVITIES CHECK LIST
DOCUMENT DOCUMENT SUBCON TAME PLN
4.0 INSTALLATION WORK
4.1 STEEL STRUCTURE
4.1.1 Clarification Foundation Handover (Civil Work to Mechanical Work) Drawing Inspection Report
4.1.1.1 Establish main civil setting points / datum are correct Handover Report A1 A1 -
4.1.1.2 Foundation check ( Center line, elevation, correctness ) Method Statement
BOILER
REFERENCE VERIFYING INSPECTION ACTIVITIES
NO DESCRIPTION & ACTIVITIES CHECK LIST
DOCUMENT DOCUMENT SUBCON TAME PLN
4.3 HEATING PIECES (Economize Coiled Tubes, 1st stage superheater Coiled Tubes, medium-temp. Reheater U-
tubes, Platen Superheater U-tubes, HT Superheater U-tubes and HT Reheater U-tubes)
4.3.1 Location & Elevation Tech Spec & Drawing Inspection Report A1 W/R R
4.3.2 Alignment Tech Spec & Drawing Inspection Report A1 W/R SW/R
4.3.3 Welding WPS-PQR/WQTR Weld History Sheet A1 W/R SW/R
4.3.4 Visual Inspection Tech Spec/Visual Insp Proc - A2 W SW
4.3.5 NDT Tech Spec/NDT Proc NDE Report A1 W/R SW/R
4.3.6 PWHT (if required) Tech Spec/PWHT Proc PWHT Chart A1 W/R SW/R
4.3.7 Visual Inspection (after PWHT) Construction Execution Plan Inspection Report A1 W/R SW/R
4.3.8 Hydrostatic Test (if required) Tech Spec/Hydro Test Proc Hydro Test Report A1 W/R W/R
4.4 WATER COOLED WALL (Upper water cooled wall outlet channels, upper water cooled wall tube bank,
middle and lower water cooled wall)
4.4.1 Location & Elevation Tech Spec & Drawing Inspection Report A1 W/R R
4.4.2 Alignment Tech Spec & Drawing Inspection Report A1 W/R SW/R
4.4.3 Welding WPS-PQR/WQTR Weld History Sheet A1 W/R SW/R
4.4.4 Visual Inspection Tech Spec/Visual Insp Proc - A2 W SW
4.4.5 NDT Tech Spec/NDT Proc NDE Report A1 W/R SW/R
4.4.6 PWHT (if required) Tech Spec/PWHT Proc PWHT Chart A1 W/R SW/R
4.4.7 Visual Inspection (after PWHT) Construction Execution Plan Inspection Report A1 W/R SW/R
4.4.8 Hydrostatic Test (if required) Tech Spec/Hydro Test Proc Hydro Test Report A1 W/R W/R
4.5 BODY PIPING (Steam Guide Piping, Main Steam Piping, Hot Reheat Steam Piping and Cold Reheat Steam
Piping)
4.5.1 Location & Elevation Tech Spec & Drawing - A2 W -
4.5.2 Edge Preparation Tech Spec & Drawing - A2 W -
4.5.3 Tack weld & alignment WPS-PQR/WQTR - A2 W SW
4.5.4 Welding WPS-PQR/WQTR Weld History Sheet A1 W/R SW/R
4.5.5 Visual Inspection Tech Spec/Visual Insp Proc - A2 W SW
4.5.6 NDT Tech Spec/NDT Proc NDE Report A1 W/R SW/R
4.5.7 PWHT (if required) Tech Spec/PWHT Proc PWHT Chart A1 W/R SW/R
4.5.8 Visual Inspection (after PWHT) Tech Spec/Visual Insp Proc Inspection Report A1 W/R SW/R
4.5.9 Hydrostatic Test ( if required ) Tech Spec/Hydro Test Proc Hydro Test Report A1 W/R W/R
4.5.10 Flushing (drain out) Tech Spec/Flushing Proc - A2 W SW
CONSORTIUM OF PT TRUBA ALAM MANUNGGAL ENGINEERING ITP no. : BBL/ITP-020
PT. TRUBA ALAM MANUNGGAL ENGINEERING
SFECO GROUP Revision : 0
INSPECTION & TEST PLAN ( ITP ) Date : March 20, 2009
PT PLN (Persero)
PLTU 3 BANGKA BELITUNG 2 x 30 MW Project no. : 2B0801
BOILER
REFERENCE VERIFYING INSPECTION ACTIVITIES
NO DESCRIPTION & ACTIVITIES CHECK LIST
DOCUMENT DOCUMENT SUBCON TAME PLN
4.6 TOP SEALING
4.6.1 Location & Elevation Tech Spec & Drawing Inspection Report A1 W/R R
4.6.2 Tack weld & alignment WPS-PQR/WQTR - A2 W SW
4.6.3 Welding WPS-PQR/WQTR - A2 W SW
4.6.4 Penetrant Test / PT (if required) Tech Spec/PT Proc Inspection Report A1 SW/R SW/R
4.6.5 Final Visual Inspection Drawing - A1 W/R W/R
4.10 AIR PREHEATER (Flue Duct Casing, Front & Rear Rotor Casing, Cold Section, Bottom Truss, Thrust
Bearing, Bearing Block, Short Shaft and Rotor Center part)
4.10.1 Re-check and Setting out of the flatness Tech Spec/Drawing Inspection report A1 W/R R
4.10.2 Internal Part Installation Drawing - A1 W SW
4.10.3 Final Visual Inspection Drawing Inspection Report A1 W/R W/R
4.10.4 Test Run in Cold State Tech Spec/Visual Insp Proc Inspection Report A2 W SW
CONSORTIUM OF PT TRUBA ALAM MANUNGGAL ENGINEERING ITP no. : BBL/ITP-020
PT. TRUBA ALAM MANUNGGAL ENGINEERING
SFECO GROUP Revision : 0
INSPECTION & TEST PLAN ( ITP ) Date : March 20, 2009
PT PLN (Persero)
PLTU 3 BANGKA BELITUNG 2 x 30 MW Project no. : 2B0801
BOILER
REFERENCE VERIFYING INSPECTION ACTIVITIES
NO DESCRIPTION & ACTIVITIES CHECK LIST
DOCUMENT DOCUMENT SUBCON TAME PLN
4.11 COAL CONVEYING SYSTEM (Bucket-Wheel Stacker Reclaimer, Revolving Frame, Lower Truss and
Reclaimer Truss Rod, Rear Truss and Rear Handrail, Arm and Counterweight)
4.11.1 Foundation Check (Location) Tech Spec/Drawing Inspection report A1 W/R R
4.11.2 Packer Setting Tech Spec/Drawing Inspection report A1 W/R SW/R
4.11.3 Location & Elevation Tech Spec/Drawing Inspection report A1 W/R SW/R
4.11.4 Alignment Tech Spec & Drawing Inspection Report A1 W/R SW/R
4.11.5 Grouting Tech Spec/Grouting Proc/Drawing - A1 W/R -
4.12 FUEL OIL SYSTEM (Oil Storage Tank, Oil Supply Pump, Oil Discharge Pump, Oil Cooler, Oil Filter, Oil
Piping and Fitting, Solenoid and Quick close Valve)
4.12.1 Foundation Check (Location) Tech Spec/Drawing Inspection report A1 W/R R
4.12.2 Location & Elevation Tech Spec/Drawing Inspection report A1 W/R SW/R
4.12.3 Alignment Tech Spec & Drawing Inspection Report A1 W/R SW/R
4.12.4 Piping Steam Purging Tech Spec/Hydro Test Proc - A1 W/R W/R
4.12.5 Pump Test Run Tech Spec/Visual Insp Proc - A2 W SW
4.12.6 Flushing System Tech Spec/Flushing Proc Inspection Report A2 W SW
BOILER
REFERENCE VERIFYING INSPECTION ACTIVITIES
NO DESCRIPTION & ACTIVITIES CHECK LIST
DOCUMENT DOCUMENT SUBCON TAME PLN
4.14 HYDROSTATIC TEST
4.14.1 Primary Steam System :
Feed Water Operating Table, Main Feed Water Piping from Feed Water Operating Table to
Economizer Inlet, Economizer System, Steam Drum, Water-cooled Wall System and Superheater and
Associated Interconnecting Piping, Drains, Blow Down, Heating, Chemical Dosing, Feed Water and
Desuperheater Water Piping and Valves
4.14.1.1 Walkdown Inspection Drawing Inspection Report A1 W/R W/R
4.14.1.2 System Hydrostatic Test Tech Spec/Hydro Test Proc Hydro Test Report A1 W/R W/R
4.14.1.3 Chemical Cleaning (if required) Drawing Inspection Report A1 W/R W/R
5.0 DOCUMENTATION
5.1 QA/QC Review of Generated Documents Tech Spec/Site Quality Procedures All of Inspection Reports R R/A R/A