Scaffodligng Calculation

The document provides details on the materials, weights, quantities, and lengths needed to construct a scaffolding system. It lists 17 items, their weights in kilograms, total quantities, total lengths, and total weights. It notes that one trailer can load 25 tons of materials and provides calculations for a scaffolding system that is 300 meters long and 10,800 cubic meters.

Uploaded by

faizan.ksa15
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
24 views

Scaffodligng Calculation

The document provides details on the materials, weights, quantities, and lengths needed to construct a scaffolding system. It lists 17 items, their weights in kilograms, total quantities, total lengths, and total weights. It notes that one trailer can load 25 tons of materials and provides calculations for a scaffolding system that is 300 meters long and 10,800 cubic meters.

Uploaded by

faizan.ksa15
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Weight

S.NO ITEMS Weight KG


k/n Note: # 1 supervisor =20 Scaffolder
Note: # Up to 12 meter A Person progress tube & coupler 12 cubic meter tower
1 Base Plat ,independent Run 15 , bairdcase 18 progress can possiable if meterials with in 10 Meter
0.005 0.509 Distance .
2 Screjack 0.509 up to 6 meter tower one person can be 15 cubic meter also.
0.0356
3 Tube 3.63
k/n System Scaffolding 25 -30 possiable with tower also , birdcase coming more.
4 plank 0.27 4.75
5 Double Coupler 1.01 One trailer can load 25 ton materials ,
6 Swivel Coupler 1.024
7 Grider Cupler 1.47
8 Putlog Coupler 0.626
9 Sleev Coupler 0.994
10 BRC 0.45

300*3*12=10800 Cubi Meter


Post Spacing longitudinal 1.8
Post Spacing transverse 1.2 107643.965
Size of Quantitiy of Total weight
S.no items Total Length weight Remarks
Materials Materials kg
1 Screw Jack 1 500 500 0.509 254.5 Every 1.8 meter post * 3 Line Post *12 Meter height
2 Post 6 1000 6000 3.63 21780 Every 1.8 meter post * 3 Line Post
3 Runners (Ledgers) 6 1350 8100 3.63 29403 one Side Runner 300 meter/6=50 pcs *3 line Base lift *9 lift including Guardrail .
4 Transoms (Bearers ) 3 1166 3498 3.63 12697.74 Every 1.8 meter post 300/1.8=166 * 7 lift
5 Board Bearers 3 200 600 3.63 2178 Below the Plank =Every 1.5 meter transom ,300/1.5
6 Bracing -Longitudinal 2.5 583 1457.5 3.63 5290.725 Every 1.8 meter post mens 166 Gaps Longitudinal site post can be Every 4 Bay *7 lift Height *both side
7 Bracing-Transverse 2.5 388 970 3.63 3521.1 Every 1.8 meter post mens 166 Gaps Transvers site post can be Every 3 Bay *7 lift Height *both side
8 plank-sills 1 500 500 4.75 2375 Number of Post
9 plank -Platfrom 4 750 3000 4.75 14250 300 meter length/ 4 meter pank * Transverse Site 10 Plank, transvers not more then 5 plank .
10 plank -Toeboard 4 150 600 4.75 2850 One ine 75 pcs .
11 Double Coupler 1 9000 9000 1.01 9090
12 Swivel Coupler 1 2000 2000 1.024 2048
13 Grider Cupler 1 0 0 1.47 0
14 Putlog Coupler-Board Barear 1 600 600 0.626 375.6
15 Putlog Coupler-Toe Board 1 332 332 0 166 post * both side
16 Sleev Coupler 1 1200 1200 0.994 1192.8 Minimum post & runner & Guardrails Joints only Even all 6 Meter Pipe
17 BRC 1 750 750 0.45 337.5 2 planks both side together mens every platfrom planks one pcs

Here Did not mention landing platform which in only 20 aditional paltfrom required .
Every 3.7 vertical & 30 meter distance required Access .