Du Pradhan Rangnekar Team03 Final Written Report-1
Du Pradhan Rangnekar Team03 Final Written Report-1
Team 3
Daniel Du, Apurva Pradhan, Sonal Rangnekar
1
Executive Summary:
This report describes the design of a methanol plant that produces 1000 metric tons per
day of commercial grade methanol. Commercial grade is defined here as 99.85% purity
with a maximum of 500 PPM water content. This plant was designed with three feedstocks:
sour natural gas, water, and carbon dioxide. The final process was split into four major
sections: acid gas removal (AGR), steam methane reformation (SMR), methanol
synthesis reactors, and product purification. The overall capital cost is $180M. The
production costs amount to $65M yearly before inflation, with annual revenue at $84M.
Claus plant. Over a 30 year period, the rate of return is 6.5%. A sensitivity analysis shows
that the parts of the process that affect the economic stability the most are the sales prices
of our final product and the price of natural gas. It is recommended that steps be taken to
2
Table of Contents:
Introduction……………………………………………………………………………………4
Design Basis………………………………………………………………………………….5
Methanol Synthesis………………………………………………………………….11
Purification……………………………………………………………………………11
Unit Sizing……………………………………………………………………………12
Capital Expenses……………………………………………………………………………13
Operating Expenses………………………………………………………………………...14
Financial Analysis……………………………………………………………………………17
References……………………………………………………………………………………20
Appendices…………………………………………………………………………………...21
3
Introduction:
Methanol is a key feedstock material for synthesizing a variety of chemicals, such as
formaldehyde, acetic acid, and dimethyl ether. Methanol can also be used as a high
performance fuel and as an octane booster in gasoline fuel. In 2014, the global demand
for methanol was 65 million metric tons, and that number has been projected to increase
to over 90 million metric tons by 2020.1 We aim to enter this lucrative market by setting
up a small methanol production plant in the United States Gulf Coast. The following report
describes a design for a plant that can produce 1000 mt/day of methanol with a purity of
This plant has been designed in ASPEN, and it contains four primary subprocess
units, three feedstock streams, and two product streams. The key feedstocks for our
methanol process are methane, carbon dioxide, and steam. The methane is provided via
a pipeline of crude natural gas. Acid gas removal (AGR) is first performed to remove H 2S
from the natural gas to prevent degradation of reaction catalysts. The H 2S gas is sent to
a Claus plant to produce sulfur as a saleable byproduct. The purified natural gas and
steam undergo steam methane reformation (SMR) to produce carbon monoxide and
hydrogen gas. Carbon dioxide, the third feedstock, is added to this stream before
performed. We weighed capital costs, such as the prices of key equipment, installment
costs, contingency, and production costs, including employee salaries, feedstock costs,
and utilities costs, against the revenue generated from selling methanol and sulfur. Rate
4
Design Basis:
The natural gas concentration is brought to the factory by pipeline at 25 ⁰C and 1000 psi.
It contains, by molar concentration, 87% methane, 5% nitrogen, 4.2% ethane, 2.6% H 2S,
1% CO2, 0.2% propane, and 0.05% water. It is assumed that the water for the SMR
furnace and the CO2 for the methanol synthesis reactors come in as pure compounds.
The product methanol must exit at a rate of 1000 metric tons per day with a purity of at
least 99.85%. The maximum water concentration in the product is 500 PPM.
The foremost assumption in this project was that the simulations done in ASPEN
were close to or near 100% accurate in our initial design of this production plant. Our next
assumption was the absence of pressure drop from pipelines and units that incorporated
no major pressure losses (e.g. columns, condensers, heaters, and coolers) in the overall
simulation. We assumed that the SMR reactor reached equilibrium so long as heat was
supplied to keep the reaction mixture at 850⁰C. We assumed that the feedstocks would
not vary in composition and that our overall process would be perfectly controlled and not
deviate from steady-state at all during operation. Our final set of assumptions was that
there would be no major unexpected deviations from market conditions during our
financial analysis and that the production quantity we would bring to the market would not
to prevent the poisoning of the catalysts being used in both SMR and methanol synthesis.
First attempts at simulating the acid gas removal process utilized Selexol ®, commonly
in ASPEN and, upon further review, realized that Rectisol ® was a better option due to its
5
main component being methanol. The reason why DEPG was first considered was that it
operated best at near room temperature, which allowed us to remove any need for
refrigeration costs.
Nitrogen was initially considered as the stripping solvent. However, our group was
advised and agreed that the easier option was to simply remove saturated methanol from
the system. This allowed for the cost of necessary nitrogen feedstock to be removed from
production costs.
Rectisol® operates best between -20⁰C and -40⁰C. We initially considered simply
having our AGR process operate at -40 ⁰C, but in order to mitigate refrigeration costs, this
number was brought up to -30⁰C. This required an additional absorption column in order
For the first couple iterations of our process, we entertained the idea of simply
passing methanol through the AGR process once before adding it back to the main
product for sale. However, it was revealed that even a small amount of H2S in our final
product would de-value the entire product as a whole and, as such, the single-pass
Initially, we had planned to use pure oxygen in our furnace, but it was found that
air was more than adequate to provide the heat duty to the SMR reactor with leftover heat
going to steam generation. This removed the cost of an air-separations plant within our
process.
Production of CO2 in house was also considered by purifying the outlet flue gases
from the SMR furnace. It was found that by locating our production plant near an ammonia
6
plant, it would be possible to buy CO2 side products from that ammonia plant at a heavily
reduced price.
The methanol synthesis reactor system also underwent a large amount of review.
reactors were used. However, this proved to be highly expensive and infeasible in terms
of sheer volume. Thus, smaller diameter reactors were used and condensers were placed
between reactors in order to push the reaction away from equilibrium at each inlet. Since
the single-pass conversion was reduced, the number of reactors was raised from two to
three.
In order to waste as little synthesis gas as possible, the remaining gas that comes
out of the final reactor is recycled after condensing the methanol out. However, it was
found that if the recycle rate became too large, the gases would go through the reactors
far too fast for the reaction to occur at a reasonable rate. Thus, various recycle rates were
analyzed and the final split ratio of 76% recycled to 24% removed was chosen.
Our heat exchange system had the strict rule of no cross-facility heat exchange
imposed upon it. As such, if a stream from AGR was needed to heat or cool a stream
from the purification step, both streams simply used utilities instead of adding a heat
exchanger and extra piping to go from one end of the facility to the other.
We chose to use floating roof tanks in order to stockpile our final product for a
capacity of a week. It was mentioned that non-floating roof tanks may be preferable, but
we chose to stay with the floating roof tanks due to the strong recommendation provided
7
Our vent gases contained excess H2, CO, and water that could have been sold or
used in previous points of the process. However, we chose to use the excess H 2 as fuel
for our furnace, steam generation, and providing fired heat to some of our utility
requirements. Due to the minimal amount of CO that exited the process, it was found that
separating CO from the gases and selling it would not be profitable. Finally, we simply did
not recycle the wastewater due to the possibility of impurities within the streams.
absorption columns and a stripping column, which allows us to use methanol (Rectisol ®)
as a recoverable solvent to remove H2S from sour natural gas. The SMR reactor takes in
a steam stream and sweet natural gas to produce H2, which is crucial for the methanol
synthesis step. The methanol synthesis step contains three reactors and inter-stage flash
drums. These flash drums condense out methanol and feed the remaining synthesis gas
to the next reactor in the chain. The overall methanol synthesis step has a recycle stream
8
after the third flash drum to prevent waste of remaining synthesis gas. The flowrates and
compositions are listed in Tables 1 and 2, with green being overall process inlet streams
and orange being overall process outlet streams. The compositions of SMR Steam and
with the specific sections stated previously clearly labelled. Compressors, pumps,
turbines, heaters, and coolers are all listed in Appendices C, D, E, and F, and are again
referenced on the PFD. The temperature and pressure profiles of all major units are
shown in Appendix H. Detailed sizing and economics of all the units are given in the
must be removed from the rest of the natural gas. Methanol is used as the solvent for
absorption of H2S in the AGR process. The absorption occurs at -30⁰C and 69 bar. Sour
9
natural gas enters the first column from the bottom and exits at the top. This slightly
sweeter natural gas then enters a second column from the bottom to drop the H 2S
concentration to the desired 50 PPB. In each column, 3 metric tons per hour of chilled
methanol is used as the solvent. Both columns have 20 stages. The stripping distillation
column also has 20 stages and operates at 20 bar, with a feed temperature of 250 ⁰C and
reflux ratio of 3. The feed enters at stage 10. The tops exit to the Claus Process at -10 ⁰C
and the bottoms exit at 170⁰C. The bottoms are recycled to the absorption columns as
purified methanol after passing through coolers and pumps. There is a make-up stream
reactors. Sweet natural gas exits from the top of the second absorption column in AGR
and is combined with steam in a 1:5 molar ratio in order to prevent coking within the SMR
packed bed. Due to the heavily endothermic nature of the SMR reaction, the SMR reactor
class revealed that GHSV and kinetic curves for SMR reactions are generally
is simulated using an adiabatic REquil block instead of RGibbs due to the presence of the
Ni/Al2O3 catalyst. A void fraction of 0.3 was assumed within the packed bed. A major
design point in the sizing of this reactor was keeping the pressure drop of the reacting
gas lower than 1 bar. The reactor is, on average, operating at a temperature of 850 ⁰C and
pressure of 20 bar. The box furnace is simulated with an RGibbs block and has an
adiabatic flame temperature of 2000⁰C and leaves the furnace at around 950⁰C. The
remaining duty from 950⁰C to the Low Heating Value (LHV) of 175⁰C is used to generate
10
steam. The SMR flash drum operates at 50⁰C and 20 bar. Condensed SMR waste water
exits from the bottom and synthesis gas, primarily H 2, exits from the top.
Methanol Synthesis
The synthesis reactors were designed to operate adiabatically with an average operating
temperature of 250⁰C and pressure of 51 bar. All reactors have inlet temperatures of
230⁰C. The first reactor is a series of five hundred 10m long Nominal 10” diameter tubes.
The second and third reactors are each two hundred and fifty 10m long Nominal 20”
diameter tubes. All reactors have Cu/ZnO catalyst with a void fraction of 0.3. The kinetics
for the methanol synthesis and water-gas shift reactions were taken from literature. 3,4 The
interstage flash drums operate at 30⁰C and 51 bar in order to condense methanol out the
bottoms and send synthesis gas to the next reactor. The synthesis gas coming out of the
third flash drum has 76% of its molar flowrate sent back to the beginning of the reactor
chain while the other 24% exits as synthesis gas to be used as fired heat in other parts
of the plant. The overall conversion of synthesis gas is 58.7%. The raw unpurified
methanol is sent to purification. Due to the temperature variation between reactors, heat
exchangers are employed to mitigate the heat duties between flash drums and reactors.
There are three heat exchangers total. Their configuration is given in detail in Appendix
E.
Purification System
The purification system consists of two distillation columns, one to remove excess
synthesis gas and one to remove the water that is generated during the synthesis reaction.
The first column consists of 6 trays and has a reflux ratio of 3. The feed is to stage 3 at a
temperature of 30⁰C. The second column is 21 trays and has a reflux ratio of 4. The feed
11
bar. The final product has a composition of 99.85% methanol, 450 PPM water and various
compounds in trace quantities. 0.25 MT/day of this product stream is taken to make up
the amount of methanol lost to the AGR process. The amount of methanol product leaving
source of fuel replaced the natural gas required to generate steam for the SMR reaction,
the natural gas required to fuel the SMR furnace, and some of the fired heat requirements
in the rest of the process. The LHV was used to calculate useable heat duty in all heat
removal system, and the inlets and outlets to every single column. Reactor feed flowrates
are also included in this list, in addition to the reactor flow compositions. Of particular
importance is the H2S composition coming out of the second AGR absorber. The last
control point is the purity of the product. Purity and composition must be monitored closely
in order to prevent catalyst poisoning in the reactors. Emergency cutoff switches should
be placed on the furnaces and the methanol synthesis reactors in order to prevent a
runaway reaction. All pressure vessels should have safety valves in accordance to ASME
regulations.
Unit Sizing
All of the units in our process were sized based on their operating parameters. Flash
drums, reactors, and columns were all modeled as pressure vessels. The diameter and
height of the flash drums were determined based on the settling velocity of the fluid they
contain as shown in chapter 16.3 of Towler. It is assumed that no demisters are present.
12
The diameter and length of the reactor vessels were determined based on the desired
flow rate and conversion of hydrogen and carbon dioxide into methanol. The temperature
and composition profiles of the reactors can be found in Appendix H. The diameter of
columns were found using ASPEN’s sizing feature while the number of trays were based
on the desired quality of the distillate and bottoms based on an optimized reflux ratio and
stream flow rates. The thickness of pressure vessel walls were found based on the
maximum allowable stress of the material being used based on the temperature and
pressure of the process as specified in chapter 14 of Towler along with a contingency for
an assumed 85% joint efficiency. In addition to carbon steel, 304 stainless steel and 316
stainless steel were also analyzed when determining minimum pressure vessel
thicknesses. Due to the absence of useable tabulated heat transfer coefficients at our
operating conditions, the surface area of heat exchangers were obtained using ASPEN’s
sizing feature.
Capital Expenses:
All unit capital costs were estimated based on Table 7.2 from Towler. 5 The cost of all
pressure vessels, including reactor shells and column shells, were determined based on
the volume of the shell itself along with the material used to construct the shell. This
volume is based on the operating conditions for the pressure vessel along with the
material being used to construct it. The cost of shells made from carbon steel, 304
stainless steel, and 316 stainless steel were analyzed, and it was found that carbon steel
was cheaper and met the requirements of all our units except for the SMR reactor, for
which 316 stainless steel is required due to high operating temperatures. Reactors were
priced by calculating the cost of the shell as a pressure vessel and adding the price of the
required catalyst. Columns were costed by approximating them with tray sizing parameter
13
references and adding on the cost of a shell simulated as a pressure vessel as described
in Table 7.2 of Towler. Heat exchangers were costed based on their required heat transfer
area while pumps, turbines, and compressors were costed based on their volumetric flow
rate or energy use as described in Towler. Each pump, turbine, and compressor include
an identical backup in order to ensure continuous operation of our plant even if one breaks
down. The capital cost for the Claus Plant, found to be $10 million, was determined using
Garrett6 after accounting for inflation. The specific costs of all of the units along with their
costing parameters and installed costs can be found in Appendix I. The total ISBL costs
piping, and utilities construction, and were assumed to be 40% of our ISBL costs, or $44
million. Working capital was assumed to be 15% of our ISBL costs at $16 million.
Contingency costs were assumed to be 10% of our total ISBL costs at $11 million. The
total capital cost of our plant is $180 million. According to Garrett, the typical capital
expenses for a methanol production facility is $120 million, and our estimate is within the
range of this average value.6 Table 3 shows a summary of the capital costs.
Operating Expenses:
Our production costing, or annual expenses, are composed of a variety of employee,
maintenance, tax, feedstock, and utility related costs. Our plant is assumed to require five
14
operators at all times. Assuming a total of four 6-hour shifts every day, we would require
a total of 20 operators who each have a 42 hour work week. A reasonable salary for an
operator working in the Gulf Coast is fifty thousand dollars per year. This results in a total
operating labor cost of $1 million per year. Operator supervision is assumed to be 25%
of the cost of the operating labor and has an annual cost of $250k. Direct salary overhead,
which includes the costs of employee insurance and health care benefits is an additional
60% of the sum of operating labor and supervision costs at $750k. Maintenance costs for
our facility were assumed to be five percent of our installed ISBL costs at $5.5 million.
Property taxes and insurance for our facility were assumed to have an annual cost worth
two percent of our installed ISBL costs at $1 million. Garrett was used to determine the
operating costs of our Claus Plant based on a throughput of 44 tons of sulfur per day.
After accounting for inflation since 1987, when Garrett was published, the annual
Feedstock costs make up a significant majority of our overall operating costs and
are calculated based on the amount of natural gas needed for our process and our fired
heat, the amount of water needed for our steam methane reformer, and the amount of
carbon dioxide needed for our methanol synthesis process. A total of 380 thousand metric
tons of natural gas is needed annually for our process. At a cost of $90 per ton, this results
in a net cost of $34.2 million per year for the natural gas. In order to compensate for the
excess hydrogen being produced by our steam methane reformer, we will be purchasing
carbon dioxide from ammonia production plants near our facility. Based on sources from
the Dakota Gasification Company, the price of CO2 on the Gulf Coast was found to be $5
per ton.7 As we are consuming 722 thousand tons of carbon dioxide per year, the net
15
expenses on carbon dioxide feed will be $3.6 million. Finally, our process uses 1.3 million
tons of water annually. Based on Towler, the cost of process water on the Gulf Coast is
$1.1 per ton, resulting in a net annual expense of $1.4 million on water. 5 In our costing,
we are assuming that make-up water for cooling systems have a negligible cost, and as
a result, are not included in our analysis. The sum of all of our feedstock costs result in
The costs of utilities were based on the amount of electricity needed to operate the
pumps and compressors in our system after accounting for the energy provided by the
turbines in our process, and accounting for the electricity costs of refrigeration. After
cost $3.49 million per year and the energy use for refrigeration will cost $4.46 million per
year.5 Our net annual electricity cost are $8 million per year.
In order to meet EPA standards, our final operating expenses involve superfund
payments and waste water treatment expenses. Superfund payments are paid to the
Environmental Protection Agency to help clean up sites that are contaminated with
16
hazardous substances and pollutants. Typically, superfund payments are one percent of
the sum of ISBL and OSBL costs. For our process, $1.5 million will be spent annually on
superfund payments. It is important to ensure the waste water produced in our process
is properly treated. Our plant produces 841 million gallons of waste water per year. Based
on Towler, wastewater treatment typically costs $6 per 1000 gallons. 5 This results in an
Altogether, our production costs are a total of $64.6 million per year. Table 4 shows a
breakdown of our production costs. Appendix J shows a more thorough breakdown of all
Financial Analysis:
It is important to complete a financial
analysis was completed on our process to see how market disturbances will affect our
cash flow. In our methanol facility’s financial analysis, we are assuming a thirty year tax
lifetime with a twenty year straight line depreciation. Furthermore, we are assuming that
there is a two percent rate of inflation and a tax rate of 40%. Assuming that it will take five
years to construct our facility, and that the plant will be operational for 30 years, our rate
of return will be 6.5% and our average return on investment over the plant’s thirty year
lifespan will be 10.2%. Figure 1 shows the cumulative discounted cash flow over the thirty-
17
year lifespan of the methanol plant. A summary of the calculations done to determine the
discounted cash flow and the rate of return can be found in Appendix L.
Figure 2: Sensitivity Analysis on Capital Costs see how it affects our rate of return.
First, the capital cost of the three most expensive units in our facility were varied in order
to see how much they affected our rate of return. As can be seen in Figure 2, variations
in the price of reactors has the greatest impact on our rate of return while furnaces and
the cost of natural gas, our plant’s rate of return will vary from 9.5 to 2.6 respectively. This
can be seen in Figure 3. This suggests that although our plant is currently viable due to
the unusually low cost of natural gas, if natural gas prices were to rise to levels seen in
the early 2000’s, our facility may not remain lucrative. Figure 4 shows how our facility
18
responds to changing production
In addition to the production costs, the market price of our product was also found
to make a major impact on our plant’s rate of return. As seen in Figure 5, a nineteen
percent drop in the market price of methanol will result in our rate of return dropping to
zero. Similarly, a thirty percent increase in the price of methanol will result in a rate of
return of thirteen percent. The price of sulfur makes a minimal impact on our facility’s rate
day at a purity of 99.85%. We recommend that our methanol plant be built along the Gulf
Coast, preferably near an ammonia plant which may supply us with carbon dioxide. Our
capital costs were found to be $180 million, and this estimate is corroborated by typical
costs for methanol plants found in texts such as Garrett. We expect our annual revenue
19
to be $84 million and our expenses to be $64 million, resulting in a net margin of $20
million. With a tax rate of 40%, a 20 year straight line depreciation, and a 2% annual
inflation rate, we expect our cumulative cash flow to reach $369 million at the end of our
plant’s thirty year tax life. We would be able to pay off our capital investment after 11
years.
However, a financial analysis of our process shows that we are unable to meet the
desired hurdle rate of 15% after thirty years of operation. Our finances show a great
dependence on the market price of natural gas and methanol. Unexpected spikes in the
price of natural gas or sudden crashes of the price of methanol will be detrimental to our
finances and may make our operation unsustainable. Nevertheless, we do have a margin
of $20 million per year, resulting in a rate of return of 6.5% and a return on investment of
10.2%. If these estimates for our ROI and rate of return are acceptable to our investors,
we recommend that contracts be signed with natural gas suppliers and methanol
purchasers to ensure that we will not be impacted by sudden changes in methanol and
natural gas market prices before construction on our plant begins. Although our rate of
return is not as high as was desired, we believe that constructing a methanol facility is a
References:
(1) Nash, M. The changing face of methanol demand
http://www.chemweek.com/lab/The-changing-face-of-methanol-
demand_72206.html (accessed May 3, 2016).
(2) Alliance Consulting International. 2008, No. October, 1–37.
(3) Kubota, T.; Hayakawa, I.; Mabuse, H.; Mori, K.; Ushikoshi, K.; Watanabe, T.;
Saito, M. 2001, No. September 1999, 121–126.
(4) GKT Project: Methanol Synthesis Reactor/Kinetic Information. 2005.
(5) Towler, G.; Sinnott, R. K. Chemical Engineering Design - Principles, Practice and
Economics of Plant and Process Design (2nd Edition); Elseiver, 2013.
(6) Garrett, D. E. Chemical Engineering Economics; Van Nostrand Reinhold, 1989.
(7) Loop, G. In IEA GHG Financial Conference; New York, 2008.
20
Appendices:
A. Overall Process Flow Diagram
B. Subprocess Steam Data
C. Compressors, Pumps, and Turbines
D. Heaters and Coolers
E. Heat Exchangers
F. Pressure Vessels and Separation Columns
G. Reactors
H. Temperature and Concentration Profiles
I. Capital Cost Expenses
J. Production Expenses
K. Revenue
L. Cash Flow Charts
M. Gantt Chart
21