7 Checked and ensured reinforcement is free from oil, mud, crease and other [ ] [ ]
forms of contamination.
CHECKS DURING EXECUTION
9 Ensured the column bars are placed as per GFC drawings with provision for [ ] [ ]
alternate lap zone.
10 Checked and ensured the spacing between the stirupps and the total [ ] [ ]
number of strirrups are as per design.
11 Ensured the anchors are provided as per drawings at the edges of the [ ] [ ]
footing
12 Ensured the chairs are provided at appropriate locations and as per design. [ ] [ ]
13 Ensured the cover blocks are of correct sizes and at correct spacing. [ ] [ ]
16 Ensured the reinforcements are clean and free from any unwanted [ ] [ ]
materials.
17 Ensured the reinforcements are tied properly with binding wire of [ ] [ ]
necessary gauge.
18 Ensured no bars are twisted or deformed in any manner. [ ] [ ]