The document discusses extra items considered in the construction of railway approaches in lieu of level crossing number 37. It lists 9 extra items including bituminous concrete laying, steel liners, precast post-tensioned girders, reinforced cement concrete works, and pile load and integrity testing. The total extra items cost is around Rs. 33.25 crore.

Uploaded by

PRADEEPA S
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
20 views2 pages

Extra Item S Reasons

The document discusses extra items considered in the construction of railway approaches in lieu of level crossing number 37. It lists 9 extra items including bituminous concrete laying, steel liners, precast post-tensioned girders, reinforced cement concrete works, and pile load and integrity testing. The total extra items cost is around Rs. 33.25 crore.

Uploaded by

PRADEEPA S
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

EIRL ITEMS

CONSTRUCTION OF RAILWAY APPROCHES IN LIEU OF LC NO. 37 AT KM:64/200-300 AT KYATSANDRA STATION YARD BETWEEN BANGALORE-TUMKUR RAILWAY STATIONS

Sl. No Item No Description Unit Extra items cosidered in KPWD SR items Remarks

Total Qty. Rate Amount


KSRRB M500-19. Providing and laying bituminous concrete using crushed aggregates of
specified grading, premixed with bituminous binder and filler, transporting the hot mix to work
site, laying w ith a paver finisher to the required grade, level and alignment, rolling with smooth This Item has not been included at the time of
EIRL -1 21.22.6 wheeled, vibratory and tandem rollers to achieve the desired compaction in all respects complete cum 358.31 9272.6 3322480.142 preparation of estimate, but as per site
as per specifications. Clause 507 of MORTH V revision using 40/60 TPH capacity H.M.P. with condition this work needs to be executed.
Mechanical Paver Gr-11 (30 mm to 40 mm) with 5.4% VG-30 Bitumen (P.No. 162/I.No.21.22.6
of CSR 2018-19)
Providing Steel Liner 10 mm thick for
Curbs and 6 mm thick for Steining of
EIRL -2 12.22 Tonne 44.16 122887.78 5426724.365 As per Aproved Drawing Steel Liners inserted.
Wells including Fabricating and Setting
out as per Detailed Drawing.
Pre Cast -Post tentioned Girders, Providing, Pre Casting, Transportation and placing in position
As per aproved drawing Change of scope of
EIRL -3 14.1 precast post-tensioned concere girders as per drawing and technical specifications cum 434.00 45439.46264 19720726.78
PSC Girder Cast in situ to precast.
KSRRB M21 00-20.2. Providing and laying Plain I Reinforced Cement Cum 5,222.00 Concrete
in Open Foundation with OPC design mix M35 @ 390kgwith 20mm and down size graded
Construction of Underpass at guddamma devi
granite metal coarse [email protected] and fine aggregates @ 0.45cum, with superplasticizer
EIRL -4 27.37 @3lts confirming to IS91 03-1999 Reaffirmed-2008. including cost of all materials, labour,
cum 70.00 5715.479 400083.53 temple.(New Structure is not covered in
HOM curing, form works, scaffolding and centering complete as per specifications. Schedule B)

KSRRB M2300-7.1. Providing and Placing Reinforced I Prestressed cement concrete in super-
structure as per drawing and Technical Specification complete as per specifications. RCC I PSC
with OPC design mix M35 @ 390kgs, with 20mm and down size graded granite metal coarse Construction of Underpass at guddamma devi
EIRL -5 29.13 aggregates @0.68cum and fine aggregates @ 0.45cum, with superplastisiser @31ts confirming cum 100.00 7281.7085 728170.85 temple.(New Structure is not covered in
to IS91 03-1999 Reaffirmed-2008,including cost of materials, labour, HOM, curing, form Schedule B)
works, scaffolding and centering complete as per specifications. MORTH Specification No.
1500,1600 & 1700
Construction of dry lean cement concrete Sub- base over a prepared sub-grade with
coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate
gradation after blending to be as per table 600-1, cement content not to be Providing cc pavement to public path way (CE
EIRL -6 6.01 less than 150 kg/ m3, optimum moisture content to be determined during trial cum 105.00 4615.29 484605.45
Inspection note is enclosed)
length construction, concrete strength not to be less than 10 Mpa at 7 days,
mixed in a batching plant, transported to site, laid with a paver with electronic
sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing.

Page 1 of 2
Sl. No Item No Description Unit Extra items cosidered in KPWD SR items Remarks

Total Qty. Rate Amount


Construction of M30 grade un-reinforced, dowel jointed, plain cement concrete pavement over a
prepared sub base with OPC, coarse and fine aggregate conforming to IS 383, maximum size of
coarse aggregate not exceeding 25 mm,mixed in a batching and mixing plant as per approved
mix design transported to site, laid with a fixed form or slip form paver, spread, compacted and Providing cc pavement to public path way (CE
EIRL -7 6.02 finished in a continuous operation including provision of contraction, expansion, construction cum 210.00 10792.37 2266397.7
Inspection note is enclosed)
and longitudinal joints,joint filler, separation membrane,sealant primer, joint sealant, debonding
strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades
as per drawing
Initial Vertical Pile
EIRL -8 Load Test For 1000mm dia. Pile, No 1.00 861918.75 861918.75 As per Aproved Drawing Conducted Test

Integrity testing of
EIRL -9 Nos 36.00 1149.23 41372.28 As per Aproved Drawing Conducted Test
Pile
Total Amount 33252479.85
33252479.85
Amount of Original sanctioned Estimate 138812223.98
Amount put to tender 126480527.10
Total E.I.R.L. Amount 33252479.85
% of Excess 33252479.85 X
23.96
138812224.0 100 =

Assistant Executive Engineer Executive Engineer


Assistant Engineer PWD Urban Sub Division, Tumkur
Tumkur