Interview Questions & Answers PDF
Interview Questions & Answers PDF
The APC is a hugely difficult task with an incredibly high fail rate.
The Interview panel can ask you any question and demand that you know the
answer in order for you to pass.
▪ Listen to the specific question carefully and only respond with your answer
that specific question.
▪ Be sure to avoid going off topic as you may fall into a trap here.
▪ You must answer all Rules of Conduct and Ethical Questions correctly,
failure to do so will result in deferral.
▪ It is OK to not know the answer to a few questions.
▪ In your responses be sure to convey these confidently and concisely, avoid
using any hypothetical language.
▪ On Level 2 type questions be sure to talk in a positive, definitive way in the
past tense about what you have actually done.
MOCK INTERVIEW QUESTION & ANSWER PRACTICE
A)
• Take responsibility.
Q) When presenting your case study you mentioned that you’ve prepared a
pre-tender estimate, could you just tell me what assumptions and exclusions
you made as part of that estimate?
A)
▪ Asbestos removal
▪ VAT is excluded
Q) Why?
A)
A)
A)
▪ Cashflow Forecast
A)
No this would not be a valid claim due to the Provisional Sum
being defined, all Main Contractor preliminary costs needed to
expend the Provisional Sum are deemed included in the Contract
Sum.
MANDATORY COMPETENCY QUESTIONS
ACCOUNTING PRINCIPLES & PROCEDURES
Q) What are the key financial statements that all companies must
provide? / What are company accounts?
A) The key financial statements to be provided by companies are
Profit and loss account, balance sheet and cash flow statement.
The contractors claim should be based on data from a recognised independent source
such as the Met Office and the rainfall and temperatures referenced would be compared
against previous years to determine if these would adversely impact the progress of the
Main Contractor for a prolonged period that is equivalent to the extent of extension of
time being sought.
QUANTIFICATION & COSTING OF CONSTRUCTION WORKS
Q) What are the key differences between SMM and NRM?
A)
▪ elements being broken down further within NRM2 with 41 work sections against the
22 trade sections in SMM7,
▪ many small items deemed to be included within the rates (these had to be priced
separately within SMM7 which was a complete uneconomical use of a surveyor’s
time),
▪ clearer definitions of prime cost and provisional works and allowances for risks,
Q) What is a Prime Cost Sum?
A)
A prime cost sum is the cost of an item that has either not been selected or the price
was unknown at the time the contact was entered into. If the price of the item chosen is
greater than the PC sum the client will pay the builder any difference plus a profit
margin as stated in the contract
Q) What is GEA?
▪ Gross External Area
▪ This is the area of the building measured externally at each floor level
▪ What is GIA?
▪ Gross Internal Area
▪ This is the area of the building measured to the internal face of the perimeter wall at
each floor
Q) Where are all of these defined?
▪ The Code of Measuring Practice, 6th Edition, published by the RICS
Q) How do you measure cut and fill?
▪ CAD Measure
▪ If I did not have this software available to me I would obtain drawings with existing
levels & proposed levels. I would divide the area of excavation into a grid &
interpolate the levels on the grid to establish an average existing & proposed level to
determine which area was in cut and which area was in fill
CLIENT CARE
Q) When should you decline an instruction of new work from a client?
A) If there is a Conflict of Interest
Not in clients interest - you can't resource the job
Illegal
Q) How many Rules of Conduct for members are there and can you name them?
▪ 9
▪ Name them
▪ Interpretation
▪ Communication
▪ Ethical Behaviour
▪ Competence
▪ Service
▪ Continuous Professional Development (CPD)
▪ Solvency
▪ Information to RICS
▪ Co-operation
Q) What procedures must you follow if you are starting up a new practice?
▪ Contact the RICS for guidance – provide a company start up pack
▪ Inform the RICS and register for regulation
▪ Appoint a contact officer for all RICS communication
▪ Prepare a complaints handling procedure
▪ Obtain PI cover
▪ Abide by the Rules of Conduct for Firms
▪ Use the designation ‘Regulated by RICS’ on all practice material
Q) What insurances would you need if you were starting up your own firm?
▪ PI
▪ Employer’s Liability
▪ Public Liability
▪ Building insurance of own office.
Q) What must a complaints handling procedure include?
A)
▪ The RICS provides a model form
▪ Must include a redress mechanism
▪ Details should be issued to the client with the Terms of Business
▪ It must be clear, quick, transparent and impartial and free of charge
▪ Names and contact details of the nominated investigating person must be stated
▪ The complaint must be investigated within 28 days
▪ All complaints, their progress and outcomes must be recorded
▪ Note the need to advise PI insurers of a complaint
▪ Must have two stages as a minimum:
▪ Consideration of the complaint by a senior member of the firm or the complaints handling officer
▪ If not resolved, referred to an independent third party with the authority to award redress
END OF Q & A