Topic 4
Topic 4
Topic 4
Cost Management
Paulo Faroleiro
Project Management
Part IV
Cost Management Cost Management
1. Price Estimation
2. Cost Control
Direct Estimate
• Estimate/experienced person
• Requires judgement
Estimate by analogy
• Compare with similar activities
• Requires judgement
Factored method
• Based on historical data
• Requires equipment lists, sizes
• Starts with equipment quotes
Gross proration method
• Based on historical data
• Near duplicate information
Detailed estimate
- Uses the WBS
- Takes the WBS down several levels
Quotation method
- Compare three quotations
- Select the best quotation
Handbook manuals
Learning curves
Construction
Cost Estimates
COST FOUNDATIONS
Cost estimating
Cost accounting
Project cash flow
Company cash flow
Direct labor costing
Overhead rate costing
Others, such as incentives, penalties, and profit-sharing
COST AND CONTROL SYSTEM
Possible cost
reductions
Cost of change
PROJECT
COSTS
CONCLUSION
A cost management system should be implemented right at
the beginning of the life cycle of the project.
CAPACITY PLANNING
The Work
Authorization Form
WORK AUTHORIZATION FORM
WBS: 31.03.02 Work order no: D1385
Description
- Test Material 2400 150 R4500 1 Aug 15 Sept
- Processing 2610 160 R7500
- Final inspection 2621 140 R3500
- Packaging 2623 46 R 750
- Delivery 2624 R 350
Work packages
Work Package
M Org WP______ORG_______
G Org Description of task_____
R Org ____________________
Sched: Start____Stop__
Budget:______________
COST ACCOUNT CHANGE NOTICE (CACN)
CACN No. _____________ Revision to Cost Account No. ____________ Date ___________
DESCRIPTION OF CHANGE:
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
BUDGET SOURCE:
Funded Contract Change
Management Reserve
Undistributed Budget
Other _________________
INITIATED BY: ____________________________ APPROVALS: Program Mgr. ________
Prog. Control ________
TYPES OF BUDGETS COST DATA
Distributed budget Labor
Management budget Material
Undistributed budget Other direct charges
Contract changes Overhead
VARIANCE ANALYSES
COST DATA COLLATION AND
REPORTING FLOW CHART
Variance Report
VARIANCES
The cost variance compares deviations only from the budget and
does not provide a measure of comparison between work
scheduled and work accomplished.
The scheduling variance provides a comparison between
planned and actual performance but does not include costs.
VARIABLES FOR VARIANCE
ANALYSIS
BUDGETED COST FOR WORKED SCHEDULED (BCWS) IS THE BUDGETED AMOUNT
OF COST FOR WORD SCHEDULED TO BE ACCOMPLISHED PLUS THE AMOUNT OF
LEVEL OF EFFORT OR APPORTIONED EFFORT SCHEDULED TO BE ACCOMPLISHED
IN A GIVEN TIME PERIOD.
CV = BCWP - ACWP
SCHEDULE VARIANCE
CALCULATION
SV = BCWP - BCWS
MANAGEMENT RESERVE
CONTRACTED COST
MANAGEMENT
ACTUAL COST RESERVE
RELEASED BUDGET
$
TIME
PROJECT VARIANCE ANALYSIS
PROJECTED COST
SV
SCHEDULE VARIANCE % =
(SVP) BCWS X 100
CV
COST VARIANCE % =
(CVP) BCWP X 100
Trend
Analyses
INFORMATION REQUIREMENTS
• Budgeted cost for work scheduled (BCWS)
• Budgeted cost for work performed (BCWP)
• Actual cost for work performed (ACWP)
• Estimated cost at completion
• Budgeted cost at completion
• Cost and schedule variances/explanations
• Traceability
VARIANCE ANALYSIS QUESTIONS
Cost account Date Cost center Date WBS element Date Date
Mgr. Mgr. Mgr.
The 50/50 Rule
THE 50/50 RULE
10
12 Work packages
8
BCWS = 38 12
BCWP = 49
SCHED. VARIANCE = +11 10
8
50-50 rule used for work in process
J F M A M J J A S O N D
USING THE 50-50 RULE
4,000
TIME LINE
10,000
LEGEND
12,000
COMPLETED
4,000
NOT COMPLETED
6,000
BCWS = 34,000
BCWP = 33,000 6,000
BAC = 52,000
10,000
TIME
EARNED VALUE STATUS
REPORTING
TIME LINE
CUMMULATIVE COST, $
BCWS
SV
ACWP
CV
BCWP
TIME
Estimated Cost At
Completion
ESTIMATE AT COMPLETION (EAC)
Budget
BCWS SCHED
VAR
BCWP
COST
VAR
ACWP
FINANCIAL
CLOSE-OUT
COST PROBLEMS
Proposal Phase
• Failure to understand customer requirements
• Unrealistic appraisal of in-house capabilities
• Underestimating time requirements
Planning phase
• Omissions
• Inaccuracy of the work breakdown structure
• Misinterpretation of information
• Use of wrong estimating techniques
• Failure to identify and concentrate on major cost elements
• Failure to assess and provide for risks!!
COST PROBLEMS PER PHASE
Negotiation phase
• Forcing a speedy compromise
• Procurement ceiling costs
• Negotiation team that must “win this one”
Contractual phase
• Contractual discrepancies
• SOW different from RFP requirements
• Proposal team different from project team!!
COST PROBLEMS PER PHASE
Design phase
• Accepting customer requests without management approval
• Problems in customer communications channels and data
items
• Problems in design review meetings
Production phase
• Excessive material costs
• Specifications that are not acceptable
• Manufacturing and engineering disagreement
SUMMARY
1. Topic 5 and 6
Quality and Risk Management