0% found this document useful (0 votes)
590 views1 page

Carpentry Quote

The document provides a detailed estimate for carpentry work at a building. It includes 13 items with descriptions, measurements, quantities, rates, and totals. The total estimated cost is over Rs. 606,000 including taxes.

Uploaded by

pranaysas33
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
590 views1 page

Carpentry Quote

The document provides a detailed estimate for carpentry work at a building. It includes 13 items with descriptions, measurements, quantities, rates, and totals. The total estimated cost is over Rs. 606,000 including taxes.

Uploaded by

pranaysas33
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

PRATIKSH INTERIOR

SEVEN DIAMOND TOWER CARPENTRY WORK


Hyderabad Carpentry Work
S.No. Description Units Nos Width H/L QTY. Rate Amount

Pantry base unit - Supply & Installation of


1 Laminate Work Edge band inside white
laminate, shelves, hardware, handles and SS
legs sft 21000 21000

2 Pantry Wall unit - Supply & Installation of


Handles, Shelves , hardware rft 20000 20000

3 Reception Table - Supply & Installation of


12mm Corian and Laminate Without joints sft 135000 135000
4 Supply & retification of Lobby entry Veener
(approx. 4 sheets needed) sft 22000 22000

Mirror Pannel - Supply & installation of Mirror


5 as per selection on Right side Should be
rectified (supply of T & L beading is in SAS
scope) sft 2 20 1 40 350 14000
6 Polish Work (Melamine Polish - Matt Finish) sft 50000 50000
7 Back ply support on Wall For Light Sft 10 1 1 10 500 5000
Wall Cove - Installation of Metal L Beading
20mm (Supply of Beading on SAS scope)
8
Rft 1 180 90 16200
Mirror Band (Top & Bottom)- Installation of
Metal T Beading 12mm (Supply of Beading on
9
SAS scope)
Rft 1 90 90 8100

Pillar Inner Edge - Installation of Metal T


10
Beading 36mm (Supply of Beading on SAS
scope) Rft 1 240 90 21600

11
Supply & Installation of Acrylic- 4424 shiny
beige from Euro Pratik brand 1.5mm sft 8 1.6 33 422.4 400 168960
12 Meeting Room & Conference Back Support For
TV sft 4 0 0 4 2500 10000
13 Supply & installtion of Toilet Mirrors & Ply
box sft 2 7.1 3.9 55.38 400 22152
Total 514012
Before Tax 514012
CGST@9% 46,261.08
SGST@9% 46,261.08
Total Tax 92,522.16
Total After Tax 606,534.16