0% found this document useful (0 votes)
16 views

06 - Turan - Design of Primary Systems

Uploaded by

all ofbest
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
16 views

06 - Turan - Design of Primary Systems

Uploaded by

all ofbest
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 48

Turan Gonen, Electric Power Distribution System Engineering, 2nd Ed.

, CRC Press

Graduate School of Energy Convergence


Prof. Yun-Su Kim
• Considerations for feeder rating
• Nature of the load

• Load density of the area

• Growth rate of the load

• Spare capacity for emergency

• Type and cost of circuit construction

• Design and capacity of substation

• Type of regulating equipment used

• Quality of service required

2
• Characteristics
• The simplest and the lowest cost

• The most common form

• Current magnitude is the


greatest in the circuit conductors
that leave the substation

• So, the conductor size can be


different from each section

• Reliability is low

3
• Modified radial-type with tie and sectionalizing switches
• Used in Korea

• Provide fast restoration service

• Fault can be isolated

4
• Radial primary feeder with express feeder and backfeed
• Express feeder
• Section between the substation and
the load center of the service area

• Subfeeder is allowed to provide


a backfeed toward the substation
from the load center

5
• Radial-type phase-area feeder
• Area for each phase is distinguished

6
• Characteristics
• Loop tie disconnect switch can be replaced by
a loop tie breaker

• The size of the feeder conductor is


kept the same throughout the loop

• Generally, a separate feeder breaker


on each end of the loop is preferred

7
• Design considerations
• Primary-feeder length • System maintenance practices

• Primary-feeder loading • The extent of tree trimming

• Number of distribution substations • Joint use of utility poles

• Rating of distribution substations • Type of pole-line design and construction

• Number of subtransmission lines • Appearance of the pole line

• Number of customers affected


by a specific outage

8
• Additional considerations

9
• Voltage levels (Used in US)

10
• Voltage-square rule
• If the feeder voltage is doubled, for the same percent voltage drop, it can supply the
same power four times the distance

• The advantage obtained is

• where

11
• Voltage-square rule (Cont’d)
• Illustration

1
Must be × 4
2

12
• Area-coverage principle
• For a constant %VD and a uniformly distributed load, the feeder service area is
proportional to:

13
• Area-coverage principle (Cont’d)
• Derivation
𝑆𝑆3𝑝𝑝 𝐴𝐴𝐴𝐴
𝑍𝑍×𝐼𝐼 𝑠𝑠𝑙𝑙𝑙𝑙×3𝑉𝑉 𝑠𝑠𝑙𝑙𝑙𝑙×3𝑉𝑉 𝑠𝑠𝑧𝑧𝐷𝐷
𝐿𝐿−𝑁𝑁 𝐿𝐿−𝑁𝑁
𝑉𝑉𝑉𝑉𝑝𝑝𝑝𝑝 = = = = 2 𝐴𝐴𝐴𝐴 𝑠𝑠 : effective length
𝑉𝑉𝐿𝐿−𝑁𝑁 𝑉𝑉𝐿𝐿−𝑁𝑁 𝑉𝑉𝐿𝐿−𝑁𝑁 3𝑉𝑉𝐿𝐿−𝑁𝑁

𝑠𝑠𝑧𝑧𝐷𝐷
2 𝐴𝐴𝑜𝑜𝑜𝑜𝑜𝑜 𝑙𝑙𝑜𝑜𝑜𝑜𝑜𝑜 2
𝑉𝑉𝑉𝑉𝑝𝑝𝑝𝑝,𝑜𝑜𝑜𝑜𝑜𝑜 3𝑉𝑉𝐿𝐿−𝑁𝑁.𝑜𝑜𝑜𝑜𝑜𝑜 𝑉𝑉𝐿𝐿−𝑁𝑁,𝑜𝑜𝑜𝑜𝑜𝑜 𝐴𝐴𝑜𝑜𝑜𝑜𝑜𝑜 𝑙𝑙𝑜𝑜𝑜𝑜𝑜𝑜
= 𝑠𝑠𝑧𝑧𝐷𝐷 = 𝑉𝑉 2
𝑉𝑉𝑉𝑉𝑝𝑝𝑝𝑝,𝑛𝑛𝑛𝑛𝑛𝑛 𝐴𝐴𝑛𝑛𝑛𝑛𝑛𝑛 𝑙𝑙𝑛𝑛𝑛𝑛𝑛𝑛 𝐿𝐿−𝑁𝑁,𝑛𝑛𝑛𝑛𝑛𝑛 𝐴𝐴𝑛𝑛𝑛𝑛𝑛𝑛 𝑙𝑙𝑛𝑛𝑛𝑛𝑛𝑛
2
3𝑉𝑉𝐿𝐿−𝑁𝑁,𝑛𝑛𝑛𝑛𝑛𝑛

1 3
2
𝐴𝐴𝑛𝑛𝑛𝑛𝑛𝑛 𝑙𝑙𝑛𝑛𝑛𝑛𝑛𝑛 𝑉𝑉𝐿𝐿−𝑁𝑁,𝑛𝑛𝑛𝑛𝑛𝑛 𝐴𝐴𝑛𝑛𝑛𝑛𝑛𝑛 𝐴𝐴2𝑛𝑛𝑛𝑛𝑛𝑛 𝐴𝐴2𝑛𝑛𝑛𝑛𝑛𝑛
= = 1 = 3 holds only if 𝐴𝐴 = 𝑙𝑙 2
𝐴𝐴𝑜𝑜𝑜𝑜𝑜𝑜 𝑙𝑙𝑜𝑜𝑜𝑜𝑜𝑜 𝑉𝑉𝐿𝐿−𝑁𝑁,𝑜𝑜𝑜𝑜𝑜𝑜
𝐴𝐴𝑜𝑜𝑜𝑜𝑜𝑜 𝐴𝐴2𝑜𝑜𝑜𝑜𝑜𝑜 𝐴𝐴2𝑜𝑜𝑜𝑜𝑜𝑜

2
2 3
𝐴𝐴𝑛𝑛𝑛𝑛𝑛𝑛 𝑉𝑉𝐿𝐿−𝑁𝑁,𝑛𝑛𝑛𝑛𝑛𝑛
=
𝐴𝐴𝑜𝑜𝑜𝑜𝑜𝑜 𝑉𝑉𝐿𝐿−𝑁𝑁,𝑜𝑜𝑜𝑜𝑜𝑜

14
• Definition
• Loading of a feeder during peak load conditions measured at the substation

• Factors affecting the loading design


• Density of the feeder load • Primary-feeder voltage level

• Nature of the feeder load • Type and cost of construction

• Growth rate of the feeder load • Location and capacity of the distribution

• Reserve capacity requirements substation

for emergency • Voltage regulation requirements

• Service reliability requirements

• Quality of service

15
• Needed to perform either
of the following functions:
• Provide emergency service
for an adjacent feeder for
reduction of outage time

• Provide emergency service


for and adjacent substation
systems, thereby eliminating
the necessity of having an
emergency backup at every
substation

16
• Objective
• Provide an example for a uniform area development plan to minimize the circuitry
changes associated with the systematic expansion of the system

• Case study
• Assumptions
• 6-mi2 area will be served with 12 feeders, 4 per transformer

• Uniform load distribution

• 12 feeders would serve 1/2-mi2 in a fully developed area

17
• Case study 1: High-load density areas
• 1-2-4-8-12 feeder method

• Adjacent service areas are served from different transformer banks

18
• Case study 2: Low-load density areas
• 1-2-4-6-8-12 feeder method

19
• Illustration

20
• Formulate the cost function of the substation and the primary system
for 20 years including the installation cost
• The objective of the cost function is to get a minimum cost to supply the total load
for a given area

• Make any variables and assumptions as you need

21
• Line current
• Can be expressed as a function of distance

• Impedance
• 𝑧𝑧 = 𝑟𝑟 + 𝑗𝑗𝑗𝑗 [ohm/unit length]

• As the total load is uniformly distributed from 𝑥𝑥 = 0 to 𝑥𝑥 = 𝑙𝑙,

 constant

22
• 𝐼𝐼𝑥𝑥̅ can be found as a function of 𝐼𝐼𝑠𝑠̅ and 𝑥𝑥
• Therefore, for 𝑑𝑑𝑑𝑑,

• From (5.10),

where

23
• Therefore, for the total feeder,

• When 𝑥𝑥 = 𝑙𝑙,

• Hence,

• Substituting (5.17) into (5.18),

Since

24
• Series voltage drop
• Also be found as a function of 𝐼𝐼𝑠𝑠 and 𝑥𝑥

• or substituting (5.20) into (5.21),

• Differential power loss


• Also be found as a function of 𝐼𝐼𝑠𝑠 and 𝑥𝑥

• or substituting (5.20) into (5.23),

25
• Series voltage drop due to 𝐼𝐼𝑥𝑥

Tip
• Substituting (5.22) into (5.25), 𝑛𝑛
𝑏𝑏 − 𝑎𝑎 𝑏𝑏 − 𝑎𝑎
lim � 𝑓𝑓 𝑎𝑎 + 𝑘𝑘
𝑛𝑛→∞ 𝑛𝑛 𝑛𝑛
𝑘𝑘=1

𝑏𝑏
= � 𝑓𝑓(𝑥𝑥) 𝑑𝑑𝑑𝑑
𝑎𝑎

• Therefore, the total VD on the main feeder is: 𝑛𝑛


𝑏𝑏 − 𝑎𝑎
lim � 1 × =
𝑛𝑛→∞ 𝑛𝑛
𝑘𝑘=1

𝑏𝑏
𝑏𝑏 − 𝑎𝑎
lim 𝑛𝑛 × = � 1 𝑑𝑑𝑑𝑑
𝑛𝑛→∞ 𝑛𝑛 𝑎𝑎

26
• Total copper loss per phase

• From (5.28), the distance 𝑥𝑥 at which


• The total load current may be concentrated, that is, lumped for the purpose of
calculating the total voltage drop, is

• From (5.30),
• for the purpose of calculating the total power loss, is

27
• Given conditions

28
• The current at 𝑥𝑥
• From Figure 5.28,
𝑑𝑑𝐼𝐼𝑥𝑥
= −𝑘𝑘 × 𝑥𝑥
𝑑𝑑𝑑𝑑

• The constant 𝑘𝑘 can be found from


𝑙𝑙
𝐼𝐼𝑆𝑆 = � −𝑑𝑑𝐼𝐼𝑥𝑥
𝑥𝑥=0
𝑙𝑙
=� 𝑘𝑘 × 𝑥𝑥𝑥𝑥𝑥𝑥
𝑥𝑥=0

𝑙𝑙 2
𝐼𝐼𝑆𝑆 = 𝑘𝑘 ×
2

• From (5.33),
2
𝑘𝑘 = 𝐼𝐼𝑆𝑆
𝑙𝑙 2

29
• Substituting (5.34) into (5.31),
𝑑𝑑𝐼𝐼𝑥𝑥 𝑥𝑥
= −2𝐼𝐼𝑆𝑆 × 2
𝑑𝑑𝑑𝑑 𝑙𝑙

• Hence, the current at 𝑥𝑥 is 𝑥𝑥


𝑥𝑥 2
𝐼𝐼𝑥𝑥 = 𝐼𝐼𝑆𝑆 − � −𝑑𝑑𝐼𝐼𝑥𝑥′ = 𝐼𝐼𝑆𝑆 − 𝑘𝑘 ×
𝑥𝑥′=0 2
2 2
2 𝑥𝑥 𝑥𝑥
= 𝐼𝐼𝑆𝑆 − 𝐼𝐼𝑆𝑆 2 × = 𝐼𝐼𝑆𝑆 1 − 2
𝑙𝑙 2 𝑙𝑙
• Differential series voltage drop

• Differential power loss

30
• Series VD due to 𝐼𝐼𝑥𝑥

• Substituting (5.38) into (5.41) and integrating the result,

• Total series VD when 𝑥𝑥 = 𝑙𝑙

• Total copper loss per phase

31
• Assumption
• Single-phase or balanced three-phase transmission or distribution circuit

• 𝑉𝑉𝑠𝑠 , 𝑃𝑃𝑟𝑟 , and cos 𝜃𝜃 are known – Commonly encountered in system design

• Taking 𝑉𝑉�𝑟𝑟 as reference

32
• Sending-end voltage in terms of general circuit constant

• where

33
• (5.49) can be written as

• From which

• Taking squares of (5.55) and (5.56), and adding them,

34
• Since

• (5.58) can be rewritten as

• Let

• Then (5.62) becomes

35
• From (5.65),

• From (5.55) and (5.56),

• where

• Therefore,

36
• By dividing (5.68) by (5.69),

• For adaptation
• (5.63), (5.66), (5.71) can be written in terms of 𝑅𝑅 and 𝑋𝑋

• For feeder shown in Fig. 5.31,

37
• For adaptation (Cont’d)
• For feeder shown in Fig. 5.31, (Cont’d)

• where

• Therefore,

• where

38
• For adaptation (Cont’d)
• For feeder shown in Fig. 5.31, (Cont’d)

• Similarly,

• where

• Substituting (5.79), (5.80), (5.83), (5.84) into (5.66),

39
• or

• where

• Also from (5.71),

40
• Kundur, “Power System Stability and Control”, Chapter 2

41
• Kundur, “Power System Stability and Control”, Chapter 2

42
• Kundur, “Power System Stability and Control”, Chapter 2

43
• Kundur, “Power System Stability and Control”, Chapter 2

44
• Example

45
• Example (Cont’d)
• Solution to (a)
• From (5.88),

• From (5.87),

46
• Example (Cont’d)
• Solution to (a) (Cont’d)
• From (5.89),

• Therefore,

47
• Example (Cont’d)
• Solution to (b)
• From the given equation

48

You might also like