06 - Turan - Design of Primary Systems
06 - Turan - Design of Primary Systems
, CRC Press
2
• Characteristics
• The simplest and the lowest cost
• Reliability is low
3
• Modified radial-type with tie and sectionalizing switches
• Used in Korea
4
• Radial primary feeder with express feeder and backfeed
• Express feeder
• Section between the substation and
the load center of the service area
5
• Radial-type phase-area feeder
• Area for each phase is distinguished
6
• Characteristics
• Loop tie disconnect switch can be replaced by
a loop tie breaker
7
• Design considerations
• Primary-feeder length • System maintenance practices
8
• Additional considerations
9
• Voltage levels (Used in US)
10
• Voltage-square rule
• If the feeder voltage is doubled, for the same percent voltage drop, it can supply the
same power four times the distance
• where
11
• Voltage-square rule (Cont’d)
• Illustration
1
Must be × 4
2
12
• Area-coverage principle
• For a constant %VD and a uniformly distributed load, the feeder service area is
proportional to:
13
• Area-coverage principle (Cont’d)
• Derivation
𝑆𝑆3𝑝𝑝 𝐴𝐴𝐴𝐴
𝑍𝑍×𝐼𝐼 𝑠𝑠𝑙𝑙𝑙𝑙×3𝑉𝑉 𝑠𝑠𝑙𝑙𝑙𝑙×3𝑉𝑉 𝑠𝑠𝑧𝑧𝐷𝐷
𝐿𝐿−𝑁𝑁 𝐿𝐿−𝑁𝑁
𝑉𝑉𝑉𝑉𝑝𝑝𝑝𝑝 = = = = 2 𝐴𝐴𝐴𝐴 𝑠𝑠 : effective length
𝑉𝑉𝐿𝐿−𝑁𝑁 𝑉𝑉𝐿𝐿−𝑁𝑁 𝑉𝑉𝐿𝐿−𝑁𝑁 3𝑉𝑉𝐿𝐿−𝑁𝑁
𝑠𝑠𝑧𝑧𝐷𝐷
2 𝐴𝐴𝑜𝑜𝑜𝑜𝑜𝑜 𝑙𝑙𝑜𝑜𝑜𝑜𝑜𝑜 2
𝑉𝑉𝑉𝑉𝑝𝑝𝑝𝑝,𝑜𝑜𝑜𝑜𝑜𝑜 3𝑉𝑉𝐿𝐿−𝑁𝑁.𝑜𝑜𝑜𝑜𝑜𝑜 𝑉𝑉𝐿𝐿−𝑁𝑁,𝑜𝑜𝑜𝑜𝑜𝑜 𝐴𝐴𝑜𝑜𝑜𝑜𝑜𝑜 𝑙𝑙𝑜𝑜𝑜𝑜𝑜𝑜
= 𝑠𝑠𝑧𝑧𝐷𝐷 = 𝑉𝑉 2
𝑉𝑉𝑉𝑉𝑝𝑝𝑝𝑝,𝑛𝑛𝑛𝑛𝑛𝑛 𝐴𝐴𝑛𝑛𝑛𝑛𝑛𝑛 𝑙𝑙𝑛𝑛𝑛𝑛𝑛𝑛 𝐿𝐿−𝑁𝑁,𝑛𝑛𝑛𝑛𝑛𝑛 𝐴𝐴𝑛𝑛𝑛𝑛𝑛𝑛 𝑙𝑙𝑛𝑛𝑛𝑛𝑛𝑛
2
3𝑉𝑉𝐿𝐿−𝑁𝑁,𝑛𝑛𝑛𝑛𝑛𝑛
1 3
2
𝐴𝐴𝑛𝑛𝑛𝑛𝑛𝑛 𝑙𝑙𝑛𝑛𝑛𝑛𝑛𝑛 𝑉𝑉𝐿𝐿−𝑁𝑁,𝑛𝑛𝑛𝑛𝑛𝑛 𝐴𝐴𝑛𝑛𝑛𝑛𝑛𝑛 𝐴𝐴2𝑛𝑛𝑛𝑛𝑛𝑛 𝐴𝐴2𝑛𝑛𝑛𝑛𝑛𝑛
= = 1 = 3 holds only if 𝐴𝐴 = 𝑙𝑙 2
𝐴𝐴𝑜𝑜𝑜𝑜𝑜𝑜 𝑙𝑙𝑜𝑜𝑜𝑜𝑜𝑜 𝑉𝑉𝐿𝐿−𝑁𝑁,𝑜𝑜𝑜𝑜𝑜𝑜
𝐴𝐴𝑜𝑜𝑜𝑜𝑜𝑜 𝐴𝐴2𝑜𝑜𝑜𝑜𝑜𝑜 𝐴𝐴2𝑜𝑜𝑜𝑜𝑜𝑜
2
2 3
𝐴𝐴𝑛𝑛𝑛𝑛𝑛𝑛 𝑉𝑉𝐿𝐿−𝑁𝑁,𝑛𝑛𝑛𝑛𝑛𝑛
=
𝐴𝐴𝑜𝑜𝑜𝑜𝑜𝑜 𝑉𝑉𝐿𝐿−𝑁𝑁,𝑜𝑜𝑜𝑜𝑜𝑜
14
• Definition
• Loading of a feeder during peak load conditions measured at the substation
• Growth rate of the feeder load • Location and capacity of the distribution
• Quality of service
15
• Needed to perform either
of the following functions:
• Provide emergency service
for an adjacent feeder for
reduction of outage time
16
• Objective
• Provide an example for a uniform area development plan to minimize the circuitry
changes associated with the systematic expansion of the system
• Case study
• Assumptions
• 6-mi2 area will be served with 12 feeders, 4 per transformer
17
• Case study 1: High-load density areas
• 1-2-4-8-12 feeder method
18
• Case study 2: Low-load density areas
• 1-2-4-6-8-12 feeder method
19
• Illustration
20
• Formulate the cost function of the substation and the primary system
for 20 years including the installation cost
• The objective of the cost function is to get a minimum cost to supply the total load
for a given area
21
• Line current
• Can be expressed as a function of distance
• Impedance
• 𝑧𝑧 = 𝑟𝑟 + 𝑗𝑗𝑗𝑗 [ohm/unit length]
constant
22
• 𝐼𝐼𝑥𝑥̅ can be found as a function of 𝐼𝐼𝑠𝑠̅ and 𝑥𝑥
• Therefore, for 𝑑𝑑𝑑𝑑,
• From (5.10),
where
23
• Therefore, for the total feeder,
• When 𝑥𝑥 = 𝑙𝑙,
• Hence,
Since
24
• Series voltage drop
• Also be found as a function of 𝐼𝐼𝑠𝑠 and 𝑥𝑥
25
• Series voltage drop due to 𝐼𝐼𝑥𝑥
Tip
• Substituting (5.22) into (5.25), 𝑛𝑛
𝑏𝑏 − 𝑎𝑎 𝑏𝑏 − 𝑎𝑎
lim � 𝑓𝑓 𝑎𝑎 + 𝑘𝑘
𝑛𝑛→∞ 𝑛𝑛 𝑛𝑛
𝑘𝑘=1
𝑏𝑏
= � 𝑓𝑓(𝑥𝑥) 𝑑𝑑𝑑𝑑
𝑎𝑎
𝑏𝑏
𝑏𝑏 − 𝑎𝑎
lim 𝑛𝑛 × = � 1 𝑑𝑑𝑑𝑑
𝑛𝑛→∞ 𝑛𝑛 𝑎𝑎
26
• Total copper loss per phase
• From (5.30),
• for the purpose of calculating the total power loss, is
27
• Given conditions
28
• The current at 𝑥𝑥
• From Figure 5.28,
𝑑𝑑𝐼𝐼𝑥𝑥
= −𝑘𝑘 × 𝑥𝑥
𝑑𝑑𝑑𝑑
𝑙𝑙 2
𝐼𝐼𝑆𝑆 = 𝑘𝑘 ×
2
• From (5.33),
2
𝑘𝑘 = 𝐼𝐼𝑆𝑆
𝑙𝑙 2
29
• Substituting (5.34) into (5.31),
𝑑𝑑𝐼𝐼𝑥𝑥 𝑥𝑥
= −2𝐼𝐼𝑆𝑆 × 2
𝑑𝑑𝑑𝑑 𝑙𝑙
30
• Series VD due to 𝐼𝐼𝑥𝑥
31
• Assumption
• Single-phase or balanced three-phase transmission or distribution circuit
• 𝑉𝑉𝑠𝑠 , 𝑃𝑃𝑟𝑟 , and cos 𝜃𝜃 are known – Commonly encountered in system design
32
• Sending-end voltage in terms of general circuit constant
• where
33
• (5.49) can be written as
• From which
34
• Since
• Let
35
• From (5.65),
• where
• Therefore,
36
• By dividing (5.68) by (5.69),
• For adaptation
• (5.63), (5.66), (5.71) can be written in terms of 𝑅𝑅 and 𝑋𝑋
37
• For adaptation (Cont’d)
• For feeder shown in Fig. 5.31, (Cont’d)
• where
• Therefore,
• where
38
• For adaptation (Cont’d)
• For feeder shown in Fig. 5.31, (Cont’d)
• Similarly,
• where
39
• or
• where
40
• Kundur, “Power System Stability and Control”, Chapter 2
41
• Kundur, “Power System Stability and Control”, Chapter 2
42
• Kundur, “Power System Stability and Control”, Chapter 2
43
• Kundur, “Power System Stability and Control”, Chapter 2
44
• Example
45
• Example (Cont’d)
• Solution to (a)
• From (5.88),
• From (5.87),
46
• Example (Cont’d)
• Solution to (a) (Cont’d)
• From (5.89),
• Therefore,
47
• Example (Cont’d)
• Solution to (b)
• From the given equation
48