0% found this document useful (0 votes)
191 views2 pages

Working Over or Near Water Permit

Uploaded by

prabhu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
191 views2 pages

Working Over or Near Water Permit

Uploaded by

prabhu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

GCC- WORKING OVER OR NEAR WATER PERMIT

STOP! Before starting working over or near water activities review all safety precautions.
Can this work be avoided or is there a safer way, even so, do not authorize work!

Project: Date of issue: Permit number:


General Construction Company
Sub- contractor (Name):
Location (Specific Area Name & Location):

The permit is required for the following situations:


 Any workplace over or near water is considered a dangerous work place, where employees working in such
workplaces are exposed to the hazard of slipping, or falling into the water.

Description of work: EMERGENCY CONTACT NUMBER


(In case of an emergency please call) –
Which of the following hazards are associated with this work? (Check “” which is applicable)
Work over water or silt Unguarded edges

Untrained workers Lack of space

Unstable working platform Exposed Electrical cables

Slip, trip & falls Manual handling of loads

Risk of falling Extreme wind

Additional Hazards (if applicable)

Precautions to be used: (Check “” which is applicable)


Platform with standard edge Harness attached to suitable anchor point

Life buoys are available Lifeline required

Life jacket are available Electrical cables are isolated

Safety watcher/supervisor

Harness with double lanyard

Additional Hazards (if applicable)

GCC-EHSF/WO-NWP/Rev.03_03032022
GCC- WORKING OVER OR NEAR WATER PERMIT
STOP! Before starting working over or near water activities review all safety precautions.
Can this work be avoided or is there a safer way, even so, do not authorize work!

Project: Date of issue: Permit number:


General Construction Company
Sub- contractor (Name):
Location (Specific Area Name & Location):

Mandatory PPE required

1. Performer’s Acknowledgement: 2. Supervisor Acknowledgement:


I understood the work that is to be carried out and will ensure the above I will monitor the work that is to be carried out and will ensure the above mentioned necessary
mentioned necessary safety precautions are followed at all times, I will complete safety precautions are followed at all times, I will complete this task in safe method and I accept

my task in safe method and I accept responsibility for this work. responsibility for this work.
Performer Name: Supervisor Name:
(Permit Receiver) Signature: (Permit Receiver) Signature:
3. Checked and approved by Acknowledgement: 4. EHS Department Acknowledgement:
Authorization is hereby granted for the works as described above. I have checked above control measures and the work area is safe to carry out the activity.
UNSAFE TO WORK
Concerned Engineer Name: SAFE TO WORK
(Permit Issuer)
Signature: Safety officer Name:
Permit Validity Period
From: To: Signature:
(Time):
5. Closed Out:
This is to certify that the works described above have been safely completed / stopped / area has been restored to a safe and orderly condition.
Name: Name:
Concerned Engineer
Signature: Safety officer
(Permit Issuer) Signature:
Closed Out Time:

GCC-EHSF/WO-NWP/Rev.03_03032022