Method Statement - Grading Works
Method Statement - Grading Works
GRADING WORKS
1. Introduction
1.1. Purpose
The purpose of this Method statement is to outline the commitment of CONTRACTOR to Construct and Complete
the work for the project as per construction milestone without sacrificing the Safety and Quality of the project.
This Method statement remains a working document subject for revision/updating throughout the duration of this
project and will be discussed during daily construction meeting and weekly progress meeting as construction phase
progresses.
This method statement however sets out to demonstrate our ability to carry out the works in the optimum time, in
the most viable and safe manner to achieve a completed project to the satisfaction of all parties involved.
A well define procedure based on standards and guidelines will be presented from this method statement by
CONTRACTOR. and the main objective is to ensure that the particular scope of works will be carried out accordingly
in accordance with the construction standards and guidelines that is applicable to the project to attain a proper
earth works that meets the design specification and place.
This Method statement for earthworks shall comply with the CLIENT inspection requirements, procedures, Codes
and Standards for Master Gas Pipeline Corridor Washout Protection Project.
2. References
This selection of references covered by the standard shall comply with the latest edition of the reference mentioned
below, unless otherwise noted.
Page 1 of 14
METHOD STATEMENT
4. Materials / Manpower
4.1. Items for Earthworks activity are included the following:
a. PPE – Personal Protective Equipment
Al-Tamimi shall provide the proper PPE (e.g., hard hat, safety glasses, safety shoes, hearing protection, gloves,
FRC) that meets SA specifications to its employees. Reference; Chapter I-3, Personal Protective Equipment
(PPE) of the SA Construction Safety Manual (CSM). Al-Tamimi shall outline the minimum personal protective
equipment to be Proper PPE (e.g. correct for type of exposure, sized to fit the worker, meets applicable
Standards, no defects) shall be provided to personnel at the work site.
LIST OF MANPOWER
INDIRECTMANPOWER
1. Project Manager
Page 2 of 14
METHOD STATEMENT
2. Construction Manager
3. Procurement QC Supervisor
4. QAQC Manager
5. QC Supervisor
6. QC Inspectors
7. Site Engineers
8. Safety Supervisor
9. Safety Officer
10. Document Control
DIRECT MANPOWER
1. Civil Foreman
2. Heavy Equipment Operators & Drivers
3. Surveyor & Crew
4. Skilled Workers
5. Laborer & Helpers
6. Flagman
7. Work Permit Receiver
LIST OF EQUIPMENT
1. Bulldozer
2. Excavator
3. Dump Trucks
4. Trailer Trucks
5. Loader
6. Grader
7. Roller Compactor
8. Rapid impact compaction equipment
9. Water Trucks
10. Fuel Tanker
11. Service Grease Truck
12. Service Cars/Pick-up
5. Scope of Works
This method statement covers the requirements for all earth works:
6. Responsibilities
6.1. Project Manager
• Work progress is carried out according to the planned program and all the equipment required to execute the
work are all available and are in good conditions as per project planning.
• Overall project policy monitoring relations with consultant and client’s team.
Page 3 of 14
METHOD STATEMENT
• Conducting daily / weekly meetings with all staff / suppliers to point out the work activities, requirement of
resources, order/ direct material and equipment at site with maximum efficiency, find solutions and taking
immediate actions Review correspondence for proper action Financial follow up and control the cost of project
duration execution, follow up monthly payment certificates, variation orders in co‐ordination with QS & Planner.
• He will be directing the Construction Manager, Site Engineer, Office Engineer, Planning Engineer, Quality
Control Engineer, Quantity Surveyor and the Safety Officer.
6.5. QC Supervisor
• To lead the team of QC Inspectors for monitoring the activities.
• Regular site visits for foreseeing the potential deficiencies based on his physical experience to share with
construction crew and guidance to QC Inspectors.
• Ensuring the availability of QC Inspector during any operations.
• Conducting routine internal meetings with QC inspectors for further vigilance to the potential problems which
must be tackled accordingly to avoid non‐conformities.
• Imitating internal Log Book Entries/NCR’s to construction crew for effective implementation of project quality
plan, ITP’s, written procedures, project specifications, IFC drawings etc.
Page 4 of 14
METHOD STATEMENT
• Prepare “two week lookahead schedule” of construction phases as per Schedule Q requirements.
Page 5 of 14
METHOD STATEMENT
• Work permit receivers shall attend and pass the classroom work permit certification course every two years in
order to maintain certification. Work permit receivers shall complete all required prerequisite training and
certifications.
• Candidates are required to successfully complete the classroom courses as prerequisites before being allowed
to take the Receivers certification course.
• Initiating and completing all applicable section of the permit to work.
• Supervising the work prescribe in the permit to work to ensure it is conducted in the most efficient manner.
• Notifying the issuer of work progress and completion, and ensuring that the site is returned to a safe and
operational state.
• Taking adequate care to preserve the permit in good condition.
• Providing and arranging all necessary resources related with performing the work.
• Revalidation of work permit is required.
7. Procedures
7.1. Quality & Safety Prior to Start any Activities
• The CONTRACTOR shall be responsible for constructing the proposed works according to the plans and
specifications and particularly refer to the CLIENT guidelines. Prior to construction, CONTRACTOR shall
provide a quality control plan that will serve as the guidelines for the construction of this scope wherein
construction requirements as per project plan and Standards will be followed.
• Procedures listed below were drafted to serve as the guiding procedure on how to execute and implement the
scope of works on site.
• All personnel shall undergo safety orientation seminar prior to site deployment.
• All necessary Personal Protective Equipment (PPE) shall be provided to those who are involve in the project.
• Risk assessment of the work activity shall be prepared.
• Surveillance and monitoring by Safety and Quality Team must be conducted for earthworks and other related
activities to prevent Safety Incident and Quality Violations.
• Approved excavation checklist must be acquired from CLIENT before any excavation execution is conducted.
7.2. Submittals
• The Contractor shall be responsible for transmitting the following submittals to the CLIENT Company
Representative:
• Compaction Test Reports, including all laboratory and field test logs and comments. Field test reports shall
include density and moisture content test logs indicating location by coordinates and elevation as per standard.
Reports shall be submitted as follows:
• Fill Materials and Water Test Reports. Sources and test results of all fill materials and compaction water shall
be submitted for approval prior to beginning fill operations. Compaction water shall be tested for Total Dissolved
Solids, Chloride (Cl‐) and Sulfate (SO4) contents according to standard.
• Controlled Low Strength Material (CLSM) mix design and 28‐day compressive strength shall be submitted for
approval prior to use on the site.
• Excavation Plan, including a Pre‐Excavation checklist, as per the CLIENT Construction Safety Manual and
Safety Management Guide shall be submitted prior to beginning excavation. Consulting Services Department
review of the Excavation Plan is required if excavation depth is greater than 6 m or if the Plan includes
support or protection for existing structures, foundations or underground utilities.
Page 6 of 14
METHOD STATEMENT
• All excavations, including shoring and sheeting materials and systems, shall meet the minimum requirements
established by the Construction Safety Manual and CLIENT Safety Management Guide. If an Excavation Plan
is required and shoring is used, the Contractor’s Excavation Plan shall:
• Dewatering Plan. If dewatering of an excavation is required, the Contractor shall submit proposed methods and
details to the CLIENT Company Representative for review and approval, before beginning dewatering and
excavation.
7.3. Environmental
• Contaminated Soils Known contaminated soils within the construction limits shall be managed in accordance with
a contaminated soil management plan provided by CLIENT prior to the start of excavation. If unexpected soil
contamination is encountered during the work, the Contractor shall stop work and notify the CLIENT Company
Representative immediately.
Erosion/Sediment Control:
• The Contractor shall ensure that all slopes and other areas subject to erosion shall be maintained using
temporary erosion and sediment control measures during construction or until relieved by the CLIENT
Company Representative or until permanent measures are completed and functioning in a satisfactory manner.
Excavation Safety:
• Before excavation activities begin, the location of any known or suspected underground utilities that are in the
area of the proposed excavation shall conform and marked.
• Pre-excavation Checklist shall be properly completed and made available at the work site.
• An Excavation Plan shall be submitted to the CLIENT Company Representative.
• All excavation shall be done in accordance with CLIENT safety requirements including, but not limited to, the
CLIENT Construction Safety Manual and Safety Management Guide, including:
• Provision of safe entry and exit.
• Precautions for Hazardous Atmospheres and Confined Spaces.
• Provision and maintenance of edge protection, clearances, barricades, and fixed lighting.
• Protection of underground utilities and installations.
• Protection against sidewall cave‐in. Shoring shall be installed or the sides shall be sloped or benched when any
excavation or trench reaches a depth of 1.2 m or when soil banks are greater than 1.5 m.
• Provision of proper inspection frequency.
Page 7 of 14
METHOD STATEMENT
• Proper backfilling and removal of shoring. Shoring may be left in‐place if so, indicated in the approved Excavation
Plan.
Hazard Mitigation:
• Whenever CLIENT determines that any excavation or embankment or fill which was created by a Contractor
and which is a hazard to life and limb, or endangers property, or adversely affects the safety, use or stability
of a roadway or drainage channel, the responsible Contractor shall immediately repair or eliminate such
excavation or embankment so as to eliminate the hazard.
• Any construction or maintenance work which restricts the full use of a pedestrian or vehicular roadway shall
comply with General Instructions, Street and Road Closure: Excavation, Reinstatement and Traffic Controls.
Page 8 of 14
METHOD STATEMENT
• Select Fill or ‘Structural Fill’ shall be composed only of inorganic material and shall have 100% passing the 5 cm
(2 in) sieve and from 0 to 20% passing the No. 200 sieve.
• The portion of Select Fill material passing the No. 40 sieve shall have a maximum liquid limit of 35 and a maximum
plasticity index of 12 per ASTM D4318. Liquid limit and plastic limit tests are not required for select fill material
with less than 15% passing the No. 200 sieve.
Compaction Water:
• Water used for compaction of fill material shall be reasonably free of salts, oil, acid, alkalis, organic matter, or
other deleterious substances.
• Use of water with Total Dissolved Solids of 10,000 ppm or more (i.e., brackish water, seawater or water obtained
from ground pits such as subkha water) is not allowed.
Stripping:
• Before any soil is removed, the area will be cleared of all debris.
• Stripping will consist of the excavation, removal, and satisfactory disposal of all topsoil and soil containing
organic material. Such stripped materials will not be used as structural fill material under any circumstances.
• Topsoil will be removed to full‐depth or as specified in the contract documents.
• Reusable materials will be stockpiled as necessary for constructor’s operations in areas approved by purchaser.
Page 9 of 14
METHOD STATEMENT
Rough Grading:
• General area grading will be completed to within a tolerance of plus or minus 0.20 feet (60 mm) of the elevations
shown in the contract documents, but will not be uniformly high or low.
• Roads, parking areas, and building areas will be excavated or filled to subgrade elevations shown in the contract
documents.
• Rock encountered through cut sections will be excavated to 1 foot (0.3 m) below subgrade elevation and will be
backfilled to the specified elevation.
• If unsatisfactory field conditions caused by rain, inclement weather, or other circumstances prevent
satisfactory performance of the work, earthwork operations will be suspended and the purchaser notified.
• After completing grading operations and before grassing operations, the graded areas that are not to be further
improved will be overlaid with topsoil of a compacted thickness of 4 inches (100 mm) minimum.
Structural Excavation:
• Structural excavation will include excavations for area paving, roadways, railways, foundations, grade beams,
sumps, basements, retaining walls, manholes, catch basins, trenches, and all other in‐ground and belowground
facilities, and areas to be used in the future to support structural loads as specified in the contract documents.
• Structural excavation will be performed in accordance with the contract documents to the dimensions, grades,
and elevations as noted and as required for formwork.
• Over excavation will not be permitted unless otherwise specified in the contract documents or approved by
engineer of record,
• Soils encountered at the bottom of excavation elevation specified in the contract documents which do not meet
the compaction requirements of standard will be removed and replaced with compacted structural fill or CLSM.
Earthen Structures:
• Earthen structures include, but are not limited to, ponds, canals, ditches, retention basins, levees, and dikes.
• Excavation for earthen structures will be made to the lines, grades, and cross sections as specified in the
contract documents.
• Side slopes of excavations will be cut and graded to the specified cross section.
• Unstable soil in the slopes will be removed, and the slopes repaired using material and methods in accordance
with standards.
• The bottoms of excavations will be graded to the elevations and configurations as specified in the contract
documents.
• Over‐excavation will be backfilled and compacted in accordance with standard.
Trenching:
• Trenches are excavations made for placement of, but not limited to, underground piping, electrical cables, duct
banks, and drainage ditches.
• The bottom of trenches will be graded to the elevations as specified in the contract documents.
• When applicable install shoring in advance of or simultaneously with trench excavation so that soils within full
height of trench excavation walls will remain laterally supported at all times.
• Unstable soil in the bottom of trenches will be removed and replaced using material as and methods in accordance
with standard.
• Over excavation of trenches will not be permitted unless otherwise specified in the contract documents or
approved by engineer of record.
Rock Excavation:
• Rock excavation will consist of excavation of boulders or pieces of detached rock measuring 1 cubic yard (0.76
cubic m) in volume or greater, or rock in ledges, bedded deposits, and conglomerate deposits so firmly cemented
Page 10 of 14
METHOD STATEMENT
that they present all the characteristics of solid rock, which cannot be excavated with earth moving, heavy
equipment. All other excavation will be earth excavation.
• If blasting is not permitted, rock will be excavated with mechanical rippers, mechanical breakers, or mechanical
drills with non‐explosive demolition agents.
• If blasting is permitted and required, blasting operations will be managed in accordance with the rock‐blasting
plan.
• If unexpected hard rock is encountered during the work, the work will be stopped until a blasting plan is
developed or until owner provides specific direction.
Stockpiling:
• Material will be stockpiled in a location specified by owner.
• Stockpiles will be placed, graded, and shaped for drainage.
• Storage or stockpiling of material will not be permitted on a completed subgrade.
• Stockpiling of contaminated soils will be in accordance with an owner approved contaminated soils management
plan or as specified by owner.
Drainage:
• Drainage of cuts, excavations, fills, stockpiles, spoil areas, surcharge embankments, and borrow areas will be
maintained at all times to prevent ponding of surface water because of ground water or rainfall by providing
temporary ditches, swales, culverts, and/or pumping systems as required in each respective site area.
• Temporary drainage facilities will be removed at the completion of the project or as specified by owner.
• A temporary surface seal (e.g., sealing with a smooth drum roller) will be constructed as required to prevent
saturation during wet weather or temporary shutdown of operations.
• Soil that becomes saturated will be removed completely or reconditioned in accordance with standard.
Page 11 of 14
METHOD STATEMENT
• For enclosed areas or tightly spaced areas, if access by proof rolling equipment is limited, hand operated rollers
or plate compactors may be used if approved by owner.
• In accordance with any other requirements specified in the contract documents including but not limited to
over‐excavation, moisture conditioning and re‐compacting of the upper soils, and chemical stabilization or other
methods of improving soil conditions.
• The density of the top 6 inches (150 mm) in areas for structural fill or loading will not be less than 90% of the
maximum Modified Proctor density in accordance with ASTM D1557, or 95% of the maximum Standard Proctor
density in accordance with ASTM D698.
• The density of the top 6 inches (150 mm) in areas of structural fill or loading, where granular soils exist that
do not exhibit well‐defined Moisture‐density relationship, will be compacted to at least 80% relative density in
accordance with ASTM D4253 and ASTM D4254.
Unless otherwise specified in the contract documents, material will be placed in loose lifts not exceeding the
following criteria, provided that the specified compaction is achieved for the full depth:
• Structural fill will be placed in lifts of 8 inches (200 mm) maximum in loose depth.
• General fill will be placed in lifts of 12 inches (300 mm) maximum in loose depth.
• General and structural fill materials placed as backfill and compacted with hand‐operated equipment will be
placed in lifts of 4 inches (100 mm) maximum in loose depth unless otherwise approved by purchaser.
• Compaction shall be performed with equipment compatible with soil type.
• Fill and backfill layers shall be uniformly compacted in accordance with the following density requirements as
per standard.
All Select Fill Material and any fill beneath and/or adjacent to foundations, grade beams, mats, buildings, lined
slopes or drainage channels, and process areas:
• At least 90% of the maximum Modified Proctor density as determined by ASTM D1557, or At least 70% Relative
Density as determined by ASTM D4253 and ASTM D4254 for cohesionless granular soils that do not exhibit
well‐defined moisture density relationship.
Select Fill Material beneath and/or adjacent to foundations with static loads over 320 kPa and foundations for
vibrating or heavy machinery:
• At least 95% of the maximum Modified Proctor density as determined by ASTM D1557, or
• At least 85% Relative Density as determined by ASTM D4253 and ASTM D4254 for cohesionless granular soils
that do not exhibit well‐defined moisture density relationship.
Page 12 of 14
METHOD STATEMENT
• Working platforms for compaction on subkha deposits shall be compacted as necessary to achieve a stable base.
Subkha working platforms must be indicated as such and accounted for in the design. Compaction testing of
working platforms is not required.
• Topsoil identified as “for planting purposes” is exempted from compaction requirements.
• Compacted surfaces of fill and backfill shall be finish graded to the cross sections, lines, grades, and elevations
as indicated on the drawings.
• Topsoil will be placed, leveled to grade and lightly rolled to produce a firm surface suitable for landscape
purposes.
• Compaction by water jetting or flooding will not be permitted.
• Fill and backfill adjacent to structures (e.g., retaining walls, pits, and basements) will not be compacted with
heavy equipment, but with hand operated equipment to a distance of 4 feet (1.2 m) or greater beyond the sides
of the structures.
• To prevent unnecessary eccentric loading on a structure or foundation, every effort will be made to place
backfill materials symmetrically and in uniform layers.
• Unless otherwise permitted by purchaser, backfill around or over cast‐in place concrete will not be permitted
until the concrete has attained 75% of its specified strength.
• Compacted surfaces of fill and backfill will be finish‐graded to the cross sections, lines, grades, elevations and
tolerances specified in the contract documents.
8. Quality
a. Work execution and activities at site shall be monitored, surveyed, witnessed and recorded according to
applicable CLIENT Standards and Typical Inspection Plans.
b. Contractor shall issue written RFI’s 24 hours in advance prior to SAPID inspection and 48 hours for weekend.
c. CLIENT approved third party laboratory and technicians shall conduct all the required tests.
d. In any inspections the Contractor QC Inspector shall conduct an initial survey or witness prior to SAPID final
inspection.
Page 13 of 14
METHOD STATEMENT
e. Deficiencies noted during inspection should be corrected as soon as possible. Progressive failure from successive
flows must be avoided by providing timely maintenance intervention.
f. QC Inspector shall raise Internal NCR if installation is not as per the Standard requirements or it is not
according to the approved drawing.
g. CONTRACTOR shall institute a quality control program that will verify or ensure that the work performed
under the Contract meets the requirements of this Standard and the Contract Documents. CLIENT shall have
access to all facilities and records of the Contractor for the purpose of conducting performance
inspection/audits. During the audit, any inspection, test reports, and/or engineering analyses and calculations
associated with the
h. Scope of work shall be furnished upon request.
i. Material receiving inspection required such as select fill materials and other materials related to use will be
inspected by client before placing.
j. All required laboratory and field acceptance tests required shall be performed by a CLIENT‐approved
independent testing agency.
k. If testing and/or inspection is done by CLIENT, this does not relieve the Contractor of the responsibility to
meet all requirements of this Standard. Should it be later found that some work has been completed not in
compliance with this Standard, it shall remain the Contractor's responsibility to repair or reconstruct
deficient work until specifications are met at no cost to CLIENT.
Page 14 of 14