Topic 4b - Building A Network For A Project
Topic 4b - Building A Network For A Project
BUILDING
A NETWORK
FOR A PROJECT
Intructor: Nguyen Thuy Trang
WBS/Work
Packages to
Network
A
Work Packages B
D
Activities
K
Relationships
among Activities C
F
1
7/29/2020
Terminology
• Activity
• Merge activity
• Parallel activity
• Burst activity
• Path
• Critical path
A B D
2
7/29/2020
• Activity-on-Node (AON)
• Uses a node to depict an activity. A C
• Activity-on-Arrow (AOA)
• Uses an arrow to depict an activity.
D
• Predecessor activities
• Successor activities
• Concurrent activities Concurrent
activity
3
7/29/2020
Activity-on-Node Fundamentals
4
7/29/2020
5
7/29/2020
6
7/29/2020
Practical Considerations
• Network Logic Errors
• Activity Numbering
• Use of Computers to Develop Networks
• Calendar Dates
• Multiple Starts and Multiple Projects
Illogical Loop
7
7/29/2020
8
7/29/2020
Use of Lags
Finish-to-Start Relationship
Start-to-Start Relationship
New Product
Development
Process
9
7/29/2020
Start-to-Finish
Relationship
Combination
Relationship
Hammock Activities
• Hammock Activity
• An activity that spans over a segment of a project.
• Duration of hammock activities is determined after the
network plan is drawn.
• Hammock activities are used to aggregate sections of the
project to facilitate getting the right amount of detail for
specific sections of a project.
10
7/29/2020
Key Terms
Activity Gantt chart
Activity-on-arrow (AOA) Hammock activity
Activity-on-node (AON) Lag relationship
Burst activity Merge activity
Concurrent engineering Network sensitivity
Critical path Parallel activity
Early and late times Slack/float—total and free
11
7/29/2020
Activity-on-Arrow
Network
Fundamentals
Activity-on-Arrow
Network
Fundamentals
12