Design Steps of Pile Foundation - Eigenplus
Design Steps of Pile Foundation - Eigenplus
Following Indian standard code can be referred to design the pile foundation:
IS code 2911-2010
Part-1 – concrete piles
Section-1 -Driven cast in situ concrete piles
Section-2 – Bored cast in situ concrete piles
Driven precast concrete piles (revised-2010)
Part 2 – timber piles
Part 3 – Under reamed piles
Part 4 – Load test on piles
These are the Indian standard code which we must have to follow while we are
designing the piles.
Before that lets discuss the basic components of the pile foundations. Please look
into the figure below. This figure shows the very basic elements of the pile
foundation. This is the case of bridges. Large compression columns of the bridge is
called piers. This pier is resting over the pile cap. This pile cap further transfer the
load to the four piles below the pile cap.
After getting the basic idea of the pile foundation its time to understand the
behaviour of the pile foundation. When you see the figure below you can understand
the load transfer mechanism in the pile foundation. The pier transfers the vertical
load to the pile cap. This pile cap finally distribute the load from the pier to the four
pile.
In the image below you can see the action of piles as column and the pile load
reaction diagram.
After this we now have to discuss the pile cap. The pile cap is acting like a slab
(which resist the load by bending action). Please refer the figure below to have a feel
about the pile cap behaviour.
Piles in detail
In this section we will see the components of pile in detail. Please refer the figure
below.
As you know we are discussing the concrete piles here. As the first step we make the
pile hole and than pour the the concrete with the reinforcements. We cast the pile
upto ground level.
Now after this we cut the some portion of the the concrete pile. The length upto
which we are removing the concrete we call it chipped off length as shown in figure.
After this we place the levelling course on lean concrete and then we tie the
reinforcement for the pile cap. After the reinforcement we place the shuttering and
then casting of pile cap.
Design of Piles
As the first step of the design we will design the piles. We have already discussed
that pile behave as the column. Hence we will design it as the column.
Longitudinal reinforcement: In the first step we will see the how to calculate
the area of longitudinal reinforcement required in the pile.
Use IS-456:2000 – Clause 39.4 (For axially loaded members)
Using this formula we can calculate the area of steel required in the pile.
Minimum reinforcement for the precast pile is mentioned in the IS 2911 Part-1
section 3. This has to follow the condition mentioned below.
The diameter and spacing of the same is chosen to impart adequate rigidity of
the reinforcing cage during its handling and installations.
The minimum diameter ≥ 8 mm and the spacing ≥ 150 mm.
Stiffner rings – Minimum dia 16 mm at 1.5 m c/c.
After the reinforcement we also need to check the concrete which we are going to
use in pile.
These are the few points which we have to take care while doing concreting of piles:
In the steps which we have discussed above we have calculated the material needed
to cast the pile. As you know casting of pile is also very difficult hence we need to
take measures about this also.
The yellow arrow shows the load coming through the pier or columns. The pile can
distribute this load to the piles as shown in figure. The red line in the figure shows
the critical plane as shown in figure.
We generally assume the distribution of load is at 45∘ . Hence, our all calculations
are based on this philosophy as shown in the figure. We are going to use this
philosophy in the design of pile cap.
Geometry of pile cap of pile foundation
As we want to design the pile cap of the pile foundation we need to fix the geometry
of the pile cap.
These are the steps which helps you in fixing the geometry of the pile cap.
In this section we will see what are the parameters we need to check, for deciding
the thickness, reinforcement, development length etc. of pile cap.
Important criteria for pile cap design are as follows:
As we know that the reaction in the footing is coming only from the piles not from
the entire footing. We have to take care that whether the piles are inside the critical
section or outside the critical section.
So, again code solved this issue, according to clause 34.2.4.2 of IS-456:2000 it says:
You can also check the critical section for the bending or flexure action pile cap. The
critical section for the bending will be just at the face of the column. Which you can
see in the figure.
After identifying the critical sections for different types of actions we can calculate
the resistance provided by the particular section. To increase the resistance capacity
of the section now we can provide the reinforcement.
The figure below shows the strut and ties model of the load transfer mechanism.
Conclusion
In this article you have learned the following key points: