0% found this document useful (0 votes)
29 views13 pages

Design Steps of Pile Foundation - Eigenplus

The document discusses the various steps involved in designing a pile foundation. It covers selecting the relevant code, understanding the basic load transfer mechanism, designing the piles by calculating reinforcement and concrete requirements, designing the pile cap by determining geometry and thickness, and checking design criteria like shear and flexure.

Uploaded by

suchendra singh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
29 views13 pages

Design Steps of Pile Foundation - Eigenplus

The document discusses the various steps involved in designing a pile foundation. It covers selecting the relevant code, understanding the basic load transfer mechanism, designing the piles by calculating reinforcement and concrete requirements, designing the pile cap by determining geometry and thickness, and checking design criteria like shear and flexure.

Uploaded by

suchendra singh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 13

EIGENPLUS

Design steps of pile foundation


edited by Editorial Team | Structural Design

The design of a pile foundation is a tedious process. It involves lots of components to


be designed. Before this, we discussed different types of deep foundations and the
construction stages of pile construction. In this article, we will discuss the different
steps involved in the pile foundation design. We will also see the strut and ties model
of the load transfer mechanism of the pile foundation.

Relevant code for pile foundation


Pile foundation can be made of many materials. We have discussed in the previous
article of deep foundation we have seen the different types of material we can use to
construct the piles. In this article we will focus on the concrete pile and we will
discuss the design procedure of concrete piles.

Following Indian standard code can be referred to design the pile foundation:

IS code 2911-2010
Part-1 – concrete piles
Section-1 -Driven cast in situ concrete piles
Section-2 – Bored cast in situ concrete piles
Driven precast concrete piles (revised-2010)
Part 2 – timber piles
Part 3 – Under reamed piles
Part 4 – Load test on piles
These are the Indian standard code which we must have to follow while we are
designing the piles.

Basic design philosophy of the pile


Before designing pile we must have to understand the basic behaviour of the pile
foundation.

Before that lets discuss the basic components of the pile foundations. Please look
into the figure below. This figure shows the very basic elements of the pile
foundation. This is the case of bridges. Large compression columns of the bridge is
called piers. This pier is resting over the pile cap. This pile cap further transfer the
load to the four piles below the pile cap.

After getting the basic idea of the pile foundation its time to understand the
behaviour of the pile foundation. When you see the figure below you can understand
the load transfer mechanism in the pile foundation. The pier transfers the vertical
load to the pile cap. This pile cap finally distribute the load from the pier to the four
pile.
In the image below you can see the action of piles as column and the pile load
reaction diagram.
After this we now have to discuss the pile cap. The pile cap is acting like a slab
(which resist the load by bending action). Please refer the figure below to have a feel
about the pile cap behaviour.

Piles in detail
In this section we will see the components of pile in detail. Please refer the figure
below.

As you know we are discussing the concrete piles here. As the first step we make the
pile hole and than pour the the concrete with the reinforcements. We cast the pile
upto ground level.

Now after this we cut the some portion of the the concrete pile. The length upto
which we are removing the concrete we call it chipped off length as shown in figure.
After this we place the levelling course on lean concrete and then we tie the
reinforcement for the pile cap. After the reinforcement we place the shuttering and
then casting of pile cap.
Design of Piles
As the first step of the design we will design the piles. We have already discussed
that pile behave as the column. Hence we will design it as the column.

These are the following steps to design the pile:

Longitudinal reinforcement: In the first step we will see the how to calculate
the area of longitudinal reinforcement required in the pile.
Use IS-456:2000 – Clause 39.4 (For axially loaded members)

Pu = 0.4fck Ac + 0.67fy Asc

Where Pu is the axial load, fck is the characteristic compressive strength of


the concrete, Ac is the area of concrete, fy is the yield strength of steel, Asc is
the area of steel.

Using this formula we can calculate the area of steel required in the pile.

We have to keep eye on the minimum reinforcement mentioned by the IS code is


0.4% throught out the section (cast in situ). The number of bars are restricted to 6
and diameter of bar is 12 mm.

Minimum reinforcement for the precast pile is mentioned in the IS 2911 Part-1
section 3. This has to follow the condition mentioned below.

1.25% of cross section area for l < 30D .

1.50% of cross section area for 30D ≤ l ≤ 40D .

2.00% pf cross section area for l ≥ 40D .

After calculation of longitudinal reinforcement now we have to calculate the lateral


reinforcement.

Lateral reinforcement of pile


We have to keep following things in mind while providing the lateral reinforcement
in the pile.

The diameter and spacing of the same is chosen to impart adequate rigidity of
the reinforcing cage during its handling and installations.
The minimum diameter ≥ 8 mm and the spacing ≥ 150 mm.
Stiffner rings – Minimum dia 16 mm at 1.5 m c/c.

After the reinforcement we also need to check the concrete which we are going to
use in pile.

These are the few points which we have to take care while doing concreting of piles:

The slump should be 150 to 180 mm at the time of pouring.


The \textbf{minimum grade} of concrete – M25
Minimum cement content 400 kg/cum, never less than 350 kg/cum

In the steps which we have discussed above we have calculated the material needed
to cast the pile. As you know casting of pile is also very difficult hence we need to
take measures about this also.

These are the few points which we need to follow:


For vertical pile max angular deviation of 1.5% and for raker pile 4%.
Pile should not deviate more than 75 mm or D/6 (whichever is less).
For a single pile – 50 mm or D/6 (whichever is less) [100 mm for pile dia 600
mm ]

Design of pile cap


After designing the pile we need to design the pile cap. The pile caps are designed for
the bending action. The main function of the pile cap is to disburse the load coming
from the pier or column to the piles.

To understand this we please refer to the figure below.

The yellow arrow shows the load coming through the pier or columns. The pile can
distribute this load to the piles as shown in figure. The red line in the figure shows
the critical plane as shown in figure.

We generally assume the distribution of load is at 45∘ . Hence, our all calculations
are based on this philosophy as shown in the figure. We are going to use this
philosophy in the design of pile cap.
Geometry of pile cap of pile foundation
As we want to design the pile cap of the pile foundation we need to fix the geometry
of the pile cap.

For this following steps needs to be followed:

We need to calculate the spacing of the piles. In Clause 6.6 of IS 2911:2010,


section -1 of the part-1 we can get the specifications for the piles. Which says
as follows:
2.5 times diameter of piles if it is end bearing piles
3 times diameter of pile if it is friction pile
After the size of the pile next step is to decide about the grouping of the piles.
If you are providing the single pile then you can have to provide the grade
beams in two direction.
If you have more than 3 piles than pile head must be fixed.

These are the steps which helps you in fixing the geometry of the pile cap.

There are a few general criteria which you have to follow:

Design criteria is similar to IS 456


Rigid pile cap
Consequential moment
Cast over 75 mm thick levelling course of concrete
Clear cover shall not be less than 60 mm
Embedment of pile into cap should be 75 mm
Design of grade beam IS 2911 Part 3

How to decide thickness of pile cap?


As you can see in the previous sections we have decided the basic geometry of the
pile cap. We have also discussed the basic design considerations from IS-456:2000.

In this section we will see what are the parameters we need to check, for deciding
the thickness, reinforcement, development length etc. of pile cap.
Important criteria for pile cap design are as follows:

One way shear (Column load transfer)


Two way shear (Column load transfer)
One way shear (Pile reaction transfer)
Two way shear (Pile reaction transfer)
Load transfer from column to pile cap (development length)
Load transfer from pile to pile cap (development length)
Flexural action (flexural reinforcement)

We will see each criteria individually.

Oneway shear for column


We have to transfer the load coming from the column to ground through the pile
cap. As you can see in the figure below that the cross section of pile at a distance d
from the column face becomes the critical section for the one way shear check.

As we know that the reaction in the footing is coming only from the piles not from
the entire footing. We have to take care that whether the piles are inside the critical
section or outside the critical section.

So, again code solved this issue, according to clause 34.2.4.2 of IS-456:2000 it says:

Dp /2 outside this distance – entire pile reaction is taken into consideration,


where Dp is the diameter of the pile.
And for the other position we have to perform the linear interpolation as
shown in the figure.

Two shear for the column


When we consider the design for two-way shear the critical section will be as shown
is the figure. The area of the cross-section of the critical section bears the shear
force.
The second part of the figure shows the critical section for the two way shear in the
plan view. There are two loads one which is coming from the pier and one which is
coming from the pile. The critical section for the pile and pier both are shown in the
figure.

You can also check the critical section for the bending or flexure action pile cap. The
critical section for the bending will be just at the face of the column. Which you can
see in the figure.

After identifying the critical sections for different types of actions we can calculate
the resistance provided by the particular section. To increase the resistance capacity
of the section now we can provide the reinforcement.

Reinforcement in the pile caps


In this section, we will see the different types of reinforcement in the pile cap. The
figure below shows the reinforcement details of the pile cap. The bar coming from
the piers should be continued to bear the high shear force. Hence we provide the
development length Ld to the bars.
A clear overhang of 100 to 150 mm is generally provided in the pile cap as you can
see in the figure. The bottom reinforcement should be placed at the cover of 75 mm
to develop the bond length we need to provide the development length to these bars
also.

Strut and tie model for the load distribution of the


pile cap
Another theory of load distribution is the strut and tie model. If you recall our
previous discussion you can recall that the strut is the compression member. The
piers transfer the load through the strut and then the strut transfers the load to the
piles as shown in the figure. The piles take care of the vertical load of the strut, but
the horizontal component of the strut ties comes into the picture.

The figure below shows the strut and ties model of the load transfer mechanism.
Conclusion
In this article you have learned the following key points:

Design: We have also discussed the different steps involved in designing of


the pile.
One-way shear: We have discussed the area which resists the one-way shear
in the article.
Two-way shear: The two-way shear by pile and piers we have seen in the
article and also discussed the critical section responsible for this.
Strut and tie model: We have discussed the strut and tie model mechanism of
the load transfer in the pile.

You might also like