Dashboard Mom With Date
Dashboard Mom With Date
Date:- 30-04-2024
M/s Kansal Engineering, Derabassi M/s Mechwell Tools & Gauges Pvt. Ltd. Faridabad
1.) Mr. Ravi Kumar 1.) Mr. Ram Lalit Singh
2.) 2.) Mr. Lalit Kumar (Project)
3.) 3.) Mr. Dinesh (Project)
4.) 4.) Mr. Tara Chandra (D&D)
Sub :- 735 NSM Dashboard Assy (P10028700D) Weld Line Development Status
Child Parts Readiness
RM BOP Completion
S.No. Description Qty with Base Plate Assy CMM Responsibility Current Status Current Status pic
Procurement Procurement Target Date
Structure
1 OP-10 Manual Handy Jig LH for Strips 1 Done Done Done Done 01-05-2024 01-05-2024 Assy Done CMM in Process
2 OP-20 Manual Handy Jig RH for Strips 1 Done Done Done Done 01-05-2024 01-05-2024 Assy Done CMM in Process
7 Receiving Gauge (Manual) 1 01-05-2024 05-05-2024 03-05-2024 07-05-2024 08-05-2024 10-05-2024 Raw Material not Available