Nasa02. NPR 7123.1c Se Proc&Reqr
Nasa02. NPR 7123.1c Se Proc&Reqr
Table of Contents
Preface
P.1 Purpose
P.2 Applicability
P.3 Authority
P.4 Applicable Documents and Forms
P.5 Measurement/Verification
P.6 Cancellation
Chapter 1. Introduction
1.1 Background
1.2 Framework for Systems Engineering Procedural Requirements
1.3 Guiding Principles of Technical Excellence
1.4 Framework for Systems Engineering Capability
1.5 Document Organization
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- TOC incorporated into a contract. This document is uncontrolled when printed. Check Page 1 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- TOC Page 2 of 142
Appendix A. Definitions
Appendix B. Acronyms
Appendix C. Reserved
Appendix D. Reserved
Appendix E. Technology Readiness Levels
Appendix F. Technical Work Product Maturity Terminology
Appendix G. Life-Cycle and Technical Review Entrance and
Success Criteria
Appendix H. Compliance Matrix for Programs/Projects
Appendix I. Standards and Handbooks List
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- TOC incorporated into a contract. This document is uncontrolled when printed. Check Page 2 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- TOC Page 3 of 142
Table of Tables
Table 5-1 - SE Work Product Maturity
Table G-1 - SRR Entrance and Success Criteria for Programs
Table G-2 - SDR Entrance and Success Criteria for Programs
Table G-3 - MCR Entrance and Success Criteria
Table G-4 - SRR Entrance and Success Criteria
Table G-5 - MDR/SDR Entrance and Success Criteria (Projects and Single-Project Program)
Table G-6 - PDR Entrance and Success Criteria
Table G-7 - CDR Entrance and Success Criteria
Table G-8 - PRR Entrance and Success Criteria
Table G-9 - SIR Entrance and Success Criteria
Table G-10 - TRR Entrance and Success Criteria
Table G-11 - SAR Entrance and Success Criteria
Table G-12 - ORR Entrance and Success Criteria
Table G-13 - MRR/FRR Entrance and Success Criteria
Table G-14 - PLAR Entrance and Success Criteria
Table G-15 - CERR Entrance and Success Criteria
Table G-16 - PFAR Entrance and Success Criteria
Table G-17 - DR Entrance and Success Criteria
Table G-18 - Disposal Readiness Review Entrance and Success Criteria
Table G-19 - Peer Review Entrance and Success Criteria
Table G-20 - PIR/PSR Entrance and Success Criteria
Table G-21 - DCR Entrance and Success Criteria
Table J-1 - Deleted Requirements and Justification
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- TOC incorporated into a contract. This document is uncontrolled when printed. Check Page 3 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- ChangeHistory Page 4 of 142
CHANGE HISTORY
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- incorporated into a contract. This document is uncontrolled when printed. Check Page 4 of 142
ChangeHistory the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Preface Page 5 of 142
Preface
P.1 Purpose
This document establishes the NASA processes and requirements for implementation of Systems
Engineering (SE) by programs/projects. NASA SE is a logical systems approach performed by
multidisciplinary teams to engineer and integrate NASA's systems to ensure NASA products meet
the customer's needs. Implementation of this systems approach will enhance NASA's core
engineering capabilities while improving safety, mission success, and affordability. This systems
approach is applied to all elements of a system (i.e., hardware, software, and human) and all
hierarchical levels of a system over the complete program/project life cycle.
P.2 Applicability
a. This NASA Procedural Requirement (NPR) applies to NASA Headquarters and NASA Centers,
including component facilities and technical and service support centers. This NPR applies to NASA
employees and NASA support contractors that use NASA processes to augment and support NASA
technical work. This NPR applies to the Jet Propulsion Laboratory (JPL), a Federally Funded
Research and Development Center, other contractors, grant recipients, or parties to agreements only
to the extent specified or referenced in the appropriate contracts, grants, or agreements. (See Chapter
4.)
b. This NPR applies to air and space flight, research and technology, information technology (IT),
and institutional programs and projects. Tailoring the requirements in this NPR and customizing
practices, based on criteria such as system/product size, complexity, criticality, acceptable risk
posture, and architectural level, is necessary and expected. See Section 2.2 for tailoring and
customizing descriptions. For IT programs and projects, see NPR 7120.7 for applicable SE tailoring.
c. In this document, projects are viewed as a specific investment with defined goals, objectives, and
requirements, with the majority containing a life-cycle cost, a beginning, and an end. Projects
normally yield new or revised products or services that directly address NASA strategic needs. They
are performed through a variety of means, such as wholly in-house, by Government, industry,
international or academic partnerships, or through contracts with private industry.
d. The requirements enumerated in this document are applicable to all new programs and projects, as
well as to all programs and projects currently in the Formulation Phase, as of the effective date of
this document. (See NPR 7120.5, NASA Space Flight Program and Project Management
Requirements; NPR 7120.7, NASA Information Technology and Institutional Infrastructure
Program and Project Management Requirements; or NPR 7120.8, NASA Research and Technology
Program and Project Management Requirements; for definitions of program phases.) This NPR also
applies to programs and projects in their Implementation Phase as of the effective date of this
document. For existing programs/projects regardless of their current phase, waivers or deviations
allowing continuation of current practices that do not comply with one or more requirements of this
NPR, may be granted using the Center's Engineering Technical Authority (ETA) Process.
e. Many other discipline areas perform functions during the program/project life cycle and influence
or are influenced by the engineering functions performed and, therefore, need to be fully integrated
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Preface incorporated into a contract. This document is uncontrolled when printed. Check Page 5 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Preface Page 6 of 142
into the SE processes. These discipline areas include but are not limited to health and medical,
safety, reliability, maintainability, quality assurance, IT, cybersecurity, logistics, operations,
training, human system integration, planetary protection, and environmental protection. The
description of these disciplines and their relationship to the overall program/project management
life-cycle are defined in other NASA directives; for example, the safety, reliability, maintainability,
and quality assurance requirements and standards are defined in the Office of Safety Mission
Assurance (OSMA) directives and standards, and health and medical requirements are defined in the
Office of the Chief Health and Medical Officer (OCHMO) directives and standards. For example,
see NASA-STD-3001, NASA Space Flight Human System Standard Volume 1 and Volume 2, and
NPR 8705.2, Human-Rating Requirements for Space Systems.
f. In this NPR, all mandatory actions (i.e., requirements) are denoted by statements containing the
term "shall." The requirements are explicitly shown as [SE-XX] for clarity and tracking purposes as
indicated in Appendix H. The terms "may" or "can" denote discretionary privilege or permission,
"should" denotes a good practice and is recommended but not required, "will" denotes expected
outcome, and "are/is" denotes descriptive material.
g. In this NPR, all document citations are assumed to be the latest version, unless otherwise noted.
P.3 Authority
a. National Aeronautics and Space Act, 51 U.S.C. § 20113(a).
b. NPD 1000.0, NASA Governance and Strategic Management Handbook.
c. NPD 1000.3, The NASA Organization.
d. NPD 1001.0, NASA Strategic Plan.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Preface incorporated into a contract. This document is uncontrolled when printed. Check Page 6 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Preface Page 7 of 142
P.5 Measurement/Verification
a. Compliance with this document is verified by the Office of the Chief Engineer by surveys, audits,
reviews, and/or reporting requirements.
b. Compliance, including tailoring, for programs and projects is documented by appending a
completed Compliance Matrix for Programs/Projects (see Appendix H) to the Systems Engineering
Management Plan (SEMP) or other equivalent program/project documentation and by submitting the
review products and plans identified in this document to the responsible NASA officials at the
life-cycle and technical reviews. Programs and projects may substitute a matrix that documents
compliance with their particular Center implementation of this NPR, if applicable.
P.6 Cancellation
NPR 7123.1B, NASA Systems Engineering Processes and Requirements, dated April 18, 2013.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Preface incorporated into a contract. This document is uncontrolled when printed. Check Page 7 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter1 Page 8 of 142
Chapter 1. Introduction
1.1 Background
1.1.1 Systems engineering at NASA requires the application of a systematic, disciplined engineering
approach that is quantifiable, recursive, iterative, and repeatable for the development, operation,
maintenance, and disposal of systems integrated into a whole throughout the life cycle of a project or
program. The emphasis of SE is on safely achieving stakeholder functional, physical, operational,
and performance (including human performance) requirements in the intended use environments
over the system's planned life within cost and schedule constraints.
1.1.2 This NPR complements the NASA policy requirements for the administration, management,
and review of all programs and projects, as specified in:
a. NPR 7120.5.
b. NPR 7120.7.
c. NPR 7120.8.
d. NPR 7150.2, NASA Software Engineering Requirements.
e. NPR 8590.1, Environmental Compliance and Restoration Program.
f. NPR 8820.2, Facility Project Requirements (FPR).
1.1.3 The processes described in this document build upon and apply best practices and lessons
learned from NASA, other governmental agencies, and industry to clearly delineate a successful
model to complete comprehensive technical work, reduce program and technical risk, and increase
the likelihood of mission success. The requirements established in this NPR should be tailored and
customized for criteria such as system/product size, complexity, criticality, acceptable risk posture,
architectural level, development plans, and schedule following the guidance of Section 2.2.
1.1.4 Precedence
The order of precedence in case of conflict between requirements is 51 U.S.C. § 20113(a)(1),
National Aeronautics and Space Act; NPD 1000.0, NASA Governance and Strategic Management
Handbook; NPD 1000.3, The NASA Organization; NPD 7120.4, NASA Engineering and
Program/Project Management Policy; and NPR 7123.1, NASA Systems Engineering Processes and
Requirements.
1.1.5 Figures
1.1.5.1 Figures within this NPR are informational.
how NASA does business and are independent of any particular program or project. These
requirements are issued by NASA Headquarters and by Center organizations and are normally
documented in NASA Policy Directives (NPDs), NASA Procedural Requirements (NPRs), NASA
Standards, Center Policy Directives (CPDs), Center Procedural Requirements (CPRs), and Mission
Directorate (MD) requirements. Figure 1-1 shows the flow down from NPD 1000.0 through
Program and Project Plans.
1.2.2 This NPR focuses on SE processes and requirements. It is one of several related Engineering
and Program/Project NPRs that flow down from NPD 7120.4, as shown in Figure 1-2.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter1 incorporated into a contract. This document is uncontrolled when printed. Check Page 9 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter1 Page 10 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter1 incorporated into a contract. This document is uncontrolled when printed. Check Page 10 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter1 Page 11 of 142
a. Clearly Documented Requirements, Policies, and Procedures. Given the complexity and
uniqueness of the systems that NASA develops and deploys, clear policies and procedures are
essential to mission success. All NASA technical policies and procedures flow directly from NPD
1000.0. Policies and procedures are only as effective as their implementation, facilitated by personal
and organizational accountability and effective training. OCE ensures policies and procedures are
consistent with and reinforce NASA's organizational beliefs and values. OCE puts in place effective,
clearly documented policies and procedures, supplemented by guidance in handbooks and standards
to facilitate optimal performance, rigor, and efficiency among NASA's technical workforce.
b. Effective Training and Development. NASA is fortunate that the importance of its mission
allows it to attract and retain the most capable technical workforce in the world. OCE bears
responsibility for providing this workforce with the technical training and development necessary to
carry out the Agency's missions. At the Agency level, NASA's Academy of Program/Project and
Engineering Leadership (APPEL) provides for the development of engineering leaders and teams
within NASA. APPEL is augmented by technical leadership development at many Centers. Training
consists of more than just transferring a set of skills. In addition to ensuring that NASA's technical
workforce is knowledgeable about standards, specifications, processes, and procedures, the training
available through APPEL and other curriculums is rooted in an engineering philosophy that grounds
NASA's approach to technical work and decision making. These offerings give historical and
philosophical perspectives that teach and reinforce NASA's organizational values and beliefs. OCE
provides full support for training and development activities that will allow NASA to maximize the
abilities of its technical workforce.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter1 incorporated into a contract. This document is uncontrolled when printed. Check Page 11 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter1 Page 12 of 142
c. Balancing Risk. Risk is an inherent factor in any spacecraft, aircraft, or technology development.
Proper risk management entails striking a balance between the tensions of program/project
management and engineering independence. Engineering rigor cannot be sacrificed for schedules
and budgets, and likewise programmatic concerns cannot be overlooked in the development of the
technical approach to a given program or project; technical risk will be consciously and deliberately
traded against budget and schedule. The Engineering Technical Authority (ETA) is responsible for
ensuring risks are considered and good engineering practices are followed in technical development
and implementation. OCE oversees all activities related to the exercise of ETA across the Agency.
Section 2.1.6 of this document contains additional information on the ETA responsibilities.
d. Continuous Communications. Communication lies at the heart of all leadership and
management challenges. Most major failures in NASA's history have stemmed in part from poor
communication. Among the Agency's technical workforce, communication takes a myriad of forms:
continuous risk management (CRM)/risk-informed decision making (RIDM), data sharing,
knowledge management, knowledge sharing, dissemination of best practices and lessons learned,
and continuous learning to name but a few. The complexity of NASA's programs and projects
demands a rigorous culture of continuous and open communication that flourishes within the context
of policies and procedures and knowledge transfer, while empowering individuals at all levels to
raise concerns without fear of adverse consequences. OCE promotes a culture of continuous
communications.
1.3.2 Personal and organizational accountability and responsibility lay the foundation for technical
excellence.
a. Personal Accountability. Personal accountability means that each individual understands that he
or she is responsible for the success of the mission. Each person, regardless of position or area of
responsibility, contributes to success. What NASA does is so complex and interdependent that every
component needs to work for the Agency to be successful. All of those who constitute NASA's
technical community need to possess the knowledge and confidence to speak up when something is
amiss in their or anyone else's area of responsibility to ensure mission success.
b. Organizational Responsibility. NASA's technical organizations have a responsibility to provide
the proper training, tools, and environment for technical excellence. Providing the proper
environment for technical excellence means establishing regular and open communication so that
individuals feel comfortable exercising their personal responsibility. It also requires ensuring that
those who prefer to remain in the technical field (instead of management) have a satisfying and
rewarding career track (e.g., NASA Technical Fellows, ST/SL or GS-15 technical leads).
1.3.3 A central component of the environment for technical excellence is strengthening the SE
capability.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter1 incorporated into a contract. This document is uncontrolled when printed. Check Page 12 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter1 Page 13 of 142
Figure 1 4 - SE Framework
a. The common technical processes of this NPR provide what has to be done to engineer quality
system products and achieve mission success. These processes are applied to the integration of
hardware, software, and human systems as one integrated whole. This NPR describes the common
SE processes as well as standard concepts and terminology for consistent application and
communication of these processes across the Agency. This NPR, supplemented by
NASA/SP-2016-6105, NASA Systems Engineering Handbook, and endorsed SE standards, also
describes a structure for applying the common technical processes.
b. Tools and methods range from the facilities and resources necessary to perform the technical
work to the clearly documented policies, processes, and procedures that allow personnel to work
safely and efficiently. Tools and methods enable the efficient and effective completion of the
activities and tasks of the common technical processes. The SE capability is strengthened through
the infusion of advanced methods and tools into the common technical processes to achieve greater
efficiency, collaboration, and communication among distributed teams. The NASA Systems
Engineering Handbook is a resource for methods and tools to support the Centers' implementation of
the required technical processes in their program/projects.
c. A well-trained, knowledgeable, and experienced technical workforce is essential for
improving SE capability. The workforce will be able to apply NASA and Center tools and methods
for the completion of the required SE processes within the context of the program or project to which
they are assigned. In addition, they will be able to effectively communicate requirements and
solutions to customers, other engineers, and management to work efficiently and effectively on a
team. Issues of recruitment, retention, and training are aspects included in this element. The OCE
will facilitate training the NASA workforce on the application of this and associated NPRs.
1.4.2 Improvements to SE capability can be measured through assessing and updating the
implementation of the common technical processes, use of adopted methods and tools, and
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter1 incorporated into a contract. This document is uncontrolled when printed. Check Page 13 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter1 Page 14 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter1 incorporated into a contract. This document is uncontrolled when printed. Check Page 14 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter2 Page 15 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter2 incorporated into a contract. This document is uncontrolled when printed. Check Page 15 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter2 Page 16 of 142
2.1.3.3 The Office of the Chief Information Officer provides leadership, planning, policy direction,
and oversight for the management of NASA information and NASA information technology (IT).
2.1.4 Center Directors
2.1.4.1 The Center Director is responsible for establishing, developing, and maintaining the
Institutional Authority (e.g., processes and procedures, human capital, facilities, and infrastructure)
required to execute programs and projects assigned to their Center. This includes:
a. Ensuring the Center is capable of accomplishing the programs, projects, and other activities
assigned to it in accordance with Agency policy and the Center's best practices and institutional
policies by establishing, developing, and maintaining institutional capabilities (processes and
procedures, human capital—including trained/certified program/project personnel, facilities, and
infrastructure) required for the execution of programs and projects.
b. Performing periodic program and project reviews to assess technical and programmatic progress
to ensure performance in accordance with their Center's and the Agency requirements, procedures,
processes, and other documentation.
c. Working with the Mission Directorate and the program and project managers, once assigned, to
assemble the program/project team(s) and to provide needed Center resources.
d. Providing support and guidance to programs and projects in resolving technical and programmatic
issues and risks.
2.1.4.2 The Center Director is responsible for developing the Center's ETA policies and practices
consistent with Agency policies and standards. The Center Director is the Center ETA responsible
for Center engineering design processes, specifications, rules, best practices, and other activities
necessary to fulfill mission performance requirements for programs, projects, and/or major systems
implemented by the Center. The Center Director delegates the Center ETA implementation
responsibility to an individual in the Center's engineering leadership. The Center ETA supports
processing changes to, and waivers or deviations from, requirements that are the responsibility of
the ETA. This includes all applicable Agency and Center engineering directives, requirements,
procedures, and standards.
Note: Centers may employ and tailor relevant government or industry standards that meet the
intent of the requirements established in this NPR to augment or serve as the basis for their
processes. A listing of endorsed technical standards is maintained on the NASA Technical
Standards System under "Endorsed Standards" https://standards.nasa.gov/endorsed_standards.
2.1.4.3 [SE-01] through [SE-05] deleted.
Note: Rather than resequence the remaining requirements, the original requirement numbering
was left intact in case Centers or other organizations refer to these requirement numbers in
their flow-down requirement documents. Appendix J is provided to account for the deleted
requirements. For each requirement that was deleted, the justification for its deletion is noted.
2.1.5 Technical Teams
2.1.5.1 Systems engineering is implemented by the technical team in accordance with the
program/project SEMP or other equivalent program/project documentation. The makeup and
organization of each technical team is the responsibility of each Center or program and includes all
the personnel required to implement the technical aspects of the program/project.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter2 incorporated into a contract. This document is uncontrolled when printed. Check Page 16 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter2 Page 17 of 142
2.1.5.2 The technical team, in conjunction with the Center's ETA, is responsible for completing the
compliance matrix in Appendix H, capturing any tailoring, and including it in the SEMP or other
equivalent program/project documentation.
2.1.5.3 For systems that contain software, the technical team ensures that software developed within
NASA, or acquired from other entities, complies with NPR 7150.2.
a. NPR 7150.2 elaborates on the requirements in NPR 7123.1 and determines the applicability of
requirements based on the Agency's software classification.
b. NPD 7120.4 contains additional Agency principles for the acquisition, development,
maintenance, and management of software.
2.1.5.4 The technical team ensures that human systems integration activities, products, planning, and
execution align with NASA/SP-2015-3709, Human Systems Integration (HSI) Practitioner's Guide.
2.1.6 Engineering Technical Authority
2.1.6.1 The ETA establishes and is responsible for the engineering design processes, specifications,
rules, best practices, and other activities necessary to fulfill programmatic mission performance
requirements. Centers delegate ETA to the level appropriate for the scope and size of the
program/project, which may be Center engineering leadership or individuals. When ETA is used in
this document, it refers generically to different levels of ETA.
2.1.6.2 ETAs or their delegates at the program or project level:
a. Serve as members of program or project control boards, change boards, and internal review
boards.
b. Work with the Center management and other TA personnel to ensure that the quality and integrity
of program or project processes, products, and standards of performance related to engineering,
SMA, and health and medical reflect the level of excellence expected by the Center and the TA
community.
c. Ensure that requests for waivers or deviations from ETA requirements are submitted to, and acted
on, by the appropriate level of ETA.
d. Assist the program or project in making risk-informed decisions that properly balance technical
merit, cost, schedule, and safety across the system.
e. Provide the program or project with the ETA view of matters based on their knowledge and
experience and raise needed dissenting opinions on decisions or actions. (See Dissenting Opinion
Sections of NPR 7120.5, NPR 7120.8, and NPR 7120.7.)
f. Serve as an effective part of NASA's overall system of checks and balances.
2.1.6.3 The ETA for the program or project leads and manages the system engineering activities.
(Note that these responsibilities can be delegated by the ETA to Chief Engineer or other personnel
as needed). A Center may have more than one engineering organization and delegates ETA to
different areas as needed. The ETA may be delegated as appropriate to the size, complexity, and
type of program/project. For example, ETA may be delegated to a line manager that is independent
of the project for smaller projects or to the CIO for purely IT projects.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter2 incorporated into a contract. This document is uncontrolled when printed. Check Page 17 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter2 Page 18 of 142
2.1.6.4 To support the program/project and maintain ETA independence and an effective check and
balance system, the ETA:
a. Will seek concurrence by the program/project manager when a program/project-level ETA is
appointed.
b. Cannot approve a request for a waiver or deviation from a non-technical derived requirement
established by a Programmatic Authority.
c. May approve a request for a waiver or deviation from a technical derived requirement if he/she
ensures that the appropriate independent Institutional Authority subject matter expert who is the
steward for the involved technology, has concurred in the decision to approve the requirement
waiver.
2.1.6.5 Although a limited number of individuals make up the ETA, their work is enabled by the
contributions of the program's or project's working-level engineers and other supporting personnel
(e.g., contracting officers). The working-level engineers do not have formally delegated Technical
Authority and consequently may not serve in an ETA capacity. These engineers perform the detailed
engineering and analysis for the program/project with guidance from their Center management
and/or lead discipline engineers and support from the Center engineering infrastructure. They
deliver the program/project products (e.g., hardware, software, designs, analysis, and technical
alternatives) that conform to applicable programmatic, Agency, and Center requirements. They are
responsible for raising issues to the program/project manager, Center engineering management,
and/or the program/project ETA and are a key resource for resolving these issues.
2.1.6.6 Requirement [SE-06] concerning SEMP approval was moved to Section 6.1.8.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter2 incorporated into a contract. This document is uncontrolled when printed. Check Page 18 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter2 Page 19 of 142
2.2.2.2 Technical teams under the guidance of the project ETA are encouraged to customize these
recommended SE practices so that the intent of the SE practice is being met in the most effective and
efficient manner. The results of this customization do not require waivers or deviations but should
be documented in the program/project SEMP or other equivalent program/project documentation.
2.2.3 Considerations for Tailoring or Customizing
Refer to NASA, SP-2016-6105 for examples of tailoring and customizing.
2.2.3.1 Considerations for tailoring or customizing should include but are not limited to:
a. Scope and visibility (e.g., organizations and partnerships involved, international agreements,
amount of effort required).
b. Risk tolerance and failure consequences.
c. System size, functionality, and complexity (e.g., human space flight/flagship science vs. subscale
technology demonstration).
d. Human involvement (e.g., human interfaces, critical crew (flight, ground) functions, interaction
with, and control/oversight of (semi-) autonomous systems).
e. Impact on Agency IT security and national security.
f. Impact on other systems.
g. Longevity.
h. Serviceability (both ground and in-flight).
i. Constraints (including cost, schedule, degree of insight/oversight permitted with partnerships or
international agreements).
j. Safety, quality, and mission assurance.
k. Current level of technology available.
l. Availability of industrial capacity.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter2 incorporated into a contract. This document is uncontrolled when printed. Check Page 19 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 20 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 20 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 21 of 142
3.1.5 The context in which the common technical processes are used is provided below: (Refer to
"The Common Technical Processes and the SE Engine" in NASA/SP-2016-6105 for further
information.)
3.1.5.1 The common technical processes are applied to each product layer to concurrently develop
the products that will satisfy the operational or mission functions of the system (end products) and
that will satisfy the life-cycle support functions of the system (enabling products). In this document,
a product layer is a horizontal slice of the product breakdown hierarchy and includes both the end
product and its associated enabling products. The enabling products facilitate the activities of system
design, product realization, operations and mission support, sustainment, and end-of-product-life
disposal or recycling by having the products and services available when needed.
3.1.5.2 The common technical processes are applied to design a system solution definition for each
product layer down and across each level of the system structure and to realize the product layer end
products up and across the system structure. Figure 3-2 illustrates how the three major sets of
processes of the Systems Engineering (SE) Engine (system design processes, product realization
processes, and technical management processes) are applied to each product layer within a system
structure.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 21 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 22 of 142
3.1.5.3 The common technical processes are used to define the product layers of the system structure
in each applicable phase of the relevant life-cycle to generate work products and system products
needed to satisfy the success criteria of the applicable phase. Figure 3-3 depicts the sequencing of
the processes.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 22 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 23 of 142
3.1.5.4 There are four system design processes applied to each product-based product layer from the
top to the bottom of the system structure:
a. Stakeholder Expectation Definition.
b. Technical Requirements Definition.
c. Logical Decomposition.
d. Design Solution Definition. (See Figure 3-1 and Figure 3-2.)
3.1.5.5 During the application of these four processes to a product layer, it is expected that there will
be a need to apply activities from other processes yet to be completed and to repeat process activities
already performed to arrive at an acceptable set of requirements and solutions. There also will be a
need to interact with the technical management processes to aid in identifying and resolving issues
and making decisions between alternatives. For software products, the technical team ensures that
the process executions comply with NPR 7150.2, software design requirements. The technical team
also ensures that human capabilities and limitations are understood and how those human
capabilities or limitations impact the hardware and software of any given system in terms of design.
Refer to NASA/SP-2015-3709.
3.1.5.6 There are five product realization processes. Four of the product realization processes are
applied to each end product of a product layer from the bottom to the top of the system structure:
a. Either Product Implementation for the lowest level or Product Integration for subsequent levels.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 23 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 24 of 142
b. Product Verification.
c. Product Validation.
d. Product Transition. (See Figure 3-1 and Figure 3-2.)
3.1.5.7 The form of the end product realized will depend on the applicable product life-cycle phase,
location within the system structure of the product layer containing the end product, and the success
criteria of the phase. Typical early phase products are reports, models, simulations, mockups,
prototypes, or demonstrators. Typical later phase products may take the form of qualification units,
final mission products, and fully assembled payloads and instruments.
3.1.5.8 There are eight technical management processes—Technical Planning, Technical
Requirements Management, Interface Management, Technical Risk Management, Configuration
Management, Technical Data Management, Technical Assessment, and Decision Analysis. (See
Figure 3-1 and Figure 3-2.) These technical management processes supplement the program and
project management directives (e.g., NPR 7120.5), which specify the technical activities for which
program and project managers are responsible.
3.1.5.9 Note that during the design and realization phases of a project, all 17 processes are used.
After the end product is developed and placed into operations the Technical Management processes
in the center chamber of the SE Engine will continue to be employed. For more information on the
use of the SE Engine during the operational phase, refer to NASA/SP-2016-6105.
3.1.5.10 The common technical processes are applied by assigned technical teams and individuals
trained in the requirements of this NPR.
3.1.5.11 The assigned technical teams and individuals use the appropriate and available sets of tools
and methods to accomplish required common technical process activities. This includes the use of
modeling and simulation as applicable to the product phase, location of the product layer in the
system structure, and the applicable phase success criteria.
3.1.6 Relationship of the SE Engine to the SE Vee.
The NASA SE Engine is a highly versatile representation of the core SE processes necessary to
properly engineer a system. It can be used for any type of life-cycle including waterfall, spiral, and
agile. It allows for use in very simple to highly complex systems. The NASA SE Engine had its
heritage in a classic SE Vee, and if being used for a simple one-pass waterfall-type life-cycle, the
right and left chambers of the engine can be represented as shown in Figure 3-4. For a more detailed
description of how the SE Engine evolved from the SE Vee, refer to the NASA Systems Engineering
Handbook.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 24 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 25 of 142
Figure 3-4 - SE Engine Implemented for a Simple Single-Pass Waterfall-Type Life Cycle
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 25 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 26 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 26 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 27 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 27 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 28 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 28 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 29 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 29 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 30 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 30 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 31 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 31 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter4 Page 32 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter4 incorporated into a contract. This document is uncontrolled when printed. Check Page 32 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter4 Page 33 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter4 incorporated into a contract. This document is uncontrolled when printed. Check Page 33 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter5 Page 34 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter5 incorporated into a contract. This document is uncontrolled when printed. Check Page 34 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter5 Page 35 of 142
Note: For example only. Refer to Figure 2-2 in NPR 7120.5 for the official life cycle. Table 2-3 reference in
Footnote 5 above is in NPR 7120.5.
Figure 5 1 - NASA Uncoupled and Loosely Coupled Program Life-Cycle
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter5 incorporated into a contract. This document is uncontrolled when printed. Check Page 35 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter5 Page 36 of 142
Note: For example only. Refer to Figure 2-3 in NPR 7120.5 for the official life cycle. Table 2-4 reference in
Footnote 5 above is in NPR 7120.5.
Figure 5-2 - NASA Tightly Coupled Program Life-Cycle
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter5 incorporated into a contract. This document is uncontrolled when printed. Check Page 36 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter5 Page 37 of 142
Note: For example only. Refer to Figure 2-4 in NPR 7120.5 for the official life cycle. Table 2-5 reference in
Footnote 5 above is in NPR 7120.5.
Figure 5-3 - NASA Single-Project Program Life-Cycle
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter5 incorporated into a contract. This document is uncontrolled when printed. Check Page 37 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter5 Page 38 of 142
Note: For example only. Refer to Figure 2-5 in NPR 7120.5 for the official life cycle. Table 2-5 reference in
Footnote 2 above is in NPR 7120.5.
Figure 5 4 - The NASA Project Life-Cycle
5.1.5 Life-cycle reviews are event based and occur when the entrance criteria for the applicable review are
satisfied. (Appendix G provides guidance.) They occur based on the maturity of the relevant technical
baseline as opposed to calendar milestones (e.g., the quarterly progress review, the yearly summary).
5.1.6 Accurate assessment of technology maturity is critical to technology advancement and its subsequent
incorporation into operational products. The program/project ensures that Technology Readiness Levels
(TRLs) and/or other measures of technology maturity are used to assess maturity throughout the life-cycle of
the program/project. When other measures of technology maturity are used, they should be mapped back to
TRLs. The definition of the TRLs for hardware and software are defined in Appendix E. Moving to higher
levels of technology maturity requires an assessment of a range of capabilities for design, analysis,
manufacture, and test. Measures for assessing technology maturity are described in NASA/SP-2016-6105.
The initial technology maturity assessment is done in the Formulation phase and updated at program/project
status reviews. The program/project approach for maturing and assessing technology is typically captured in
a Technology Development Plan, the SEMP, or other equivalent program/project documentation.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter5 incorporated into a contract. This document is uncontrolled when printed. Check Page 38 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter5 Page 39 of 142
5.2.1 Planning
5.2.1.1 The technical team shall develop and document plans for life-cycle and technical reviews for use in
the program/project planning process [SE-32].
5.2.1.2 The life-cycle and technical review schedule, as documented in the SEMP or other equivalent
program/project documentation, will be reflected in the overall program/project plan. The results of each
life-cycle and technical review will be used to update the technical review plan as part of the SEMP (or other
equivalent program/project documentation) update process. The review plans, data, and results should be
maintained and dispositioned as Federal Records.
5.2.1.3 The technical team ensures that system aspects interfacing with crew or human operators (e.g., users,
maintainers, assemblers, and ground support personnel) are included in all life-cycle and technical reviews
and that HSI requirements are implemented. Additional HSI guidance is provided in NASA/SP-2015-3709
and NASA/SP-2016-6105/SUPPL Expanded Guidance for NASA Systems Engineering Volumes 1 and 2.
5.2.1.4 The technical team ensures that system aspects represented or implemented in software are included
in all life-cycle and technical reviews and that all software review requirements are implemented. Software
review requirements are provided in NPR 7150.2, with guidance provided in NASA-HDBK-2203, NASA
Software Engineering Handbook.
5.2.1.5 The technical team shall participate in the life-cycle and technical reviews as indicated in the
governing program/project management NPR [SE-33]. Additional description of technical reviews is
provided in NASA/SP-2016-6105, NASA Systems Engineering Handbook and in NASA/SP-2014-3705,
NASA Spaceflight Program & Project Management Handbook. (For requirements on program and project
life cycles and management reviews, see the appropriate NPR, e.g., NPR 7120.5.)
5.2.2 Conduct
5.2.2.1 The technical team shall participate in the development of entrance and success criteria for each of
the respective reviews [SE-34]. The technical team should utilize the guidance defined in Appendix G as
well as Center best practices for defining entrance and success criteria.
5.2.2.2 The technical team shall provide the following minimum products at the associated life-cycle review,
at the indicated maturity level. If the associated life-cycle review is not held, the technical team will need to
seek a waiver or deviation to tailor these requirements. If the associated life-cycle review is held but
combined with other life-cycle reviews or resequenced, this is considered customization and therefore no
waiver is required (but approach should still be documented in the SEMP or Review Plan for clarity).
a. Mission Concept Review (MCR):
(1) Baselined stakeholder identification and expectation definitions [SE-35].
(2) Baselined concept definition [SE-36].
(3) Approved MOE definition [SE-37].
b. System Requirements Review (SRR):
(1) Baselined SEMP (or other equivalent program/project documentation) for projects, single-project
programs, and one-step AO programs [SE-38].
(2) Baselined requirements [SE-39].
c. Mission Definition Review/System Definition Review (MDR/SDR):
(1) Approved TPM definitions [SE-40].
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter5 incorporated into a contract. This document is uncontrolled when printed. Check Page 39 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter5 Page 40 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter5 incorporated into a contract. This document is uncontrolled when printed. Check Page 40 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter5 Page 41 of 142
in Appendix F.
5.2.2.6 The technical team ensures that each program or project hosting equipment, experiments, or payloads
with radio frequency (RF) requirements include success criteria in all life-cycle and technical reviews to
receive approval from the responsible Center spectrum manager that program or project spectrum goals and
progress are being achieved and satisfy all spectrum regulatory requirements. Spectrum certification
requirements are provided in NPD 2570.5 and NPR 2570.1, NASA Radio Frequency (RF) Spectrum
Management Manual. NPR 2570.1 takes precedence over this document regarding spectrum related
procedures and processes.
Table 5-1 - SE Work Product Maturity
2 For uncoupled, tightly coupled, loosely coupled programs, and two-step AO programs.
5.2.2.7 Technical teams shall monitor technical effort through periodic technical reviews [SE-57].
5.2.2.8 For each type of program/project, technical efforts are monitored throughout the life- cycle to ensure
that the technical goals of the program/project are being achieved and that the technical direction of the
program/project is appropriate.
5.2.2.9 A technical review is an evaluation of the program/project, or element thereof, by the technical team
and other knowledgeable participants for the purposes of:
a. Assessing the status of and progress toward accomplishing the planned activities.
b. Validating the technical tradeoffs explored and design solutions proposed.
c. Identifying technical weaknesses or marginal design and potential problems (risks) and recommending
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter5 incorporated into a contract. This document is uncontrolled when printed. Check Page 41 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter5 Page 42 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter5 incorporated into a contract. This document is uncontrolled when printed. Check Page 42 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter6 Page 43 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter6 incorporated into a contract. This document is uncontrolled when printed. Check Page 43 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter6 Page 44 of 142
6.1.2 The SEMP is consistent with higher level SEMPs and the Program/Project Plan, allowing for
tailoring and customization. For example, a Project level SEMP would be consistent with the
Program level SEMP and the Project Plan.
6.1.3 The content of a SEMP for an in-house technical effort may differ from an external technical
effort. For an external technical effort, the NASA SEMP should include details on developing
requirements for source selection, monitoring performance, and transferring and integrating
externally produced products to NASA. (See Appendix J of NASA/SP-2016-6105 for further
details.)
6.1.4 The NASA SEMP also provides the basis for determining the required contractor's
documentation specifying their SE approach to the scope of activities described by the 17 common
technical processes (See Section 4.2.3).
6.1.5 The ETA shall approve the SEMP, waiver or deviation authorizations, and other key technical
documents to ensure independent assessment of technical content [SE-06].
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter6 incorporated into a contract. This document is uncontrolled when printed. Check Page 44 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter6 Page 45 of 142
6.2.7 The technical team shall report the TPMs to the Program/Project Manager on an agreed-to
reporting interval [SE-61].
6.2.8 A technical leading indicator is a subset of the TPMs that provides insight into the potential
future states. The technical team shall ensure that the set of TPMs include the following leading
indicators:
a. Mass margins for projects involving hardware [SE-62].
b. Power margins for projects that are powered [SE-63].
6.2.9 The technical team shall ensure that a set of review trends is created and maintained that
includes closure of review action documentation (RIDs, RFAs, and/or Action Items as established
by the project [SE-64].
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter6 incorporated into a contract. This document is uncontrolled when printed. Check Page 45 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 46 of 142
Appendix A. Definitions
Acceptable Risk: The risk that is understood and agreed to by the program/project, governing PMC,
Mission Directorate, and other customers such that no further specific mitigating action is required.
(Some mitigating actions might have already occurred.)
Activity: A set of tasks that describe the technical effort to accomplish a process and help generate
expected outcomes.
Affordability: The practice of balancing system performance and risk with cost and schedule
constraints over the system life, satisfying system operational needs in concert with strategic
investment and evolving stakeholder value.
Approve (with respect to Technology Maturation Products from Appendix F): Used for a
product, such as Concept Documentation, that is not expected to be put under classic configuration
control but still requires that changes from the “approved” version are documented at each
subsequent “update.”
Baseline: An agreed-to set of requirements, designs, or documents that will have changes controlled
through a formal approval and monitoring process.
Baseline (with respect to Technology Maturation Products from Appendix F): Indicates putting
the product under configuration control so that changes can be tracked, approved, and
communicated to the team and any relevant stakeholders. The expectation on products labeled
“baseline” is that they will be at least final drafts going into the designated review and baselined
coming out of the review. Baselining a product does not necessarily imply that it is fully mature at
that point in the life-cycle. Updates to baselined documents require the same formal approval
process as the original baseline.
Bidirectional Traceability: The ability to trace any given requirement/expectation to its parent
requirement/expectation and to its allocated children requirements/expectations.
Brassboard: A medium fidelity functional unit that typically tries to make use of as much of the
final product as possible and begins to address scaling issues associated with the operational system.
It does not have the engineering pedigree in all aspects but is structured to be able to operate in
simulated operational environments in order to assess performance of critical functions
Breadboard: A low fidelity unit that demonstrates function only, without respect to form or fit. It
often uses commercial and/or ad hoc components and is not intended to provide definitive
information regarding operational performance.
Certification Package: The body of evidence that results from the verification activities and other
activities such as reports, special forms, models, waivers, or other supporting documentation that is
evaluated to indicate the design is certified for flight/use.
Component Facilities: Complexes that are geographically separated from the NASA Center or
institution to which they are assigned but are still part of the Agency.
Concept of Operations (ConOps): Developed early in Pre-Phase A, describes the overall
high-level concept of how the system will be used to meet stakeholder expectations, usually in a
time sequenced manner. It describes the system from an operational perspective and helps facilitate
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 46 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 47 of 142
time sequenced manner. It describes the system from an operational perspective and helps facilitate
an understanding of the system goals. It stimulates the development of the requirements and
architecture related to the user elements of the system. It serves as the basis for subsequent definition
documents and provides the foundation for the long-range operational planning activities (for
nominal and contingency operations). It provides the criteria for the validation of the system. In
cases where an Operations Concept (OpsCon) is developed, the ConOps feeds into the OpsCon and
they evolve together. The ConOps becomes part of the Concept Documentation.
Construction of Facilities: A NASA corporate program that funds planning for future facility
needs, design of facilities projects, revitalization projects (repair, rehabilitation, and modification of
existing facilities), construction of new facilities, and acquisition of collateral equipment.
Contractor: For the purposes of this NPR, an individual, partnership, company, corporation,
association, or other service having a contract with the Agency for the design, development,
manufacture, maintenance, modification, operation, or supply of items or services under the terms of
a contract to a program or project within the scope of this NPR. Research grantees, research
contractors, and research subcontractors are excluded from this definition.
Corrective Action: Action taken on a product to correct and preclude recurrence of a failure or
anomaly, e.g., design change, procedure change, personnel training.
Critical Event: An event in the operations phase of the mission that is time sensitive and is required
to be accomplished successfully in order to achieve mission success. These events will be
considered early in the life-cycle as drivers for system design.
Customer: The organization or individual that has requested a product and will receive the product
to be delivered. The customer may be an end user of the product, the acquiring agent for the end
user, or the requestor of the work products from a technical effort. Each product within the system
hierarchy has a customer.
Customizing: The modification of recommended SE practices that are used to accomplish the SE
requirements. Examples of these practices are in NASA/SP-2016-6105.
Decision Authority: The individual authorized by the Agency to make important decisions for
programs and projects under their authority.
Derived Requirements: Requirements arising from constraints, consideration of issues implied but
not explicitly stated in the high-level direction provided by Agency and Center institutional
requirements or factors introduced by the selected architecture and design.
Deviation: A documented authorization releasing a program or project from meeting a requirement
before the requirement is put under configuration control at the level the requirement will be
implemented.
Documentation: Captured information and its support medium that is suitable to be placed under
configuration control. Note that the medium may be paper, photograph, electronic storage (digital
documents and models), or a combination thereof.
Enabling Products: The life-cycle support products and services (e.g., production, test,
deployment, training, maintenance, and disposal) that facilitate the progression and use of the
operational end product through its life-cycle. Since the end product and its enabling products are
interdependent, they are viewed as a system. Program/project responsibility thus extends to
responsibility for acquiring services from the relevant enabling products in each life-cycle phase.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 47 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 48 of 142
responsibility for acquiring services from the relevant enabling products in each life-cycle phase.
When a suitable enabling product does not already exist, the program/project that is responsible for
the end product can also be responsible for creating and using the enabling product. An example is
below in Figure A-1.
Engineering Technical Authority: One of the three identified lines of technical authority (i.e.,
Engineering, Safety and Mission Assurance, and Health and Medical). ETA includes individuals
who have been formally delegated Technical Authority that flows from the Administrator to the
NASA Chief Engineer and to the Center Directors for further delegation to Center engineering
leadership and individuals. These individuals are funded independent from a program or project and
are a key part of NASA’s system of checks and balances that provides independent oversight of
programs and projects in support of safety and mission success. The ETA establishes and is
responsible for the engineering processes, specifications, rules, best practices, and other activities
throughout the life-cycle, necessary to fulfill programmatic mission performance requirements. The
ETA for the program or project leads and manages the engineering activities, including systems
engineering, design, development, sustaining engineering, and operations.
Engineering Unit: A high fidelity unit that demonstrates critical aspects of the engineering
processes involved in the development of the operational unit. Engineering test units are intended to
closely resemble the final product (hardware/software) to the maximum extent possible and are built
and tested so as to establish confidence that the design will function in the expected environments. In
some cases, the engineering unit can become the final product, assuming proper traceability has
been exercised over the components and hardware handling.
Entrance Criteria: Guidance for minimum accomplishments the program or project fulfills prior to
a life-cycle review.
Expectation: A statement of needs, desires, capabilities, and wants that are not expressed as a
requirement (not expressed as a “shall” statement). Once the set of expectations from applicable
stakeholders is collected, analyzed, and converted into a “shall” statement, the “expectation”
becomes a “requirement.” Expectations can be stated in either qualitative (non-measurable) or
quantitative (measurable) terms. Expectations can be stated in terms of functions, behaviors, or
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 48 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 49 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 49 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 50 of 142
information system owner (or common security controls owner for inherited controls) that provides
an overview of the security requirements for the system and describes the security controls in place
or planned for meeting those requirements. The plan can also contain as supporting appendices or as
references, other key security-related documents such as a risk assessment, privacy impact
assessment, system interconnection agreements, contingency plan, security configurations,
configuration management plan, and incident response plan.
Initial (with respect to Technology Maturation Products from Appendix F): Applied to
products that are continually developed and updated as the program or project matures.
Insight: An element of Government surveillance that monitors contractor compliance using
Government-identified metrics and contracted milestones. Insight is a continuum that can range
from low intensity, such as reviewing quarterly reports, to high intensity, such as performing surveys
and reviews.
Institutional Authority: Institutional Authority encompasses all those organizations and authorities
not in the Programmatic Authority. This includes Engineering, Safety and Mission Assurance, and
Health and Medical organizations; Mission Support organizations; and Center Directors.
Iterative: Application of a process to the same product or set of products to correct a discovered
discrepancy or other variation from requirements. (See Recursive and Repeatable.)
Joint Confidence Level: A process and product that helps inform management of the likelihood of
a project’s programmatic success. The probability that cost will be equal to or less than the targeted
cost and that schedule will be equal to or less than the targeted schedule date.
Key Decision Point (KDP): The event at which the Decision Authority determines the readiness of
a program/project to progress to the next phase of the life cycle (or to the next KDP).
Key Performance Parameters (KPP): Those capabilities or characteristics (typically
engineering-based or related to health and medical, safety, or operational performance) considered
most essential for successful mission accomplishment. Failure to meet a KPP threshold can be cause
for the program, project, system, or advanced technology development to be reevaluated or
terminated or for the system concept or the contributions of the individual systems to be reassessed.
A program/project’s KPPs are identified and quantified in the program/project baseline. (See
Technical Performance Parameter.)
Laboratory Environment: An environment that does not address in any manner the environment to
be encountered by the system, subsystem, or component (hardware or software) during its intended
operation. Tests in a laboratory environment are solely for the purpose of demonstrating the
underlying principles of technical performance (functions) without respect to the impact of
environment.
Leading Indicator: A measure for evaluating the effectiveness of how a specific activity is applied
on a program or project in a manner that provides information about impacts likely to affect the
system performance objectives. A leading indicator may be an individual measure or collection of
measures predictive of future system (and project) performance before the performance is realized.
The goal of the indicators is to provide insight into potential future states to allow management to
take action before problems are realized. A technical leading indicator is a subset of the Technical
Performance Measures (TPMs) that provides insight into the potential future states.
Logical Decomposition: The decomposition of the defined technical requirements by functions,
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 50 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 51 of 142
time, and behaviors to determine the appropriate set of logical and data architecture models and
related derived technical requirements. Models may include functional flow block diagrams,
timelines, data control flow, states and modes, behavior diagrams, operator tasks, system data,
metadata, data standards, taxonomy, and functional failure modes.
Loosely Coupled Programs: Programs that address specific objectives through multiple space
flight projects of varied scope. While each individual project has an assigned set of mission
objectives, architectural and technological synergies and strategies that benefit the program as a
whole are explored during the Formulation process. For instance, Mars orbiters designed for more
than one Mars year in orbit are required to carry a communication system to support present and
future landers.
Measure of Effectiveness (MOE): A measure by which a stakeholder’s expectations will be judged
in assessing satisfaction with products or systems produced and delivered in accordance with the
associated technical effort. An MOE is deemed to be critical to not only the acceptability of the
product by the stakeholder but also critical to operational/mission usage. An MOE is typically
qualitative in nature or not able to be used directly as a “design-to” requirement.
Measure of Performance (MOP): A quantitative measure that, when met by the design solution,
will help ensure that an MOE for a product or system will be satisfied. MOPs are given special
attention during design to ensure that the MOEs with which they are associated are met. There are
generally two or more measures of performance for each MOE.
Operational Environment: The environment in which the final product will be operated. In the
case of space flight hardware/software, it is space. In the case of ground-based or airborne systems
that are not directed toward space flight, it will be the environments defined by the scope of
operations. For software, the environment will be defined by the operational platform.
Operations Concept (OpsCon): Developed later in the life-cycle and baselined at PDR, a more
detailed description of how the flight system and the ground system are used together to ensure that
the concept of operation is reasonable. This might include how mission data of interest, such as
engineering data, scientific data, and data standards/metadata are captured, returned to Earth,
processed, made searchable, accessible, and available to users, and archived for future reference. The
OpsCon should describe how the flight system and ground system work together across mission
phases for planning, training, launch, cruise, critical activities, science observations, and end of
mission to achieve the mission. This product should be informed by the ConOps and they should
evolve together. They may exist as a single product or separate products.
Other Interested Parties: Groups or individuals that are not customers of a planned technical effort
but may be affected by the resulting product, the manner in which the product is realized or used, or
who have a responsibility for providing life-cycle support services. A subset of “stakeholders.” (See
Stakeholder.)
Oversight: An element of Government surveillance that occurs in line with the contractor’s
processes in which the Government retains and exercises the right to concur or non-concur with the
contractor’s decisions.
Peer Review: See Peer Review in Appendix G, Table G-19.
Preliminary (with respect to Technology Maturation Products from Appendix F): The
documentation of information as it stabilizes but before it goes under configuration control. It is the
initial development leading to a baseline. Some products will remain in a preliminary state for
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 51 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 52 of 142
multiple reviews. The initial preliminary version is likely to be updated at a subsequent review but
remains preliminary until baselined.
Process: A set of activities used to convert inputs into desired outputs to generate expected
outcomes and satisfy a purpose.
Product: A part of a system consisting of end products that perform operational functions and
enabling products that perform life-cycle services related to the end product or a result of the
technical efforts in the form of a work product (e.g., plan, baseline, or test result).
Product Layer: The end product is decomposed into a hierarchy of smaller and smaller products.
The product layer is defined as a horizontal slice of this product breakdown hierarchy and includes
both the end product and associated enabling products.
Product Realization: The act of making, buying, or reusing a product or the assembly and
integration of lower level realized products into a new product, as well as the verification and
validation that the product satisfies its appropriate set of requirements and the transition of the
product to its customer.
Program: A strategic investment by a Mission Directorate (or mission support office) that has
defined goals, objectives, architecture, funding level, and a management structure that supports one
or more projects.
Program Commitment Agreement: The contract between the Administrator and the cognizant
Mission Directorate Associate Administrator (MDAA) or Mission Support Office Directorate
(MSOD) Associate Administrator for implementation of a program.
Project: A specific investment having defined goals, objectives, requirements, life-cycle cost, a
beginning, and an end. A project yields new or revised products or services that directly address
NASA’s strategic needs. They may be performed wholly in-house; by Government, industry, or
academia partnerships; or through contracts with private industry.
Prototype Unit: The prototype unit demonstrates form, fit, and function at a scale deemed to be
representative of the final product operating in its operational environment. A subscale test article
provides fidelity sufficient to permit validation of analytical models capable of predicting the
behavior of full-scale systems in an operational environment.
Radio Frequency Authorization: Given by the National Telecommunications and Information
Administration (NTIA) for the use of radio frequency spectrum for radio transmissions for
telecommunications or for other purposes.
Realized Product: The desired output from application of the five Product Realization Processes.
The form of this product is dependent on the phase of the product life-cycle and the phase success
criteria.
Recursive: Value that is added to the system by the repeated application of processes to design next
lower layer system products or to realize next upper layer end products within the system structure.
This also applies to repeating application of the same processes to the system structure in the next
life-cycle phase to mature the system definition and satisfy phase success criteria.
Relevant Environment: Not all systems, subsystems, and/or components need to be operated in the
operational environment in order to satisfactorily address performance margin requirements.
Consequently, the relevant environment is the specific subset of the operational environment that is
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 52 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 53 of 142
required to demonstrate critical “at risk” aspects of the final product performance in an operational
environment. It is an environment that focuses specifically on “stressing” the technology advance in
question.
Relevant Stakeholder: A subset of the term “stakeholder” that applies to people or roles that are
designated in a plan for stakeholder involvement. Since “stakeholder” may describe a very large
number of people, attempting to deal with all of them might require unnecessary time and effort. For
this reason, “relevant stakeholder” is used in most practice statements to describe the people
identified to contribute to a specific task.
Repeatable: In the context of systems engineering, a repeatable process is a characteristic that can
be applied to products at any level of the system structure or within any life-cycle phase.
Request for Action/Review Item Discrepancy (RFA/RID): The most common names for the
comment forms that reviewers submit during life-cycle reviews that capture their comments,
concerns, and/or issues about the product or documentation. Each Center defines their own
RFA/RID disposition process.
Requirement: The agreed upon need, capability, capacity, or demand for personnel, equipment,
facilities, or other resources or services by specified quantities for specific periods of time or at a
specified time expressed as a “shall” statement. Acceptable form for a requirement statement is
individually clear, correct, feasible to obtain, unambiguous in meaning, and can be validated at the
level of the system structure at which stated. In pairs of requirement statements or as a set,
collectively, they are not redundant, are adequately related with respect to terms used, and are not in
conflict with one another.
Review Trends: Metrics that show how the identified life-cycle and technical reviews are
progressing such as tracking the closure of action items, RIDs, or RFAs throughout the life-cycle.
Risk: In the context of mission execution, the potential for performance shortfalls, which may be
realized in the future, with respect to achieving explicitly established and stated performance
requirements. The performance shortfalls may be related to any one or more of the following
mission execution domains: (1) safety, (2) technical, (3) cost, and (4) schedule. (See NPR 8000.4.)
Single Point Failure: An independent element of a system (hardware, software, or human), the
failure of which would result in loss of objectives, hardware, or crew.
Single-Project Programs: Programs that tend to have long development and/or operational
lifetimes, represent a large investment of Agency resources, and have contributions from multiple
organizations/agencies. These programs frequently combine program and project management
approaches, which they document through tailoring.
Software: In this directive, “software” is defined as (1) computer programs, procedures and possibly
associated documentation and data pertaining to the operation of a computer system; (2) all or a part
of the programs, procedures, rules, and associated documentation of an information processing
system; (3) program or set of programs used to run a computer; (4) all or part of the programs which
process or support the processing of digital information; (5) part of a product that is the computer
program or the set of computer programs software, and open-source software components. This
definition applies to software developed by NASA, software developed for NASA,
commercial-off-the-shelf (COTS) software, Government-off-the-shelf (GOTS) software,
modified-off-the-shelf (MOTS) software, reused software, auto-generated code, embedded software,
the software executed on processors embedded in Programmable Logic Devices (see
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 53 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 54 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 54 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 55 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 55 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 56 of 142
Technology Readiness Level: A scale against which to measure the maturity of a technology. TRLs
range from 1 (Basic Technology Research) to 9 (Systems Test, Launch, and Operations).
Tightly Coupled Programs: Programs with multiple projects that execute portions of a mission(s).
No single project is capable of implementing a complete mission. Typically, multiple NASA Centers
contribute to the program. Individual projects may be managed at different Centers. The program
may also include other agency or international partner contributions.
Transition: The act of delivery or moving a product from one location to another location. This act
can include packaging, handling, storing, moving, transporting, installing, and sustainment activities.
Uncoupled Programs: Programs implemented under a broad theme and/or a common program
implementation concept, such as providing frequent flight opportunities for cost-capped projects
selected through AO or NASA Research Announcements. Each such project is independent of the
other projects within the program.
Update (with respect to Technology Maturation Products from Appendix F): Applied to
products that are expected to evolve as the formulation and implementation processes evolve. Only
expected updates are indicated. However, any document may be updated as needed.
Validation (of a product): The process of showing proof that the product accomplishes the intended
purpose based on stakeholder expectations and the Concept of Operations. May be determined by a
combination of test, analysis, demonstration, and inspection. (Answers the question, “Am I building
the right product?”)
Validation (of requirements): The continuous process of ensuring that requirements are
well-formed (clear and unambiguous), complete (agrees with customer and stakeholder needs and
expectations), consistent (conflict free), and individually verifiable and traceable to a higher level
requirement or goal. (Answers the question, “Will I build the right product?”)
Verification (of a product): Proof of compliance with requirements/specifications. Verification
may be determined by test, analysis, demonstration, inspection, or a combination thereof. (Answers
the question, “Did I build the product right?”)
Waiver: A documented authorization releasing a program or project from meeting a requirement
after the requirement is put under configuration control at the level the requirement will be
implemented.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 56 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixB Page 57 of 142
Appendix B. Acronyms
AO Announcement of Opportunity
APPEL Academy of Program/Project and Engineering Leadership
ASM Acquisition Strategy Meeting
CDR Critical Design Review
CERR Critical Event Readiness Review
CMMI Capability Maturity Model® IntegrationSM
ConOps Concept of Operations
COTS Commercial Off the Shelf
CPD Center Policy Directive
CPR Center Procedural Requirements
CPU Central Processing Unit
CRM Continuous Risk Management
DCR Design Certification Review
DR Decommissioning Review
DRR Disposal Readiness Review
EEE Electrical, Electronic, and Electromechanical
EMC Electromagnetic Compatibility
EMI Electromagnetic Interference
ETA Engineering Technical Authority
FA Formulation Agreement
FAD Formulation Authorization Document
FMEA/CIL Failure Mode and Effects Analysis/Critical Items List
FMECA Failure Mode, Effects, and Criticality Analysis
FRR Flight Readiness Review
GIDEP Government-Industry Data Exchange Program
GOTS Government Off-the-Shelf
HSI Human Systems Integration
HSIP Human Systems Integration Plan
ILSP Integrated Logistics Support Plan
IMS Integrated Master Schedule
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixB incorporated into a contract. This document is uncontrolled when printed. Check Page 57 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixB Page 58 of 142
IP Institutional Projects
IT Information Technology
JCL Joint Confidence Level
JPL Jet Propulsion Laboratory
KDP Key Decision Point
KPP Key Performance Parameter
LRR Launch Readiness Review
MCR Mission Concept Review
MD Mission Directorate
MDAA Mission Directorate Associate Administrator
MDR Mission Definition Review
MOE Measure of Effectiveness
MOP Measure of Performance
MOTS Modified Off the Shelf
MRR Mission Readiness Review
MSD Mission Support Directorate
NODIS NASA On-Line Directives Information System
NPD NASA Policy Directive
NPR NASA Procedural Requirements
NTIA National Telecommunications and Information Administration
OCE Office of the Chief Engineer
OCHMO Office of the Chief Health and Medical Officer
OpsCon Operations Concept
ORR Operational Readiness Review
OSMA Office of Safety and Mission Assurance
PCA Program Commitment Agreement
PDR Preliminary Design Review
PFAR Post-Flight Assessment Review
PIR Program Implementation Review
PLAR Post-Launch Assessment Review
PM Program or Project Manager
PMC Program Management Committee
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixB incorporated into a contract. This document is uncontrolled when printed. Check Page 58 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixB Page 59 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixB incorporated into a contract. This document is uncontrolled when printed. Check Page 59 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixC Page 60 of 142
Appendix C. Reserved
Guidance for implementing the core SE processes has been moved to NASA/SP-2016-6105.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixC incorporated into a contract. This document is uncontrolled when printed. Check Page 60 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixD Page 61 of 142
Appendix D. Reserved
The outline for the Systems Engineering Management Plan has moved to Appendix J of
NASA/SP-2016-6105.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixD incorporated into a contract. This document is uncontrolled when printed. Check Page 61 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixE Page 62 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixE incorporated into a contract. This document is uncontrolled when printed. Check Page 62 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixE Page 63 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixE incorporated into a contract. This document is uncontrolled when printed. Check Page 63 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixE Page 64 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixE incorporated into a contract. This document is uncontrolled when printed. Check Page 64 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixE Page 65 of 142
operational
feasibility. Most
software bugs
removed. Limited
documentation
available.
Examples:
a. Mars Pathfinder Rover flight and operation on Mars as a technology demonstration
for future micro-rovers based on that system design.
b. First flight test of a new launch vehicle, which is a performance demonstration in the
operational environment. Design changes could follow as a result of the flight test.
c. In-space demonstration missions for technology (e.g., autonomous robotics and
deep space atomic clock). Successful flight demonstration could result in use of the
technology in a future operational mission
d. Robotic External Leak Locator (RELL): Originally flown as a technology
demonstrator, the test article was subsequently put to use to help operators locate the
likely spot where ammonia was leaking from the International Space Station (ISS)
External Active Thermal Control System Loop B.
8 Actual system The final product in All software has Documented test
completed and its final been thoroughly performance verifying
"flight qualified" configuration is debugged and fully analytical predictions.
through test and successfully integrated with all
demonstration. demonstrated operational
through test and hardware and
analysis for its software systems.
intended operational All user
environment and documentation,
platform (ground, training
airborne, or space). documentation, and
If necessary*, life maintenance
testing has been documentation
completed. completed. All
functionality
successfully
demonstrated in
simulated
operational
scenarios.
Verification and
Validation
completed.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixE incorporated into a contract. This document is uncontrolled when printed. Check Page 66 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixE Page 67 of 142
Note:
*"If necessary" refers to the need to life test either for worn out mechanisms, for
temperature stability over time, and for performance over time in extreme environments.
An evaluation on a case-by-case basis should be made to determine the system/systems
that warrant life testing and the tests begun early in the technology development process to
enable completion by TRL 8. It is preferable to have the technology life test initiated and
completed at the earliest possible stage in development. Some components may require
life testing on or after TRL 5.
Examples:
a. a. The level is reached when the final product is qualified for the operational
environment through test and analysis. Examples are when Cassini and Galileo were
qualified, but not yet flown.
b. b. Interim Cryo Propulsion Stage (ICPS): A Delta Cryogenic Second Stage modified
to meet Space Launch System requirements for Exploration Mission-1 (EM-1).
Qualified and accepted by NASA for flight on EM-1.
9 Actual system The final product is All software has Documented mission
flight proven successfully been thoroughly operational results.
through successful operated in an actual debugged and fully
mission operations. mission. integrated with all
operational
hardware and
software systems.
All documentation
has been
completed.
Sustaining software
support is in place.
System has been
successfully
operated in the
operational
environment.
Examples:
a. Flown spacecraft (e.g., Cassini, Hubble Space telescope).
b. Technologies flown in an operational environment.
c. Nanoracks CubeSat Deployer: Commercially developed and operated small satellite
deployer on-board the ISS.
Note: In cases of conflict between NASA directives concerning TRL definitions, NPR 7123.1 will
take precedence.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixE incorporated into a contract. This document is uncontrolled when printed. Check Page 67 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixF Page 68 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixF incorporated into a contract. This document is uncontrolled when printed. Check Page 68 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 69 of 142
1 Refer to any applicable NPRs, (e.g., NPR 7120.5, 7150.2, 8705.2) and table 5-1 in this document for required products. Refer to
NASA-HDBK-2203 section 7.8, if applicable, for guidance on software products.
Tailoring and customizing are expected for projects and programs. The entrance and success criteria
and products required for each review will be tailored and customized appropriately for the
particular program or project being reviewed. The decision not to tailor and customize life-cycle
review criteria should be justified to the ETA.
The recommended criteria in the following tables are focused on demonstrating acceptable
program/project technical maturity, adequacy of technical planning and credibility of budget,
schedule and risks (as applicable), and readiness to proceed to the next phase. Customized or tailored
criteria developed by programs or projects for life-cycle reviews should also be focused on assessing
these factors.
Programs and projects use different Appendix G tables for some life-cycle reviews. Programs
(except single-project programs) use tables G-1 and G-2 for program-level SRR and SDRs. Projects
and single-project programs use the tables starting with G-3.
G.1 System Requirements Review (SRR) for Programs
The SRR for a program is used to ensure that the program’s functional and performance
requirements are properly formulated and correlated with the Agency and Mission Directorate
strategic objectives.
Table G-1 – SRR Entrance and Success Criteria for Programs
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 69 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 70 of 142
a timely closure plan exists 3. The program cost and schedule estimates are
for those remaining open. credible to meet program requirements within
2. A preliminary Program available resources.
SRR agenda, success 4. Program implementation plans are credible to
criteria, and instructions to achieve mission success.
the review board have 5. The program risks have been identified and
been agreed to by the mitigation strategies appear reasonable.
technical team, the 6. Allocation of program requirements to projects has
program manager, and the been completed and proposed projects are feasible
review chair prior to the within available resources.
Program SRR. 7. The maturity of the program’s definition and
3. All planned higher level associated plans is sufficient to begin preliminary
SRRs and peer reviews design.
have been successfully 8. The program/project has demonstrated compliance
conducted and with applicable NASA and implementing Center
RID/RFA/Action Items requirements, standards, processes, and procedures.
have been addressed with 9. TBD and TBR items are clearly identified with
the originator or acceptable plans and schedules for their disposition.
designated TA. 10. Program has clearly identified plans and schedules
4. Programmatic products are for applicable RF system certification data package
ready for review at the submissions (experimental, developmental, or
maturity levels stated in operational).
the governing 11. Center spectrum manager at responsible Center was
program/project notified of preliminary requirement assessment.
management NPR.
5. Top program risks with
significant technical, health
and medical, safety, cost,
and schedule impacts have
been identified along with
corresponding mitigation
strategies.
6. An approach for verifying
compliance with program
requirements has been
defined.
7. Procedures for controlling
changes to program
requirements have been
defined and approved.
8. The following primary
products are ready for
review:
a. **Program
requirements
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 70 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 71 of 142
(including
performance, health
and medical, safety,
and defined external
system interfaces to
other programs) are
ready to be baselined
after review
comments are
incorporated.
b. **For single-project
programs and
one-step AO
programs, SEMP (or
equivalent program
documentation) is
ready to be baselined
after review
comments are
incorporated.
9. Other program SRR
technical products have
been made available to the
cognizant participants
prior to the review:
a. *Preliminary
traceability of
program-level
requirements on
projects to the
Agency strategic
goals and Mission
Directorate
requirements and
constraints.
b. *Initial risk
mitigation plans and
resources for
significant technical
risks.
c. *Preliminary cost
and schedule for
uncoupled, loosely
coupled, and tightly
coupled programs.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 71 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 72 of 142
d. *Preliminary
documentation of
Basis of Estimate
(cost and schedule)
for uncoupled,
loosely coupled, and
tightly coupled
programs.
e. *Review Plan ready
to be baselined after
review comments are
incorporated.
f. *Preliminary
Configuration
Management Plan.
g. *Preliminary SEMP
(or equivalent
program
documentation) for
uncoupled, loosely
coupled, tightly
coupled, and
two-step AO
programs.
h. ***RF (radio
frequency) spectrum
requirements have
been identified.
i. *Preliminary IT Plan.
*Product is required for programs/projects covered by NPR 7120.5. If there is disagreement between this table and NPR 7120.5,
NPR 7120.5 takes precedence.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 72 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 73 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 74 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 75 of 142
constraints.
b. *Traceability of
program-level
requirements on
projects to the
Agency strategic
goals and Mission
Directorate
requirements and
constraints that is
ready to be baselined
after review
comments are
incorporated.
c. Preliminary system
interface definitions.
d. Preliminary
implementation plans.
e. Preliminary
integration plans.
f. *Preliminary
verification and
validation plans.
g. *Updated cost and
schedule.
h. *Updated SEMP (or
equivalent program
documentation) for
one-step AO
programs and
single-project
programs.
i. *Updated risk
mitigation plans and
resources for
significant technical
risks.
j. *Updated cost and
schedule.
k. *Updated
Documentation of
Basis of Estimate
(cost and schedule).
l. *Preliminary plans
for technical work to
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 75 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 76 of 142
be accomplished
during
Implementation.
m. *Updated Review
Plan.
n. *Configuration
Management Plan
that is ready to be
baselined after
review comments are
incorporated.
o. ***Preliminary
assessment of RF
spectrum
requirements.
p. *Baseline IT Plan.
q. *Preliminary IT
System Security Plan.
*Product is required for programs/projects covered by NPR 7120.5. If there is disagreement between this table and NPR 7120.5,
NPR 7120.5 takes precedence.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 76 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 77 of 142
designated TA, or a timely 6. The cost and schedule estimates are credible and
closure plan exists for those sufficient resources are available for project
remaining open. formulation.
3. The following primary 7. The program/project has demonstrated
products are ready for review: compliance with applicable NASA and
a. **Stakeholders have implementing Center requirements, standards,
been identified and processes, and procedures.
stakeholder expectations 8. TBD and TBR items are clearly identified with
have been defined and acceptable plans and schedule for their
are ready to be disposition.
baselined after review 9. Alternative concepts have adequately considered
comments are the use of existing assets or products that could
incorporated. satisfy the mission or parts of the mission.
b. **The concept has been 10. Technical planning is sufficient to proceed to the
developed to a sufficient next phase and includes planning for hardware,
level of detail to software, human systems, and data deliverables.
demonstrate a 11. Risk and mitigation strategies have been
technically feasible identified and are acceptable based on technical
solution to the risk assessments.
mission/project needs 12. Software components meet the success criteria
and is ready to be defined in the NASA-HDBK-2203.
baselined after review 13. Concurrence by the responsible Center spectrum
comments are manager that RF needs have been properly
incorporated. identified and addressed.
c. **MOEs and any other
mission success criteria
have been defined and
are ready to be
approved.
4. Programmatic products are
ready for review at the
maturity levels stated in the
governing program/project
management NPR.
5. Other technical products (as
applicable) for hardware,
software, and human system
elements have been made
available to the cognizant
participants prior to the
review:
a. *Mission/project goals
and objectives that are
ready to be baselined
after review comments
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 77 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 78 of 142
are incorporated.
b. Alternative concepts
that have been analyzed
and are ready to be
reviewed.
c. *Initial risk-informed
cost and schedule
estimates for
implementation.
d. *Preliminary mission
descope options.
e. *A preliminary
assessment performed
by the team of top
technical, cost,
schedule, and safety
risks with developed
associated risk
management and
mitigation strategies and
options.
f. *Preliminary approach
to verification and
validation for the
selected concept(s).
g. *A preliminary SEMP
(or equivalent project
documentation),
including technical
plans.
h. *Technology
Development Plan that
is ready to be baselined
after review comments
are incorporated.
i. *Initial technology
readiness that has been
assessed and
documented with
technology assets,
heritage products, and
gaps identified.
j. Single Point
Failure/Fault Tolerance
philosophy.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 78 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 79 of 142
k. Preliminary engineering
development assessment
and technical plans to
achieve what needs to
be accomplished in the
next phase.
l. Conceptual life-cycle
support strategies
(logistics, supply chain
management,
manufacturing, and
operation).
m. Software criteria and
products, per
NASA-HDBK-2203.
n. ***Preliminary
assessment of RF
spectrum needs.
*Product is required for programs/projects covered by NPR 7120.5. If there is disagreement between this table and NPR 7120.5,
NPR 7120.5 takes precedence.
G.4 System Requirements Review (SRR) for Projects and Single-Project Programs
The SRR evaluates whether the functional and performance requirements defined for the system of
interest are responsive to the program’s requirements and ensures the preliminary project plan and
requirements will satisfy the mission. This table is used for projects and single-project programs. For
other types of programs, refer to Table G-1.
Table G-4 – SRR Entrance and Success Criteria
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 79 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 80 of 142
board have been agreed to the requirements definition at lower levels within
by the technical team, schedule constraints.
project manager, and review 4. System Interfaces with external entities and
chair prior to the SRR. between major internal elements have been
3. All planned higher level identified.
SRR and peer reviews have 5. Preliminary approaches have been determined for
been successfully conducted how requirements will be verified and validated.
and RID/RFA/Action Items 6. Major risks have been identified and technically
have been addressed and assessed, and viable mitigation strategies have
resolved with the originator been defined.
or designated TA, or a 7. The program/project has demonstrated compliance
timely closure plan exists for with applicable NASA and implementing Center
those remaining open. requirements, standards, processes, and
4. Programmatic products are procedures.
ready for review at the 8. TBD and TBR items are clearly identified with
maturity levels stated in the acceptable plans and schedule for their disposition.
governing program/project 9. Software components meet the success criteria
management NPR. defined in NASA-HDBK-2203.
5. The following primary 10. Concurrence by the responsible Center spectrum
technical products for manager that the program/project has provided
hardware, software and requisite RF system data.
human system elements are 11. Proposed tailoring is appropriate and consistent
available to the cognizant with applicable Agency and Center guidance.
participants prior to the 12. Lessons Learned from other projects and programs
review: have been identified and addressed.
a. **Requirements for 13. Single Point Failure/Fault Tolerance philosophy is
system being reviewed reflected in requirements.
are ready to be
baselined after the
review and
preliminary allocation
to the next lower level
system has been
performed.
b. **For projects,
one-step AO programs
and single-project
programs, the SEMP
(or equivalent
program/project
documentation) is
ready to be baselined
after review comments
are incorporated.
6. Other SRR work products
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 80 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 81 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 81 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 82 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 82 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 83 of 142
be accomplished in the
next phase.
w. Software criteria and
products, per the
NASA-HDBK-2203.
x. ***RF spectrum
requirements have
been addressed
including preparing
requisite data for the
responsible Center
Spectrum Manager for
possible Stage 1
Certification.
y. *Preliminary IT Plan.
a`. Product certification
or product acceptance
data requirements.
*Product is required for programs/projects covered by NPR 7120.5. If there is disagreement between this table and NPR 7120.5,
NPR 7120.5 takes precedence.
G.5 Mission Definition Review/System Definition Review (MDR/SDR) for Project and
Single-Project Programs
The MDR/SDR evaluates whether the proposed mission/system architecture is responsive to the
program mission/system functional and performance requirements and whether requirements have
been allocated to the next lower product layer and to all functional elements of the mission/system.
This table is to be used for projects and single-project programs.
Table G-5 – MDR/SDR Entrance and Success Criteria (Projects
and Single-Project Program)
Mission Definition Review/ System Definition Review for Projects and Single-Project
Programs
Entrance Criteria Success Criteria
1. The project has successfully 1. The proposed mission/system architecture is
completed the previously credible and responsive to program requirements
planned life-cycle reviews and constraints, including resources.
and all RFAs and RIDs have 2. The program/project cost and schedule estimates
been addressed and resolved, are credible to meet program/project
or a timely closure plan exists requirements within available resources with
for those items remaining acceptable risk.
open. 3. The project’s mission/system definition and
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 83 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 84 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 84 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 85 of 142
leading indicators,
margins, TPMs, and
resolution of the
previous review
discrepancies
addressing effectiveness
of technical
achievement and
communicating the
overall risk to the
project.
6. Other MDR/SDR technical
products listed below for both
hardware and software system
elements have been made
available to the cognizant
participants prior to the
review:
a. Supporting analyses,
functional/timing
descriptions, and
allocations of functions
to architecture elements.
b. *Updated SEMP (or
equivalent
program/project
documentation).
c. *Updated risk
management plan.
d. *Updated risk
assessment and
mitigations (if required
by the governing PM
NPR, including PRA).
e. *Updated Technology
Development Plan.
f. *Updated technology
readiness that has been
assessed and
documented with
technology assets,
heritage products, and
gaps identified.
g. *Updated cost and
schedule data with
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 85 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 86 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 86 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 87 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 87 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 88 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 88 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 89 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 89 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 90 of 142
assessments, GIDEP,
counterfeit avoidance).
a`. List of potential single point
failures.
*Product is required for programs/projects covered by NPR 7120.5. If there is disagreement between this table and NPR 7120.5,
NPR 7120.5 takes precedence.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 90 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 91 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 91 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 92 of 142
addressing
effectiveness of
technical achievement
and communicating
the overall risk to the
project.
e. Defined operational
limits and constraints.
f. Updated technical
resource utilization
estimates and margins.
g. Acceptance plans that
are ready to be
baselined after review
comments are
incorporated.
h. Command and
telemetry list.
i. *Updated verification
plan.
j. *Updated validation
plan.
k. Preliminary launch
site operations plan.
l. Preliminary checkout
and activation plan.
m. Preliminary disposal
plan (including
decommissioning or
termination).
n. *Updated technology
readiness assessment.
o. *Updated Technology
Development Plan.
p. *Updated risk
assessment and
mitigation.
q. Updated Human
Systems Integration
Plan (HSIP).
r. *Updated Human
Rating Certification
Package.
s. Updated reliability
analyses and
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 92 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 93 of 142
assessments.
t. *Updated Life-Cycle
Costs and IMS.
u. *Updated ILSP.
v. *Updated Project
Protection Plan.
w. Subsystem-level and
preliminary operations
safety analyses that are
ready to be baselined
after review comments
are incorporated.
x. Systems and
subsystem certification
plans and
requirements (as
needed) that are ready
to be baselined after
review comments are
incorporated.
y. *System safety
analysis with
associated
verifications that is
ready to be baselined
after review comments
are incorporated.
a`. Software criteria and
products, per
NASA-HDBK-2203.
aa. ***Received Stage 2
(Experimental) RF
system certification
signed by NTIA.
ab. ***Provided
measured/as-designed
parameter updates to
Center/facility
spectrum manager for
request for
certification of Stage 4
(Operational)
spectrum support no
later than 60 days
prior to CDR.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 93 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 94 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 94 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 95 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 95 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 96 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 97 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 98 of 142
and control.
Table G-10 – TRR Entrance and Success Criteria
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 99 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 100 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 100 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 101 of 142
documentation.
i. Updated risk
assessment and
mitigation.
j. Required safety,
shipping, handling,
checkout, and
operational plans and
procedures.
k. Software criteria and
products, per
NASA-HDBK-2203.
l. *Received Stage 4
(Operational) system
certification signed by
NTIA.
m. Completed planning for
sustaining the system.
n. Updated list of all
single point failures
and their effects.
*Required per NPD 2570.5.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 102 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 103 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 103 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 104 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 104 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 105 of 142
6. The following primary products are ready for processes, and procedures.
review: 7. TBD and TBR items are
a. **Final certification for flight/use. resolved.
b. **Baselined V&V results. 8. Open items and waivers have
7. Other MRR/FRR technical products have been been examined and residual
made available to the cognizant participants risk from these is deemed to be
prior to the review: acceptable.
a. *Updated cost. 9. The flight and recovery
b. *Updated schedule. environmental factors are
c. Updated as-built hardware and software within constraints.
documentation. 10. All open safety and mission
d. Updated operations procedures. risk items have been addressed,
e. Updated decommissioning plan. and the residual risk is deemed
f. Updated disposal plan acceptable.
g. Software criteria and products, per 11. Supporting organizations are
NASA-HDBK-2203. ready to support flight/mission
8. ***Received Stage 4 (Operational) system operations.
certification signed by NTIA. 12. Software components meet the
9. ***All requisite spectrum (radio frequency) success criteria defined in
authorizations are in place. NASA-HDBK-2203.
10. Updated list of all single point failures and their 13. Responsible Center spectrum
effects. manager(s) concur that all
necessary spectrum
certification(s) and
authorization(s) have been
obtained.
*Product is required for programs/projects covered by NPR 7120.5. If there is disagreement between this table and NPR 7120.5,
NPR 7120.5 takes precedence.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 105 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 106 of 142
1. The launch and early 1. The observed spacecraft and science payload performance
operations agrees with prediction, or if not, is adequately understood
performance, so that future behavior can be predicted with confidence.
including (when 2. All anomalies have been adequately documented and
appropriate) the early their impact on operations assessed. Further, anomalies
propulsive maneuver impacting spacecraft health and medical, safety, or
results, are available. critical flight operations have been properly dispositioned.
2. The observed 3. The mission operations capabilities, including staffing
spacecraft and and plans, are adequate to accommodate the actual flight
science instrument performance.
performance, 4. Open items, if any, on operations identified as part of the
including instrument ORR have been satisfactorily dispositioned.
calibration plans and 5. *Concurrence by the responsible Center spectrum
status, are available. manager that the system is compliant with spectrum
3. The launch vehicle policy and regulation.
performance
assessment and
mission implications,
including launch
sequence assessment
and launch
operations
experience with
lessons learned, are
completed.
4. The mission
operations and
ground data system
experience, including
tracking and data
acquisition support
and spacecraft
telemetry data
analysis, is available.
5. The mission
operations
organization,
including status of
staffing, facilities,
tools, and mission
software (e.g.,
spacecraft analysis
and sequencing), is
available.
6. In-flight anomalies
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 106 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 107 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 107 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 108 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 108 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 109 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 109 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 110 of 142
Decommissioning Review
Entrance Criteria Success Criteria
1. The requirements 1. The rationale for decommissioning is documented.
associated with 2. The decommissioning plan is complete, meets
decommissioning are requirements, is approved by appropriate
defined. management, and is compliant with applicable
2. Plans are in place for Agency safety, environmental, and health
decommissioning and any regulations.
other removal from service 3. Operations plans for decommissioning, including
activities. contingencies, are complete and approved.
3. Resources are in place to 4. Adequate resources (schedule, budget, and staffing)
support and implement have been identified and are available to
decommissioning. successfully complete all decommissioning
4. Programmatic products are activities.
ready for review at the 5. All required support systems for decommissioning
maturity levels stated in the are available.
governing program/project 6. All personnel have been properly trained for the
management NPR. nominal and contingency decommissioning
5. Health and medical, safety, procedures.
environmental, and any 7. Safety, health, and environmental hazards have
other constraints have been been identified, and controls have been verified.
identified. 8. Risks associated with the decommissioning have
6. Current system capabilities been identified and adequately mitigated.
relating to 9. Residual risks have been accepted by the required
decommissioning are management.
understood. 10. Any TBD and TBR items are clearly identified
7. Off-nominal operations, all with acceptable plans and schedule for their
contributing events, disposition.
conditions, and changes to 11. Plans for archival and subsequent analysis of
the originally expected mission data have been defined and approved, and
baseline have been arrangements have been finalized for the execution
considered and assessed. of such plans.
8. The following primary 12. Plans for the capture and dissemination of
product is ready for review: appropriate lessons learned during the project
a. **Updated life-cycle have been defined and approved.
Decommissioning 13. Plans for transition of personnel have been defined
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 110 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 111 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 111 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 112 of 142
Peer Review
Entrance Criteria Success Criteria
1. The product to be reviewed 1. Peer review has thoroughly evaluated the technical
(e.g., document, process, integrity and quality of the product.
model, design details) has 2. Any defects have been identified and characterized.
been identified and made 3. Results of the peer review are communicated to the
available to the review team. appropriate project personnel.
2. Peer reviewers independent 4. Spectrum-related aspects have been concurred to
from the project have been by the responsible Center spectrum manager.
selected for their technical
background related to the
product being reviewed.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 112 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 113 of 142
3. A preliminary agenda,
success criteria, and
instructions to the review
team have been agreed to
by the technical team and
project manager.
4. Rules have been
established to ensure
consistency among the
team members involved in
the peer review process.
5. *Spectrum (radio
frequency) considerations
addressed.
*Required per NPD 2570.5.
G.20 Program Implementation Reviews (PIR) and Program Status Reviews (PSR)
PIRs or PSRs are periodically conducted, as required by the Decision Authority and documented in
the program plan, during the Implementation phase to evaluate the program’s continuing relevance
to the Agency’s Strategic Plan. These reviews assess the program performance with respect to
expectations and determine the program’s ability to execute the implementation plan with acceptable
risk within cost and schedule constraints.
Table G-20 – PIR/PSR Entrance and Success Criteria
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 113 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 114 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 114 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 115 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 115 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 116 of 142
fabrication, and
maintenance
constraints are
documented.
i. Updated risk
assessment and
mitigation.
j. Waivers/deviations
affecting the
qualification articles,
procedures, or
environments.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 116 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 117 of 142
Req NPR
Requirement Statement Rationale Comply? Justification
ID Section
SE-01 Deleted See rationale in the
to 05 Deleted Requirements
Table J-1.
SE-06 6.1.8 The ETA shall approve the This requirement
SEMP, waiver or deviation ensures that the ETA
authorizations, and other has reviewed and
key technical documents to approved of key
ensure independent systems engineering
assessment of technical documents.
content.
SE- 07 3.2.2.1 Program/Project Managers This requirement
shall identify and ensures that the
implement an program/project and
ETA-approved Stakeholder the ETA identifies how
Expectations Definition they will gather and
process to include address stakeholder
activities, requirements, expectations. This
guidelines, and ensures that the
documentation, as tailored program/project will
and customized for the gain a thorough
definition of stakeholder understanding of what
expectations for the the customer and other
applicable product layer. stakeholders expect.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 117 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 118 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 118 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 119 of 142
each of the
program/projects will
be documented in the
SEMP or other
equivalent
program/project
documentation.
SE- 11 3.2.6.1 Program/Project Managers This requirement
shall identify and ensures that the
implement an program/project and
ETA-approved Product the ETA identifies how
Implementation process to they will execute the
include activities, designs, whether
requirements, guidelines, through buying items
and documentation, as off the shelf or
tailored and customized for contracting to have
implementation of a design them built,
solution definition by building/coding them
making, buying, or reusing within the Center, or
an end product of the reusing products
applicable product layer. already developed by
another
program/project. The
specifics for how each
program/project will
make this
determination for the
various
components/assemblies
within the product
hierarchy are
documented in the
SEMP or other
equivalent
program/project
documentation.
SE- 12 3.2.7.1 Program/Project Managers This requirement
shall identify and ensures that the
implement an program/project and
ETA-approved Product the ETA identifies how
Integration process to they will approach the
include activities, integration of products
requirements, guidelines, within successive
and documentation, as levels of the product
tailored and customized for hierarchy. This ensures
the integration of lower that planning is
level products into an end performed that will
product of the applicable enable a smooth
product layer in accordance integration of products
with its design solution into higher level
definition. assemblies.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 119 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 120 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 120 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 121 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 121 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 122 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 122 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 123 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 123 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 124 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 124 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 125 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 125 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 126 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 126 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 127 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 127 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 128 of 142
SE- 35 5.2.2.2.a The technical team shall For an MCR one of the
(1) provide the following key products is
minimum products at the capturing the
associated life-cycle review stakeholder
at the indicated maturity expectations. These
level: MCR: Baselined may be identified as
stakeholder identification needs, goals, and
and expectation definitions. objectives, or other
methods for capturing
their expectations.
These are captured in a
document or a
database/model. After
all comments from the
MCR are dispositioned,
the set of stakeholder
expectations are
updated with the
approved comments
and then baselined.
SE- 36 5.2.2.2. The technical team shall Presenting one or more
a provide the following feasible ways of
(2) minimum products at the accomplishing the
associated life-cycle review stakeholder
at the indicated maturity expectations is a key
level: MCR: Baselined product of the MCR.
concept definition. These are captured in a
document or a
database/model. After
all comments from the
MCR are dispositioned,
the concept(s) are
updated with the
approved comments
and then baselined.
SE- 37 5.2.2.2. The technical team shall The MOE capture the
a provide the following stakeholders’ view of
(3) minimum products at the what would be
associated life-cycle review considered the
at the indicated maturity successful achievement
level: MCR: Approved of each expectation.
Measures of Effectiveness These will help in the
(MOE) definition. later identification of
requirements, criteria
for trade studies and in
the success criteria for
the validation efforts.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 128 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 129 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 129 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 130 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 130 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 131 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 131 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 132 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 132 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 133 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 133 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 134 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 134 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 135 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 135 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 136 of 142
SE- 59 6.2.5 The technical team shall Since the SEMP is the
ensure that any technical primary planning
plans and discipline plans document for the SE
are consistent with the effort, all subsequent
SEMP (or equivalent planning documents are
program/project in alignment and
documentation) and are consistent with the
accomplished as fully SEMP.
integrated parts of the
technical effort.
SE- 60 6.2.6 The technical team shall The measures that the
establish TPMs for the program/project will
program/project that use to track the
track/describe the current progress of key aspects
state versus plan. of the technical effort
are identified and
documented. These
TPMs will include the
required leading
indicators described in
other requirements of
this NPR and also any
project-unique
measures deemed
necessary to track the
key performance
parameters.
SE- 61 6.2.7 The technical team shall The selected TPMs
report the TPMs to the need to be measured
Program/Project Manager periodically and their
on an agreed-to reporting trends reported to the
interval. program/project
manager at the
agreed-to interval as
documented in the
SEMP (or other
equivalent
program/project
documentation). This
ensures the PM and
ETA are kept up to
date on these key
parameters so that
decisions can be made
in a timely manner.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 136 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 137 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 137 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 138 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 138 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixI Page 139 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixI incorporated into a contract. This document is uncontrolled when printed. Check Page 139 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixJ Page 140 of 142
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixJ incorporated into a contract. This document is uncontrolled when printed. Check Page 140 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixJ Page 141 of 142
[SE-49] 5.2.1.7 The technical team shall Operational plans are optional and may be
provide the following minimum outside the purview of systems engineering
products at the associated milestone to develop.
review at the indicated maturity
level: g. ORR: (1) Updated
operational plans.
[SE-50] 5.2.1.7 The technical team shall Operational plans are optional and may be
provide the following minimum outside the purview of systems engineering
products at the associated milestone to develop.
review at the indicated maturity
level: g. ORR: (2) Updated
operational procedures.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixJ incorporated into a contract. This document is uncontrolled when printed. Check Page 141 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixK Page 142 of 142
Appendix K. References
The following documents were used as reference materials in the development of this SE NPR. The
documents are offered as informational sources and are not evoked in this NPR, though they may be
referenced.
1. NPD 7120.6, Knowledge Policy on Program and Projects.
2. NPD 8081.1, NASA Chemical Rocket Propulsion Testing.
3. NPD 8700.1, NASA Policy for Safety and Mission Success.
4. NPR 1400.1, NASA Directives and Charters Procedural Requirements.
5. NPR 2810.1, Security of Information Technology.
6. NPR 7120.10, Technical Standards for NASA Programs and Projects.
7. NPR 7120.11, NASA Health and Medical Technical Authority (HMTA) Implementation.
8. NPR 8705.4, Risk Classification for NASA Payloads.
9. NASA/SP-2010-3404, Work Breakdown Structure (WBS) Handbook.
10. NASA/SP-2014-3705, NASA Spaceflight Program & Project Management Handbook.
11. NASA-STD-7009, Standard for Models and Simulations.
12. MIL-STD-499B (draft), Systems Engineering.
13. ANSI/EIA 632, Processes for Engineering a System. Note: EIA 632 is a commercial document
that evolved from the never released, but fully developed, 1994 Mil-Std 499B, Systems
Engineering. It was intended to provide a framework for developing and supporting universal SE
discipline for both defense and commercial environments. EIA 632 was intended to be a top-tier
standard further defined to lower level standards that define specific practices. IEEE 1220 is a
second-tier standard that implements EIA 632 by defining one way to practice SE.
14. AS9100: Quality Management Systems—Requirements for Aviation, Space, and Defense
Organizations.
15. ISO/IEC 15288, Systems and Software Engineering—System Life-Cycle Processes.
16. ISO/IEC TR 19760, Systems Engineering—A Guide for the Application of ISO/IEC 15288
(System Life-Cycle Processes).
17. The Capability Maturity Model Integration (CMMI) ® Model.
18. Defense Acquisition University Systems Engineering Fundamentals. Ft. Belvoir, Virginia:
Defense Acquisition University Press, December 2000.
19. International Council on Systems Engineering Systems Engineering Guide.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixK incorporated into a contract. This document is uncontrolled when printed. Check Page 142 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.