0% found this document useful (0 votes)
187 views142 pages

Nasa02. NPR 7123.1c Se Proc&Reqr

Uploaded by

Ismail Cicek
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
187 views142 pages

Nasa02. NPR 7123.1c Se Proc&Reqr

Uploaded by

Ismail Cicek
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 142

NPR 7123.

1C -- TOC Page 1 of 142

| NODIS Library | Program Formulation(7000s) | Search |


NASA NPR 7123.1C
Effective Date: February 14,
Procedural 2020
Expiration Date: February 14,
Requirements 2025
COMPLIANCE IS MANDATORY FOR NASA EMPLOYEES

NASA Systems Engineering Processes and Requirements


(w/Change 2)
Responsible Office: Office of the Chief Engineer

Systems Engineering Handbook, Rev 2


eBook Systems Engineering Handbook, Rev 2
SE Expanded Guidance on Systems Engineering, Vol 1
SE Expanded Guidance on Systems Engineering, Vol 2

Table of Contents
Preface
P.1 Purpose
P.2 Applicability
P.3 Authority
P.4 Applicable Documents and Forms
P.5 Measurement/Verification
P.6 Cancellation

Chapter 1. Introduction
1.1 Background
1.2 Framework for Systems Engineering Procedural Requirements
1.3 Guiding Principles of Technical Excellence
1.4 Framework for Systems Engineering Capability
1.5 Document Organization

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- TOC incorporated into a contract. This document is uncontrolled when printed. Check Page 1 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- TOC Page 2 of 142

Chapter 2. Institutional and Programmatic Requirements


2.1 Roles and Responsibilities Relative to System Engineering Practices
2.2 Tailoring and Customizing

Chapter 3. Requirements for Common Technical Processes


3.1 Introduction
3.2 Common Technical Processes Requirements

Chapter 4. NASA Systems Engineering Activities on Contracted


Projects
4.1 Introduction
4.2 Prior to Contract Award
4.3 During Contract Performance
4.4 Contract Completion

Chapter 5. Systems Engineering Life-Cycle and Technical


Reviews
5.1 Life-Cycle
5.2 Life-Cycle and Technical Review Requirement

Chapter 6. Systems Engineering Management Plan


6.1 Systems Engineering Management Plan Function
6.2 Technical Team Responsibilities

Appendix A. Definitions
Appendix B. Acronyms
Appendix C. Reserved
Appendix D. Reserved
Appendix E. Technology Readiness Levels
Appendix F. Technical Work Product Maturity Terminology
Appendix G. Life-Cycle and Technical Review Entrance and
Success Criteria
Appendix H. Compliance Matrix for Programs/Projects
Appendix I. Standards and Handbooks List

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- TOC incorporated into a contract. This document is uncontrolled when printed. Check Page 2 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- TOC Page 3 of 142

Appendix J. Deleted Requirements


Appendix K. References
Table of Figures
Figure 1-1 - Hierarchy of Related Documents
Figure 1-2 - Documentation Relationships
Figure 1-3 - Technical Excellence - Pillars and Foundation
Figure 1 4 - SE Framework
Figure 3 1 - Systems Engineering (SE) Engine
Figure 3-2 - Application of SE Engine Common Technical Processes Within System Structure
Figure 3-3 - Sequencing of the Common Technical Processes
Figure 3-4 - SE Engine Implemented for a Simple Single-Pass Waterfall-Type Life Cycle
Figure 5 1 - NASA Uncoupled and Loosely Coupled Program Life Cycle
Figure 5-2 - NASA Tightly Coupled Program Life Cycle
Figure 5-3 - NASA Single-Project Program Life Cycle
Figure 5 4 - The NASA Project Life Cycle
Figure A-1 - Enabling Product Relationship to End Products

Table of Tables
Table 5-1 - SE Work Product Maturity
Table G-1 - SRR Entrance and Success Criteria for Programs
Table G-2 - SDR Entrance and Success Criteria for Programs
Table G-3 - MCR Entrance and Success Criteria
Table G-4 - SRR Entrance and Success Criteria
Table G-5 - MDR/SDR Entrance and Success Criteria (Projects and Single-Project Program)
Table G-6 - PDR Entrance and Success Criteria
Table G-7 - CDR Entrance and Success Criteria
Table G-8 - PRR Entrance and Success Criteria
Table G-9 - SIR Entrance and Success Criteria
Table G-10 - TRR Entrance and Success Criteria
Table G-11 - SAR Entrance and Success Criteria
Table G-12 - ORR Entrance and Success Criteria
Table G-13 - MRR/FRR Entrance and Success Criteria
Table G-14 - PLAR Entrance and Success Criteria
Table G-15 - CERR Entrance and Success Criteria
Table G-16 - PFAR Entrance and Success Criteria
Table G-17 - DR Entrance and Success Criteria
Table G-18 - Disposal Readiness Review Entrance and Success Criteria
Table G-19 - Peer Review Entrance and Success Criteria
Table G-20 - PIR/PSR Entrance and Success Criteria
Table G-21 - DCR Entrance and Success Criteria
Table J-1 - Deleted Requirements and Justification

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- TOC incorporated into a contract. This document is uncontrolled when printed. Check Page 3 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- ChangeHistory Page 4 of 142

CHANGE HISTORY

Chg# Date Description/Comments


1 01/19/2021 Updated with admin changes: Section 3.1.5.9 Editorial fix;
Section 5.2.2.4 Reference fix; Appendix A "Will" to "can"
in Engineering Unit definition; Appendix G Changes to
Table G-9; Success Criteria 7 and 8, Table G-12; Entrance
Criteria 9.d, and Table G-13, Entrance criteria 7.e
2 02/22/2022 Updated with admin changes: Appendix E, TRL, delete
example b. under TRL 2

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- incorporated into a contract. This document is uncontrolled when printed. Check Page 4 of 142
ChangeHistory the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Preface Page 5 of 142

Preface
P.1 Purpose
This document establishes the NASA processes and requirements for implementation of Systems
Engineering (SE) by programs/projects. NASA SE is a logical systems approach performed by
multidisciplinary teams to engineer and integrate NASA's systems to ensure NASA products meet
the customer's needs. Implementation of this systems approach will enhance NASA's core
engineering capabilities while improving safety, mission success, and affordability. This systems
approach is applied to all elements of a system (i.e., hardware, software, and human) and all
hierarchical levels of a system over the complete program/project life cycle.

P.2 Applicability
a. This NASA Procedural Requirement (NPR) applies to NASA Headquarters and NASA Centers,
including component facilities and technical and service support centers. This NPR applies to NASA
employees and NASA support contractors that use NASA processes to augment and support NASA
technical work. This NPR applies to the Jet Propulsion Laboratory (JPL), a Federally Funded
Research and Development Center, other contractors, grant recipients, or parties to agreements only
to the extent specified or referenced in the appropriate contracts, grants, or agreements. (See Chapter
4.)
b. This NPR applies to air and space flight, research and technology, information technology (IT),
and institutional programs and projects. Tailoring the requirements in this NPR and customizing
practices, based on criteria such as system/product size, complexity, criticality, acceptable risk
posture, and architectural level, is necessary and expected. See Section 2.2 for tailoring and
customizing descriptions. For IT programs and projects, see NPR 7120.7 for applicable SE tailoring.
c. In this document, projects are viewed as a specific investment with defined goals, objectives, and
requirements, with the majority containing a life-cycle cost, a beginning, and an end. Projects
normally yield new or revised products or services that directly address NASA strategic needs. They
are performed through a variety of means, such as wholly in-house, by Government, industry,
international or academic partnerships, or through contracts with private industry.
d. The requirements enumerated in this document are applicable to all new programs and projects, as
well as to all programs and projects currently in the Formulation Phase, as of the effective date of
this document. (See NPR 7120.5, NASA Space Flight Program and Project Management
Requirements; NPR 7120.7, NASA Information Technology and Institutional Infrastructure
Program and Project Management Requirements; or NPR 7120.8, NASA Research and Technology
Program and Project Management Requirements; for definitions of program phases.) This NPR also
applies to programs and projects in their Implementation Phase as of the effective date of this
document. For existing programs/projects regardless of their current phase, waivers or deviations
allowing continuation of current practices that do not comply with one or more requirements of this
NPR, may be granted using the Center's Engineering Technical Authority (ETA) Process.
e. Many other discipline areas perform functions during the program/project life cycle and influence
or are influenced by the engineering functions performed and, therefore, need to be fully integrated

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Preface incorporated into a contract. This document is uncontrolled when printed. Check Page 5 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Preface Page 6 of 142

into the SE processes. These discipline areas include but are not limited to health and medical,
safety, reliability, maintainability, quality assurance, IT, cybersecurity, logistics, operations,
training, human system integration, planetary protection, and environmental protection. The
description of these disciplines and their relationship to the overall program/project management
life-cycle are defined in other NASA directives; for example, the safety, reliability, maintainability,
and quality assurance requirements and standards are defined in the Office of Safety Mission
Assurance (OSMA) directives and standards, and health and medical requirements are defined in the
Office of the Chief Health and Medical Officer (OCHMO) directives and standards. For example,
see NASA-STD-3001, NASA Space Flight Human System Standard Volume 1 and Volume 2, and
NPR 8705.2, Human-Rating Requirements for Space Systems.
f. In this NPR, all mandatory actions (i.e., requirements) are denoted by statements containing the
term "shall." The requirements are explicitly shown as [SE-XX] for clarity and tracking purposes as
indicated in Appendix H. The terms "may" or "can" denote discretionary privilege or permission,
"should" denotes a good practice and is recommended but not required, "will" denotes expected
outcome, and "are/is" denotes descriptive material.
g. In this NPR, all document citations are assumed to be the latest version, unless otherwise noted.

P.3 Authority
a. National Aeronautics and Space Act, 51 U.S.C. § 20113(a).
b. NPD 1000.0, NASA Governance and Strategic Management Handbook.
c. NPD 1000.3, The NASA Organization.
d. NPD 1001.0, NASA Strategic Plan.

P.4 Applicable Documents and Forms


e. Government Contract Quality Assurance, 48 CFR, subpart 1846.4.
f. NPD 2570.5, NASA Electromagnetic Spectrum Management.
g. NPD 7120.4, NASA Engineering and Program/Project Management Policy.
h. NPR 1441.1, NASA Records Management Program Requirements.
i. NPR 2570.1, NASA Radio Frequency (RF) Spectrum Management Manual.
j. NPR 7120.5, NASA Space Flight Program and Project Management Requirements.
k. NPR 7120.7, NASA Information Technology and Institutional Infrastructure Program and Project
Management Requirements.
l. NPR 7120.8, NASA Research and Technology Program and Project Management Requirements.
m. NPR 7150.2, NASA Software Engineering Requirements.
n. NPR 8000.4, Agency Risk Management Procedural Requirements.
o. NPR 8590.1, Environmental Compliance and Restoration Program.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Preface incorporated into a contract. This document is uncontrolled when printed. Check Page 6 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Preface Page 7 of 142

p. NPR 8705.2, Human-Rating Requirements for Space Systems.


q. NPR 8705.5, Technical Probabilistic Risk Assessment (PRA) Procedures for Safety and Mission
Success for NASA Programs and Projects.
r. NPR 8820.2, Facility Project Requirements (FPR).
s. NASA-HDBK-2203, NASA Software Engineering Handbook.
t. NASA-STD-3001, NASA Space Flight Human System Standard.
u. NASA/SP-2010-576, NASA Risk-Informed Decision Making Handbook.
v. NASA/SP-2011-3422, NASA Risk Management Handbook.
w. NASA/SP-2015-3709, Human Systems Integration (HSI) Practitioner's Guide.
x. NASA/SP-2016-6105, NASA Systems Engineering Handbook.
y. NASA/SP-2016-6105-SUPPL, Expanded Guidance for NASA Systems Engineering.

P.5 Measurement/Verification
a. Compliance with this document is verified by the Office of the Chief Engineer by surveys, audits,
reviews, and/or reporting requirements.
b. Compliance, including tailoring, for programs and projects is documented by appending a
completed Compliance Matrix for Programs/Projects (see Appendix H) to the Systems Engineering
Management Plan (SEMP) or other equivalent program/project documentation and by submitting the
review products and plans identified in this document to the responsible NASA officials at the
life-cycle and technical reviews. Programs and projects may substitute a matrix that documents
compliance with their particular Center implementation of this NPR, if applicable.
P.6 Cancellation
NPR 7123.1B, NASA Systems Engineering Processes and Requirements, dated April 18, 2013.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Preface incorporated into a contract. This document is uncontrolled when printed. Check Page 7 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter1 Page 8 of 142

Chapter 1. Introduction
1.1 Background
1.1.1 Systems engineering at NASA requires the application of a systematic, disciplined engineering
approach that is quantifiable, recursive, iterative, and repeatable for the development, operation,
maintenance, and disposal of systems integrated into a whole throughout the life cycle of a project or
program. The emphasis of SE is on safely achieving stakeholder functional, physical, operational,
and performance (including human performance) requirements in the intended use environments
over the system's planned life within cost and schedule constraints.
1.1.2 This NPR complements the NASA policy requirements for the administration, management,
and review of all programs and projects, as specified in:
a. NPR 7120.5.
b. NPR 7120.7.
c. NPR 7120.8.
d. NPR 7150.2, NASA Software Engineering Requirements.
e. NPR 8590.1, Environmental Compliance and Restoration Program.
f. NPR 8820.2, Facility Project Requirements (FPR).
1.1.3 The processes described in this document build upon and apply best practices and lessons
learned from NASA, other governmental agencies, and industry to clearly delineate a successful
model to complete comprehensive technical work, reduce program and technical risk, and increase
the likelihood of mission success. The requirements established in this NPR should be tailored and
customized for criteria such as system/product size, complexity, criticality, acceptable risk posture,
architectural level, development plans, and schedule following the guidance of Section 2.2.
1.1.4 Precedence
The order of precedence in case of conflict between requirements is 51 U.S.C. § 20113(a)(1),
National Aeronautics and Space Act; NPD 1000.0, NASA Governance and Strategic Management
Handbook; NPD 1000.3, The NASA Organization; NPD 7120.4, NASA Engineering and
Program/Project Management Policy; and NPR 7123.1, NASA Systems Engineering Processes and
Requirements.
1.1.5 Figures
1.1.5.1 Figures within this NPR are informational.

1.2 Framework for Systems Engineering Procedural


Requirements
1.2.1 Institutional requirements are the responsibility of the institutional authorities. They focus on
how NASA does business and are independent of any particular program or project. These
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter1 incorporated into a contract. This document is uncontrolled when printed. Check Page 8 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter1 Page 9 of 142

how NASA does business and are independent of any particular program or project. These
requirements are issued by NASA Headquarters and by Center organizations and are normally
documented in NASA Policy Directives (NPDs), NASA Procedural Requirements (NPRs), NASA
Standards, Center Policy Directives (CPDs), Center Procedural Requirements (CPRs), and Mission
Directorate (MD) requirements. Figure 1-1 shows the flow down from NPD 1000.0 through
Program and Project Plans.

Figure 1-1 - Hierarchy of Related Documents

1.2.2 This NPR focuses on SE processes and requirements. It is one of several related Engineering
and Program/Project NPRs that flow down from NPD 7120.4, as shown in Figure 1-2.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter1 incorporated into a contract. This document is uncontrolled when printed. Check Page 9 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter1 Page 10 of 142

Figure 1-2 - Documentation Relationships

1.3 Guiding Principles of Technical Excellence


1.3.1 The Office of the Chief Engineer (OCE) provides leadership for technical excellence at NASA.
As depicted in Figure 1-3, there are four pillars to achieving technical excellence and strengthening
the SE capability. These pillars are intended to ensure that every NASA program and project meets
the highest possible technical excellence.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter1 incorporated into a contract. This document is uncontrolled when printed. Check Page 10 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter1 Page 11 of 142

Figure 1-3 - Technical Excellence - Pillars and Foundation

a. Clearly Documented Requirements, Policies, and Procedures. Given the complexity and
uniqueness of the systems that NASA develops and deploys, clear policies and procedures are
essential to mission success. All NASA technical policies and procedures flow directly from NPD
1000.0. Policies and procedures are only as effective as their implementation, facilitated by personal
and organizational accountability and effective training. OCE ensures policies and procedures are
consistent with and reinforce NASA's organizational beliefs and values. OCE puts in place effective,
clearly documented policies and procedures, supplemented by guidance in handbooks and standards
to facilitate optimal performance, rigor, and efficiency among NASA's technical workforce.
b. Effective Training and Development. NASA is fortunate that the importance of its mission
allows it to attract and retain the most capable technical workforce in the world. OCE bears
responsibility for providing this workforce with the technical training and development necessary to
carry out the Agency's missions. At the Agency level, NASA's Academy of Program/Project and
Engineering Leadership (APPEL) provides for the development of engineering leaders and teams
within NASA. APPEL is augmented by technical leadership development at many Centers. Training
consists of more than just transferring a set of skills. In addition to ensuring that NASA's technical
workforce is knowledgeable about standards, specifications, processes, and procedures, the training
available through APPEL and other curriculums is rooted in an engineering philosophy that grounds
NASA's approach to technical work and decision making. These offerings give historical and
philosophical perspectives that teach and reinforce NASA's organizational values and beliefs. OCE
provides full support for training and development activities that will allow NASA to maximize the
abilities of its technical workforce.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter1 incorporated into a contract. This document is uncontrolled when printed. Check Page 11 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter1 Page 12 of 142

c. Balancing Risk. Risk is an inherent factor in any spacecraft, aircraft, or technology development.
Proper risk management entails striking a balance between the tensions of program/project
management and engineering independence. Engineering rigor cannot be sacrificed for schedules
and budgets, and likewise programmatic concerns cannot be overlooked in the development of the
technical approach to a given program or project; technical risk will be consciously and deliberately
traded against budget and schedule. The Engineering Technical Authority (ETA) is responsible for
ensuring risks are considered and good engineering practices are followed in technical development
and implementation. OCE oversees all activities related to the exercise of ETA across the Agency.
Section 2.1.6 of this document contains additional information on the ETA responsibilities.
d. Continuous Communications. Communication lies at the heart of all leadership and
management challenges. Most major failures in NASA's history have stemmed in part from poor
communication. Among the Agency's technical workforce, communication takes a myriad of forms:
continuous risk management (CRM)/risk-informed decision making (RIDM), data sharing,
knowledge management, knowledge sharing, dissemination of best practices and lessons learned,
and continuous learning to name but a few. The complexity of NASA's programs and projects
demands a rigorous culture of continuous and open communication that flourishes within the context
of policies and procedures and knowledge transfer, while empowering individuals at all levels to
raise concerns without fear of adverse consequences. OCE promotes a culture of continuous
communications.
1.3.2 Personal and organizational accountability and responsibility lay the foundation for technical
excellence.
a. Personal Accountability. Personal accountability means that each individual understands that he
or she is responsible for the success of the mission. Each person, regardless of position or area of
responsibility, contributes to success. What NASA does is so complex and interdependent that every
component needs to work for the Agency to be successful. All of those who constitute NASA's
technical community need to possess the knowledge and confidence to speak up when something is
amiss in their or anyone else's area of responsibility to ensure mission success.
b. Organizational Responsibility. NASA's technical organizations have a responsibility to provide
the proper training, tools, and environment for technical excellence. Providing the proper
environment for technical excellence means establishing regular and open communication so that
individuals feel comfortable exercising their personal responsibility. It also requires ensuring that
those who prefer to remain in the technical field (instead of management) have a satisfying and
rewarding career track (e.g., NASA Technical Fellows, ST/SL or GS-15 technical leads).
1.3.3 A central component of the environment for technical excellence is strengthening the SE
capability.

1.4 Framework for Systems Engineering Capability


1.4.1 The framework for SE capability consists of three elements—the common technical processes,
tools and methods, and training for a skilled workforce. The relationship of the three elements is
illustrated in Figure 1-4. The integrated implementation of the three elements of the SE framework is
intended to strengthen and improve the overall capability required for the efficient and effective
engineering of NASA systems. Each element is described below.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter1 incorporated into a contract. This document is uncontrolled when printed. Check Page 12 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter1 Page 13 of 142

Figure 1 4 - SE Framework

a. The common technical processes of this NPR provide what has to be done to engineer quality
system products and achieve mission success. These processes are applied to the integration of
hardware, software, and human systems as one integrated whole. This NPR describes the common
SE processes as well as standard concepts and terminology for consistent application and
communication of these processes across the Agency. This NPR, supplemented by
NASA/SP-2016-6105, NASA Systems Engineering Handbook, and endorsed SE standards, also
describes a structure for applying the common technical processes.
b. Tools and methods range from the facilities and resources necessary to perform the technical
work to the clearly documented policies, processes, and procedures that allow personnel to work
safely and efficiently. Tools and methods enable the efficient and effective completion of the
activities and tasks of the common technical processes. The SE capability is strengthened through
the infusion of advanced methods and tools into the common technical processes to achieve greater
efficiency, collaboration, and communication among distributed teams. The NASA Systems
Engineering Handbook is a resource for methods and tools to support the Centers' implementation of
the required technical processes in their program/projects.
c. A well-trained, knowledgeable, and experienced technical workforce is essential for
improving SE capability. The workforce will be able to apply NASA and Center tools and methods
for the completion of the required SE processes within the context of the program or project to which
they are assigned. In addition, they will be able to effectively communicate requirements and
solutions to customers, other engineers, and management to work efficiently and effectively on a
team. Issues of recruitment, retention, and training are aspects included in this element. The OCE
will facilitate training the NASA workforce on the application of this and associated NPRs.
1.4.2 Improvements to SE capability can be measured through assessing and updating the
implementation of the common technical processes, use of adopted methods and tools, and

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter1 incorporated into a contract. This document is uncontrolled when printed. Check Page 13 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter1 Page 14 of 142

workforce engineering training.

1.5 Document Organization


1.5.1 This SE NPR is organized into the following chapters:
a. The Preface describes items such as the purpose, applicability, authority, and applicable
documents of this NPR.
b. Chapter 1 describes the SE framework and document organization.
c. Chapter 2 describes the institutional and programmatic requirements, including roles and
responsibilities. Tailoring of SE requirements and customizing SE practices are also addressed.
d. Chapter 3 describes the core set of common Agency-level technical processes and requirements
for engineering NASA system products throughout the product life-cycle.
e. Chapter 4 describes the activities and requirements to be accomplished by assigned NASA
technical teams or individuals (NASA employees and NASA support contractors) when performing
technical oversight of a prime or other external contractor.
f. Chapter 5 describes the life-cycle and technical review requirements throughout the program and
project life-cycles. Appendix G contains entrance/success criteria guidance for each of the reviews.
g. Chapter 6 describes the Systems Engineering Management Plan (SEMP), including the SEMP
role, functions, and content. Appendix J of NASA/SP-2016-6105 provides details of a generic
SEMP annotated outline.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter1 incorporated into a contract. This document is uncontrolled when printed. Check Page 14 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter2 Page 15 of 142

Chapter 2. Institutional and Programmatic


Requirements
2.1 Roles and Responsibilities Relative to System Engineering
Practices
2.1.1 General
The roles and responsibilities of senior management are defined in part in NPD 1000.0 and NPD
7120.4. The roles and responsibilities of program and project managers are defined in NPR 7120.5,
NPR 7120.7, NPR 7120.8, NPR 8820.2, and other NASA directives. This NPR establishes SE
processes and responsibilities.
2.1.1.1 For programs and projects involving more than one Center, the governing Mission
Directorate or mission support office determines whether a Center executes a program/project in a
lead role or in a supporting role. For Centers in supporting roles, compliance to this NPR should be
jointly negotiated and documented in the lead Center's program/project SEMP or other equivalent
program/project documentation along with approval through the lead Center's ETA process.
2.1.1.2 The roles and responsibilities associated with program and project management and
Technical Authority (TA) are defined in the Program and Project Management NPRs (for example,
NPR 7120.5 for space flight projects). Specific roles and responsibilities of the program/project
manager and the ETA related to the SEMP are defined in Sections 2.1.6 and 6.2 of this NPR.
2.1.2 Office of the Chief Engineer (OCE)
2.1.2.1 The NASA Chief Engineer is responsible for policy, oversight, and assessment of the NASA
engineering and program/project management process; implements the ETA process; and serves as
principal advisor to the Administrator and other senior officials on matters pertaining to the
Agency's technical capability and readiness to execute NASA programs and projects.
2.1.2.2 The NASA Chief Engineer provides overall leadership for the ETA process for programs and
projects, including Agency engineering policy direction, requirements, and standards. The NASA
Chief Engineer hears appeals of engineering decisions when they cannot be resolved at lower levels.
2.1.3 Mission Directorate or Headquarters Program Offices
2.1.3.1 The Mission Directorate Associate Administrator (MDAA) is responsible for establishing,
developing, and maintaining the Programmatic Authority (i.e., policy and procedures, programs,
projects, budgets, and schedules) in managing programs and projects within their Mission
Directorate.
2.1.3.2 When programs and projects are managed at Headquarters or within Mission Directorates,
that program office is responsible for the requirements in this NPR. Technical teams residing at
Headquarters will follow the requirements of this NPR unless tailored by the governing organization
and responsible ETA. The technical teams residing at Centers will follow Center-level process
requirement documents.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter2 incorporated into a contract. This document is uncontrolled when printed. Check Page 15 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter2 Page 16 of 142

2.1.3.3 The Office of the Chief Information Officer provides leadership, planning, policy direction,
and oversight for the management of NASA information and NASA information technology (IT).
2.1.4 Center Directors
2.1.4.1 The Center Director is responsible for establishing, developing, and maintaining the
Institutional Authority (e.g., processes and procedures, human capital, facilities, and infrastructure)
required to execute programs and projects assigned to their Center. This includes:
a. Ensuring the Center is capable of accomplishing the programs, projects, and other activities
assigned to it in accordance with Agency policy and the Center's best practices and institutional
policies by establishing, developing, and maintaining institutional capabilities (processes and
procedures, human capital—including trained/certified program/project personnel, facilities, and
infrastructure) required for the execution of programs and projects.
b. Performing periodic program and project reviews to assess technical and programmatic progress
to ensure performance in accordance with their Center's and the Agency requirements, procedures,
processes, and other documentation.
c. Working with the Mission Directorate and the program and project managers, once assigned, to
assemble the program/project team(s) and to provide needed Center resources.
d. Providing support and guidance to programs and projects in resolving technical and programmatic
issues and risks.
2.1.4.2 The Center Director is responsible for developing the Center's ETA policies and practices
consistent with Agency policies and standards. The Center Director is the Center ETA responsible
for Center engineering design processes, specifications, rules, best practices, and other activities
necessary to fulfill mission performance requirements for programs, projects, and/or major systems
implemented by the Center. The Center Director delegates the Center ETA implementation
responsibility to an individual in the Center's engineering leadership. The Center ETA supports
processing changes to, and waivers or deviations from, requirements that are the responsibility of
the ETA. This includes all applicable Agency and Center engineering directives, requirements,
procedures, and standards.
Note: Centers may employ and tailor relevant government or industry standards that meet the
intent of the requirements established in this NPR to augment or serve as the basis for their
processes. A listing of endorsed technical standards is maintained on the NASA Technical
Standards System under "Endorsed Standards" https://standards.nasa.gov/endorsed_standards.
2.1.4.3 [SE-01] through [SE-05] deleted.
Note: Rather than resequence the remaining requirements, the original requirement numbering
was left intact in case Centers or other organizations refer to these requirement numbers in
their flow-down requirement documents. Appendix J is provided to account for the deleted
requirements. For each requirement that was deleted, the justification for its deletion is noted.
2.1.5 Technical Teams
2.1.5.1 Systems engineering is implemented by the technical team in accordance with the
program/project SEMP or other equivalent program/project documentation. The makeup and
organization of each technical team is the responsibility of each Center or program and includes all
the personnel required to implement the technical aspects of the program/project.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter2 incorporated into a contract. This document is uncontrolled when printed. Check Page 16 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter2 Page 17 of 142

2.1.5.2 The technical team, in conjunction with the Center's ETA, is responsible for completing the
compliance matrix in Appendix H, capturing any tailoring, and including it in the SEMP or other
equivalent program/project documentation.
2.1.5.3 For systems that contain software, the technical team ensures that software developed within
NASA, or acquired from other entities, complies with NPR 7150.2.
a. NPR 7150.2 elaborates on the requirements in NPR 7123.1 and determines the applicability of
requirements based on the Agency's software classification.
b. NPD 7120.4 contains additional Agency principles for the acquisition, development,
maintenance, and management of software.
2.1.5.4 The technical team ensures that human systems integration activities, products, planning, and
execution align with NASA/SP-2015-3709, Human Systems Integration (HSI) Practitioner's Guide.
2.1.6 Engineering Technical Authority
2.1.6.1 The ETA establishes and is responsible for the engineering design processes, specifications,
rules, best practices, and other activities necessary to fulfill programmatic mission performance
requirements. Centers delegate ETA to the level appropriate for the scope and size of the
program/project, which may be Center engineering leadership or individuals. When ETA is used in
this document, it refers generically to different levels of ETA.
2.1.6.2 ETAs or their delegates at the program or project level:
a. Serve as members of program or project control boards, change boards, and internal review
boards.
b. Work with the Center management and other TA personnel to ensure that the quality and integrity
of program or project processes, products, and standards of performance related to engineering,
SMA, and health and medical reflect the level of excellence expected by the Center and the TA
community.
c. Ensure that requests for waivers or deviations from ETA requirements are submitted to, and acted
on, by the appropriate level of ETA.
d. Assist the program or project in making risk-informed decisions that properly balance technical
merit, cost, schedule, and safety across the system.
e. Provide the program or project with the ETA view of matters based on their knowledge and
experience and raise needed dissenting opinions on decisions or actions. (See Dissenting Opinion
Sections of NPR 7120.5, NPR 7120.8, and NPR 7120.7.)
f. Serve as an effective part of NASA's overall system of checks and balances.
2.1.6.3 The ETA for the program or project leads and manages the system engineering activities.
(Note that these responsibilities can be delegated by the ETA to Chief Engineer or other personnel
as needed). A Center may have more than one engineering organization and delegates ETA to
different areas as needed. The ETA may be delegated as appropriate to the size, complexity, and
type of program/project. For example, ETA may be delegated to a line manager that is independent
of the project for smaller projects or to the CIO for purely IT projects.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter2 incorporated into a contract. This document is uncontrolled when printed. Check Page 17 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter2 Page 18 of 142

2.1.6.4 To support the program/project and maintain ETA independence and an effective check and
balance system, the ETA:
a. Will seek concurrence by the program/project manager when a program/project-level ETA is
appointed.
b. Cannot approve a request for a waiver or deviation from a non-technical derived requirement
established by a Programmatic Authority.
c. May approve a request for a waiver or deviation from a technical derived requirement if he/she
ensures that the appropriate independent Institutional Authority subject matter expert who is the
steward for the involved technology, has concurred in the decision to approve the requirement
waiver.
2.1.6.5 Although a limited number of individuals make up the ETA, their work is enabled by the
contributions of the program's or project's working-level engineers and other supporting personnel
(e.g., contracting officers). The working-level engineers do not have formally delegated Technical
Authority and consequently may not serve in an ETA capacity. These engineers perform the detailed
engineering and analysis for the program/project with guidance from their Center management
and/or lead discipline engineers and support from the Center engineering infrastructure. They
deliver the program/project products (e.g., hardware, software, designs, analysis, and technical
alternatives) that conform to applicable programmatic, Agency, and Center requirements. They are
responsible for raising issues to the program/project manager, Center engineering management,
and/or the program/project ETA and are a key resource for resolving these issues.
2.1.6.6 Requirement [SE-06] concerning SEMP approval was moved to Section 6.1.8.

2.2 Tailoring and Customizing


Tailoring can be differentiated from customizing as described in NASA/SP-2016-6105. Tailoring is
removing requirements by use of waiver or deviation. Customizing is meeting the intent of the
requirement through alternative approaches and does not require waivers or deviations.
2.2.1 Tailoring SE Requirements
2.2.1.1 SE requirements tailoring is the process used to seek relief from SE NPR requirements when
that relief is consistent with program or project objectives, acceptable risk, and constraints.
2.2.1.2 The tailoring process (which can occur at any time in the program or project life cycle)
results in deviations or waivers to requirements depending on the timing of the request (see
Appendix A for definition of deviation and waiver).
2.2.1.3 The results of the program/project technical team's tailoring SE requirements from either this
NPR, or a particular Center's implementation of this NPR, will be documented in the SEMP or other
equivalent project documentation, along with supporting rationale that includes the risk evaluation,
and documented approvals through the Center's ETA process.
2.2.2 Customizing SE Practices
2.2.2.1 Customizing is the adaptation of SE practices that are used to accomplish the SE
requirements as appropriate to the size, complexity, and acceptable risk of the program/project.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter2 incorporated into a contract. This document is uncontrolled when printed. Check Page 18 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter2 Page 19 of 142

2.2.2.2 Technical teams under the guidance of the project ETA are encouraged to customize these
recommended SE practices so that the intent of the SE practice is being met in the most effective and
efficient manner. The results of this customization do not require waivers or deviations but should
be documented in the program/project SEMP or other equivalent program/project documentation.
2.2.3 Considerations for Tailoring or Customizing
Refer to NASA, SP-2016-6105 for examples of tailoring and customizing.
2.2.3.1 Considerations for tailoring or customizing should include but are not limited to:
a. Scope and visibility (e.g., organizations and partnerships involved, international agreements,
amount of effort required).
b. Risk tolerance and failure consequences.
c. System size, functionality, and complexity (e.g., human space flight/flagship science vs. subscale
technology demonstration).
d. Human involvement (e.g., human interfaces, critical crew (flight, ground) functions, interaction
with, and control/oversight of (semi-) autonomous systems).
e. Impact on Agency IT security and national security.
f. Impact on other systems.
g. Longevity.
h. Serviceability (both ground and in-flight).
i. Constraints (including cost, schedule, degree of insight/oversight permitted with partnerships or
international agreements).
j. Safety, quality, and mission assurance.
k. Current level of technology available.
l. Availability of industrial capacity.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter2 incorporated into a contract. This document is uncontrolled when printed. Check Page 19 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 20 of 142

Chapter 3. Requirements for Common


Technical Processes
3.1 Introduction
3.1.1 This chapter establishes the core set of common technical processes and requirements to be
used by NASA programs or projects in engineering system products during all life-cycle phases to
meet phase success criteria and program/project objectives. The 17 common technical processes are
enumerated according to their description in this chapter and their interactions shown in Figure 3-1.
This SE common technical processes model illustrates the use of:
a. System design processes for "top-down" design of each product in the system structure.
b. Product realization processes for "bottom-up" realization of each product in the system structure.
c. Cross-cutting technical management processes for planning, assessing, and controlling the
implementation of the system design and product realization processes and to guide technical
decision making (decision analysis).
3.1.2 The SE common technical processes model is referred to as an "SE engine" in this NPR to
stress that these common technical processes are used to drive the development of the system
products and associated work products required by management to satisfy the applicable product
life-cycle phase success criteria while meeting stakeholder expectations within cost, schedule, and
risk constraints.
3.1.3 This chapter identifies the following for each of the 17 common technical processes:
a. The specific requirement for Program/Project Managers to identify and implement (as defined in
Section 3.2.1) the ETA-approved process.
b. A brief description of how the process is used as an element of the Systems Engineering Engine.
3.1.4 Typical practices for each process are identified in NASA/SP-2016-6105, where each process
is described in terms of purpose, inputs, outputs, and activities. It should be emphasized that the
practices documented in the handbook do not represent additional requirements that need to be
executed by the technical team but provide best practices associated with the 17 common technical
processes. As the technical team develops a tailored and customized approach for the application of
these processes, sources of SE guidance and technical standards, such as NASA/SP-2016-6105 and
endorsed industry standards, should be considered. Appendix I provides a list of NASA and
endorsed military and industry standards applicable to Systems Engineering and available on the
NASA Technical Standards System, found at https://standards.nasa.gov/endorsed_standards, and
should be applied as appropriate for each program or project. For additional guidance on mapping
HSI into the SE Engine, refer to NASA/SP-2015-3709, Section 3.0.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 20 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 21 of 142

Figure 3 1 - Systems Engineering (SE) Engine

3.1.5 The context in which the common technical processes are used is provided below: (Refer to
"The Common Technical Processes and the SE Engine" in NASA/SP-2016-6105 for further
information.)
3.1.5.1 The common technical processes are applied to each product layer to concurrently develop
the products that will satisfy the operational or mission functions of the system (end products) and
that will satisfy the life-cycle support functions of the system (enabling products). In this document,
a product layer is a horizontal slice of the product breakdown hierarchy and includes both the end
product and its associated enabling products. The enabling products facilitate the activities of system
design, product realization, operations and mission support, sustainment, and end-of-product-life
disposal or recycling by having the products and services available when needed.
3.1.5.2 The common technical processes are applied to design a system solution definition for each
product layer down and across each level of the system structure and to realize the product layer end
products up and across the system structure. Figure 3-2 illustrates how the three major sets of
processes of the Systems Engineering (SE) Engine (system design processes, product realization
processes, and technical management processes) are applied to each product layer within a system
structure.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 21 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 22 of 142

Figure 3-2 - Application of SE Engine Common Technical Processes


Within System Structure

3.1.5.3 The common technical processes are used to define the product layers of the system structure
in each applicable phase of the relevant life-cycle to generate work products and system products
needed to satisfy the success criteria of the applicable phase. Figure 3-3 depicts the sequencing of
the processes.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 22 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 23 of 142

Figure 3-3 - Sequencing of the Common Technical Processes

3.1.5.4 There are four system design processes applied to each product-based product layer from the
top to the bottom of the system structure:
a. Stakeholder Expectation Definition.
b. Technical Requirements Definition.
c. Logical Decomposition.
d. Design Solution Definition. (See Figure 3-1 and Figure 3-2.)
3.1.5.5 During the application of these four processes to a product layer, it is expected that there will
be a need to apply activities from other processes yet to be completed and to repeat process activities
already performed to arrive at an acceptable set of requirements and solutions. There also will be a
need to interact with the technical management processes to aid in identifying and resolving issues
and making decisions between alternatives. For software products, the technical team ensures that
the process executions comply with NPR 7150.2, software design requirements. The technical team
also ensures that human capabilities and limitations are understood and how those human
capabilities or limitations impact the hardware and software of any given system in terms of design.
Refer to NASA/SP-2015-3709.
3.1.5.6 There are five product realization processes. Four of the product realization processes are
applied to each end product of a product layer from the bottom to the top of the system structure:
a. Either Product Implementation for the lowest level or Product Integration for subsequent levels.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 23 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 24 of 142

b. Product Verification.
c. Product Validation.
d. Product Transition. (See Figure 3-1 and Figure 3-2.)
3.1.5.7 The form of the end product realized will depend on the applicable product life-cycle phase,
location within the system structure of the product layer containing the end product, and the success
criteria of the phase. Typical early phase products are reports, models, simulations, mockups,
prototypes, or demonstrators. Typical later phase products may take the form of qualification units,
final mission products, and fully assembled payloads and instruments.
3.1.5.8 There are eight technical management processes—Technical Planning, Technical
Requirements Management, Interface Management, Technical Risk Management, Configuration
Management, Technical Data Management, Technical Assessment, and Decision Analysis. (See
Figure 3-1 and Figure 3-2.) These technical management processes supplement the program and
project management directives (e.g., NPR 7120.5), which specify the technical activities for which
program and project managers are responsible.
3.1.5.9 Note that during the design and realization phases of a project, all 17 processes are used.
After the end product is developed and placed into operations the Technical Management processes
in the center chamber of the SE Engine will continue to be employed. For more information on the
use of the SE Engine during the operational phase, refer to NASA/SP-2016-6105.
3.1.5.10 The common technical processes are applied by assigned technical teams and individuals
trained in the requirements of this NPR.
3.1.5.11 The assigned technical teams and individuals use the appropriate and available sets of tools
and methods to accomplish required common technical process activities. This includes the use of
modeling and simulation as applicable to the product phase, location of the product layer in the
system structure, and the applicable phase success criteria.
3.1.6 Relationship of the SE Engine to the SE Vee.
The NASA SE Engine is a highly versatile representation of the core SE processes necessary to
properly engineer a system. It can be used for any type of life-cycle including waterfall, spiral, and
agile. It allows for use in very simple to highly complex systems. The NASA SE Engine had its
heritage in a classic SE Vee, and if being used for a simple one-pass waterfall-type life-cycle, the
right and left chambers of the engine can be represented as shown in Figure 3-4. For a more detailed
description of how the SE Engine evolved from the SE Vee, refer to the NASA Systems Engineering
Handbook.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 24 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 25 of 142

Figure 3-4 - SE Engine Implemented for a Simple Single-Pass Waterfall-Type Life Cycle

3.2 Common Technical Processes Requirements


3.2.1 For Section 3.2, "identify" means to either use an approved process or a customized process
that is approved by the ETA or their delegate. "Implement" includes documenting and
communicating the approved process, providing resources to execute the process, providing training
on the process, and monitoring and controlling the process. The technical team is responsible for the
execution of these 17 required processes per Section 2.1.5.
3.2.2 Stakeholder Expectations Definition Process
3.2.2.1 Program/Project Managers shall identify and implement an ETA-approved Stakeholder
Expectations Definition process to include activities, requirements, guidelines, and documentation,
as tailored and customized for the definition of stakeholder expectations for the applicable product
layer [SE-07].
3.2.2.2 The Stakeholder Expectations Definition process is used to elicit and define use cases,
scenarios, concept of operations, and stakeholder expectations for the applicable product life-cycle
phases and product layer. This includes expectations such as:
a. Operational end products and life-cycle-enabling products of the product layer.
b. Affordability.
c. Operator or user interfaces.
d. Expected skills and capabilities of operators or users.
e. Expected number of simultaneous users.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 25 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 26 of 142

f. System and human performance criteria.


g. Technical authority, standards, regulations, and laws.
h. Factors such as health and medical, safety, planetary protection, orbital debris, quality,
cybersecurity, context of use by humans, reliability, availability, maintainability, electromagnetic
compatibility, interoperability, testability, transportability, supportability, usability, and
disposability.
i. For crewed missions, crew health and performance capabilities and limitations, risk posture, crew
survivability, and system habitability.
j. Local management constraints on how work will be done (e.g., operating procedures).
3.2.2.3 The baselined stakeholder expectations are used for validation of the product layer end
product during product realization. At this point, Measures of Effectiveness (MOEs) are defined. For
more information of MOEs refer to NASA/SP-2016-6105, NASA Systems Engineering Handbook.
3.2.3 Technical Requirements Definition Process
3.2.3.1 Program/Project Managers shall identify and implement an ETA-approved Technical
Requirements Definition process to include activities, requirements, guidelines, and documentation,
as tailored and customized for the definition of technical requirements from the set of agreed upon
stakeholder expectations for the applicable product layer [SE-08].
3.2.3.2 The technical requirements definition process is used to transform the baselined stakeholder
expectations into unique, quantitative, and measurable technical requirements expressed as "shall"
statements that can be used for defining a design solution for the product layer end product and
related enabling products. This process also includes validation of the requirements to ensure that the
requirements are well-formed (clear and unambiguous), complete (agrees with customer and
stakeholder needs and expectations), consistent (conflict free), and individually verifiable and
traceable to a higher level requirement or goal. As part of this process, Measures of Performance
(MOPs) and Technical Performance Measures (TPMs) are defined. For more information of MOPs
and TPMs, refer to NASA/SP-2016-6105, NASA Systems Engineering Handbook.
3.2.4 Logical Decomposition Process
3.2.4.1 Program/Project Managers shall identify and implement an ETA-approved Logical
Decomposition process to include activities, requirements, guidelines, and documentation, as
tailored and customized for logical decomposition of the validated technical requirements of the
applicable product layer [SE-09].
3.2.4.2 The logical decomposition process is used to improve understanding of the defined technical
requirements and the relationships among the requirements (e.g., functional, behavioral,
performance, and temporal) and to transform the defined set of technical requirements into a set of
logical decomposition models and their associated set of derived technical requirements for lower
levels of the system and for input to the design solution definition process.
3.2.5 Design Solution Definition Process
3.2.5.1 Program/Project Managers shall identify and implement an ETA-approved Design Solution
Definition process to include activities, requirements, guidelines, and documentation, as tailored and
customized for designing product solution definitions within the applicable product layer that satisfy

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 26 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 27 of 142

the derived technical requirements [SE-10].


3.2.5.2 The Design Solution Definition process is used to translate the outputs of the logical
decomposition process into a design solution definition that is in a form consistent with the product
life-cycle phase and product layer location in the system structure and that will satisfy phase success
criteria. This includes transforming the defined logical decomposition models and their associated
sets of derived technical requirements into alternative solutions, then analyzing each alternative to be
able to select a preferred alternative and fully defining that alternative into a final design solution
definition that will satisfy the requirements.
3.2.5.3 These design solution definitions will be used for generating end products, either by using the
product implementation process or product integration process, as a function of the position of the
product layer in the system structure and whether there are additional subsystems of the end product
that need to be defined. The output definitions from the design solution (end product specifications)
will be used for conducting product verification.
3.2.6 Product Implementation Process
3.2.6.1 Program/Project Managers shall identify and implement an ETA-approved Product
Implementation process to include activities, requirements, guidelines, and documentation, as
tailored and customized for implementation of a design solution definition by making, buying, or
reusing an end product of the applicable product layer [SE-11].
3.2.6.2 The Product Implementation Process is used to generate a specified product of a product
layer through buying, making, or reusing in a form consistent with the product life-cycle phase
success criteria and that satisfies the design solution definition (e.g., drawings, specifications).
3.2.7 Product Integration Process
3.2.7.1 Program/Project Managers shall identify and implement an ETA-approved Product
Integration process to include activities, requirements, guidelines, and documentation, as tailored
and customized for the integration of lower level products into an end product of the applicable
product layer in accordance with its design solution definition [SE-12].
3.2.7.2 The Product Integration Process is used to transform lower level, verified and validated end
products into the desired end product of the higher level product layer through assembly and
integration.
3.2.8 Product Verification Process
3.2.8.1 Program/Project Managers shall identify and implement an ETA-approved Product
Verification process to include activities, requirements/specifications, guidelines, and
documentation, as tailored and customized for verification of end products generated by the product
implementation process or product integration process against their design solution definitions
[SE-13].
3.2.8.2 The Product Verification process is used to demonstrate that an end product generated from
product implementation or product integration conforms to its requirements as a function of the
product life-cycle phase and the location of the product layer end product in the system structure.
Special attention is given to demonstrating satisfaction of the MOPs defined for each MOE during
performance of the technical requirements definition process.
3.2.9 Product Validation Process

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 27 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 28 of 142

3.2.9.1 Program/Project Managers shall identify and implement an ETA-approved Product


Validation process to include activities, requirements, guidelines, and documentation, as tailored and
customized for validation of end products generated by the product implementation process or
product integration process against their stakeholder expectations [SE-14].
3.2.9.2 The Product Validation process is used to confirm that a verified end product generated by
product implementation or product integration fulfills (satisfies) its intended use when placed in its
intended environment and to ensure that any anomalies discovered during validation are
appropriately resolved prior to delivery of the product (if validation is done by the supplier of the
product) or prior to integration with other products into a higher level assembled product (if
validation is done by the receiver of the product). The validation is done against the set of baselined
stakeholder expectations. Special attention should be given to demonstrating satisfaction of the
MOEs identified during performance of the stakeholder expectations definition process. The type of
product validation is a function of the form of the product and product life-cycle phase and in
accordance with an applicable customer agreement.
3.2.10 Product Transition Process
3.2.10.1 Program/Project Managers shall identify and implement an ETA-approved Product
Transition process to include activities, requirements, guidelines, and documentation, as tailored and
customized for transitioning end products to the next higher level product layer customer or user
[SE-15].
3.2.10.2 The Product Transition process is used to transition a verified and validated end product
that has been generated by product implementation or product integration to the customer at the next
level in the system structure for integration into an end product or, for the top-level end product,
transitioned to the intended end user. The form of the product transitioned will be a function of the
product life-cycle phase and the location within the system structure of the product layer in which
the end product exists.
3.2.11 Technical Planning Process
3.2.11.1 Program/Project Managers shall identify and implement an ETA-approved Technical
Planning process to include activities, requirements, guidelines, and documentation, as tailored and
customized for planning the technical effort [SE-16].
3.2.11.2 The Technical Planning process is used to plan for the application and management of each
common technical process, including tailoring of organizational requirements and requirements
specified in this NPR. It is also used to identify, define, and plan the technical effort applicable to the
product life-cycle phase for product layer location within the system structure and to meet
program/project objectives and product life-cycle phase success criteria. A key document generated
by this process is the SEMP (See Chapter 6).
3.2.12 Requirements Management Process
3.2.12.1 Program/Project Managers shall identify and implement an ETA-approved Requirements
Management process to include activities, requirements, guidelines, and documentation, as tailored
and customized for management of requirements throughout the system life-cycle [SE-17].
3.2.12.2 The Requirements Management process is used to:
a. Manage the product requirements identified, baselined, and used in the definition of the product

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 28 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 29 of 142

layer products during system design.


b. Provide bidirectional traceability back to the top product layer requirements.
c. Manage the changes to established requirement baselines over the life-cycle of the system
products.
3.2.13 Interface Management Process
3.2.13.1 Program/Project Managers shall identify and implement an ETA-approved Interface
Management process to include activities, requirements, guidelines, and documentation, as tailored
and customized for management of the interfaces defined and generated during the application of the
system design processes [SE-18].
3.2.13.2 The Interface Management process is used to:
d. Establish and use formal interface management to assist in controlling system product
development efforts when the efforts are divided between Government programs, contractors, and/or
geographically diverse technical teams within the same program or project.
e. Maintain interface definition and compliance among the end products and enabling products that
compose the system, as well as with other systems with which the end products and enabling
products will interoperate.
3.2.14 Technical Risk Management Process
3.2.14.1 Program/Project Managers shall identify and implement an ETA-approved Technical Risk
Management process to include activities, requirements, guidelines, and documentation, as tailored
and customized for management of the risk identified during the technical effort [SE-19].
3.2.14.2 The Technical Risk Management process is used to make risk-informed decisions and
examine, on a continuing basis, the potential for deviations from the program/project plan and the
consequences that could result should they occur. This enables risk-handling activities to be planned
and invoked as needed across the life of the program or project to mitigate impacts on achieving
product life-cycle phase success criteria and meeting technical objectives. The technical team
supports the development of potential health and medical, safety, cost, and schedule impacts for
identified technical risks and any associated mitigation strategies. NPR 8000.4, Agency Risk
Management Procedural Requirements, is to be used as a source document for defining this process
and NPR 8705.5, Technical Probabilistic Risk Assessment (PRA) Procedures for Safety and Mission
Success for NASA Programs and Projects, provides one means of identifying and assessing technical
risk. While the focus of this process is the management of technical risk, the highly interdependent
nature of health and medical, safety, technical, cost, and schedule risks require the broader
program/project team to consistently address risk management with an integrated approach.
NASA/SP-2011-3422, NASA Risk Management Handbook, provides guidance for managing risk in
an integrated fashion.
3.2.15 Configuration Management Process
3.2.15.1 Program/Project Managers shall identify and implement an ETA-approved Configuration
Management process to include activities, requirements, guidelines, and documentation, as tailored
and customized for configuration management [SE-20].
3.2.15.2 The Configuration Management process for end products, enabling products, and other

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 29 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 30 of 142

work products placed under configuration control is used to:


a. Identify the items to be placed under configuration control.
b. Identify the configuration of the product or work product at various points in time.
c. Systematically control changes to the configuration of the product or work product.
d. Maintain the integrity and traceability of the configuration of the product or work product
throughout its life.
e. Preserve the records of the product or end product configuration throughout its life-cycle,
dispositioning them in accordance with NPR 1441.1, NASA Records Management Program
Requirements.
3.2.16 Technical Data Management Process
3.2.16.1 Program/Project Managers shall identify and implement an ETA-approved Technical Data
Management process to include activities, requirements, guidelines, and documentation, as tailored
and customized for management of the technical data generated and used in the technical effort
[SE-21].
3.2.16.2 The Technical Data Management Process is used to plan for, acquire, access, manage,
protect, and use data of a technical nature to support the total life-cycle of a system. This process is
used to capture trade studies, cost estimates, technical analyses, reports, and other important
information.
3.2.17 Technical Assessment Process
3.2.17.1 Program/Project Managers shall identify and implement an ETA-approved Technical
Assessment process to include activities, requirements, guidelines, and documentation, as tailored
and customized for making assessments of the progress of planned technical effort and progress
toward requirements satisfaction [SE-22].
3.2.17.2 The Technical Assessment process is used to help monitor progress of the technical effort
and provide status information for support of the system design, product realization, and technical
management processes. A key aspect of the technical assessment process is the conduct of life-cycle
and technical reviews throughout the system life-cycle in accordance with Chapter 5.
3.2.18 Decision Analysis Process
3.2.18.1 Program/Project Managers shall identify and implement an ETA-approved Decision
Analysis process to include activities, requirements, guidelines, and documentation, as tailored and
customized for making technical decisions [SE-23].
3.2.18.2 The Decision Analysis process, including processes for identification of decision criteria,
identification of alternatives, analysis of alternatives, and alternative selection, is applied to technical
issues to support their resolution. It considers relevant data (e.g., engineering performance, quality,
and reliability) and associated uncertainties. Decision analysis is used throughout the system
life-cycle to formulate candidate decision alternatives and evaluate their impacts on health and
medical, safety, technical, cost, and schedule performance. NASA/SP-2010-576, NASA
Risk-Informed Decision Making Handbook, provides guidance for analyzing decision alternatives in
a risk-informed fashion.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 30 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter3 Page 31 of 142

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter3 incorporated into a contract. This document is uncontrolled when printed. Check Page 31 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter4 Page 32 of 142

Chapter 4. NASA Systems Engineering


Activities on Contracted Projects
4.1 Introduction
4.1.1 Work contracted in support of programs and projects is critical to mission success. Inputs or
requirements in support of a solicitation (such as Requests for Proposals (RFP)) typically include a
Statement of Work, product requirements, Independent Government Estimate, Data Requirements
List, Deliverables List, and Surveillance Plan. These should be developed considering the risk
posture of the program/project and fit within the cost and schedule constraints. In addition to
developing the product requirements, a critical aspect of the solicitation is for the technical team to
define the insight and oversight requirements. "Insight" is a monitoring activity, whereas "oversight"
is an exercise of authority by the Government. The Federal Acquisition Regulation and the NASA
Supplement to the Federal Acquisition Regulation govern the acquisition planning, contract
formation, and contract administration process. Authority to interface with the contractor can be
delegated only by the contracting officer. The activities listed in Section 4.2 will be coordinated with
the cognizant contracting officer. Detailed definitions for insight and oversight are provided in 48
CFR, sbpt. 1846.4. As stated in Section 1.1.3, the requirements should be appropriately tailored and
customized for system/product size, complexity, criticality, acceptable risk posture, and architectural
level.
4.1.2 This chapter defines a minimum set of technical activities and requirements for a NASA
program/project technical team to perform before contract award, during contract performance, and
upon completion of the contract on program/projects. These activities and requirements are intended
to supplement the common technical process activities and requirements of Chapter 3 and thus
enhance the outcome of the contracted effort and ensure the required integration between work
performed by the contractor and the program or project.

4.2 Prior to Contract Award


4.2.1 The NASA technical team shall define the engineering activities for the periods before contract
award, during contract performance, and upon contract completion in the SEMP or other equivalent
program/project documentation [SE-24].
4.2.2 The content of Appendix J of NASA/SP-2016-6105 should be used as a guide in the
development of the SEMP or other equivalent program/project documentation.
4.2.3 The NASA technical team shall establish the technical inputs to the solicitation appropriate for
the product(s) to be developed, including product requirements and Statement of Work tasks
[SE-25].
4.2.3.1 The technical team uses knowledge of the 17 common technical processes to identify
products and desired practices to include in the solicitation.
4.2.4 The NASA technical team shall determine the technical work products to be delivered by the
offeror or contractor, to include contractor documentation that specifies the contractor's SE approach

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter4 incorporated into a contract. This document is uncontrolled when printed. Check Page 32 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter4 Page 33 of 142

to the scope of activities described by the 17 common technical processes [SE-26].


4.2.5 The NASA technical team shall provide the requirements for technical insight and oversight
activities planned in the NASA SEMP or other equivalent program/project documentation to the
contracting officer for inclusion in the solicitation [SE-27].
4.2.6 Care should be taken that no requirements or solicitation information is divulged prior to the
release of the solicitation.
4.2.7 The NASA technical team shall participate in the evaluation of offeror proposals in accordance
with applicable NASA and Center source selection procedures [SE-28].
4.2.7.1 This requirement ensures that the proposal addresses the requirements, products, and
processes specified in the solicitation.

4.3 During Contract Performance


4.3.1 The NASA technical team, under the authority of the contracting officer, shall perform the
technical insight and oversight activities established in the contract including modifications to the
original contract [SE-29].
4.3.2 The requirements levied on the technical team in Section 4.2 for establishing the contract
applies to any modifications or additions to the original contract.

4.4 Contract Completion


4.4.1 The NASA technical team shall participate in the review(s) to finalize Government acceptance
of the deliverables [SE-30].
4.4.2 The NASA technical team shall participate in product transition as defined in the NASA SEMP
or other equivalent program/project documentation [SE-31].

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter4 incorporated into a contract. This document is uncontrolled when printed. Check Page 33 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter5 Page 34 of 142

Chapter 5. Systems Engineering Life-Cycle and


Technical Reviews
5.1 Life-Cycle
5.1.1 NPR 7120.5 defines four types of programs that may contain projects:
a. Uncoupled programs.
b. Loosely coupled programs.
c. Tightly coupled programs.
d. Single-project programs.
5.1.1.1 Which life-cycle a program/project uses will be dependent on what type of program/project it is and
whether the program/project is producing products for space flight, advanced technology development,
information technology, infrastructure, or other applications.
5.1.1.2 A specific life-cycle may be required by associated project management NPRs. For example, NPR
7120.5 defines the life-cycles for space flight programs and projects, and NPR 7120.7 defines life-cycles for
IT. For Announcement of Opportunity (AO) driven projects, refer to NPR 7120.5, Section 2.2.7.1. For
purposes of illustration, life-cycles from NPR 7120.5 are repeated here in Figures 5-1 through 5-4.
5.1.2 The application of the common technical processes within each life-cycle phase produces technical
results and work products that provide inputs to life-cycle and technical reviews and support informed
management decisions for progressing to the next life-cycle phase.
5.1.3 Each program and project will perform the life-cycle reviews as required by or tailored in accordance
with their governing program/project management NPR, applicable Center policies and procedures, and the
requirements of this document. These reviews provide a periodic assessment of a program or project's
technical and programmatic status and health at key points in the life-cycle. The technical team provides the
technical inputs to be incorporated into the overall program/project review package. Appendix G provides
guidelines for the entrance and success criteria for each of these reviews with a focus on the technical
products. Additional programmatic work products may also be required by the governing program/project
NPR. Programs/projects are expected to tailor the reviews and customize the entrance/success criteria as
appropriate to the size/complexity and unique needs of their activities. Approved tailoring is captured in the
SEMP or other equivalent program/project documents.
5.1.4 The progress between life-cycle phases is marked by key decision points (KDPs). At each KDP,
management examines the maturity of the technical aspects of the program/project. For example,
management evaluates the adequacy of the resources (staffing and funding) allocated to the planned technical
effort, the technical maturity of the product, the management of technical and nontechnical internal issues
and risks, and the responsiveness to any changes in stakeholder expectations. If the technical and
management aspects of the program/project are satisfactory, including the implementation of corrective
actions, then the program/project can be approved by the designated Decision Authority to proceed to the
next phase. Program and project management NPRs (NPR 7120.5, NPR 7120.7, and NPR 7120.8) contain
further details relating to life-cycle progress.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter5 incorporated into a contract. This document is uncontrolled when printed. Check Page 34 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter5 Page 35 of 142

Note: For example only. Refer to Figure 2-2 in NPR 7120.5 for the official life cycle. Table 2-3 reference in
Footnote 5 above is in NPR 7120.5.
Figure 5 1 - NASA Uncoupled and Loosely Coupled Program Life-Cycle

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter5 incorporated into a contract. This document is uncontrolled when printed. Check Page 35 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter5 Page 36 of 142

Note: For example only. Refer to Figure 2-3 in NPR 7120.5 for the official life cycle. Table 2-4 reference in
Footnote 5 above is in NPR 7120.5.
Figure 5-2 - NASA Tightly Coupled Program Life-Cycle

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter5 incorporated into a contract. This document is uncontrolled when printed. Check Page 36 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter5 Page 37 of 142

Note: For example only. Refer to Figure 2-4 in NPR 7120.5 for the official life cycle. Table 2-5 reference in
Footnote 5 above is in NPR 7120.5.
Figure 5-3 - NASA Single-Project Program Life-Cycle

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter5 incorporated into a contract. This document is uncontrolled when printed. Check Page 37 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter5 Page 38 of 142

Note: For example only. Refer to Figure 2-5 in NPR 7120.5 for the official life cycle. Table 2-5 reference in
Footnote 2 above is in NPR 7120.5.
Figure 5 4 - The NASA Project Life-Cycle

5.1.5 Life-cycle reviews are event based and occur when the entrance criteria for the applicable review are
satisfied. (Appendix G provides guidance.) They occur based on the maturity of the relevant technical
baseline as opposed to calendar milestones (e.g., the quarterly progress review, the yearly summary).
5.1.6 Accurate assessment of technology maturity is critical to technology advancement and its subsequent
incorporation into operational products. The program/project ensures that Technology Readiness Levels
(TRLs) and/or other measures of technology maturity are used to assess maturity throughout the life-cycle of
the program/project. When other measures of technology maturity are used, they should be mapped back to
TRLs. The definition of the TRLs for hardware and software are defined in Appendix E. Moving to higher
levels of technology maturity requires an assessment of a range of capabilities for design, analysis,
manufacture, and test. Measures for assessing technology maturity are described in NASA/SP-2016-6105.
The initial technology maturity assessment is done in the Formulation phase and updated at program/project
status reviews. The program/project approach for maturing and assessing technology is typically captured in
a Technology Development Plan, the SEMP, or other equivalent program/project documentation.

5.2 Life-Cycle and Technical Review Requirement

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter5 incorporated into a contract. This document is uncontrolled when printed. Check Page 38 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter5 Page 39 of 142

5.2.1 Planning
5.2.1.1 The technical team shall develop and document plans for life-cycle and technical reviews for use in
the program/project planning process [SE-32].
5.2.1.2 The life-cycle and technical review schedule, as documented in the SEMP or other equivalent
program/project documentation, will be reflected in the overall program/project plan. The results of each
life-cycle and technical review will be used to update the technical review plan as part of the SEMP (or other
equivalent program/project documentation) update process. The review plans, data, and results should be
maintained and dispositioned as Federal Records.
5.2.1.3 The technical team ensures that system aspects interfacing with crew or human operators (e.g., users,
maintainers, assemblers, and ground support personnel) are included in all life-cycle and technical reviews
and that HSI requirements are implemented. Additional HSI guidance is provided in NASA/SP-2015-3709
and NASA/SP-2016-6105/SUPPL Expanded Guidance for NASA Systems Engineering Volumes 1 and 2.
5.2.1.4 The technical team ensures that system aspects represented or implemented in software are included
in all life-cycle and technical reviews and that all software review requirements are implemented. Software
review requirements are provided in NPR 7150.2, with guidance provided in NASA-HDBK-2203, NASA
Software Engineering Handbook.
5.2.1.5 The technical team shall participate in the life-cycle and technical reviews as indicated in the
governing program/project management NPR [SE-33]. Additional description of technical reviews is
provided in NASA/SP-2016-6105, NASA Systems Engineering Handbook and in NASA/SP-2014-3705,
NASA Spaceflight Program & Project Management Handbook. (For requirements on program and project
life cycles and management reviews, see the appropriate NPR, e.g., NPR 7120.5.)
5.2.2 Conduct
5.2.2.1 The technical team shall participate in the development of entrance and success criteria for each of
the respective reviews [SE-34]. The technical team should utilize the guidance defined in Appendix G as
well as Center best practices for defining entrance and success criteria.
5.2.2.2 The technical team shall provide the following minimum products at the associated life-cycle review,
at the indicated maturity level. If the associated life-cycle review is not held, the technical team will need to
seek a waiver or deviation to tailor these requirements. If the associated life-cycle review is held but
combined with other life-cycle reviews or resequenced, this is considered customization and therefore no
waiver is required (but approach should still be documented in the SEMP or Review Plan for clarity).
a. Mission Concept Review (MCR):
(1) Baselined stakeholder identification and expectation definitions [SE-35].
(2) Baselined concept definition [SE-36].
(3) Approved MOE definition [SE-37].
b. System Requirements Review (SRR):
(1) Baselined SEMP (or other equivalent program/project documentation) for projects, single-project
programs, and one-step AO programs [SE-38].
(2) Baselined requirements [SE-39].
c. Mission Definition Review/System Definition Review (MDR/SDR):
(1) Approved TPM definitions [SE-40].

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter5 incorporated into a contract. This document is uncontrolled when printed. Check Page 39 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter5 Page 40 of 142

(2) Baselined architecture definition [SE-41].


(3) Baselined allocation of requirements to next lower level [SE-42].
(4) Initial trend of required leading indicators [SE-43].
(5) Baseline SEMP (or other equivalent program/project documentation) for uncoupled, loosely coupled,
tightly coupled, and two-step AO programs [SE-44].
d. Preliminary Design Review (PDR):
(1) Preliminary design solution definition [SE-45].
e. Critical Design Review (CDR):
(1) Baseline detailed design [SE-46].
f. System Integration Review (SIR):
(1) Updated integration plan [SE-47].
(2) Preliminary Verification and Validation (V&V) results [SE-48].
g. Operational Readiness Review (ORR):
(1) [SE-49] deleted.
(2) [SE-50] deleted.
(3) Preliminary decommissioning plans [SE-51].
h. Flight Readiness Review (FRR):
(1) Baseline disposal plans [SE-52].
(2) Baseline V&V results [SE-53].
(3) Final certification for flight/use [SE-54].
i. Decommissioning Review (DR):
(1) Baseline decommissioning plans [SE-55].
j. Disposal Readiness Review (DRR):
(1) Updated disposal plans [SE-56].
5.2.2.3 Table 5-1 shows the maturity of primary SE work products at the associated life-cycle reviews for all
types and sizes of programs/projects. The required SE products identified above are notated with "**" in the
table. For further description of the primary SE work products, refer to Appendix G. For additional guidance
on software product maturity for program/project life-cycle reviews, refer to NASA-HDBK-2203. Additional
programmatic work products are required by the governing program/project management NPRs, but not
listed herein.
5.2.2.4 The expectation for work products identified as "baselined" in Section 5.2.2.2 and Table 5-1 is that
they will be at least final drafts going into the designated life-cycle review. Subsequent to the review, the
final draft will be updated in accordance with approved review comments, Review Item Discrepancies
(RID), or Requests for Action (RFA) and formally baselined.
5.2.2.5 Terms for maturity levels of technical work products identified in this section are addressed in detail

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter5 incorporated into a contract. This document is uncontrolled when printed. Check Page 40 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter5 Page 41 of 142

in Appendix F.
5.2.2.6 The technical team ensures that each program or project hosting equipment, experiments, or payloads
with radio frequency (RF) requirements include success criteria in all life-cycle and technical reviews to
receive approval from the responsible Center spectrum manager that program or project spectrum goals and
progress are being achieved and satisfy all spectrum regulatory requirements. Spectrum certification
requirements are provided in NPD 2570.5 and NPR 2570.1, NASA Radio Frequency (RF) Spectrum
Management Manual. NPR 2570.1 takes precedence over this document regarding spectrum related
procedures and processes.
Table 5-1 - SE Work Product Maturity

**Item is a required product for that review.

1 For projects, single-project programs, and one-step AO programs.

2 For uncoupled, tightly coupled, loosely coupled programs, and two-step AO programs.

5.2.2.7 Technical teams shall monitor technical effort through periodic technical reviews [SE-57].
5.2.2.8 For each type of program/project, technical efforts are monitored throughout the life- cycle to ensure
that the technical goals of the program/project are being achieved and that the technical direction of the
program/project is appropriate.
5.2.2.9 A technical review is an evaluation of the program/project, or element thereof, by the technical team
and other knowledgeable participants for the purposes of:
a. Assessing the status of and progress toward accomplishing the planned activities.
b. Validating the technical tradeoffs explored and design solutions proposed.
c. Identifying technical weaknesses or marginal design and potential problems (risks) and recommending

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter5 incorporated into a contract. This document is uncontrolled when printed. Check Page 41 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter5 Page 42 of 142

improvements and corrective actions.


d. Making judgments on the activity's readiness for the follow-on events, including additional future
evaluation milestones to improve the likelihood of a successful outcome.
e. Making assessments and recommendations to the program/project team, Center, and Agency management.
f. Providing a historical record of decisions that were made during these formal reviews which can be
referenced at a later date.
g. Assessing the technical risk status and current risk profile.
5.2.3 Completion
5.2.3.1 Life-cycle reviews are considered complete when the following are accomplished:
a. Agreement (including with the appropriate TA) exists for the disposition of all RIDs and RFAs.
b. The review board report and minutes are complete and distributed.
c. Agreement (including with the appropriate TA) exists on a plan to address the issues and concerns of
insufficient program/project performance with respect to the LCR success criteria in the review board's
report.
d. Agreement (including with the appropriate TA) exists on a plan for addressing the actions identified out of
the review.
e. Liens against the review results are closed, or an adequate and timely plan exists for their closure.
f. Differences of opinion between the program/project under review and the review board(s) have been
resolved, or a timely plan exists to resolve the issues.
g. A report is given by the review board chairperson to the appropriate management and governing Program
Management Committees (PMCs) charged with oversight of the program/project.
h. Appropriate procedures and controls are instituted to ensure that all actions from reviews are followed and
verified through implementation to closure.
i. The Program/Project Decision Authority signs a decision memo (e.g., memorandum or other appropriate
format) documenting successful completion of the review.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter5 incorporated into a contract. This document is uncontrolled when printed. Check Page 42 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter6 Page 43 of 142

Chapter 6. Systems Engineering Management


Plan
6.1 Systems Engineering Management Plan Function
6.1.1 A Systems Engineering Management Plan (SEMP) is used to establish the technical content of
the engineering work early in the Formulation phase for each program/project and updated as needed
throughout the program/project life-cycle. The resulting technical plan represents the agreed to and
approved tailoring of the requirements of this NPR and the customizing of SE practices to satisfy
program/project technical requirements.
6.1.1.1 The SEMP provides the specifics of the technical effort and describes what common
technical processes will be used, how the processes will be applied using appropriate activities, how
the program/project will be organized to accomplish the activities, and the technical resources
required (including cost, schedule, and personnel) for accomplishing the activities. The process
activities are driven by the critical events during any phase of a life-cycle (including operations) that
set the objectives and work product outputs of the processes and how the processes are integrated.
(See Appendix J of NASA/SP-2016-6105 for a suggested annotated outline for the SEMP.)
6.1.1.2 The SEMP provides the communication bridge between the program/project management
team and the executing technical team. It also facilitates effective communication within the
technical team.
6.1.1.3 The SEMP provides the framework to realize the appropriate work products of the applicable
program/project life-cycle phases to provide management with necessary information for assessing
technical progress.
6.1.1.4 The SEMP may be a stand-alone document or may be included as sections within other
documentation such as the program or project plan.
6.1.1.5 The SEMP provides the basis for implementing the technical effort and communicating what
will be done and by whom, when, where, how, and why it is being done including any applicable
constraints on the implementation. In addition, the SEMP identifies the roles and responsibility
interfaces of the technical effort and how those interfaces will be managed.
6.1.1.6 The SEMP is the vehicle that documents and communicates the technical approach,
including the application of the common technical processes; resources to be used; and key technical
tasks, activities, and events along with their metrics and success criteria. The SEMP communicates
the technical effort that will be performed by the assigned technical team to the team itself,
managers, customers, and other stakeholders.
6.1.1.7 The SEMP is a living document that captures a program/project's current and evolving SE
strategy and its relationship with the overall program/project management effort throughout the life
cycle of the system. Whereas the primary focus is on the current and upcoming phase in which the
technical effort will be done, the planning extends to a summary of the technical efforts that are
planned for future phases. The SEMP's purpose is to guide all technical aspects of the
program/project.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter6 incorporated into a contract. This document is uncontrolled when printed. Check Page 43 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter6 Page 44 of 142

6.1.2 The SEMP is consistent with higher level SEMPs and the Program/Project Plan, allowing for
tailoring and customization. For example, a Project level SEMP would be consistent with the
Program level SEMP and the Project Plan.
6.1.3 The content of a SEMP for an in-house technical effort may differ from an external technical
effort. For an external technical effort, the NASA SEMP should include details on developing
requirements for source selection, monitoring performance, and transferring and integrating
externally produced products to NASA. (See Appendix J of NASA/SP-2016-6105 for further
details.)
6.1.4 The NASA SEMP also provides the basis for determining the required contractor's
documentation specifying their SE approach to the scope of activities described by the 17 common
technical processes (See Section 4.2.3).
6.1.5 The ETA shall approve the SEMP, waiver or deviation authorizations, and other key technical
documents to ensure independent assessment of technical content [SE-06].

6.2 Technical Team Responsibilities


6.2.1 Working with the Program/Project Manager, the technical team under the guidance of the ETA
determines the appropriate level within the system structure at which SEMPs are to be developed,
taking into account factors such as number and complexity of interfaces, operating environments,
and risk factors.
6.2.2 The technical team establishes the initial SEMP early in the Formulation phase and updates it
as necessary to reflect changes in scope or improved technical development. The technical team will
have their approaches approved through the Center's ETA process 7. As changes occur, the SEMP
will be updated by the technical team, reviewed and reapproved by both the Center's ETA and the
program/project manager, and presented at subsequent life-cycle reviews or their equivalent. The
SEMP is updated at major life-cycle reviews through the SIR.
6.2.3 The technical teams shall define in the program/project SEMP how the required 17 common
technical processes, as tailored, will be recursively applied to the various levels of program/project
product layer system structure during each applicable life-cycle phase [SE-58].
6.2.4 The technical team baselines the SEMP per the Center's procedures and the governing PM
policy. (For example, for spaceflight projects under NPR 7120.5, it is baselined at SRR for projects
and single-project programs and System Definition Review (SDR) for loosely coupled programs,
tightly coupled programs, and uncoupled programs). The content of Appendix J of
NASA/SP-2016-6105 should be used as a guide for producing the work product. For small projects,
the SEMP material can be incorporated in the Project Plan provided the ETA approves the SEMP
material.
6.2.5 The technical team shall ensure that any technical plans and discipline plans are consistent
with the SEMP (or equivalent program/project documentation) and are accomplished as fully
integrated parts of the technical effort [SE-59].
6.2.6 The technical team shall establish TPMs for the program/project that track/describe the current
state versus plan [SE-60]. These measures are typically described in the SEMP per Appendix J of
NASA/SP-2016-6105 guide.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter6 incorporated into a contract. This document is uncontrolled when printed. Check Page 44 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- Chapter6 Page 45 of 142

6.2.7 The technical team shall report the TPMs to the Program/Project Manager on an agreed-to
reporting interval [SE-61].
6.2.8 A technical leading indicator is a subset of the TPMs that provides insight into the potential
future states. The technical team shall ensure that the set of TPMs include the following leading
indicators:
a. Mass margins for projects involving hardware [SE-62].
b. Power margins for projects that are powered [SE-63].
6.2.9 The technical team shall ensure that a set of review trends is created and maintained that
includes closure of review action documentation (RIDs, RFAs, and/or Action Items as established
by the project [SE-64].

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- Chapter6 incorporated into a contract. This document is uncontrolled when printed. Check Page 45 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 46 of 142

Appendix A. Definitions
Acceptable Risk: The risk that is understood and agreed to by the program/project, governing PMC,
Mission Directorate, and other customers such that no further specific mitigating action is required.
(Some mitigating actions might have already occurred.)
Activity: A set of tasks that describe the technical effort to accomplish a process and help generate
expected outcomes.
Affordability: The practice of balancing system performance and risk with cost and schedule
constraints over the system life, satisfying system operational needs in concert with strategic
investment and evolving stakeholder value.
Approve (with respect to Technology Maturation Products from Appendix F): Used for a
product, such as Concept Documentation, that is not expected to be put under classic configuration
control but still requires that changes from the “approved” version are documented at each
subsequent “update.”
Baseline: An agreed-to set of requirements, designs, or documents that will have changes controlled
through a formal approval and monitoring process.
Baseline (with respect to Technology Maturation Products from Appendix F): Indicates putting
the product under configuration control so that changes can be tracked, approved, and
communicated to the team and any relevant stakeholders. The expectation on products labeled
“baseline” is that they will be at least final drafts going into the designated review and baselined
coming out of the review. Baselining a product does not necessarily imply that it is fully mature at
that point in the life-cycle. Updates to baselined documents require the same formal approval
process as the original baseline.
Bidirectional Traceability: The ability to trace any given requirement/expectation to its parent
requirement/expectation and to its allocated children requirements/expectations.
Brassboard: A medium fidelity functional unit that typically tries to make use of as much of the
final product as possible and begins to address scaling issues associated with the operational system.
It does not have the engineering pedigree in all aspects but is structured to be able to operate in
simulated operational environments in order to assess performance of critical functions
Breadboard: A low fidelity unit that demonstrates function only, without respect to form or fit. It
often uses commercial and/or ad hoc components and is not intended to provide definitive
information regarding operational performance.
Certification Package: The body of evidence that results from the verification activities and other
activities such as reports, special forms, models, waivers, or other supporting documentation that is
evaluated to indicate the design is certified for flight/use.
Component Facilities: Complexes that are geographically separated from the NASA Center or
institution to which they are assigned but are still part of the Agency.
Concept of Operations (ConOps): Developed early in Pre-Phase A, describes the overall
high-level concept of how the system will be used to meet stakeholder expectations, usually in a
time sequenced manner. It describes the system from an operational perspective and helps facilitate
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 46 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 47 of 142

time sequenced manner. It describes the system from an operational perspective and helps facilitate
an understanding of the system goals. It stimulates the development of the requirements and
architecture related to the user elements of the system. It serves as the basis for subsequent definition
documents and provides the foundation for the long-range operational planning activities (for
nominal and contingency operations). It provides the criteria for the validation of the system. In
cases where an Operations Concept (OpsCon) is developed, the ConOps feeds into the OpsCon and
they evolve together. The ConOps becomes part of the Concept Documentation.
Construction of Facilities: A NASA corporate program that funds planning for future facility
needs, design of facilities projects, revitalization projects (repair, rehabilitation, and modification of
existing facilities), construction of new facilities, and acquisition of collateral equipment.
Contractor: For the purposes of this NPR, an individual, partnership, company, corporation,
association, or other service having a contract with the Agency for the design, development,
manufacture, maintenance, modification, operation, or supply of items or services under the terms of
a contract to a program or project within the scope of this NPR. Research grantees, research
contractors, and research subcontractors are excluded from this definition.
Corrective Action: Action taken on a product to correct and preclude recurrence of a failure or
anomaly, e.g., design change, procedure change, personnel training.
Critical Event: An event in the operations phase of the mission that is time sensitive and is required
to be accomplished successfully in order to achieve mission success. These events will be
considered early in the life-cycle as drivers for system design.
Customer: The organization or individual that has requested a product and will receive the product
to be delivered. The customer may be an end user of the product, the acquiring agent for the end
user, or the requestor of the work products from a technical effort. Each product within the system
hierarchy has a customer.
Customizing: The modification of recommended SE practices that are used to accomplish the SE
requirements. Examples of these practices are in NASA/SP-2016-6105.
Decision Authority: The individual authorized by the Agency to make important decisions for
programs and projects under their authority.
Derived Requirements: Requirements arising from constraints, consideration of issues implied but
not explicitly stated in the high-level direction provided by Agency and Center institutional
requirements or factors introduced by the selected architecture and design.
Deviation: A documented authorization releasing a program or project from meeting a requirement
before the requirement is put under configuration control at the level the requirement will be
implemented.
Documentation: Captured information and its support medium that is suitable to be placed under
configuration control. Note that the medium may be paper, photograph, electronic storage (digital
documents and models), or a combination thereof.
Enabling Products: The life-cycle support products and services (e.g., production, test,
deployment, training, maintenance, and disposal) that facilitate the progression and use of the
operational end product through its life-cycle. Since the end product and its enabling products are
interdependent, they are viewed as a system. Program/project responsibility thus extends to
responsibility for acquiring services from the relevant enabling products in each life-cycle phase.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 47 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 48 of 142

responsibility for acquiring services from the relevant enabling products in each life-cycle phase.
When a suitable enabling product does not already exist, the program/project that is responsible for
the end product can also be responsible for creating and using the enabling product. An example is
below in Figure A-1.

Figure A-1 – Enabling Product Relationship to End Products

Engineering Technical Authority: One of the three identified lines of technical authority (i.e.,
Engineering, Safety and Mission Assurance, and Health and Medical). ETA includes individuals
who have been formally delegated Technical Authority that flows from the Administrator to the
NASA Chief Engineer and to the Center Directors for further delegation to Center engineering
leadership and individuals. These individuals are funded independent from a program or project and
are a key part of NASA’s system of checks and balances that provides independent oversight of
programs and projects in support of safety and mission success. The ETA establishes and is
responsible for the engineering processes, specifications, rules, best practices, and other activities
throughout the life-cycle, necessary to fulfill programmatic mission performance requirements. The
ETA for the program or project leads and manages the engineering activities, including systems
engineering, design, development, sustaining engineering, and operations.
Engineering Unit: A high fidelity unit that demonstrates critical aspects of the engineering
processes involved in the development of the operational unit. Engineering test units are intended to
closely resemble the final product (hardware/software) to the maximum extent possible and are built
and tested so as to establish confidence that the design will function in the expected environments. In
some cases, the engineering unit can become the final product, assuming proper traceability has
been exercised over the components and hardware handling.
Entrance Criteria: Guidance for minimum accomplishments the program or project fulfills prior to
a life-cycle review.
Expectation: A statement of needs, desires, capabilities, and wants that are not expressed as a
requirement (not expressed as a “shall” statement). Once the set of expectations from applicable
stakeholders is collected, analyzed, and converted into a “shall” statement, the “expectation”
becomes a “requirement.” Expectations can be stated in either qualitative (non-measurable) or
quantitative (measurable) terms. Expectations can be stated in terms of functions, behaviors, or
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 48 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 49 of 142

quantitative (measurable) terms. Expectations can be stated in terms of functions, behaviors, or


constraints with respect to the product being engineered or the process used to engineer the product.
Federal Records: All books, papers, maps, photographs, machine-readable materials, digital
models, or other documentary materials, regardless of physical form or characteristics, made or
received by an agency of the U.S. Government under Federal law or in connection with the
transaction of public business and preserved or appropriate for preservation by that agency or its
legitimate successor as evidence of the organization, functions, policies, decisions, procedures,
operations, or other activities of the Government or because of the informational value of the data in
them.
Final (with respect to Technology Maturation Products from Appendix F): Applied to products
that are expected to exist in a specified form (e.g., minutes and final reports).
Formulation Phase: The first part of the NASA management life cycle defined in NPR 7120.5,
where system requirements are baselined, feasible concepts are determined, a system definition is
baselined for the selected concept(s), and preparation is made for progressing to the Implementation
phase.
Human Systems Integration (HSI): An interdisciplinary and comprehensive management and
technical process that focuses on the integration of human considerations into the system acquisition
and development processes to enhance human system design, reduce life-cycle ownership cost, and
optimize total system performance. Human system domain design activities associated with
operations, training, human factors engineering, safety, quality, maintainability and supportability,
habitability, and survivability are considered concurrently and integrated with all other SE design
activities.
Identify (with respect to identification of processes in Chapter 3): To either use an approved
process or a customized process that is approved by the ETA or their delegate.
Implement (with respect to Implementation of processes in Chapter 3): To document and
communicate the approved process, provide resources to execute the process, provide training on the
process, and monitor and control the process.
Implementation Phase: The part of the NASA management life-cycle defined in NPR 7120.5,
where the detailed design of system products is completed and the products to be deployed are
fabricated, assembled, integrated, and tested and the products are deployed to their customers or
users for their assigned use or mission.
Information Technology Plan: A plan that provides the Information System Description, which
encompasses the complete set of interconnected IT systems, their subsystems and components, and
the system dataset and log data. This plan includes the IT system configuration management,
network diagram, the system interconnections, the data flow, the data type, and the data
categorization/data tagging/metadata. This plan is a foundational element for the IT System Security
Plan and facilitates correct reporting for the Federal Information Technology Acquisition Reform
Act (FITARA). This plan is required for all programs and projects. It would include corporate IT,
industrial control systems, and mission IT (including all computing systems, avionics buses, and
other related components). For a space system the network diagram would include all IT nodes such
as, but not limited to, the Launch Control Center, mission control center, data processing center(s),
science operations center, and on-board system IT.
Information Technology System Security Plan: The formal document prepared by the

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 49 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 50 of 142

information system owner (or common security controls owner for inherited controls) that provides
an overview of the security requirements for the system and describes the security controls in place
or planned for meeting those requirements. The plan can also contain as supporting appendices or as
references, other key security-related documents such as a risk assessment, privacy impact
assessment, system interconnection agreements, contingency plan, security configurations,
configuration management plan, and incident response plan.
Initial (with respect to Technology Maturation Products from Appendix F): Applied to
products that are continually developed and updated as the program or project matures.
Insight: An element of Government surveillance that monitors contractor compliance using
Government-identified metrics and contracted milestones. Insight is a continuum that can range
from low intensity, such as reviewing quarterly reports, to high intensity, such as performing surveys
and reviews.
Institutional Authority: Institutional Authority encompasses all those organizations and authorities
not in the Programmatic Authority. This includes Engineering, Safety and Mission Assurance, and
Health and Medical organizations; Mission Support organizations; and Center Directors.
Iterative: Application of a process to the same product or set of products to correct a discovered
discrepancy or other variation from requirements. (See Recursive and Repeatable.)
Joint Confidence Level: A process and product that helps inform management of the likelihood of
a project’s programmatic success. The probability that cost will be equal to or less than the targeted
cost and that schedule will be equal to or less than the targeted schedule date.
Key Decision Point (KDP): The event at which the Decision Authority determines the readiness of
a program/project to progress to the next phase of the life cycle (or to the next KDP).
Key Performance Parameters (KPP): Those capabilities or characteristics (typically
engineering-based or related to health and medical, safety, or operational performance) considered
most essential for successful mission accomplishment. Failure to meet a KPP threshold can be cause
for the program, project, system, or advanced technology development to be reevaluated or
terminated or for the system concept or the contributions of the individual systems to be reassessed.
A program/project’s KPPs are identified and quantified in the program/project baseline. (See
Technical Performance Parameter.)
Laboratory Environment: An environment that does not address in any manner the environment to
be encountered by the system, subsystem, or component (hardware or software) during its intended
operation. Tests in a laboratory environment are solely for the purpose of demonstrating the
underlying principles of technical performance (functions) without respect to the impact of
environment.
Leading Indicator: A measure for evaluating the effectiveness of how a specific activity is applied
on a program or project in a manner that provides information about impacts likely to affect the
system performance objectives. A leading indicator may be an individual measure or collection of
measures predictive of future system (and project) performance before the performance is realized.
The goal of the indicators is to provide insight into potential future states to allow management to
take action before problems are realized. A technical leading indicator is a subset of the Technical
Performance Measures (TPMs) that provides insight into the potential future states.
Logical Decomposition: The decomposition of the defined technical requirements by functions,

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 50 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 51 of 142

time, and behaviors to determine the appropriate set of logical and data architecture models and
related derived technical requirements. Models may include functional flow block diagrams,
timelines, data control flow, states and modes, behavior diagrams, operator tasks, system data,
metadata, data standards, taxonomy, and functional failure modes.
Loosely Coupled Programs: Programs that address specific objectives through multiple space
flight projects of varied scope. While each individual project has an assigned set of mission
objectives, architectural and technological synergies and strategies that benefit the program as a
whole are explored during the Formulation process. For instance, Mars orbiters designed for more
than one Mars year in orbit are required to carry a communication system to support present and
future landers.
Measure of Effectiveness (MOE): A measure by which a stakeholder’s expectations will be judged
in assessing satisfaction with products or systems produced and delivered in accordance with the
associated technical effort. An MOE is deemed to be critical to not only the acceptability of the
product by the stakeholder but also critical to operational/mission usage. An MOE is typically
qualitative in nature or not able to be used directly as a “design-to” requirement.
Measure of Performance (MOP): A quantitative measure that, when met by the design solution,
will help ensure that an MOE for a product or system will be satisfied. MOPs are given special
attention during design to ensure that the MOEs with which they are associated are met. There are
generally two or more measures of performance for each MOE.
Operational Environment: The environment in which the final product will be operated. In the
case of space flight hardware/software, it is space. In the case of ground-based or airborne systems
that are not directed toward space flight, it will be the environments defined by the scope of
operations. For software, the environment will be defined by the operational platform.
Operations Concept (OpsCon): Developed later in the life-cycle and baselined at PDR, a more
detailed description of how the flight system and the ground system are used together to ensure that
the concept of operation is reasonable. This might include how mission data of interest, such as
engineering data, scientific data, and data standards/metadata are captured, returned to Earth,
processed, made searchable, accessible, and available to users, and archived for future reference. The
OpsCon should describe how the flight system and ground system work together across mission
phases for planning, training, launch, cruise, critical activities, science observations, and end of
mission to achieve the mission. This product should be informed by the ConOps and they should
evolve together. They may exist as a single product or separate products.
Other Interested Parties: Groups or individuals that are not customers of a planned technical effort
but may be affected by the resulting product, the manner in which the product is realized or used, or
who have a responsibility for providing life-cycle support services. A subset of “stakeholders.” (See
Stakeholder.)
Oversight: An element of Government surveillance that occurs in line with the contractor’s
processes in which the Government retains and exercises the right to concur or non-concur with the
contractor’s decisions.
Peer Review: See Peer Review in Appendix G, Table G-19.
Preliminary (with respect to Technology Maturation Products from Appendix F): The
documentation of information as it stabilizes but before it goes under configuration control. It is the
initial development leading to a baseline. Some products will remain in a preliminary state for

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 51 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 52 of 142

multiple reviews. The initial preliminary version is likely to be updated at a subsequent review but
remains preliminary until baselined.
Process: A set of activities used to convert inputs into desired outputs to generate expected
outcomes and satisfy a purpose.
Product: A part of a system consisting of end products that perform operational functions and
enabling products that perform life-cycle services related to the end product or a result of the
technical efforts in the form of a work product (e.g., plan, baseline, or test result).
Product Layer: The end product is decomposed into a hierarchy of smaller and smaller products.
The product layer is defined as a horizontal slice of this product breakdown hierarchy and includes
both the end product and associated enabling products.
Product Realization: The act of making, buying, or reusing a product or the assembly and
integration of lower level realized products into a new product, as well as the verification and
validation that the product satisfies its appropriate set of requirements and the transition of the
product to its customer.
Program: A strategic investment by a Mission Directorate (or mission support office) that has
defined goals, objectives, architecture, funding level, and a management structure that supports one
or more projects.
Program Commitment Agreement: The contract between the Administrator and the cognizant
Mission Directorate Associate Administrator (MDAA) or Mission Support Office Directorate
(MSOD) Associate Administrator for implementation of a program.
Project: A specific investment having defined goals, objectives, requirements, life-cycle cost, a
beginning, and an end. A project yields new or revised products or services that directly address
NASA’s strategic needs. They may be performed wholly in-house; by Government, industry, or
academia partnerships; or through contracts with private industry.
Prototype Unit: The prototype unit demonstrates form, fit, and function at a scale deemed to be
representative of the final product operating in its operational environment. A subscale test article
provides fidelity sufficient to permit validation of analytical models capable of predicting the
behavior of full-scale systems in an operational environment.
Radio Frequency Authorization: Given by the National Telecommunications and Information
Administration (NTIA) for the use of radio frequency spectrum for radio transmissions for
telecommunications or for other purposes.
Realized Product: The desired output from application of the five Product Realization Processes.
The form of this product is dependent on the phase of the product life-cycle and the phase success
criteria.
Recursive: Value that is added to the system by the repeated application of processes to design next
lower layer system products or to realize next upper layer end products within the system structure.
This also applies to repeating application of the same processes to the system structure in the next
life-cycle phase to mature the system definition and satisfy phase success criteria.
Relevant Environment: Not all systems, subsystems, and/or components need to be operated in the
operational environment in order to satisfactorily address performance margin requirements.
Consequently, the relevant environment is the specific subset of the operational environment that is

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 52 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 53 of 142

required to demonstrate critical “at risk” aspects of the final product performance in an operational
environment. It is an environment that focuses specifically on “stressing” the technology advance in
question.
Relevant Stakeholder: A subset of the term “stakeholder” that applies to people or roles that are
designated in a plan for stakeholder involvement. Since “stakeholder” may describe a very large
number of people, attempting to deal with all of them might require unnecessary time and effort. For
this reason, “relevant stakeholder” is used in most practice statements to describe the people
identified to contribute to a specific task.
Repeatable: In the context of systems engineering, a repeatable process is a characteristic that can
be applied to products at any level of the system structure or within any life-cycle phase.
Request for Action/Review Item Discrepancy (RFA/RID): The most common names for the
comment forms that reviewers submit during life-cycle reviews that capture their comments,
concerns, and/or issues about the product or documentation. Each Center defines their own
RFA/RID disposition process.
Requirement: The agreed upon need, capability, capacity, or demand for personnel, equipment,
facilities, or other resources or services by specified quantities for specific periods of time or at a
specified time expressed as a “shall” statement. Acceptable form for a requirement statement is
individually clear, correct, feasible to obtain, unambiguous in meaning, and can be validated at the
level of the system structure at which stated. In pairs of requirement statements or as a set,
collectively, they are not redundant, are adequately related with respect to terms used, and are not in
conflict with one another.
Review Trends: Metrics that show how the identified life-cycle and technical reviews are
progressing such as tracking the closure of action items, RIDs, or RFAs throughout the life-cycle.
Risk: In the context of mission execution, the potential for performance shortfalls, which may be
realized in the future, with respect to achieving explicitly established and stated performance
requirements. The performance shortfalls may be related to any one or more of the following
mission execution domains: (1) safety, (2) technical, (3) cost, and (4) schedule. (See NPR 8000.4.)
Single Point Failure: An independent element of a system (hardware, software, or human), the
failure of which would result in loss of objectives, hardware, or crew.
Single-Project Programs: Programs that tend to have long development and/or operational
lifetimes, represent a large investment of Agency resources, and have contributions from multiple
organizations/agencies. These programs frequently combine program and project management
approaches, which they document through tailoring.
Software: In this directive, “software” is defined as (1) computer programs, procedures and possibly
associated documentation and data pertaining to the operation of a computer system; (2) all or a part
of the programs, procedures, rules, and associated documentation of an information processing
system; (3) program or set of programs used to run a computer; (4) all or part of the programs which
process or support the processing of digital information; (5) part of a product that is the computer
program or the set of computer programs software, and open-source software components. This
definition applies to software developed by NASA, software developed for NASA,
commercial-off-the-shelf (COTS) software, Government-off-the-shelf (GOTS) software,
modified-off-the-shelf (MOTS) software, reused software, auto-generated code, embedded software,
the software executed on processors embedded in Programmable Logic Devices (see

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 53 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 54 of 142

NASA-HDBK-4008), and open-source software components.


Specification: A document or data that prescribes, in a complete, precise, verifiable manner, the
requirements, design, behavior, or characteristics of a system or system component. In this
document, specification is treated as a requirement.
Spectrum Certification: A program or project obtains certification by the NTIA (located within the
Department of Commerce) that the radio frequency required can be made available before a program
or project submits estimates for the development or procurement of major radio spectrum-dependent
communication-electronics systems (including all systems employing space satellite techniques).
Spectrum Certification Stage 1, Conceptual: The initial planning effort has been completed,
including proposed frequency bands and other available characteristics. Certification of spectrum
support for telecommunication systems or subsystems at Stage 1 provides guidance, from the NTIA,
on the feasibility of obtaining certification of spectrum support at subsequent stages. The guidance
provided will indicate any modifications, including more suitable frequency bands, necessary to
assure conformance with the NTIA Manual. (Refer to NPR 2570.1.)
Spectrum Certification Stage 2, Experimental: The preliminary design has been completed and
radiation impact assessment, using such things as test equipment or preliminary models may be
required. Certification of spectrum support for telecommunication systems or subsystems at Stage 2
is a prerequisite for NTIA authorization of radiation in support of experimentation for systems. It
also provides guidance for assuring certification of spectrum support at subsequent stages. (Refer to
NPR 2570.1.)
Spectrum Certification Stage 3, Developmental: The major design has been completed, and
radiation impact assessment may be required during testing. Certification of spectrum support for
telecommunication systems or subsystems at Stage 3 is a prerequisite for NTIA authorization of
radiation in support of developmental testing for systems. It also provides guidelines for assuring
certification of spectrum support at Stage 4. At this point, the intended frequency band will have
been determined and certification at Stage 3 will be required for testing of proposed operational
hardware and potential equipment configurations. (Refer to NPR 2570.1.)
Spectrum Certification Stage 4, Operational: Development has been essentially completed, and
final operating constraints or restrictions required to assure compatibility need to be identified.
Certifying spectrum support for major telecommunication systems or subsystems at Stage 4 is a
prerequisite for NTIA authorization to radiate. Tracking, telemetry, and telecommand operations for
major satellite networks require NTIA Stage 4 certification of spectrum support before the launch of
the spacecraft. Stage 4 certification provides restrictions on the operation of the system or subsystem
as may be necessary to prevent harmful interference. (Refer to NPR 2570.1.)
Stakeholder: A group or individual who is affected by or has an interest or stake in a program or
project. See “Customer,” “Relevant Stakeholder,” and “Other Interested Parties.”
Success Criteria: Specific accomplishments that need to be satisfactorily demonstrated to meet the
objectives of a life-cycle and technical review so that a technical effort can progress further in the
life-cycle. Success criteria are documented in the corresponding technical review plan.
System: The combination of elements that function together to produce the capability required to
meet a need. The elements include all hardware, software, equipment, facilities, personnel,
processes, and procedures needed for this purpose. (Refer to NPR 7120.5.)

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 54 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 55 of 142

Systems Approach: The application of a systematic, disciplined engineering approach that is


quantifiable, recursive, iterative, and repeatable for the development, operation, and maintenance of
systems integrated into a whole throughout the life-cycle of a project or program.
Systems Engineering Engine: The NASA SE model shown in Figure 3-1 that provides the 17
technical processes and their relationship with each other. The model is called an “SE Engine” in
that the appropriate set of processes is applied to the products being engineered to drive the technical
effort.
Systems Engineering Management Plan: The SEMP identifies the roles and responsibility
interfaces of the technical effort and how those interfaces will be managed. The SEMP is the vehicle
that documents and communicates the technical approach, including the application of the common
technical processes; resources to be used; and key technical tasks, activities, and events along with
their metrics and success criteria.
System of Interest: The system whose characteristics are under consideration regardless of where it
lies in the product hierarchy.
System Safety: The application of engineering and management principles, criteria, and techniques
to optimize safety within the constraints of operational effectiveness, time, and cost throughout all
phases of the system life-cycle.
Tailoring: The process used to seek relief from SE NPR requirements consistent with program or
project objectives, allowable risk, and constraints. The tailoring process results in the generation of
deviations and waivers depending on the timing of the request.
Technical Authority: Part of NASA’s system of checks and balances that provides independent
oversight of programs and projects in support of safety and mission success through the selection of
individuals at delegated levels of authority. These individuals are the Technical Authorities.
Technical Authority delegations are formal and traceable to the Administrator. Individuals with
Technical Authority are funded independently of a program or project. TA originates with the
Administrator and is formally delegated to the NASA AA and then to the NASA Chief Engineer for
Engineering Technical Authority; the Chief, Safety and Mission Assurance for SMA Technical
Authority; the NASA Chief Health and Medical Officer for Health and Medical Technical
Authority; and then to the Center Directors.
Technical Performance Measures: The set of performance measures that are monitored by
comparing the current actual achievement of the parameters with that anticipated at the current time
and on future dates. Used to confirm progress and identify deficiencies that might jeopardize
meeting a system requirement. Assessed parameter values that fall outside an expected range around
the anticipated values indicate a need for evaluation and corrective action. Technical performance
measures are typically selected from the defined set of Measures of Performance (MOPs).
Technical Requirements: The requirements that capture the characteristics, features, functions and
performance that the end product will have to meet stakeholder expectations.
Technical Risk: Risk associated with the achievement of a technical goal, criterion, or objective. It
applies to undesired consequences related to technical performance, human health and medical,
safety, mission assets, or environment.
Technical Team: Members of a multidisciplinary team responsible for defining and implementing
the technical aspects of a program or project.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 55 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixA Page 56 of 142

Technology Readiness Level: A scale against which to measure the maturity of a technology. TRLs
range from 1 (Basic Technology Research) to 9 (Systems Test, Launch, and Operations).
Tightly Coupled Programs: Programs with multiple projects that execute portions of a mission(s).
No single project is capable of implementing a complete mission. Typically, multiple NASA Centers
contribute to the program. Individual projects may be managed at different Centers. The program
may also include other agency or international partner contributions.
Transition: The act of delivery or moving a product from one location to another location. This act
can include packaging, handling, storing, moving, transporting, installing, and sustainment activities.

Uncoupled Programs: Programs implemented under a broad theme and/or a common program
implementation concept, such as providing frequent flight opportunities for cost-capped projects
selected through AO or NASA Research Announcements. Each such project is independent of the
other projects within the program.
Update (with respect to Technology Maturation Products from Appendix F): Applied to
products that are expected to evolve as the formulation and implementation processes evolve. Only
expected updates are indicated. However, any document may be updated as needed.
Validation (of a product): The process of showing proof that the product accomplishes the intended
purpose based on stakeholder expectations and the Concept of Operations. May be determined by a
combination of test, analysis, demonstration, and inspection. (Answers the question, “Am I building
the right product?”)
Validation (of requirements): The continuous process of ensuring that requirements are
well-formed (clear and unambiguous), complete (agrees with customer and stakeholder needs and
expectations), consistent (conflict free), and individually verifiable and traceable to a higher level
requirement or goal. (Answers the question, “Will I build the right product?”)
Verification (of a product): Proof of compliance with requirements/specifications. Verification
may be determined by test, analysis, demonstration, inspection, or a combination thereof. (Answers
the question, “Did I build the product right?”)
Waiver: A documented authorization releasing a program or project from meeting a requirement
after the requirement is put under configuration control at the level the requirement will be
implemented.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixA incorporated into a contract. This document is uncontrolled when printed. Check Page 56 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixB Page 57 of 142

Appendix B. Acronyms
AO Announcement of Opportunity
APPEL Academy of Program/Project and Engineering Leadership
ASM Acquisition Strategy Meeting
CDR Critical Design Review
CERR Critical Event Readiness Review
CMMI Capability Maturity Model® IntegrationSM
ConOps Concept of Operations
COTS Commercial Off the Shelf
CPD Center Policy Directive
CPR Center Procedural Requirements
CPU Central Processing Unit
CRM Continuous Risk Management
DCR Design Certification Review
DR Decommissioning Review
DRR Disposal Readiness Review
EEE Electrical, Electronic, and Electromechanical
EMC Electromagnetic Compatibility
EMI Electromagnetic Interference
ETA Engineering Technical Authority
FA Formulation Agreement
FAD Formulation Authorization Document
FMEA/CIL Failure Mode and Effects Analysis/Critical Items List
FMECA Failure Mode, Effects, and Criticality Analysis
FRR Flight Readiness Review
GIDEP Government-Industry Data Exchange Program
GOTS Government Off-the-Shelf
HSI Human Systems Integration
HSIP Human Systems Integration Plan
ILSP Integrated Logistics Support Plan
IMS Integrated Master Schedule

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixB incorporated into a contract. This document is uncontrolled when printed. Check Page 57 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixB Page 58 of 142

IP Institutional Projects
IT Information Technology
JCL Joint Confidence Level
JPL Jet Propulsion Laboratory
KDP Key Decision Point
KPP Key Performance Parameter
LRR Launch Readiness Review
MCR Mission Concept Review
MD Mission Directorate
MDAA Mission Directorate Associate Administrator
MDR Mission Definition Review
MOE Measure of Effectiveness
MOP Measure of Performance
MOTS Modified Off the Shelf
MRR Mission Readiness Review
MSD Mission Support Directorate
NODIS NASA On-Line Directives Information System
NPD NASA Policy Directive
NPR NASA Procedural Requirements
NTIA National Telecommunications and Information Administration
OCE Office of the Chief Engineer
OCHMO Office of the Chief Health and Medical Officer
OpsCon Operations Concept
ORR Operational Readiness Review
OSMA Office of Safety and Mission Assurance
PCA Program Commitment Agreement
PDR Preliminary Design Review
PFAR Post-Flight Assessment Review
PIR Program Implementation Review
PLAR Post-Launch Assessment Review
PM Program or Project Manager
PMC Program Management Committee

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixB incorporated into a contract. This document is uncontrolled when printed. Check Page 58 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixB Page 59 of 142

PRA Probabilistic Risk Assessment


PRR Production Readiness Review
PSR Program Status Review
RF Radio Frequency
RFA Request for Action
RFP Request for Proposals
RID Review Item Discrepancy
RIDM Risk-Informed Decision Making
S&MA Safety and Mission Assurance
SAR System Acceptance Review
SCRM Supply Chain Risk Management
SDR System Definition Review
SE Systems Engineering
SE NPR Systems Engineering NASA Procedural Requirements
SEMP Systems Engineering Management Plan
SIR System Integration Review
SMSR Safety and Mission Success Review
SP Special Publication
SRB Standing Review Board
SRR System Requirements Review
TA Technical Authority
TBD To Be Determined
TBR To Be Resolved
TPM Technical Performance Measure
TRL Technology Readiness Level
TRR Test Readiness Review
U.S.C. United States Code
V&V Verification and Validation

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixB incorporated into a contract. This document is uncontrolled when printed. Check Page 59 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixC Page 60 of 142

Appendix C. Reserved
Guidance for implementing the core SE processes has been moved to NASA/SP-2016-6105.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixC incorporated into a contract. This document is uncontrolled when printed. Check Page 60 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixD Page 61 of 142

Appendix D. Reserved
The outline for the Systems Engineering Management Plan has moved to Appendix J of
NASA/SP-2016-6105.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixD incorporated into a contract. This document is uncontrolled when printed. Check Page 61 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixE Page 62 of 142

Appendix E. Technology Readiness Levels


Hardware Software
TRL Definition Success criteria
Description Description
1 Basic principles Scientific knowledge Scientific Peer reviewed
observed and generated knowledge documentation of
reported. underpinning generated research underlying
hardware technology underpinning basic the proposed
concepts/applications. properties of concept/application.
software
architecture and
mathematical
formulation.
Examples:
a. Initial Paper published providing representative examples of phenomenon as well as
supporting equations for a concept.
b. Conference presentations on concepts and basic observations presented within the
scientific community.
2 Technology Invention begins, Practical Documented
concept and/or practical application application is description of the
application is identified but is identified but is application/concept
formulated. speculative, no speculative; no that addresses
experimental proof experimental proof feasibility and benefit.
or detailed analysis or detailed analysis
is available to is available to
support the support the
conjecture. conjecture. Basic
properties of
algorithms,
representations, and
concepts defined.
Basic principles
coded. Experiments
performed with
synthetic data.
Examples: Carbon nanotube composites were created for lightweight, high-strength
structural materials for space structures.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixE incorporated into a contract. This document is uncontrolled when printed. Check Page 62 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixE Page 63 of 142

3 Analytical and Research and Development of Documented


experimental development are limited analytical/experimental
proof-of-concept initiated, including functionality to results validating
of critical function analytical and validate critical predictions of key
and/or laboratory studies to properties and parameters.
characteristics. validate predictions predictions using
regarding the non-integrated
technology. software
components.
Examples:
a. High efficiency Gallium Arsenide solar panels for space application is conceived for
use over a wide temperature range. The concept critically relies on improved
welding technology for the cell assembly. Samples of solar cell assemblies are
manufactured and submitted to a preliminary thermal environment test at ambient
pressure for demonstrating the concept viability.
b. A fiber optic laser gyroscope is envisioned using optical fibers for the light
propagation and Sagnac Effect. The overall concept is modeled including the laser
source, the optical fiber loop, and the phase shift measurement. The laser injection
in the optical fiber and the detection principles are supported by dedicated
experiments.
c. In Situ Resource Utilization: Demonstrated the application of a cryofreezer for CO2
acquisition and microwave processor for water extraction from soils.
4 Component and/or A low fidelity Key, functionality Documented test
breadboard system/component critical software performance
validation in a breadboard is built components are demonstrating
laboratory and operated to integrated and agreement with
environment. demonstrate basic functionally analytical predictions.
functionality in a validated to Documented definition
laboratory establish of potentially relevant
environment. interoperability and environment.
begin architecture
development.
Relevant
environments
defined and
performance in the
environment
predicted.
Examples:
a. a. Fiber optic laser gyroscope: A breadboard model is built including the proposed
laser diode, optical fiber and detection system. The angular velocity measurement
performance is demonstrated in the laboratory for one axis rotation.
b. b. Bi-liquid chemical propulsion engine: A breadboard of the engine is built and

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixE incorporated into a contract. This document is uncontrolled when printed. Check Page 63 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixE Page 64 of 142

thrust performance is demonstrated at ambient pressure. Calculations are done to


estimate the theoretical performance in the expected environment (e.g., pressure,
temperature).
c. c. A new fuzzy logic approach to avionics is validated in a lab environment by
testing the algorithms in a partially computer-based, partially bench-top component
(with fiber optic gyros) demonstration in a controls lab using simulated vehicle
inputs.
d. d. Variable Specific Impulse Magnetosphere Rocket (VASIMR): 100 kW
magnetoplasma engine operated 10 hours cumulative (up to 3 minutes continuous)
in a laboratory vacuum chamber.
5 Component and/or A medium-fidelity End-to-end Documented test
brassboard component and/or software elements performance
validated in a brassboard, with implemented and demonstrating
relevant realistic support interfaced with agreement with
environment. elements, is built and existing analytical predictions.
operated for systems/simulations Documented definition
validation in a conforming to of scaling
relevant environment target environment. requirements.
so as to demonstrate End-to-end Performance
overall performance software system predictions are made
in critical areas. tested in relevant for subsequent
environment, development phases.
meeting predicted
performance.
Operational
environment
performance
predicted.
Implementations.
Examples:
a. A 6.0-meter deployable space telescope comprised of multiple
petals is proposed for near infrared astronomy operating at
30K. Optical performance of individual petals in a cold
environment is a critical function and is driven by material
selection. A series of 1m mirrors (corresponding to a single
petal) were fabricated from different materials and tested at
30K to evaluate performance and to select the final material
for the telescope. Performance was extrapolated to the
full-sized mirror.
b. For a launch vehicle, TRL 5 is the level demonstrating the
availability of the technology at subscale level (e.g., the fuel
management is a critical function for a re-ignitable upper
stage). The demonstration of the management of the propellant
is achieved on the ground at a subscale level.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixE incorporated into a contract. This document is uncontrolled when printed. Check Page 64 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixE Page 65 of 142

c. ISS Additive Manufacturing Facility: Characterization tests


compare parts and material properties of polymer specimens
printed on ISS to copies printed on the ground.
6 System/sub-system A high-fidelity Prototype Documented test
model or prototype prototype of the implementations of performance
demonstration in a system/subsystems the software demonstrating
relevant that adequately demonstrated on agreement with
environment. addresses all critical full-scale, realistic analytical predictions.
scaling issues is built problems. Partially
and tested in a integrated with
relevant environment existing
to demonstrate hardware/software
performance under systems. Limited
critical documentation
environmental available.
conditions. Engineering
feasibility fully
demonstrated.
Examples:
a. A remote sensing camera includes a large 3-meter telescope, a detection assembly, a
cooling cabin for the detector cooling, and an electronics control unit. All elements
have been demonstrated at TRL 6 except for the mirror assembly and its optical
performance in orbit, which is driven by the distance between the primary and
secondary mirrors needing to be stable within a fraction of a micrometer. The
corresponding critical part includes the two mirrors and their supporting structure. A
full-scale prototype consisting of the two mirrors and the supporting structure is
built and tested in the relevant environment (e.g., including thermo-elastic
distortions and launch vibrations) for demonstrating the required stability can
effectively be met with the proposed design.
b. Vacuum Pressure Integrated Suit Test (VPIST): Demonstrated the integrated
performance of the Orion suit loop when integrated with human-suited test subjects
in a vacuum chamber.
7 System prototype A high-fidelity Prototype software Documented test
demonstration in prototype or exists having all performance
an operational engineering unit that key functionality demonstrating
environment. adequately addresses available for agreement with
all critical scaling demonstration and analytical predictions.
issues is built and test. Well
functions in the integrated with
actual operational operational
environment and hardware/software
platform (ground, systems
airborne, or space). demonstrating
operational
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixE incorporated into a contract. This document is uncontrolled when printed. Check Page 65 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixE Page 66 of 142

operational
feasibility. Most
software bugs
removed. Limited
documentation
available.
Examples:
a. Mars Pathfinder Rover flight and operation on Mars as a technology demonstration
for future micro-rovers based on that system design.
b. First flight test of a new launch vehicle, which is a performance demonstration in the
operational environment. Design changes could follow as a result of the flight test.
c. In-space demonstration missions for technology (e.g., autonomous robotics and
deep space atomic clock). Successful flight demonstration could result in use of the
technology in a future operational mission
d. Robotic External Leak Locator (RELL): Originally flown as a technology
demonstrator, the test article was subsequently put to use to help operators locate the
likely spot where ammonia was leaking from the International Space Station (ISS)
External Active Thermal Control System Loop B.
8 Actual system The final product in All software has Documented test
completed and its final been thoroughly performance verifying
"flight qualified" configuration is debugged and fully analytical predictions.
through test and successfully integrated with all
demonstration. demonstrated operational
through test and hardware and
analysis for its software systems.
intended operational All user
environment and documentation,
platform (ground, training
airborne, or space). documentation, and
If necessary*, life maintenance
testing has been documentation
completed. completed. All
functionality
successfully
demonstrated in
simulated
operational
scenarios.
Verification and
Validation
completed.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixE incorporated into a contract. This document is uncontrolled when printed. Check Page 66 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixE Page 67 of 142

Note:
*"If necessary" refers to the need to life test either for worn out mechanisms, for
temperature stability over time, and for performance over time in extreme environments.
An evaluation on a case-by-case basis should be made to determine the system/systems
that warrant life testing and the tests begun early in the technology development process to
enable completion by TRL 8. It is preferable to have the technology life test initiated and
completed at the earliest possible stage in development. Some components may require
life testing on or after TRL 5.
Examples:
a. a. The level is reached when the final product is qualified for the operational
environment through test and analysis. Examples are when Cassini and Galileo were
qualified, but not yet flown.
b. b. Interim Cryo Propulsion Stage (ICPS): A Delta Cryogenic Second Stage modified
to meet Space Launch System requirements for Exploration Mission-1 (EM-1).
Qualified and accepted by NASA for flight on EM-1.
9 Actual system The final product is All software has Documented mission
flight proven successfully been thoroughly operational results.
through successful operated in an actual debugged and fully
mission operations. mission. integrated with all
operational
hardware and
software systems.
All documentation
has been
completed.
Sustaining software
support is in place.
System has been
successfully
operated in the
operational
environment.
Examples:
a. Flown spacecraft (e.g., Cassini, Hubble Space telescope).
b. Technologies flown in an operational environment.
c. Nanoracks CubeSat Deployer: Commercially developed and operated small satellite
deployer on-board the ISS.

Note: In cases of conflict between NASA directives concerning TRL definitions, NPR 7123.1 will
take precedence.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixE incorporated into a contract. This document is uncontrolled when printed. Check Page 67 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixF Page 68 of 142

Appendix F. Technical Work Product


Maturity Terminology
F.1 For non-configuration-controlled documents, the following terms and definitions are used in this
document:
a. "Initial" is applied to products that are continually developed and updated as the program or
project matures.
b. "Final" is applied to products that are expected to exist in this final form, e.g., minutes and final
reports.
c. "Update" is applied to products that are expected to evolve as the formulation and implementation
processes evolve. Only expected updates are indicated. However, any document may be updated as
needed.
F.2 For configuration-controlled documents, the following terms and definitions are used in
this document:
a. "Preliminary" is the documentation of information as it stabilizes but before it goes under
configuration control. It is the initial development leading to a baseline. Some products will remain
in a preliminary state for multiple reviews. The initial preliminary version is likely to be updated at a
subsequent review but remains preliminary until baselined.
b. "Baseline" indicates putting the product under configuration control so that changes can be
tracked, approved, and communicated to the team and any relevant stakeholders. The expectation on
products labeled "baseline" is that they will be at least final drafts going into the designated review
and baselined coming out of the review. Baselining a product does not necessarily imply that it is
fully mature at that point in the life-cycle. Updates to baselined documents require the same formal
approval process as the original baseline.
c. "Approve" is used for a product, such as Concept Documentation, that is not expected to be put
under classic configuration control but still requires that changes from the "Approved" version are
documented at each subsequent "Update."
d. "Update" is applied to products that are expected to evolve as the formulation and implementation
processes evolve. Only expected updates are indicated. However, any document may be updated as
needed. Updates to baselined documents require the same formal approval process as the original
baseline.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixF incorporated into a contract. This document is uncontrolled when printed. Check Page 68 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 69 of 142

Appendix G. Life-Cycle and Technical Review


Entrance and Success Criteria
This appendix describes the recommended best practices for entrance and success criteria for the
life-cycle and technical reviews required in Chapter 5 regardless of whether the review is
accomplished in a one-step or two-step process. The entrance criteria do not provide a complete list
of all products and their required maturity levels. 1 Terms for maturity levels of technical products
defined in the tables of this appendix are addressed in detail in Appendix F. Additional
programmatic products may also be required by the appropriate governing NPRs for the
project/program.

1 Refer to any applicable NPRs, (e.g., NPR 7120.5, 7150.2, 8705.2) and table 5-1 in this document for required products. Refer to
NASA-HDBK-2203 section 7.8, if applicable, for guidance on software products.

Tailoring and customizing are expected for projects and programs. The entrance and success criteria
and products required for each review will be tailored and customized appropriately for the
particular program or project being reviewed. The decision not to tailor and customize life-cycle
review criteria should be justified to the ETA.
The recommended criteria in the following tables are focused on demonstrating acceptable
program/project technical maturity, adequacy of technical planning and credibility of budget,
schedule and risks (as applicable), and readiness to proceed to the next phase. Customized or tailored
criteria developed by programs or projects for life-cycle reviews should also be focused on assessing
these factors.
Programs and projects use different Appendix G tables for some life-cycle reviews. Programs
(except single-project programs) use tables G-1 and G-2 for program-level SRR and SDRs. Projects
and single-project programs use the tables starting with G-3.
G.1 System Requirements Review (SRR) for Programs
The SRR for a program is used to ensure that the program’s functional and performance
requirements are properly formulated and correlated with the Agency and Mission Directorate
strategic objectives.
Table G-1 – SRR Entrance and Success Criteria for Programs

System Requirements Review for Programs


Entrance Criteria Success Criteria
1. The Program has 1. Evidence is provided that the program formulation
successfully completed the activities are complete and implementation plans
MCR life-cycle review (if are credible to meet mission success.
applicable) and all RFAs 2. The program requirements address critical NASA
and RIDs have been needs as identified in the Mission Directorate
addressed and resolved, or strategic objectives.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 69 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 70 of 142

a timely closure plan exists 3. The program cost and schedule estimates are
for those remaining open. credible to meet program requirements within
2. A preliminary Program available resources.
SRR agenda, success 4. Program implementation plans are credible to
criteria, and instructions to achieve mission success.
the review board have 5. The program risks have been identified and
been agreed to by the mitigation strategies appear reasonable.
technical team, the 6. Allocation of program requirements to projects has
program manager, and the been completed and proposed projects are feasible
review chair prior to the within available resources.
Program SRR. 7. The maturity of the program’s definition and
3. All planned higher level associated plans is sufficient to begin preliminary
SRRs and peer reviews design.
have been successfully 8. The program/project has demonstrated compliance
conducted and with applicable NASA and implementing Center
RID/RFA/Action Items requirements, standards, processes, and procedures.
have been addressed with 9. TBD and TBR items are clearly identified with
the originator or acceptable plans and schedules for their disposition.
designated TA. 10. Program has clearly identified plans and schedules
4. Programmatic products are for applicable RF system certification data package
ready for review at the submissions (experimental, developmental, or
maturity levels stated in operational).
the governing 11. Center spectrum manager at responsible Center was
program/project notified of preliminary requirement assessment.
management NPR.
5. Top program risks with
significant technical, health
and medical, safety, cost,
and schedule impacts have
been identified along with
corresponding mitigation
strategies.
6. An approach for verifying
compliance with program
requirements has been
defined.
7. Procedures for controlling
changes to program
requirements have been
defined and approved.
8. The following primary
products are ready for
review:
a. **Program
requirements

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 70 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 71 of 142

(including
performance, health
and medical, safety,
and defined external
system interfaces to
other programs) are
ready to be baselined
after review
comments are
incorporated.
b. **For single-project
programs and
one-step AO
programs, SEMP (or
equivalent program
documentation) is
ready to be baselined
after review
comments are
incorporated.
9. Other program SRR
technical products have
been made available to the
cognizant participants
prior to the review:
a. *Preliminary
traceability of
program-level
requirements on
projects to the
Agency strategic
goals and Mission
Directorate
requirements and
constraints.
b. *Initial risk
mitigation plans and
resources for
significant technical
risks.
c. *Preliminary cost
and schedule for
uncoupled, loosely
coupled, and tightly
coupled programs.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 71 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 72 of 142

d. *Preliminary
documentation of
Basis of Estimate
(cost and schedule)
for uncoupled,
loosely coupled, and
tightly coupled
programs.
e. *Review Plan ready
to be baselined after
review comments are
incorporated.
f. *Preliminary
Configuration
Management Plan.
g. *Preliminary SEMP
(or equivalent
program
documentation) for
uncoupled, loosely
coupled, tightly
coupled, and
two-step AO
programs.
h. ***RF (radio
frequency) spectrum
requirements have
been identified.
i. *Preliminary IT Plan.
*Product is required for programs/projects covered by NPR 7120.5. If there is disagreement between this table and NPR 7120.5,
NPR 7120.5 takes precedence.

**Product is required per NPR 7123.1.

***Required per NPD 2570.5.

G.2 System Definition Review for Programs


The SDR for a program evaluates the credibility and responsiveness of the proposed program
requirements/architecture to the Mission Directorate requirements, the allocation of program
requirements to the projects, and the maturity of the programs mission/system definition. Programs
(except single-project programs) should use the entrance and success criteria in Table G-2. For
project and single-project programs, refer to Table G-5.
Table G-2 – SDR Entrance and Success Criteria for Programs

System Definition Review for Programs

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 72 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 73 of 142

Entrance Criteria Success Criteria


1. The program has 1. Evidence is provided that the program formulation
successfully completed the activities are complete and implementation plans
previous planned life-cycle are credible to meet mission success.
reviews and all RFAs and 2. The program requirements address critical NASA
RIDs have been addressed needs as identified in the Mission Directorate
and resolved, or a timely strategic objectives.
closure plan exists for 3. The program cost and schedule estimates are
those remaining open. credible to meet program requirements within
2. An agenda for the program available resources.
SDR, success criteria, and 4. Program implementation plans are credible to
instructions to the review achieve mission success.
board have been agreed to 5. The program risks have been identified and
by the technical team, the mitigation strategies appear reasonable.
project manager, and the 6. Allocation of program requirements to projects has
review chair prior to the been completed and proposed projects are feasible
review. within available resources.
3. All planned higher level 7. The maturity of the program’s definition and
SDRs and peer reviews associated plans is sufficient to begin preliminary
have been successfully design.
conducted and 8. The program/project has demonstrated compliance
RID/RFA/Action Items with applicable NASA and implementing Center
have been addressed with requirements, standards, processes, and procedures.
the originator or 9. TBD and TBR items are clearly identified with
designated TA. acceptable plans and schedules for their disposition.
4. Programmatic products are 10. Program has clearly identified plans and schedules
ready for review at the for applicable RF system certification data package
maturity levels stated in submissions (experimental, developmental, or
the governing operational).
program/project 11. Center spectrum manager at responsible Center was
management NPR. notified of preliminary requirement assessment.
5. The following primary
products are ready for
review:
a. **Approved
definition of program
TPMs.
b. **Program
architecture
definition and a list
of specific
supporting projects
that are ready to be
baselined after
review comments are
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 73 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 74 of 142

review comments are


incorporated.
c. **Allocation of
program
requirements to the
supporting projects
that is ready to be
baselined after
review comments are
incorporated.
d. **Approval and
status of technical
performance related
to leading indicators,
margins, TPMs, and
resolution of the
previous review
discrepancies
addressing
effectiveness of
technical
achievement and
communicating the
overall risk to the
project.
e. **SEMP (or
equivalent program
documentation)
ready to be baselined
for uncoupled,
tightly coupled, and
loosely coupled
programs and for
two-step AO
programs.
6. Other SDR technical
products (as applicable) for
hardware, software, and
human system elements
have been made available
to the cognizant
participants prior to the
review:
a. *Updated program
requirements and

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 74 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 75 of 142

constraints.
b. *Traceability of
program-level
requirements on
projects to the
Agency strategic
goals and Mission
Directorate
requirements and
constraints that is
ready to be baselined
after review
comments are
incorporated.
c. Preliminary system
interface definitions.
d. Preliminary
implementation plans.
e. Preliminary
integration plans.
f. *Preliminary
verification and
validation plans.
g. *Updated cost and
schedule.
h. *Updated SEMP (or
equivalent program
documentation) for
one-step AO
programs and
single-project
programs.
i. *Updated risk
mitigation plans and
resources for
significant technical
risks.
j. *Updated cost and
schedule.
k. *Updated
Documentation of
Basis of Estimate
(cost and schedule).
l. *Preliminary plans
for technical work to

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 75 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 76 of 142

be accomplished
during
Implementation.
m. *Updated Review
Plan.
n. *Configuration
Management Plan
that is ready to be
baselined after
review comments are
incorporated.
o. ***Preliminary
assessment of RF
spectrum
requirements.
p. *Baseline IT Plan.
q. *Preliminary IT
System Security Plan.
*Product is required for programs/projects covered by NPR 7120.5. If there is disagreement between this table and NPR 7120.5,
NPR 7120.5 takes precedence.

**Product is required per NPR 7123.1.

G.3 Mission Concept Review


The MCR affirms the mission/project need and evaluates the proposed mission’s objectives and the
ability of the concept to fulfill those objectives.
Table G-3 – MCR Entrance and Success Criteria

Mission Concept Review


Entrance Criteria Success Criteria
1. An agenda for the MCR, 1. Mission objectives are clearly defined and stated
success criteria, and and are unambiguous and internally consistent.
instructions to the review 2. The selected concept(s) satisfactorily meets the
board have been agreed to by stakeholder expectations.
the technical team, the project 3. The mission is feasible. A concept has been
manager, and the review chair identified that is technically and logistically
prior to the review. feasible. A rough cost estimate is within an
2. All planned higher level acceptable cost range.
MCRs and peer reviews have 4. The concept evaluation criteria to be used in
been successfully conducted candidate systems evaluation have been
and RID/RFA/Action Items identified and prioritized.
have been addressed and 5. The need for the mission has been clearly
resolved with the originator or identified.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 76 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 77 of 142

designated TA, or a timely 6. The cost and schedule estimates are credible and
closure plan exists for those sufficient resources are available for project
remaining open. formulation.
3. The following primary 7. The program/project has demonstrated
products are ready for review: compliance with applicable NASA and
a. **Stakeholders have implementing Center requirements, standards,
been identified and processes, and procedures.
stakeholder expectations 8. TBD and TBR items are clearly identified with
have been defined and acceptable plans and schedule for their
are ready to be disposition.
baselined after review 9. Alternative concepts have adequately considered
comments are the use of existing assets or products that could
incorporated. satisfy the mission or parts of the mission.
b. **The concept has been 10. Technical planning is sufficient to proceed to the
developed to a sufficient next phase and includes planning for hardware,
level of detail to software, human systems, and data deliverables.
demonstrate a 11. Risk and mitigation strategies have been
technically feasible identified and are acceptable based on technical
solution to the risk assessments.
mission/project needs 12. Software components meet the success criteria
and is ready to be defined in the NASA-HDBK-2203.
baselined after review 13. Concurrence by the responsible Center spectrum
comments are manager that RF needs have been properly
incorporated. identified and addressed.
c. **MOEs and any other
mission success criteria
have been defined and
are ready to be
approved.
4. Programmatic products are
ready for review at the
maturity levels stated in the
governing program/project
management NPR.
5. Other technical products (as
applicable) for hardware,
software, and human system
elements have been made
available to the cognizant
participants prior to the
review:
a. *Mission/project goals
and objectives that are
ready to be baselined
after review comments

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 77 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 78 of 142

are incorporated.
b. Alternative concepts
that have been analyzed
and are ready to be
reviewed.
c. *Initial risk-informed
cost and schedule
estimates for
implementation.
d. *Preliminary mission
descope options.
e. *A preliminary
assessment performed
by the team of top
technical, cost,
schedule, and safety
risks with developed
associated risk
management and
mitigation strategies and
options.
f. *Preliminary approach
to verification and
validation for the
selected concept(s).
g. *A preliminary SEMP
(or equivalent project
documentation),
including technical
plans.
h. *Technology
Development Plan that
is ready to be baselined
after review comments
are incorporated.
i. *Initial technology
readiness that has been
assessed and
documented with
technology assets,
heritage products, and
gaps identified.
j. Single Point
Failure/Fault Tolerance
philosophy.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 78 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 79 of 142

k. Preliminary engineering
development assessment
and technical plans to
achieve what needs to
be accomplished in the
next phase.
l. Conceptual life-cycle
support strategies
(logistics, supply chain
management,
manufacturing, and
operation).
m. Software criteria and
products, per
NASA-HDBK-2203.
n. ***Preliminary
assessment of RF
spectrum needs.
*Product is required for programs/projects covered by NPR 7120.5. If there is disagreement between this table and NPR 7120.5,
NPR 7120.5 takes precedence.

**Product is required per NPR 7123.1.

***Required per NPD 2570.5.

G.4 System Requirements Review (SRR) for Projects and Single-Project Programs
The SRR evaluates whether the functional and performance requirements defined for the system of
interest are responsive to the program’s requirements and ensures the preliminary project plan and
requirements will satisfy the mission. This table is used for projects and single-project programs. For
other types of programs, refer to Table G-1.
Table G-4 – SRR Entrance and Success Criteria

System Requirements Review for Projects and Single-Project Programs


Entrance Criteria Success Criteria
1. The project has successfully 1. The functional and performance requirements
completed the previously defined for the system are responsive to the
planned life-cycle reviews stakeholder needs and parent requirements, reflect
and responses have been the systems intended operational use, and
made to all RFAs and RIDs, represent capabilities likely to be achieved within
or a timely closure plan the scope of the project.
exists for those items 2. The maturity of the requirements definition and
remaining open. associated plans is sufficient to begin Phase B.
2. A preliminary SRR agenda, 3. The project utilizes a sound process for the
success criteria, and allocation and control of requirements throughout
instructions to the review all levels, and a plan has been defined to complete

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 79 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 80 of 142

board have been agreed to the requirements definition at lower levels within
by the technical team, schedule constraints.
project manager, and review 4. System Interfaces with external entities and
chair prior to the SRR. between major internal elements have been
3. All planned higher level identified.
SRR and peer reviews have 5. Preliminary approaches have been determined for
been successfully conducted how requirements will be verified and validated.
and RID/RFA/Action Items 6. Major risks have been identified and technically
have been addressed and assessed, and viable mitigation strategies have
resolved with the originator been defined.
or designated TA, or a 7. The program/project has demonstrated compliance
timely closure plan exists for with applicable NASA and implementing Center
those remaining open. requirements, standards, processes, and
4. Programmatic products are procedures.
ready for review at the 8. TBD and TBR items are clearly identified with
maturity levels stated in the acceptable plans and schedule for their disposition.
governing program/project 9. Software components meet the success criteria
management NPR. defined in NASA-HDBK-2203.
5. The following primary 10. Concurrence by the responsible Center spectrum
technical products for manager that the program/project has provided
hardware, software and requisite RF system data.
human system elements are 11. Proposed tailoring is appropriate and consistent
available to the cognizant with applicable Agency and Center guidance.
participants prior to the 12. Lessons Learned from other projects and programs
review: have been identified and addressed.
a. **Requirements for 13. Single Point Failure/Fault Tolerance philosophy is
system being reviewed reflected in requirements.
are ready to be
baselined after the
review and
preliminary allocation
to the next lower level
system has been
performed.
b. **For projects,
one-step AO programs
and single-project
programs, the SEMP
(or equivalent
program/project
documentation) is
ready to be baselined
after review comments
are incorporated.
6. Other SRR work products

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 80 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 81 of 142

(as applicable) for hardware,


software, and human system
elements have been made
available to the cognizant
participants.
a. *Updated concept
definition.
b. *Updated concept of
operations.
c. Updated parent
requirements.
d. *Risk management
plan ready to be
baselined after review
comments are
incorporated.
e. *Updated risk
assessment and
mitigations.
f. *Configuration
management plan
ready to be baselined
after review comments
are incorporated.
g. Initial document tree
or model structure.
h. Preliminary
verification and
validation method
identified for each
requirement.
i. Preliminary system
safety analysis.
j. Product certification
or product acceptance
data requirements.
k. Interfaces with
external systems are
identified and
preliminary definitions
are ready to be
baselined (e.g.,
Interface Control
Documents).
l. Preliminary MOPS

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 81 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 82 of 142

and TPM and other


key driving
requirements.
m. Other specialty
discipline analyses, as
required.
n. *Updated cost and
schedule estimates for
the project
implementation.
o. *Updated
documentation of
Basis of Estimate (cost
and schedule).
p. *Updated Technology
Development Plan.
q. *Updated technology
readiness assessment
that has been reviewed
and documented that
includes technology
assets, heritage
products, and
capability gaps
identified.
r. Logistics
documentation (e.g.,
preliminary
maintenance plan).
s. *Initial Human Rating
Certification Package.
t. *System safety and
mission assurance
plan ready to be
baselined after review
comments are
incorporated.
u. *Preliminary
operations concept.
v. Preliminary
engineering
development
assessment and
technical plans to
achieve what needs to

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 82 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 83 of 142

be accomplished in the
next phase.
w. Software criteria and
products, per the
NASA-HDBK-2203.
x. ***RF spectrum
requirements have
been addressed
including preparing
requisite data for the
responsible Center
Spectrum Manager for
possible Stage 1
Certification.
y. *Preliminary IT Plan.
a`. Product certification
or product acceptance
data requirements.
*Product is required for programs/projects covered by NPR 7120.5. If there is disagreement between this table and NPR 7120.5,
NPR 7120.5 takes precedence.

**Product is required per NPR 7123.1.

***Required per NPD 2570.5.

G.5 Mission Definition Review/System Definition Review (MDR/SDR) for Project and
Single-Project Programs
The MDR/SDR evaluates whether the proposed mission/system architecture is responsive to the
program mission/system functional and performance requirements and whether requirements have
been allocated to the next lower product layer and to all functional elements of the mission/system.
This table is to be used for projects and single-project programs.
Table G-5 – MDR/SDR Entrance and Success Criteria (Projects
and Single-Project Program)

Mission Definition Review/ System Definition Review for Projects and Single-Project
Programs
Entrance Criteria Success Criteria
1. The project has successfully 1. The proposed mission/system architecture is
completed the previously credible and responsive to program requirements
planned life-cycle reviews and constraints, including resources.
and all RFAs and RIDs have 2. The program/project cost and schedule estimates
been addressed and resolved, are credible to meet program/project
or a timely closure plan exists requirements within available resources with
for those items remaining acceptable risk.
open. 3. The project’s mission/system definition and

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 83 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 84 of 142

2. A preliminary MDR/SDR associated plans are sufficiently mature to begin


agenda, success criteria, and Phase B.
instructions to the review 4. All technical requirements are allocated to the
board have been agreed to by architectural elements.
the technical team, project 5. The architecture tradeoffs are completed, and
manager, and review chair those planned for Phase B adequately address the
prior to the MDR/SDR. option space.
3. All planned higher level 6. Significant development, mission, and health and
MDR/SDR and peer reviews medical safety risks are identified and technically
have been successfully assessed, and a process and resources exist to
conducted and manage the risks.
RID/RFA/Action Items have 7. Adequate planning exists for the development,
been addressed with the insertion, or deployment of any enabling new
originator or designated TA. technology.
4. Programmatic products are 8. The operations concept is consistent with
ready for review at the proposed design concept(s) and is in alignment
maturity levels stated in the with the mission requirements.
governing program/project 9. The program/project has demonstrated
management NPR. compliance with applicable NASA and
5. The following primary implementing Center requirements, standards,
technical products for processes, and procedures.
hardware, software, and 10. TBD and TBR items are clearly identified with
human system elements are acceptable plans and schedule for their
available to the cognizant disposition.
participants prior to the 11. Software components meet the success criteria
review: defined in NASA-HDBK-2203.
a. **Defined architecture, 12. Concurrence by the responsible Center spectrum
including major manager that RF spectrum considerations have
tradeoffs and options been addressed.
ready to be baselined 13. Procurement and supply chain risk management
after review comments execution is complementary with the technical
are incorporated. development schedule.
b. **Allocation of 14. Architecture supports the Single Point
requirements to next Failure/Fault Tolerance requirements.
lower level is ready to
be baselined after
review comments are
incorporated.
c. **MOPs, TPM, and
other key driving
requirement ready to be
approved.
d. **Approval and status
of technical
performance related to

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 84 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 85 of 142

leading indicators,
margins, TPMs, and
resolution of the
previous review
discrepancies
addressing effectiveness
of technical
achievement and
communicating the
overall risk to the
project.
6. Other MDR/SDR technical
products listed below for both
hardware and software system
elements have been made
available to the cognizant
participants prior to the
review:
a. Supporting analyses,
functional/timing
descriptions, and
allocations of functions
to architecture elements.
b. *Updated SEMP (or
equivalent
program/project
documentation).
c. *Updated risk
management plan.
d. *Updated risk
assessment and
mitigations (if required
by the governing PM
NPR, including PRA).
e. *Updated Technology
Development Plan.
f. *Updated technology
readiness that has been
assessed and
documented with
technology assets,
heritage products, and
gaps identified.
g. *Updated cost and
schedule data with

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 85 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 86 of 142

ranges and a basis of the


estimates.
h. *Preliminary Integrated
Logistics Support Plan
(ILSP).
i. Human Systems
Integration Plan (HSIP)
ready to be baselined
after review comments
are incorporated.
j. *Updated Human
Rating Certification
Package.
k. Preliminary system
interface definitions.
l. Initial technical
resource utilization
estimates and margins.
m. *Updated safety and
mission assurance
(S&MA) plan.
n. *Preliminary operations
concept.
o. Preliminary system
safety analysis.
p. Software criteria and
products, per
NASA-HDBK-2203.
q. ***RF spectrum
considerations
assessment.
r. *Baseline IT Plan.
s. *Preliminary IT System
Security Plan.
*Product is required for programs/projects covered by NPR 7120.5. If there is disagreement between this table and NPR 7120.5,
NPR 7120.5 takes precedence.

**Product is required per NPR 7123.1.

***Required per NPD 2570.5.

G.6 Preliminary Design Review (PDR)


The PDR demonstrates that the preliminary design meets all system of interest requirements with
acceptable risk and within the cost and schedule constraints and establishes the basis for proceeding
with detailed design.
Table G-6 – PDR Entrance and Success Criteria

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 86 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 87 of 142

Preliminary Design Review


Entrance Criteria Success Criteria
1. The Project has successfully 1. The top-level requirements—including
completed the previous planned mission success criteria, TPMs, and any
life-cycle reviews, and all RFAs and sponsor-imposed constraints—are agreed
RIDs have been addressed and upon, finalized, stated clearly, and
resolved, or a timely closure plan consistent with the preliminary design.
exists for those remaining open. 2. The flow down of verifiable requirements
2. A preliminary PDR agenda, success is complete and proper, or, if not, an
criteria, and instructions to the adequate plan exists for timely resolution
review board have been agreed to by of open items. Requirements are traceable
the technical team, project manager, to parent technical requirements and to
and review chair prior to the PDR. mission goals and objectives.
3. All planned lower level PDRs and 3. The program/project cost, schedule, and
peer reviews have been successfully JCL analysis (when required) are credible
conducted, and RID/RFA/Action and within program/project constraints;
Items have been addressed with the are ready for NASA commitment; and are
originator or designated TA. ready for the Management Agreement (for
4. Programmatic products are ready for projects governed by NPR 7120.5).
review at the maturity levels stated 4. The preliminary design is expected to
in the governing program/project meet the requirements at an acceptable
management NPR. level of risk.
5. The following primary products are 5. Definition of the system interfaces (both
ready for review: external entities and between internal
a. **A preliminary design that elements) is consistent with the overall
can be shown to meet all technical maturity, associated risks have
technical requirements and been identified and represents an
performance measures or has acceptable level of risk.
waivers. 6. Any required new technology has been
6. Other PDR technical work products developed to an adequate state of
(as applicable) for hardware, readiness, or backup options exist and are
software, and human system supported to make them viable
elements have been made available alternatives.
to the cognizant participants prior to 7. The project risks are understood and have
the review: been credibly assessed, and plans, a
a. Subsystem design process, and resources exist to effectively
specifications (hardware and manage them.
software), with supporting 8. Safety and mission assurance (e.g., safety,
trade-off analyses and data, as reliability, maintainability, quality
required, that are ready to be controls, quality verifications, supplier
baselined after review risk management, and Electrical,
comments are incorporated. Electronic, and Electromechanical (EEE)
b. Status of technical parts) have been adequately addressed in

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 87 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 88 of 142

performance related to preliminary designs and any applicable


margins, TPMs, and resolution S&MA products (e.g., PRA, system
of the previous review safety analysis, and failure modes and
discrepancies addressing effects analysis) meet requirements, are at
effectiveness of technical the appropriate maturity level for this
achievement and phase of the program/project life-cycle,
communicating the overall risk and indicate that the program/project
to the project. safety/reliability residual risks will be at
c. *Updated technology readiness an acceptable level.
assessment. 9. Adequate technical and programmatic
d. *Updated Technology margins (e.g., mass, power, memory) and
Development Plan. resources exist to complete the
e. *Updated risk assessment and development within budget, schedule, and
mitigation. known risks.
f. *Life-Cycle Cost and 10. The operational concept is technically
Integrated Master Schedule sound, includes (where appropriate)
(IMS) that are ready to be human systems, and includes the flow
baselined after review down of requirements for its execution.
comments are incorporated. 11. Technical trade studies are mostly
When required, the Joint complete to sufficient detail and
Confidence Level (JCL) remaining trade studies are identified,
analysis. plans exist for their closure, and potential
g. *Baselined Integrated impacts are understood.
Logistics Support Plan (ILSP). 12. The program/project has demonstrated
h. *Baselined Project Protection compliance with applicable NASA and
Plan. implementing Center requirements,
i. Applicable technical plans that standards, processes, and procedures.
are ready to be baselined after 13. TBD and TBR items are clearly identified
review comments are with acceptable plans and schedule for
incorporated (e.g., technical their disposition.
performance measurement 14. Preliminary analysis of the primary
plan, contamination control subsystems has been completed and
plan, parts management plan, summarized, highlighting performance
environments control plan, and design margin challenges.
Electromagnetic Interference/ 15. Appropriate modeling and analytical
Electromagnetic Compatibility results are available and have been
(EMI/EMC) control plan, considered in the design.
payload-to-carrier integration 16. Heritage designs have been suitably
plan, assessed for applicability and
producibility/manufacturability appropriateness.
program plan, reliability 17. Manufacturability has been adequately
program plan, quality included in design.
assurance plan). 18. Software components meet the success
j. Applicable design standards criteria defined in NASA-HDBK-2203.
that have been identified and 19. Concurrence by the responsible Center

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 88 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 89 of 142

incorporated. spectrum manager that the


k. *Updated safety analyses and program/project has provided requisite RF
plans. system data.
l. Preliminary engineering 20. Procurement and supply chain risk
drawing tree. management execution is complementary
m. Interface control documents with the technical development schedule.
that are ready to be baselined
after review comments are
incorporated.
n. *Verification/validation plan
that is ready to be baselined
after review comments are
incorporated.
o. Plans to respond to regulatory
requirements (e.g.,
Environmental Impact
Statement), as required, that
are ready to be baselined after
review comments are
incorporated.
p. Preliminary Disposal Plan.
q. Updated technical resource
utilization estimates and
margins.
r. *Baseline operations concept.
s. Updated Human Systems
Integration Plan (HSIP).
t. *Updated Human Rating
Certification Package.
u. Software criteria and products,
per NASA-HDBK-2203.
v. ***Design and requisite data
submitted to Center/facility
spectrum manager for
preparation of request for
certification of Stage 2
spectrum support by at least 60
days prior to PDR.
w. *Updated IT Plan.
x. *Baseline IT System Security
Plan.
y. Procurement status including
Supply Chain Risk
Management (SCRM)
activities (e.g., audits and

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 89 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 90 of 142

assessments, GIDEP,
counterfeit avoidance).
a`. List of potential single point
failures.
*Product is required for programs/projects covered by NPR 7120.5. If there is disagreement between this table and NPR 7120.5,
NPR 7120.5 takes precedence.

**Product is required per NPR 7123.1.

***Required per NPD 2570.5.

G.7 Critical Design Review (CDR)


The CDR demonstrates that the maturity of the design is appropriate to support proceeding with
full-scale fabrication, assembly, integration, and test. The CDR determines that the technical effort
is on track to complete the system development, meeting functional and performance requirements
within the identified cost and schedule constraints at an acceptable risk.
Table G-7 – CDR Entrance and Success Criteria

Critical Design Review


Entrance Criteria Success Criteria
1. The project has successfully 1. The detailed design is expected to meet the
completed the previous requirements with adequate margins.
planned life-cycle reviews, 2. Interface control documents are sufficiently
and all RFAs and RIDs have mature to proceed with fabrication, assembly,
been addressed and resolved integration, and test, and plans are in place to
or a timely closure plan manage any open items.
exists for those remaining 3. The program/project cost and schedule estimates
open. are credible and within program/project
2. A preliminary CDR agenda, constraints.
success criteria, and 4. High confidence exists in the product baseline, and
instructions to the review adequate documentation exists or will exist in a
board have been agreed to timely manner to allow proceeding with
by the technical team, fabrication, assembly, integration, and test.
project manager, and review 5. The product verification and product validation
chair prior to the CDR. requirements and plans are complete.
3. All planned lower level 6. The testing approach is comprehensive, and the
CDRs and peer reviews planning for system assembly, integration, test,
have been successfully and launch site and mission operations is sufficient
conducted, and to progress into the next phase.
RID/RFA/Action Items have 7. Adequate technical and programmatic margins
been addressed with the (e.g., mass, power, memory) and resources exist to
originator or designated TA. complete the development within budget,
4. Programmatic products are schedule, and known risks.
ready for review at the 8. Risks to safety and mission success are understood
maturity levels stated in the and credibly assessed and plans and resources

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 90 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 91 of 142

governing program/project exist to effectively manage them.


management NPR. 9. Safety and mission assurance (e.g., safety,
5. **A baselined detailed reliability, maintainability, quality controls,
design that can be shown to SCRM, QA, and EEE parts) have been adequately
meet all technical addressed in system and operational designs, and
requirements and any applicable S&MA products (e.g., PRA,
performance measures or system safety analysis, and failure modes and
has waivers. effects analysis) meet requirements, are at the
6. Other CDR technical work appropriate maturity level for this phase of the
products (as applicable) for program/project life-cycle, and indicate that the
hardware, software, and program/project safety/reliability residual risks
human system elements will be at an acceptable level.
have been made available to 10. The program/project has demonstrated compliance
the cognizant participants with applicable NASA and implementing Center
prior to the review: requirements, standards, processes, and
a. Product build-to procedures.
specifications along 11. TBD and TBR items are clearly identified with
with supporting acceptable plans and schedule for their disposition.
trade-off analyses and 12. Engineering test units, life test units, and/or
data that are ready to modeling and simulations have been developed
be baselined after and tested per plan.
review comments are 13. Material properties tests are completed along with
incorporated. analyses of loads, stress, fracture control,
b. Fabrication, assembly, contamination generation, and other analyses.
integration, and test 14. EEE parts have been selected, and planned testing
plans and procedures and delivery will support build schedules.
are being developed 15. The operational concept has matured, is at a CDR
and are ready to be level of detail, and has been considered in test
baselined after review planning.
comments are 16. Manufacturability has been adequately included in
incorporated. design.
c. Technical data 17. Software components meet the success criteria
package (e.g., defined in NASA-HDBK-2203.
integrated schematics, 18. Concurrence by the responsible Center spectrum
spares provisioning manager that the program/project has provided
list, interface control requisite RF system data.
documents, 19. Procurement and supply chain risk management
engineering analyses, execution is complementary with the technical
and specifications). development schedule.
d. Status of technical
performance related to
margins, TPMs and
resolution of the
previous review
discrepancies

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 91 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 92 of 142

addressing
effectiveness of
technical achievement
and communicating
the overall risk to the
project.
e. Defined operational
limits and constraints.
f. Updated technical
resource utilization
estimates and margins.
g. Acceptance plans that
are ready to be
baselined after review
comments are
incorporated.
h. Command and
telemetry list.
i. *Updated verification
plan.
j. *Updated validation
plan.
k. Preliminary launch
site operations plan.
l. Preliminary checkout
and activation plan.
m. Preliminary disposal
plan (including
decommissioning or
termination).
n. *Updated technology
readiness assessment.
o. *Updated Technology
Development Plan.
p. *Updated risk
assessment and
mitigation.
q. Updated Human
Systems Integration
Plan (HSIP).
r. *Updated Human
Rating Certification
Package.
s. Updated reliability
analyses and

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 92 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 93 of 142

assessments.
t. *Updated Life-Cycle
Costs and IMS.
u. *Updated ILSP.
v. *Updated Project
Protection Plan.
w. Subsystem-level and
preliminary operations
safety analyses that are
ready to be baselined
after review comments
are incorporated.
x. Systems and
subsystem certification
plans and
requirements (as
needed) that are ready
to be baselined after
review comments are
incorporated.
y. *System safety
analysis with
associated
verifications that is
ready to be baselined
after review comments
are incorporated.
a`. Software criteria and
products, per
NASA-HDBK-2203.
aa. ***Received Stage 2
(Experimental) RF
system certification
signed by NTIA.
ab. ***Provided
measured/as-designed
parameter updates to
Center/facility
spectrum manager for
request for
certification of Stage 4
(Operational)
spectrum support no
later than 60 days
prior to CDR.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 93 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 94 of 142

ac. *Updated IT Plan.


ad. *Updated IT System
Security Plan.
ae. Procurement status
including Supply
Chain Risk
Management (SCRM)
activities (e.g., audits
and assessments,
GIDEP, counterfeit
avoidance,
surveillance tailoring).
af. List of all single point
failures and their
effects as well as
rationale for
acceptance.
*Product is required for programs/projects covered by NPR 7120.5. If there is disagreement between this table and NPR 7120.5,
NPR 7120.5 takes precedence.

**Product is required per NPR 7123.1.

***Required per NPD 2570.5.

G.8 Production Readiness Review (PRR)


For projects developing or acquiring multiple systems/units (typically greater than three or as
determined by the project). The PRR determines the readiness of the system developers to efficiently
produce the required number of systems. It ensures that the production plans, fabrication, assembly,
integration enabling products, operational support, and personnel are in place and ready to begin
production.
Table G-8 – PRR Entrance and Success Criteria

Production Readiness Review


Entrance Criteria Success Criteria
1. The significant 1. High confidence exists that the system requirements
production engineering will be met in the final production configuration.
problems and 2. Adequate resources are in place to support production.
nonconformances 3. The program/project cost and schedule estimates are
encountered during credible and within program/project constraints.
development are 4. Design-for-manufacturing considerations have been
resolved. incorporated to ensure ease and efficiency of
2. The design production and assembly.
documentation needed 5. The product is deemed manufacturable. Evidence is
to support production is provided that the program/project is compliant with
available. NASA and Implementing Center requirements,

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 94 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 95 of 142

3. The production plans standards, processes, and procedures.


(including but not 6. TBD and TBR items are clearly identified, with
limited to critical acceptable plans and schedule for their disposition.
process controls, Alternate sources for resources have been identified for
control limits, and key items.
procedures) and 7. Adequate spares have been planned and budgeted.
preparation to begin 8. Required facilities and tools are sufficient for
fabrication are end-product production.
developed. 9. Specified special tools and test equipment are available
4. The in proper quantities.
production-enabling 10. Production and support staff are qualified.
products are ready. 11. Drawings and/or production models are
5. Raw materials are approved/certified.
approved and certified. 12. Production engineering and planning are sufficiently
6. Resources are mature for cost-effective production.
available, have been 13. Production processes and methods are consistent with
allocated, and are ready quality requirements and compliant with occupational
to support end product health and medical, safety, environmental, and energy
production. conservation regulations.
7. Updated costs and 14. Qualified suppliers are available for materials that are to
schedules. be procured.
8. Risks have been 15. Software components meet the success criteria defined
identified, credibly in NASA-HDBK-2203.
assessed, and 16. Concurrence by the responsible Center spectrum
characterized, and manager that program/project complies with RF
mitigation efforts have spectrum policy and regulation.
been defined. 17. PRR plans are mature and results to date indicate high
9. The bill of materials is likelihood of supplier quality control success.
available and critical
parts identified.
10. Delivery schedules are
available.
11. In-process and
end-item inspections
and tests have been
identified and planned.
12. Software criteria and
products, per
NASA-HDBK-2203.
13. *Spectrum (radio
frequency)
consideration
assessments.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 95 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 96 of 142

*Required per NPD 2570.5.

G.9 System Integration Review (SIR)


An SIR ensures segments, components, and subsystems are on schedule to be integrated into the
system of interest, and integration facilities, support personnel, and integration plans and procedures
are on schedule to support integration.
Table G-9 – SIR Entrance and Success Criteria

System Integration Review


Entrance Criteria Success Criteria
1. The project has successfully 1. Integration plans and procedures are on track for
completed the previous completion and approval to support system
planned life-cycle reviews, integration.
and all RFAs and RIDs have 2. Previous component, subsystem, and system test
been addressed and resolved results form a satisfactory basis for proceeding to
or a timely closure plan integration.
exists for those remaining 3. The program/project cost and schedule estimates
open. are credible with adequate margins and within
2. A preliminary SIR agenda, program/project constraints.
success criteria, and 4. Risks are identified and accepted by
instructions to the review program/project leadership, as required.
board have been agreed to by 5. The program/project has demonstrated
the technical team, project compliance with applicable NASA and
manager, and review chair implementing Center requirements, standards,
prior to the SIR. processes, and procedures.
3. The following primary 6. TBD and TBR items are clearly identified with
products are ready for review: acceptable plans and schedule for their
a. **Integration plans dispositions.
baselined at PDR that 7. The integration procedures and workflow have
have been updated and been clearly defined and documented or are on
approved. schedule to be clearly defined and documented
b. **Initial V&V results prior to their need date.
from any lower tier 8. The review of the integration plans, as well as the
products that have procedures, environment, and configuration of the
been verified. items to be integrated, provides a reasonable
4. Programmatic products are expectation that the integration will proceed
ready for review at the successfully.
maturity levels stated in the 9. All training necessary to properly integrate the
governing program/project system has been performed.
management NPR. 10. Software components meet the success criteria
5. Status of technical defined in NASA-HDBK-2203.
performance related to
margins, TPMs, and
resolution of the previous
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 96 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 97 of 142

resolution of the previous


review discrepancies
addressing effectiveness of
technical achievement and
communicating the overall
risk to the project.
6. Integration procedures have
been identified and are
scheduled for completion
prior to their need dates.
7. Segments and/or components
are on schedule to be
available for integration.
8. Mechanical and electrical
interface requirements for
hardware necessary to start
system integration have been
verified in accordance with
the interface control
documentation and plans for
verification of remaining
hardware exist.
9. All functional, unit-level,
subsystem, and qualification
testing has been conducted
successfully or is on track to
be conducted prior to
scheduled integration.
10. Integration facilities,
including clean rooms,
ground support equipment,
handling fixtures, overhead
cranes, and electrical test
equipment, and their
associated quality controls
are ready or will be available
when required.
11. Support personnel have been
trained.
12. Handling and safety
requirements have been
documented.
13. All known system
discrepancies have been
identified, dispositioned, and

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 97 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 98 of 142

are on schedule for closure.


14. The quality control
organization is ready to
support integration effort.
15. Other SIR technical products
(as applicable) for hardware,
software, and human system
elements have been made
available to the cognizant
participants prior to the
review:
a. *Updated Life-Cycle
Costs and IMS.
b. *Updated design
solution definition.
c. Updated interface
definition(s).
d. *Updated verification
and validation plans.
e. Final transportation
criteria and instructions.
f. *Preliminary mission
operations plans.
g. Preliminary
decommissioning plans.
h. Preliminary disposal
plans.
i. Software criteria and
products, per
NASA-HDBK-2203.
j. Procurement status
including Supply Chain
Risk Management
(SCRM) activities
(e.g., audits and
assessments, GIDEP,
counterfeit avoidance).
*Product is required for programs/projects covered by NPR 7120.5. If there is disagreement between this table and NPR 7120.5,
NPR 7120.5 takes precedence.

**Product is required per NPR 7123.1.

G.10 Test Readiness Review (TRR)


A TRR for each planned test or series of tests ensures that the test article (hardware/software), test
facility, support personnel, and test procedures are ready for testing and data acquisition, reduction,
and control.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 98 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 99 of 142

and control.
Table G-10 – TRR Entrance and Success Criteria

Test Readiness Review


Entrance Criteria Success Criteria
1. A preliminary TRR 1. Adequate test plans are completed and approved for the
agenda, success system under test.
criteria, and 2. Adequate identification and coordination of required
instructions to the test resources are completed.
review team have been 3. The program/project has demonstrated compliance with
agreed to by the applicable NASA and implementing Center
technical team, project requirements, standards, processes, and procedures.
manager, and review 4. TBD and TBR items are clearly identified with
chair prior to the TRR. acceptable plans and schedule for their disposition.
2. The objectives of the 5. Risks have been identified, credibly assessed, and
testing have been appropriately mitigated.
clearly defined and 6. Residual risk is accepted by program/project leadership
documented. as required.
3. Approved test plans, 7. Plans to capture any lessons learned from the test
test procedures, test program are documented.
environment, and 8. The objectives of the testing have been clearly defined
configuration of the and documented, and the review of all the test plans, as
test item(s) that well as the procedures, environment, and configuration
support test objectives of the test item, provides a reasonable expectation that
are available. the objectives will be met.
4. All test interfaces have 9. The test cases have been analyzed and are consistent
been placed under with the test plans and objectives.
configuration control 10. Test personnel have received appropriate training in test
or have been defined operation and health and medical safety procedures.
in accordance with an 11. *Concurrence by the responsible Center spectrum
agreed to plan, and manager that all tests are performed. in accordance with
version description spectrum policy and regulation.
document(s) for both
test and support
systems have been
made available to TRR
participants prior to
the review.
5. All known system
discrepancies have
been identified and
dispositioned in
accordance with an
agreed-upon plan.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 99 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 100 of 142

6. All required test


resources—people
(including a
designated test
director), facilities, test
articles, test
instrumentation, and
other test-enabling
products—have been
identified and are
available to support
required tests.
7. Roles and
responsibilities of all
test participants are
defined and agreed to.
8. Test safety planning
has been
accomplished, and all
personnel have been
trained.
9. Spectrum (radio
frequency)
considerations
addressed.
10. As-built hardware and
software
documentation
defining the
configuration of the
item under test are
released and under
configuration control.
*Required per NPD 2570.5.

G.11 System Acceptance Review (SAR)


The SAR verifies the completeness of the specific end products in relation to their expected maturity
level, requirement verification, compliance to stakeholder expectations, and ensures that the system
of interest has sufficient technical maturity to authorize its acceptance for operational use or delivery
to the launch site or operational environment.
Table G-11 – SAR Entrance and Success Criteria

System Acceptance Review

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 100 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 101 of 142

Entrance Criteria Success Criteria


1. The project has successfully 1. Required tests and analyses are complete and
completed the previous indicate that the system will perform properly in
planned life-cycle reviews, the expected operational environment.
RFA/RIDs have been closed, 2. Risks are identified and mitigated to acceptable
and plans to complete open levels.
work are defined. 3. System meets the established acceptance criteria.
2. A preliminary SAR agenda, 4. TBD and TBR items are resolved.
success criteria, and 5. Acceptance data package is complete and reflects
instructions to the review the delivered system.
team have been agreed to by 6. All applicable lessons learned for organizational
the technical team, project improvement and system operations are captured.
manager, and review chair 7. Software components meet the success criteria
prior to the review. defined in NASA-HDBK-2203.
3. The following SAR technical 8. *Concurrence by the responsible Center spectrum
products have been made manager that the Stage 4 (Operational) system
available to the cognizant certification has been obtained and the system is
participants prior to the compliant with spectrum policy and regulation.
review: 9. The system hardware, software, documentation,
a. Results of the SARs and associated products are complete and ready
conducted at the major for acceptance.
suppliers.
b. Product verification
results.
c. Product validation
results.
d. Documentation that the
delivered system
complies with the
established acceptance
criteria.
e. Documentation that the
system will perform
properly in the
expected operational
environment.
f. Technical data package
that has been updated
to include all test
results.
g. Final Certification
Package.
h. Baselined as-built
hardware and software
documentation.
This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 101 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 102 of 142

documentation.
i. Updated risk
assessment and
mitigation.
j. Required safety,
shipping, handling,
checkout, and
operational plans and
procedures.
k. Software criteria and
products, per
NASA-HDBK-2203.
l. *Received Stage 4
(Operational) system
certification signed by
NTIA.
m. Completed planning for
sustaining the system.
n. Updated list of all
single point failures
and their effects.
*Required per NPD 2570.5.

G.12 Operational Readiness Review (ORR)


The ORR ensures that all system and support (flight and ground) hardware, software, personnel,
procedures, supporting capabilities, and user documentation accurately reflect the deployed state of
the system and are operationally ready.
Table G-12 – ORR Entrance and Success Criteria

Operational Readiness Review


Entrance Criteria Success Criteria
1. All planned ground-based testing 1. The system, including all enabling products,
has been completed. is determined to be ready to be placed in an
2. Test failures and anomalies from operational status.
verification and validation testing 2. All applicable lessons learned for
have been resolved, and the organizational improvement and systems
results/mitigations/work-arounds operations have been captured.
have been incorporated into 3. All waivers and anomalies have been closed.
supporting and enabling 4. Systems hardware, software, personnel,
operational products. tools, supporting infrastructure, and
3. All operational supporting and procedures are in place to support
enabling products (e.g., facilities, operations.
equipment, documents, software 5. Operations plans and schedules are

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 102 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 103 of 142

tools, databases) that are necessary consistent with mission objectives.


for nominal and contingency 6. Mission risks have been identified, planned
operations have been tested and mitigations are adequate, and residual risks
delivered/installed at the site(s) are accepted by the program/project
necessary to support operations. manager.
4. Programmatic products are ready 7. Testing is consistent with the expected
for review at the maturity levels operational environment.
stated in the governing 8. The program/project cost and schedule
program/project management NPR. estimates are credible and within
5. Operations documentation (e.g., program/project constraints.
handbook, procedures) has been 9. The program/project has demonstrated
written, verified, and approved. compliance with applicable NASA and
6. Users/operators have been trained implementing Center requirements,
on the correct operation of the standards, processes, and procedures.
system. 10. TBD and TBR items are resolved.
7. Operational contingency planning 11. Software components meet the success
has been completed, and criteria defined in NASA-HDBK-2203.
operations personnel have been 12. Concurrence by the responsible Center
trained on their use. spectrum manager that all necessary
8. The following primary products spectrum certification(s) and
are ready for review: authorization(s) have been obtained.
a. **Preliminary V&V results. 13. An operational Human Systems Integration
b. **Baseline capability has been established and HSI
decommissioning plan. planning is in place for the remaining
c. **Baseline Disposal Plans. life-cycle phases.
9. Other ORR technical products
have been made available to the
cognizant participants prior to the
review:
a. *Updated cost and schedule.
b. *Updated Project Protection
Plan.
c. Updated as-built hardware
and software documentation.
d. Baselined operations plans.
e. Updated operational
procedures.
f. Preliminary certification for
flight/use.
g. *Updated Human Rating
Certification Package.
h. Software criteria and
products, per
NASA-HDBK-2203.
10. ***Received Stage 4 (Operational)

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 103 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 104 of 142

system certification signed by


NTIA.
11. ***All requisite radio frequency
authorizations are in place.
12. Updated list of all single point
failures (SPF) and their effects
including rationale for acceptance
of any new SPFs.
*Product is required for programs/projects covered by NPR 7120.5. If there is disagreement between this table and NPR 7120.5,
NPR 7120.5 takes precedence.

**Product is required per NPR 7123.1.

***Required per NPD 2570.5.

G.13 Mission Readiness Review/Flight Readiness Review (MRR/FRR)


The MRR/FRR examines tests, demonstrations, analyses, and audits that determine the system’s
readiness for a safe and successful flight or launch and for subsequent flight operations. The
MRR/FRR also ensures that all flight and ground hardware, software, personnel, and procedures are
operationally ready.
Table G-13 – MRR/FRR Entrance and Success Criteria

Mission Readiness Review/Flight Readiness Review


Entrance Criteria Success Criteria
1. The flight vehicle/system is
ready for flight/mission
operations.
2. The hardware is deemed
1. The system and support elements are ready and acceptably safe for
have been properly configured for flight/mission operations.
flight/mission operations. 3. Certification that flight
2. System and support element interfaces have operations can safely proceed
been demonstrated to function as expected. with acceptable risk has been
3. The system state supports a launch “go” achieved.
decision based on the established go/no-go 4. Flight and ground software
criteria. elements are ready to support
4. Programmatic products are ready for review at launch and flight operations.
the maturity levels stated in the governing 5. Interfaces have been checked
program/project management NPR. and demonstrated to be
5. Failures and anomalies from previously functional.
completed flights, tests, and reviews have been 6. The program/project has
resolved, and the demonstrated compliance with
results/mitigations/work-arounds have been applicable NASA and
incorporated into supporting and enabling implementing Center
operational products. requirements, standards,

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 104 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 105 of 142

6. The following primary products are ready for processes, and procedures.
review: 7. TBD and TBR items are
a. **Final certification for flight/use. resolved.
b. **Baselined V&V results. 8. Open items and waivers have
7. Other MRR/FRR technical products have been been examined and residual
made available to the cognizant participants risk from these is deemed to be
prior to the review: acceptable.
a. *Updated cost. 9. The flight and recovery
b. *Updated schedule. environmental factors are
c. Updated as-built hardware and software within constraints.
documentation. 10. All open safety and mission
d. Updated operations procedures. risk items have been addressed,
e. Updated decommissioning plan. and the residual risk is deemed
f. Updated disposal plan acceptable.
g. Software criteria and products, per 11. Supporting organizations are
NASA-HDBK-2203. ready to support flight/mission
8. ***Received Stage 4 (Operational) system operations.
certification signed by NTIA. 12. Software components meet the
9. ***All requisite spectrum (radio frequency) success criteria defined in
authorizations are in place. NASA-HDBK-2203.
10. Updated list of all single point failures and their 13. Responsible Center spectrum
effects. manager(s) concur that all
necessary spectrum
certification(s) and
authorization(s) have been
obtained.
*Product is required for programs/projects covered by NPR 7120.5. If there is disagreement between this table and NPR 7120.5,
NPR 7120.5 takes precedence.

**Product is required per NPR 7123.1.

***Required per NPD 2570.5.

G.14 Post-Launch Assessment Review (PLAR)


A PLAR evaluates the readiness of the spacecraft systems to proceed with full, routine operations
after post-launch deployment. The review also evaluates the status of the project plans and the
capability to conduct the mission with emphasis on near-term operations and mission-critical events.
Table G-14 – PLAR Entrance and Success Criteria

Post-Launch Assessment Review


Entrance Criteria Success Criteria

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 105 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 106 of 142

1. The launch and early 1. The observed spacecraft and science payload performance
operations agrees with prediction, or if not, is adequately understood
performance, so that future behavior can be predicted with confidence.
including (when 2. All anomalies have been adequately documented and
appropriate) the early their impact on operations assessed. Further, anomalies
propulsive maneuver impacting spacecraft health and medical, safety, or
results, are available. critical flight operations have been properly dispositioned.
2. The observed 3. The mission operations capabilities, including staffing
spacecraft and and plans, are adequate to accommodate the actual flight
science instrument performance.
performance, 4. Open items, if any, on operations identified as part of the
including instrument ORR have been satisfactorily dispositioned.
calibration plans and 5. *Concurrence by the responsible Center spectrum
status, are available. manager that the system is compliant with spectrum
3. The launch vehicle policy and regulation.
performance
assessment and
mission implications,
including launch
sequence assessment
and launch
operations
experience with
lessons learned, are
completed.
4. The mission
operations and
ground data system
experience, including
tracking and data
acquisition support
and spacecraft
telemetry data
analysis, is available.
5. The mission
operations
organization,
including status of
staffing, facilities,
tools, and mission
software (e.g.,
spacecraft analysis
and sequencing), is
available.
6. In-flight anomalies

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 106 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 107 of 142

and the responsive


actions taken,
including any
autonomous fault
protection actions
taken by the
spacecraft or any
unexplained
spacecraft telemetry,
including alarms, are
documented.
7. The need for
significant changes to
the system (e.g.,
hardware, software,
or interfaces),
support systems,
operations (e.g.,
schedules, processes
and procedures), and
staffing has been
documented.
8. Documentation is
updated, including
any updates
originating from the
early operations
experience.
9. Plans for post-launch
development have
been addressed.
*Required per NPD 2570.5.

G.15 Critical Event Readiness Review (CERR)


A CERR evaluates the readiness of the project and the flight system to execute the critical event
during flight operation.
Table G-15 – CERR Entrance and Success Criteria

Critical Event Readiness Review


Entrance Criteria Success Criteria

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 107 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 108 of 142

1. Critical event/activity 1. The critical activity design complies with


requirements and constraints have requirements. The preparation for the critical
been identified, including activity, including the verification and
spectrum considerations. validation, is thorough.
2. Critical event/activity design and 2. The project (including all the systems,
implementation are complete. supporting services, and documentation) is
3. Critical event/activity testing is ready to support the activity.
complete. 3. The requirements for the successful
4. Critical event/activity operations execution of the critical event(s) are
planning, including contingencies, complete and understood and have flowed
is complete. down to the appropriate levels for
5. Operations personnel training for implementation.
the critical event/activity has been 4. Any TBD and TBR items related to the
conducted. critical event have been resolved.
6. Critical event/activity sequence 5. All open risk items related to the critical
verification and validation is event have been addressed, and the residual
complete. risk is deemed acceptable.
7. Flight system is healthy and 6. *Concurrence by the responsible Center
capable of performing the critical spectrum manager that the system is
event/activity. compliant with spectrum policy and
8. Flight failures and anomalies from regulation.
critical event/activity testing have
been resolved, and the
results/mitigations/work-arounds
have been incorporated into
supporting and enabling
operational products.
9. The following technical products
have been made available to the
cognizant participants prior to the
review:
a. Final certification for critical
event readiness.
b. Updated operations
procedures.
*Required per NPD 2570.5.

G.16 Post-Flight Assessment Review (PFAR)


The PFAR evaluates how well mission objectives were met during a mission and identifies all flight
and ground system anomalies that occurred during the flight and determines the actions necessary to
mitigate or resolve the anomalies for future flights of the same spacecraft design.
Table G-16 – PFAR Entrance and Success Criteria

Post-Flight Assessment Review

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 108 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 109 of 142

Entrance Criteria Success Criteria


1. All anomalies that 1. Formal final report documenting flight performance and
occurred during the recommendations for future missions is complete and
mission, as well as adequate.
during preflight 2. All anomalies have been adequately documented and
testing, countdown, dispositioned.
and ascent, are 3. The impact of anomalies on future flight operations has
dispositioned. been assessed and documented.
2. All flight and 4. Reports and other documentation have been retained for
post-flight performance comparison and trending.
documentation 5. Responsible Center spectrum manager was notified of
applicable to future any RF spectrum interference issues.
flights of the 6. Recommendations for updates to the system design, test
spacecraft or the and operations procedures, or safety inspections have
design is available. been identified and a credible plan exists to incorporate
3. All planned activities the changes.
to be performed
post-flight have been
completed.
4. Problem reports,
corrective action
requests, and
post-flight anomaly
records are
completed. Include
spectrum (radio
frequency)
interference or other
related factors during
assessment.
5. All post-flight
hardware and flight
performance data
evaluation reports are
completed.
6. Plans for retaining
assessment
documentation and
imaging have been
made.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 109 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 110 of 142

G.17 Decommissioning Review (DR)


A DR confirms the decision to terminate or decommission the system and assesses the readiness of
the system for the safe decommissioning and disposal of system assets. This review can be applied
for the system that was deployed through earlier efforts of this program/project or for a legacy
capability that will be replaced by the system being deployed.
Table G-17 – DR Entrance and Success Criteria

Decommissioning Review
Entrance Criteria Success Criteria
1. The requirements 1. The rationale for decommissioning is documented.
associated with 2. The decommissioning plan is complete, meets
decommissioning are requirements, is approved by appropriate
defined. management, and is compliant with applicable
2. Plans are in place for Agency safety, environmental, and health
decommissioning and any regulations.
other removal from service 3. Operations plans for decommissioning, including
activities. contingencies, are complete and approved.
3. Resources are in place to 4. Adequate resources (schedule, budget, and staffing)
support and implement have been identified and are available to
decommissioning. successfully complete all decommissioning
4. Programmatic products are activities.
ready for review at the 5. All required support systems for decommissioning
maturity levels stated in the are available.
governing program/project 6. All personnel have been properly trained for the
management NPR. nominal and contingency decommissioning
5. Health and medical, safety, procedures.
environmental, and any 7. Safety, health, and environmental hazards have
other constraints have been been identified, and controls have been verified.
identified. 8. Risks associated with the decommissioning have
6. Current system capabilities been identified and adequately mitigated.
relating to 9. Residual risks have been accepted by the required
decommissioning are management.
understood. 10. Any TBD and TBR items are clearly identified
7. Off-nominal operations, all with acceptable plans and schedule for their
contributing events, disposition.
conditions, and changes to 11. Plans for archival and subsequent analysis of
the originally expected mission data have been defined and approved, and
baseline have been arrangements have been finalized for the execution
considered and assessed. of such plans.
8. The following primary 12. Plans for the capture and dissemination of
product is ready for review: appropriate lessons learned during the project
a. **Updated life-cycle have been defined and approved.
Decommissioning 13. Plans for transition of personnel have been defined

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 110 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 111 of 142

Plan and approved.


9. Other DR technical 14. Concurrence by the responsible Center spectrum
products have been made manager that the decommissioning plans are
available to the cognizant compliant with spectrum policy and regulation.
participants prior to the
review:
a. *Updated cost.
b. Updated schedule.
c. *Updated disposal
plan.
*Product is required for programs/projects covered by NPR 7120.5. If there is disagreement between this table and NPR 7120.5,
NPR 7120.5 takes precedence.

**Product is required per NPR 7123.1.

G.18 Disposal Readiness Review (DRR)


A DRR confirms the readiness for the final disposal of the system assets. This review can be applied
for the system that was deployed through earlier efforts of this program/project or for a legacy
capability that will be disposed of and replaced by the system being deployed.
Table G-18 – DRR Entrance and Success Criteria

Disposal Readiness Review


Entrance Criteria Success Criteria
1. Requirements 1. The rationale for disposal is documented.
associated with 2. The disposal plan is complete, meets requirements, is
disposal are defined. approved by appropriate management, and is compliant
2. Plans are in place for with applicable Agency safety, environmental, and health
disposal and any regulations.
other removal from 3. Operations plans for disposal, including contingencies,
service activities. are complete and approved.
3. Resources are in 4. All required support systems for disposal are available.
place to support 5. All personnel have been properly trained for the nominal
disposal. and contingency disposal procedures.
4. Safety, 6. Safety, health, and environmental hazards have been
environmental, identified, and controls have been verified.
health, and any other 7. Risks associated with the disposal have been identified
constraints are and adequately mitigated.
described. 8. Residual risks have been accepted by the required
5. Current system management.
capabilities related to 9. If hardware is to be recovered from orbit:
disposal are a. Return site activity plans have been defined and
described and approved.
understood. b. Required facilities are available and meet
6. Off-nominal requirements, including those for contamination

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 111 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 112 of 142

operations, all control, if needed.


contributing events, c. Transportation plans are defined and approved.
conditions, and d. Shipping containers and handling equipment, as
changes to the well as contamination and environmental control
originally expected and monitoring devices, are available.
baseline have been 10. Plans for disposition of mission-owned assets (i.e.,
considered and hardware, software, and facilities) have been defined and
assessed. approved.
7. *Updated cost. 11. Adequate resources (schedule, budget, and staffing) have
8. Updated schedule. been identified and are available to successfully complete
9. The following all disposal activities.
primary product is 12. All mission and project data and documentation has been
ready for review: archived per disposal plan.
a. **Updated 13. TBD and TBR items related to system disposal have all
disposal plan. been dispositioned.
14. Concurrence by the responsible Center spectrum manager
that the disposal plans are compliant with spectrum policy
and regulation.
*Product is required for programs/projects covered by NPR 7120.5. If there is disagreement between this table and NPR 7120.5,
NPR 7120.5 takes precedence

**Product is required per NPR 7123.1.

G.19 Peer Reviews


Peer reviews provide the technical insight essential to ensure product and process quality. Peer
reviews are focused, in-depth technical reviews that support the evolving design and development of
a product, including critical documentation or data packages. The participants in a peer review are
the technical experts and key stakeholders for the scope of the review. Another purpose of the peer
review is to add value and reduce risk through expert knowledge infusion, confirmation of approach,
identification of defects, and specific suggestions for product improvements.
Table G-19 – Peer Review Entrance and Success Criteria

Peer Review
Entrance Criteria Success Criteria
1. The product to be reviewed 1. Peer review has thoroughly evaluated the technical
(e.g., document, process, integrity and quality of the product.
model, design details) has 2. Any defects have been identified and characterized.
been identified and made 3. Results of the peer review are communicated to the
available to the review team. appropriate project personnel.
2. Peer reviewers independent 4. Spectrum-related aspects have been concurred to
from the project have been by the responsible Center spectrum manager.
selected for their technical
background related to the
product being reviewed.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 112 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 113 of 142

3. A preliminary agenda,
success criteria, and
instructions to the review
team have been agreed to
by the technical team and
project manager.
4. Rules have been
established to ensure
consistency among the
team members involved in
the peer review process.
5. *Spectrum (radio
frequency) considerations
addressed.
*Required per NPD 2570.5.

G.20 Program Implementation Reviews (PIR) and Program Status Reviews (PSR)
PIRs or PSRs are periodically conducted, as required by the Decision Authority and documented in
the program plan, during the Implementation phase to evaluate the program’s continuing relevance
to the Agency’s Strategic Plan. These reviews assess the program performance with respect to
expectations and determine the program’s ability to execute the implementation plan with acceptable
risk within cost and schedule constraints.
Table G-20 – PIR/PSR Entrance and Success Criteria

Program Implementation and Program Status Reviews


Entrance Criteria Success Criteria
1. A preliminary PIR 1. Program still meets Agency needs and should continue.
agenda, success 2. The program cost and schedule estimates are credible
criteria, and and within program constraints.
instructions to the 3. Risks are identified and accepted by program/project
review team have been leadership, as required.
agreed to by the 4. Technical trends are within acceptable bounds.
technical team, project 5. Adequate progress has been made relative to plans,
manager, and review including the technology readiness levels.
chair prior to the 6. For technology development programs, technologies
review. have been identified that are ready to be transitioned to
2. The current status of another project or to an organization outside the Agency.
the overall technical 7. Spectrum-related aspects have been concurred to by the
effort is available and responsible Center spectrum manager.
ready to be reviewed.
3. Programmatic products
are ready for review at
the maturity levels

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 113 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 114 of 142

stated in the governing


program/project
management NPR.
4. Current actual and
estimated costs are
available and
compared to the
expected plan.
5. Current schedule is
available showing
remaining work
planned.
6. Trending of the
selected Technical
Performance
Parameters relevant to
the current Program
phase is available.
7. Updated technical
plans are available.
8. *Spectrum (radio
frequency)
considerations
addressed.
*Required per NPD 2570.5.

G.21 Design Certification Review (DCR)


This review is not depicted in the standard life-cycle review figures but has proven useful to larger
projects such as human space flight. Projects/Centers may choose to add this review to their standard
life-cycle if they feel it is useful. The DCR ensures that the design complies with functional and
performance requirements, as demonstrated in verification, validation, and qualification evidence.
The certified design forms the basis from which system acceptance will be assessed. A DCR should,
ideally, be held after a CDR and before a SAR.
Table G-21 – DCR Entrance and Success Criteria

Design Certification Review


Entrance Criteria Success Criteria
1. The project has 1. Qualification tests, configurations, and test
successfully completed the environments demonstrate the system can meet
previous planned life-cycle functional and performance requirements across all
reviews, RFA/RIDs have applicable flight envelopes, configurations, and
been closed, and plans to environments.
complete open work are 2. Required tests and analyses are complete and

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 114 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 115 of 142

defined. indicate that the system will perform properly in the


2. A preliminary DCR expected design environments.
agenda, success criteria, 3. Design certification data package is complete and
and instructions to the reflects the as-certified system.
review team have been 4. Waivers/deviations and non-conformance affecting
agreed to by the technical the qualification test articles, procedures, or
team, project manager, and environments have been approved.
review chair prior to the 5. Design mitigations have been appropriately
review. implemented in response to safety products (e.g.,
3. The following DCR FEMA/CILs, FMECA, Safety, and Hazard
technical products have Reports) and indicate residual safety and mission
been made available to the success risks are acceptable for all intended uses of
cognizant participants prior the system.
to the review: 6. Operating, production or fabrication, and
a. Updated Verification maintenance constraints demonstrate a viable path
and Validation Plan. to producing the system per the design.
b. As-run qualification 7. Risks are known and manageable.
test procedures, 8. TBD and TBR items are resolved.
configurations, test 9. *Concurrence by the responsible Center spectrum
environments, and manager that all tests are performed in accordance
test results. with spectrum policy and regulation.
c. Product verification
results.
d. Product validation
results.
e. Documentation that
the system will
perform properly in
the design
environments.
f. Final design
certification package.
g. Safety products (e.g.,
Failure Mode and
Effects
Analysis/Critical
Items Lists
(FMEA/CILs),
Failure Mode,
Effects, and
Criticality Analysis
(FMECA), Safety,
Hazard Reports).
h. All operating,
production or

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 115 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixG Page 116 of 142

fabrication, and
maintenance
constraints are
documented.
i. Updated risk
assessment and
mitigation.
j. Waivers/deviations
affecting the
qualification articles,
procedures, or
environments.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixG incorporated into a contract. This document is uncontrolled when printed. Check Page 116 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 117 of 142

Appendix H. Compliance Matrix for Programs/Projects


Template Instructions
The Compliance Matrix documents the program/projects compliance or intent to comply with the requirements of this
NPR or justification for tailoring. It is attached to the SEMP or other equivalent program/project documentation when
submitted for approval. The matrix lists:
The unique requirement identifier.
The paragraph reference.
The NPR 7123.1 requirement statement.
The rationale for the requirement.
A “Comply?” column to describe applicability or intent to tailor.
The “Justification” column to justify how tailoring is to be applied.
Programs/Projects may substitute a matrix that documents their compliance with their particular Center’s
implementation of NPR 7123.1.
The “Comply?” column is filled in to identify the program/projects approach to the requirement. An “FC” is inserted
for “fully compliant,” “T” for “tailored,” or “NA” for a requirement that is “not applicable.” The column titled
“Justification” documents the rationale for tailoring, documents how the requirement will be tailored, or justifies why
the requirement is not applicable.

Req NPR
Requirement Statement Rationale Comply? Justification
ID Section
SE-01 Deleted See rationale in the
to 05 Deleted Requirements
Table J-1.
SE-06 6.1.8 The ETA shall approve the This requirement
SEMP, waiver or deviation ensures that the ETA
authorizations, and other has reviewed and
key technical documents to approved of key
ensure independent systems engineering
assessment of technical documents.
content.
SE- 07 3.2.2.1 Program/Project Managers This requirement
shall identify and ensures that the
implement an program/project and
ETA-approved Stakeholder the ETA identifies how
Expectations Definition they will gather and
process to include address stakeholder
activities, requirements, expectations. This
guidelines, and ensures that the
documentation, as tailored program/project will
and customized for the gain a thorough
definition of stakeholder understanding of what
expectations for the the customer and other
applicable product layer. stakeholders expect.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 117 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 118 of 142

SE- 08 3.2.3.1 Program/Project Managers This requirement


shall identify and ensures that the
implement an program/project and
ETA-approved Technical the ETA identifies how
Requirements Definition they will select and
process to include gain agreement on the
activities, requirements, technical requirements.
guidelines, and
documentation, as tailored
and customized for the
definition of technical
requirements from the set
of agreed upon stakeholder
expectations for the
applicable product layer.
SE- 09 3.2.4.1 Program/Project Managers This requirement
shall identify and ensures that the
implement an program/project and
ETA-approved Logical the ETA identifies how
Decomposition process to they will take the
include activities, technical requirements
requirements, guidelines, for the program/project
and documentation, as and glean from them
tailored and customized for what is needed to
logical decomposition of accomplish them (e.g.,
the validated technical functional block
requirements of the diagrams, timing,
applicable product layer. architectures). This
places the requirements
into context and
ensures they are
understood well
enough to begin the
design process.
SE- 10 3.2.5.1 Program/Project Managers This requirement
shall identify and ensures that the
implement an program/project and
ETA-approved Design the ETA identifies how
Solution Definition process they will take the
to include activities, information from the
requirements, guidelines, stakeholder
and documentation, as expectations,
tailored and customized for requirements, and
designing product solution logical decomposition
definitions within the and perform the design
applicable product layer function. Since all
that satisfy the derived designs are unique, this
technical requirements. will describe the
general steps that are
taken. The specifics for
each of the

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 118 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 119 of 142

each of the
program/projects will
be documented in the
SEMP or other
equivalent
program/project
documentation.
SE- 11 3.2.6.1 Program/Project Managers This requirement
shall identify and ensures that the
implement an program/project and
ETA-approved Product the ETA identifies how
Implementation process to they will execute the
include activities, designs, whether
requirements, guidelines, through buying items
and documentation, as off the shelf or
tailored and customized for contracting to have
implementation of a design them built,
solution definition by building/coding them
making, buying, or reusing within the Center, or
an end product of the reusing products
applicable product layer. already developed by
another
program/project. The
specifics for how each
program/project will
make this
determination for the
various
components/assemblies
within the product
hierarchy are
documented in the
SEMP or other
equivalent
program/project
documentation.
SE- 12 3.2.7.1 Program/Project Managers This requirement
shall identify and ensures that the
implement an program/project and
ETA-approved Product the ETA identifies how
Integration process to they will approach the
include activities, integration of products
requirements, guidelines, within successive
and documentation, as levels of the product
tailored and customized for hierarchy. This ensures
the integration of lower that planning is
level products into an end performed that will
product of the applicable enable a smooth
product layer in accordance integration of products
with its design solution into higher level
definition. assemblies.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 119 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 120 of 142

SE- 13 3.2.8.1 Program/Project Managers This requirement


shall identify and ensures that the
implement an program/project and
ETA-approved Product the ETA identifies how
Verification process to they will verify that the
include activities, end products will
requirements/specifications, comply with each of
guidelines, and the technical
documentation, as tailored requirements.
and customized for
verification of end products
generated by the product
implementation process or
product integration process
against their design solution
definitions.
SE- 14 3.2.9.1 Program/Project Managers This requirement
shall identify and ensures that the
implement an program/project and
ETA-approved Product the ETA identifies how
Validation process to they will show that the
include activities, end products will meet
requirements, guidelines, the stakeholder
and documentation, as expectations in the
tailored and customized for intended environment.
validation of end products This is in addition to
generated by the product verifying they meet the
implementation process or stated requirements and
product integration process ensures the stakeholder
against their stakeholder is getting what was
expectations. expected.
SE- 15 3.2.10.1 Program/Project Managers This requirement
shall identify and ensures that the
implement an program/project and
ETA-approved Product the ETA identifies how
Transition process to they will handle the
include activities, end products as they
requirements, guidelines, move from one
and documentation, as location to another.
tailored and customized for This includes shipping,
transitioning end products handling,
to the next higher level transportation criteria,
product layer customer or physical security,
user. cybersecurity, and
receiving facility
storage needs. It
ensures that receiving
facilities are ready to
accept the product and
that no damage occurs
to the product during

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 120 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 121 of 142

to the product during


handling and
transportation.
SE- 16 3.2.11.1 Program/Project Managers This requirement
shall identify and ensures that the
implement an program/project and
ETA-approved Technical the ETA identifies how
Planning process to include they will perform and
activities, requirements, document all the
guidelines, and technical planning for
documentation, as tailored the program/project.
and customized for This includes all plans
planning the technical effort. developed for the
technical effort
—Systems Engineering
Management Plans,
risk plans, integration
plans, and V&V plans.
This ensures that the
program/project teams
are thinking ahead for
the work to be
performed and
capturing that
information so it can
be communicated to
the rest of the team,
customers, and other
stakeholders.
SE- 17 3.2.12.1 Program/Project Managers This requirement
shall identify and ensures that the
implement an program/project and
ETA-approved the ETA identifies how
Requirements Management they will handle
process to include tracking and changes to
activities, requirements, the baselined set of
guidelines, and requirements. It defines
documentation, as tailored who has authority to
and customized for submit and approve
management of changes and how
requirements throughout requirements are
the system life-cycle. tracked as they flow
down to other elements
in the product
breakdown structure.
This ensures that
changes to
requirements are
evaluated and that their
impacts are understood
and communicated to
the rest of the team.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 121 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 122 of 142

the rest of the team.


SE- 18 3.2.13.1 Program/Project Managers This requirement
shall identify and ensures that the
implement an program/project and
ETA-approved Interface the ETA identifies how
Management process to they will manage the
include activities, internal and external
requirements, guidelines, interfaces of their end
and documentation, as product. This will
tailored and customized for ensure compatibility
management of the when the various parts
interfaces defined and of the system are
generated during the brought together for
application of the system assembly/integration.
design processes.
SE- 19 3.2.14.1 Program/Project Managers This requirement
shall identify and ensures that the
implement a Technical program/project and
Risk Management process the ETA identifies how
to include activities, they will handle the
requirements, guidelines, technical portions of
and documentation, as the program/project
tailored and customized for risks and report them
management of the risk for inclusion with the
identified during the cost and schedule risk
technical effort. portions. It ensures that
the technical aspects of
risks to the
program/projects
successful execution
are captured and
reported to
program/project
management who will
be developing the
overall risk posture.
SE- 20 3.2.15.1 Program/Project Managers This requirement
shall identify and ensures that the
implement an program/project and
ETA-approved the ETA identifies how
Configuration Management they will perform
process to include configuration
activities, requirements, management of the end
guidelines, and products, enabling
documentation, as tailored products and other
and customized for work products key to
configuration management. the program/project.
The technical products
to be controlled are
identified and tracked
to ensure that the team

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 122 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 123 of 142

to ensure that the team


knows what the
configuration of their
system is at all phases
of the life-cycle.
SE- 21 3.2.16.1 Program/Project Managers This requirement
shall identify and ensures that the
implement an program/project and
ETA-approved Technical the ETA identifies how
Data Management process they will handle all the
to include activities, technical data that is
requirements, guidelines, generated by the
and documentation, as program/project. This
tailored and customized for will include all data
management of the needed to manage,
technical data generated operate, and support
and used in the technical the system products
effort. over the life-cycle. It
ensures that the data is
available and secure
when needed.
SE- 22 3.2.17.1 Program/Project Managers This requirement
shall identify and ensures that the
implement an program/project and
ETA-approved Technical the ETA identifies how
Assessment process to they will assess the
include activities, progress of the
requirements, guidelines, program/project’s
and documentation, as technical efforts,
tailored and customized for including life-cycle
making assessments of the reviews. It ensures that
progress of planned the program/project
technical effort and team, customers, and
progress toward other key stakeholders
requirements satisfaction. know how the effort is
progressing and if
additional actions are
needed to resolve
issues prior to
becoming too costly.
SE- 23 3.2.18.1 Program/Project Managers This requirement
shall identify and ensures that the
implement an program/project and
ETA-approved Decision the ETA identify how
Analysis process to include they will make and
activities, requirements, document key technical
guidelines, and decisions. It helps to
documentation, as tailored ensure that all team
and customized for making members know who
technical decisions. can make decisions,
what their authority

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 123 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 124 of 142

what their authority


levels are, and where to
go to gain an
understanding of what
key decisions have
been made.
SE- 24 4.2.1 The NASA technical team It is important for both
shall define the engineering the Government and
activities for the periods contractor technical
before contract award, teams to understand
during contract what activities will be
performance, and upon handled by which
contract completion in the organization
SEMP or other equivalent throughout the product
program/project life-cycle. The
documentation. contractor(s) will
typically develop a
SEMP or other
equivalent
program/project
documentation to
describe the technical
activities in their
portion of the project,
but an overarching
SEMP (or other
equivalent
program/project
documentation) is
needed that will
describe all technical
activities across the
life-cycle whether
contracted or not.
SE- 25 4.2.2 The NASA technical team The technical team’s
shall establish the technical participation in the
inputs to the solicitation development of the
appropriate for the solicitation is critical to
product(s) to be developed, enabling a successful
including product contracted effort.
requirements and Statement Ensuring that the
of Work tasks. proper application of
the common technical
processes into the
contracted effort will
enhance the chances
for success.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 124 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 125 of 142

SE- 26 4.2.3 The NASA technical team The technical team is in


shall determine the the best position to
technical work products to determine what kind of
be delivered by the offeror work products from the
or contractor, to include technical effort will
contractor documentation need to be delivered.
that specifies the These products will
contractor’s SE approach to eventually be used by
the scope of activities the technical team to
described by the 17 determine the
common technical suitability of the
processes. contracted effort in its
ability to meet
requirements, satisfy
the stakeholder
expectations, and
perform as planned.
SE- 27 4.2.4 The NASA technical team In addition to the work
shall provide the description and
requirements for technical products to be
insight and oversight delivered, how the
activities planned in the technical team will
NASA SEMP or other gain an adequate
equivalent program/project understanding of the
documentation to the contracted work, what
contracting officer for authority (if any) they
inclusion in the solicitation. will have to direct or
influence the work, and
their participation at
key life-cycle reviews.
In the end the technical
team needs enough
information to advise
the Program/Project
Manager and ETA as
to the adequacy of the
technical work.
SE- 28 4.2.5 The NASA technical team Technical personnel
shall participate in the will need to be
evaluation of offeror involved in reviewing
proposals in accordance the proposals and
with applicable NASA and providing
Center source selection advice/guidance on
procedures. their merits. These
personnel may or may
not be part of the
technical team that will
execute the
program/project.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 125 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 126 of 142

SE- 29 4.3.1 The NASA technical team, After the contract is


under the authority of the awarded, the
contracting officer, shall contracting officer will
perform the technical depend on the technical
insight and oversight team to execute the
activities established in the oversight/ insight of
contract including the technical work as
modifications to the defined in their SEMP
original contract. (or other equivalent
program/project
documentation) and the
contract.
SE- 30 4.4.1 The NASA technical team Per the agreement in
shall participate in the the SEMP (or other
review(s) to finalize equivalent
Government acceptance of program/project
the deliverables. documentation) and the
contract, the technical
team will participate in
the life-cycle reviews.
Ultimately, this
knowledge will enable
the technical team to
provide advice to the
program/project and
ETA as to the
suitability of the
product for acceptance.
SE- 31 4.4.2 The NASA technical team In accordance with the
shall participate in product SEMP (or other
transition as defined in the equivalent
NASA SEMP or other program/project
equivalent program/project documentation), the
documentation. technical team will
participate in the
execution of the final
aspects of the end
product—either its
transference in whole
to the program/ project
customer, its
operations, and/or the
final decommissioning
and disposal. These
activities may be
performed by the same
team that was involved
in its development or
by other technical
teams.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 126 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 127 of 142

SE- 32 5.2.1.1 The technical team shall Each of the life-cycle


develop and document reviews, as well as any
plans for life-cycle and other technical status
technical reviews for use in reviews, needs to be
the program/project identified and
planning process. documented so that all
stakeholders will know
how the program/
projects progress will
be assessed. This will
typically be captured
within the SEMP, in a
separate Review Plan
or other equivalent
program/project
documentation.
SE- 33 5.2.1.5 The technical team shall The technical team will
participate in the life-cycle be responsible for
and technical reviews as generating and
indicated in the governing presenting many of the
program/project technical topics during
management NPR. a life-cycle and
technical review.
SE- 34 5.2.2.1 The technical team shall The entrance and
participate in the success criteria in
development of entrance Appendix G are
and success criteria for provided as guidelines
each of the respective (not requirements). It is
reviews. expected that they will
be modified as needed
by the program/project
according to their size,
complexity, type of
end product being
produced, formality,
and risk acceptance
posture. Specific
names of documents
may be provided for
clarity, non-applicable
products eliminated,
and new products
added as needed for
clarity and
completeness.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 127 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 128 of 142

SE- 35 5.2.2.2.a The technical team shall For an MCR one of the
(1) provide the following key products is
minimum products at the capturing the
associated life-cycle review stakeholder
at the indicated maturity expectations. These
level: MCR: Baselined may be identified as
stakeholder identification needs, goals, and
and expectation definitions. objectives, or other
methods for capturing
their expectations.
These are captured in a
document or a
database/model. After
all comments from the
MCR are dispositioned,
the set of stakeholder
expectations are
updated with the
approved comments
and then baselined.
SE- 36 5.2.2.2. The technical team shall Presenting one or more
a provide the following feasible ways of
(2) minimum products at the accomplishing the
associated life-cycle review stakeholder
at the indicated maturity expectations is a key
level: MCR: Baselined product of the MCR.
concept definition. These are captured in a
document or a
database/model. After
all comments from the
MCR are dispositioned,
the concept(s) are
updated with the
approved comments
and then baselined.
SE- 37 5.2.2.2. The technical team shall The MOE capture the
a provide the following stakeholders’ view of
(3) minimum products at the what would be
associated life-cycle review considered the
at the indicated maturity successful achievement
level: MCR: Approved of each expectation.
Measures of Effectiveness These will help in the
(MOE) definition. later identification of
requirements, criteria
for trade studies and in
the success criteria for
the validation efforts.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 128 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 129 of 142

SE- 38 5.2.2.2. The technical team shall The SEMP is a key


b provide the following document for the
(1) minimum products at the technical effort in a
associated life-cycle review similar manner that the
at the indicated maturity program/project plan
level: SRR: Baselined captures the
SEMP (or other equivalent programmatic efforts.
program/project These are captured in a
documentation) for document or a
projects, single-project database/model. For
programs, and one-step AO projects, single-project
programs. programs, and one-step
AO programs after all
comments from the
SRR are dispositioned,
the SEMP (or other
equivalent
program/project
documentation) is
updated with the
approved comments
and then baselined.
The SEMP (or other
equivalent
program/project
documentation) is
baselined in a later
phase for the other
types of programs and
so will be a “Not
Applicable” in this line
for uncoupled, tightly
coupled, and loosely
coupled programs.
SE- 39 5.2.2.2. The technical team shall The program/project
b provide the following requirements are a key
(2) minimum products at the product for the SRR.
associated life-cycle review These are captured in a
at the indicated maturity document or a
level: SRR: Baselined database/model. After
requirements. all comments from the
SRR are dispositioned,
the requirements are
updated with the
approved comments
and then baselined.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 129 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 130 of 142

SE- 40 5.2.2.2.c The technical team shall A key product at the


(1) provide the following SDR is the set of TPMs
minimum products at the that the
associated life-cycle review program/project has
at the indicated maturity identified as the
level: MDR/ SDR: important measures to
Approved TPM definitions. track for their efforts.
These may be
associated with the key
driving requirements,
key performance
parameters, leading or
lagging indicators, or
other measures that are
important to
periodically measure
and track.
SE- 41 5.2.2.2.c The technical team shall One of the key
(2) provide the following products of an SDR is
minimum products at the the proposed
associated life-cycle review architecture that will
at the indicated maturity accomplish the
level: MDR/ SDR: requirements. These
Baselined architecture are captured in a
definition. document or a
database/model. After
all comments from the
SDR are dispositioned,
the architecture
description is updated
with the approved
comments and then
baselined.
SE- 42 5.2.2.2.c The technical team shall Now that the
(3) provide the following overarching
minimum products at the architecture has been
associated life-cycle review defined, it is important
at the indicated maturity to show how the
level: MDR/ SDR: requirements are
Baselined allocation of allocated to the
requirements to next lower architecture elements
level. of the next lower level
of the product
hierarchy. These are
captured in a document
or a database/ model.
After all comments
from the SDR are
dispositioned, the
allocation is updated
with the approved

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 130 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 131 of 142

with the approved


comments and then
baselined.
SE- 43 5.2.2.2.c The technical team shall The trend is presented
(4) provide the following for the leading
minimum products at the indicators that have
associated life-cycle review been identified by the
at the indicated maturity Agency as required for
level: MDR/ SDR: Initial each program/project.
trend of required leading These will typically be
indicators. in graphical form but
could also be tabular or
other form appropriate
for the project. At SDR
this will be the initial
set of trends that have
been captured since
SRR. Since final
hardware has not been
produced at this point,
the trends will be on
the estimated
parameters.
SE- 44 5.2.2.2.c The technical team shall The SEMP is a key
(5) provide the following document for the
minimum products at the technical effort in a
associated life-cycle review similar manner that the
at the indicated maturity program plan captures
level: MDR/ SDR: Baseline the programmatic
SEMP (or other equivalent efforts. These are
program/project captured in a document
documentation) for or a database/model.
uncoupled, loosely coupled, For uncoupled, loosely
tightly coupled, and coupled, tightly
two-step AO programs. coupled, and two-step
AO programs, after all
comments from the
MDR/SDR are
dispositioned, the
SEMP (or other
equivalent
program/project
documentation) is
updated with the
approved comments
and then baselined.
The SEMP (or other
equivalent
program/project
documentation) is
baselined in an earlier
phase for projects and

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 131 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 132 of 142

phase for projects and


single-project programs
and so will be a “Not
Applicable” in this line
for those types of
programs.
SE- 45 5.2.2.2. The technical team shall The key product of a
d provide the following PDR is the preliminary
(1) minimum products at the design itself. The
associated life-cycle review design is captured in
at the indicated maturity one or more
level: PDR: Preliminary documents, models,
design solution definition. databases, drawings,
and other means.
Comments from the
PDR will be captured
in the final design for
the next review.
SE- 46 5.2.2.2. The technical team shall The key product of a
e provide the following CDR is the final
(1) minimum products at the design. The design is
associated life-cycle review captured in one or
at the indicated maturity more documents,
level: CDR: Baseline models, databases,
detailed design. drawings, and other
means. The final
design is updated with
approved comments
from the review, and
the design is updated to
represent the design
that will be
implemented.
SE- 47 5.2.2.2.f The technical team shall A key product of an
(1) provide the following SIR is the updated
minimum products at the integration plans.
associated life-cycle review These will describe
at the indicated maturity how the products
level: SIR: Updated associated with this
integration plan. review will be
integrated.
SE- 48 5.2.2.2.f The technical team shall Another key product of
(2) provide the following an SIR is the initial
minimum products at the V&V results from any
associated life-cycle review of the lower level
at the indicated maturity products that are
level: SIR: Preliminary associated with this
V&V results. review. With the
recursive nature of the
SE engine, products
will be integrated and

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 132 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 133 of 142

will be integrated and


verified/validated from
the bottom of the
product layer to the
top. So, prior to
integration into larger
assemblies, lower level
products will have
been through their
V&V activities. This
ensures that, when they
are assembled into the
higher product layers,
they will work as
intended.
Programs/projects may
decide to perform V&V
only at assembly
levels—as captured in
their SEMP (or other
equivalent
program/project
documentation)—and
so initial V&V results
may or may not be
available.
SE-49 Deleted See rationale in the
and 50 Deleted Requirements
Table.
SE- 51 5.2.2.2.g The technical team shall At ORR it is important
(3) provide the following to describe how the
minimum products at the product will ultimately
associated life-cycle review be decommissioned
at the indicated maturity when it has
level: ORR: Preliminary accomplished its
decommissioning plans. mission. This is to
ensure that
decommissioning will
be feasible before the
product is put into use.
These are captured in a
document or a
database/model. After
all comments from the
ORR are dispositioned,
the plan is updated
with the approved
comments and then
baselined.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 133 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 134 of 142

SE- 52 5.2.2.2.h The technical team shall At FRR it is also


(1) provide the following important to describe
minimum products at the how the product will
associated life-cycle review ultimately be disposed
at the indicated maturity of when it has
level: FRR: Baseline accomplished its
disposal plans. mission. This is to
ensure that disposal
will be feasible before
the product is put into
use. These are captured
in a document or a
database/model. After
all comments from the
FRR are dispositioned,
the plan is updated
with the approved
comments and then
baselined.
SE- 53 5.2.2.2.h The technical team shall At FRR, the baselined
(2) provide the following V&V results for the
minimum products at the product are presented
associated life-cycle review and any remaining
at the indicated maturity open work identified.
level: FRR: Baseline V&V This is to ensure that
results. the product is ready for
flight. Note that for
some
programs/projects the
V&V results may need
to be baselined at ORR
per Center
policies/procedures.
Maturing and
presenting a product
earlier than required in
the Agency NPR is at
the discretion of the
program/project/Center
and does not require a
waiver.
SE- 54 5.2.2.2.h The technical team shall The key product at the
(3) provide the following FRR is the certification
minimum products at the that the product is
associated life-cycle review ready for flight/use.
at the indicated maturity This gains agreement
level: FRR: Final with all key
certification for flight/use. stakeholders that the
product is ready to put
into the operational
phase. Any remaining

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 134 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 135 of 142

phase. Any remaining


open items are
identified and plans for
closure are developed.
SE- 55 5.2.2.2.i The technical team shall The key product at the
(1) provide the following DR is the plan on how
minimum products at the the product will be
associated life-cycle review removed from service.
at the indicated maturity The approved
level: DR: Baseline comments from the DR
decommissioning plans. are used to baseline the
plan.
SE- 56 5.2.2.2.j The technical team shall The key product of the
(1) provide the following DRR is the plan on
minimum products at the how the product will be
associated life-cycle review disposed of after it has
at the indicated maturity been decommissioned.
level: DRR: Updated The approved
disposal plans. comments from the
DRR are used to update
the plan.
SE- 57 5.2.2.7 Technical teams shall In addition to the
monitor technical effort life-cycle reviews, the
through periodic technical technical teams need to
reviews. periodically monitor
the technical progress
of their
program/project. These
may be held formally
or informally with
relevant personnel.
SE- 58 6.2.3 The technical teams shall The SEMP is the key
define in the document that lays out
program/project SEMP the work that the
how the required 17 technical team needs to
common technical perform and the
processes, as tailored, will manner in which they
be recursively applied to will perform it. This
the various levels of requirement ensures
program/project product that each of the 17
layer system structure common technical
during each applicable processes is addressed
life-cycle phase. and how it will be
applied to the various
levels in the end-item
product hierarchy and
their associated
enabling products.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 135 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 136 of 142

SE- 59 6.2.5 The technical team shall Since the SEMP is the
ensure that any technical primary planning
plans and discipline plans document for the SE
are consistent with the effort, all subsequent
SEMP (or equivalent planning documents are
program/project in alignment and
documentation) and are consistent with the
accomplished as fully SEMP.
integrated parts of the
technical effort.
SE- 60 6.2.6 The technical team shall The measures that the
establish TPMs for the program/project will
program/project that use to track the
track/describe the current progress of key aspects
state versus plan. of the technical effort
are identified and
documented. These
TPMs will include the
required leading
indicators described in
other requirements of
this NPR and also any
project-unique
measures deemed
necessary to track the
key performance
parameters.
SE- 61 6.2.7 The technical team shall The selected TPMs
report the TPMs to the need to be measured
Program/Project Manager periodically and their
on an agreed-to reporting trends reported to the
interval. program/project
manager at the
agreed-to interval as
documented in the
SEMP (or other
equivalent
program/project
documentation). This
ensures the PM and
ETA are kept up to
date on these key
parameters so that
decisions can be made
in a timely manner.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 136 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 137 of 142

SE- 62 6.2.8. a The technical team shall If the program/project


ensure that the set of TPMs has hardware elements,
include the following tracking of the
leading indicators: Mass remaining margins
margins for projects associated with their
involving hardware. mass is a required
leading indicator
measure by the
Agency. This is
especially important
for flight projects. For
ground or other
projects in which mass
is not relevant, a
waiver to this
requirement can be
documented in the
SEMP or other
equivalent
program/project
documentation.
SE- 63 6.2.8. b The technical team shall If the program/project
ensure that the set of TPMs has elements that
include the following require power, tracking
leading indicators: Power of the remaining
margins for projects that margins associated
are powered. with their power
consumption is a
required leading
indicator measure by
the Agency. This is
especially important
for flight projects. For
ground or other
projects in which
power consumption is
not relevant, a waiver
to this requirement can
be documented in the
SEMP or other
equivalent
program/project
documentation.
SE- 64 6.2.9 The technical team shall During life-cycle
ensure that a set of review reviews, comments
trends is created and from the reviewers are
maintained that includes captured on forms,
closure of review action databases,
documentation (RIDs, spreadsheets, or other
RFAs, and/or Action Items manner. Depending on
as established by the the program/project,

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 137 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixH Page 138 of 142

as established by the the program/project,


project). these may be called
RFAs, RIDs, Action
Items, or other
terminology. Whatever
they are called, the
disposition and closure
of these
comments—typically
called their
burndown—are
required indicator
trends by the Agency.
This ensures that the
approved comments
are incorporated into
the designs and plans
in a timely manner.

Submitted By: Approved By:

_______________________ ___________ _______________________________ __________


Program/Project Manager Date Engineering Technical Authority Date

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixH incorporated into a contract. This document is uncontrolled when printed. Check Page 138 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixI Page 139 of 142

Appendix I. Standards and Handbooks List


The following is a list of NASA Handbooks, NASA Standards, and endorsed military and industry
standards that are applicable to systems engineering. These documents are available on the NASA
Technical Standards System found at https://standards.nasa.gov/endorsed_standards, and should be
applied as appropriate for each program or project.

Document Number Name


AE/GEIA-859 Data Management, Revision B
ANSI/EIA 632 Processes for Engineering a System
IEEE 1012 Standard for System, Software, and Hardware Verification and
Validation Software Reviews and Audits
IEEE 1028 Standard for Software Reviews and Audits
IEEE 15939:2017 Systems and Software Engineering
IEEE 828 Standard for Configuration Management in Systems and Software
Engineering
ISO/IEC 20246 Software and Systems Engineering Work Product Reviews
ISO/IEC TS 24748 Systems and Software Engineering Life Cycle Management
ISO/IEEE 15288 Systems and Software Engineering - System Life-Cycle Processes
ISO/IEEE 16085 Systems and Software Engineering - Risk Management
ISO/IEEE 29148 Systems and Software Engineering - Requirements Engineering
MIL-STD-31000B Department of Defense Standard Practice Technical Data Packages
NASA/SP-2010-576 NASA Risk-Informed Decision Making Handbook
NASA/SP-2011-3422 NASA Risk Management Handbook
NASA/SP-2016-6105 NASA Systems Engineering Handbook
NASA-HDBK-2203 NASA Software Engineering Handbook
NASA-HDBK-7009 NASA Handbook for Models and Simulations
NASA-STD-3001 NASA Space Flight Human System Standard
NASA-STD-7009 NASA Standard for Models and Simulations
SAE/EIA-649-2 Configuration Management Requirements for NASA Enterprises
SAE/EIA-649B Configuration Management Standard
SAE/GEIA-HB-649 Configuration Management Standard Implementation Guide

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixI incorporated into a contract. This document is uncontrolled when printed. Check Page 139 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixJ Page 140 of 142

Appendix J. Deleted Requirements


The following requirements have been deleted from the original version of NPR 7123.1. Rather than
resequence the remaining requirements, the original requirement numbering was left intact in case
Centers or other organizations refer to these requirement numbers in their flow-down requirement
documents. For each requirement that was deleted, the justification for its deletion is noted.
Table J-1 Deleted Requirements and Justification

Req No Requirement Statement Justification for Deletion


[SE-01] 2.1.4.3 Center Directors shall Original text was used to ensure each
perform the following activities: a. Center has a defined SE process. Now, 10
Establish policies, procedures, and years after the initial SE NPR was
processes to execute the requirements generated, Centers have defined processes.
of this SE NPR. The emphasis is now that each
program/project identifies and implements
SE processes that are approved by the ETA.
[SE-02] 2.1.4.3 Center Directors shall Original text was used to ensure each
perform the following activities: b. Center has a process for continuous
Assess and take corrective actions to improvement of their SE process. Now, 10
improve the execution of the years after the initial SE NPR was
requirements of this SE NPR. generated, Centers routinely make updates
and a requirement is no longer needed.
[SE-03] 2.1.4.3 Center Directors shall Selection of technical standards applicable
perform the following activities: c. to a specific project is an ETA
Select appropriate standards responsibility.
applicable to projects under their
control.
[SE-04] 2.1.4.3 Center Directors shall The H.1 and H.2 compliance matrices were
perform the following activities: d. combined into a single matrix.
Complete the compliance matrix, as Responsibility for compliance matrix
tailored, in Appendix H.1 for those completion is now the responsibility of the
requirements owned by the Office of program/project and ETA.
Chief Engineer (OCE) and provide to
the OCE upon request.
[SE-05] 2.1.5.2 For those requirements owned The H.1 and H.2k compliance matrices
by Center Directors, the technical were combined into a single matrix.
team shall complete the compliance Responsibility for compliance matrix
matrix in Appendix H.2 and include completion is now the responsibility of the
it in the SEMP. program/project and ETA.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixJ incorporated into a contract. This document is uncontrolled when printed. Check Page 140 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixJ Page 141 of 142

[SE-49] 5.2.1.7 The technical team shall Operational plans are optional and may be
provide the following minimum outside the purview of systems engineering
products at the associated milestone to develop.
review at the indicated maturity
level: g. ORR: (1) Updated
operational plans.
[SE-50] 5.2.1.7 The technical team shall Operational plans are optional and may be
provide the following minimum outside the purview of systems engineering
products at the associated milestone to develop.
review at the indicated maturity
level: g. ORR: (2) Updated
operational procedures.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixJ incorporated into a contract. This document is uncontrolled when printed. Check Page 141 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.
NPR 7123.1C -- AppendixK Page 142 of 142

Appendix K. References
The following documents were used as reference materials in the development of this SE NPR. The
documents are offered as informational sources and are not evoked in this NPR, though they may be
referenced.
1. NPD 7120.6, Knowledge Policy on Program and Projects.
2. NPD 8081.1, NASA Chemical Rocket Propulsion Testing.
3. NPD 8700.1, NASA Policy for Safety and Mission Success.
4. NPR 1400.1, NASA Directives and Charters Procedural Requirements.
5. NPR 2810.1, Security of Information Technology.
6. NPR 7120.10, Technical Standards for NASA Programs and Projects.
7. NPR 7120.11, NASA Health and Medical Technical Authority (HMTA) Implementation.
8. NPR 8705.4, Risk Classification for NASA Payloads.
9. NASA/SP-2010-3404, Work Breakdown Structure (WBS) Handbook.
10. NASA/SP-2014-3705, NASA Spaceflight Program & Project Management Handbook.
11. NASA-STD-7009, Standard for Models and Simulations.
12. MIL-STD-499B (draft), Systems Engineering.
13. ANSI/EIA 632, Processes for Engineering a System. Note: EIA 632 is a commercial document
that evolved from the never released, but fully developed, 1994 Mil-Std 499B, Systems
Engineering. It was intended to provide a framework for developing and supporting universal SE
discipline for both defense and commercial environments. EIA 632 was intended to be a top-tier
standard further defined to lower level standards that define specific practices. IEEE 1220 is a
second-tier standard that implements EIA 632 by defining one way to practice SE.
14. AS9100: Quality Management Systems—Requirements for Aviation, Space, and Defense
Organizations.
15. ISO/IEC 15288, Systems and Software Engineering—System Life-Cycle Processes.
16. ISO/IEC TR 19760, Systems Engineering—A Guide for the Application of ISO/IEC 15288
(System Life-Cycle Processes).
17. The Capability Maturity Model Integration (CMMI) ® Model.
18. Defense Acquisition University Systems Engineering Fundamentals. Ft. Belvoir, Virginia:
Defense Acquisition University Press, December 2000.
19. International Council on Systems Engineering Systems Engineering Guide.

This document does not bind the public, except as authorized by law or as
NPR 7123.1C -- AppendixK incorporated into a contract. This document is uncontrolled when printed. Check Page 142 of 142
the NASA Online Directives Information System (NODIS) Library to verify that
this is the correct version before use: https://nodis3.gsfc.nasa.gov.

You might also like