Work Method Statement - Chuka Ahp
Work Method Statement - Chuka Ahp
Additionally, we will have a multi task labour force directly employed whose activity
will be to police site cleanliness and to coordinate the removal of waste containers.
A Waste Management Compound will be set up within the site, allowing for the
segregation of refuse and recyclables in separate skips including:
General safety lighting will be provided across the site, with specific mobile
task lighting being employed for specific operations as the buildings are
erected.
All temporary services will have identified isolation points to enable quick and
effective isolation in case of an emergency and efficient management of
energy.
The project manager will be responsible for establishing a Fire Safety Plan
which will be updated as required during the construction process.
Designated fire ‘call points’ will be established around the site in strategic
locations supported with an evacuation plan and directional signage
identifying the escape routes and muster point.
2.7 SITE SECURITY
Security on site during the Construction Phase will be provided at the site entrance
at all times while the site is operational, and the management team will be
responsible for:
Areas such as container storage will be externally lit with photocells and
movement detectors which will only be illuminated when there is activity in
the immediate area, at times of darkness.
Intruder alarms will be fitted to the main Site Office accommodation and to
the building at a later stage. The system will be linked directly our 24 hour
Helpdesk. The need for further alarms in secure containers and/or in the
building as it progresses will be monitored on an on-going basis.
The hardstanding for the container storage and the access road will be
formed and the cabins erected, allowing the temporary services to be
connected and the lighting and security installations.
3.1 SUBSTRUCTURES
The subsoil is clay and bulk excavations for basement up to 6.0 meter in depth are
required for the structure.
Once the excavations for the foundation have been completed, the concrete works
for the column bases, columns retaining walls, basements floors shall commence in
line with our programme requirements.
3.1 SUPERSTRUCTURES
When the substructures are suitably advanced the construction of the
reinforced masonry walling will commence.
Scaffolding will be erected to permit the raising of the walls, ground floor flat
roof construction and internally, concrete floors will be installed.
Trussed roof components fabricated off-site will be craned into position onto
the wall plates and secured/wind-braced, followed by the actual roof
coverings.
Floor partitions will be built using masonry. Ceilings, linings and plastering will then
complete the actual construction works.
The services installation will generally follow the works sequence as outlined
above, so that services can be installed, tested and commissioned by the
completion date.
The M&E co-ordinator will be responsible for managing a sign-off process aimed at
identifying and dealing with defects throughout the construction period. This
process will commence at the first fix stage with a permit system being operated to
log inspections and sign off to allow next stage of works to progress.
The process outlined above not only serves the construction process but also
provide an early compliance check in regards to design. Throughout this process we
engage closely with Building Control and the warranty provider to ensure they are
fully involved and informed on works progress and quality standards
Maintaining the phased sequence outlined previously the fit-out will progress
through 5 key phases as follows:
First Fix
Co-ordinated closely with the Mechanical and Electrical installation the first fix
stage of the fit out will mainly be focused around installing floor screed and
constructing partition walls.
Second Fix
Maintaining strong links with the Mechanical and Electrical installation teams
the second fix stage will see the completion of partition walls, installation of
ceilings, plastering, first fix joinery, and general preparations for applied
finishes.
When all parties are satisfied that the first fix element is complete the
permits will be signed off to provide clearance to progress to the next stage.
Finishes
At this stage the M&E installations will be substantially complete and
progressing into the pre-commissioning stage.
This stage of the works will be focused on second fix joinery e.g. door sets, fitted
furniture, wall protection, wall and floor finishes. Having activated the building
heating systems during the previous stage the aim will be to maintain a consistent
environment to allow natural materials to acclimatise and avoid stressing due to
sudden changes.
The snagging process during this phase will become very focussed on the
standards of finishes and quality of workmanship in driving towards a defect
free.
During this stage of the project the aim is to complete the construction works and
achieve a ‘dust free’ environment to enable us to move into the final testing and
commissioning of the building services.
Snagging/ De-snagging
This stage of the process will run parallel with the testing and commissioning
process. A final detailed snagging procedure will be implemented in conjunction
with an independent Inspector.
The snagging works will be inspected and signed off until all items are closed out.
At the appropriate stage a final builder’s clean will be carried out to prepare the
building for completion.
The commissioning of the houses will be carried out in 2 distinct phases and
all individual activities within these phases will be fully detailed on the
commissioning programme prior to the commencement of the commissioning
exercise. The two phases of commissioning are as follows:
Around the perimeter of the houses the hard landscaping works will follow
the dismantling of the external access scaffolds and the site hoarding.
During the last weeks of the contract, the site cabins will be removed to
permit the completion of the car park and access drive. Fences and gates
will be erected, paths laid and soft landscaping planted/turfs laid.
Excavation/Earthworks - Hazards
Access & Egress
Entering and coming out of the pits shall be by means of ladders and steps. Every
excavated pit where work is taking place shall have its own ladder.
Ladders shall be regularly inspected by the employees using them to find out if they
are in good working condition. Damaged ladders shall be removed from site and
taken to the workshop for repair. Entry into excavations must be in an area where
stabilization measures have taken place; this shall be suitably identified.
Poor lighting or low light
Working in excavated pits shall only take place in broad day light. Any work
required to take place at night shall only be permitted if effective and efficient flood
lights are provided. When there is darkness and visibility is impaired, work shall be
stopped immediately.
Overcrowding
The number of people entering excavated pits shall be kept to the minimum.
Overcrowding per excavated pit shall not be permitted; this will help to prevent the
possibility of exhausting oxygen in the pit and causing asphyxia. A record shall be
kept of persons working in excavated pits.
Hand gloves if operations entail manual handling or activities that might result to
Casualty handling
Soils or debris shall be cleared from the face of the casualties and from their chests
to enable them to breathe and for necessary first aid to be administered effectively;
resuscitation equipment shall be taken into the pits by a first aider at site or by the
rescue team members.
Concrete being a mixture of cement, sand, water and aggregate has certain risks,
which must be prevented so as to protect workers from injuries, harm and having
poor health. Cement which is used in concreting is the most dangerous owing to the
substances used to make it. Most dangers associated with concrete emanate from
cement itself, and as a result, it is imperative to handle both cement and concrete
carefully in order to prevent these risks.
AAC shall ensure that concrete work activities are carried out in a manner likely to
promote safety and good health of all employees involved. To achieve this certain
controls shall be put in place and adhered to by all workers.
5.0 Controls
Safe Working Procedures
Training
Workers handling cement shall receive effective trained to educate them on
the hazards associated with concrete and mitigation measures. Daily Toolbox Talks
shall be conducted every morning to educate workers on best ways to handle
concrete.
Hygiene
Workers handling concrete shall remove any clothing that is contaminated by wet
cement.
Any skin that is in contact with concrete shall be washed immediately with
Working area shall be cleared of concrete immediately after work in the evening
handling concrete.
Waterproof safety boots shall be worn by concrete handlers.
Goggles that fully cover the eyes shall be worn by concrete handlers.
Fall arrestors.
First Aid
In the event that one’s skin or eyes come into contact with concrete, either of
soon as possible.
Flush open sores or cuts thoroughly with suitable dressings.