Module 11 Construction Disputes
Module 11 Construction Disputes
CONSTRUCTION DISPUTES
Construction disputes arise as a result of disagreements between the parties involved in a contract. These disputes
themselves are not a breach of contract, but they may lead to a breach of contract, termination, or even claims threatening
the contractor’s surety bonds if unmitigated.
This is extracted from the writings of Victor P. Lazatin, a member of the Integrated Bar of the Philippines.
Listed below are some of the usual causes of construction disputes:
1. Ambiguous/Unclear Provision
Nothing has bred more disputes in the construction industry than ambiguous or unclear provisions.
a. Scope of Work. If the scope of work is not well defined, it is easy to imagine that the owner and the contractor
will keep on arguing about what the contractor was supposed to have done versus what he delivered. It means
not only clarifying what is included or what is in the “Scope of the Work” but in several instances, it is also
necessary to state “what is excluded.” It is the so-called “implied” or “necessary” works that usually cause
dispute.
b. Unclear Specifications. This applies both to the materials to be used, the construction procedure to be followed,
and the finishing and workmanship.
This dispute on the percentage of completion will resolve itself upon the completion of the project, i.e. 100%.
Escalation clauses are also a fertile source of disputes, more so if the base prices or indices are not clear, the future
reference price or indices are not easily verifiable, or the items subject to escalation are not defined. Unless an
escalation clause is provided in the contract, the contractor is generally not entitled to an escalation of the contract
price.
6. Extent of Warranty-Guaranty
Several disputes have arisen with respect to defects that have become manifest after the work has been turned over
to, and accepted by the owner.
7. Amount of Damages
For every dispute, a corollary issue invariably surfaces, i.e., what is the appropriate measure of damages suffered
by a party for a certain violation or breach of the contract? For delays, contracts invariably provide for a certain
amount of liquidated damages per day that the project is delayed.
In practice, the owner has the right to issue “change orders,” and usually said change orders which are usually
executed by the contractor and do not violate or invalidate the contract.
Extra work usually means work outside the scope of the contract. While the extra work is not within the scope of the
contract, usually the owner is given the right to require the contractor to do the “extra work” at a pre-agreed price.
9. Delays
Delay is one of the most common disputes in construction. It could be:
a. The delay in the accomplishment.
b. Delay in the supply of materials.
c. Delay in payment of the progress billing.
d. Delay of other contractors, especially contractors or sub-contractors.
It is important for the construction contract not only to have a definite reckoning date for the start and end of the
project but likewise to create periods of time or milestones in between to monitor the progress of the work. In cases
where there are milestones for accomplishments and these milestones are not achieved on schedule, the usual
penalty is not liquidated damages for delay but rather for the contractor to put in additional manpower or materials
and closer supervision to speed up or crash the work. It may also be good practice to give the contractor an incentive
to complete the project on time or early completion bonuses.
Another common dispute in the delay of construction is the interfacing and coordination with other contractors,
subcontractors, or specialty subcontractors. Usually, in a given construction project, there are several contractors
and specialty sub-contractors not directly under the main or general contractor.
At times, the owner has its own construction crew and is doing some portion of the work on its own. You can
appreciate what lack of coordination or interfacing between these different groups of people can do to delay the
project and how difficult it is to ascertain who is ultimately responsible, as the delay of one group will invariably delay
the work of most, not all of the others.
2
MODES OF SETTLEMENT
It is unlikely for a project to run from start to finish without a dispute arising.
How are these construction disputes resolved in the construction industry today?
Basically, resolution of these disputes follows civilized society’s ways of settling disputes, i.e., either:
It should be pointed out that arbitration may involve judicial action, especially with respect to its enforcement, should the losing
party in an arbitration case refuse to abide by its terms and conditions. Settlement of construction disputes is better achieved
through the arbitration or reconciliation process.
Negotiation
In most cases, the first step in resolving a problem is negotiation. Before turning to alternative methods of dispute resolution,
the parties in a disagreement will negotiate to attempt to come to a mutually agreeable settlement. It is the simplest, least
expensive, and might produce the fastest and most fruitful outcomes.
Mediation
When two parties cannot come to an agreement, mediation is used to help them reach a compromise. Although it is not a
legally binding means of dispute resolution, mediation is one of the best ways to resolve an issue before it becomes more
serious. Before pursuing other options, the parties make an effort to come to a fair agreement outside of court.
Arbitration
When it comes to conflict resolution, contractors and professionals choose arbitration. The majority of contractors list it as a
means of resolving contractual disagreements. If the parties choose arbitration, they must select a third party who is neutral
and has the necessary expertise to help them reach a mutually agreeable resolution. In contrast to mediation, where the
mediator just helps the parties reach a resolution, arbitration determines the final outcome of the dispute. Arbitration has much
higher expenses, and in some places, the results are also legally binding.
Litigation
Trials that are enforceable and legally binding are a part of litigation. It is the most exhaustive, intricate, and expensive dispute
resolution procedure. The majority of parties use alternative dispute resolution procedures since they are also very slow.
PREVENTING DISPUTES
Construction disputes are common, and it is better to avoid a disagreement than to deal with it after it arises. If participants
are unable to resolve issues through effective deliberation, they can end up abandoning the entire project. Here are a few of
the most effective techniques to avoid disagreements:
Communication
Disputes can also develop when the parties limit communication. When a project starts, most developers and contractors will
communicate, and they anticipate everything will go according to schedule. This is frequently the case, and parties should
communicate at every stage of the project to resolve any issues that arise during the building process.
Keep Records
Make sure to document everything at all times. Notices, letters, emails, images, and diaries should all be included in records.
3
Follow the Contract
The parties concerned should make sure they understand the contract in its entirety, including all of its provisions, terms, and
modifications. Once both parties are aware of the terms of the agreement, they should strictly adhere to them for the duration
of the project.
The success of a project depends on how quickly you can identify significant problems and communicate with the right people
to address them. Implementing building contracts enables success and avoids the endless disagreements that are likely to
sink your project.
References