Exp10 Synchronizing of Alts
Exp10 Synchronizing of Alts
Date:
Experiment No:10
Aim: Synchronization of 3-phase alternators with common bus bars by (i) Three dark
lamp method (ii) Two bright one dark lamp method and (iii) Synchroscope method
Apparatus:
Name of Equipment/Apparatus Nos.
Motor-Alternator Set 1/2
Three phase auto transformer 1/2
Three Phase MCB 3
Digital Multi meter 3
Load Bank 1
Synchronizing Panel 1
Frequency meter 3
Incandescent Lamps 6
Connecting wires
Speed Type
Theoretical Background
Need of parallel operation:
The parallel operation of alternator is needed for following reasons:
1. Several alternators can supply a bigger load demand exceeding the load capacity of single
generator.
2. During period of light load, one or more alternators of large rating may be shut down and
those low rating alternators remaining in operation, work on full load increase efficiency.
3. When one machine is taken out during scheduled shutdown for its maintenance or
emergency shutdown in case of faults in generator or grid, remaining unit maintains the
continuous power supply without interruption to the grid hence increasing the reliability of
grid for the end users of the power.
4. It becomes important to take into consideration the optimal and economy while delivering
power to grid, by both the utility companies as well as customer’s point of view. Parallel
operations help in the same.
5. For increasing future demand of load more machines can be added without disturbing
original installation.
6. Operation cost and cost of energy generated are reduced.
Thus parallel operation of alternators ensures greater security of supply and enable
overall economic generation.
An incoming alternator cannot be directly connected to the grid without matching the condition
for synchronization described below.
Synchronization is the process of interconnecting alternator and the grid while ensuring the
necessary condition for synchronization.
Procedure:
Procedure of synchronization with three dark lamps method (Figure 1)
1. Connect the circuit as per the circuit diagram shown in Fig. 1.
2. Initially, make sure the Synchronizing switch is open.
3. Adjust L-L voltage for infinite bus bar to 10 volts using auto transformer and check its
phase sequence. Say the phase sequence of infinite bus bar voltage is clockwise.
4. Also check the frequency of infinite bus bar. It is expected to near 50 Hz.
5. Now increase L-L voltage of infinite bus bar to rated 415 volts using auto transformer and
read it through the voltmeter connected at infinite bus bar end.
6. Adjust the DC supply voltage of DC motor to run it at its rated speed. This DC motor acts
as prime mover for the incoming synchronous generator.
7. Now gradually increase the field voltage of synchronous generator and note the rise in its
terminal L-L voltage.
8. Check the phase sequence of the generated terminal voltage of synchronous generator. If it
is not same as infinite bus bar, then reduce the field voltage to zero, ensure zero voltage
across generator terminal and then only interchange any two phases to adjust the same
phase sequence of both machines.
9. Now raise the field voltage to get rated terminal voltage of 415 volts of incoming
synchronous generator.
10. Adjust the frequency of incoming synchronous generator by adjusting the speed of DC
motor and bring its frequency near to 50 Hz.
11. If the voltage and frequency of incoming generator and infinite bus are not same, then
instantaneous voltage across all three lamps will be present and all three lamps will go
bright. The brightness of the lamp will depend on non-zero value of instantaneous potential
difference across the lamps. Higher the value of instantaneous potential difference across
the lamps, the lamps will glow brighter.
12. In case of non-zero instantaneous potential difference across the lamps, the operator has to
control (i) terminal voltage of incoming synchronous generator by controlling its field
excitation (ii) frequency of incoming synchronous generator by controlling its rotor speed
by adjusting the speed of DC motor.
13. Once instantaneous potential difference across the lamps become zero after these
adjustments and when all three lamps go top dark, the operator can synchronize the
incoming synchronous generator to infinite bus by closing the synchronizing switch as
shown in Fig. 1.
3. Connect the source selector switch at source 1 to connect input from source 1 to alternator.
4. Check the alternator excitation unit “OFF”.
5. Apply rated voltage to field winding of the D.C. shunt motor which acts as a prime mover
to rotate it at synchronous speed of the alternator.
6. Connect voltage selector switch (VSS Switch) to R-Y phase to measure the generated
voltage.
7. Switch ON the D.C. supply to the field winding and increase the excitation voltage till the
generated voltage is equal to the rated value.
8. With the help of phase sequence indicator provided in the synchronizing panel, check
whether clockwise or anticlockwise rotation is indicated. Phase sequence indicator shows
clockwise or anticlockwise rotation when the Phase sequence indicator switch is kept
pressed. Note that this switch is not for continuous use.
9. With the help of frequency meter provided in the synchronizing panel, check whether the
frequency of the generated voltage is 50Hz. If the frequency is not equal to 50Hz, adjust
the field excitation till the frequency of the generated voltage is 50Hz.
10. Now, switch the source selector switch from source 1 to source 2 to make the connection
with the grid. The meters/indicators on panel will now correspond to the grid quantities.
11. Gradually increase the output of the 3-phase autotransformer till the rated value.
12. Check the frequency and phase sequence of the grid with the help of frequency meter and
phase sequence indicator provided in the synchronizing panel.
13. Ensure that the voltage, phase sequence and frequency of the alternator matched with that
of the grid. Once this is ensured, close the synchronizing switch provided on the
synchronizing panel.
14. Connect the lamp method switch from off to all dark lamp.
15. Adjust the excitation voltage of alternator, till all lamps become dark.
16. Also with the help of synchroscope provided in the synchronizing panel, determine whether
the alternator is synchronized with the grid or not. This can be determined by turning the
Synchroscope switch for a short time. Note that this switch is not for continuous use.
17. Lastly, with the lamp method switch select two bright and one dark lamp method. If two
lamps are ON (glowing brightly) and one lamp is dark then the synchronization is achieved.
Conclusion: