Project Management Seatwork With Answer
Project Management Seatwork With Answer
B C
I
A D
F
J
E
G H
1. ABCIJ = 13
2. ADFIJ =14
3. ADGHJ = 16 is the CRITICAL PATH – which is the LONGEST path
4. EFIJ = 13
5. EGHJ =15
2. A project consists of 11 activities, lettered A through K, below. For each activity, the
preceding activity is given, and a deterministic estimate of the length of time required to complete
it in weeks..
Preceding Preceding
Activity Time Activity Activity Time Activity
A 1 week - G 4 weeks E
B 3 A H 6 F
C 2 A I 2 G
D 4 C J 1 H,I
E 2 - K 1 B,D,J
F 3 E
a. Draw the precedence network for this project, with the activities on the arrows.
Paths:
ACDK = 8
ABK = 5
EFHJK = 13 --- CRITICAL PATH
EGHJK = 10
f. The materials required to accomplish activity F have been delayed for two weeks by a
strike at the supplier's plant. What effect will this have on the length of time required
to complete the project? This will DELAY the entire project by 2 weeks.
g. An equipment breakdown has delayed activity B for one week. What effect will this
have on the length of time required to complete the project? NO EFFECT
CRASHING
Crashing means eliminating. There are some activities that can be crashed to free up time.
Crashing involves adding capacity.
For example: Assume Activity H is painting the house, which usually takes 4 weeks to
complete. But because rainy season is near and you want to complete the painting job faster, you
have to add capacity (painters) to help you finish the job faster. Adding capacity will also
increase cost.
Objective: We need to also manage cost (compute lowest cost) and crash the activities so that
the critical path will match the requirement in the problem, which is 11 Weeks.
3. Crashing: Given the following data based from Problem # 1, crash the activity to be able to
reach 11 weeks.
E 6 3 550 B
F 3 1 400 I
G 4 2 150 I
H 4 2 350 B
I 3 2 120 B
Effects of Crashing
Paths Time 1 2 3 4 5 6
ABCIJ 13 13 12 12 12 9 9
ADFIJ 14 14 13 13 12 12 11
ADGHJ 16 14 14 12 11 11 11
EFIJ 13 13 12 12 12 12 11
EGHJ 15 13 13 11 11 11 11
Choices from Critical Final Choice How Many Cost Critical Path
Step Path Weeks? left
1 D, G, H G 2 300 14
2 D, F, I, H I 1 120 14
3 D, H H 2 350 13
4 D, F D 1 250 12
5 B, C, D, F, E B 1, 2 or 3 400 12
6 D, E, F F 1 400 11
Total = 1,820