0% found this document useful (0 votes)
63 views104 pages

Lus Cp07c4c5c6 Ajp Mat Ir 00001 00 Lredc B

Uploaded by

Swaraj Rajan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
63 views104 pages

Lus Cp07c4c5c6 Ajp Mat Ir 00001 00 Lredc B

Uploaded by

Swaraj Rajan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 104

Elsaid Antar Approved with comments

Main Haddad
Refer to PMCM and SC comments
28-10-2020
03/11/2020
02-11-2020
Sensitive
#

REVIEW COMMENT SHEET

LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD, LUSAIL PROJECT – CP07-C, 4, 5, &6

PROJECT: LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD CONTRACT NO and PROJECT NO.: 9469 / CP07C4C5C6
RCS NUMBER: LUS-CP07C4C5C6-RCS-MAT-IR-00001 REV.: 00 DATE: 28-Oct-20
ORIGINATOR: DORSCH TRANSMITTAL NO and Workflow No. / DATE: AJEQATAR-WTRAN-000609WF-000707
DOCUMENT NO.: LUS-CP07C4C5C6-AJP-MAT-IR-00001 REV.: 00 DISCIPLINE: IRRIGATION

MATERIAL SUBMITTAL FOR HDPE PIPE AND FITTINGS (LANDWORX TRADING &
DOCUMENT TITLE: DOCUMENT TYPE: MATERIAL SUBMITTAL
CONTRACTING)
To be filled by
To be filled by CSC/PMC/LREDC CSC/PMC/LREDC
Comment Codes;
To be filled by Contractor
For Compliance : Work can proceed subject to compliance with requirement
Open/Closed
Note : Note about reviewed Document
For Implementation : Work cannot proceed until comment is addressed

No. Initial Page / Section / Clause Comment Code CSC Comments Contractor's Reply Reply Status by Reviewer

Approval Status regards to any document shall not relieve the Contractor any of the obligation, risk or
1 AS Note liability under the Contract.

2 AS Note Please refer to the marking in hard copy.

Item "C" in the attached Technical Data Sheet (Actual calculated values are 6.4 bar for PE 100 and 6.3
3 AS 3.3 Data sheet Note bar for PE80) is applicable for SDR 26 PE 100 PN 6 and SDR 21 PE 80 PN 6 .
Item "C" is not applicable for the proposed pipe HDPE PE 100 SDR 11 PN 16

5.1 Samples &


4 AS For Compliance Contractor to Submit Sample board for the item.
Accessories

The items mentioned in "5.2 Lead time delivery" are in imperial sizes but the proposed pipes are in
5 AS 5.2 Lead time delivery For Compliance metric sizes .
Contractor to ensure Compatibility of Proposed Pipe and fittings.

6 AS For Compliance Contractor to attach technical data sheet for the proposed fittings

Scope of work for proposed material is limited to Master Control Valve, Filtration & Flow Sensor
7 AS For Compliance Chambers and as per approved shop drawing.
Size of the proposed HDPE pipe and fittings shall be as per approved Shop drawing.

A. Approved B. Approved with comments C. Revise & Re-submit D. Rejected


Document Review Status Code By CSC:
E. Reviewed for Information

Name: ABDESSALEM BAYOUDHI Position: PROJECT MANAGER Signature: Date:

Page 1 of 1
Sensitive #

REVIEW COMMENT SHEET

LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD, LUSAIL PROJECT – CP07-C, 4, 5, &6

PROJECT: LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD CONTRACT NO and PROJECT NO.: 9469 / CP07C4C5C6
RCS NUMBER: LUS-CP07C4C5C6-RCS-MAT-IR-00001 REV.: 00 DATE: 28-Oct-20
ORIGINATOR: DORSCH TRANSMITTAL NO and Workflow No. / DATE: AJEQATAR-WTRAN-000609WF-000707
DOCUMENT NO.: LUS-CP07C4C5C6-AJP-MAT-IR-00001 REV.: 00 DISCIPLINE: IRRIGATION

MATERIAL SUBMITTAL FOR HDPE PIPE AND FITTINGS (LANDWORX TRADING &
DOCUMENT TITLE: DOCUMENT TYPE: MATERIAL SUBMITTAL
CONTRACTING)

To be filled by
To be filled by CSC/PMC/LREDC CSC/PMC/LREDC
Comment Codes;
To be filled by Contractor
For Compliance : Work can proceed subject to compliance with requirement
Open/Closed
Note : Note about reviewed Document
For Implementation : Work cannot proceed until comment is addressed

No. Initial Page/Section/Clause Comment Code PM/CM Comments Contractor's Reply Reply Status by Reviewer

The PMCM notes that the attached test reports in page 35 of the submittal are meant for another pipes. The
1 TS Page 35 For Compliance
contractor shall attached updated test reports for the proposed HDPE pipes as per the submittal.

The attached warranties from HEPWORTH and GEORG in page 44 and 45 are meant for another projects. The
2 TS Page 44/45 For Compliance warranty and guarantee shall be as per project requirement and shall be addressed to the client with project name
and contract code being mentioned on it.
The Water regulations advisory scheme letter in page 40 has expired. The contractor shall submit renewed copy in
3 TS Page 40 For Compliance
the next submission.
The contractor/manufacturer/supplier shall ensure that test certificates shall be provided with each delivery of
4 TS General Note
material.
HDPE piping system shall be installed as per manufacturer recommendations, project specification & approved
5 TS General Note
method statement.
Contractor to ensure the materials and test procedure shall conform to project specification, QCS and related
6 TS General Note
standards approved by the Engineer.

7 TS General For Compliance Physical samples for each HDPE pipes and fittings shall be provided for review and final approval.

Status Code Legend:

A. Approved B. Approved with comments C. Revise & Re-submit D. Rejected

Document Review Status Code By PM/CM: B E. Reviewed for Information

Name: Elsaid Antar Position: CM Signature: Date: 02 November 2020

No. Initial Page/Section/Clause Comment Code LREDC Comments Contractor's Reply Reply Status by Reviewer

1
A. Approved B. Approved with comments C. Revise & Re-submit D. Actioned
Document Review Status Code By LREDC:
E. Reviewed for Information

Name: Position: Signature: Date:

LUS-CP07C4C5C6-DCQ-FMT-RCS-00001 Rev.0 Date: 11/08/2020

Page 2 of 2
PROJECT/CONTRACT REF: CP07C4C5C6 I 9469

CONSTRUCTION PACKAGE CP07C4, C5 & C6


LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & D3

LUSAIL DEVELOPMENT
DOHA, QATAR

DOCUMENT TITLE:

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-IR-00001 00

CONTRACTOR:

AL JABER &PARTNERS FOR CONSTRUCTION AND ENERGY PROJECTS W.L.L

Issued for
19-10-2020 00 Corporate Quality
Approval
QA/QC Engineer manager Construction Manager Project Manager

Reason for
Date Rev.: Prepared Checked Checked Approved
Issue
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-IR-00001 Rev. No.: 00 Sheet: 2 of 26

TAB LE OF CONTENTS

1. Checklist
2. SupplierNendor Info.
2.1 Supplier/vendor in the preferred Vendor list?
2.2 Commercial Registration
2.3 Trade License
2.4 ISO Certificate
2.5 Organizational Chart
2.6 Authorized distributor letter/Certificate

3. Manufacturing & Technical Information


3.1 Material Country of Origin
3.2 Comparison of compliance sheet
3.3 Data sheet
3.4 Safety Data sheet
3.5 Drawing references
3.6 Lab/Test report
3.7 Guarantee/Warrantee
3.8 Manufacturer data and instruction

4. Compliance with Authorities Having Jurisdiction


4.1 QCCD
4.2 MOI - Security System Department
4.3 MOE
4.4 Others

5. Sample
5.1 Samples & accessories.
5.2 Lead time delivery
5.3 Spare parts requirements
5.4 Recommended Spare parts

6. References
6.1 List of projects
1.0 CHECKLIST
MATERIAL SUBMITTAL CHECKLIST

Brand and Description: HDPE Pi pes & Fittings

Specification reference: QCS 2010 Section 28 Part 2, COMMERCIAL BOULEYARD (CP7C-4)


LANDSCAPE QCS SECTION 28 AMENDMENT PART 2.1 SPECIFICATION.

SN DESCRJPTION YES NO NIA QAQC Comments

I Table of Content YES


2. Supplier/Vendor Info.
2.1 Supplier/vendor in the preferred Please refer to
Vendor list? ![ not, substantiate reasons (pr YES attached Previous
deviation in seoarate attachment A11orovals.
2.2 Commercial Registration YES
2.3 Trade License YES
2.4 ISO Certificate YES
2.5 Organizational Chart NO Not available
2.6 Authorized distributor
NIA
letter/Certificate
3. Manufacturing & Technical Information
3.1 Material Country of Origin YES
3.2 Comparison of compliance sheet YES
3.3 Data sheet YES
3 .4 Safety Data sheet YES
3.5 Drawing references YES
3.6 Lab/Test report YES
3. 7 Guarantee/Warrantee YES
3.8 Manufacturer data and instruction YES
4. Compliance with Authorities Having Jurisdiction (Check as Applicable)
4.1 QCCD N/A
4.2 MOI - Security System Department NI A
4.3 MOE N/A
4.4 Others NIA
5. Sample
To be provided in
5.1 Samples & accessories.
due course.
5.2 Lead time delivery (days) YES
5.3 Spare parts requirements (Qty) YES
5.4 Recommended Spare parts (Qty & Price) YES
6. References
6.1 List of projects YES
General Contractor
Signature & Stamp
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-IR-00001 Rev. No.: 00 Sheet: 3 of 26

Z. Supplier/Vendor Info.
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C - 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & D3

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-IR-00001 Rev. No.: 00 Sheet: 4 of 26

2.1 Supplier/vendor in the preferred


Vendor list

LUS-CP07C4C5C6-AJP-MAT-1R-00001_00 Page 4 of 26
after all valves' pressures have been adjusted.

3. Appendix

3.1. List of Pre-qualified Manufacturers/Suppliers


3.1.1. Irrigation Solenoid Valves
a. Rain Bird
b. Hunter
c. Toro
d. Hit
e. Weathermatic
f . Baseline
g. Motorola
3.1.2. Sprayer I Sprinkler Heads
a. Rain Bird
b. Hunter
c. Toro
d. Hit
e. Weathermatic
f. K-Rain
g. Baseline
h. Motorola
3.1.3. Emitters I Bubblers
a. Rain Bird
b. Hunter
c. Toro
d. Hit
e. Weathermatic
f. Baseline
g. Motorola
3.1.4. uPVC Pipes
a. Gulf Eternit
b. Hepworth
3.1.5. uPVC Fittings
a. George Fischer - up to 6"
b. Dura pipe - up to 6"
c. FIP - up to 4"
d. Atlas - up to 3"
3.1.6. PE Pipes
a. Gulf Eternit
b. Hepworth
c. National Plastic
d. Rain Bird (with built in emitters)

lUSAll REAL ESTATE DEVELOPMENT COMPANY


e. Eurodrip (with built in emitters)
f. Toro Ag. (with built in emitters)
3.1.7. Flanged Valves
a. AVK
b. Belgicast
3.1.8. Threaded Valves
a. Pegler
b. Pex
3.1.9. Valve Boxes
a. Carson
b. Rain bird
c. Applied engineering
d. Associated Plastics
e. Cosmoplast
f . Baseline
g. Motorola
3.1.10. Irrigation control systems
a. Rain bird
b. Hunter
c. Toro
d. Grisworld
e. Motorola
f. Waterman
g. Baseline
h. Motorola

SECTION F - LANDSCAPE LIGHTING

1. General Requirements

1.1. Scope of work


1.1.1. This section covers the specifications requirements for materials and installation of
exterior lighting, which include but are not limited to the following :
a. Landscape lighting fixtures (Bollard, Spike up ...etc.)
b. Water features lighting fixtures (Fountains, Cascades ... etc.)
c. Lighting Poles
d. Exterior Lighting Controls

1.2. References
1.2.1. The following international standards shall be referred to for the supply, design and
installation of all lighting works:
a. IEC 364 Electrical Installations in Buildings

LUSAIL REAL ESTATE DEVELOPMENT COMPANY


AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-IR-00001 Rev. No.: 00 Sheet: 5 of 26

2.2 Commercial Registration

LUS-CP07C4C5C6-AJP-MAT-IR-00001_00 Page 5 of 26
d..clia.Jlg OJl;illl OJljg
Ministry of Commerce and Industry

Registration and Commercial ~loJb!


Licenses Department ~l:;ull ~ljillg

2020/08/05 :ad~bJI ~Ju

111111111111111111111111111111111111111111111

000002694020943 ·UlJJpjl
• .. .. ~I... ..
,a.DJ 22901/1 :UlJ~I J+u>JI ,.cll'.>J
: ~J ~I Ci.o.JJJJ I po -~l.pl.'='1! uJgwn :UlJ~I ,ruoDI
13/02/2021 :J+u>JI .clinii I 2JJ u 25/10/2007 :J+w.11 .c Lilli I 2JJ u
0 :JLaJI u.ulJ c">J g:no C4,J gilu.o ub a5µl> :utigililJI ~I
po :oLlu.o.11 ~ h.il>.i :J+w.ll alb
0 :fg_µlll J.J.C
JlDiUI ulog!Ao
4760588 :JlaWI pl6Ji 50207 ::11.W I l9 g1iD

28282600432
25163400766
27225000382

Page 1of2
1/22901 ; J;i..wll ,.a.DJ

amber certifies that the above mentioned establishment has been registered
a.cl.i.a.Jlg . o~ 1·9
o~ UlJI ~
Ministry of Commerce and Industry

Registration and Commercial ~lo;b!


Licenses Department ZyJl.:µJI ~ljlllg

cwl5g llllil;ili.og ~!411 ~U!ll OJ~


llllilo. -

Page 2 of 2
1122901 : Ml p.g,

amber certifies that the above mentioned establishment has been registered
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C - 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-I R-00001 Rev. No.: 00 Sheet: 6 of 26

2.3 Trade License

LUS-CP07C4C5C6-AJP-MAT-IR-00001 _00 Page 6 of 26


2020/08/08 :acl+.bJI 2-JJli'
No 1 of 1 :,rui1 Cu.O.n

Registration and Commercial ~loJb!


Licenses Department OJL:;illlg :aUai9JJI OJljg a,Jl:µJI lP!=llJillg
Ministry of Economy ond Commerce

I 1111111111111111111111111111111111

2014/07 /17 :Cu::lipl Jl::ll:l I .?.!J Ii 14037 :Cu::lipl pDJ


2021/01/31 :am.iJI .c~I .?.!Jli #> -.,,ril.pl.1,/1! 0J9!/,ll) :1..J11Qill ,a..wlll
22901 :1..J1JQill ~I ,o.DJ a.5_µ1i :d!J QI! I oLi.u.aJ I f. gi
:d!J QI! I ito..ulJ I
: Jgg.w.o.11>!~I vU ~

~~ :iJUJ! i.141.w~ lfa-~ :Jgl.wJlll J!.J.o.ll p.wl


21225000302 :u4JVI ,.oi>J
: ~90ll vli~
17 :,.oi>11lfu: '!LC li..r::J : gf> g.o.l I ~

:o:l..)gJI /19.:UI ,.oi>J ~ --=~~lfgi


J9J4ll #> : 1lfu2J I dJlo ,a..w I 92 : CUib.i.o.J I
11 Ul4D ~1o_pg11 ap.l! : ulgi.S2.ll uiog ~I uld.ie.11 :f1Uilll
359 : fJWlll ,.oi>J
: Ct!J~I ~!JI
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C - 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & D3

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-IR-00001 Rev. No.: 00 Sheet: 7 of 26

'

2.4 ISO Certificate

LUS-CP07C4C5C6-AJP-MAT-IR-00001_00 Page 7 of 26
HEPWORTH PME QATAR W.L.L
Mesaieed Industrial City - Light Industries Area,
P. 0. Box: 50207, Mesaieed
STATE OF QATAR
Bureau Veritas Certification Holding SAS - UK Branch cert{fies that the Management
System of the above organisation has been audited and found to be in accordance with
the requirements of the management system standards detailed below

ISO 9001 :2015


Scope of certification

THE MANUFACTURE, FABRICATION, STOCKING, DISTRIBUTION AND


SALE OF THERMOPLASTIC PIPING SYSTEMS •

Original cycle start date: OSth December 2006

Expiry date of previous cycle: 17'11 September 2021

Re-Certification audit date: 03rc1October2019

Re-Certification cycle start date: 14t11November2019


Subject to the continued satisfactory operation of the organisation's Management
System, this certificate expires on: ostti November 2022.

Certificate No. ~90 U Version: No. 1 Revision date: 1411> November 2019

*
Vlnoth. K. P - Certification Manager
CeltificatJon body address
Local office: G1-G3, Ground Floor, KG Bullding
(Bldg. No. 194, Street No. 230), C Ring Road,
1.----------·1
5'1' Floor, 66 Prescot Street, London E1 BHG, United Kingdom

~,, •- I ,..... ·1 I
Oppo!lffe Guff Times, P. 0. Box: 22157, - ;, ~ l j'
(Doha) Qatar • 1 V
i UKAS, I
· ~ 1

I .... l
Fur1her clarifications regarding the scope of this certificate and the applicability of the management system
requirements may be ob!ained by consulting the organ!!lation.
To Check this certificate validity please cali: +974 40329729

Page 1 of1
HEPWORTH PME QATAR W.L.L
Mesaieed Industrial City - Light Industries Area,
P. 0. Box: 50207, Mesaieed
STATE OF QATAR
Bureau Veritas Certification Holding SAS - UK Branch certifies that the Management
System of the above organisation has been audited and found to be in accordance with
the requirements of the management system standards detailed below

ISO 14001:2015
Scope of certification

THE MANUFACTURE, FABRICATION, STOCKING, DISTRIBUTION AND


SALE OF THERMOPLASTIC PIPING SYSTEMS .

Original cycle start dcite: 13tti July 2016

Expiry date of previous cycle: 14t11 July 2022

Re-Certification audit date: 03rd October 2019

Re-Certification cycle start date: 14t11 November 2019

Subject to the continued satisfactory operation of the organisation's Management


System, this certificate expires on: ost11 November 2022.
Certificate No. IND 19.8990 u Version: No. 1 .Revision date: 14111 November 2019

;¥~~v
VInOJr:K. P • Cettlflcation Manager
Certification body address S"' Floor, 66 Prescot Street, LQndon E1 BHG, United Kingdom
Local office: G1·G3, Ground Floor, KG Building
(Bldg. No. 194, Sfreet No. 230), C Ring Road,
Oppo$ite Gulf Times, P. O. Bolt: 22157,
(Oohs) QB1llr

Hiit

Further clarifications regarding the scope of this certifical!;! and the applicabilitY of the managementsystem __ _
roquiremenls lllllY be obl.ailleO by consulting the organisation.
To check this certificate validity please can: +974 40;l29729

Page 1of1
HEPWORTH PME QATAR W.LL
Mesaieed Industrial City- Light Industries Area,
P. 0. Box: 50207, Mesaieed
STATE OF QATAR

Bureau Veritas Certification Holding SAS - UK Branch certifies that the Management
System of the above organisation has been audited and found to be in accordance with
the requirements of the management system standards detailed below

ISO 45001 :2018


Scope of certification

THE MANUFACTURE, FABRICATION, STOCKING, DISTRIBUTION AND


SALE OF THERMOPLASTIC PIPING SYSTEMS •

Original cycle start date: 14111 November2019

Expiry date of previous cycle: NIA

Certification audit date: 03l'CI October 2019

Certification cycle start date: 14111 November2019


Subject to the continued satisfactory operation of the organisation's Management
System, this certificate expires on: ost11November2022.
Certificate No. IND 19.8990 U Version: No. 1 Revision date: 1411t November 2019

$ ... v
Vinoth. K. P • Cettilication Manager
Certification body ¢dress 5"' Floor, ff Prescot Street. London E1 BHG, United Kingdom
Local office: G1-G3, Ground Floor, KG Building
(Bldg. No. 1!U, Street No. 2311), C Ring Road,
OpposJtfl Guff Timts, P. o. Box: 22157,
(Doha) Qafar

Page 1of1
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C - 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-IR-00001 Rev. No. : 00 Sheet: 8 of 26

2.5 Organizational Chart

NA

LUS-CP07C4C5C6-AJP-MAT-IR-00001_00 Page 8 of 26
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-IR-00001 Rev . No.: 00 Sheet: 9 of 26

2.6 Authorized distributor

letter/Certificate

Not Applicable

LUS-CP07C4C5C6-AJP-MAT-IR-00001 _00 Page 9 of 26


AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C - 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITIAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-I R-00001 Rev. No.: 00 Sheet: 10 of 26

3. Manufacturing S
Technical Information

LUS-CP07C4C5C6-AJP-MAT-I R-00001 _00 Page 10 of 26


AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-IR-00001 Rev . No.: 00 Sheet: 11 of 26

3.1 Material Country of Origin

LUS-CP07C4C5C6-AJP-MAT-1R-00001_00 Page 11of26


QUALITY ~\
~- ~ "
..._OOMPLIANC--~~ ·t"r ..\ (~) ·151·rl vi

CGRTlf:ICATG HEPWORl'H
P.M.B. {QATAR) W.L.L.

TO WHOM IT MAY cor~CER

This Is to certify that the following product supplied to the above customer are
manufactured and inspected to ISO 4427:2007 Standa.-·d and Company's
sseN1soeao1:2oos internal specifications and they are of QATP.R ORIGIN
CERT NO: FM 614004
SUPPLIED BY

HEPWORTH P.M.E. W.L.L. (<>ATP.~)


Quality Control Department
PE Division,
QATAR
A 8SI REGISTERED FIRM
ISO - tlOO·l: 2C 98
PRODUCTS
DS EN llZHIZOOO
LJ"'as:e I/DI .522746 ~ HOPE PIPES PE100 SDR9 PN20 Black for Water (20bar)
? HOPE PIPES PE100 SDR11 PN16 Black for Water :. 16ba.)
~ HOPE PIPES PE100 SDR13.6 PN12.5 Blaclt forWr:.ter (1::.5bar)
>-- HDPE PIPES PE100 SDR17 PN10 Black for Water 1JOba)
}:lo HOPE PIPES PE100 SDR21 PN8 Black for Water (tbar)
;.. HOPE PIPES PE100 SDR26 PN6 Black for Water (Gbar)
BS4Sl4~
Ucen10 Ho1 ml'47
FABRICATED FlTTINGS

HOPE Fabricated Rttings of the above are manufac:ured f:1d inspected by


Hepworth PME as per 1804427:2007 standard and compa.1y's internal

:~
Bl> _ .• 1401-1:1998
specifications.

. -· LJCl_!l~_l!D:_!22748 MOLDED FITTINGS

HOPE Molded Fittings are manufactured and inspec~ed b~ Georg Fischer


Piping systems as per relevant standards and they are o; Switzerland
Oriain.

JOINTING

Butt Fusion and Electro Fusion Methods

-- --~ ..

·,·.. : t l i"'! - ·, C'·\l (. ;1;~, () ';: f• . i•' · · · : : : • ~


\• . ,• ; "· t; .. i :· ~ •. ,.., : 1, :. ,. ~ » !· ; I « .• ~. ..
.... : -.

MAR 325 ·Rev.OO • , ._ ~ _ !·.~G.. !. L: ~:; rt . L ; .: . .. 118-.


AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C - 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMIITAL FOR HOPE PIPE & FIITINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-IR-00001 Rev. No.: 00 Sheet: 12 of 26

3.2 Comparison of compliance sheet

LUS-CP07C4C5C6-AJ P-MAT-1R-00001 _00 Page 12 of 26


COMPLIANCE STATEMENT

Item Material Description I SPECIFICATION I REMARKS


I REQUIREMENT I
HOPE Pipe & Fittings

MOPE and HOPE (PE) pipes and fittings shall be manufactured from virgin
1 Comply
materials only. Recycled, re-ground or re-generated materials shall not be used.
,_
HOPE pressure pipes and fittings shall be manufactured tram material
conforming to polymer classification PElOO having a minimum required strength
2 value (MRS) of 10 MPa at so years and 20•C In accordance with ISO 4427. Comply
Design stress shall be 8 MPa. The pipe manufacturer shall identify the
manufacturer of the resin~ the resin type and classification.
-
The HOPE pipe material shall be certified as meeting the requirements of the
3 Comply
PE10o+ Association .
..__
HOPE pipes shall have a standard dimension ratio (SOR) of 11 unless indicated
otherwise by the Engineer and shall have a pressure rating of 16 bar (PN16) at
s 2o•c (de-rated to 11.8 bar at 40•C, in accordance with Annex A of ISO 4427 Part
Comply
1) unless indicated otherwise by the Engineer.

-
Pipes and fittings shall be designed to achieve a minimum working life of SO
6 Comply
years under all applicable loads, environmental and installation conditions.
- Pipes and fittings shall be homogeneous throughout and free of visible cracks,
9 Comply
holes, foreign inclusions, voids and other injurious defects.
~
3.10.2 Manufacture The resin trom wnicn tne pipes and fittings are manu1actured shall comply w1tn
10 the requirements of ISO 4427 Part 1 and be protected from UV attack by the Comply
~
addition nf ra•hnn black in accorda nce with the s"'ndard.
Straight lengths of PE pipe shall be supplied in standard lengths of 12m (·0/+50
mm) measured at 23'C ± 2'C. Unless otherwise specified, coll length shall not
exceed lOOm. Coiled pipes shall be coiled such that localised deformation is
avoided and the minimum internal diameter of the coil shall not be Jess than 20
11 x outside diameter. Prior to Jointing the degree of pipe ovality shall not exceed Comply
the permissible levels given in Table 1 of ISO 4427, Part 2 and the Contractor
shall, if required, use mechanical re~roundlog equipment to meet these
requirements. Field cut lengths of pipe used as closures may not be shorter than
0.75 metre Jn length and shall be approved by the Engineer.
- All pipes shall be Indelibly marked at Intervals of maximum lm. The colour of
the pipe marking shall always contrast with the colour of the pipe. Markings Comply
shall include the rollowine information:
(a) Manufacturer's name, trademark Comply
{b) Material and designation i.e. PE100 Comply
(c) The nominal pressure (PN) of the pipe/ fitting Comply
(d) Dimension of the pipe (nominal outside diameter x nominal wall
Comply
12 thickness)
(e) Standard Dimension Ratio (SOR) Comply
(!) Production period (date/ batch code) Comply
(g) International Standard to which the pipe/ fitting has been produced
Comply
to
(h) Designation of the medium for which the pipe is produced for (water,
comply
gas, sewage)
{i) Stencilled in legible letters the pipe identification number on the outslc Comply
umess otnerwJSe spec111co11y approvea ay tne tngmeer, a•1~t pressure p1pe
fittings for use with pipes of up to 355 mm OD shall be injection moulded with
the same polymer classification, material type and pressure rating as the pipe to
1 Comply
which they are to be connected. All joints between PE pipes and fittings shall

- 2
whenever possible be by thermal butt fusion welding or electro-fusion welding
'-·-·-·-
Connections of PE pipes and fittings to metallic fittings shall be made with PN16
backing rings with a stainless steel stiffener insert or as recommended by the
pipe or fitting manufacturer and approved by the Engineer.
Comply
,_ 3.10.3 Fittings All PE fittings shall, as a minimum, be indelibly marked with the following
Comply
Information:
(a) Manufacturer's name, trademark Comply
(b) International Standard to which the pipe/ fitting has been produced
Comply
7 to

LANDWORXS
..:.i"J_,\i.JI_, oJ.~..ll ui6J.J ~'i
1.ANDWORX TRADING & CONlRACTING W.LL
CR. 72958, P.0.BOX: 20185
COMPLIANCE STATEMENT
SPECIFICATION
Item Material Description REMARKS
REQUIREMENT
HOPE Pipe & Fittings
(c) Material and designation i.e. PElOO Comply
(d) The nominal pressure (PN) of the pipe /fitting Comply
(e) Outside diameter and Standard Dimension Ratio (SDR) Comply
(f) Production period (date I batch code) Comply

L~N~\~OP~s
. .~.J':J .j\1~\..) o.;4:\ll ~ .:u'i
.)J
LANDWORX TRADING& CONTRACTING W.LL
CR. "12956, P.O.BOX: 20185
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT -I R-00001 Rev. No.: 00 Sheet: 13 of 26

3.3 Data sheet

LUS-CP07C4C5C6-AJ P-MA T-I R-00001_00 Page 13 of 26


s:
)>
;:c

"'"' ~
.a
01
;:c
CD
~
0

~
0

Ploeseries
SDR6 5DR7,4 5DR9 5DR11 SDR13,6 SDR17 SOR 17,6 SDR21 SDR26 SDR33 5DR41
52,5 53,2 54 SS 56,3 SB 58,3 S10 512,5 s 16 520

&t PE4D - PN10 PNB - PN5


Nominal aressure, PN • in bar
PN4 - PN3,2 PN2,5
PE63 - - - PN10 PN8 - PN6 PN5 PN4 PN3,2 PN2,5

+ PE80 PN25
-
PN20 PN16 PN12,5 PN 10 PNB PN 6° PN5 PN4 PN3,2

.,.. - -
PE100 PN25 PN20 PN16 I PN12,5 PN10 PN6e
(i) PNB PN5 PN4

+
Nom.
Size
16
20
25
"""'
3,0°
3,4
4,2
emox
3,4
3,9
4,8
"""'
2,3Cl
3,0°
2,5
2,7
3,4
4,0
em•
2,0e
2,3
3,o•
""""
2,3
2,7
3,4
e"'"
-
2.ot:
2,3
e-
-
2,3
2,7
"""'- """"
- 2,3
2,oe
-
Wall thicknesses •
e..., em• e,.,.. e"'"

-
""""
-
"""' """"
-
em•

-
e..,., e"""

::s!G)
32
40
5,4
6,7
6,1
7,5
4,4
5,5
5,0
6,2
3,6
4,5
4,1
5,1
3,0e
3,7
3,4
4,2
2,4
3,0
2,8
3,5
2,0t:
2,4
2,3
2,8
2,0•
2,3
2.3
2,7
-
2,od
-
2.3
- - - -
..,,m
zO
G>~
50
63
8,3
10,5
9,3
11,7
6,9
8,6
7,7
9,6
5,6
7,1
6,3
e.o
4,6

...
5,8
5,2
6.5
3,7
4,7
4,2
5,3
3,0
3,8
3,4
4,3
2,9
3,6
3,3
4.1
2,4
3,0
2,8
3,4
2,0
2,5
2,3
2,9
-
DLJ 12,5 13,9 10,3 11,5 8,4 9,4 D 5,6 6,3 4,5 5.1 4,3 4,9 3,6 4,1 2,9 3,3 -
~:!!
90
D1D
15,0
18,3
16,7
20,3
12,3
15,1
13,7
16,8
10,1
12,3
11,3
13,7
82 92
1
6,7
6,1
7,5
9,1
5,4
6,6
6,1
7,4
5,1
6,3
5,8
7,1
4,3
5,3
4,9
6,0
3.5
4,2
4,0
4,8
-- - --
- i Ill
mn
s::c
vim :;a
125
140
c;=i
20,8
23,3
26,6
29,9
23,0
25,8
29,4
33,0
17,1
19,2
21,9
24,6
19,0
21,3
24,2
27,2
14,0
15,7
17,9
20,1
15,6
17,4
19,8
22,3
...
11.4
,
12.7

16.4
12,7
141
16.2
18,2
9,2
10,3
11,8
13,3
10,3
11,5
13,1
14,8
7,4
8,3
9,5
10,7
8,3
9,3
10,6
11,9
7,1
8,0
9.1
10,2
8,0
9,0
10,2
11,4
6,0
6,7
7,7
8,6
6,7
7,5
8,6
9,6
4,8
5.4
6,2
6,9
5,4
6,1
7,0
7,7 .
-
-
--
200 33,2 36,7 27,4 30,3 22,4 248 182 20,2 14,7 16,3 11,9 13,2 11,4 12,7 9,6 10,7 7,7 8,6
225 37,4 41,3 30,8 34,0 25,2 27~ 20,5 22,7 16.6 18,4 13,4 14,9 12,8 14,2 10,8 12,0 8,6 9,6
250 4115 45,8 34,2 37,8 27,9 30,B 22,7 25,1 18,4 20,4 14,6 16,4 14,2 15,8 11,9 13,2 9,6 10,7
280
315
46,5
52,3
51,3
57,7
38,3
43,1
42,3
47,6
31,3
35,2
34,6
38,9
25,4
28,6
28,1
31,8
20,6
23,2
22,8
25,7
16,6
18,7
16,4
20,7
15,9
17,9
17,6
19,8
13,4
15,0
14,9
16,6
10,7
12,1
11,9
13,5 9,7 10,8 7,7
-
8,6
355 59,0 65.0 48,6 53,5 39,7 43,8 32,2 35,6 26,1 28,9 21,1 23,4 20,1 22,3 16,9 18,7 13,6 15,1 10,9 12,1 8,7 9,7
400
450
-. -
54,7
61,5
60,3
67,8
447.
50,3
49,3
SM
36,3
40,9
40,1
45,1
29,4
33,1
32,5
36,6
23,7
26,1
26,2
29,6
22,7
25,5
25,1
28,2
19,1
21,5
21,2
23,8
15,3
17,2
17,0
19,1
12,3
13,8
13,7
15,3
9,8
11,0
10,9
12,2
500 -- 55,8 61,5 45.4 50,1 36,8 40,6 29,7 32.8 26,3 31,3 23,9 26,4 19,1 21,2 15,3 17,0 12,3 13,7
550 - - -- 50,8 56,0 41,2 45,5 33,2 36,7 3t7 35,0 26,7 29,5 21.4 23,7 17,2 19,1 13,7 15,2
630
710
57,2
- .
63,1 46,3
52,2
51,1
57,6
37,4
42,1
41,3
46,5
35,7
40,2
39,4
44,4
30,0
33,9
33,1
37.4
24,1
27,2
26,1
30,1
19,3
21,8
21.4
24,1
15,4
17,4
17,1
19,3
800
900 .- - -
.- -
- 58,8 64,8 47,4
53,3
52,3
58,8
45,3
51,0
50,0
58,2
38,1
42,9
42,1
47,3
30,6
34,4
33,8
38.3
24,5
27,6
27,1
30,5
19,6
22,0
21,7
24,3
1000 - 59,3 65.4 56,6 62.4 47,7 52,6 38,2 42,2 30,6 33,5 24,5 27,1
1200
1400
- -- - - - - - 57.2 63,1 45,9
53,5
50,6
59,0
36,7
42,9
40,5
47,3
29,4
34,3
32,5
37,9
1600 - - . - - - 61 .2 675 490 540 39 2 433
a PN values are based on C =1,25.
b Tolerances In accordance with grade V of ISO 11922·1: 1997[1).
ccAe1ualcaleulated values are 6.4 bar for PE 100 and 6,3 bar for PE 80.
d The calculated value of emln nso 4065 12U Is rounded uo to the nearest value of either 2.0 2,3 or 3,0. This is to satlltv certain national requirements.

~
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-IR-00001 Rev. No.: 00 Sheet: 14 of 26

3.4 Safety Data sheet

LUS-CP07C4C5C6-AJP-MA T-1R-00001_00 Page 14 of 26


Polyethylene pipes and fittings have been used safely and effectively throughout the world, in a wide variety of installation conditions, for almost 40
years. At all times, the health and safety of operatives, and other people, involved in the processing, handling, jointing, installation, testing and use
of polyethylene pipe systems has been of paramount importance to Hepworth P.M.E. To achieve and maintain these objectives, good worl<ing
practice is essential.

The Material Jointing


Polyethylene is chemically unreactive and generally regarded as Butt fusion or electrofusion jointing of PE pipes and fittings should
biologically inert. It is not classified as a dangerous product (EEO. always be carried out in well-ventilated areas. The fusion process is a
high temperature operation and fumes are produced around the
Ingestion jointing area. Inhalation of the fumes should be avoided or kept to a
Ingestion of polyethylene in any form should be avoided. minimum.

Inhalation During the butt fusion operation, molten PE is lonned. This should not
Inhalation of PE dust can irritate the respiratory system. Wherever be allowed to come into contact with the skin as it will adhere strongly
possible, when cutting or scraping PE pipes, operatives should work in and cause severe burns. Protective gloves should be worn during the
the open air or in well-ventilated areas. jointing process and when cleaning the heater plates of the welding
machinery.
Physical Contact
Polyethylene is not regarded to be a skin irritant. During the electrofusion process, care should be taken to prevent the
ejection of molten material from the joint area. Protective clothing,
When cutting or scraping PE pipes or fittings, PE dust particles may including gloves and safety eyewear, should always be worn during the
cause eye irritation and it is recommended that protective eyewear be jointing process.
used.
Disposal of Waste Material
Fire Hazards Surplus or waste polyethylene material can be reprocessed i.nto new
Polyethylene burns but is not classified as Ramrnable. It has a Hash pipes or other products. Alternatively, it can be used as landfill or
point of 360'C approximately. incinerated, dependant on local regulations. Proper combustion does
not require special exhaust control technology.
Above 300'C, PE will degrade to produce carbon rnonoXJde, water and
small amounts of various hydrocarbons and aldehydes. The Environment
Polyethylene is not considered dangerous for the environment
Avoid the accurnrnulation of PE dust particles as they could give a
potential risk Of dust explosion. FimAld
The following are recommel'ldations for immediate first aid to be
AU electrical equipment in the area should be carefully sited and applied in the event of an accident involving polyethylene products.
earthed. However, qualified medical attention should be obtained as soon
as practically possible.
In the event of fire involving PE materials, apply water in a spread jet
Dry chemical, foam and carbon dioxide can also be used. Ingestion: Wash mouth out with water

Handling Inhalation: Move affected person into fresh air situation.


PE pipes and fittings should be handled and moved in accordance with If 1n distress, apply oxygen or artificial respiralion.
the instructions detailed in the Handling & Storage section of this
publication. Eye Injury: If PE particles enter the eye, immediately flood with water,
repeating as necessary.
Particular care should be taken when handling large diameter PE pipes.
Burns: If molten PE material comes into contact with the skin, cool
Safely clothing and equipment should be used at all times when the affected area immediately by Hooding with cold water.
handling and moving PE pipes and fittings. DO NOT remove the PE material from the skin - seek
medical attention as quickly as possible even for the
When transporting, handling and releasing coils of PE pipes, extreme smallest burn.
caution should be taken, instructions detailed in the Handling &
Storage section MUST be strictly adhered to.

- Hepworth
MAR 325 Rev.OD
+GF+ GEORG FISCHER
PIPING SYSTEMS
56
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & D3

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-IR-00001 Rev. No.: 00 Sheet: 15 of 26

3.5 Drawing references

LUS-CP07C4C5C6-AJP-MAT-IR-00001_00 Page 15 of26


V8f'tica1 Bends(Uplhrust) Mio. ConCfe{e VollMTle {M3) 90 o ELBOW TEE
Project
t~ a
PUBLIC REALM LUSAIL
PioeDia 9{)0 45 ° 22.5 ° 1125 ° Pipe Dia(") A{mlr.) B(mtr.) C(mtr.) D{mtr.) P~Dia\) Almlr.l B{mtr.) C(mtr.t D{mtr.l
COMMERCIAL
BOULEVARD(CP7C-4)
2" 0.41 D.22 D.11 0.06 2 0.50D 0.380 0.350 D.500 2 D.37D D.2DD D.370 D.500 Prepared
3" D.79 0.46 0.40 D.2D 3 0.7DO 0.600 D.500 0.700 3 0.545 0.25D 0.545 0.700 Lusail Real Estate
4· 0.88 0.48 D.24 0.12 4 0.900 0.760 0.80D 0.700 4 D.7DO 0.30D 0.7DO 0.7DO Development Company
6" 3.13 0.70 0.40 0.44

~
f......, 6 1.460 0.970 I.COO I.COO 6 1.050 D.4-00 I.DOD I.ODO Project No: 14.33008.00
8" 5.31 2.67 1.46 D.46 8 2.510 UDO I.ODO 1.200 8 1.770 0.400 I.DOD 1.200

lil..LlllOUlOIO
=~a~: .Hl.OC!Cic..JNSl
PR01EC1FWNC•JTHOQl8.£MIAP
1£AVTillll'rPO•.T£!H.!l((Sfl!:EllllO
Area of Concrete (sq.m.)
Pipe Dia
1"
3"
4•
TEE
D.137
D.294
0.486
9{)0

D.19
D.42
0. 69
45°
0.11
D.23
0.37
22.5
O.D5
0.12
0.19
° 11.25
D.D6
D.10
O.ID
° Pip&Dia(' )

4
2
J
A(mtr.)
0.250
0.440
0.650
45 o ELBOW
B(mtr.)
0.250
0.300
0.350
C(mtr.)
D.45D
0.52D
0.570
D(mtr.)
0.500
0.700
0.700
II
HOK London
Outi&,90W'1i!ield51rvet
loMon.W1HEZ,U
1+44!0)2075362006
HOK Dubai
HflolerTaweia,SZR
o..illtl, U.1.EPOBc».2'437
/+971(CJ•lB2681la
lw..l(t)21171i$51S1!7 f+971 (1)J43!2 611to
0.4 ) 6 1.000 0.400 0.800 1.000
6" 1.050 1.48 D.BD 0.20
(i:') TtflUST BLOCK ARRANGEMENT: TYPfCAl Pl.MS & SECTION
11o11o LL
6" t. 770 2.51 1.36 0.69 0.35
8 1.240 0.550 I.ICC 1.200 ~D~
--~.,....,.. ....--.9-•:>. ........
FounlalnsDln=ctUd .
.-21.T~Cl)o.AwDW.r.-..d• _ _ P_
:;e,~F-.s...,.,.,

MASTER CONTROL VALVE, FILTERATION 3500 - - -- - ...


~~~3;.~~:~:01.IM~Z..,.d~ood,PO
&FLOW SENSOR CHAMBERS
Ecoscape A11ricultu nil l Con11Ullani•

©
NO I DESCRIPTION
I BUITERFLYVALVE
·-·
101,AIZ•_,,.Uuildloi,Abu _,,. .... H<ilR<M""UAli

ut1.111<o<......,.1<a•. 1...-s1i1SNW.U"

='.!."~~- ..... ~
Y.sTRAIER ~·
=:...,..__T-.-•""'1.
PRES&lAERElllJam IMST£R VM.~ WSPIParsoo • ~ft

SY-l'ASSVAl.VE
~~~~~Ollc.ot-.•- ... 2 -
AUT0ClEANDLSCFlTERS(S)3'dili

t#.NHOLECOVERWITHFAAME

REINFORCED CONCRETE VALVE CHAMBER

FLr:JNSENSOR

LAOOER-ftSTAl.lEDASPERlOCM.COOE{S)
ll>PEPIPE(SCZEASPER~~ELAYOUTOAAWllGS)

WORK ~T IRRIGAH.>NNtlWORK MAllHCINH.l.CTOR - I ~y OTHER~ J


PA~POUO
PIAN PLAN
IAAICi.l.lllNH!TWORKMAINYALYtCHAM8!A! YO' [ONNHTIONWCR~S

~EJ~i .. ""--

SECTION
~• ..W...,.jt>y: SBG
Draw"Oa,.:18/05/2017 Sct111@..,1· 1:100
MD TES Scti•@A3 1;500
Prej.c!Nc: 14,33008,00 (Apptel<.~
1S!ZfSQf!UITEAFLYYALY!,BYPmv~LYl.Y ·SflWllER.PR(SStrRERE!ll(fjliMAiU.mVt:.FlO\llS(NSQR

IRRIGATION
MASTER CONTROL VflJ..VF., FILTERATION & FLOW SENSOR CHAMBERS (4' DIA) INSTALLATION DETAILS
EXISTING DISTRIBl!TION CAHl.1BER ~ ~KlATION NETWORK MAIN (DONE BY OnlERS)

_ _______
PACKAGE CP07-05
.............. ...... ""' .,

IR60005 00
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-1R-00001 Rev. No.: 00 Sheet: 16 of 26

3.6 Lab/Test report

LUS-CP07C4C5C6-AJP-MAT-IR-00001_00 Page 16 of 26
Hepworth

TO WHOM IT MAY CONCERN


Product : 315mm PE100 SDR11 PN16 Black Polyethylene Pipe
Batch No. : WK· 28 YR-18, Shift: AIB
Material : H1000PC/1G150286
Standard : ISO 4427:2007/ QCS2014
Country of Origin : State of Qatar
Warranty : 365days from the date of delivery of materials to your project site
Certificate Status : Sample
Issue Date : 22.07.2018

Inspection Certificate Type 3.1 in accordance with EN 10204


We certify that the above listed articles comply with the following requirements:
Raw Material test
Comrol and rest
ISO & OCS Clause No. Opa1aton or Tesl Requirements Test Resul!s
Method No.

1$04427-1:2007 4.4 Tablc-1 Melt Flow Rate Tile MFR or the compound shall nol 02270 110mins
IS01133
OCS 2014 Section 8 Part3 Teble1 da~a1e by more than+/. 20 I)~ (3.18%. Passed)

IS04427-1:20074.4 Tabl ..1 Densl!Y(R') ISO 1183-2 ~ 0.930 gm/an' 0.959gmlcm' i Passed
1504427-1:20074.4 Tabl ..1 60 Minules; Passed
Thetmal Stability 15011357-6 >20Mlnutes
QCS 2014 Section 8 Pan3 Tablo1

1$04427-1:2007 4.4 Tablo-1 Carbon Sleck (R") 1506964 2.25 •I· 0.25 % 2.40%; Pe5'ed

~~·~1 ...

Tho Internal and external surfaco ahaD


1504427-2:2007 (5.1) be smooth, clean and free from searing,
Visual fnspecUon 1504427
cavities and surface ddec:.ls wh!c:h may
Passed
QCS2014 se-cUon 8 Pa'13 Tabla 2
affect pipe performance

IS04427·2".2007(6.2) <Mtside Diameter 150161·1 Min. 315.00 mm OOObsen.e.d


OCS 2014 Section B Part 3 Tabla2 fTolsrances 15011922·1 Mall 316.90 mm 315.2S mm; Pa"cd

1504427-2:2007(6.3) WallThielule.. 1504065 Min. 28.60 mm Min. 28.98 mm


QCS 2014 Soc6on 8 Par1 3 Teble2 FToleranceJ 15011922-1 Max.31.60mm Max. 31.18 mm Passed

1504427-2:2007(6.2)
Ovalft)' lfolurances 15011922-1 Max.11.1omm Ova~ty-4.00 mm Passed
QCS 2014 Section 8 Parl 3 Teble2

As stipulated in lhe
1504427-2:2007 (6.5) Longlh ordor
12Mu Passed

1504427·2:2007 8.2 Table-5


Thennal Stability 15011357·6 > 20 Minutes 60 Minule5; Pa$,f3d

1504427·2:2007 8.2 Table-5 Tho chanoo In MFR caused by 0252g /1Dmms


Mell Flow Raio ISO 1133
QCS 2014 secion 8 Par13Tabla 2 processing shall nol be more lhan 20% (1.61% :PaS$ed)

Elongation at break 0!350% 750%; Passed


1504427·2:2007 8.2 Teble-5
1506259
QCS 2014 Secion 8 Part 3Table 2
Tensile Suenglh @ Yield <19Mpa 2':20 Mpa, Passed

1504427-2:2007 (11) Marking 1504427 Minimum as .per st.andatd Passed

MAR 325 Rev.00 105


Hepworth

TO WHOM IT MAY CONCERN

Product : 250mm HOPE PE100SDR11 PN16 Black Polyethylene Pipe


Batch No. :WK-10YR-18,Shift: AIB
Material : P901BK/171206002
Standard : ISO 4427:2007/ QCS2014
Country of Origin : State of Qatar
Warranty : 365days from the date of delivery of materials to your project site
Certificate Status : Sam ple
Issue Date : 07.03.2018

Inspection Certificate Type 3.1 In accordance with EN '10204


We certify that the above listed articles comply with the following requirements:
Raw Material test
Conlral .and Tesl
150 & 0CS CJauu No O,>etation .:ir Test Requirements Te.&I Results
Molhcd No.

IS04427-1:2007 4.4 Ta!>l .. 1 Mell Flow Rate The MFR of the compound shall ool 0.227g /tOmtn•
1$01133 de\oia1e by moro lhan -+/· 20 % (3 . 18~, Psssed)
QCS 2014 Sac1ion s Part3 Tabla!
1504427-1:2007 4.4 Table-1 Oanslly (R") 1$01183·2 <t. 0.930 gmttm' o.959gm/cm>; Passed
1504427-1:2007 4.4 Table-1 SO Minutes; Passed
Theimol Slabdlty 16011357-6 :>20 Mfnute::s
QCS 2014 5eotion 8 Part3 Tabfo1
1504427-1:2007 4.4 Table· I Carbon Blaok (R"] 1$06964 2.25 ·~025% 2.40%: P;::issed
PfOdud t S

The lnlemal and e>demal surface shaU


1504427°2:2007 (5.1 ) 15()1427
be smooth, clean and free from SCOf'ing , Passed
Vlaual ln51>eclioo
OCS2014 Secllon8 Psrt3 Table 2 CS'dlie:; and surta~ defects which may
affect prpe pelformance

IS04427-2:2007{621 Oulsida Oiamo1er 150181-1 Min. 250.00 mm OOObserwd

(~)
QCS 2014 SecUan 8 Part 3 Teble2 ITo!erancus 15011922·1 Max. 251.SOmm 250.78 rnm: Passed

1504427-2:2007(8.3) Wal Thickness ISOI065 Min. 22.70 mm Min. 22.92 mm


QCS 2014 Sedon 8 Par13 Tablo2 /Tolerances 15011922·1 Max. 25.10 mm Max. 24.42 mm PeHed
1504427·2:2007{82) Ovafily lfolcraneas 15011922·1 Max.5.00mm Ovality-3.00 mm Passed
I illi IJrnlD!il QCS 2014 5e<:tion 8 Part3 Teblo2

1504427-2:2007 (B.5) Lenglh


As stipulated In Passed
12Mlr
lheorctor
Should eusla1n 12.4 MPa for 100 hours
1~04427-2:2007 7 2 Tablo·3 Hydrootefic 5ttength 1501187
@200egC
Paned

1504427-2:2007 8.2 Table-5 ThannalSlabiily 15011357.S >20Minutss 60 Minut05; Passed


1504427·2:2007 8.2 Tabfe-5 Tho chanve in MFR oaused by 0 .2350110mins
Mell Flow Rata 1501133
QCS 2014 Saollon B Part 3Tabla 2 ptOCeSstng shall nolbe m01e flan 20% (0.12% ;Paosed)
E!Ongation at bt11a~ >350% 750%; Passed
1$04427-2:2007 8.2 Tebl..S
1506259
QCS 2014 Seotion 8 Part JTabfe 2 Tensile Sfranglh @ Viefd >19 Mpa >20Mpa,Passed

IS04427·2:2007 (11) Marl!lng 1504427 ~mum as per standard Pused


Note: •: Reference to respective batch Certificate of Analysis

.o!Jt'll'PJ4Jl.ce o~ ' t

·!""Hepworth\
a
~ ',~ ~-
/
,;

MAR 325 Rev.00 106


Hepworth

TO WHOM IT MAY CONCERN


Product : 160mm HOPE PE100 SOR11 PN16 Black Polyethylene Pipe
Batch No. : WK-10 YR-18, Shift: N B
Material : P901BK/171206002
Standard : 1504427:2007/QCS 2014
Country of Origin : State of Qatar
Warranty : 365days from the date of delivery of materials to your project site
Certificate Status : Sample
Issue Date : 07.03.2018

Inspect ion Certificate Type 3.1 in acc.orda11ce with EN 10204


We certify that the above listed artlcles comply with the following requirements:
Ftaw Material test
Control and Tes!
150 & QC5 Clause No. Operation ot Tesl Requlromenls Tes1 Results
MelhcdNo.

1504427-1:2007 4.4 Teblo·I MettAov1Rate The MFR ol \tur c;:ompcund shall nol 0.227g n0m1ns
1501133
QCS 2014 Section a Pa113 Tabl•1 de~alB by more lhan ... 1--20 % (3.18%, Passed)
1504427-1:20074.4 Table·! Oensily (R') 150118'1-2 ~ 0.930 gmlcm3 0.959gm.len1'; Passed
1504427-1:20074.4 Table-I
Thcnnel Slablily 15011357-6 >20 Minutes 60 Minulcis; Passed
QCS 2014 Section 8 Parl3 Table!

1504427-1:20074.4 Table-I CarbOn Black (R') IS06!HW 225+/-025% 2.40!~; PaHed

P-•~• 1..1

The lnlemal and e:d.emal surface shall


1504427-2:2007 (5.1) be .smoolh, clean and free from scoring,
Viaual Inspection 1501427 Passed
QCS2014 Saclion 8 Part 3 Table 2 ca~tie& end surface defeels wflich may
affeot pipe performance

1504427-2:2007(62) Outside Diameter ISOIBl-1 Mtn. 160.00 mm ODObseMd


ClCS 2014 Section 6 Pert 3 Tsble2 rroterances 15011922-1 Max 161.00 mm 160.42 mm; Passed

1504427-2:2007(11.3) Walllhicknass 1$04065 Min. .14.60 mm Min. 14.74 mm


QCS 2014 Section 8 Part 3 Table2 /Tolerances 15011922-1 Max. 18.20 mm Max. 15.98 mm Pasead
1504427-2:2007(8.2)
QvaJlry /Tolarances 15011922- 1 Max.320mm Ovality-1.54 mm P..sed
OCS 2014 Sccion 8 Part 3 Table2
Al sUpulaled In
1504427-2:2007 {6.5) Lenglh 12MIT Passe,d
theon.1sr
1504427-2:2007 8.2 Table-5 TllonnalSlabiily ISOl1357-6 >20Minufes 60 Minutes; Passed
1504427-2.°2007 82 Table-5
QCS 2014 Saclion 8 Part 3Tabla 2
Longitudinal Revet51on 1502505-1 Max 3% change: in tho lnldal longlh 1.00 %; Passed
1504427·2:2007 8.2 Tabla-5 The change In MFR caused by o 228911om1ns
Melt Flow Rate 1$01133
QCS 2014 SacUon 8 Part3Tabla 2 procesalng shall no1 ba more than 20% (0.44% ;Passed)

Elongation al break •350% 750%;Paased


1$04427-2:2007 8.2 Tsbla-5
15C6259
0CS 2014 Section 8 Part 3Table 2 ~20
Tensile Strength @ Yield •19Mpa Mpa, Passed

1504427-2:2007 (11) Marking ISOl427 Minimum as per stam:fard Passed

Note:•: Reference to respective batch Certificate of Analysis

MAR 325 Rev.00 107


orth
TO WHOM IT MAY CONCERN
Product : 180mm HOPE PE100 SDR11 PN16 Black Polyethylene Pipe
Batch No. ; WK· 10 YR-18, Shift: AIB
Material : P901 BK/171206002
Standard : ISO 4427:2007/ QCS2014
Country of Origin : State of Qatar
Warranty : 366days from the date of delivery of materials to your project site
Certificate Status : Sample
Issue Date : 14.03.2018

Inspection Certificate Type 3.1 in accordance with EN 10204


We certify that the above listed articles comply with the following requirements:
Raw Material test;
CQnlro1 and Tesl
ISO & OCS Clause No. Operation or Tesl
MoU1od No
RoqulremenlS Te6l Results

1504427-1:20074.4 Table-1 Mell Flow Rate The MFR of lhe compound shall not 02279/\0mins
1501133
OCS 2014 Seclion B Part3 Teble1 de\iate by moro lhan +/-20 % (3.18%, Passed)
1504427-1:2007 4.4 Tabl&-1 Oens/ly(R') 1501183-2 2 0.930 gm/cm 3 0.959gm/c.m11 : Passod
1504427-1:20074.4 Table·1
Therms1 Stabirity 15011357-6 > 20 Minutes 60 f-A!nules; Passed
OCS 2014 Section 8 Part.3 T;ble1
1504427-1:20074.4 Teble-1 Carbon Blaol< (R') 1506984 2.25 +/- 025 % 2.40%; Passed
Product e"•~
The Internal and eX1emsl surface shall
1504427-2:2007 (5.1) be smooth. dean and free from staring,
Visual Inspection 1504427 Passed
QCS2014 Section 8 Pan 3 Table 2 ca\1Ues and sul'face defects which may
aKact plpo petfonnance

1504427-2:2007(6.2) Out.side Diameter 150161-1 Min. 180.00 mm OOObserve.d


QCS 2014 5ection 8 Part 3 Table2 fTolerancea 15011922-1 Max.181.10 mm 160.42 mm, Passed

1504427-2:2007(8 3) Wall Thick.ness 1504065 Min. 18.40 mm Min. 18.74 mm


QCS 2014 Section 8 Part 3 Table2 /Tolerances 1$011922-1 MS>< 18.20 mm Max. 17.98mm Passed
1504427-2:2007(62)
QCS 2014 Secfon 8 Part 3 Table2
Ovality /Tolerancoa 15011922-1 Max.3.60mm Ovatit~1.S4 mm Passed

As slipula!ed In tho
1504427-2:2007 (8.5) Length 12M~ Passed
order
1504427-2:2007 8.2 Table-5 Tllennel 5labitty 15011357-6 >2D Minutes 60 Minutes: Passed
1504427-2:2007 8.2 Tabla-$ The changa in MFR caused by 0.220gl10mins
MellFtowRato 1501133
QCS 2014 Section 8 Pert 3Teble 2 processing aha I not be morD lhiln 20% (4.34% ;Passed)
Elongallon at break >350% 750%·; Passed
1504427-2:2007 8.2 Table-5
1506259
QCS 2014 Section 8 Part 3Table 2
Tensie S~anglh @ Vlelcl ~19Mpa 2i<l Mpa, Passed

1504427-2:2007 (11) Marfling 1504427 Minimum as per stlndord Passed

Note: •: Reference to respective batch Certificate Ot Analysis

MAR 325 Rev.00 108


Hepw rth
7-~·r:t. tllt.
jt.:(.(:- _..!. (..._: 1/-. / >1·fzl1·
L./_. 'l i:L
., ~.. {.{ L,...

..,._.·
TO WHOM IT MAY CONCERN
Product : 125mm HOPE PE100 SDR11 PN16 Black Polyethylene Pipe
Batch No. : WK· 10YR·18Shift: AIB
Material : P901BK/171206002
Standard : ISO 4427:2007/ QCS2014
Country of Origin : State of Qatar
Warranty : 365days from the date of delivery of materials to your project site
Certificate Status : Sample
Issue Date : 14.03.2018

Inspection Certificate Type 3.1 in accordance with EN ·t0204


We certify that the above listed articles comply with the following requirements:
Raw Material test
Control and Tcsl

~
!SO & OCS Clause No Operation ar Tes! Requiiemenls Tesl Resulls
Method No.

1804427-1:2007 4.4 Table-1 MellflQ\\IRsl!t The MFR of Iha compound snail not 0.227g /10mlns
1$01133
OCS 2014 Secdon 8 Part3 Table1 de..Cata by m0<e than -+/-20 % (3.18% ,Paased)

1504427-1:20074.4 Tablo·1 Density (R') 1501183·2 :ie0.930gmA:::mS 0.959gmlcm': Passed

I~.'fL~t:?.1 1504427-1:20074.4 Table-1


QCS 201-4 Section 8 Par13 Jablo1

1504427·1:2007 4.4 Table·1


Thermal Slabiity

Carbon Black !R'J


15011357-6

1506964
>2DM!nul0&

225 +/-0.25 %
60 Minul•s: Passed

2.40%; Passed

w APPROVED
1504427-2:2007 (5.1)
QCS2014 Section 8 Par! 3 Tobie 2

1504427·2:2007(6.2)
Visual Inspection

Outaide Diameter
1504427

150t6H
The lnlemal and eldemaJ 1urfece shall
be smoolh, chsan anti free fl'om 'toting,
cavitia& end suttace defects which mPy
arrect pipe performance

Min. 125.00 mm
Pa:ned

00 Obserwd
QCS 2014 Section 8 Part 3 Table2 /Tolerances 15011922·1 Max. 125.80 mm 125.28 mm, Passed

1504427-2:2007(6.3) wau Th!C:lmoss 1504065 Min. tt 40mm Min. 11.82 mm


QCS 2014 Seclion 8 Pert 3 Tablo2 /Tolerances 15011922·1 Max.12.70mm Max. 12.22 mm Peued

1504427-2:2007(6.2)
QCS 2014 Sociion 8 Pert 3 Tabla2
Ova!ity /Tolerances 15011922-1 Max.2.SOmm Ovaliy-1.10 mm Passed

As stipulated In
1504427·2:2007 (6.S) Lenolh lhaorder
12M~ Passed

1504427-2"2007 8.2 Tabla-5 60 Minutes; Passed


rnennol SJabiily 15011357-6 >20Mlnutos
1504427-2:2007 8.2 Tablo-5
Longlludlnal Reversion 1502505-1 Max 3% cl'lange in the lniial lenglh 0.90 %; PaHed
QCS 2014 Sections Part3fetile 2
1504427-2:2007 8.2 Tabl ..s
MellFlgwRate Tho char>lJD in MFR COU•ed by 0.240g /10mlns
1501133
CCS 2014 Section 8 Pert 3Tebla 2 proce11lng shall not be more l!lan 20% (5.88% ;Passed)

Elongation at break >350% 750%;.Paesod


1504427·2."2007 8.2 Tabla-5
150ll259
QCS 2014 Seclion e Part 3Tabla 2
Ten5iie Sll'eng!h@ Yield >19 Mpe 220 Mpa, Passed

1504427-2:2007 (11) Marl<Jng IS04427 Minimum as perstandard Passed

Note:•: Reference to respective batch Certificate 9f Analysis

MAR 325 Rev.DO 109


Approval Number: 1509527
WRAS
APPROVED MATERIAL
Test Report: MA5482/X

Water Regulations Advisory Scheme Ltd.


Unit 13,
1s1h April 2017 Willow Road,
Pen y Fan Industrial Estate,
Hepworth PME {Qatar) WLL Crumlin,
PO Box 50207, Gwent,
Mesaieed, NP11 4EG
Qatar

WATER REGULATIONS ADVISORY SCl'iEME LTD. {WAAS)


MATERIAL APPROVAL

The material referred to in this letter is suitable tor contact with wholesome water for domestic purposes having met the
requirements of 856920-1 :2000 and/or 2014 'Suitabilily of non-metallic products for use in contacl wilh water intended for human
consumption with regard to their effect on the quality of lhe water'.

The reference relates solely to its effect on the quality of the water with which it may come into contact and does not signify the
approval of its mechanical or physical properties for any use.

POLYETHYLENE· COMPONENTS. 5240

'Hepworth PESO & PE100' pipes. Black coloured or blue coloured PESO or PE100, extruded polyethylene pipes. For use with
water up to so•c.

APPROVAL NUMBER: 1509527


APPROVAL HOLDER: HEPWORTH PME (QATAR) WLL

The Scheme reserves the right to review approval.


Approval 1509527 is valid between September 2015 and September 2020

An entry, as above, will accordingly be included in Iha Water Fittings Directory on-line under the section headed, "Materials which
have passed full tests of effect on water quality".

The Directory may be found at: www.wras.co.uk/directory

Yours faithfully

Jason Furnival
Approvals & Enquiries Manager
Water Regulations Advisory Scheme

""""""""""",.,,......................................."""._____........____________________.........................................................._
The Waler ReQIJ!ations Advisory Sdleme Lid. Reaistared ln England NO, 06663930 Registered offJCS: 60 Loviici< Closs, Haud Grow, Sla<kport, SK7 5ED
Tcl:+44(0)333 207 9030 Fax:+44(0)1495 248540 Ema»:lnfo@m;ts.c.o.uk websile~v.wms.co.uk
MAR 325 Rev.00 111
WRAS MATERIAL APPROVAL· MATERIALS WHICH HAVE PASSED FULL TESTS OF EFFECT ON WATER QUALITY

The material referred 10 in this letter is suitable for contact with water for domestic purposes. Approval of this material does not
signify the approval of Its mechanical or physical properties for any use.

Manufacturers or applicants may only quote in their sales literature terms which are used in this letter, namely that; 'the material
as listed, having passed the tests of effect on water quality, is suitable for use in contact with wholesome water'

This may be abbreviated to 'Water Regulations Advisory Scheme· Approved Material' or 'WRAS Approved Material'.

The scope of an Approval does not extend to rebranded materials unless otherwise agreed by the Scheme.

Use of the WRAS Approved Mater(al Logo

Approval holders may use the WAAS Approved Material logo and make reference to any approval issued by WRAS Ltd. in
respect of a particular material or range ol materials provided the approval is, and remains valid.

Approval holders are entitled to use the logo on the packing, promotional literature and point of sale advertising Approved
Materials.

Modifications to existing Approvals

II is a condition of WAAS Material Approval that NO changes or modifications to the Approved Material, be made without the
Approval Holder first notifying WRAS Ltd. Full details of the proposed changes must be provided to the Scheme. Failure to
comply with this condition will immediately invalidate a previously granted Approval.

Re-Approval

WAAS will write to you 1 year before the approval expires asking whether you would like to renew it. Please complete the
relevant section of the MA3 application form which will be included with the letter and return to WAAS (via e-mail or post).

Please note it is the responsibility of the Approval Holder to ensure the Approval remains valid. WAAS Ltd. accepts no liability for
1he delay in granting approval where this is caused by circumstances outside of the Scheme's control.

Th• Water Rogulations llcMSOf)' Scheme Lid. Regls1..-ed in England No, 06863930 Regislsrod olfice: 60 Lowick Closi>, Hazel G!OVV, SIOCkporl, SK7 5EO
Tel:+-44(0)333 207 9030 Fax:+44(0)H95 248 S40 Email:lnlo@,.,ras.co.uk wtbsne>W11v.wras.co.uk
MAR 325 Rev.OD 112
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-I R-00001 Rev. No.: 00 Sheet: 17 of 26

3.7 Guarantee/Warrantee

LUS-CP07C4C5C6-AJP-MAT -I R-00001 _00 Page 17 of 26


,~~__, ..' J "
·r ·r ·3 (_,_...6..3) ..s\ ·rb•

HEPWORTH
P.ME. (QATAR) WL.L.

WARRANTY CERTIFICATE Date: 24.03.2019

Kind Attention,

Customer : M/s LANDWORX


Project : AL MAHA CENTRE FOR CHILDREN AND YOUNG
ADULTS PROJECT

Our Reference;
Sample Warranty Certificate for Submittal

Product:
~ 25mm HOPE PE100 SDR11 PN16 Black Pipe
~ 32mm HOPE PE100 SDR11 PN16 Black Pipe
~ 40mm HOPE PElOO SOR11 PN16 Black Pipe
~ SOmm HOPE PE100 SDRll PN16 Black Pipe
~ 63mm HOPE PE100 SDR11 PN16 Black Pipe
~ 90mm HOPE PE100 SDR11 PN16 Black Pipe

Hepworth PME (Qatar) WLL hereby warrants that the Products manufactured and supplied to
the Buyer are manufactured to the appropriate specifications and for the use intended.
Hepworth PME (Qatar) WLL further warrants that the Products shall be free from manufacturing
or workmanship defects. The warranty shall extend for a period of 400 days from the date of
project completion (Testing, Commisioning and final acceptance from the consultant
/client/local authorities) to your project site. Hepworth PME (Qatar) WLL liability hereunder is
limited to the replacement cost of the defective products and does in no way cover labour or
installation charges or any other charges whatsoever. Hepworth PME (Qatar) WLL shall, in no
event, be held liable for indirect or consequential damages sustained by the Buyer.

Thanking you

Louai Al Nazer
Head of Quality Assurance

PO Box 50207
Mesaieed
I Mesaieed
Tel 4760588
Doha
Tel4506810
;....Jolll
£<>,,1;1.~
I
Qatar Fax 4760525 Fax 4506811 to·''" 1 u-Sli
www.hepworthpme.com.qa [email protected]

MAR 325 Rev.00 220


GEORG FISCHER
+GF+ PIPING SYSTEMS

Georg Fischer Piping Systems


(Switzerland) Ltd.,
Qatar Sales Office
Doha, glh_ February 2014
P.O. Bo)( 50207, Salwa Road.
Aziziah Filling Station,
Doha, Qatar.
Tel. +974 44719274
Mis. LANDWORX, www.piping.georgfischer.com
P. 0. Box 20185, Husein Yusuf
Doha, Qatar Mobile +974 33879185
[email protected]

Project Consultants: GULF ENGINEERING & INDUSTRIAL CONSULTANCY

Project: AL MAHA CENTRE FOR CHILDREN AND YOUNG ADULTS PROJECT.


Subject: Warranty on Georg Fischer manufactured Polyethylene PE-100 fittings

Georg Fischer Piping Systems Ltd. hereby confirms that the PE-100 fittings, produced and
supplied to the above project are manufactured to the appropriate specifications and for the use
intended. Further warrants that the Products shall be free from manufacturing defects. The
warranty shall extent for a period of 400 days from the date of receipt of materials to the above
project site.
Georg Fischer Piping Systems Ltd. states that our liability hereunder is limited to the replacement
cost of the defective products and does in no way cover labour or installation charges or any other
charges or damages what so ever to other services and applications surrounding the intended
products, and at the same time not be held liable for indirect or consequential damages sustained
by the Buyer.

Georg Fischer Piping Systems

Husein Yusuf
Technical Sales Manager
Georg Fischer - Qatar

GF VPVC fdlings & Hop<M>f1h j>ipes

MAR 325 Rev.OD 221


AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-IR-00001 Rev. No.: 00 Sheet: 18 of 26

3.8 Manufacturer data and instruction

LUS-CP07C4C5C6-AJ P-MAT-I R-00001_00 Page 18 of 26


Hepworth

POLYETHYLENE PIPES AND FITTINGS


FOR PRESSURISED WATER, GAS AND INDUSTRIAL APPLICATIONS

GEORG FISCHER
+GF+ PIPING SYSTEMS

MAR 325 Rev.00 15


CCP-ly§
~ 1
BUILDING
MATERIALS
Hepworth
Corys Building Materials is a holding company based in Dubai, Hepworth is the Middle East's premier manufacturer and
UAE, which manages three leading regional construction and supplier of high quality plastic piping systems for the
building materials businesses: Hepworth, Carys Build Centre and distribution and transmission of water, waste water.
Corys Geosynthetics.
Hepworth has been manufacturing and marketing pipes.
Corys Build Centre is a retail business that supplies pipes, fittings fittings and related products in the Middle East for over
and complementary construction products to contractors and 40 years. We manufacture PVC, HDPE, PPR and ABS
maintenance companies. Retail outlets can be found in Dubai, pipes and fittings in the UAE and Qatar and trade
Abu Dhabi, Sharjah, Al Ain, Doha, Manama and Muscat. through our subsidiary companies in Oman, Bahrain,
Saudi Arabia and export operations.
Corys Geosynthetics manufactures geomembranes in Dubai and
trades regionally in related products including geotextiles. We represent and manufacture pipes and fittings under
licence for Wavin and Georg Fischer and distribute other
Corys Building Materials is a subsidiary of Green Coast complementary products including equipments and
Enterprises, a Dubai-based private industrial and investment valves for AVK and other principals.
group owned by the Abdul Ghaffar Hussain family.

MAR 325 Rev.00


Hepworth +GF+ GEORG FISCHER
PIPING SYSTEMS
16 -
Quality Assurance

HEPWORTH PME ( LLC) is accredited to BS EN 9001 :2008 by the "-. an opti mum process organisation
British Standards Institution. We also maintain several BSI
Kitemark licences Strict quality control procedures are routinely "-. a certified quality management system in
conducted throughout the production process to ensure that our accordance with ISO 9001 :2008
products are fully compliant with the relevant specifications. We
~ established active continuous improvement
are audited on a regular basis by British Standards inspectorate
processes ( CIP ), which utilize the knowledge
including testing of samples in their UK facility to further ensure
and experience of our staff
that we are operating within the scope of our Kitemark licences.
Measuring and test instruments used in our Dubai laboratory are ~ a continuous evaluation and improvement
routinely verified and are traceable to International Standards. Our of our Personel Management System.
commitment to quality control thus serves to assure the client
that our products are of the highest quality and provide an
excellent service life.

- Hepworth +GF+
MAR 325 Rev.00
GEORG FISCHER
PIPING SYSTEMS
17
Polyethylene pipes, according to ISO 4427 and ISO 4437 are A wide range of both standard and bespoke fabricated fittings
extruded in our factories both in Dubai, UAE and Doha, Qatar with diameters of up to 1200mm are produced in our factories.
with diameters ranging from 20mm to 800mm SDR's (Standard Our design team can offer solutions for specific piping applica-
Dimensional Ratio l* of SDR 1t and SOR 17 are the most tions in situations where the use of a standard fitting is not
frequently requested specifications we can also produce SDR 9 practical or possible. We have a wealth of experience in designing
< 20 bar l, SOR 21 < 6 bar l and SDR 26 <5 bar), Black and bespoke fittings which can overcome many on-site application
blue colours are available for water applications whilst yellow is problems. Please contact our Technical Department for further
commonly used for gas. Pipes can also beproduced with colour information or assistance.
coded stripes to suit various applications. For pipes of other SDR's,
diameters and colours, please contact our Technical Department.
Pipes can be supplied as cut lengths or, for diameters up to
t 25mm, in coiled form.

The raw material used in the manufacture of pipes is of the


highest quality and it is important to note that we use only
100% virgin material in our production. Our suppliers of
polyethylene granules, issue a certificate of conformity with each
batch of material supplied. This is just one of the numerous
quality control checks covered by our BS EN ISO 9001 :2008
accreditation that feature in our production process.

'Standard D1mensionol Ratio "<SOR J is defined as Out;ide Diometer/WoU Thickness


Hepworth PME ( LLC )manufactures a full range of PESO and This Manual contains details of the following polyethylene pipes for
PE100 Polyethylene pipes at its factories in Dubai and Qatar that potable water supply and industrial uses;
meet the requirements of international standards

Application Medium Nominal size range Specifications

potable water 16mm - 800mm ISO 4427:2007


PESO Pipes for below ground use
gas ISO 4437:2007

PESO Pipes for above and below ground use, u.e.industrial uses and various 16mm-800mm ISO 4427:2007
other applications below ground, e.g. sewerage and pumping mains>

potable water 16mm-800mm ISO 4427:2007


PEl 00 Pipes for below ground use
gas ISO 4437:2007

PE100 Pipes for above and below ground use, Ci.e.industrial uses and various 16mm-800mm ISO 4427:2007
other applications below ground, e.g. sewerage and pumping mains)

Technical 8. Design Services

A comprehensive advice and consultancy service is available from


Hepworth PME < LLC l Our team of qualified water services and
sewerage engineers provide comprehensive advice on all Hepworth
P.M.E polyethylene and PVC-U water supply and sewerage systems.

~ ~
APPROVBJ KITEMARK

- Hepworth
MAR 325 Rev.OD
+GF+ GEORG FISCHER
PIPING SYSTEMS
19
Fabrication Division
PE pipes from manufacturers bearing the BSI Kitemark have been type tested
In our fabrication factory in Dubai, we are able to produce an extensive by the British Standards Institution and this is therefore an assurance that the
range of standard and bespoke butt-welded fitting to suit almost any product complies with the relevant standard ISO 4427 and EN 12201 are for
situation. Our strength is in our ability to design bespoke according to PE pipe intended to be used for the conveyance of water under pressure for
dient's requirements for situation where a standard fitting is simply not general purpose, as well as for the supply of drinking water. Fittings should
suitable. Using a wide range of Georg Fischer butt-fusion workshop also have internationally recognized approval.
machines our trained technicians can produce the necessary fitting in If PE pipes are to be used above ground they should be protected against UV
Dubai - fast. Each butt-welded joint is supplied with a certificate of light in accordance with recommended practice.
traceability confimning that the joint has been processed according to
specification. Traceability extends as far back as the batch number of Polyethylene Fusion Equipment
virgin material used in the production of the original pipe extrusion.
This ensures that the client can be confident about the integrity of the Machine Hire
joints and ability of the fitting to perform. In certain cases it not always viable for a clients to purchase Butt-fusion or
electro-fusion welding machines. HEPWORTH PME CLLO offers one of the
Manufacturing Standards region's rental PE welding machines, the expertise to maintain and calibrate
such and the ability to provide certified training to dient's Engineers either on
HEPWORTH PME <LLO operates a Quality Management System site or in the purpose of built training school in Dubai. Where necessary
Aocredited to BS EN ISO 9001 :2008 certified by the British Standards HEPWORTH PME <LLO can also supeivision to ensure that all jointing is
Institution. Polyethylene pipes for water supply are manufactured executed according to specification avoiding costly remedial work as a result of
according to ISO 4427 and are also covered by two British Standard poor welding techniques. Regular in-house training courses are offered for
Kitemarks Licences for all sizes and SDR's our production capability. For larger groups of engineers, each of whom will receive certification upon
gas applications we produce BS Kitemarked pipes according to ISO 4437 achieving required standard.
and if required, we can Supply according to the British Gas pie standard
PL2.

A Note to Specifiers

When specifying polyethylene Pipe for water supply it is important that


the correct standards are recommended to ensure that the pipe supplied
is suitable for the which it is intended. Reputable manufacturers of PE
pipes will be accredited to ISO 9001 :2008.

MAR 325 Rev.OD


Hepworth +GF+ GEORG FISCHER
PIPING SYSTEMS

20 -
Minimum Required Strength <MRS> PE100 Pipe S)l$lems
A high perfonnance PE100 polyethylene pipe material for use in
Polyethylene pipes and fittings materials are evaluated by their underground potable water and gas mains. The new material's
Minimum Required Strength <MRS>. higher pennissible design strength (PE100 - SMPa: PE80 - 5MPal,
together with its superior toughness, allows the design engineer to
When PESO pipes are hydrostatically tested at 20t:, ISO 1167 use PE100 pipes at substantially higher operating pressures than
specify a Minimum Required Strength at SO years of SMPa (SO PESO pipes with equivalent SOR rating.
daN/cm2) - MRSSO.
In addition to their superior qualities, PE100 also has greater
When PE100 pipes are hydrostatically tested at 20t:, ISO 1167 resistance to rapid crack propagation. PE100 pipes are supplied for
specifies a Minimum Required Strength at 50 years of 1OMPa working pressures up to 16 bar for underground potable water and
Cl 00 daN/cm2> - MRSl 00. 10 bar for gas mains.

Design Stre$$
The design stress for PESO pipes is 6.3MPa. The design stress for
PE 100 pipes is S MPa.

PESO Pipe S)l$tems


Introduced in the early 19SO's, to replace low density materials,
PESO polyethylene pipe is today used in the water industrY for
underground potable water supply, above ground water supply and
industrial uses.

Its many benefits indude:

Fully end-load bearing pipe system


Hyd1aulically smooth bore
Surge attenuating characteristics
Corrosion-free and resistant to most chemicals
Extremely tough and durable
Comparatively light in weight and easy to handle
Jointing by butt welding, electrofusion or mechanical joints
Inherently flexible in long lengths
Available in straight pipe lengths or in long, continuous lengths in
coils.
Standard Dimension Ratio CSDR>
In polyethylene pipes of 25mm nominal size and above, the pipe
c Material SDR17 SDR11 SDR9
pressures bar pressures bar pressures bar
wall thickness bears a constant ratio to the outside diameter, for a
given pressure rating. This is known as the Standard Dimension Water PESO s 12.5 16
Ratio CSDR>, which is calculated as follows: - 1.25 PE100 10 16 20

Nominal outside diameter


=SDR Gas PESO 5 8 10
Minimum wall thickness
E.g.The SOR of a 90mm, 1O bar rated PESO pipe is:- 2 PE100 6 10 12.5

-1Q... =SDR 11 All pressures based on 50 year design life at 20 "C Averoge Temperature
S.2
The SDR of a 90mm, 1O bar rated, PE100 pipe is:- Table 1-SDR and Maximum Rated Working Pressures
-1Q... = SDR 17.6
5.1
Pressure Rating
The pressure rating of polyetllylene pipes is generally referred to in
'bar', where 1 bar equals 10.2m head (approx>. Table 1 gives the
pressure rating and SOR of both PESO and PE100 pipes.

- Hepworth +GF+
MAR 325 Rev.DO
GEORG FISCHER
PIPING SYSTEMS

23
Typical Physical Properties
PE 100 - Physical Properties
Table 3 shows typical physical properties of both PESO and PE100
In addition to the quoted properties of PESO, PE100 pipe has enhanced
polyethylene raw materials.
toughness, higher pennissible design strength and improved resistance
to rapid crack propagation. PE100 pipe offers the water engineer
PESO - Physical Properties
substantial benefits in efficiency and economy.
The physical properties of pipe produced from these compounds
combine the flexibility and toughness of low density polyethylene
and the strength and rigidity of high density to give a highly
durable pipe eminently suited for the distribution of potable water
and gas under pressure.
PE proirerties !reference values>
PESO PE 100
Characteristics Value Value Units Test Standard
Densily 0.93 0.95 g/crn' EN ISO 1183-1
Yield stress at 23 •c 18 25 N/mm2 EN ISO 527-1
Tensile e-modulus at 23 •c 700 900 Mlmm1 EN !SO 527-1
Charpy notched impact strength «l 23 •c 110 83 l:.Jlm' EN ISO 17~-111 cA
Charpy notched impact strength at -40 •c 7 16 kJ/ mz EN ISO 179-1/leA
Ball indentalion hardness (132N> 37 MPa EN ISO 2039 .1
Crystallile melling poinl 131 130 'C DIN S1007
Thennal expansion ooefficient 0.15 ... 0.20 mm/mK DIN 53752
Heat conductivity at 23 ·c 0.43 0.38 W/mK F..N 12664
Waler absorption at 23 "C 0.01 - O.Q4 % EN 150 62
Colour 9005 RAL
Limiting oxygen index <LCD 17.4 % 1504589-1

Table 3-Physical Properties


• PESO - Melt Characteristics •pe 1oo - Melt Characteristics
Melt characteristics of commercially available PESO can vary. Pipes Melt characteristics of commercially available PE100 can vary. Pipes of
of different manufacture produced to the requirements of ISO different manufacture produced to the requirements of ISO 4427/4437
4427/4437, BS 6572 and kite marked or produced to WRC and WRC specification 4.32.13 and stamped accordingly can be fusion
specifications 4.32.03 and 4.32.09 and stamped accordingly can be jointed. In all other cases, please seek further advice from the Hepworth
fusion jointed. In all other cases, please seek further advice from the P.M.E Technical Services Department
Hepworth P.M.E Technical Services Department

MAR 325 Rev.DO


Hepworth +GF+ GEORG FISCHER
PIPING SYSTEMS
24 -
This section briefly describes the characteristics and properties of polyethylene as a guidance to the selection, design and use of the material
for installation. Reference is also made to relevant research and testing procedures.

General Properties
The properties of polyethylene have been described as:

.,.. Light and easy to handle ...._ Systems can be fully end-load bearing
,..., Conveniently flexible .,... Resists cracking
..._. Good fusibility -... Non corrodible
.,.. Tough ...._ Resistant to chemical attack by aqueous media
.... Strong ..... Low frictional resistance,

Strength
The "strength" of a pipeline may be considered as the ability to A safety factor is applied to the MRS to determine the Hydro-
withstand Choop) stress in the pipe material under internal pressure static Design Stress { HOS >. Recent European practice has been
over a prolonged period of time. The design stress considered the to specify the ISO minimum safetyfactor for PE of 1.2S for buried
is taken to be a life expectancy in excess of SO years. water applications 2.0 for buried gas applications and 1.6 for
aboue ground non gas applications. PE pipes are not
The stress/life characteristics are obtained by a standard universally recommended for above ground gas applications
accepted test procedure, regression curve prediction. The
regression curve shows the performance ability of the material Using these analyses, the predicted minimum failure stress of
under a specified load for a design life in excess of SO years. PESO material is 8.0 MPa - < based on the extrapolated SO year
97.5% LCL stress value at 20t: ). Figure 1 gives a regression
The strength of polyethylene is known to be time/ temperature curve <or series of data points ) for a material at 20'C.
dependent. This characteristic is used to assess the future available
strength of the pipe material by generating regression curves from The predicted minimum failure stress of PE 100 material is
varying stress/life to failure tests at higher temperatures than 10.0 MPa. With a design co-efficient of 1.2S, the design stress of
that normally experienced in distribution mains. These prolonged this material is 8.0.
tests, in excess of 10,000 hours, are accelerated for quality control
purposes by using elevated temperatures ( typically sot: l.

The method therefore identifies a Minimum Required Strength


(MRS) value derived from the SO year extrapolated 97.5%
Lower confidence limit ( LCL ) failure stress.

" "
. •100

' •8,0

,..
TIME tHOIJRS.1 Cog scMd
'" .
figure I-Regression Cwves for PESO Materiols at 20'C Figure 2-Regressiotl Curves for PEIOO Materials •I 2o•c

- Hepworth +GF+
MAR 325 Rev.DO
GEORG FISCHER
PIPING SYSTEMS

25
Hepworth

CONTENTS

1. Introduction

2. Specificat ions

3. Characteristics & Properties

4. Design Considerat ions

5. Handling & Storage

6. Jointing Method

7. Installation

8. Testing & Commissioning

9. Health & Safety

10. Other Approvals


11. Notes

Hepworth +GF+ GEORG FISCHER


PIPING SYSTEMS
26
Toughness may have useful fatigue characteristics where cyclic loadings are
In practice it is recognised that PE is a tough, resilient material present, !pumping mains, heavy traffic loading conditions, etc.l. Its
capable of withstanding the normal rigours of pipelaying conditions. absorption of groundmovement is advantageous in potentially
The many years of successful installation of polyethylene pipe in the unstable areas such as recently filled ground or mining areas.
gas and water industry adds confidence to this recognition.
However, the definition and description of this characteristic is The property of Hexibility and the ability to deform without
difficult and complex. There is no single test or measure one can permanent damage (creep/relaxation proper!Yl enables pipelines
apply, as it is a combination of many characteristics and properties. to be contoured to difficult road layouts or rapid changes of
direction. Polyethylene is subject to creep under stress but those
Abrasion stresses developed will relax with time. This characteristic requires
Although the material has high resistance to abrasion by suspended a different approach from the traditional pressure testing
partides being carried in the water, the external surface can be procedures.
scratched and gouged by sharp objects. Careful handling is
therefore required but provided the depth of the notch is no greater Crack Resistance
than 100/o of the wall thickness there is no significant Joss in the PE is tough with brittle type failure difficult to achieve even in
performance of the pipe. laboratory tests unless it is at very low temperature. Failure cracks
are usually of a ductile nature and, so far, tests indicate that rapid
Flexibility, Recovery and Creep crack propagation !RCPJ in water filled SOR 11 pipe is slow.
The inherent flexibility and recovery of PE enables the pipeline to Catastrophic failure, rapid crack propagation, appears unlikely
absorb impact loads, vibration and stress caused by soil or ground under normal distribution conditions. The difference between
movement. This also implies that PE pipes brittle and ductile failure is illustrated in Specification ISO 116 7.
Chemical Resistance and Stability
Group Generalised
Corrosion Resistance exarnoles Effect on PE
For all practical purposes PE is chemically inert within its nonnal Oxidizers Very strong adds Degradation
Cracking Detergents No degradation but under high
temperature range of use. It does not rot, rust, pit, corrode or lose Agents temperatures, accelerates cracking
wall thickness through chemical or electrical reaction with the under sb ess in brittle manner
Solvents Hydrocarbons, sudi No degradation but may be
surrounding soil. It does not nonnally support the growth of. nor is as petrols and oils absorbed into pipe wall causing
affected by algae, bacteria or fungi. reduction in hoop strength and
possible taste problems
Chemical Effects Table 1-Hannful Chemicals
PE has a good resistance to a wide range of chemicals. In the water Where pipelines are to be laid in environments where concentra-
supply context the main concern is the effect of certain chemicals tions of such chemicals may prevail (e.g. garage forecourts, within
existing in contaminated ground, some of which can have harmful certain processing works, etc.l the use of PE is NOT
effect upon the pipe material or may cause minor taste problems in recommended unless suitably protected. For further information,
extreme cases. In broad terms the most common harmful Hepworth P.M.E Technical Services Department should be
chemicals can be grouped into Oxidisers, Cracking Agents and consulted. The effect of specific chemicals on polyethylene pipe is
certain solvents as follows: considered in the ISO specification, ISO DP 10358.
Penneability
All grades of polyethylene can be shown to be permeable to certain gases and liquids under extreme conditions, the rate of
permeation being mainly dependent upon the media involved and the wall thickness of the pipe concerned.

Weatherability and Temperature Changes


problems in system design except where large diameter
Generally PE material has good weatherability properties and can
compression fittings are proposed.
readily withstand the variations of weather without degradation but
certain properties require consideration.
Temperature Range
From the time of manufacture to the time that a PE pipeline is
Coefficient of Expansion
commissioned, the pipe will normally be subject to a range of
PE has a coeffcient of linear expeansion of approximately between
temperatures and some exposure to UV light <sunfightl. Both
0.16-0.20mm per meter per 'L which is an order of magnitude
require attention during this period. Once installed underground,
greater than exists in metal pipelines and this characteristic must
the effects are usually insignificant as the viscoelastic properties of
be considered carefully in the design of the pipeline and during
the material make it quite adaptable to relaxing or adjusting with
installation. The coefficient of circumferential expansion is
time to stresses imposed by thermal changes due to weather and
approximately one half the linear value and seldom presents
soil temperature.

MAR 325 Rev.00


Hepworth +GF+ GEORG FISCHER
PIPING SYSTEMS
27 -
Temperature Stability Low Temperature
The exposure of PE to normal changes in temperature does not The mechanical properties of polyethylene allow the pipe to be
cause degradation of the material. During manufacture and fusion successfully operated in low temperature environments. Laboratory
jointing the material is sub1ected to temperatures in the range of based tests indicate that PE will retain its flexibility until tempera-
200'C - 240'C and to safeguard against degradation at these high tures as low as -60'C are reached. At the moderately cold tempera-
melt temperatures special stabilisers are used. PE pipe should not tures. the low thermal conductivity of PE will delay the freezing of
be used under pressure at constant temperatures in excess of 20'C the water contained within the pipe. In addition, should the water
without an appropriate reduction in its design pressure rating if the become frozen, the inherent flexibility of the material will accommo-
minimum design life of 50 years is to be achieved. date the expansion due to the formation of ice without leading to
rupture of the pipe wall.

UV Degradation
PE pipe is subject to a degree of degradation when exposed to PE is basically intended for use in buried conditions unless
excessive ultra violet light <sunlight). UV stabilisers (ant~oxidantsl protected from prolonged sunlight exposure. This is reflected in the
are used in the manufacture to counteract this effect and such current recommendation to provide protection when used in
material has withstood practical exposures for periods in excess of above-ground situations or when stored outside for periods greater
a year without apparent deleterious effects. This surface degrada- than one year.
tion has a particular impact when using fusion jointing techniques
and leads to recommendations for the peeling of the surface of the
material prior to jointing.

Thermal and Electrical Conduction


PE is a poor conductor of heat but is flammable, therefore a naked electrical equipment; similarly the contents of such pipes cannot be
Harne should not be used for the thawing of frozen pipework. At all thawed by electrical techniques using the pipe as the conductor.
times pipes should be protected against radiant heat that could Because of its high electrical resistivity, caution is required in the use
raise its surface temperature above 60'C. PE is also a poor of PE pipes where high levels of static electricity may be present.
conductor of electricity and no attempt should, therefore, be made
to use pipework constructed of the material as a means of earthing

Hydraulic Properties
The smooth bore of PE pipes enables them to be treated as for the purpose of calculation of flow rates in NEW pipelines the
"hydraulically smooth" when used for the conveyance of potable Colebrook-White formula may be used in which the value of the
water. The smooth surface discourages the formation of scale in hydraulic roughness factor Ks is 0.003mm for dean water.
hard water areas but particular waters may, at certain times, give
rise to slime and silt deposits associated mainly at joints or fittings
which may increase frictional losses.

- Hepworth
MAR 325 Rev.00
+GF+ GEORG FISCHER
PIPING SYSTEMS

28
Although principally developed for conveying water and gas,
polyethylene pipes have many other applications, some of which
are:-
C1lSewage pumping mains, where the materials resilience provides
excellent resistance to the surge pressures generated by continuous
pump starting and stopping.
<2l Slurry conveyance in quarries, mines, etc. In this application, PE
pipes provide superb resistance to abrasion. When comparing PE
pipes with conventionalpipes used for slurry applications, consider-
able increase in lifetimes can be achieved.
(3) Fire mains FM Approved piping systems offer safe, secure and
correction free solutions for underground fire fighting mains.
(4) Chilled Water
(5) Demineralised Water
(6) Industrial/Chemical applications
(7J Submarine pipelines
(8) Rehabilitation of existing pipelines by relining
(9) Compressed Air Lines
(1 Ol Vaccum Sewage
(I 1l Telecom Applications
0 2l Ship Building
(13) Irrigation
(14l Sea Water Intakes
(15) Aqua and Marine Parks
(16) Potable Water
C17l Cable Duct

MAR 325 Rev.DO


HepwoTth +GF+ GEORG FISCHER
PIPING SYSTEMS
29
-
When considering the design of polyethylene pipe systems, the appropriate international specifications should be taken into consideration. For
example extracts from the WRc Manual are published here with acknowledgment to the Foundation for Water Research.

Review of Current Position The properties of PE make such pipelines particularly suitable for
PE80 and PE 100 pressure gas and water mains are inert flexible, areas subject to ground movement due to seismic forces, mining
lightweight and have the required structural strength without being subsidence, compaction of filled sites or the disturbance caused by
brittle. They are suitable for use where ground movement is expected, the activities of other utilities in the vicinity.
where corrosive soils are present and where long ducts and flexibility in
bending are required. They appear to withstand surge pressures better Where PE 1s to be used in environments with temperatures greater
than PVC-U pipe and to be even more resistant to freezing because of than 20'C the allowable operating pressures should be reduced in
the improved thermal insulation properties. accordance with !he manufacturer's recommendations.

Fusion welded PE piping systems resist axial stresses arising from Corrosive ground (e.g. ground with low pH or high sulphate
thermal or pressurisation effects, except at the transition points to non characteristics) has little or no effect upon PE but all metal fittings,
end load bearing pipe systems. Thrust bloks and anchorages need only anclllaiy equipment, bolts, etc., should be carefully protected in the
to be considered in thise cases. normal way.

Both PESO and PEl 00 pipes allow the use of many modem no dig Contaminated ground, however, must be considered carefully. PE is
techniques. resistant to many chemicals, but is vulnerable to petroleum products
and certain solvents; where concentrations of such contaminants exist
Environment PE should NOT be used unless suitably protected. Where any doubt
PE pipes are normally joined using fusion techniques. Butt fusion exists soil sampling should be undertaken and specialists advice
jointing is usually carried out above ground and after cooling; long sought.
lengths of pipe are snaked into the trench.
Where the natural ground water table is high, or the construction
Fusion jointing using the electrofusion jointing technique may be trench is liable to flooding, special consideration should be given to
carried out at the trench bottom, but care must be taken to keep !he possible flotation of the pipe. This particularly applies to the large
jointing surfaces dean and dry. diameters where special anchoring or weighting may be necessary
prior to the backfill being installed.
The sub surface material to be excavated should be assessed for its
suitability as selected backfill material. i.e., free from large sharp stones,
heavy clay, etc. If the material is unsuitable for bedding and surround to
the pipe !hen imported material should be utilised and the surplus spoil
removed from site.

Operating Conditions The DYNAMIC loads normally considered during operation are the:
Both the static and dynamic loads to which the pipe system is likely to
be subjected should be considered with care. However variations or internal cydic loading e.g., surge associated with pumping
pressure due to demand seldom warrant special design consideration regimes or the rapid dosure of valves;
with regard to !he pipe material. Pipe systems designed with the
relevant safety factor take account of occasional deviations from the external cydic loadings due to traffic conditions.
maximum rated pressure. These occas10nal pressure excursions within
conditions reflected by the safety factor are therefore acceptable. Further
advice should be sought from Hepworth P.M.E Technical Services.

- Hepworth
MAR 325 Rev.00
+GF+ GEORG FISCHER
PIPING SYSTEMS
30
Design for Surge and Fatigue External Dynamic Loading
When considering applications where surge transient pressures may For external dynamic loading conditions the use of PE pressure mains
occur, polyethylene pipes exhibit significant advantages. The relatively under MAJOR CARRIAGEWAYS is dependent on the type of trench
low material modulus for polyethylene means that, for a given change bedding conditions.
in fluid velocity, the surge transient pressure induced will be
approximately one third of that induced in ductile iron pipes. In Experience has shown that if the PESO and PE100 pipes are laid with
addition, quality pipe grade polyethylene resins are almost immune to the correct installation techniques, PE pressure mains can be laid under
fatigue damage for typical fatigue loadings in water and effluent major roads.
pipelines, hence no de-rating is required for the pipe. However, this is
a complex area and a full analysis should always be undertaken. A comprehensive testing programme has been undertaken which
commenced prior to the publication of the original PESO manual on
Surge Design the potential risk of the failure of butt welded PESO pipes by rapid
A critical factor when assessing surge transient pressures generated in crack propagation.
Polyethylene pipes, is the RATE at which the pressure rises in the
pipe subsequent to a surge transient pressure being generated by for The result of these tests showed that it was not possible to generate a
instance, the rapid operation of a pump or v.ilve. Detailed study of the fast fracture in PESO completely full of water even under arduous
UK water network over a period of time has shown that this 'Pressure conditions of low temperature and high pressure.
Rise Rate' has rarely exceeded 8 bar/second and in 'normal' operating
conditions, rarely reaches this figure. Full scale fast fracture tests were also earned out on PE 100 material.
The tests were carried out on 500mm pipe tested at 1.5 times the
Fatigue maximum rated pressure of the pipes <16 bar and 10 bar for SDR11
There is no necessity to de-rate Polyethylene pipeswhere fatigue and SDR 17.6 respectively>. Nitrogen las air substitute) was used as
conditions are encountered, providingthe pipes meet the stress crack pressuring medium to simulate the worst case situation. It was not
resistance requirements of ISO 1167. possible to generate fast fracture in fully gas filled PE100 pipes.

Resistance to Vacuum Therefore the significant advantage of PE100 pipe is that it can be
Polyethylene pipes can safely withstand negative pressure, for instance used at its respective full rated pressure without the risk of failure by
when subjected to vacuum subsequent to sudden power failure to the fast fracture.
pumps in a pumping main.

When large diameter Polyethylene pipelines are to be laid in ground


conditions which raise doubts regarding the suitability of the
backfill/native soil stiffness, the designer should cany out a detailed
analysis of both ground conditions as well as projected soil loadings.

The complete analysis of pressure transients, particularly in complex


water disttibution mains, requires specialist advrce, knowledge and
exµerience. For computer analysis of the likely pressure transients
many specialist consultants are available. By utilising these sources of
guidance and expertise, the.very good response of polyethylene pipes
to surge and fatigue loading can be used by water engineers to the
advantage of their company.

MAR 325 Rev.00


Hepworth +GF+ GEORG FISCHER
PIPING SYSTEMS
31 -
Hydraulic Flow - Pipes Where
The hydraulically smooth bore of a PE pipe gives excellent flow V = velocity in metres per second
characteristics which are usually retained through its operational life. The g = gravitational acceleration (a value of 9 .80 7 ms..2 may be assumed)
hydraulic frictional coefficients normally used in the design of continu- i = hydraulic gradient
ous straight PE pipes working under pressure are: v =kinematic viscosity (a value of /sm101.14126-x may be assumed
for water at 1S'O
Colebrook-White Ks - 0.003 mm Ks = linear measure of roughness in mm = 0.003
D = mean internal diameter of pipe in metres.
~ Hazen Williams C = 1SO
For ease of reference. a typical Design Flow Chart based upon these
The metric Colebrook-White formula for the velocity of water in a coefficients is reproduced as
smooth bore pipe under laminar conditions takes the form:
Figure 1 for Pipes up to 1OOOmm
V = 212gDi. Log. { ~ 2.15v }
3.70 oJ2gDi

..... -~
~ 1t 1.' .-...ttt•· ~ I ·:. .. ! " '~ ,; .t n...tr"'c''
. .
11

- .
'H
::;

~
...,,u
,.r;:r
.~
I• "-.
.. il.. !I Utt·- w....
~ , ,,
"
~ ~j
...-·
"I'
- :"f ~
.,-... if~
·~q
m
... 111
. .....-. I
l"I

re.
.
;
H: :ii!

,. '...!. ·,
r cl

... .
'" ::'
·-
r:'l9
; ~~ 1) 1. • [l l1 rn~ ••
. ~;::. . r.· ::-: •I ..
·m
r
·-
fl.
.
-~~ --
n;::q ·I
I
i~ :i -
M

---.. ! :
i-.

~ ....
J~
~


...
. ~ .
.. u

"'111i'·I I
'
·- :<.

r l'l
"" ~

- ..
•"'' ...
I
...
.t;
~~
• I

·~ ~H"<· 'ffi
II

,
I
1'1..1 ~~
... - =·••
J

18 I).~ 112 11, z , " 2'T


~I. Iii· " - J !I

Example: PE pipe PN 6 225 x 12.Bmm (Dia. = 200mmJ. discharge 251/s. Friction diagram for PE and PVC pipes calculated according to
Fallow the Dia. line= 200mm until this line cuts the discharge line= 25 /Is. Colebrook, For diameters up to 200mm k = 0.01mm, and for
This gives the value far friction= 2.8 per thousand and the velodty = 0.75 diameters exceeding this k = 0.05mm. Water temperature + 10°C
mis
Flow Chart -Pipes up to 1OOOrnm

Hepworth +GF+ GEORG FISCHER


PIPING SYSTEMS
MAR 325 Rev.OD 32
Frictional Loss - Values and Fittings
The frictional losses occasioned by flow through valves and fillings are
approximately proportional to the square of the liquid velocity.

K.V2
H ,,.
2g Tolli 1111t"!_l (•rnron1r>t
•1111 I ' ,, O< ,.,
' -1;,"l'}I'•' 1111 .1 1-l ii'wHt ll •~'
,, 'f-J"
l·1Jtll J •• u ',tt 1111> J !r!J
H loss of head
V liquid velocity 1 Ferrule connection 20 0.1 0.9 20
g acceleration due to gravity 25 0.1 0.7 1.5
K coefficient dependent on type of filling. 32 0.2 0.4
63 0.5 1.5
Table 1 gives commonly used values for K 2 Stop valves \!, 0.6 3.7 9.5
'lo\ 0.2 1.2 1.9
1 0.4 0.7
, ....... 1.p· I ... , , . 1)0
2
0.1 0.2
0.1
0.9
0.4
2 .2
0.8
3 Boundary boxes 20 o.8· 4.5" 10.0·
90 Elbow K= 1.00
45Elbow (with meter) ZS O.T 3.2" 8.1'
K= 0.4
Boundary boxes 25 0.5" 1.!l"' 3.4"
22 'h Elbow K·• 0.2
{without meter)
90 Bend K= 0.2
4 Double check valves 20 1.8 4.0 6.0
45 Bend K•- 0 1 2.0 2.7
25 1.2
22 'h Bend K ~ o.os
32 1.3 1.8
90 Tee flow in line K= 0.35 50 2.5
90 tee flow into branch K= 1.20 63 0.4 0.9
Gate vafve: open K= 0.12 5 Adaptors 20 0.4 0.6
v. Oosed K ~ t.0 ZS 0.1 0.1

'"'I• Clo5"d
aosed K= 6.0 32 0.1
K= 24.0 8 Elbows 20 0.3 1.3 2.4
Butterllyvalve: open K= 0.3 25 0.1 0.2 0.4
32 0.1 0.2
50 0.2
Table I-Commonly used values for K 63 0.1
Perhaps a more convenient way of allowing for the frictional resistance 7 Tees (on Branch) 20 0.2 1.0
25 0.3 0.6
of valves, fittings, obstruction, etc., is to consider an equivalent straight 32 0.1 0.2
50 0.3
length of pipe which would create the sarne frictional resistance. 0.2
"'
• These table numbers refer to tables 1 • 7 in report FR 0255
· These flaures refe r lo resutts aoneraled 1rom various sources
Actual headless characteristics for a range of service pipe sizes and
appropriate fillings were researched by WRc during 1991 - 1992 to Table 2-Average Headless in fittings and Components
detennine overall headless for PESO pipes in specific service pipe
These design procedures are readily applied to individual mains or
installations.
simple layouts. The charts are also invaluable for establishing an initial
selection for pipelines forming an integral part of more complex
For a typical service pipe length of 2Sm, the pipew01i< contributes up to
layouts. As pipe networks become more extensive and hence more
3 50/o of the total head loss. The average results are given here as Table
2 for quick and easy reference. hydraulically complex, use must be made of computer-aided design
for which a variety of programs are available. The selection of program
The effect of the frictional resistance created by the internal beads in will depend upon both the complexity and format of output required.
butt welded joints is hardly significant in normal distribution installations
but in the smaller diameters or where the joints are frequent (say every The jointing method
2 metres for some continuous lengths) an increase in the frictional The trench width (standard, or narrow>
resistance of about 2% should be allowed.
PE pipe is available either in coils or straight lengths depending upon
Pipeline Selection pipe size.
The selection of both material and size of a paJticular pipeline will be
influenced by any particular design policy or "standards" employed by Straight pipes are usually produced in 12m lengths but other lengths
the developing body. Within the normal distribution range <up to are available by upon request
630mml the use of ''standard" sizes and designs may well prove cost
effective in tenns of simplication of design, operation, repair or renewal, Coils are available in sizes up to 125mm and usually up to 1OOm
stores levels, etc. length.

MAR 325 Rev.DO


Hepworth +GF+ GEORG FISCHER
PIPING SYSTEMS
33 -
Narrow trenching has the considerable advantages of reduced Wherever practical. a looped or ring main should be formed.
reinstatement costs and less spoil to handle but not all subsoils are
conducive to such a technique and proper laying, bedding and Where dead legs cannot be avoided they should have a
compaction is not always possible at the required depths of cover. washout facility and air bleed facility !preferably a hydrant>
Trenchless techniques such as micro-tunneling and impact moling can adjacent to the last service connection.
be used particularly well with PE systems, as alternatives to conventional
trenching techniques. The Oexibility of PE allows the accurate alignment Mains should follow and be located on the side of the
of the pipeline to awkwardly contoured kerb lines on housing sites. This public highway serving the most properties to minimise
is particularly valuable in cul de sacs where turning circles and hammer the length of service pipes.
heads are prevalent In such layouts it can prove quite economic to
provide a looped service main and consideration may also be given to The possibility of incorporating leakage detection or control
installing the service connections prior to the pressure test. Apart from devices should be considered, thus benefiting a planned
the avoidance of high stress environments and unsuitable ground zonal approach to leakage control.
situation as mentioned previously, the selection of layouts and routes for
Consideration should be given to possible future extension
PE pipelines needs no other special consideration than that which would
of the site and of fire service requirements.
be given to other pipeline materials··

The provision and siting of ancillary equipment for PE pipelines is also


similar to other pipeline layout except for one aspect; The ease with
which PE can accommodate gradual changes of direction in the
vertical plane requires special attention to the provision of adequate
and properly sited air valves at high points.

Figure 2-lYplcal Open Trench

Bends and Cold Bending


Nrnn11al fv"11Pi.""1l.JJn Cole! Bi:nding R<tdu 111 Meters
The bending of PESO and PE100 is permissible and the properties of
dr~me1e1 at 2oa at oa
fusion jointed systems enable changes of direction without recourse to
the provision of special bends. However, pipes should not normally be 20 0.5 1.0
COLD bent to a radius less than 25 times the outside diameter of the 25 0.625 1.25
pipe at 20'C !Ref. Table 3). In special circumstances and in the smaller 32 0.8 1.6
service diameters this requirement may be relaxed to 15 x OD for 50 1.25 2.5
SDR 11 pipe, provided no joints or tappings occur on the bend and care
63 1.58 3.15
is taken not to kink the pipe.
90 2.25 4.5
125 3.125 6.25
At O'C pipes should not normally be cold bent to radii Jess than 50 x
the outside diameter of the pipe <Ref. Table 31. 180 45 9.0
250 6.25 12.5
A full range of moulded or mitred elbows are available. In addition 315 7.88 15.75
preformed pipe bends and configurations are available upon request Table 3-Recommended Minimum Cold Bending Radii

- Hepworth
MAR 325 Rev.00
+GF+ GEORG FISCHER
PIPING SYSTEMS
34
Anchorage and Thrust Blocks The PE pipe itself may be partially or completely surrounded by
One of the fundamental features of fully integrated fusion welded PE concrete but should be protected by a heavy duty polyethylene
pipe systems is that they are end load resistant and anchorage is not membrane to a minimum thickness of 3mm. The membrane should
normally required at the junctions or bends. extend outside of the concrete to avoid possible damage during
pouring or compaction and minimise local stresses.
However, an exception to this is at transition points to non end load
bearing pipe systems where thrust anchoring will be required. Where concrete surround to the pipe barrel is to be provided as
anchorage, the forces may be transmitted to the concrete by the
The designer should consider all aspects of the system, induding the introduction of a stub Oange or similar fitting to form a puddle Oange.
imbalanced loads imposed by testing procedures, unusual configura-
tions, large temperature variations, etc., and where excessive stress on
the pipe system is envisaged, additional anchorage should beconsid-
ered.

Concrete Support Consideration should be given to the provision of weight and any excessive turning movements which may be created
concrete support to all heavy fittings or ancillary equipment installed on under operating conditions (hydrants, air valves, etc.l.
PE mains. The support design should take into account both the dead

Pipe Entry into Structures Wherever the PE pipework meets or passes


through rigid structures careful consideration should be given to at least:

..._. the need to affect a watertight joint at the interface;

the extent to which the structure itself is required to with Figure3


stand forces transmitted from the pipe;

where there is RIGID connection between pipe and structure Wall_.


the adaption of standard fittings or the introduction
of special fittings is necessary. Such fittings influence the
degree to which compressive, tensile, bending and shear
forces are generated;

..... where DIFFERENTIAL settlement may occur, the pipe


flexibility can normally be relied upon to withstand the
bending and shear stresses set up.

..... Where pipe is to be connected by a flange to a large rigid


structure, localised movement and bending can be preve-
nted by a reinforced support pad as shown in Figure 4. Reinforced Support Pad
This pad should extend one pipe diameter or a minimum of
300mm from the flanged joint The strapping should be
provided with a compressible protection to the pipe.
Figure 3 and Figure 4 show typicaldetails of

Pipe passing through a structure


Rigid connection to a structure

MAR 325 Rev.00


Hepworth +GF+ GEORG FISCHER
PIPING SYSTEMS
35 -
Effect on Temperature Variation Effect of Temperature Variation on Mechanical Properties
The tensile strength of thennoplastics materials istemperature
Expansion and Contraction dependent. As a consequence the recommended maximum
The coefficient of linear expansion for PE pipe is between 0.16mm sustained operating pressures of PE pipes must be reduced for
-0.20mm per degree celcius operating temperatures over 20'C if a SO-year minimum life is to be
maintained.
Due allowance must be made for movement created by temperature
variation when designing pipe systems. The position of rigid fixings or Where operating Figure S plots pressure reduction factors against
anchor points must be carefully considered, particularly in above ground temperature for polyethylene pipe. temperatures are 1n excess of 20'C
installations. By utilising the inherent flexibility of the pipe and by the designer must ensure that adequate pipe support is provided in
judicious siting of supports, anchors, etc., expansion and contraction can above ground situations and that the medium being conveyed will
be conveniently accommodated at changes in direction. For further not degrade or attack the pipe material.
details contact Hepworth P.M.E Technical Department.
polyethylene can be use for pressure applications in the temperative
Table 4 gives expansion/contraction in mm for a range of temperature range of -SO"C to +60"C Subject to pressure de-rating due to
variations and pipe lengths. The effect of expansion/contraction requires operating temperatures.
particular attention if the pipe system indudes one or more push fit, non
end load bearing joint. In these circumstances pipes installed at relatively
high ambient temperatures may contract to such an extent when
operating at service temperatures that movement in the joint may result
in leakage. Pipe bracket spacing for PE for liquids with a density of 1 g/cm

Movement caused by thermal variation in pipe systems jointed by one of Pipe brac.kel intervals L for pipes SOR l 1 in mm .it pipe
wall 1emperaturc:-
the fusion welding techniques (full end load bearing joints) will generate
Size mm d20"C 30'C 40'C 50'C 60"C
tensile or compression stresses within the pipe material. In buried
16 500 450 450 400 350
pipelines which have been allowed to stabilise to trench bottom ambient 20 57, 550 500 450 400
25 650 600 550 S50 500
temperatures the elastic properties of the material will normally 32 750 650 650 550
750
adequately accommodate these forces which are rarely of sufficient 40 900 850 750 750 650
magnitude to adversely affect the performance of the system. A more so IOSO 1000 900 850 750
63 1200 1150 1050 1000 900
critical consequence of this movement could be its effect at pipe 7S 1350 1300 1200 1100 1000
90 ISOO 1450 1350 1250 1150
supports, or branch connections to plant/equipment and other 110 1650 1600 1500 1450 1300
pipelines. Such points should be analysed for shear and bending 125 1750 1700 1600 1550 1400
140 1900 1850 17SO 1650 1SOO
stresses. 160 20SO 1950 1850 1750 1600
180 2150 2050 1950 1850 1750
200 2300 2200 2100 2000 1900
22S 2450 2350 22SO 21SO 2050
250 2600 2500 2400 2300 2100
length in Temperature Variation In •c 280 2750 2650 2550 2400 2200
metres 5 10 15 20 30 40 315 2900 2800 2700 2550 2350
1 0.8 1.6 2A 3.2 4.8 6.4 )55 3100 3000 2900 2750 2SSO
400 )300 3150 3050 2900 2700
2 1.6 3.2 4.8 6.4 9.6 12.8
4 3.2 6.4 9.6 12.8 19.2 25.6 450 3450 3330 3200 3050 2850
4.8 9.6 14.4 19.2 500 3700 3SOO 3400 3250 3030
6 28.8 38.4
8 6.4 12.8 19.2 25.6 38.4 51.2
10 B 16 24 32 48 64
For other SOR. ratings multiply the values given in lhe table wilh the followlng factors~~
12 96 19.2 28.8 38.4 57.6 76.8
20 16 32 48 64 96 128 SOR 17 arnl SOR 17.6 with 0.91
50 40 80 120 160 240 320 SOR 7.4 with 1.07
100 80 160 240 320 480 640
The pipe bracket spacing given in lhe table may be increased by 30 % in the case of vertical
Table 4 pipe runs, i.e. muftip!y the values given by 1.3.
Abovedalc lmedoocotffidenl trl.expansionD.16mm/metrr/°C
AUdimeuionsinmm Pipe bracket spacing for PE for huids of a density other than 1 g/cm3
If the liqulcl to be uanspol1ed has a density not equal 1 g/arP. lhen !he bracket spacing in the
!able abo\le should be mtJltipli<d by the fader of !he following !able:-

I De[DftY of the ftufd lntlfanJ Factor for giiue bracket •~


For pipe systems above or below ground and intended to carry water I 1.25 0.96
I 1.50 0.92
it is advisable to make final connections during the coolest time of the I <0.01 1.30forSOR 11
1.21 lor SOR 7.4
day.

- Hepworth
MAR 325 Rev.00
+GF+ GEORG FISCHER
PIPING SYSTEMS

36
The importance of good handling and storage of polyethylene pipes
and fittings applies equally to all forms of installation. The procedures
and recommendations should be followed at all times giving particular
attention to handling and storage at site.

General Principles The recommendations for handling and storage are


Particular attention should be given to the effective securing and
the same for both PESO and PE100 pipes although, due to the
storage under such conditions. Extra care should also be taken when
increased stiffness, PE 100 pipes may require even greater care in
handling large diameter prefabricated fittings during very cold weather.
handling pipe coils than PESO pipes of similar wall thickness. Polyethyl-
As far as practicable the protective packaging <pallets, strapping, bags
ene is a tough resilient material which isrelatively light and easy to
etc.) should be kept intact until the material is required fur use. The
handle although it is prone to damage through scoring by sharp
temporary capping or plugging of pipe ends is recommended. Pipes
objects. Therefore careful handling is always required and the dragging
and fittings likely to be stored outside for periods longer than 12
of straight pipe and coils should be avoided whenever possible. The
months, should be covered by tarpaulin or black polythene sheeting to
maximum allowable depth of scoring of the external surface of the
prevent ultra violet degradation from sunlight. Electrofusion fittings
pipe is I 0% of the wall thickness. Pipes and fittings showing obvious
should be stored under cover and in their protective packaging. For
defects or excessive scoring should be withdrawn and clearly identified
hygiene purposes, the pipe ends must be protected from the ingress
as unsuitable. The general properties of polyethylene are unaffected by
of dirt/water etc. This protection should be carefully disposed of
low ambient temperatures but having very smooth surfaces, the pipes
following use.
and fittings become slippery in wet or frosty weather.

Transport and Delivery


For transporting bulk loads the vehicles should be provided with a
Strapped
clean flat bed, free from nails or other projections which may cause Timber Frames
damage. If high sided lorries are used, special care must be taken to ~-;,ii",,../ . . . .~__
prevent slippage or excessive bowing of the pipes and extra protection __......... -
given at all sharp edges. Care should be taken to avoid positioning
pipes and fittings near or adjacent to exhaust systems or other heat
sources and to avoid possible contamination from materials such as
diesel oil. Metal chains or slings should not be brought into direct
contact with the material. Webbed slings of polypropylene or nylon are
recommended. Straight pipes should be fully supported and bound
together. Pipes must not rest on the integral socket if one is incorpo- Figure 1 'fypical Framed pack of PE Pipes
rated. When transporting 'pupped' fittings, these should not be loaded
in a way that could distort the pup end. Both vertical and horizontal
deliveries of coiled pipes are permissible, although in the case of
horizontal transportation special arrangements may be required. Off
Loading - Frame Packed Pipes When lifting by crane, non metallic
wide band slings or ropes should be used, and for pipe lengths greater
than 6m, load spreading beams of a length at least equivalent to one
quarter of the length of the pipe or bundlepack should be employed.

Figure 2 Lifting Framed packs by Crane

MAR 325 Rev.00


Hepworth +GF+ GEORG FISCHER
PIPING SYSTEMS
37 -
Chains or end hooks should not be used. Care should be taken to avoid Bundlepacks greater than 6m long should be handled either by a side
damage to pipes and pipe ends during lifting, Some bending should be loader with a minimum of four supporting forks, or by a crane using
allowed for in the middle of the lift when loading and unloading pipe a spreader beam and suitable slings. Individual pipes may be handled
and because of this lifting poirits should always be well spread and in the same way. Off-loading on site may be made easier by using
evenly spaced <see Figure 2). Standard bundlepacks, 6m long. may be skid timbers and rope slings, <Figure 3).
handled by fork lift trucks and due allowance made for the flexible
nature of the pipes in the positioning of the forks and the raising of the
load.

Figure 3- Off Loading using Skid Timbers"


Pipes must never be thrown from delivery vehicles or slid from the tailboard of a moving flat-bed wagon

Coiled Pipes
SAFETY CONSIDERATIONS
It is now well understood that coiled pipe contains a considerable
amount of stored energy which has the potential to cause injury if
handled in an incorrect way. To ensure a safe working environment
during the installation of large diameter pipe in coil form it is intended
that coils should only be dispensed from an approved coil dispenser.
Always ensure that the tail ends of coils are released in a restrained and
controlled manner and never cut all the retaining straps at one time or in
one operation. The work area should be restricted to essential personnel .... ··
i ,. "'11' ., 'u' .. '1t ... if - i
, .. , , .. •
... - ••,j..... 11.---.• i·-- u •"' ·,
only who should always wear hard hat, gloves, safety shoes and eye ·.';'..· ·--·· ·- ~ -· ··-=·· ·--··
protection when carrying-out this type of operation. After completion of i ·,j '1i "1i JI ·,
the dispensing operation it is important to ensure that the free tail-end of 6 (j(j(j:·~::·()
any part-used coil is 'secured' before transporting it from the site. BANDS OR TAPE AT POSITIONS
Reinforced adhesive tape at least 2" wide is used for banding. Complete B, D AND F l\EtfASE INNER
COUTERJ WRAP
coils are secured by outer and intermediate bands and individual layers
are also independently secured as shown in Figure 4. These should not
BANDS OR TAPE AT
POSITIONS B, D AND F
RELEASE COMPLETE INNER I
.. -. II
,·'"•,
II
....... - .. -..
h II f
WRAP :.,::~ ::.;: : ,;:::'.)! :.
be removed until the pipe is required for
actual use and the method of release
. ... ..... •, .
,: l
~ •' '• ,. ,• . ....
detailed in Figure S MUST ALWAYS
befollowed. 78Ek<:>:;;
BANDS OR TAPE AT POSmONS
E. C AND REINFORCID TAPE AT
There should be facilities to restrain A RELEASE REMAINING WRAP
BANDS OR TAPE AT
securely each coil individually throughout POSITIONS I\ C AND E
RELEASE COMPLETE INNER
individually transit and the unloadingpro- WRAP
cess.•

N.8. BEFOllE STARTING


Figure 4- Banding of individual Layen of Coils Pl.EA5E TAKE NOTE OF THf
SAFETY CONSIOEAATIONS
BANDS OR TAPE AT
POsrTIONS B, DANO F
RELEASE INNER !OUTER> WRAP

Figure 5-Releasing lnstruCllon fur c:oiled Pipe Retaining Straps

- Hepworth
MAR 325 Rev.00
+GF+ GEORG FISCHER
PIPING SYSTEMS

38
f"lttings Hooks should not be used to lift fittings, which are supplied Strapped
in cardboard boxes or polythene bags. Timber Frames

Storage at Depot
All materials should be carefully inspected at the time of delivery and
any defective material set aside before accepting the delivery into
stores. Any such defects should be notified to the supply source
immediately.

Pipes and fittings should be used in the order of delivery to ensure the
correct rotation of stock. Polyethylene pipes are date stamped at the Ordinary Ground
time of manufacture and checks should be made to ensure the stock
is being rotated on an "oldest out first" basis. Figure 6-Storage of Framed Packs

Blue polyethylene pipe should preferably be stored under cover and


protected from direct sunlight until required for use. Where storage
facilities necessitate the material to be exposed externally for more
than twelve months, suitable opaque protective sheeting should be
used.

All pipe stacks should be made on sufficiently firm, flat ground to


support the weight of the pipes and any necessary lifting equipment.
Stacking heights should be kept to a minimum and adequate space
allocated for lifting machinery to manoeuvre without accidental
damage occurring.
Horizontal Storage: Each coil must be protected
from surface contact by usirtg wooden battens or pallets
For safety and convenience of handling the stacking height for
manufacturers bundles should not be more than 1 metre. To prevent Figure 7-Storage of Colts

possible deformation of the pipes, bundles must be stored timber to


timber as shown in Figure 6. Polyethylene fittings should be stored under cover, preferably on
racking and the manufacturer's protective wrapping or cartons kept
For similar reasons, pipe coils should be stored Hat, see Fig. 7, and the intact for as long as possible.
number of coils per stack should be limiled to;
At all times pipes and fittings should be stored away from exhaust
...._ 7 coils for 20mm diameter pipe outlets and all other high temperature sources. Care should also be
...._ 6 coils for 25mm diameter pipe taken to avoid contact with lubricating or hydraulic oils, gasolines,
...._ 5 coils for 32mm diameter pipe solvents and other aggressive chemicals.
...._ 4 coils for SOmm diameter pipe
...._ 3 coils for 63mm diameter pipe All special tools and equipment associated with the jointing of PE pipes
...._ 2 coils for 90mm diameter pipe and fittings should be stored separately and securely until they are
...._ 1 coil for 11 Omm diameter pipe required for use. The heating faces of fusion tools should be kept 1n a
...._ 1 coil for 125mm diameter pipe position where the surfaces are protected from scratching or other
-.... 1 coil for 180mm diameter pipe damage. Tools incorporating cutting edges should likewise be protected
from damage which could cause poor joint preparation.
Where individual pipe lengths are stacked in pyramidal fashion,
deformation may occur in the lower layers, particularly in warm weather.
Such stacks should therefore be not greater than 1 metre high. Socket
or coupled pipes should be stacked with the sockets at alternate ends
and with the sockets protruding to avoid uneven stacking which may
permanently distort the pipes, as shown in Figure 8.

MAR 325 Rev.DO


Hepworth +GF+ GEORG FISCHER
PIPING SYSTEMS
39 -
Storage On Site
On major projects the establishment of a sub depot which is manned or For safety at site locations, stacking of large diameter pipes should be
securely compounded may have the features and requirements as set strictly limited to two units high and the store adequately fenced and
out above. On medium sized projects, or work within a congested area, protected.
it is often necessary to store pipes and materials at selected points dose
lo the laying operations whilst on the smaller works, or laying in rural or Where stringing is adopted, pipes should be placed well clear of the
less congested areas, pipe stringing may be acceptable. In all cases digger tracks and away from the excavated material area. They
careful consideration should be given to the following aspects: should be wedged to prevent accidental movement. Where necessary
protective barriers should be erected with adequate warning signs
and lamps.
Security of all materials and equipment from theft, van
dalism, accidental damage or contamination.

Safety of pedestrians, especially children and blind persons.

The movement of traffic, construction equipment, farming


machinery and animals.
All pipe store locations should be on suitably firm, level ground, free
Figure 8· Individual Pipe Stacks
from damaging material with adequate access for construction vehicles
and/or lifting equipment.

- Hepworth +GF+
MAR 325 Rev.00
GEORG FISCHER
PIPING SYSTEMS
40
Butt Fusion

This Technique is used in situations where the pipes to be joined are


of the same material <PESO OR PE 100) and having the same
nominal wall thickness and outside diameter <SDRl. Pipes sizes greater
than 90mm can be jointed using this technique. HEPWORTH PME
( LLC l offers a range of butt fusion machines for both site and
workshop use. Dramatic increases in productivity in jointing long pipe
systems can be cooling whilst a second joint is prepared. Certain
machines within our range also offer full tracability for each welded
joint identifying not only the operator responsible for the joint but also
technical data relating to that joint.

Electrofusion
Electrofusion is suitable for materials and/or
SDR's being the same or dissimilar providing that
the appropriate couplers are used. This method ls
particularly suitable in situations where access is restricted
or when jointing direct from a coil. HEPWORTH PME ( LLC )
offers a comprehensive range of couplers from Georg Fischer
covering pipe sizes of 20mm to 630mm. All electrofusion fittings
conform to EN12201 and EN1 SSS and are manufactured from PE
100 material. As with butt fusion we offer the option of producing
traceability reports for each joint. Additionally many of the
electrofusion joints supplied by HEPWORTH PME ( LLC ) offer bar
coded settings for the jointing parameters eliminating the chance of
operator error when inputting such data into the electrofusion
machine.

Mechanical Fittings
Hepworth PME ( LLC ) stocks a wide range of mechanical fittings
suitable for jointing PE pipe.

MAR 325 Rev.DO


Hepworth +GF+ GEORG FISCHER
PIPING SYSTEMS
41 -
Range of Joints Butt Fusion and Electrofusion Mechanical Fittings
The advantages of a PE integrated end load resistant system is usually Plastic mechanical fittings for sizes up to and induding 110 mm
achieved most economically by fusion welded jointing. Butt fusion is should be manufactured to ISO 14236: 2000. Wide tolerance
perhaps more commonly applied although electrofusion may be couplings and ftange adaptors tor use with pipes of different materials:
preferred where butt fusion is impractical due to lack of space for ductile iron. steel, PVC-U, PE. fiber-<:ement should be manufactured to
example. EN 14525:2004.

Training in Fusion Jointing


Although the principles of fusion jointing are relatively simple, in it is strongly recommended that such training is given at both
practice care is needed to maintain the integrity of the PE system operator and supervisor levels. In-house schooling followed by some
through appropriate instruction and on site monitoring. on-site experience under supervision is recommended.

Fusion Machines and Equipment


Fusion machines and equipment may be bought or hired through
Hepworth P.M.E. Owners usually arrange for periodic maintenance
contracts and the available servicing facilities should be taken into
account before purchase. Georg Fischer issue comprehensive and
detailed literature on their products and their use, which should be
studied prior to use of the equipment.

The mating surface of all heater plates must be kept dean to ensure
good heat transfer and to prevent contamination at the weld interface.
Any deposit on the surface should be carefully removed when the plate
is cold using a soft woOden spatula and/or a rag soaked in a suitable
solvent such as lso-propanol. Protective and refurbishing techniques are
available.

Trimming tools are required to prepare the fusion faces of the pipe
prior to heating and are usually an integral part of the machine. The Agure 1-Typlcal Butt Fusion Equipment
cutting edges should be maintained in clean and sharp condition.

Most fusion tools are made from aluminium because of its good heat
conduction properties but this is a relatively soft material and easily
suffers impact damage. Heater plates should be protected when not in
use. Recent development of automatic butt fusion machines and fully
retractable heater plates may reduce the risk of contaminating heater
plate surfaces.

Fusion machines must be capable of applying a controlled fusion


pressure at the joint interface but at the same time be capable of
developing high pull-up forces to cope with the work of drawing long
pipe strings. Power driven, centreline action thrust cylinders provide
smoothness and help to prevent misalignment. Frequent roller support
to the pipe string lessens the required pulling forces and prevents
unnecessary drag and scratching of the pipeline. This is particularly
I
essential when dual pressure welding machines are used. Agure 2- Typkal Electrofuslon Equipment

- Hepworth
MAR 325 Rev.00
+GF+ GEORG FISCHER
PIPING SYSTEMS
42
Fusion Jointing
The recommended procedures for fusion jointing are specified in ISO The correct procedures for jointing dissimilar materials and wall
12176 parts 112/3: 1998 - 2001. Materials suitable for the manufac- thickness are outlined below. Only similar materials and similar wall
ture of pipes and fittings to the above specification may not be thickness should be joined by butt fusion
compatible for fusion jointing under certain circumstances and
guidance should be sought before attempting to join materials with
different pressure ratings or with different diameters.

SDR1Z6

PE100 PESO

CORRECT
Dissimilar materials and dissimilar
wall thickness can be joined by electrofusion

""''""~'" "'"
WRONG WRONG
Dissimilar materials must no! Dissimilar materials must not
be 1oined by butt fusion be joined by butt fusion

Butt Fusion Jointing


Pipes and fittings can be jointed by butt fusion using an electrically fittings in the same size range However, only pipes and fittings with
heated plate. The facility to independently check the face temperature same SDR ratings and material may be jointed together using this
in the field is essential. Butt fusion is suitable for jointing pipes and technique.

Electrofusion Jointing welding shelters are used to ensure that dust and rain
do not contaminate the joint and to protect it against
Electrofusion fittings have sockets that contain electrical wires which, draughts.
when connected to the appropriate power source, fuse the socket onto
the pipe without the need for additional heating equipment. It is possible to join dissimilar polyethylene pipe material and wall
thickness. For example, PESO pipe can be joined to a PE1 00 pipe of
It is essential that jointers take special care to ensure that jointing the same pressure rating using electrofusion couplers with the
procedures are rigorously respected and, in particular, that: appropriate pressure rating. Electrofusion couplers are available up to
size 630mm but larger sizes are being developed.

The oxidised surface of the pipe over the socket depth NOTE: Some coiled pipes may be too oval to fit into couplers, or the
1s removed using a mechanical peeling tool. bend of the pipe may make alignment of the ends impossible. A
number of approaches have been proposed, 1nduding:
The peeled area 1s deaned with lsopropyl Alcohol
(minimum 70%) prior to insertion of pipe into fitting. Cil use a mechanical pipe straightener or rerounding tool;
Clamps are used to ensure that no movement of the
joint can take place during the heating and cooling (iil fusion joint a straight length of pipe onto the end of the coil
cycle. before jointing.

MAR 325 Rev.00


Hepworth +GF+ GEORG FISCHER
PIPING SYSTEMS
43 -
Mechanical Joints and Fittings

There is a wide range of proprietary metal and plastic mechanical joints For transition from polyethylene pipe to flanged metal fittings, either
and fittings available. All such fittings should be assembled in polyethylene stub faced flanges with metal backing rings or mechanical
accordance with the manufacturer's instructions and all metal fittings flanged adaptors complying to IS014236 and EN 14525: 2004 can
should be supplied with suitable protection from possible corrosion. be used. The gasket and bolt length used should be appropriate to the
particular adaptor. A jointing compound should NOT be used.
The most common group of metal fittings associated with polyethylene
are: When tightening polyethylene flanges, care should be taken to
produce an even torque load to the limits given by the manufacturer.
flanged and other adaptors; The use of a torque wrench is strongly recommended.
mechanical type couplers;
compression fittings; Typical bolt torques are shown in Table below
gun metal ferrules.

Mechanical fittings are dassified into three distinct endload


perfonnance levels. These are defined as follows:
Nominal Screw tightening
diameter torque £NmJ
Type 1 fitting: The end-load resistance of the joint shall be greater than
DN
the longitudinal strength of the pipe;
Flat gasket Profile
up to max. Oring up to
Note I; Type 1 fittings are applicable to polyethylene pipe only. pressure max.
Such fittings could be used on PE pipeline s, for example, in of 10 bar pressure
areas of mining subsidence and for pull-through applications. of 16 bar
Pipelines installed using this type of fitting would not require
15 15 15
anchoring except where connected to non end load bearing
pipe systems. 20 15 15
25 15 15
Note 2: All fittings for use with polyethylene pipe with outside 32 20 15
diameters Including 63 mm are required to be manufactured 40 30 15
to the requirements of Type 1 50 35 20
Branch Connections 65 40 25
Normally, branch connections on the main as opposed to service 80 40 25
connections are achieved by introducing fusion tees during installation 100 40 30
of the main. A subsequent branch connection into an existing
125 so 35
polyethylene main can be achieved by using:
150 60 40
Note: Pipelines installed using Type 2 fittings would not nonnally 200 70 J) so
require anchoring. Type 3 fitting, The end-load resistance 250 801) 55
of the joint is less than that required by the Type 2 300 1001) 60
definition. 350 1001) 70
400 1201) 80
Note: Pipelines installed using Type 3 fittings will normally
require anchoring as for an unrestrained pipeline and the 1l up to a maximum working pressure of 6 bar
advice of the manufacturer should be sought.

..... standard fusion tee with electrofusion couplers;

...._ standard electrofusion branch connections;

..... branch or saddle fusion fittings <requiring special


fusion equipmentl.

- Hepworth
MAR 325 Rev.00
+GF+ GEORG FISCHER
PIPING SYSTEMS
44
Buried Installations
Polyethylene is a thermoplastic material that when extruded produces a
pipe of flexible nature and to which the principles of flexible pipeline
design must be applied not only at the design stage but throughout
installation as well. In particular the quality of materials and workman-
ship employed in trench preparation, bedding, backfilling and
compaction must be of a high standard if the full strength potential of
the pipeline is to be achieved and pipe deformation limited to that
calculated by the design engineer. The following sub-sections deal with
trench preparation, bedding, backfill and compaction

Site Conditions
For each pipeline development, consideration must first be given to the
nature of the site in terms of configuration, existing surface material
and the likely subsoil component materials.

the machinery and equipment necessary to carry out


the work,
Figure 1- The versatility of PE pipes
the method of installation Ci.e., by trenching or guided
drilling),

the need or otherwise of imported material for


bedding and surround,

the requirements in respect of the surface restor ation.

Traditional Open Trenching


Generally the width of the trench should be the minimum dimension Long lengths of fusion jointed pipeline, having joints made above
compatible with safe working and the satisfactory laying, jointing and ground can be rolled or snaked into narrow trenches. Such trenches
bedding of the pipe. The depth of the trench must allow for may be excavated by narrow bucket or vacuum methods where
compliance with the cover depth requirements Ci.e., minimum 750mm subsoil conditions permit
for service pipes and 900mni for mains from the crown of the pipe,
dependent upon local regulation I soil conditions) together with any In uniform, relatively soft, fine-grained soils free from large flints,
allowance for the base of the excavation to be prepared in such a way stones, or other hard objects, and where the bottom can readily be
as to ensure the firm even support of the pipeline along its entire brought to an even finish, providing a uniform support for the pipes
length. over their length, it may be permissible to lay PE pipes directly on the
trimmed bottom of the trench. In other cases the trench should be
Any exposed pipes and cables belonging to other utilities must be excavated to a depth below the bottom of the pipe sufficient to allow
supported and protected throughout the work to the satisfaction of the for the necessary thickness of selected bedding material.
owners. Any damage must be reported immediately to the appropriate
utility or authority. As excavation proceeds, all unstable trench walls
need to be supported and this requirement is mandatory for trenches
of 1.2 metres or deeper.

MAR 325 Rev.DO


Hepworth +GF+ GEORG FISCHER
PIPING SYSTEMS
45 -
Narrow Trenching
This technique involves the use of a trench with a width of pipe outside
diameter plus 1 OOmm minimum, with all the laying and jointing
operations carried out at ground level. A whole range of specially adapted
compactors, hand tools and narrow trenching machines have been
developed. Since any length of PE pipe string can be pre-welded on the
surface, the trench can be narrow along its entire length and will have
minimal associated embedment and reinstatement costs.

Trenchless Systems
PE is a versatile material and particularly through its toughness and
Hexibility, it is able to be used with a range of cost effective "no dig"
methods of installation.

Systems of thrust boring and m1crotunnelling techniques have become


more readily available within the last decade or so.

Guided drilling or "no dig" systems can be classified into several broad
groups according to the way in which the actual excavation of the pilot
bore takes place.
Microtunnelling using PE pipes
These are:

...._ Fluid jet cutting. High pressure jet nozzles use relatively low
flows of water or bentonite-based mud to cut the hole.
Mechanical blade, Huid assisted. A chisel blade cuts the soil
and ftuid jets directed onto the blade help in cooling and
lubrication.

.,. Impact moles. Percussive moles with slant faces cut


through the soil under thrust and rotation. Down-the-hole
air motors can also be used for cutting harder grounds. The
new PE pipe is then inserted through the bore hole, often
directly below the mole.

....._ Rod pushing. An angled tool is forced through the


ground, compacting the soil and forming a pilot bore .

...._ Pipe bursting. Size for size replacement <or upsizingl of


many existing pipelines is achieved by winching a percussive
or hydraulic mole through the deficient pipeline, thereby
splitting it and displacing the fragments outwards. A new PE
pipe, with or without an outer sleeve, is then pulled through
the enlarged borehole. NarTOw Trenching using PE pipes

Conventional and Oose-F"lt Lining


Slip lining a smaller diameter PE pipe through an old mains is probably The polyethylene pipe is then re-expanded to be close fit in the host
the earliest form of no-dig technology. This has been developed to pipe either by the use of internal pres~ure. or by allowing it to revert
various "closefit" systems. A polyethylene pipe having an outside naturally.
diameter at least as great as the inside diameter of the pipeline to be
lined, is temporarily reduced in diameter by passing it through a die or
rollers, and this enables it to be pulled through the existing pipeline just
as in the sliplining process.

- Hepworth +GF+
MAR 325 Rev.DO
GEORG FISCHER
PIPING SYSTEMS
46
Pipe Bedding and Surround
It is essential that pipelines are laid on a bed of material which will Suitable materials for bedding and surround include free draining sand,
provide even and continuous support. In suitable soils this can be gravels and soils of a friable nature which are then compacted in layers
provided by the hand trimming of the base of the trench with any according to the specified requirements. This "finefill" material is
predominantly hard or soft spots being removed and replaced by
acceptable up to a maximum of 250mm above the pipeline after which
compacted fine material.
the fill is to be backfill material as defined by local regulations.
Where such trimming cannot be easily achieved <e.g. in narrow
trenching) small irregularities can be overcome by the placing and The highway surfaces can be grouped as;
compaction of selected site material or imported fine granular material
to depth of at least SOmm.
flexible and composite roads.
The surround to the pipe effectively forms the foundation element of rigid and modular roads.
the reinstatement and therefore must offer adequate support for the footways, footpaths and cycle tracks.
remainder of the restoration and be capable of transmitting the
imposed loading to the subgrade below the pipe or apparatus. verges.

Flexible or Composite
.._____,"Or------'
Rigid or Modular

Running Surface
_ Qve.!Jat. _
Concrete stab
or bedded
_.__________,
( module

Sub base

Trech Reinstatement-Zone Technology

Other considerations when selecting a surround should include the if this is undesirable, by enclosing the surround within a suitable filter
potential for the migration of "linefill" from the adjacent ground <and membrane.
the backfill) into open-textured surround. Such action normally results
in settlement of the adjacent ground land/or the backfilD. Migration of
Bricks or other hard material should not be placed under the PE
"finefill" ain be prevented by using a dose textured surround or,
pipe as temporary support.

MAR 325 Rev.DO


Hepworth +GF+ GEORG FISCHER
PIPING SYSTEMS
47 -
Backfill and Sub-Base
There are four dasses of acceptable material (dependent on local Unsuitable material for any part of the permanent backfill would
regulations) which may be used in the backfill zone between the top of indude large stones, flints, lumps of clay, frozen earth, organic matter
the surround and the sub-base zone in highway reinstatement. or chemically contaminated soil.

Heavy mechanical compaction machinery should not be used until the


These are: fill has reached a depth of at least 300mm above the top of the pipe.
Gass A : Graded granular materials
Gass B : Granular materials
Gass C : Cohesive/Granular materials
Gass D : Cohesive materials

Pipe diameter + 300mm

\\ \ \ \ \ 'ti

... \ ~fll
§ ,_ \ \
\ \ \\\ =E
i;::
Q.
0
Cll
g \ \ \ \ ~
0 u,?>
E
~ u \ \ a;i:s 3
E E \ \ \ c cfll ·-
'ti c
'E ~ \\\ ·-
fll 'ti fll
Cll .c
·e; E
·c: \ \ E
41
u u
.., Cll
e ·e; \ \ \ \ \ \ c::: 'ii. E
E
0 E \ \\\
0 E
°'
-
0
0

-
T
"Cl 'ti
c c
ftl fll
"Cl .c
8 >-
t cl:~
c:n
c
:a
'ti
41
i E ti
e!
o0 E
0

t-
.Q MU
E
~
E
:5 ~
E Imported Granular Fill
E Typically Smm - 10mm
E pea gravel
0
0

Recommended Bedding, Side Fill and Back Fm

- Hepworth
MAR 325 Rev.00
+GF+ GEORG FISCHER
PIPING SYSTEMS

48
Typical Tests for Suitability of Soil Material !imported or local> Strike off the top surface level with the top of the cylinder and remove
for Surrounding Buried Plastic Pipes all surplus spilled material. Lift the cylinder up clear of its contents and
place on a fresh area of Hat surface. Place about one-quarter of the
Particle Size contents back in the cylinder and tamp vigorously with the metal
This maximum partide size should generally not exceed 20mm. The rammer until no further compaction can be obtained. Repeat with the
presence of an occasional partide between 20mm and 40mm is second quarter, tamping as before, and so on for the third and fourth
acceptable provided the total quantity of such particles is only a very quarters, tamping the final surface as level as possible.
small fraction of the whole. If particles over 40mm are present the
material should be rejected. Measure down from the top of the cylinder to the surface of the
compacted material. This distance in centimetres divided by the height
In cases of doubt a representative sample of material Cabout 2kgl of the cylinder (25cml is referred to as the 'Compaction fraction'.
should be sieved, using test sieves of 19mm and 38mm nominal mesh
size. Test
Apparatus
NOTE 1 - To obtain a representative sample, about 50kg of the 1. Open-ended cylinder 25cm long and 15:t0.6cm internal
proposed material should be heaped on a clean surface and divided diameter <1 Scm diameter PVC pipe is suitable).
with the spade down the middle. One of these halves should then be
similarly divided, and so on unUI the required mass of sample is left 2. Metal rammer with striking face 40mm diameter and weighing
1.0±0.lkg.
NOTE 2 - In the sieving, clumps of material that break up under light
finger pressure may be helped through the sieve, but considerable 3. Rule.
force shall not be used to squeeze oversize clumps through the mesh.
Interpretation of results
If (i) any particles are retained on the 3Bmm sieve, or f!O more than 50/o Compaction
by mass of the sample is retained on the 19mm sieve the material is fraction Suitability for use
not recommended. 0.1 or less Material suitable.
0.1 to0.3 Material suitable but requires extra
Procedure - Obtain a representative sample tsee Particle Size, Note care in compaction.
1l more than sufficient to fill the cylinder (about 11 kgl. It is important
Not suitable if the pipe is subject to
that the moisture content of the sample should not differ materially
waterlogged conditions after laying.
from that of the main body of material at the time of its use in the
Over0.3 Material unsuitable.
trench. Place the cylinder on a firm flat surface and gently pour the
sample material into it, loosely and without tamping.

Procedure
Cal Place cylinder on a firm flat surface
and fill to overflowing with a typical
sample of soil excavated from pipe
trench. .·l/;. · ... '

l -----l
<bl Skim off overfill and remove spillage
<cl Lift cylinder so that contents are left
behind
(dl Place now empty cylinder onto
another firm ftat surface.
(el Place one-quarter of material back
into cylinder and tamp down until
completely compacted.
(I) Repeat with 2nd, 3rd and 4th
quarters.
(gl Measure in mm from top of cylinder
to surface of material to obtain
figure"X".
(h) Divide figure "X" by 250 to obtain a
compaction figure.
0.1 or less - suitable
0.1 to 0.3 - suitable with care,
except in ground
conditions generally
waterlogged.
over 0.3 - unsuitable.

MAR 325 Rev.OD


Hepworth +GF+ GEORG FISCHER
PIPING SYSTEMS
49 -
Mainlaying
This Section covers mainlaying including the lowering, laying and
preparation for testing of the pipeline and summary of installation
methods.

Preparation
Generally polyethylene pipes are joined to form a string above
ground prior to snaking into the trench. To prevent scoring
pre-made pipe systems, pipe rollers should be used.

Before commencing of pipelaying, the person responsible should


ensure that the trench is safe in accordance with the health and
safety procedures.

Before lowering polyethylene pipelines into the trench, a check


should be made for cuts, deep scratches or other pipe damage and
in fusion jointed systems that the system has cooled sufficiently
before stress is imposed upon any pre-made joints. When lowering
pipe into trenches, care should again be taken to avoid scoring of
the pipe by contact with the sides and bottom of the trench. Special
care is needed when passing under/around obstructions or other
utility services. Use may be made of planks and ropes where
appropriate but wire ropes or chains should not be used.

During lowering no-one should be allowed to stand underneath


the suspended pipe. Figure 6-Jointed PE pipes prior to laying
Pipelaying
Gradual changes in direction of polyethylene can be accommo-
dated by pipe deflection but every effort should be made to keep Whenever possible, a minimum distance of 300mm from
the pipe as central as possible within the trench to enable correct obstructions and other services should be maintained. This
side-fill compaction. Similar care should be taken when any distance is often possible when laying parallel to other services but
distortion of coiled pipe has occurred. not always practicable when crossing other services. A separation
distance of 75mm may be allowed for a square crossing but
During the pipelaying of continuous fusion jointed systems, due suitable protection should be provided from possible point
care and allowance should be made for the movements likely to loading, interference, damage or contamination.
occur due to the thermal expansion I contraction of the material.
This effect is most pronounced at end connections to fixed Polyethylene is not a conductor of electricity and no
positions and at branch connections. attempt should be made to use PE pipework as a means of
earthing electrical equipment. Similarly, because of its high
For summer time installations with two fixed connection points, a electrical resistivity, caution is required in the use of the material
slightly longer length of polyethylene may be required to compen- where static electricity may be an important consideration.
sate for contraction of the pipe in the cooler trench bottom. The
snaking in the trench which naturally occurs with pipe 90mm and
The bending of polyethylene is permissible and the properties of
below is normally sufficient to compensate for this anticipated
fusion jointed systems enable changes of direction without
thennal contraction.
recourse to the provision of special bends or anchor blocks.
However, the pipe should not normally be cold bent to a radius
During a winter installation, the exact length of pipe should be
smaller than the limits prescribed (see Design Considerations). For
used. Pipe which is too short or not aligned must not be drawn up
mechanical non end load resistant jointing systems, anchor blocks
by the bolts of a Hanged connection because of overstressing the
to withstand the resultant thrusts must be provided in the
stub end, Hanged adaptor and ultimately the valve or fixture to
traditional manner, ( See Design Considerations ).
which it is connected.

It is advisable to defer the final tie-in connections until thermal The hot bending of polyethylene pipe is possible under carefully
stability of the pipeline has occurred. Once a pipeline is installed controlled conditions but under no circumstances should hot
and in service,. the temperature variation is usually small, occurring bending be attempted under site conditions.
over an extended period of time and is not likely to induce any
significant stress or movement in the pipe system. Polyethylene is a poor conductor of heat but is flammable and
should not be exposed to naked flame.

- Hepworth +GF+
MAR 325 Rev.DO
GEORG FISCHER
PIPING SYSTEMS
50
The installation of flanged fittings such as sluice valves, hydrant tees, After completion of an installation, pipework and fittings should be
end caps etc., usually requires the use of polyethylene stub flanges inspected and made ready for testing to ensure the safety and
complete with backing rings and gaskets. Care should be taken when efficiency of the system. If the system is a large one it should be
tightening these flanges to provide even and balanced torque. Provision tested in sections of convenient length up to a maximum length of
should be made at all heavy fitting installation points for concrete 800m.
support both for the weight and to resist the turning moments
associated with valves and hydrants. The degree to which the trenchline is backfilled prior to testing will be
influenced by:
Where flange connections are included in the pipeline these must be ..... the prevailing site and/or traffic conditions.
properly aligned and care taken when tightening to provide even and ...._ the potential risk of floatation.
balanced torque. Bolts should be tightened in a North/South, ....._ the imbalanced forces due to configuration and
East/West, NE/SE, etc.. pattern. On no account must flanged connec- imposed test pressure.
tions be used as a means to overcome poor alignment. Where practical it is advisable to leave joints exposed throughout the
test.
Recommended torque for flanged connections is given in Jointing
Methods. As part of the preparation for the hydrostatic pressure test all
anchorages and stnuts should be checked to ensure they are
It should be noted that at three way fusion jointed fabricated tee adequate to withstand the excess pressures and it is advisable to
installations, additional equipment and care in handling is necessary 1f retighten all bolted flanged joints and to check that all intermediate
the risk of damage is to be avoided. Consideration should be given to control valves are open.
introducing a flanged connection on the branch outlet of the tee so that
the branch main joint can be made in a separate operation. Complete and accurate records should be taken of the installation. It
is useful for records to be taken before the pipes are buried whilst
Polyethylene pipes and fittings may be partially or completely memories are fresh and key elements are still visible. Photographic
surrounded by concrete but the pipe should be protected by a heavy records of important or complex features should be considered.
duty polyethylene membrane to avoid possible damage during pouring
or compaction and to prevent high localised stresses. Marker tape should be laid along the line of main and connected at
each end to either a sluice valve or hydrant. The recommended
position of the tape is 350mm below the surface directly above the
crown of the pipe.

On-Site Jointing
The various heat fusion techniques available for jointing PE pipe allow
In cases where jointing equipment is continuously moved to joint
the installer a greater degree of freedom when considering the most
positions along the length of the pipeline, protection from the
cost effective/practical installation method suitable to a particular
elements should still be provided and ii joints are to be made in the
construction site. The main element of choice is that jointing a number
trench then sufficient ground material must be excavated to provide
of straight pipe lengths can be carried out at a fixed jointing station
adequate space for the operative and jointing equipment. In wet
outside the trench area or conventionally at each joint position along the
trench conditions precautions must be taken to ensure that the area
pipeline either outside the trench area or in the trench bottom.
Generally and providing site conditions permit, the greatest advantage around the jointing station remains dry.
is obtained from jointing at a fixed position outside the trench area. In
this circumstance pipes are transported by hand or mechanical means
depending on size and class from the site storage area to the jointing
station. During this phase all recommendations given in the 'Handling
& Storage' section apply. The jointing station should consist of a
covered shelter heated in winter months) adequately lit to give the
jointing operative dear vision around the pipe joint and of all pressure
and temperature gauges, etc. Even in summer months it is good site
practice to include for a shelter at the jointing station to provide
protection against wind, rain, dampness, sands etc. These recommenda-
tions apply equally to projects where Electrofusion or Butt fusion jointing
techniques are used but are most common for Butt fusion. Normally on
land installations pipes are pulled through the jointing station by hand,
winch, tractor, etc., depending on pipeline length, size and class. It is
strongly recommended that the jointed pipeline is supported on
sufficient free-running rollers as will prevent the jointed pipes from
-
coming into contact with the ground. This will not only make pipe
handling and the jointing operation easier but will prevent the pipe
from being scratched and scored.

-
On-Site Jointing Station Cover

GEORG FISCHER
Hepworth +GF+ PIPING SYSTEMS
MAR 325 Rev.DO 51
Installing Coiled Pipes - Sizes 160mm and above
Coiled Polyethylene Pipes in 160mm sizes and above should be
moved and uncoiled using an approved dispensing trailer. There
should be facilities available on site to restrain securely each coil
individually throughout the transit and unloading process. Pipes should
be uncoiled strictly in accordance with the releasing instructions for
coiled pipe retaining straps detailed in Handling 8. Storage. After
sufficient pipe has been cut from the coil, the protective end cap must
be replaced on the remainder of the coil.

Pipeline Rehabilitation I Re-Lining


The use of PE pipes for water main rehabilitation by slip lining
techniques is now well established across the globe.

It is recognised that the properties of the material, particularly its


flexibility, toughness and smooth bore are ideally suited for this
application.

Pipeline rehabilitation is, of itself, an extensive subject and many profe- Coiled PE Pipe
ssional contractors specialising in these techniques have emerged over
the last decade.

This section, therefore, is not exhaustive but is intended to draw atten~


ion to some common aspects of this application for PE pipes which
should not be overlooked.
PE pipes to be used for re-lining applications are normally Butt
Pipe Selection fusion jointed.
The outside diameter and pomure class of the pipe required will
probably be selected by considering: ft is normal practice to remove the external weld bead in order to
provide a smooth continuous pipe surface when using pipe insertion
Flow requirements technique.

~ Size and condition of pipe to be relined

~ The anulus to be grouted

~ Is the system pressure or non-pressure

~ Medium being conveyed e.g., potable water, sewage,


industrial effluent, etc.

Tipical Slip Lining Installation

- Hepworth
MAR 325 Rev.00
+GF+ GEORG FISCHER
PIPING SYSTEMS
52
Sub-Aqueous Installations
Polyethylene pipes have been used extensively for many years in sub-
aqueous installations. Here, in addition to efHuent disposal projects,
polyethylene potable water distrihution mains link communities and
Public Utility pumping stations over several kilometres. There are
numerous examples where one continuous butt-welded polyethylene
pipeline, traverses land and water over many kilometres.

Above Ground Installations


Where PE pipes are to be used in above ground installations, they must
be protected against exposure to direct sunlight It is good design
practice to insulate thermoplastic pipes above ground. This will help to
reduce the amount of movement caused by temperature variation.

Support for Horizontally and Vertically Suspended Pipes


There are two main factors to be considered when specifying support
details for suspended PE pipe systems .

...,.,_ Technical re<iuirements


...,.,_ Aesthetics

Technical Requirements:
Polyethylene pipes installed in above ground systems will generally be
black. Where PE pipe is specified this must be protected from direct
exposure to ultra violet light <sunhghtl.

The correct specification of restraints and supports is an essential part of


suspended PE pipe system design, and must take account of expansion
and contraction at the extreme maximum and minimum service

MAR 325 Rev.00


Hepworth +GF+ GEORG FISCHER
PIPING SYSTEMS
53
-
Connection to Polyethylene Mains
The preferred method of connecting polyethylene service pipes from
polyethylene mains is my means of electrofusion self-tapping tees .

Electrofusion Self Tapping Tee

Laying Polyethylene Sentices


Service pipes are available in coils and thus offer an opportunity to limit electrofusion couplers
the number of joints required in a particular situation. This, together
push fit couplers
with the facility to joint above ground enables narrow trenches to be
adopted where conditions are suitable. compression fittings <metal or plasbcl

The ideal bed and surround requirements normally applied to


mainlaying may not always be achievable. Care should be taken to
ensure the pipe is not bedded on uneven or sharp projecting material.
Every effort should be made to adequately compact suitable fine
material around the pipe to at least 1OOmm above the pipe before
normal back-filling takes place.

- Hepworth
MAR 325 Rev.00
+GF+ GEORG FISCHER
PIPING SYSTEMS
54
Testing and Commissioning
This Section deals with the standard procedures for testing installed After being tested, all service pipes must be subjected to a final
pipelines prior to commissioning. These standards will normally require, disinfection process before being introduced into the supply system.
as a minimum, the adequate flushing of the service and the testing of
all pipes and ioints to the maximum head to which the system is to be Special attention should be paid to the proper sterilisation of those
subjected. services laid to hospitals and renal-dialysis machines.

Hydrostatic Pressure Testing


The normal testing procedure used for most pipelinematerials requires However, when applying this regime to PE pipelines it is found that,
the application of a nominated hydraulic pressure to the pipeline, then due to the characteristic stress relaxation of the material, confusing
isolating the pressure pump for a period of 1 hour. The success of the and occasionally meaningless results are obtained. The relevant
test is then judged by the quantity of water required to restore the procedure that should be adopted for PE is outlined below.
original test pressure measured against a given formula.

Type 1 Pressure Test: 3. Record and plot the pressure gauge readings at the
following intervals:
Introduction O- 10 mins @ 2 minute S readings
This is a short simple test whereby the creep in the PE pipe .is sustained 10 - 30 mins @ 5 minute 4 readings
by maintaining the test pressure for a period of 30 minutes. By opening 30 - 90 mins @ 1o minute 6 readings
the control valve the pressure is then reduced to a nominal amount
before redosing the valve The subsequent "recovery" of pressure in the The pressure should be seen to rise due to the
pipeline is indicative of a sound pipeline. This simple PASS/FAIL test visco-elastic response of tlie pipe material.
may be found appropriate for short lengths of small diameter main
where there is no residual air in the test section. 4. The resulting graph for a leak-tight system should
have a characteristic profile similar to that shown in
The detailed test procedure is as follows:- the following graph.
1. The selected test pressure is applied and this pressure
maintained by additional pumping as required for a 5. The degree to which the creep in the material af fects
period of 30 minutes. During this time an inspection the pressure graph and the time for response to
should be carried out to identify any obviousleaks at reduced pressure will be influenced by:-
this pressure within the system under test.
the length of the test section
2. The pressure should then be reduced by rapidly the diameter of the pipe
bleeding water from the system to a nominal pressure the presence of air
of, say 2 bars at the test gauge. Close the control valve the efficiency of the bedding and compaction
to isolate the installation.

Within about a 90 minute period a good indication will normally be


10 .-----o comrotvalve~
available. If during that period there is a falling away of pressure, this
would indicate a leak within the system. It is advisable to check all
Pmsure rapidly <lreppcd mechanical fittings before visually inspecting the welded joints. Any
lo• nomiNI Mt C2 lnrl
defects in the installation revealed by the test should, of course be
lndicA!fve of $0und main .., PASS rectified and the test repeated after the line has been allowed to relax
----
lnd1ative ol unK<tptable 11."dk •FAIL
for an appropriate period of time.

O O-~--'~"'--'-~!>--_.__.~..___,____.~.i._-'---''--~ Type 2 Pressure Test:


-30 -20 · 10 10 20 30 40 50 60 70 80 90
TJM;E<rrinl This is a more sophisticated and comprehensive tes.t than the Type 1
Provisional Pressure Test lYPE 1
T)'pital Pressure Graph
Test ahd is used for large diameter pipes and long pipeline
installations. Full details of the Type 2 Pressure Test are included in
the WRc Manual for Polyethylene Pipe Systems for Water Supply
Applications.

MAR 325 Rev.OD


Hepworth +GF+ GEORG FISCHER
PIPING SYSTEMS
55 -
<§:>
APPROVED
The increasing acceptance of polyethylene as an approved Main pipeline sizes from 90mm to 400mm are approved for
material for safe transportation and distribution of both gas and fire-fighting applications together with a wide range of fittings.
water has led to the fire fighting industry introducing the
materialfor fire-fighting applications. Stringent FM Testing and Auditing guarantees customers complete
confidence for the use of polyethylene as a material for buried
Hepworth PME ( LLC) and our principal Georg Fischer Piping fire-fighting applications. Fusion welded joints ensure that the
Systems ( Switzerland) have successfully undertaken FM Approval subsequent pipe system is secure and safe and Is able to give an
Testing and Auditing which means that we are now able to offer operational lifetime of more than 50 years, leak and corrosion free
fully Factory Mutual (FM) approved Fire Fighting Pipe Systems for with minimal maintenance.
buried applications with operating pressures up to and including
12 bars.

- .. ---

Please refer to our installation instructions when


undertaking any fire-fighting pipeline installations.
Copy available upon request.

<:£9 ~
APPROVED KITEMARK
MAR 325 Rev.00
I~\ ~
~ ~I
00 1
Hepworth +GF+ GEORG FISCHER
PIPING SYSTEMS
57 -
U.A.E. OFFICES
ABU DHABI
P.O. Box: 4894, Abu Dhabi, UAE
Tel: +971 2 6727585
Fax: +971 2 6783578
Email: [email protected]

SHARJAH
P.O. Box: 23363, Sharjah, UAE
Tel: +971 6 5438459
Fax: +971 6 5428147
Email: [email protected]

ALAIN
P.O. Box: 80862, Al Ain, UAE
Tel: +971 3 7210727
Fax: ..,971 3 7211292
Email: [email protected]

QATAR OFFIC E
DOHA
HEPWORTH PME (QATAR) W.L.L.
P.O. Box 50207, Doha, Qatar
Tel: +974 44506810
Fax: +974 44506811
Email: [email protected]

MESAIEED
HEPWORTH PME (QATAR) W.L.L.
P.O. Box 50207, Mesaieed, Qatar
Tel: +974 44760588
Fax: +974 44760525

OMAN
ABDUL GHAFFAR HUSSAIN
TRADING LLC
P.O. Box 117, PC 130,
Muscat, Sultanate of Oman
Tel: +968 24216938
Fax: +968 24210032
Email: [email protected]
Email: [email protected]

BAHRAIN
HEPWORTH W.L.L.
Building 1, Avenue 001 O
HEAD OFFICE P.O. Box 143, Manama, Bahrain
H&WOR'Tff PME U:C Tel: +973 17672050
DUMI Fax: +973 17672583
Email: [email protected]
P.0.8ox ~. Dubel, UAE
T.S: ..a7 4 2884870 SAUDI ARABIA
Far .en 4289482011 ABDUL GHAFFAR INDUSTRIES LLC
Emal:W~ Al Nuwar Bini Malik Street,
Building 18 - Al Rawdah District
SALElllCUS1"0t SERVICE Tel: +966 547900444
cuatomer..wvtceOCOlp;ae Email: [email protected] www.hepworth.ae
MAR 325 Rev.00 58
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-IR-00001 Rev. No.: 00 Sheet: 19 of 26

4. Compliance with
Authorities Having
Jurisdiction

LUS-CP07C4C5C6-AJP-MAT-IR-00001_00 Page 19 of 26
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITIAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-IR-00001 Rev. No.: 00 Sheet: 20 of 26

NA

LUS-CP07C4C5C6-AJP-MA T-1R-00001_00 Page 20 of 26


AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C - 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-IR-00001 Rev. No.: 00 Sheet: 21 of 26

S. Sample

LUS-CP07C4C5C6-AJP-MAT-IR-00001_00 Page 21of26


AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-I R-00001 Rev. No.: 00 Sheet: 22 of 26

5.1 Samples & accessories

To be provided in due course

LUS-CP07C4C5C6-AJP-MAT-I R-00001 _00 Page 22 of 26


AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-I R-00001 Rev. No.: 00 Sheet: 23 of 26

5.2 Lead time delivery (days)

LU S-CP07C4C5C6-AJP-MAT-1R-00001_00 Page 23 of26


SN TYPE DESCRIPTION QUANTITY LEAD TIME FOR
SAMPLE
1
HOPE PIPE, SOR11/PN16 3" x 300mm HOPE Pipe 1 pc 7 days

2 HOPE PIPE, SOR11/PN16 4" x 300mm HOPE Pipe 1 pc 7 days

3 HOPE PIPE, SOR11/PN16 6" x 300mm UPVC Pipe 1 pc 7 days

4 HOPE PIPE FITIING 3" ELBOW FITTING 1 pc 7 days

5 HOPE PIPE FITTING 4" TEE FITTING 1 pc 7 days

6 HOPE PIPE FITTING 6" ELBOW FITTING 1 pc 7 days


AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-IR-00001 Rev. No.: 00 Sheet: 24 of 26

5.3 Spare parts requirements

5.4 Recommended Spare parts

LUS-CP07C4C5C6-AJP-MA T-1R-00001_00 Page 24 of 26


SN TYPE DESCRIPTION UNIT QUANTITY

1 HDPE PIPE, SDR11/PN16 6" DIA. HOPE Pipe LINEAL METER 53

As per actual
2 HOPE PIPE, SDR11/PN16 3" DIA. HOPE Pipe LINEAL METER
site condition
As per actual
3 HOPE PIPE, SDR11/PN16 4" DIA. HOPE Pipe LINEAL METER
site condition
HOPE PIPE FITTING As per actual
4 3" Elbow fitting pc
SDR11/PN16 site condition
HOPE PIPE FITTING As per actual
5 4" Tee fitting pc
SDR11/PN16 site condition
HOPE PIPE FITTING As per actual
6 6" Elbow fitting pc
SDR11/PN16 site condition
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C - 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-I R-00001 Rev. No. : 00 Sheet: 25 of 26

6. References

LUS-CP07C4C5C6-AJP-MAT-1R-00001_00 Page 25 of26


AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03

MATERIAL SUBMITTAL FOR HOPE PIPE & FITTINGS

(LANDWORX TRADING & CONTRACTING W.L.L.)

LUS-CP07C4C5C6-AJP-MAT-IR-00001 Rev. No.: 00 Sheet: 26 of 26

6.1 List of projects

LUS-CP07C4C5C6-AJP-MAT-IR-00001_00 Page 26 of26


REFERENCE LIST
HIGH DENSITY POLYETHYLENE (HOPE)
HEPWORTH PIPES AND GEORG FISCHER FITTINGS

ISD
9001
Sr. No. CONTRACTOR PROJECT NAME
~~-It
flirntr.-.t;·1

New Horizon Contracting & GTC 558/2013 - Three Years Call - Off Contract
l5D 1
14001 Maintenance WLL for Extension of Water Distribution
b:vtW"'l(r~ •

'"'"~""
Qatar Gas Transport Company
DHSAS 2 Erhama Bin Jaber Jalahma Shipyard
18001 Ltd. (NAKILAT)
o.:,in.ttr,1:<
llf'111r. 1 ·..0S1'1: ~
"- -u~ttl
Aktor S.A. - Al Jaber
3 ISF Camp - Duhail
Engineering JV

Roads and Infrastructure in Bani Hajer North


4 Combined Group Company
Phases 1 & 2, Package 01

WRAS
APPROVED PRODUCT
North Road Project
5 Al Darwish Engineering WLL
Al Waab Complex Public Roads (Package 1,2 &
3)

~
APPROVED
6 QD-SBG Constructions QPR-Dukhan Road (East Contract)

Al Jaber Transport & General


7 Al Muntazah Extension Project (Package 13)
Contracting LLC

Bin Omran Trading &


8 Al Huwailah Link Road
Contracting
CP 94- GSE Maintenance Facility, Motor
• , . ,.!\., , . -_ Aktor S.A. -Al Darwish Transport Workshop, Facilities Maintenance
'·% ·~ 9
, 11;,1 tf! tiRUfl
Engineering Facility Building and Facilities Maintenance
_ ,. 11 uP1Hi ~. ti r . ~ ti
Workshop

10 Sinohydro Group Limited Doha Expressway {Package6)

Hepworth PMF. (Qatar) Wl. L


PO Box 50207. Mesaieed. Qatar Tel: 4476 0586 - Fax: 4476 0525 - Doha Sales Office Tel: 4450 6810 - Fax: 4450 6811
llO· lA" ~~ ito· lA\• 0~ ci'.:>3..UI o~ ~ - iiVl ·0\'0 \)"Sl.9 f.iVl •OAA 0~ p.9 - ~ 0·\'-V:y.ua
Email: [email protected] Website: www.hepworth.qa
Subsidiary of Carys Building Materials Authorised, issued & paid-up share capital QR.40,000,000

MAR 325 Rev.DO 213


Sr. No. CONTRACTOR PROJECT NAME
150
9001
(i>.1) -lt
P 1r•)tirt•,1
Design and Construct Service Road Enhancement
11 Tekfen Construction
to North Road Corridor (Project 059)
150
14001
£..,. ·w~•· GTC 305/2009 - Replacement of Primary and
&.• ,r•1n·•1f 12 Boom Construction
Distribution Networks at Doha - Phase Ill
01i5A5
18001 Lusail Development CP 1- Primary Infrastructure
O«v;ui.:11;:.
l•1 ;hl· 1·9s.•,1, 13 Combined Group Company
l ~'\J;.::-cu Works

14 Drake & Scull New Rayyan - Package 2 MEP Works

Ceremonial National Day Road


15 Tekfen Construction (Link Road between Dukhan Road and North

~WRAS
APP~oveo PRODUCT
Road)

w
Hyundai Engineering & Hamad City- Hospital fit out
16
Construction CO. Ltd (BA/09/10/C004/G)

Immigration/ 901 / 3A- (Al Hanna)

APPROVED 17 J & P (Overseas) Ltd. {QATAR)


{Immigration) ERC0491/Cl Salwah Interchange

18 Powerline Engineering CP303

19 HBK GTC70

20 Bemco Contracting CP 13 - Utilities Package

Hepworth PME (Qatar) WU.

PO Box 50207, Mesaieed, Qatar Tel: 4476 0588 - Fax: 4476 0525- Doha Sales Office lei: 4450 6810 - Fax: 4450 6811
H.0· 1A\\ v-Sl.9 t.E.O· 1A\· 0si!zh hjJ.ll o~ ~ - EEV1 •OYO u.Sl.9 EEV1 ·OAA 0~~ _,.b.9 - ~ O·Y·V:y.ua
Email: [email protected] Website: www;hepworlh.qa

Subsidiary of Carys Building Materials Authorised, Issued & paid-up share capital QR.40,000,000

MAR 325 Rev.00 214


Sr. No. CONTRACTOR PROJECT NAME

ISO
9001
(\:'l<lt
;.i,~ .. l' ....... , Water Supply to Motorcycle Race Track

ISO
1~001 CP 288 Effluent Mains TS to D
t ..... ·l"l'">Cdl
llrtol)'ll" • ·.:i

CP 646 Effluent Mains T6 ton ERC 0492/Cl Al


OHSAS
18001 Gharaffa Interchange
0m.Of1.JJvl
t't'1'1)..1 ·.C: ~t'1:\
V.n~'ii-'« 1
Al Jaber Engineering Wll Qatalum, Ground & Civil Works for Rectifier
21
(Qatar) Stations

Reconstruction of Roads and Infrastructure in


Mesaieed Community Area

~WRAS Gabro Project


APPROVED PRODU CT

Wet Utility at Ras Laffan

~ APPROVED 22 AOCC-JV
NOIA Airline Support facilities CP11

CP-94 Joint Venture

NOIA Aircraft maintenance Hangar CP26

23 Valtas limited NOIA CP19

24 Sinohydro lusail Primary Infrastructure - CP1

25 Qatar Building Company Barwa Housing Project

Hepworth PME {Qatar) WLL


PO Box 50207, Mesaieed, Qatar Tel: 4476 0588 - Fax: 4476 0525 - Doha Sales Office Tel: 4450 6810 - Fax: 4450 6811
~t0· 1A\\ \.)4.51.9t~0·1A\· 0 # ~sJ..11 ~~ ~ - H.Vl ·0\'0 v-Sl.9 HV1·OAA0# _,.b.9 - ~ 0·\'·V:y.l.JO
Email: [email protected] Website: \VWW.hepworth.qa
Subsidiary of Corys Building Materials Authorised, issued & paid-up share capital QR.40,000,000

MAR 325 Rev.00 215


Sr. No. CONTRACTOR PROJECT NAME

Construction of Qatar Primary Routes in North


26 Tekfen Construction
150
Road CP - 2&3 by Ashghal TSE Works
9001
(\;;\' ft
L'1r<11Jt:a"'.I

27 Boom Construction Suhim Bin Hamad Road, TSE


150
14001
lr-.'"ct~~ra
&lit4illff'\l
Construction of TSE main to Al Rakhia Farm
28 Petroserv limited
CP714
O>iSAS
18001
Oc~!i:r>!f
1;,~ . .. -.ie'»·•~\
1.•.,1~ .~ ~ I
29 Mid mac Yuksel Ras Abu Aboud Project TSE

Development of Small & Medium Scale Area


30 Combined Group
Phase II

~WRAS 31 Larsen & Toubro Limited


QP- Ras Laffan - Electrical & Telecom Utility for
Support Services Area Phase 1&2
APPROVED PRODUCT

~
F-Ring Parson Inter

32 CCC Dukhan Highway


APPROVED
N DIA CP 27 - 76 - 91- 92 - 94

33 SEG Qatar Nakhilat Project

34 Punj Lloyd Limited NDIACP29

35 HBK Engineering Abu Samra Highway

Hepworth PME {Qatar) WLL

PO Box 50207, Mesaieed, Qatar Tel: 4476 0588 • Fax: 4476 0525 • Doha Sales Office Tel: 4450 6810 • Fax: 4450 6811
Et0· 111\\ v-Sl.9 llO· lA\· 0~ <b._9-l}I 0~ ~ - lEV1 ·OYO v-Sl.9 lEV1 ·OM 0~ µ · ~ O•Y.Y:y •...,o
Email: [email protected] Websi1e: www.hepworlh.qa
Subsidiary of Corys Building Materials Authorised, issued & paid·up share capital QR.40,000,000

MAR 325 Rev.00 216


Sr. No. CONTRACTOR PROJECT NAME

Umm Bab

00
9001
36 Gulf Consolidated Contractors Construction of Roads, Utilities Crossing & Street
o..;1,
Vtr•J'-r.t
Lighting in the Industrial Area - Mesaieed

150
14001 Construction of Doha Rawan Sewerage
!r-1 """""o3f'
,.,..,.)11,, ..'11
Improvements to Existing TSE Network

OHSAS
18001 QIS204 Tanker Reception Facility - Doha West
o.;,um.,'1 37 Metito Qatar
w ~111. J·.CS•'m Sewage Treatment Plant
"'•"'F··irt

Al Waha Contracting & Trading GTC/232/2008 - Head Works Construction for


38
Company Doha South RPS & Associated Pipelines

HBK Contracting Co. & QBS


39 Development of Main Roads in Zone 46
International WLL
WRAS
APPROYEI> PROOUCT
40 Samsung C & T Lusail Development Primary Infrastructure CPSB

<FM>
~
41
Qatar Electro Mechanical
Group Al Mana
Marina Mix-50 @ Lusail

APPROVED
Construction of Multipurpose Hall at Al Sadd
42 Aktor S.A
Sports Club Package 2-Main Works

Construction of Integrated Chiller, Freezer,


Target Engineering
43 Laundry, Dining, & Accommodation Facilities in
Construction Company
Halul, Qatar
.'
~ z t~
~ :'- ~·· -- . :.~ Abdullah Al Muftah Trading &
44 The Pearl LPE 12 Villa (B+G+l+P), The Pearl Qatar
'1·d .li; GfU:[ff Contracting Co WLL
• l"\i,_t'l i 'l ::G t ...1 1:; I'

GEC Services for Local Roads & Drainage - Area 4


Boom Construction Company
(Doha South) DS131 - Roads and Infrastructure
45 WLL & Lotus Trading and
for Government Residential Division Project in
Contracting Company JV
North Al Wukair

Hepworth PME (Qatar) WLL

PO Box 50207, Mesaieed, Qatar Tel: 4476 0588 ·Fax: 4476 0525 - Doha Sales Office Tel: 4450 6810 - Fax: 4450 6811
U.O• lA\\ l)'.Sl9 H.O· lA\· 0.9¥.:i h,9.i.JI u~ ~ - H.Vl ·0\'0 ~l9 ££Vl ·OM .Jsi!Ji fa-9. ~ 0•\'-V:y.va
Email: [email protected] Website: www.hepworth.qa
Subsidiary of Corys Building Materials Authorised, issued & paid-up share capital QR.40,000,000

MAR 325 Rev.00 217


Sr. No. CONTRACTOR PROJECT NAME

Hyundai Engineering &


46 P003: Lusail Expressway
Construction

150
9001 Hamad and Mohamad Al
47 Doha Festival City - Energy Centre
"""
J.'Y"•:;crrr-1 Futaim

150
14001 Gulf Marine Engineering &
[ r -,•CFr.-..:<>!•
M.,...-;urt•J
48 Doha Marriot Gulf Hotel
Construction WLL

OHS AS
18001
OIU:r;Nln"Ltl
' '" ''o~ · -cis~·r., 49 QBC-MSF New Doha Port (NPPOSO)
·~1.1;:"T<tl

United Construction
50 New Doha Port (NPPOS7)
Establishment - Sinohydro JV

WRAS
J.PPROVED PRODUCT Construction Development
Aspire Zone

51
Company

~
Mr. Omar Alfardan Residential Villas in LPC 22 to
25 @The Pearl Qatar

APPROVED

: > ·- ._... ,
;'-~ ~ ~

~ ~ :rt11ti!M:~H", .. u

Hepworth PME (Qatar) WLL

PO Box 50207, Mesaieed, Qatar Tel: 4476 0588 - Fax: 4476 0525- Doha Sales Office Tel: 4450 6810- Fax: 4450 6811
f.E0· 1An v-Sl.9 f.f.O• lA\· 0sD-!i h,9J.ll u~ y.A5:.o - f.f.Vl -oro tY-'51.9 tf.Vl •OAA 0_9JlJ3 _,hii. ~ 0·\"·V:y.,,;a
Email: [email protected] Website: www.hepworth.qa
Subsidiary of Corys Builcllng Materials Authorised, Issued & paid-up share capital QR.40,000,000

MAR 325 Rev.DO 218

You might also like