Lus Cp07c4c5c6 Ajp Mat Ir 00001 00 Lredc B
Lus Cp07c4c5c6 Ajp Mat Ir 00001 00 Lredc B
Main Haddad
Refer to PMCM and SC comments
28-10-2020
03/11/2020
02-11-2020
Sensitive
#
PROJECT: LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD CONTRACT NO and PROJECT NO.: 9469 / CP07C4C5C6
RCS NUMBER: LUS-CP07C4C5C6-RCS-MAT-IR-00001 REV.: 00 DATE: 28-Oct-20
ORIGINATOR: DORSCH TRANSMITTAL NO and Workflow No. / DATE: AJEQATAR-WTRAN-000609WF-000707
DOCUMENT NO.: LUS-CP07C4C5C6-AJP-MAT-IR-00001 REV.: 00 DISCIPLINE: IRRIGATION
MATERIAL SUBMITTAL FOR HDPE PIPE AND FITTINGS (LANDWORX TRADING &
DOCUMENT TITLE: DOCUMENT TYPE: MATERIAL SUBMITTAL
CONTRACTING)
To be filled by
To be filled by CSC/PMC/LREDC CSC/PMC/LREDC
Comment Codes;
To be filled by Contractor
For Compliance : Work can proceed subject to compliance with requirement
Open/Closed
Note : Note about reviewed Document
For Implementation : Work cannot proceed until comment is addressed
No. Initial Page / Section / Clause Comment Code CSC Comments Contractor's Reply Reply Status by Reviewer
Approval Status regards to any document shall not relieve the Contractor any of the obligation, risk or
1 AS Note liability under the Contract.
Item "C" in the attached Technical Data Sheet (Actual calculated values are 6.4 bar for PE 100 and 6.3
3 AS 3.3 Data sheet Note bar for PE80) is applicable for SDR 26 PE 100 PN 6 and SDR 21 PE 80 PN 6 .
Item "C" is not applicable for the proposed pipe HDPE PE 100 SDR 11 PN 16
The items mentioned in "5.2 Lead time delivery" are in imperial sizes but the proposed pipes are in
5 AS 5.2 Lead time delivery For Compliance metric sizes .
Contractor to ensure Compatibility of Proposed Pipe and fittings.
6 AS For Compliance Contractor to attach technical data sheet for the proposed fittings
Scope of work for proposed material is limited to Master Control Valve, Filtration & Flow Sensor
7 AS For Compliance Chambers and as per approved shop drawing.
Size of the proposed HDPE pipe and fittings shall be as per approved Shop drawing.
Page 1 of 1
Sensitive #
PROJECT: LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD CONTRACT NO and PROJECT NO.: 9469 / CP07C4C5C6
RCS NUMBER: LUS-CP07C4C5C6-RCS-MAT-IR-00001 REV.: 00 DATE: 28-Oct-20
ORIGINATOR: DORSCH TRANSMITTAL NO and Workflow No. / DATE: AJEQATAR-WTRAN-000609WF-000707
DOCUMENT NO.: LUS-CP07C4C5C6-AJP-MAT-IR-00001 REV.: 00 DISCIPLINE: IRRIGATION
MATERIAL SUBMITTAL FOR HDPE PIPE AND FITTINGS (LANDWORX TRADING &
DOCUMENT TITLE: DOCUMENT TYPE: MATERIAL SUBMITTAL
CONTRACTING)
To be filled by
To be filled by CSC/PMC/LREDC CSC/PMC/LREDC
Comment Codes;
To be filled by Contractor
For Compliance : Work can proceed subject to compliance with requirement
Open/Closed
Note : Note about reviewed Document
For Implementation : Work cannot proceed until comment is addressed
No. Initial Page/Section/Clause Comment Code PM/CM Comments Contractor's Reply Reply Status by Reviewer
The PMCM notes that the attached test reports in page 35 of the submittal are meant for another pipes. The
1 TS Page 35 For Compliance
contractor shall attached updated test reports for the proposed HDPE pipes as per the submittal.
The attached warranties from HEPWORTH and GEORG in page 44 and 45 are meant for another projects. The
2 TS Page 44/45 For Compliance warranty and guarantee shall be as per project requirement and shall be addressed to the client with project name
and contract code being mentioned on it.
The Water regulations advisory scheme letter in page 40 has expired. The contractor shall submit renewed copy in
3 TS Page 40 For Compliance
the next submission.
The contractor/manufacturer/supplier shall ensure that test certificates shall be provided with each delivery of
4 TS General Note
material.
HDPE piping system shall be installed as per manufacturer recommendations, project specification & approved
5 TS General Note
method statement.
Contractor to ensure the materials and test procedure shall conform to project specification, QCS and related
6 TS General Note
standards approved by the Engineer.
7 TS General For Compliance Physical samples for each HDPE pipes and fittings shall be provided for review and final approval.
No. Initial Page/Section/Clause Comment Code LREDC Comments Contractor's Reply Reply Status by Reviewer
1
A. Approved B. Approved with comments C. Revise & Re-submit D. Actioned
Document Review Status Code By LREDC:
E. Reviewed for Information
Page 2 of 2
PROJECT/CONTRACT REF: CP07C4C5C6 I 9469
LUSAIL DEVELOPMENT
DOHA, QATAR
DOCUMENT TITLE:
LUS-CP07C4C5C6-AJP-MAT-IR-00001 00
CONTRACTOR:
Issued for
19-10-2020 00 Corporate Quality
Approval
QA/QC Engineer manager Construction Manager Project Manager
Reason for
Date Rev.: Prepared Checked Checked Approved
Issue
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03
TAB LE OF CONTENTS
1. Checklist
2. SupplierNendor Info.
2.1 Supplier/vendor in the preferred Vendor list?
2.2 Commercial Registration
2.3 Trade License
2.4 ISO Certificate
2.5 Organizational Chart
2.6 Authorized distributor letter/Certificate
5. Sample
5.1 Samples & accessories.
5.2 Lead time delivery
5.3 Spare parts requirements
5.4 Recommended Spare parts
6. References
6.1 List of projects
1.0 CHECKLIST
MATERIAL SUBMITTAL CHECKLIST
Z. Supplier/Vendor Info.
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C - 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & D3
LUS-CP07C4C5C6-AJP-MAT-1R-00001_00 Page 4 of 26
after all valves' pressures have been adjusted.
3. Appendix
1. General Requirements
1.2. References
1.2.1. The following international standards shall be referred to for the supply, design and
installation of all lighting works:
a. IEC 364 Electrical Installations in Buildings
LUS-CP07C4C5C6-AJP-MAT-IR-00001_00 Page 5 of 26
d..clia.Jlg OJl;illl OJljg
Ministry of Commerce and Industry
111111111111111111111111111111111111111111111
000002694020943 ·UlJJpjl
• .. .. ~I... ..
,a.DJ 22901/1 :UlJ~I J+u>JI ,.cll'.>J
: ~J ~I Ci.o.JJJJ I po -~l.pl.'='1! uJgwn :UlJ~I ,ruoDI
13/02/2021 :J+u>JI .clinii I 2JJ u 25/10/2007 :J+w.11 .c Lilli I 2JJ u
0 :JLaJI u.ulJ c">J g:no C4,J gilu.o ub a5µl> :utigililJI ~I
po :oLlu.o.11 ~ h.il>.i :J+w.ll alb
0 :fg_µlll J.J.C
JlDiUI ulog!Ao
4760588 :JlaWI pl6Ji 50207 ::11.W I l9 g1iD
28282600432
25163400766
27225000382
Page 1of2
1/22901 ; J;i..wll ,.a.DJ
amber certifies that the above mentioned establishment has been registered
a.cl.i.a.Jlg . o~ 1·9
o~ UlJI ~
Ministry of Commerce and Industry
Page 2 of 2
1122901 : Ml p.g,
amber certifies that the above mentioned establishment has been registered
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C - 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03
I 1111111111111111111111111111111111
'
LUS-CP07C4C5C6-AJP-MAT-IR-00001_00 Page 7 of 26
HEPWORTH PME QATAR W.L.L
Mesaieed Industrial City - Light Industries Area,
P. 0. Box: 50207, Mesaieed
STATE OF QATAR
Bureau Veritas Certification Holding SAS - UK Branch cert{fies that the Management
System of the above organisation has been audited and found to be in accordance with
the requirements of the management system standards detailed below
Certificate No. ~90 U Version: No. 1 Revision date: 1411> November 2019
*
Vlnoth. K. P - Certification Manager
CeltificatJon body address
Local office: G1-G3, Ground Floor, KG Bullding
(Bldg. No. 194, Street No. 230), C Ring Road,
1.----------·1
5'1' Floor, 66 Prescot Street, London E1 BHG, United Kingdom
~,, •- I ,..... ·1 I
Oppo!lffe Guff Times, P. 0. Box: 22157, - ;, ~ l j'
(Doha) Qatar • 1 V
i UKAS, I
· ~ 1
I .... l
Fur1her clarifications regarding the scope of this certificate and the applicability of the management system
requirements may be ob!ained by consulting the organ!!lation.
To Check this certificate validity please cali: +974 40329729
Page 1 of1
HEPWORTH PME QATAR W.L.L
Mesaieed Industrial City - Light Industries Area,
P. 0. Box: 50207, Mesaieed
STATE OF QATAR
Bureau Veritas Certification Holding SAS - UK Branch certifies that the Management
System of the above organisation has been audited and found to be in accordance with
the requirements of the management system standards detailed below
ISO 14001:2015
Scope of certification
;¥~~v
VInOJr:K. P • Cettlflcation Manager
Certification body address S"' Floor, 66 Prescot Street, LQndon E1 BHG, United Kingdom
Local office: G1·G3, Ground Floor, KG Building
(Bldg. No. 194, Sfreet No. 230), C Ring Road,
Oppo$ite Gulf Times, P. O. Bolt: 22157,
(Oohs) QB1llr
Hiit
Further clarifications regarding the scope of this certifical!;! and the applicabilitY of the managementsystem __ _
roquiremenls lllllY be obl.ailleO by consulting the organisation.
To check this certificate validity please can: +974 40;l29729
Page 1of1
HEPWORTH PME QATAR W.LL
Mesaieed Industrial City- Light Industries Area,
P. 0. Box: 50207, Mesaieed
STATE OF QATAR
Bureau Veritas Certification Holding SAS - UK Branch certifies that the Management
System of the above organisation has been audited and found to be in accordance with
the requirements of the management system standards detailed below
$ ... v
Vinoth. K. P • Cettilication Manager
Certification body ¢dress 5"' Floor, ff Prescot Street. London E1 BHG, United Kingdom
Local office: G1-G3, Ground Floor, KG Building
(Bldg. No. 1!U, Street No. 2311), C Ring Road,
OpposJtfl Guff Timts, P. o. Box: 22157,
(Doha) Qafar
Page 1of1
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C - 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03
NA
LUS-CP07C4C5C6-AJP-MAT-IR-00001_00 Page 8 of 26
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03
letter/Certificate
Not Applicable
3. Manufacturing S
Technical Information
CGRTlf:ICATG HEPWORl'H
P.M.B. {QATAR) W.L.L.
This Is to certify that the following product supplied to the above customer are
manufactured and inspected to ISO 4427:2007 Standa.-·d and Company's
sseN1soeao1:2oos internal specifications and they are of QATP.R ORIGIN
CERT NO: FM 614004
SUPPLIED BY
:~
Bl> _ .• 1401-1:1998
specifications.
JOINTING
-- --~ ..
MOPE and HOPE (PE) pipes and fittings shall be manufactured from virgin
1 Comply
materials only. Recycled, re-ground or re-generated materials shall not be used.
,_
HOPE pressure pipes and fittings shall be manufactured tram material
conforming to polymer classification PElOO having a minimum required strength
2 value (MRS) of 10 MPa at so years and 20•C In accordance with ISO 4427. Comply
Design stress shall be 8 MPa. The pipe manufacturer shall identify the
manufacturer of the resin~ the resin type and classification.
-
The HOPE pipe material shall be certified as meeting the requirements of the
3 Comply
PE10o+ Association .
..__
HOPE pipes shall have a standard dimension ratio (SOR) of 11 unless indicated
otherwise by the Engineer and shall have a pressure rating of 16 bar (PN16) at
s 2o•c (de-rated to 11.8 bar at 40•C, in accordance with Annex A of ISO 4427 Part
Comply
1) unless indicated otherwise by the Engineer.
-
Pipes and fittings shall be designed to achieve a minimum working life of SO
6 Comply
years under all applicable loads, environmental and installation conditions.
- Pipes and fittings shall be homogeneous throughout and free of visible cracks,
9 Comply
holes, foreign inclusions, voids and other injurious defects.
~
3.10.2 Manufacture The resin trom wnicn tne pipes and fittings are manu1actured shall comply w1tn
10 the requirements of ISO 4427 Part 1 and be protected from UV attack by the Comply
~
addition nf ra•hnn black in accorda nce with the s"'ndard.
Straight lengths of PE pipe shall be supplied in standard lengths of 12m (·0/+50
mm) measured at 23'C ± 2'C. Unless otherwise specified, coll length shall not
exceed lOOm. Coiled pipes shall be coiled such that localised deformation is
avoided and the minimum internal diameter of the coil shall not be Jess than 20
11 x outside diameter. Prior to Jointing the degree of pipe ovality shall not exceed Comply
the permissible levels given in Table 1 of ISO 4427, Part 2 and the Contractor
shall, if required, use mechanical re~roundlog equipment to meet these
requirements. Field cut lengths of pipe used as closures may not be shorter than
0.75 metre Jn length and shall be approved by the Engineer.
- All pipes shall be Indelibly marked at Intervals of maximum lm. The colour of
the pipe marking shall always contrast with the colour of the pipe. Markings Comply
shall include the rollowine information:
(a) Manufacturer's name, trademark Comply
{b) Material and designation i.e. PE100 Comply
(c) The nominal pressure (PN) of the pipe/ fitting Comply
(d) Dimension of the pipe (nominal outside diameter x nominal wall
Comply
12 thickness)
(e) Standard Dimension Ratio (SOR) Comply
(!) Production period (date/ batch code) Comply
(g) International Standard to which the pipe/ fitting has been produced
Comply
to
(h) Designation of the medium for which the pipe is produced for (water,
comply
gas, sewage)
{i) Stencilled in legible letters the pipe identification number on the outslc Comply
umess otnerwJSe spec111co11y approvea ay tne tngmeer, a•1~t pressure p1pe
fittings for use with pipes of up to 355 mm OD shall be injection moulded with
the same polymer classification, material type and pressure rating as the pipe to
1 Comply
which they are to be connected. All joints between PE pipes and fittings shall
- 2
whenever possible be by thermal butt fusion welding or electro-fusion welding
'-·-·-·-
Connections of PE pipes and fittings to metallic fittings shall be made with PN16
backing rings with a stainless steel stiffener insert or as recommended by the
pipe or fitting manufacturer and approved by the Engineer.
Comply
,_ 3.10.3 Fittings All PE fittings shall, as a minimum, be indelibly marked with the following
Comply
Information:
(a) Manufacturer's name, trademark Comply
(b) International Standard to which the pipe/ fitting has been produced
Comply
7 to
LANDWORXS
..:.i"J_,\i.JI_, oJ.~..ll ui6J.J ~'i
1.ANDWORX TRADING & CONlRACTING W.LL
CR. 72958, P.0.BOX: 20185
COMPLIANCE STATEMENT
SPECIFICATION
Item Material Description REMARKS
REQUIREMENT
HOPE Pipe & Fittings
(c) Material and designation i.e. PElOO Comply
(d) The nominal pressure (PN) of the pipe /fitting Comply
(e) Outside diameter and Standard Dimension Ratio (SDR) Comply
(f) Production period (date I batch code) Comply
L~N~\~OP~s
. .~.J':J .j\1~\..) o.;4:\ll ~ .:u'i
.)J
LANDWORX TRADING& CONTRACTING W.LL
CR. "12956, P.O.BOX: 20185
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03
"'"' ~
.a
01
;:c
CD
~
0
~
0
Ploeseries
SDR6 5DR7,4 5DR9 5DR11 SDR13,6 SDR17 SOR 17,6 SDR21 SDR26 SDR33 5DR41
52,5 53,2 54 SS 56,3 SB 58,3 S10 512,5 s 16 520
+ PE80 PN25
-
PN20 PN16 PN12,5 PN 10 PNB PN 6° PN5 PN4 PN3,2
.,.. - -
PE100 PN25 PN20 PN16 I PN12,5 PN10 PN6e
(i) PNB PN5 PN4
+
Nom.
Size
16
20
25
"""'
3,0°
3,4
4,2
emox
3,4
3,9
4,8
"""'
2,3Cl
3,0°
2,5
2,7
3,4
4,0
em•
2,0e
2,3
3,o•
""""
2,3
2,7
3,4
e"'"
-
2.ot:
2,3
e-
-
2,3
2,7
"""'- """"
- 2,3
2,oe
-
Wall thicknesses •
e..., em• e,.,.. e"'"
-
""""
-
"""' """"
-
em•
-
e..,., e"""
::s!G)
32
40
5,4
6,7
6,1
7,5
4,4
5,5
5,0
6,2
3,6
4,5
4,1
5,1
3,0e
3,7
3,4
4,2
2,4
3,0
2,8
3,5
2,0t:
2,4
2,3
2,8
2,0•
2,3
2.3
2,7
-
2,od
-
2.3
- - - -
..,,m
zO
G>~
50
63
8,3
10,5
9,3
11,7
6,9
8,6
7,7
9,6
5,6
7,1
6,3
e.o
4,6
...
5,8
5,2
6.5
3,7
4,7
4,2
5,3
3,0
3,8
3,4
4,3
2,9
3,6
3,3
4.1
2,4
3,0
2,8
3,4
2,0
2,5
2,3
2,9
-
DLJ 12,5 13,9 10,3 11,5 8,4 9,4 D 5,6 6,3 4,5 5.1 4,3 4,9 3,6 4,1 2,9 3,3 -
~:!!
90
D1D
15,0
18,3
16,7
20,3
12,3
15,1
13,7
16,8
10,1
12,3
11,3
13,7
82 92
1
6,7
6,1
7,5
9,1
5,4
6,6
6,1
7,4
5,1
6,3
5,8
7,1
4,3
5,3
4,9
6,0
3.5
4,2
4,0
4,8
-- - --
- i Ill
mn
s::c
vim :;a
125
140
c;=i
20,8
23,3
26,6
29,9
23,0
25,8
29,4
33,0
17,1
19,2
21,9
24,6
19,0
21,3
24,2
27,2
14,0
15,7
17,9
20,1
15,6
17,4
19,8
22,3
...
11.4
,
12.7
16.4
12,7
141
16.2
18,2
9,2
10,3
11,8
13,3
10,3
11,5
13,1
14,8
7,4
8,3
9,5
10,7
8,3
9,3
10,6
11,9
7,1
8,0
9.1
10,2
8,0
9,0
10,2
11,4
6,0
6,7
7,7
8,6
6,7
7,5
8,6
9,6
4,8
5.4
6,2
6,9
5,4
6,1
7,0
7,7 .
-
-
--
200 33,2 36,7 27,4 30,3 22,4 248 182 20,2 14,7 16,3 11,9 13,2 11,4 12,7 9,6 10,7 7,7 8,6
225 37,4 41,3 30,8 34,0 25,2 27~ 20,5 22,7 16.6 18,4 13,4 14,9 12,8 14,2 10,8 12,0 8,6 9,6
250 4115 45,8 34,2 37,8 27,9 30,B 22,7 25,1 18,4 20,4 14,6 16,4 14,2 15,8 11,9 13,2 9,6 10,7
280
315
46,5
52,3
51,3
57,7
38,3
43,1
42,3
47,6
31,3
35,2
34,6
38,9
25,4
28,6
28,1
31,8
20,6
23,2
22,8
25,7
16,6
18,7
16,4
20,7
15,9
17,9
17,6
19,8
13,4
15,0
14,9
16,6
10,7
12,1
11,9
13,5 9,7 10,8 7,7
-
8,6
355 59,0 65.0 48,6 53,5 39,7 43,8 32,2 35,6 26,1 28,9 21,1 23,4 20,1 22,3 16,9 18,7 13,6 15,1 10,9 12,1 8,7 9,7
400
450
-. -
54,7
61,5
60,3
67,8
447.
50,3
49,3
SM
36,3
40,9
40,1
45,1
29,4
33,1
32,5
36,6
23,7
26,1
26,2
29,6
22,7
25,5
25,1
28,2
19,1
21,5
21,2
23,8
15,3
17,2
17,0
19,1
12,3
13,8
13,7
15,3
9,8
11,0
10,9
12,2
500 -- 55,8 61,5 45.4 50,1 36,8 40,6 29,7 32.8 26,3 31,3 23,9 26,4 19,1 21,2 15,3 17,0 12,3 13,7
550 - - -- 50,8 56,0 41,2 45,5 33,2 36,7 3t7 35,0 26,7 29,5 21.4 23,7 17,2 19,1 13,7 15,2
630
710
57,2
- .
63,1 46,3
52,2
51,1
57,6
37,4
42,1
41,3
46,5
35,7
40,2
39,4
44,4
30,0
33,9
33,1
37.4
24,1
27,2
26,1
30,1
19,3
21,8
21.4
24,1
15,4
17,4
17,1
19,3
800
900 .- - -
.- -
- 58,8 64,8 47,4
53,3
52,3
58,8
45,3
51,0
50,0
58,2
38,1
42,9
42,1
47,3
30,6
34,4
33,8
38.3
24,5
27,6
27,1
30,5
19,6
22,0
21,7
24,3
1000 - 59,3 65.4 56,6 62.4 47,7 52,6 38,2 42,2 30,6 33,5 24,5 27,1
1200
1400
- -- - - - - - 57.2 63,1 45,9
53,5
50,6
59,0
36,7
42,9
40,5
47,3
29,4
34,3
32,5
37,9
1600 - - . - - - 61 .2 675 490 540 39 2 433
a PN values are based on C =1,25.
b Tolerances In accordance with grade V of ISO 11922·1: 1997[1).
ccAe1ualcaleulated values are 6.4 bar for PE 100 and 6,3 bar for PE 80.
d The calculated value of emln nso 4065 12U Is rounded uo to the nearest value of either 2.0 2,3 or 3,0. This is to satlltv certain national requirements.
~
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03
Inhalation During the butt fusion operation, molten PE is lonned. This should not
Inhalation of PE dust can irritate the respiratory system. Wherever be allowed to come into contact with the skin as it will adhere strongly
possible, when cutting or scraping PE pipes, operatives should work in and cause severe burns. Protective gloves should be worn during the
the open air or in well-ventilated areas. jointing process and when cleaning the heater plates of the welding
machinery.
Physical Contact
Polyethylene is not regarded to be a skin irritant. During the electrofusion process, care should be taken to prevent the
ejection of molten material from the joint area. Protective clothing,
When cutting or scraping PE pipes or fittings, PE dust particles may including gloves and safety eyewear, should always be worn during the
cause eye irritation and it is recommended that protective eyewear be jointing process.
used.
Disposal of Waste Material
Fire Hazards Surplus or waste polyethylene material can be reprocessed i.nto new
Polyethylene burns but is not classified as Ramrnable. It has a Hash pipes or other products. Alternatively, it can be used as landfill or
point of 360'C approximately. incinerated, dependant on local regulations. Proper combustion does
not require special exhaust control technology.
Above 300'C, PE will degrade to produce carbon rnonoXJde, water and
small amounts of various hydrocarbons and aldehydes. The Environment
Polyethylene is not considered dangerous for the environment
Avoid the accurnrnulation of PE dust particles as they could give a
potential risk Of dust explosion. FimAld
The following are recommel'ldations for immediate first aid to be
AU electrical equipment in the area should be carefully sited and applied in the event of an accident involving polyethylene products.
earthed. However, qualified medical attention should be obtained as soon
as practically possible.
In the event of fire involving PE materials, apply water in a spread jet
Dry chemical, foam and carbon dioxide can also be used. Ingestion: Wash mouth out with water
- Hepworth
MAR 325 Rev.OD
+GF+ GEORG FISCHER
PIPING SYSTEMS
56
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & D3
~
f......, 6 1.460 0.970 I.COO I.COO 6 1.050 D.4-00 I.DOD I.ODO Project No: 14.33008.00
8" 5.31 2.67 1.46 D.46 8 2.510 UDO I.ODO 1.200 8 1.770 0.400 I.DOD 1.200
lil..LlllOUlOIO
=~a~: .Hl.OC!Cic..JNSl
PR01EC1FWNC•JTHOQl8.£MIAP
1£AVTillll'rPO•.T£!H.!l((Sfl!:EllllO
Area of Concrete (sq.m.)
Pipe Dia
1"
3"
4•
TEE
D.137
D.294
0.486
9{)0
D.19
D.42
0. 69
45°
0.11
D.23
0.37
22.5
O.D5
0.12
0.19
° 11.25
D.D6
D.10
O.ID
° Pip&Dia(' )
4
2
J
A(mtr.)
0.250
0.440
0.650
45 o ELBOW
B(mtr.)
0.250
0.300
0.350
C(mtr.)
D.45D
0.52D
0.570
D(mtr.)
0.500
0.700
0.700
II
HOK London
Outi&,90W'1i!ield51rvet
loMon.W1HEZ,U
1+44!0)2075362006
HOK Dubai
HflolerTaweia,SZR
o..illtl, U.1.EPOBc».2'437
/+971(CJ•lB2681la
lw..l(t)21171i$51S1!7 f+971 (1)J43!2 611to
0.4 ) 6 1.000 0.400 0.800 1.000
6" 1.050 1.48 D.BD 0.20
(i:') TtflUST BLOCK ARRANGEMENT: TYPfCAl Pl.MS & SECTION
11o11o LL
6" t. 770 2.51 1.36 0.69 0.35
8 1.240 0.550 I.ICC 1.200 ~D~
--~.,....,.. ....--.9-•:>. ........
FounlalnsDln=ctUd .
.-21.T~Cl)o.AwDW.r.-..d• _ _ P_
:;e,~F-.s...,.,.,
©
NO I DESCRIPTION
I BUITERFLYVALVE
·-·
101,AIZ•_,,.Uuildloi,Abu _,,. .... H<ilR<M""UAli
ut1.111<o<......,.1<a•. 1...-s1i1SNW.U"
='.!."~~- ..... ~
Y.sTRAIER ~·
=:...,..__T-.-•""'1.
PRES&lAERElllJam IMST£R VM.~ WSPIParsoo • ~ft
SY-l'ASSVAl.VE
~~~~~Ollc.ot-.•- ... 2 -
AUT0ClEANDLSCFlTERS(S)3'dili
t#.NHOLECOVERWITHFAAME
FLr:JNSENSOR
LAOOER-ftSTAl.lEDASPERlOCM.COOE{S)
ll>PEPIPE(SCZEASPER~~ELAYOUTOAAWllGS)
~EJ~i .. ""--
SECTION
~• ..W...,.jt>y: SBG
Draw"Oa,.:18/05/2017 Sct111@..,1· 1:100
MD TES Scti•@A3 1;500
Prej.c!Nc: 14,33008,00 (Apptel<.~
1S!ZfSQf!UITEAFLYYALY!,BYPmv~LYl.Y ·SflWllER.PR(SStrRERE!ll(fjliMAiU.mVt:.FlO\llS(NSQR
IRRIGATION
MASTER CONTROL VflJ..VF., FILTERATION & FLOW SENSOR CHAMBERS (4' DIA) INSTALLATION DETAILS
EXISTING DISTRIBl!TION CAHl.1BER ~ ~KlATION NETWORK MAIN (DONE BY OnlERS)
_ _______
PACKAGE CP07-05
.............. ...... ""' .,
IR60005 00
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03
LUS-CP07C4C5C6-AJP-MAT-IR-00001_00 Page 16 of 26
Hepworth
1$04427-1:2007 4.4 Tablc-1 Melt Flow Rate Tile MFR or the compound shall nol 02270 110mins
IS01133
OCS 2014 Section 8 Part3 Teble1 da~a1e by more than+/. 20 I)~ (3.18%. Passed)
IS04427-1:20074.4 Tabl ..1 Densl!Y(R') ISO 1183-2 ~ 0.930 gm/an' 0.959gmlcm' i Passed
1504427-1:20074.4 Tabl ..1 60 Minules; Passed
Thetmal Stability 15011357-6 >20Mlnutes
QCS 2014 Section 8 Pan3 Tablo1
1$04427-1:2007 4.4 Tablo-1 Carbon Sleck (R") 1506964 2.25 •I· 0.25 % 2.40%; Pe5'ed
~~·~1 ...
1504427-2:2007(6.2)
Ovalft)' lfolurances 15011922-1 Max.11.1omm Ova~ty-4.00 mm Passed
QCS 2014 Section 8 Parl 3 Teble2
As stipulated in lhe
1504427-2:2007 (6.5) Longlh ordor
12Mu Passed
IS04427-1:2007 4.4 Ta!>l .. 1 Mell Flow Rate The MFR of the compound shall ool 0.227g /tOmtn•
1$01133 de\oia1e by moro lhan -+/· 20 % (3 . 18~, Psssed)
QCS 2014 Sac1ion s Part3 Tabla!
1504427-1:2007 4.4 Table-1 Oanslly (R") 1$01183·2 <t. 0.930 gmttm' o.959gm/cm>; Passed
1504427-1:2007 4.4 Table-1 SO Minutes; Passed
Theimol Slabdlty 16011357-6 :>20 Mfnute::s
QCS 2014 5eotion 8 Part3 Tabfo1
1504427-1:2007 4.4 Table· I Carbon Blaok (R"] 1$06964 2.25 ·~025% 2.40%: P;::issed
PfOdud t S
(~)
QCS 2014 SecUan 8 Part 3 Teble2 ITo!erancus 15011922·1 Max. 251.SOmm 250.78 rnm: Passed
.o!Jt'll'PJ4Jl.ce o~ ' t
·!""Hepworth\
a
~ ',~ ~-
/
,;
1504427-1:2007 4.4 Teblo·I MettAov1Rate The MFR ol \tur c;:ompcund shall nol 0.227g n0m1ns
1501133
QCS 2014 Section a Pa113 Tabl•1 de~alB by more lhan ... 1--20 % (3.18%, Passed)
1504427-1:20074.4 Table·! Oensily (R') 150118'1-2 ~ 0.930 gmlcm3 0.959gm.len1'; Passed
1504427-1:20074.4 Table-I
Thcnnel Slablily 15011357-6 >20 Minutes 60 Minulcis; Passed
QCS 2014 Section 8 Parl3 Table!
P-•~• 1..1
1504427-1:20074.4 Table-1 Mell Flow Rate The MFR of lhe compound shall not 02279/\0mins
1501133
OCS 2014 Seclion B Part3 Teble1 de\iate by moro lhan +/-20 % (3.18%, Passed)
1504427-1:2007 4.4 Tabl&-1 Oens/ly(R') 1501183-2 2 0.930 gm/cm 3 0.959gm/c.m11 : Passod
1504427-1:20074.4 Table·1
Therms1 Stabirity 15011357-6 > 20 Minutes 60 f-A!nules; Passed
OCS 2014 Section 8 Part.3 T;ble1
1504427-1:20074.4 Teble-1 Carbon Blaol< (R') 1506984 2.25 +/- 025 % 2.40%; Passed
Product e"•~
The Internal and eX1emsl surface shall
1504427-2:2007 (5.1) be smooth. dean and free from staring,
Visual Inspection 1504427 Passed
QCS2014 Section 8 Pan 3 Table 2 ca\1Ues and sul'face defects which may
aKact plpo petfonnance
As slipula!ed In tho
1504427-2:2007 (8.5) Length 12M~ Passed
order
1504427-2:2007 8.2 Table-5 Tllennel 5labitty 15011357-6 >2D Minutes 60 Minutes: Passed
1504427-2:2007 8.2 Tabla-$ The changa in MFR caused by 0.220gl10mins
MellFtowRato 1501133
QCS 2014 Section 8 Pert 3Teble 2 processing aha I not be morD lhiln 20% (4.34% ;Passed)
Elongallon at break >350% 750%·; Passed
1504427-2:2007 8.2 Table-5
1506259
QCS 2014 Section 8 Part 3Table 2
Tensie S~anglh @ Vlelcl ~19Mpa 2i<l Mpa, Passed
..,._.·
TO WHOM IT MAY CONCERN
Product : 125mm HOPE PE100 SDR11 PN16 Black Polyethylene Pipe
Batch No. : WK· 10YR·18Shift: AIB
Material : P901BK/171206002
Standard : ISO 4427:2007/ QCS2014
Country of Origin : State of Qatar
Warranty : 365days from the date of delivery of materials to your project site
Certificate Status : Sample
Issue Date : 14.03.2018
~
!SO & OCS Clause No Operation ar Tes! Requiiemenls Tesl Resulls
Method No.
1804427-1:2007 4.4 Table-1 MellflQ\\IRsl!t The MFR of Iha compound snail not 0.227g /10mlns
1$01133
OCS 2014 Secdon 8 Part3 Table1 de..Cata by m0<e than -+/-20 % (3.18% ,Paased)
1506964
>2DM!nul0&
225 +/-0.25 %
60 Minul•s: Passed
2.40%; Passed
w APPROVED
1504427-2:2007 (5.1)
QCS2014 Section 8 Par! 3 Tobie 2
1504427·2:2007(6.2)
Visual Inspection
Outaide Diameter
1504427
150t6H
The lnlemal and eldemaJ 1urfece shall
be smoolh, chsan anti free fl'om 'toting,
cavitia& end suttace defects which mPy
arrect pipe performance
Min. 125.00 mm
Pa:ned
00 Obserwd
QCS 2014 Section 8 Part 3 Table2 /Tolerances 15011922·1 Max. 125.80 mm 125.28 mm, Passed
1504427-2:2007(6.2)
QCS 2014 Sociion 8 Pert 3 Tabla2
Ova!ity /Tolerances 15011922-1 Max.2.SOmm Ovaliy-1.10 mm Passed
As stipulated In
1504427·2:2007 (6.S) Lenolh lhaorder
12M~ Passed
The material referred to in this letter is suitable tor contact with wholesome water for domestic purposes having met the
requirements of 856920-1 :2000 and/or 2014 'Suitabilily of non-metallic products for use in contacl wilh water intended for human
consumption with regard to their effect on the quality of lhe water'.
The reference relates solely to its effect on the quality of the water with which it may come into contact and does not signify the
approval of its mechanical or physical properties for any use.
'Hepworth PESO & PE100' pipes. Black coloured or blue coloured PESO or PE100, extruded polyethylene pipes. For use with
water up to so•c.
An entry, as above, will accordingly be included in Iha Water Fittings Directory on-line under the section headed, "Materials which
have passed full tests of effect on water quality".
Yours faithfully
Jason Furnival
Approvals & Enquiries Manager
Water Regulations Advisory Scheme
""""""""""",.,,......................................."""._____........____________________.........................................................._
The Waler ReQIJ!ations Advisory Sdleme Lid. Reaistared ln England NO, 06663930 Registered offJCS: 60 Loviici< Closs, Haud Grow, Sla<kport, SK7 5ED
Tcl:+44(0)333 207 9030 Fax:+44(0)1495 248540 Ema»:lnfo@m;ts.c.o.uk websile~v.wms.co.uk
MAR 325 Rev.00 111
WRAS MATERIAL APPROVAL· MATERIALS WHICH HAVE PASSED FULL TESTS OF EFFECT ON WATER QUALITY
The material referred 10 in this letter is suitable for contact with water for domestic purposes. Approval of this material does not
signify the approval of Its mechanical or physical properties for any use.
Manufacturers or applicants may only quote in their sales literature terms which are used in this letter, namely that; 'the material
as listed, having passed the tests of effect on water quality, is suitable for use in contact with wholesome water'
This may be abbreviated to 'Water Regulations Advisory Scheme· Approved Material' or 'WRAS Approved Material'.
The scope of an Approval does not extend to rebranded materials unless otherwise agreed by the Scheme.
Approval holders may use the WAAS Approved Material logo and make reference to any approval issued by WRAS Ltd. in
respect of a particular material or range ol materials provided the approval is, and remains valid.
Approval holders are entitled to use the logo on the packing, promotional literature and point of sale advertising Approved
Materials.
II is a condition of WAAS Material Approval that NO changes or modifications to the Approved Material, be made without the
Approval Holder first notifying WRAS Ltd. Full details of the proposed changes must be provided to the Scheme. Failure to
comply with this condition will immediately invalidate a previously granted Approval.
Re-Approval
WAAS will write to you 1 year before the approval expires asking whether you would like to renew it. Please complete the
relevant section of the MA3 application form which will be included with the letter and return to WAAS (via e-mail or post).
Please note it is the responsibility of the Approval Holder to ensure the Approval remains valid. WAAS Ltd. accepts no liability for
1he delay in granting approval where this is caused by circumstances outside of the Scheme's control.
Th• Water Rogulations llcMSOf)' Scheme Lid. Regls1..-ed in England No, 06863930 Regislsrod olfice: 60 Lowick Closi>, Hazel G!OVV, SIOCkporl, SK7 5EO
Tel:+-44(0)333 207 9030 Fax:+44(0)H95 248 S40 Email:lnlo@,.,ras.co.uk wtbsne>W11v.wras.co.uk
MAR 325 Rev.OD 112
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03
3.7 Guarantee/Warrantee
HEPWORTH
P.ME. (QATAR) WL.L.
Kind Attention,
Our Reference;
Sample Warranty Certificate for Submittal
Product:
~ 25mm HOPE PE100 SDR11 PN16 Black Pipe
~ 32mm HOPE PE100 SDR11 PN16 Black Pipe
~ 40mm HOPE PElOO SOR11 PN16 Black Pipe
~ SOmm HOPE PE100 SDRll PN16 Black Pipe
~ 63mm HOPE PE100 SDR11 PN16 Black Pipe
~ 90mm HOPE PE100 SDR11 PN16 Black Pipe
Hepworth PME (Qatar) WLL hereby warrants that the Products manufactured and supplied to
the Buyer are manufactured to the appropriate specifications and for the use intended.
Hepworth PME (Qatar) WLL further warrants that the Products shall be free from manufacturing
or workmanship defects. The warranty shall extend for a period of 400 days from the date of
project completion (Testing, Commisioning and final acceptance from the consultant
/client/local authorities) to your project site. Hepworth PME (Qatar) WLL liability hereunder is
limited to the replacement cost of the defective products and does in no way cover labour or
installation charges or any other charges whatsoever. Hepworth PME (Qatar) WLL shall, in no
event, be held liable for indirect or consequential damages sustained by the Buyer.
Thanking you
Louai Al Nazer
Head of Quality Assurance
PO Box 50207
Mesaieed
I Mesaieed
Tel 4760588
Doha
Tel4506810
;....Jolll
£<>,,1;1.~
I
Qatar Fax 4760525 Fax 4506811 to·''" 1 u-Sli
www.hepworthpme.com.qa [email protected]
Georg Fischer Piping Systems Ltd. hereby confirms that the PE-100 fittings, produced and
supplied to the above project are manufactured to the appropriate specifications and for the use
intended. Further warrants that the Products shall be free from manufacturing defects. The
warranty shall extent for a period of 400 days from the date of receipt of materials to the above
project site.
Georg Fischer Piping Systems Ltd. states that our liability hereunder is limited to the replacement
cost of the defective products and does in no way cover labour or installation charges or any other
charges or damages what so ever to other services and applications surrounding the intended
products, and at the same time not be held liable for indirect or consequential damages sustained
by the Buyer.
Husein Yusuf
Technical Sales Manager
Georg Fischer - Qatar
GEORG FISCHER
+GF+ PIPING SYSTEMS
HEPWORTH PME ( LLC) is accredited to BS EN 9001 :2008 by the "-. an opti mum process organisation
British Standards Institution. We also maintain several BSI
Kitemark licences Strict quality control procedures are routinely "-. a certified quality management system in
conducted throughout the production process to ensure that our accordance with ISO 9001 :2008
products are fully compliant with the relevant specifications. We
~ established active continuous improvement
are audited on a regular basis by British Standards inspectorate
processes ( CIP ), which utilize the knowledge
including testing of samples in their UK facility to further ensure
and experience of our staff
that we are operating within the scope of our Kitemark licences.
Measuring and test instruments used in our Dubai laboratory are ~ a continuous evaluation and improvement
routinely verified and are traceable to International Standards. Our of our Personel Management System.
commitment to quality control thus serves to assure the client
that our products are of the highest quality and provide an
excellent service life.
- Hepworth +GF+
MAR 325 Rev.00
GEORG FISCHER
PIPING SYSTEMS
17
Polyethylene pipes, according to ISO 4427 and ISO 4437 are A wide range of both standard and bespoke fabricated fittings
extruded in our factories both in Dubai, UAE and Doha, Qatar with diameters of up to 1200mm are produced in our factories.
with diameters ranging from 20mm to 800mm SDR's (Standard Our design team can offer solutions for specific piping applica-
Dimensional Ratio l* of SDR 1t and SOR 17 are the most tions in situations where the use of a standard fitting is not
frequently requested specifications we can also produce SDR 9 practical or possible. We have a wealth of experience in designing
< 20 bar l, SOR 21 < 6 bar l and SDR 26 <5 bar), Black and bespoke fittings which can overcome many on-site application
blue colours are available for water applications whilst yellow is problems. Please contact our Technical Department for further
commonly used for gas. Pipes can also beproduced with colour information or assistance.
coded stripes to suit various applications. For pipes of other SDR's,
diameters and colours, please contact our Technical Department.
Pipes can be supplied as cut lengths or, for diameters up to
t 25mm, in coiled form.
PESO Pipes for above and below ground use, u.e.industrial uses and various 16mm-800mm ISO 4427:2007
other applications below ground, e.g. sewerage and pumping mains>
PE100 Pipes for above and below ground use, Ci.e.industrial uses and various 16mm-800mm ISO 4427:2007
other applications below ground, e.g. sewerage and pumping mains)
~ ~
APPROVBJ KITEMARK
- Hepworth
MAR 325 Rev.OD
+GF+ GEORG FISCHER
PIPING SYSTEMS
19
Fabrication Division
PE pipes from manufacturers bearing the BSI Kitemark have been type tested
In our fabrication factory in Dubai, we are able to produce an extensive by the British Standards Institution and this is therefore an assurance that the
range of standard and bespoke butt-welded fitting to suit almost any product complies with the relevant standard ISO 4427 and EN 12201 are for
situation. Our strength is in our ability to design bespoke according to PE pipe intended to be used for the conveyance of water under pressure for
dient's requirements for situation where a standard fitting is simply not general purpose, as well as for the supply of drinking water. Fittings should
suitable. Using a wide range of Georg Fischer butt-fusion workshop also have internationally recognized approval.
machines our trained technicians can produce the necessary fitting in If PE pipes are to be used above ground they should be protected against UV
Dubai - fast. Each butt-welded joint is supplied with a certificate of light in accordance with recommended practice.
traceability confimning that the joint has been processed according to
specification. Traceability extends as far back as the batch number of Polyethylene Fusion Equipment
virgin material used in the production of the original pipe extrusion.
This ensures that the client can be confident about the integrity of the Machine Hire
joints and ability of the fitting to perform. In certain cases it not always viable for a clients to purchase Butt-fusion or
electro-fusion welding machines. HEPWORTH PME CLLO offers one of the
Manufacturing Standards region's rental PE welding machines, the expertise to maintain and calibrate
such and the ability to provide certified training to dient's Engineers either on
HEPWORTH PME <LLO operates a Quality Management System site or in the purpose of built training school in Dubai. Where necessary
Aocredited to BS EN ISO 9001 :2008 certified by the British Standards HEPWORTH PME <LLO can also supeivision to ensure that all jointing is
Institution. Polyethylene pipes for water supply are manufactured executed according to specification avoiding costly remedial work as a result of
according to ISO 4427 and are also covered by two British Standard poor welding techniques. Regular in-house training courses are offered for
Kitemarks Licences for all sizes and SDR's our production capability. For larger groups of engineers, each of whom will receive certification upon
gas applications we produce BS Kitemarked pipes according to ISO 4437 achieving required standard.
and if required, we can Supply according to the British Gas pie standard
PL2.
A Note to Specifiers
20 -
Minimum Required Strength <MRS> PE100 Pipe S)l$lems
A high perfonnance PE100 polyethylene pipe material for use in
Polyethylene pipes and fittings materials are evaluated by their underground potable water and gas mains. The new material's
Minimum Required Strength <MRS>. higher pennissible design strength (PE100 - SMPa: PE80 - 5MPal,
together with its superior toughness, allows the design engineer to
When PESO pipes are hydrostatically tested at 20t:, ISO 1167 use PE100 pipes at substantially higher operating pressures than
specify a Minimum Required Strength at SO years of SMPa (SO PESO pipes with equivalent SOR rating.
daN/cm2) - MRSSO.
In addition to their superior qualities, PE100 also has greater
When PE100 pipes are hydrostatically tested at 20t:, ISO 1167 resistance to rapid crack propagation. PE100 pipes are supplied for
specifies a Minimum Required Strength at 50 years of 1OMPa working pressures up to 16 bar for underground potable water and
Cl 00 daN/cm2> - MRSl 00. 10 bar for gas mains.
Design Stre$$
The design stress for PESO pipes is 6.3MPa. The design stress for
PE 100 pipes is S MPa.
-1Q... =SDR 11 All pressures based on 50 year design life at 20 "C Averoge Temperature
S.2
The SDR of a 90mm, 1O bar rated, PE100 pipe is:- Table 1-SDR and Maximum Rated Working Pressures
-1Q... = SDR 17.6
5.1
Pressure Rating
The pressure rating of polyetllylene pipes is generally referred to in
'bar', where 1 bar equals 10.2m head (approx>. Table 1 gives the
pressure rating and SOR of both PESO and PE100 pipes.
- Hepworth +GF+
MAR 325 Rev.DO
GEORG FISCHER
PIPING SYSTEMS
23
Typical Physical Properties
PE 100 - Physical Properties
Table 3 shows typical physical properties of both PESO and PE100
In addition to the quoted properties of PESO, PE100 pipe has enhanced
polyethylene raw materials.
toughness, higher pennissible design strength and improved resistance
to rapid crack propagation. PE100 pipe offers the water engineer
PESO - Physical Properties
substantial benefits in efficiency and economy.
The physical properties of pipe produced from these compounds
combine the flexibility and toughness of low density polyethylene
and the strength and rigidity of high density to give a highly
durable pipe eminently suited for the distribution of potable water
and gas under pressure.
PE proirerties !reference values>
PESO PE 100
Characteristics Value Value Units Test Standard
Densily 0.93 0.95 g/crn' EN ISO 1183-1
Yield stress at 23 •c 18 25 N/mm2 EN ISO 527-1
Tensile e-modulus at 23 •c 700 900 Mlmm1 EN !SO 527-1
Charpy notched impact strength «l 23 •c 110 83 l:.Jlm' EN ISO 17~-111 cA
Charpy notched impact strength at -40 •c 7 16 kJ/ mz EN ISO 179-1/leA
Ball indentalion hardness (132N> 37 MPa EN ISO 2039 .1
Crystallile melling poinl 131 130 'C DIN S1007
Thennal expansion ooefficient 0.15 ... 0.20 mm/mK DIN 53752
Heat conductivity at 23 ·c 0.43 0.38 W/mK F..N 12664
Waler absorption at 23 "C 0.01 - O.Q4 % EN 150 62
Colour 9005 RAL
Limiting oxygen index <LCD 17.4 % 1504589-1
General Properties
The properties of polyethylene have been described as:
.,.. Light and easy to handle ...._ Systems can be fully end-load bearing
,..., Conveniently flexible .,... Resists cracking
..._. Good fusibility -... Non corrodible
.,.. Tough ...._ Resistant to chemical attack by aqueous media
.... Strong ..... Low frictional resistance,
Strength
The "strength" of a pipeline may be considered as the ability to A safety factor is applied to the MRS to determine the Hydro-
withstand Choop) stress in the pipe material under internal pressure static Design Stress { HOS >. Recent European practice has been
over a prolonged period of time. The design stress considered the to specify the ISO minimum safetyfactor for PE of 1.2S for buried
is taken to be a life expectancy in excess of SO years. water applications 2.0 for buried gas applications and 1.6 for
aboue ground non gas applications. PE pipes are not
The stress/life characteristics are obtained by a standard universally recommended for above ground gas applications
accepted test procedure, regression curve prediction. The
regression curve shows the performance ability of the material Using these analyses, the predicted minimum failure stress of
under a specified load for a design life in excess of SO years. PESO material is 8.0 MPa - < based on the extrapolated SO year
97.5% LCL stress value at 20t: ). Figure 1 gives a regression
The strength of polyethylene is known to be time/ temperature curve <or series of data points ) for a material at 20'C.
dependent. This characteristic is used to assess the future available
strength of the pipe material by generating regression curves from The predicted minimum failure stress of PE 100 material is
varying stress/life to failure tests at higher temperatures than 10.0 MPa. With a design co-efficient of 1.2S, the design stress of
that normally experienced in distribution mains. These prolonged this material is 8.0.
tests, in excess of 10,000 hours, are accelerated for quality control
purposes by using elevated temperatures ( typically sot: l.
" "
. •100
' •8,0
,..
TIME tHOIJRS.1 Cog scMd
'" .
figure I-Regression Cwves for PESO Materiols at 20'C Figure 2-Regressiotl Curves for PEIOO Materials •I 2o•c
- Hepworth +GF+
MAR 325 Rev.DO
GEORG FISCHER
PIPING SYSTEMS
25
Hepworth
CONTENTS
1. Introduction
2. Specificat ions
6. Jointing Method
7. Installation
UV Degradation
PE pipe is subject to a degree of degradation when exposed to PE is basically intended for use in buried conditions unless
excessive ultra violet light <sunlight). UV stabilisers (ant~oxidantsl protected from prolonged sunlight exposure. This is reflected in the
are used in the manufacture to counteract this effect and such current recommendation to provide protection when used in
material has withstood practical exposures for periods in excess of above-ground situations or when stored outside for periods greater
a year without apparent deleterious effects. This surface degrada- than one year.
tion has a particular impact when using fusion jointing techniques
and leads to recommendations for the peeling of the surface of the
material prior to jointing.
Hydraulic Properties
The smooth bore of PE pipes enables them to be treated as for the purpose of calculation of flow rates in NEW pipelines the
"hydraulically smooth" when used for the conveyance of potable Colebrook-White formula may be used in which the value of the
water. The smooth surface discourages the formation of scale in hydraulic roughness factor Ks is 0.003mm for dean water.
hard water areas but particular waters may, at certain times, give
rise to slime and silt deposits associated mainly at joints or fittings
which may increase frictional losses.
- Hepworth
MAR 325 Rev.00
+GF+ GEORG FISCHER
PIPING SYSTEMS
28
Although principally developed for conveying water and gas,
polyethylene pipes have many other applications, some of which
are:-
C1lSewage pumping mains, where the materials resilience provides
excellent resistance to the surge pressures generated by continuous
pump starting and stopping.
<2l Slurry conveyance in quarries, mines, etc. In this application, PE
pipes provide superb resistance to abrasion. When comparing PE
pipes with conventionalpipes used for slurry applications, consider-
able increase in lifetimes can be achieved.
(3) Fire mains FM Approved piping systems offer safe, secure and
correction free solutions for underground fire fighting mains.
(4) Chilled Water
(5) Demineralised Water
(6) Industrial/Chemical applications
(7J Submarine pipelines
(8) Rehabilitation of existing pipelines by relining
(9) Compressed Air Lines
(1 Ol Vaccum Sewage
(I 1l Telecom Applications
0 2l Ship Building
(13) Irrigation
(14l Sea Water Intakes
(15) Aqua and Marine Parks
(16) Potable Water
C17l Cable Duct
Review of Current Position The properties of PE make such pipelines particularly suitable for
PE80 and PE 100 pressure gas and water mains are inert flexible, areas subject to ground movement due to seismic forces, mining
lightweight and have the required structural strength without being subsidence, compaction of filled sites or the disturbance caused by
brittle. They are suitable for use where ground movement is expected, the activities of other utilities in the vicinity.
where corrosive soils are present and where long ducts and flexibility in
bending are required. They appear to withstand surge pressures better Where PE 1s to be used in environments with temperatures greater
than PVC-U pipe and to be even more resistant to freezing because of than 20'C the allowable operating pressures should be reduced in
the improved thermal insulation properties. accordance with !he manufacturer's recommendations.
Fusion welded PE piping systems resist axial stresses arising from Corrosive ground (e.g. ground with low pH or high sulphate
thermal or pressurisation effects, except at the transition points to non characteristics) has little or no effect upon PE but all metal fittings,
end load bearing pipe systems. Thrust bloks and anchorages need only anclllaiy equipment, bolts, etc., should be carefully protected in the
to be considered in thise cases. normal way.
Both PESO and PEl 00 pipes allow the use of many modem no dig Contaminated ground, however, must be considered carefully. PE is
techniques. resistant to many chemicals, but is vulnerable to petroleum products
and certain solvents; where concentrations of such contaminants exist
Environment PE should NOT be used unless suitably protected. Where any doubt
PE pipes are normally joined using fusion techniques. Butt fusion exists soil sampling should be undertaken and specialists advice
jointing is usually carried out above ground and after cooling; long sought.
lengths of pipe are snaked into the trench.
Where the natural ground water table is high, or the construction
Fusion jointing using the electrofusion jointing technique may be trench is liable to flooding, special consideration should be given to
carried out at the trench bottom, but care must be taken to keep !he possible flotation of the pipe. This particularly applies to the large
jointing surfaces dean and dry. diameters where special anchoring or weighting may be necessary
prior to the backfill being installed.
The sub surface material to be excavated should be assessed for its
suitability as selected backfill material. i.e., free from large sharp stones,
heavy clay, etc. If the material is unsuitable for bedding and surround to
the pipe !hen imported material should be utilised and the surplus spoil
removed from site.
Operating Conditions The DYNAMIC loads normally considered during operation are the:
Both the static and dynamic loads to which the pipe system is likely to
be subjected should be considered with care. However variations or internal cydic loading e.g., surge associated with pumping
pressure due to demand seldom warrant special design consideration regimes or the rapid dosure of valves;
with regard to !he pipe material. Pipe systems designed with the
relevant safety factor take account of occasional deviations from the external cydic loadings due to traffic conditions.
maximum rated pressure. These occas10nal pressure excursions within
conditions reflected by the safety factor are therefore acceptable. Further
advice should be sought from Hepworth P.M.E Technical Services.
- Hepworth
MAR 325 Rev.00
+GF+ GEORG FISCHER
PIPING SYSTEMS
30
Design for Surge and Fatigue External Dynamic Loading
When considering applications where surge transient pressures may For external dynamic loading conditions the use of PE pressure mains
occur, polyethylene pipes exhibit significant advantages. The relatively under MAJOR CARRIAGEWAYS is dependent on the type of trench
low material modulus for polyethylene means that, for a given change bedding conditions.
in fluid velocity, the surge transient pressure induced will be
approximately one third of that induced in ductile iron pipes. In Experience has shown that if the PESO and PE100 pipes are laid with
addition, quality pipe grade polyethylene resins are almost immune to the correct installation techniques, PE pressure mains can be laid under
fatigue damage for typical fatigue loadings in water and effluent major roads.
pipelines, hence no de-rating is required for the pipe. However, this is
a complex area and a full analysis should always be undertaken. A comprehensive testing programme has been undertaken which
commenced prior to the publication of the original PESO manual on
Surge Design the potential risk of the failure of butt welded PESO pipes by rapid
A critical factor when assessing surge transient pressures generated in crack propagation.
Polyethylene pipes, is the RATE at which the pressure rises in the
pipe subsequent to a surge transient pressure being generated by for The result of these tests showed that it was not possible to generate a
instance, the rapid operation of a pump or v.ilve. Detailed study of the fast fracture in PESO completely full of water even under arduous
UK water network over a period of time has shown that this 'Pressure conditions of low temperature and high pressure.
Rise Rate' has rarely exceeded 8 bar/second and in 'normal' operating
conditions, rarely reaches this figure. Full scale fast fracture tests were also earned out on PE 100 material.
The tests were carried out on 500mm pipe tested at 1.5 times the
Fatigue maximum rated pressure of the pipes <16 bar and 10 bar for SDR11
There is no necessity to de-rate Polyethylene pipeswhere fatigue and SDR 17.6 respectively>. Nitrogen las air substitute) was used as
conditions are encountered, providingthe pipes meet the stress crack pressuring medium to simulate the worst case situation. It was not
resistance requirements of ISO 1167. possible to generate fast fracture in fully gas filled PE100 pipes.
Resistance to Vacuum Therefore the significant advantage of PE100 pipe is that it can be
Polyethylene pipes can safely withstand negative pressure, for instance used at its respective full rated pressure without the risk of failure by
when subjected to vacuum subsequent to sudden power failure to the fast fracture.
pumps in a pumping main.
..... -~
~ 1t 1.' .-...ttt•· ~ I ·:. .. ! " '~ ,; .t n...tr"'c''
. .
11
- .
'H
::;
•
~
...,,u
,.r;:r
.~
I• "-.
.. il.. !I Utt·- w....
~ , ,,
"
~ ~j
...-·
"I'
- :"f ~
.,-... if~
·~q
m
... 111
. .....-. I
l"I
re.
.
;
H: :ii!
~·
,. '...!. ·,
r cl
... .
'" ::'
·-
r:'l9
; ~~ 1) 1. • [l l1 rn~ ••
. ~;::. . r.· ::-: •I ..
·m
r
·-
fl.
.
-~~ --
n;::q ·I
I
i~ :i -
M
---.. ! :
i-.
•
~ ....
J~
~
-·
...
. ~ .
.. u
"'111i'·I I
'
·- :<.
r l'l
"" ~
- ..
•"'' ...
I
...
.t;
~~
• I
·~ ~H"<· 'ffi
II
,
I
1'1..1 ~~
... - =·••
J
Example: PE pipe PN 6 225 x 12.Bmm (Dia. = 200mmJ. discharge 251/s. Friction diagram for PE and PVC pipes calculated according to
Fallow the Dia. line= 200mm until this line cuts the discharge line= 25 /Is. Colebrook, For diameters up to 200mm k = 0.01mm, and for
This gives the value far friction= 2.8 per thousand and the velodty = 0.75 diameters exceeding this k = 0.05mm. Water temperature + 10°C
mis
Flow Chart -Pipes up to 1OOOrnm
K.V2
H ,,.
2g Tolli 1111t"!_l (•rnron1r>t
•1111 I ' ,, O< ,.,
' -1;,"l'}I'•' 1111 .1 1-l ii'wHt ll •~'
,, 'f-J"
l·1Jtll J •• u ',tt 1111> J !r!J
H loss of head
V liquid velocity 1 Ferrule connection 20 0.1 0.9 20
g acceleration due to gravity 25 0.1 0.7 1.5
K coefficient dependent on type of filling. 32 0.2 0.4
63 0.5 1.5
Table 1 gives commonly used values for K 2 Stop valves \!, 0.6 3.7 9.5
'lo\ 0.2 1.2 1.9
1 0.4 0.7
, ....... 1.p· I ... , , . 1)0
2
0.1 0.2
0.1
0.9
0.4
2 .2
0.8
3 Boundary boxes 20 o.8· 4.5" 10.0·
90 Elbow K= 1.00
45Elbow (with meter) ZS O.T 3.2" 8.1'
K= 0.4
Boundary boxes 25 0.5" 1.!l"' 3.4"
22 'h Elbow K·• 0.2
{without meter)
90 Bend K= 0.2
4 Double check valves 20 1.8 4.0 6.0
45 Bend K•- 0 1 2.0 2.7
25 1.2
22 'h Bend K ~ o.os
32 1.3 1.8
90 Tee flow in line K= 0.35 50 2.5
90 tee flow into branch K= 1.20 63 0.4 0.9
Gate vafve: open K= 0.12 5 Adaptors 20 0.4 0.6
v. Oosed K ~ t.0 ZS 0.1 0.1
'"'I• Clo5"d
aosed K= 6.0 32 0.1
K= 24.0 8 Elbows 20 0.3 1.3 2.4
Butterllyvalve: open K= 0.3 25 0.1 0.2 0.4
32 0.1 0.2
50 0.2
Table I-Commonly used values for K 63 0.1
Perhaps a more convenient way of allowing for the frictional resistance 7 Tees (on Branch) 20 0.2 1.0
25 0.3 0.6
of valves, fittings, obstruction, etc., is to consider an equivalent straight 32 0.1 0.2
50 0.3
length of pipe which would create the sarne frictional resistance. 0.2
"'
• These table numbers refer to tables 1 • 7 in report FR 0255
· These flaures refe r lo resutts aoneraled 1rom various sources
Actual headless characteristics for a range of service pipe sizes and
appropriate fillings were researched by WRc during 1991 - 1992 to Table 2-Average Headless in fittings and Components
detennine overall headless for PESO pipes in specific service pipe
These design procedures are readily applied to individual mains or
installations.
simple layouts. The charts are also invaluable for establishing an initial
selection for pipelines forming an integral part of more complex
For a typical service pipe length of 2Sm, the pipew01i< contributes up to
layouts. As pipe networks become more extensive and hence more
3 50/o of the total head loss. The average results are given here as Table
2 for quick and easy reference. hydraulically complex, use must be made of computer-aided design
for which a variety of programs are available. The selection of program
The effect of the frictional resistance created by the internal beads in will depend upon both the complexity and format of output required.
butt welded joints is hardly significant in normal distribution installations
but in the smaller diameters or where the joints are frequent (say every The jointing method
2 metres for some continuous lengths) an increase in the frictional The trench width (standard, or narrow>
resistance of about 2% should be allowed.
PE pipe is available either in coils or straight lengths depending upon
Pipeline Selection pipe size.
The selection of both material and size of a paJticular pipeline will be
influenced by any particular design policy or "standards" employed by Straight pipes are usually produced in 12m lengths but other lengths
the developing body. Within the normal distribution range <up to are available by upon request
630mml the use of ''standard" sizes and designs may well prove cost
effective in tenns of simplication of design, operation, repair or renewal, Coils are available in sizes up to 125mm and usually up to 1OOm
stores levels, etc. length.
- Hepworth
MAR 325 Rev.00
+GF+ GEORG FISCHER
PIPING SYSTEMS
34
Anchorage and Thrust Blocks The PE pipe itself may be partially or completely surrounded by
One of the fundamental features of fully integrated fusion welded PE concrete but should be protected by a heavy duty polyethylene
pipe systems is that they are end load resistant and anchorage is not membrane to a minimum thickness of 3mm. The membrane should
normally required at the junctions or bends. extend outside of the concrete to avoid possible damage during
pouring or compaction and minimise local stresses.
However, an exception to this is at transition points to non end load
bearing pipe systems where thrust anchoring will be required. Where concrete surround to the pipe barrel is to be provided as
anchorage, the forces may be transmitted to the concrete by the
The designer should consider all aspects of the system, induding the introduction of a stub Oange or similar fitting to form a puddle Oange.
imbalanced loads imposed by testing procedures, unusual configura-
tions, large temperature variations, etc., and where excessive stress on
the pipe system is envisaged, additional anchorage should beconsid-
ered.
Concrete Support Consideration should be given to the provision of weight and any excessive turning movements which may be created
concrete support to all heavy fittings or ancillary equipment installed on under operating conditions (hydrants, air valves, etc.l.
PE mains. The support design should take into account both the dead
Movement caused by thermal variation in pipe systems jointed by one of Pipe brac.kel intervals L for pipes SOR l 1 in mm .it pipe
wall 1emperaturc:-
the fusion welding techniques (full end load bearing joints) will generate
Size mm d20"C 30'C 40'C 50'C 60"C
tensile or compression stresses within the pipe material. In buried
16 500 450 450 400 350
pipelines which have been allowed to stabilise to trench bottom ambient 20 57, 550 500 450 400
25 650 600 550 S50 500
temperatures the elastic properties of the material will normally 32 750 650 650 550
750
adequately accommodate these forces which are rarely of sufficient 40 900 850 750 750 650
magnitude to adversely affect the performance of the system. A more so IOSO 1000 900 850 750
63 1200 1150 1050 1000 900
critical consequence of this movement could be its effect at pipe 7S 1350 1300 1200 1100 1000
90 ISOO 1450 1350 1250 1150
supports, or branch connections to plant/equipment and other 110 1650 1600 1500 1450 1300
pipelines. Such points should be analysed for shear and bending 125 1750 1700 1600 1550 1400
140 1900 1850 17SO 1650 1SOO
stresses. 160 20SO 1950 1850 1750 1600
180 2150 2050 1950 1850 1750
200 2300 2200 2100 2000 1900
22S 2450 2350 22SO 21SO 2050
250 2600 2500 2400 2300 2100
length in Temperature Variation In •c 280 2750 2650 2550 2400 2200
metres 5 10 15 20 30 40 315 2900 2800 2700 2550 2350
1 0.8 1.6 2A 3.2 4.8 6.4 )55 3100 3000 2900 2750 2SSO
400 )300 3150 3050 2900 2700
2 1.6 3.2 4.8 6.4 9.6 12.8
4 3.2 6.4 9.6 12.8 19.2 25.6 450 3450 3330 3200 3050 2850
4.8 9.6 14.4 19.2 500 3700 3SOO 3400 3250 3030
6 28.8 38.4
8 6.4 12.8 19.2 25.6 38.4 51.2
10 B 16 24 32 48 64
For other SOR. ratings multiply the values given in lhe table wilh the followlng factors~~
12 96 19.2 28.8 38.4 57.6 76.8
20 16 32 48 64 96 128 SOR 17 arnl SOR 17.6 with 0.91
50 40 80 120 160 240 320 SOR 7.4 with 1.07
100 80 160 240 320 480 640
The pipe bracket spacing given in lhe table may be increased by 30 % in the case of vertical
Table 4 pipe runs, i.e. muftip!y the values given by 1.3.
Abovedalc lmedoocotffidenl trl.expansionD.16mm/metrr/°C
AUdimeuionsinmm Pipe bracket spacing for PE for huids of a density other than 1 g/cm3
If the liqulcl to be uanspol1ed has a density not equal 1 g/arP. lhen !he bracket spacing in the
!able abo\le should be mtJltipli<d by the fader of !he following !able:-
- Hepworth
MAR 325 Rev.00
+GF+ GEORG FISCHER
PIPING SYSTEMS
36
The importance of good handling and storage of polyethylene pipes
and fittings applies equally to all forms of installation. The procedures
and recommendations should be followed at all times giving particular
attention to handling and storage at site.
Coiled Pipes
SAFETY CONSIDERATIONS
It is now well understood that coiled pipe contains a considerable
amount of stored energy which has the potential to cause injury if
handled in an incorrect way. To ensure a safe working environment
during the installation of large diameter pipe in coil form it is intended
that coils should only be dispensed from an approved coil dispenser.
Always ensure that the tail ends of coils are released in a restrained and
controlled manner and never cut all the retaining straps at one time or in
one operation. The work area should be restricted to essential personnel .... ··
i ,. "'11' ., 'u' .. '1t ... if - i
, .. , , .. •
... - ••,j..... 11.---.• i·-- u •"' ·,
only who should always wear hard hat, gloves, safety shoes and eye ·.';'..· ·--·· ·- ~ -· ··-=·· ·--··
protection when carrying-out this type of operation. After completion of i ·,j '1i "1i JI ·,
the dispensing operation it is important to ensure that the free tail-end of 6 (j(j(j:·~::·()
any part-used coil is 'secured' before transporting it from the site. BANDS OR TAPE AT POSITIONS
Reinforced adhesive tape at least 2" wide is used for banding. Complete B, D AND F l\EtfASE INNER
COUTERJ WRAP
coils are secured by outer and intermediate bands and individual layers
are also independently secured as shown in Figure 4. These should not
BANDS OR TAPE AT
POSITIONS B, D AND F
RELEASE COMPLETE INNER I
.. -. II
,·'"•,
II
....... - .. -..
h II f
WRAP :.,::~ ::.;: : ,;:::'.)! :.
be removed until the pipe is required for
actual use and the method of release
. ... ..... •, .
,: l
~ •' '• ,. ,• . ....
detailed in Figure S MUST ALWAYS
befollowed. 78Ek<:>:;;
BANDS OR TAPE AT POSmONS
E. C AND REINFORCID TAPE AT
There should be facilities to restrain A RELEASE REMAINING WRAP
BANDS OR TAPE AT
securely each coil individually throughout POSITIONS I\ C AND E
RELEASE COMPLETE INNER
individually transit and the unloadingpro- WRAP
cess.•
- Hepworth
MAR 325 Rev.00
+GF+ GEORG FISCHER
PIPING SYSTEMS
38
f"lttings Hooks should not be used to lift fittings, which are supplied Strapped
in cardboard boxes or polythene bags. Timber Frames
Storage at Depot
All materials should be carefully inspected at the time of delivery and
any defective material set aside before accepting the delivery into
stores. Any such defects should be notified to the supply source
immediately.
Pipes and fittings should be used in the order of delivery to ensure the
correct rotation of stock. Polyethylene pipes are date stamped at the Ordinary Ground
time of manufacture and checks should be made to ensure the stock
is being rotated on an "oldest out first" basis. Figure 6-Storage of Framed Packs
- Hepworth +GF+
MAR 325 Rev.00
GEORG FISCHER
PIPING SYSTEMS
40
Butt Fusion
Electrofusion
Electrofusion is suitable for materials and/or
SDR's being the same or dissimilar providing that
the appropriate couplers are used. This method ls
particularly suitable in situations where access is restricted
or when jointing direct from a coil. HEPWORTH PME ( LLC )
offers a comprehensive range of couplers from Georg Fischer
covering pipe sizes of 20mm to 630mm. All electrofusion fittings
conform to EN12201 and EN1 SSS and are manufactured from PE
100 material. As with butt fusion we offer the option of producing
traceability reports for each joint. Additionally many of the
electrofusion joints supplied by HEPWORTH PME ( LLC ) offer bar
coded settings for the jointing parameters eliminating the chance of
operator error when inputting such data into the electrofusion
machine.
Mechanical Fittings
Hepworth PME ( LLC ) stocks a wide range of mechanical fittings
suitable for jointing PE pipe.
The mating surface of all heater plates must be kept dean to ensure
good heat transfer and to prevent contamination at the weld interface.
Any deposit on the surface should be carefully removed when the plate
is cold using a soft woOden spatula and/or a rag soaked in a suitable
solvent such as lso-propanol. Protective and refurbishing techniques are
available.
Trimming tools are required to prepare the fusion faces of the pipe
prior to heating and are usually an integral part of the machine. The Agure 1-Typlcal Butt Fusion Equipment
cutting edges should be maintained in clean and sharp condition.
Most fusion tools are made from aluminium because of its good heat
conduction properties but this is a relatively soft material and easily
suffers impact damage. Heater plates should be protected when not in
use. Recent development of automatic butt fusion machines and fully
retractable heater plates may reduce the risk of contaminating heater
plate surfaces.
- Hepworth
MAR 325 Rev.00
+GF+ GEORG FISCHER
PIPING SYSTEMS
42
Fusion Jointing
The recommended procedures for fusion jointing are specified in ISO The correct procedures for jointing dissimilar materials and wall
12176 parts 112/3: 1998 - 2001. Materials suitable for the manufac- thickness are outlined below. Only similar materials and similar wall
ture of pipes and fittings to the above specification may not be thickness should be joined by butt fusion
compatible for fusion jointing under certain circumstances and
guidance should be sought before attempting to join materials with
different pressure ratings or with different diameters.
SDR1Z6
PE100 PESO
CORRECT
Dissimilar materials and dissimilar
wall thickness can be joined by electrofusion
""''""~'" "'"
WRONG WRONG
Dissimilar materials must no! Dissimilar materials must not
be 1oined by butt fusion be joined by butt fusion
Electrofusion Jointing welding shelters are used to ensure that dust and rain
do not contaminate the joint and to protect it against
Electrofusion fittings have sockets that contain electrical wires which, draughts.
when connected to the appropriate power source, fuse the socket onto
the pipe without the need for additional heating equipment. It is possible to join dissimilar polyethylene pipe material and wall
thickness. For example, PESO pipe can be joined to a PE1 00 pipe of
It is essential that jointers take special care to ensure that jointing the same pressure rating using electrofusion couplers with the
procedures are rigorously respected and, in particular, that: appropriate pressure rating. Electrofusion couplers are available up to
size 630mm but larger sizes are being developed.
The oxidised surface of the pipe over the socket depth NOTE: Some coiled pipes may be too oval to fit into couplers, or the
1s removed using a mechanical peeling tool. bend of the pipe may make alignment of the ends impossible. A
number of approaches have been proposed, 1nduding:
The peeled area 1s deaned with lsopropyl Alcohol
(minimum 70%) prior to insertion of pipe into fitting. Cil use a mechanical pipe straightener or rerounding tool;
Clamps are used to ensure that no movement of the
joint can take place during the heating and cooling (iil fusion joint a straight length of pipe onto the end of the coil
cycle. before jointing.
There is a wide range of proprietary metal and plastic mechanical joints For transition from polyethylene pipe to flanged metal fittings, either
and fittings available. All such fittings should be assembled in polyethylene stub faced flanges with metal backing rings or mechanical
accordance with the manufacturer's instructions and all metal fittings flanged adaptors complying to IS014236 and EN 14525: 2004 can
should be supplied with suitable protection from possible corrosion. be used. The gasket and bolt length used should be appropriate to the
particular adaptor. A jointing compound should NOT be used.
The most common group of metal fittings associated with polyethylene
are: When tightening polyethylene flanges, care should be taken to
produce an even torque load to the limits given by the manufacturer.
flanged and other adaptors; The use of a torque wrench is strongly recommended.
mechanical type couplers;
compression fittings; Typical bolt torques are shown in Table below
gun metal ferrules.
- Hepworth
MAR 325 Rev.00
+GF+ GEORG FISCHER
PIPING SYSTEMS
44
Buried Installations
Polyethylene is a thermoplastic material that when extruded produces a
pipe of flexible nature and to which the principles of flexible pipeline
design must be applied not only at the design stage but throughout
installation as well. In particular the quality of materials and workman-
ship employed in trench preparation, bedding, backfilling and
compaction must be of a high standard if the full strength potential of
the pipeline is to be achieved and pipe deformation limited to that
calculated by the design engineer. The following sub-sections deal with
trench preparation, bedding, backfill and compaction
Site Conditions
For each pipeline development, consideration must first be given to the
nature of the site in terms of configuration, existing surface material
and the likely subsoil component materials.
Trenchless Systems
PE is a versatile material and particularly through its toughness and
Hexibility, it is able to be used with a range of cost effective "no dig"
methods of installation.
Guided drilling or "no dig" systems can be classified into several broad
groups according to the way in which the actual excavation of the pilot
bore takes place.
Microtunnelling using PE pipes
These are:
...._ Fluid jet cutting. High pressure jet nozzles use relatively low
flows of water or bentonite-based mud to cut the hole.
Mechanical blade, Huid assisted. A chisel blade cuts the soil
and ftuid jets directed onto the blade help in cooling and
lubrication.
- Hepworth +GF+
MAR 325 Rev.DO
GEORG FISCHER
PIPING SYSTEMS
46
Pipe Bedding and Surround
It is essential that pipelines are laid on a bed of material which will Suitable materials for bedding and surround include free draining sand,
provide even and continuous support. In suitable soils this can be gravels and soils of a friable nature which are then compacted in layers
provided by the hand trimming of the base of the trench with any according to the specified requirements. This "finefill" material is
predominantly hard or soft spots being removed and replaced by
acceptable up to a maximum of 250mm above the pipeline after which
compacted fine material.
the fill is to be backfill material as defined by local regulations.
Where such trimming cannot be easily achieved <e.g. in narrow
trenching) small irregularities can be overcome by the placing and The highway surfaces can be grouped as;
compaction of selected site material or imported fine granular material
to depth of at least SOmm.
flexible and composite roads.
The surround to the pipe effectively forms the foundation element of rigid and modular roads.
the reinstatement and therefore must offer adequate support for the footways, footpaths and cycle tracks.
remainder of the restoration and be capable of transmitting the
imposed loading to the subgrade below the pipe or apparatus. verges.
Flexible or Composite
.._____,"Or------'
Rigid or Modular
Running Surface
_ Qve.!Jat. _
Concrete stab
or bedded
_.__________,
( module
Sub base
Other considerations when selecting a surround should include the if this is undesirable, by enclosing the surround within a suitable filter
potential for the migration of "linefill" from the adjacent ground <and membrane.
the backfill) into open-textured surround. Such action normally results
in settlement of the adjacent ground land/or the backfilD. Migration of
Bricks or other hard material should not be placed under the PE
"finefill" ain be prevented by using a dose textured surround or,
pipe as temporary support.
\\ \ \ \ \ 'ti
... \ ~fll
§ ,_ \ \
\ \ \\\ =E
i;::
Q.
0
Cll
g \ \ \ \ ~
0 u,?>
E
~ u \ \ a;i:s 3
E E \ \ \ c cfll ·-
'ti c
'E ~ \\\ ·-
fll 'ti fll
Cll .c
·e; E
·c: \ \ E
41
u u
.., Cll
e ·e; \ \ \ \ \ \ c::: 'ii. E
E
0 E \ \\\
0 E
°'
-
0
0
-
T
"Cl 'ti
c c
ftl fll
"Cl .c
8 >-
t cl:~
c:n
c
:a
'ti
41
i E ti
e!
o0 E
0
t-
.Q MU
E
~
E
:5 ~
E Imported Granular Fill
E Typically Smm - 10mm
E pea gravel
0
0
- Hepworth
MAR 325 Rev.00
+GF+ GEORG FISCHER
PIPING SYSTEMS
48
Typical Tests for Suitability of Soil Material !imported or local> Strike off the top surface level with the top of the cylinder and remove
for Surrounding Buried Plastic Pipes all surplus spilled material. Lift the cylinder up clear of its contents and
place on a fresh area of Hat surface. Place about one-quarter of the
Particle Size contents back in the cylinder and tamp vigorously with the metal
This maximum partide size should generally not exceed 20mm. The rammer until no further compaction can be obtained. Repeat with the
presence of an occasional partide between 20mm and 40mm is second quarter, tamping as before, and so on for the third and fourth
acceptable provided the total quantity of such particles is only a very quarters, tamping the final surface as level as possible.
small fraction of the whole. If particles over 40mm are present the
material should be rejected. Measure down from the top of the cylinder to the surface of the
compacted material. This distance in centimetres divided by the height
In cases of doubt a representative sample of material Cabout 2kgl of the cylinder (25cml is referred to as the 'Compaction fraction'.
should be sieved, using test sieves of 19mm and 38mm nominal mesh
size. Test
Apparatus
NOTE 1 - To obtain a representative sample, about 50kg of the 1. Open-ended cylinder 25cm long and 15:t0.6cm internal
proposed material should be heaped on a clean surface and divided diameter <1 Scm diameter PVC pipe is suitable).
with the spade down the middle. One of these halves should then be
similarly divided, and so on unUI the required mass of sample is left 2. Metal rammer with striking face 40mm diameter and weighing
1.0±0.lkg.
NOTE 2 - In the sieving, clumps of material that break up under light
finger pressure may be helped through the sieve, but considerable 3. Rule.
force shall not be used to squeeze oversize clumps through the mesh.
Interpretation of results
If (i) any particles are retained on the 3Bmm sieve, or f!O more than 50/o Compaction
by mass of the sample is retained on the 19mm sieve the material is fraction Suitability for use
not recommended. 0.1 or less Material suitable.
0.1 to0.3 Material suitable but requires extra
Procedure - Obtain a representative sample tsee Particle Size, Note care in compaction.
1l more than sufficient to fill the cylinder (about 11 kgl. It is important
Not suitable if the pipe is subject to
that the moisture content of the sample should not differ materially
waterlogged conditions after laying.
from that of the main body of material at the time of its use in the
Over0.3 Material unsuitable.
trench. Place the cylinder on a firm flat surface and gently pour the
sample material into it, loosely and without tamping.
Procedure
Cal Place cylinder on a firm flat surface
and fill to overflowing with a typical
sample of soil excavated from pipe
trench. .·l/;. · ... '
l -----l
<bl Skim off overfill and remove spillage
<cl Lift cylinder so that contents are left
behind
(dl Place now empty cylinder onto
another firm ftat surface.
(el Place one-quarter of material back
into cylinder and tamp down until
completely compacted.
(I) Repeat with 2nd, 3rd and 4th
quarters.
(gl Measure in mm from top of cylinder
to surface of material to obtain
figure"X".
(h) Divide figure "X" by 250 to obtain a
compaction figure.
0.1 or less - suitable
0.1 to 0.3 - suitable with care,
except in ground
conditions generally
waterlogged.
over 0.3 - unsuitable.
Preparation
Generally polyethylene pipes are joined to form a string above
ground prior to snaking into the trench. To prevent scoring
pre-made pipe systems, pipe rollers should be used.
It is advisable to defer the final tie-in connections until thermal The hot bending of polyethylene pipe is possible under carefully
stability of the pipeline has occurred. Once a pipeline is installed controlled conditions but under no circumstances should hot
and in service,. the temperature variation is usually small, occurring bending be attempted under site conditions.
over an extended period of time and is not likely to induce any
significant stress or movement in the pipe system. Polyethylene is a poor conductor of heat but is flammable and
should not be exposed to naked flame.
- Hepworth +GF+
MAR 325 Rev.DO
GEORG FISCHER
PIPING SYSTEMS
50
The installation of flanged fittings such as sluice valves, hydrant tees, After completion of an installation, pipework and fittings should be
end caps etc., usually requires the use of polyethylene stub flanges inspected and made ready for testing to ensure the safety and
complete with backing rings and gaskets. Care should be taken when efficiency of the system. If the system is a large one it should be
tightening these flanges to provide even and balanced torque. Provision tested in sections of convenient length up to a maximum length of
should be made at all heavy fitting installation points for concrete 800m.
support both for the weight and to resist the turning moments
associated with valves and hydrants. The degree to which the trenchline is backfilled prior to testing will be
influenced by:
Where flange connections are included in the pipeline these must be ..... the prevailing site and/or traffic conditions.
properly aligned and care taken when tightening to provide even and ...._ the potential risk of floatation.
balanced torque. Bolts should be tightened in a North/South, ....._ the imbalanced forces due to configuration and
East/West, NE/SE, etc.. pattern. On no account must flanged connec- imposed test pressure.
tions be used as a means to overcome poor alignment. Where practical it is advisable to leave joints exposed throughout the
test.
Recommended torque for flanged connections is given in Jointing
Methods. As part of the preparation for the hydrostatic pressure test all
anchorages and stnuts should be checked to ensure they are
It should be noted that at three way fusion jointed fabricated tee adequate to withstand the excess pressures and it is advisable to
installations, additional equipment and care in handling is necessary 1f retighten all bolted flanged joints and to check that all intermediate
the risk of damage is to be avoided. Consideration should be given to control valves are open.
introducing a flanged connection on the branch outlet of the tee so that
the branch main joint can be made in a separate operation. Complete and accurate records should be taken of the installation. It
is useful for records to be taken before the pipes are buried whilst
Polyethylene pipes and fittings may be partially or completely memories are fresh and key elements are still visible. Photographic
surrounded by concrete but the pipe should be protected by a heavy records of important or complex features should be considered.
duty polyethylene membrane to avoid possible damage during pouring
or compaction and to prevent high localised stresses. Marker tape should be laid along the line of main and connected at
each end to either a sluice valve or hydrant. The recommended
position of the tape is 350mm below the surface directly above the
crown of the pipe.
On-Site Jointing
The various heat fusion techniques available for jointing PE pipe allow
In cases where jointing equipment is continuously moved to joint
the installer a greater degree of freedom when considering the most
positions along the length of the pipeline, protection from the
cost effective/practical installation method suitable to a particular
elements should still be provided and ii joints are to be made in the
construction site. The main element of choice is that jointing a number
trench then sufficient ground material must be excavated to provide
of straight pipe lengths can be carried out at a fixed jointing station
adequate space for the operative and jointing equipment. In wet
outside the trench area or conventionally at each joint position along the
trench conditions precautions must be taken to ensure that the area
pipeline either outside the trench area or in the trench bottom.
Generally and providing site conditions permit, the greatest advantage around the jointing station remains dry.
is obtained from jointing at a fixed position outside the trench area. In
this circumstance pipes are transported by hand or mechanical means
depending on size and class from the site storage area to the jointing
station. During this phase all recommendations given in the 'Handling
& Storage' section apply. The jointing station should consist of a
covered shelter heated in winter months) adequately lit to give the
jointing operative dear vision around the pipe joint and of all pressure
and temperature gauges, etc. Even in summer months it is good site
practice to include for a shelter at the jointing station to provide
protection against wind, rain, dampness, sands etc. These recommenda-
tions apply equally to projects where Electrofusion or Butt fusion jointing
techniques are used but are most common for Butt fusion. Normally on
land installations pipes are pulled through the jointing station by hand,
winch, tractor, etc., depending on pipeline length, size and class. It is
strongly recommended that the jointed pipeline is supported on
sufficient free-running rollers as will prevent the jointed pipes from
-
coming into contact with the ground. This will not only make pipe
handling and the jointing operation easier but will prevent the pipe
from being scratched and scored.
-
On-Site Jointing Station Cover
GEORG FISCHER
Hepworth +GF+ PIPING SYSTEMS
MAR 325 Rev.DO 51
Installing Coiled Pipes - Sizes 160mm and above
Coiled Polyethylene Pipes in 160mm sizes and above should be
moved and uncoiled using an approved dispensing trailer. There
should be facilities available on site to restrain securely each coil
individually throughout the transit and unloading process. Pipes should
be uncoiled strictly in accordance with the releasing instructions for
coiled pipe retaining straps detailed in Handling 8. Storage. After
sufficient pipe has been cut from the coil, the protective end cap must
be replaced on the remainder of the coil.
Pipeline rehabilitation is, of itself, an extensive subject and many profe- Coiled PE Pipe
ssional contractors specialising in these techniques have emerged over
the last decade.
- Hepworth
MAR 325 Rev.00
+GF+ GEORG FISCHER
PIPING SYSTEMS
52
Sub-Aqueous Installations
Polyethylene pipes have been used extensively for many years in sub-
aqueous installations. Here, in addition to efHuent disposal projects,
polyethylene potable water distrihution mains link communities and
Public Utility pumping stations over several kilometres. There are
numerous examples where one continuous butt-welded polyethylene
pipeline, traverses land and water over many kilometres.
Technical Requirements:
Polyethylene pipes installed in above ground systems will generally be
black. Where PE pipe is specified this must be protected from direct
exposure to ultra violet light <sunhghtl.
- Hepworth
MAR 325 Rev.00
+GF+ GEORG FISCHER
PIPING SYSTEMS
54
Testing and Commissioning
This Section deals with the standard procedures for testing installed After being tested, all service pipes must be subjected to a final
pipelines prior to commissioning. These standards will normally require, disinfection process before being introduced into the supply system.
as a minimum, the adequate flushing of the service and the testing of
all pipes and ioints to the maximum head to which the system is to be Special attention should be paid to the proper sterilisation of those
subjected. services laid to hospitals and renal-dialysis machines.
Type 1 Pressure Test: 3. Record and plot the pressure gauge readings at the
following intervals:
Introduction O- 10 mins @ 2 minute S readings
This is a short simple test whereby the creep in the PE pipe .is sustained 10 - 30 mins @ 5 minute 4 readings
by maintaining the test pressure for a period of 30 minutes. By opening 30 - 90 mins @ 1o minute 6 readings
the control valve the pressure is then reduced to a nominal amount
before redosing the valve The subsequent "recovery" of pressure in the The pressure should be seen to rise due to the
pipeline is indicative of a sound pipeline. This simple PASS/FAIL test visco-elastic response of tlie pipe material.
may be found appropriate for short lengths of small diameter main
where there is no residual air in the test section. 4. The resulting graph for a leak-tight system should
have a characteristic profile similar to that shown in
The detailed test procedure is as follows:- the following graph.
1. The selected test pressure is applied and this pressure
maintained by additional pumping as required for a 5. The degree to which the creep in the material af fects
period of 30 minutes. During this time an inspection the pressure graph and the time for response to
should be carried out to identify any obviousleaks at reduced pressure will be influenced by:-
this pressure within the system under test.
the length of the test section
2. The pressure should then be reduced by rapidly the diameter of the pipe
bleeding water from the system to a nominal pressure the presence of air
of, say 2 bars at the test gauge. Close the control valve the efficiency of the bedding and compaction
to isolate the installation.
- .. ---
<:£9 ~
APPROVED KITEMARK
MAR 325 Rev.00
I~\ ~
~ ~I
00 1
Hepworth +GF+ GEORG FISCHER
PIPING SYSTEMS
57 -
U.A.E. OFFICES
ABU DHABI
P.O. Box: 4894, Abu Dhabi, UAE
Tel: +971 2 6727585
Fax: +971 2 6783578
Email: [email protected]
SHARJAH
P.O. Box: 23363, Sharjah, UAE
Tel: +971 6 5438459
Fax: +971 6 5428147
Email: [email protected]
ALAIN
P.O. Box: 80862, Al Ain, UAE
Tel: +971 3 7210727
Fax: ..,971 3 7211292
Email: [email protected]
QATAR OFFIC E
DOHA
HEPWORTH PME (QATAR) W.L.L.
P.O. Box 50207, Doha, Qatar
Tel: +974 44506810
Fax: +974 44506811
Email: [email protected]
MESAIEED
HEPWORTH PME (QATAR) W.L.L.
P.O. Box 50207, Mesaieed, Qatar
Tel: +974 44760588
Fax: +974 44760525
OMAN
ABDUL GHAFFAR HUSSAIN
TRADING LLC
P.O. Box 117, PC 130,
Muscat, Sultanate of Oman
Tel: +968 24216938
Fax: +968 24210032
Email: [email protected]
Email: [email protected]
BAHRAIN
HEPWORTH W.L.L.
Building 1, Avenue 001 O
HEAD OFFICE P.O. Box 143, Manama, Bahrain
H&WOR'Tff PME U:C Tel: +973 17672050
DUMI Fax: +973 17672583
Email: [email protected]
P.0.8ox ~. Dubel, UAE
T.S: ..a7 4 2884870 SAUDI ARABIA
Far .en 4289482011 ABDUL GHAFFAR INDUSTRIES LLC
Emal:W~ Al Nuwar Bini Malik Street,
Building 18 - Al Rawdah District
SALElllCUS1"0t SERVICE Tel: +966 547900444
cuatomer..wvtceOCOlp;ae Email: [email protected] www.hepworth.ae
MAR 325 Rev.00 58
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03
4. Compliance with
Authorities Having
Jurisdiction
LUS-CP07C4C5C6-AJP-MAT-IR-00001_00 Page 19 of 26
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C • 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03
NA
S. Sample
As per actual
2 HOPE PIPE, SDR11/PN16 3" DIA. HOPE Pipe LINEAL METER
site condition
As per actual
3 HOPE PIPE, SDR11/PN16 4" DIA. HOPE Pipe LINEAL METER
site condition
HOPE PIPE FITTING As per actual
4 3" Elbow fitting pc
SDR11/PN16 site condition
HOPE PIPE FITTING As per actual
5 4" Tee fitting pc
SDR11/PN16 site condition
HOPE PIPE FITTING As per actual
6 6" Elbow fitting pc
SDR11/PN16 site condition
AL JABER PARTNERS FOR CONSTRCUTION AND ENERGY
PROJECTS W.L.L.
CONSTRUCTION PACKAGE CP07C - 4, 5 & 6
LANDSCAPE WORKS FOR COMMERCIAL BOULEVARD ON
ROAD A4, LINEAR PARKS AND ROAD A3 & 03
6. References
ISD
9001
Sr. No. CONTRACTOR PROJECT NAME
~~-It
flirntr.-.t;·1
New Horizon Contracting & GTC 558/2013 - Three Years Call - Off Contract
l5D 1
14001 Maintenance WLL for Extension of Water Distribution
b:vtW"'l(r~ •
'"'"~""
Qatar Gas Transport Company
DHSAS 2 Erhama Bin Jaber Jalahma Shipyard
18001 Ltd. (NAKILAT)
o.:,in.ttr,1:<
llf'111r. 1 ·..0S1'1: ~
"- -u~ttl
Aktor S.A. - Al Jaber
3 ISF Camp - Duhail
Engineering JV
WRAS
APPROVED PRODUCT
North Road Project
5 Al Darwish Engineering WLL
Al Waab Complex Public Roads (Package 1,2 &
3)
~
APPROVED
6 QD-SBG Constructions QPR-Dukhan Road (East Contract)
~WRAS
APP~oveo PRODUCT
Road)
w
Hyundai Engineering & Hamad City- Hospital fit out
16
Construction CO. Ltd (BA/09/10/C004/G)
19 HBK GTC70
PO Box 50207, Mesaieed, Qatar Tel: 4476 0588 - Fax: 4476 0525- Doha Sales Office lei: 4450 6810 - Fax: 4450 6811
H.0· 1A\\ v-Sl.9 t.E.O· 1A\· 0si!zh hjJ.ll o~ ~ - EEV1 •OYO u.Sl.9 EEV1 ·OAA 0~~ _,.b.9 - ~ O·Y·V:y.ua
Email: [email protected] Website: www;hepworlh.qa
Subsidiary of Carys Building Materials Authorised, Issued & paid-up share capital QR.40,000,000
ISO
9001
(\:'l<lt
;.i,~ .. l' ....... , Water Supply to Motorcycle Race Track
ISO
1~001 CP 288 Effluent Mains TS to D
t ..... ·l"l'">Cdl
llrtol)'ll" • ·.:i
~ APPROVED 22 AOCC-JV
NOIA Airline Support facilities CP11
~
F-Ring Parson Inter
PO Box 50207, Mesaieed, Qatar Tel: 4476 0588 • Fax: 4476 0525 • Doha Sales Office Tel: 4450 6810 • Fax: 4450 6811
Et0· 111\\ v-Sl.9 llO· lA\· 0~ <b._9-l}I 0~ ~ - lEV1 ·OYO v-Sl.9 lEV1 ·OM 0~ µ · ~ O•Y.Y:y •...,o
Email: [email protected] Websi1e: www.hepworlh.qa
Subsidiary of Corys Building Materials Authorised, issued & paid·up share capital QR.40,000,000
Umm Bab
00
9001
36 Gulf Consolidated Contractors Construction of Roads, Utilities Crossing & Street
o..;1,
Vtr•J'-r.t
Lighting in the Industrial Area - Mesaieed
150
14001 Construction of Doha Rawan Sewerage
!r-1 """""o3f'
,.,..,.)11,, ..'11
Improvements to Existing TSE Network
OHSAS
18001 QIS204 Tanker Reception Facility - Doha West
o.;,um.,'1 37 Metito Qatar
w ~111. J·.CS•'m Sewage Treatment Plant
"'•"'F··irt
<FM>
~
41
Qatar Electro Mechanical
Group Al Mana
Marina Mix-50 @ Lusail
APPROVED
Construction of Multipurpose Hall at Al Sadd
42 Aktor S.A
Sports Club Package 2-Main Works
PO Box 50207, Mesaieed, Qatar Tel: 4476 0588 ·Fax: 4476 0525 - Doha Sales Office Tel: 4450 6810 - Fax: 4450 6811
U.O• lA\\ l)'.Sl9 H.O· lA\· 0.9¥.:i h,9.i.JI u~ ~ - H.Vl ·0\'0 ~l9 ££Vl ·OM .Jsi!Ji fa-9. ~ 0•\'-V:y.va
Email: [email protected] Website: www.hepworth.qa
Subsidiary of Corys Building Materials Authorised, issued & paid-up share capital QR.40,000,000
150
9001 Hamad and Mohamad Al
47 Doha Festival City - Energy Centre
"""
J.'Y"•:;crrr-1 Futaim
150
14001 Gulf Marine Engineering &
[ r -,•CFr.-..:<>!•
M.,...-;urt•J
48 Doha Marriot Gulf Hotel
Construction WLL
OHS AS
18001
OIU:r;Nln"Ltl
' '" ''o~ · -cis~·r., 49 QBC-MSF New Doha Port (NPPOSO)
·~1.1;:"T<tl
United Construction
50 New Doha Port (NPPOS7)
Establishment - Sinohydro JV
WRAS
J.PPROVED PRODUCT Construction Development
Aspire Zone
51
Company
~
Mr. Omar Alfardan Residential Villas in LPC 22 to
25 @The Pearl Qatar
APPROVED
: > ·- ._... ,
;'-~ ~ ~
~ ~ :rt11ti!M:~H", .. u
PO Box 50207, Mesaieed, Qatar Tel: 4476 0588 - Fax: 4476 0525- Doha Sales Office Tel: 4450 6810- Fax: 4450 6811
f.E0· 1An v-Sl.9 f.f.O• lA\· 0sD-!i h,9J.ll u~ y.A5:.o - f.f.Vl -oro tY-'51.9 tf.Vl •OAA 0_9JlJ3 _,hii. ~ 0·\"·V:y.,,;a
Email: [email protected] Website: www.hepworth.qa
Subsidiary of Corys Builcllng Materials Authorised, Issued & paid-up share capital QR.40,000,000