OBJ Datastream
OBJ Datastream
A Thesis
of
Drexel University
By
Andrew S. Golder
of
October 2006
ii
© Copyright 2006
Andrew S. Golder. All Rights Reserved.
iii
ACKNOWLEDGEMENTS
I would like to thank my advisor Dr. Karen Miu, for all of her help and guidance
in the research and development of this thesis. I also thank her for the opportunity to
study and perform research at the Center for Electric Power Engineering (CEPE). My
education in the field of power systems engineering began with Dr. Miu as an
undergraduate and has continued through my graduate education. I appreciate her skill
and enthusiasm as a teacher and mentor; my education here at Drexel University has
I would like to thank Dr. Fischl and Dr. Nwankpa for serving on my thesis
committee. Their comments and suggestions throughout the development of this work
have been valuable and are greatly appreciated. I appreciate their time and commitment
TABLE OF CONTENTS
LIST OF TABLES………………………………………………………………..…….VII
ABSTRACT……………………………………………………………………….….... IX
1. INTRODUCTION………………………………………………………………..…… 1
1.1. MOTIVATION…………………………………………………………….... 1
1.2. BACKGROUND…………………………………………...……………..… 2
1.4. OVERVIEW…………………………………………………………....…… 5
1.5. CONTRIBUTIONS………………………………………………..………... 7
2. BACKGROUND……………………………………………………………………… 8
PHOTOVOLTAIC CELL…………………………………………………...….. 26
ARRAY…………………………………………………………..…….. 31
CHARACTERISTIC EQUATION…………………………………… 33
EQUATION…………………………………………………………..… 34
POWER FLOW………………………………………………………………………… 45
6.1 CONCLUSIONS…………………………………………………...………. 61
LIST OF REFERENCES……………………………………………………………..… 65
…………………………………………………………………………………………....75
LIST OF TABLES
LIST OF FIGURES
Figure 2.5: I-V Characteristic of a solar module under varied solar irradiance…………16
Figure 2.6: I-V Characteristic of a solar module under varied ambient temperature……16
Figure 3.1: I-V curve showing the three points given on a typical specification sheet…25
Figure 5.2: Real power demand of the 394 bus test case for peak load….………………57
Figure 5.3: TMY2 Irradiance profile for Binghamton NY, July 16……………………..58
Figure 5.4: TMY2 Ambient temperature profile for Binghamton NY, July 16................58
Figure 5.5: Real power demand at the substation under varying capacity of PHV
generation………………………………………………………………………………...59
ABSTRACT
Photovoltaic Generator Modeling for Large Scale Distribution System Studies
Andrew S. Golder
Dr. Karen Miu, Ph.D.
significant impact on the distribution system. This work presents the development of a
simulation model for utility distribution systems with installed PHV generation. The
calculate power output based on the environmental conditions which determine generator
behavior. This output is then integrated into an unbalanced distribution power flow
solver using either a constant PQ or constant P|V| generator model. The model has been
implemented and simulations will be presented for a 394 bus test system. In order to
environmental conditions and 24 hour load curves have been automated. Simulations are
performed in order to perform system studies in the areas of demand profiles, phase
balancing, feeder balancing, power factor changes and voltage rise. Analysis is
performed to identify issues that will be most relevant to engineers working in planning
1. Introduction
1.1 Motivation
renewable energy marketplace due to its ability to quietly produce emission free power at
the load site. The main advantage of these systems over other forms of renewable energy
is the feasibility of small PHV systems which can be owned and operated by the
consumer. Economic and political trends, along with increased social desire for
alternative energy sources has produced a significant increase in the installation of small
scale (on the order of 1kW) residential and commercial PHV power systems on the utility
distribution system. In the US, as of 2003, 15 states have implemented programs which
encourage or mandate the growth of renewable energy [9]. In addition some utilities
such as Austin Energy of Texas, USA have offered their customers rebates up to $4.00
per watt to help offset the installation cost of PHV systems [2]. In 2006 the California
state government passed the California Solar Initiative (CSI) which is the largest solar
energy policy enacted in the US. The initiative allots $2.9 billion dollars for solar energy
rebates which will aid residents and businesses in reducing the installation costs of PHV
generation systems. The goal of the CSI is to increase installed solar capacity in
described above are currently causing a significant and rapid increase in the total installed
capacity of grid connected PHV generation in the United States. Because PHV
generation is most often owned and operated by the consumer, system planners and
operators have reduced knowledge of and control over the distribution systems yet it is
2
their responsibility to manage these networks. This situation is similar to system loads
where the day to day behavior of which is determined by the customer. However in the
case of loads the utility has more control over where new loads are connected to the
existing network, where as the location and sizing of PHV generators is determined by
the customer. As installed capacity increases, planners and operators will be faced with
an entirely new set of problems and challenges which will require new engineering
solutions.
behavior, identify problems which are most likely to occur, and test the optimal control
schemes is power flow analysis. Power flow analysis requires mathematical models of
every component connected to the power system being studied. Thus it is important to
develop models which allow for distribution system analysis with PHV generation to be
performed.
1.2 Background
PHV generators are most often connected to the distribution system for several
reasons. A high percentage of grid connected PHV generators are owned by small,
residential and commercial consumers, and are therefore connected at the load site on the
generators are typically physically small, low voltage, and low power systems and it is
therefore appropriate to interface these systems with the low voltage distribution system.
PHV generation is unique in that the residential and small commercial systems for
example in the U.S. which make up a majority of the installations are often configured
for single phase power generation. It is therefore appropriate to connect PHV generators
3
to the distribution grid which contains single phase feeders and is designed to handle an
The study of renewable generation in utility distribution systems began in the late
system planning and operations were presented in [17, 18]. Subsequent studies have
compared power demand curves with PHV production curves in order to predict system
load profiles [12]. Other studies have calculated line loss savings from a distribution
PHV system installation based on simplified distribution line models [13]. To this date
an unbalanced distribution power flow solver incorporating PHV generation has not been
developed and documented publicly. While PHV generation systems have been in use
since the late 1970’s economic considerations have limited their contribution to overall
power production, and the distribution power system impacts of these small number of
installations has not seen extensive study. In addition unbalanced distribution system
modeling and power flow analysis, which increase the accuracy of distribution system
analysis were developed in the late 80’s and 90’s and have only recently evolved as state
of the art methods [35, 36]. Recently in the early 21st century economic and political
trends suggest that certain geographic areas could see high penetrations of PHV
generation on the distribution system, and therefore studies of their impact on large scale
unique set of problems. For example in order to counteract the inherently unbalanced
nature of distribution systems load balancing schemes have been investigated and have
been implemented typically in seasonal manners [3, 1] and more recently with higher
4
frequency [8]. Methods to enhance the voltage stability and reduce power losses of
distribution systems by optimal placement and control switching of capacitors have been
investigated in [23, 32]. Schemes for service restoration of distribution systems have
been investigated in [22, 24, 25] utilizing techniques including network configuration and
capacitor control. Investigations in the field of distribution automation are extensive with
goals such as cost reduction [34], reliability improvement [28], and power quality
monitoring [19].
Now, with a significant number of small scale, single-phase PHV systems coming
online, it may be useful to make updates to these works in order to include the special
addition, the intermittent nature of PHV generation creates new challenges with regard to
distribution capacity planning and maintaining load balance. New distribution system
analysis and automation tools are needed to accommodate the problems associated with
The objective of this work is to develop a component model for grid connected
PHV generation which can be integrated with an unbalanced distribution power flow
solver. The component model must be practical for use by system planners and operators
in order to serve its function for systems level studies. Then, a combined model, which
describes the PHV generator and system models together, will use state of the art
methods and equations for PHV generator modeling and unbalanced distribution power
flow. The model will be implemented using an existing unbalanced distribution power
1.4 Overview
distribution systems with grid connected photovoltaic generation. The model is formed
generation system, with ii) an existing unbalanced distribution power flow solver. A
simulation tool has been developed using MATLAB which is used to simulate the
behavior of distribution systems with grid connected PHV generation over the course of a
day.
which model the two main components of the PHV generator, the photovoltaic array, and
the power conditioning unit (PCU). First the model of the PHV array calculates the DC
power output under the given environmental conditions. Second the model of the PCU
converts the DC power value to a specific AC power injection to the utility grid. These
The basic building block of the PHV array model is the standard equation which
describes the I-V characteristic of a single solar cell. By making some assumptions it is
possible to perform scaling operations in order to define an equation which describes the
I-V characteristic of a PHV array. The developed model uses the available inputs to
calculate the required parameters of the array characteristic equation. Because the
solution to the characteristic equation is not unique an appropriate initial condition and
iterative technique are used to calculate the solution vector of the array characteristic
equation. The model then determines the solution corresponding to the maximum power
output, and defines this as the DC power output of the PHV array.
6
The model of the PCU is characterized by the choice of one of two inverter
control schemes, which determines the use of either a constant PQ injection or a constant
P|V| injection model. In both schemes the DC power output of the PHV array is first
scaled down according to the efficiency of the PCU, and second an AC power injection to
steady state model of the utility distribution system. A traditional Newton Raphson
method is used to perform three phase power flow analysis using the appropriate
component models for unbalanced distribution power flow. Power injections determined
by the PHV array model are integrated with the power flow using the traditional PQ and
P|V| generator models. The overall model of the power system is used to perform power
flow analysis in order to model the steady state behavior of the distribution system.
Therefore the model is an instantaneous model which describes the steady state behavior
MATLAB and simulations are performed using a 394 bus test system. Twenty four
simulations, each of which represents the average behavior of the system for the time
period of one hour, are used to study the system conditions over the course of the day.
Profiles for load demand and environmental conditions are used to simulate the test
performed with a primary focus placed on phase balancing and feeder balancing. Several
issues are addressed with the goal of identifying the problems which are most relevant to
make it appropriate for them to be connected to the utility distribution system. It then
details the background and history of distribution systems studies involving PHV
1.5 Contributions:
• Practical PHV generator model for systems engineers requiring limited input data
• Matlab based simulation tool which integrates the PHV model with an unbalanced
• Simulation methods, results, and analysis for 24 hour system studies using a 394
This thesis provides an additional component model for the field of steady state
ii) unbalanced distribution power flow and PQ and P|V| generator models. Chapter 3
describes the PHV array model, specifying all input and output parameters, assumptions
and procedures. In Chapter 4 the PCU model and integration of the calculated power
2. Background
• First, a grid tied photovoltaic generator, its components and their functions.
generator modeling.
radiation to energy in the form of electric current. The basic component of a PHV system
is the photovoltaic cell. Multiple cells are connected in series and parallel to form solar
panels or modules, which are sold commercially for applications such as grid tied solar
generation. Solar modules are connected in series and parallel in order to create a PHV
array. The solar array produces DC power which for grid tie systems must be adjusted by
inverter. These functions are performed by the power conditioning unit (PCU) which is
composed of the MPPT and inverter [29]. An example a PHV generator system without
energy storage devices is shown in Figure 2.1. In the discussion below the PHV array
and its components will be addressed first followed by the PCU and its components.
when driven by a flux of solar radiation from the sun. This occurs when radiation is
incident upon absorbing material and separates positive and negative charge carriers in
the presence of an electric field. The electric field exists permanently at junctions or in-
devices. A silicon semiconductor junction device contains a p-n junction similar to that
of a common diode, however in a solar cell it exists over a large surface area. When not
illuminated and connected to a forward bias the ideal solar cell mimics the electrical
characteristics of an ideal diode, modeled by the Shockley equation (2.1), where the
⎛ kTVc q ⎞
I D = I o ⎜ e cK − 1⎟ (2.1)
⎜ ⎟
⎝ ⎠
where:
I D = dark current (A)
I o = saturation current of the diode (A)
Vc = cell voltage (V)
q = 1.6*10−19 (coul )
k = 1.38*10−23 ( j / K )
TcK = Cell Temperature (K)
The current in the cell that results from solar radiation is called the photo current
Il which flows in the direction opposite of the forward dark current. Its value remains the
same regardless of external voltage and therefore it can be measured by the short circuit
current (Isc = Il). This current varies linearly with the intensity of solar radiation as
10
increased radiation is able to separate increased charge carriers. The overall current is
then described as the difference between the dark current and the photocurrent. If the
sign convention of current flow is reversed to describe the current which is produced by
an illuminated cell (Ic) then the cell equation can be written as shown in (2.2):
⎛ kTVc q ⎞
I c = I l − I o ⎜ e cK − 1⎟ (2.2)
⎜ ⎟
⎝ ⎠
where:
I c = cell current (A)
I l = photo current (A)
G = solar irradiance (W/m 2 )
TA = ambient temperature (°C)
I l = I l (G )
Vc = Vc (G, TA)
photovoltaic cell shown in Figure 2.2 [29]. The production of photocurrent is modeled
with a DC current source and the dark current is modeled with a diode referred to as the
diffusion diode.
Modeling of non-ideal solar cells and the behavior of solar cells under varying
cells, with the additional components of blocking and bypass diodes. While the
manufacture and size of solar cells vary, in general a single cell has a relatively low
voltage handling capability on the order of 0.6 V [10]. In order to package solar cells as a
more practical device most manufacturers produce solar modules; a group of solar cells
connected in series and parallel in order to increase the voltage and current handling
common scheme for PHV modules used in grid tied power generation is a connection of
In most PHV design and modeling applications the following assumption is made,
A1: Connection of solar cells in series will directly multiply the voltage handling
capability of the system and connections in parallel will directly multiply current
production.
For this assumption to be reasonable it is necessary for all solar cells to behave in a
uniform manner (further discussion in Section 3.2.2.), however it is clear that this is not
always the case. Solar modules contain blocking and isolation or bypass diodes as shown
in Figure 2.3 to reduce the effects of cells which do not act uniformly. Without these
devices it is possible for cells or strings which are not operating uniformly to consume
power generated by other cells or strings. These devices therefore reduce the power loss
12
associated with non-uniformity and allow the behavior of the array to more closely
resemble the uniform case by reducing the negative impact of non uniform cells.
Thus for this work, the following additional assumptions are made:
A2: Each cell behaves in a uniform manner. Under a given environmental condition the
A3: For the purposes of modeling a solar array in this work the bypass diodes and
With these assumptions in place, bypass diodes are reverse biased and act as open circuits
while isolation or blocking diodes are forward biased and act as short circuits. Therefore
Chapter 3.
Bypass diode:
Bypass diodes are placed across each cell in a solar module in order to ensure that
each series string of cells produces the maximum possible voltage. This protects against
the case where a given solar cell does not receive the same illumination as other cells in
the string. For example, given a string of cells, if a single cell is covered in dirt and thus
absorbs less radiation it is possible for the voltage gain of this cell to reverse its direction
13
(ID > Il, as shown by the center cell in Figure 2.3) which would significantly reduce the
voltage gain of the entire string. Therefore, a bypass diode is connected in parallel to
each solar cell which becomes forward biased if the voltage gain of a cell is reversed, and
effectively creates a short across this cell. Then, when a cell voltage is reversed the
voltage capability of the string is increased by the action of the bypass diode [5].
Isolation/Blocking Diodes:
Isolation or blocking diodes are often placed between each string of modules and
the PCU in order to prevent module strings from absorbing power from the system when
not illuminated. Under zero illumination and in the presence of forward voltage
(provided by a battery, the grid, or other module strings) a string of solar modules will
draw current from the circuit [5]. Therefore an isolation or blocking diode is placed
between the module string and the voltage source as shown in Figure 2.3. The term
blocking diode often refers to a single diode used in PHV systems with battery storage,
while isolation diodes refer to multiple diodes placed on the positive terminal of each
series string of solar modules. These diodes perform the same function of blocking a
reverse current flow however multiple isolation diodes provide additional protection in
the case of shading on a single string of modules. These diodes become reversed biased
when the string is not illuminated thus preventing current flow to the string. In some
cases, the function of a blocking diode is performed by switching in the PCU, however
this only prevents the array from absorbing power from the grid, it does not prevent a
single module string from absorbing power from the rest of the array.
14
modules. The number of modules connected in series and parallel is based on the voltage
requirements of the system and the desired power output of the array. Grid connected
systems require an inverter which in order to successfully interface with the grid requires
a specific DC input voltage range generally on the order of 200-600 Volts DC [33]. PHV
arrays are designed to produce a voltage close to the top of this range at rated power
production. This allows the inverter to operate for the largest possible range of DC
Once the voltage requirement is met, power handling capability can be increased
by connecting additional module strings in parallel. This is done by first connecting the
correct number of modules in series to fulfill the voltage requirement creating a string of
modules. Next, additional strings of the same number of modules may be added to
increase the current production and thus the power capability of the array. It is important
that each string is composed of an identical number of modules of the same brand and
power rating. If strings are not matched the voltage production of each string may not be
identical. In this case the voltage output of the array will be lower than that of the highest
producing string, therefore the highest producing string does not operate at maximum
efficiency.
The power conditioning unit (PCU) is a device which interfaces the solar array
with the utility grid. In a grid tie system without storage the PCU consists of a maximum
power point tracker (MPPT) and a DC to AC inverter, as shown in Figure 2.4. In most
15
cases the PCU also contains protection devices which disconnect the PHV system from
the grid in the case of grid failure. Many PCU’s use the existing controllable switches of
The MPPT is a DC to DC voltage converter which ensures that the PHV array
provides the maximum available power to the inverter. Typical I-V characteristics are
shown in Figure 2.5 and Figure 2.6 where environmental conditions are varied. As can
be seen in the figures, a solar array is able to provide constant current for a range of
voltages below a given threshold, where the maximum power point occurs just beyond
this threshold. The MPPT device assures that the input to the inverter remains constant at
G = 1200 W/m2
5
G = 1000 W/m2
4
DC Amperes
G = 800 W/m2
3
0
0 5 10 15 20 25 30 35 40
DC Volts
Figure 2.5: I-V Characteristic of a solar module under varied solar irradiance
4.5
3.5
3 Ta=35°C
DC Amperes
2.5
2 Ta=25°C
1.5
1
Ta=15°C
0.5
0
0 5 10 15 20 25 30 35 40
DC Volts
Figure 2.6: I-V Characteristic of a solar module under varied ambient temperature
The DC to AC voltage converter ties the DC output of the MPPT with the AC bus
of the utility grid. Most grid tie PCU’s use self-commutated voltage source inverters
17
which are built with switching devices such as IGBT’s or MOSFET’s. These types of
switches have the advantage of allowing control of both the on and off switching events.
allows for the existing switches of the inverter to be used for protection functions. Thus
the self-commutated inverter can provide control of the power factor and suppression of
inverter is capable of executing two separate control schemes, current control and voltage
control. The control scheme is selected based on the size and function of the PHV
generator.
The current control scheme is the most widely used scheme for grid tied PHV
generators. This is because of its ability to provide a very high power factor with simple
control circuitry [14]. This scheme senses the voltage waveform of the grid for a
reference value and matches the phase angle of the current output to the reference within
a certain tolerance. A high power factor results because the current phase is controlled to
match the phase of the grid. The current control scheme is ideal for residential and small
commercial PHV generators where control of the bus voltage magnitude is not necessary;
however, a high power factor and reduced cost of the inverter are priorities.
The voltage control scheme is used for most off grid applications and some grid
tied applications where it is desired to control the voltage magnitude of the AC bus. This
scheme taps the grid for a reference and matches the voltage output to the reference
with less lower-order harmonic components [14]. Control of the output voltage is
necessary for off grid applications where the PHV generator is the only source of power
18
maintained by the generator for proper operation of the loads and storage devices which
rely on the PHV generator for power. Large commercial or industrial grid tied PHV
generators may also use this scheme in order to control the voltage magnitude of the
output bus. The power output of a PHV system varies over a wide range in a single day,
and the power injected to the grid will affect the voltage at the output bus. Therefore,
large PHV generators could create undesirable swings in the voltage level at the output
bus including significant over voltage levels. In order to prevent a large PHV generator
from causing such disturbance problems in the grid a voltage control scheme can be
utilized in the inverter. With this scheme the voltage magnitude of the output bus is
maintained regardless of the power output which prevents the PHV generator from
The type of control scheme selected for a given PHV generator will determine the
generator modeling scheme to be used when integrating with an unbalanced power flow
analysis. Utilizing the current control scheme will cause a PHV generator to be modeled
as a constant PQ power source while use of the voltage control scheme will result in a
The goal of this work is to study the affect PHV generators will have on the utility
distribution grid. PHV generators are often single phase devices which produce power at
low voltage levels. These characteristics match well with distribution systems which
allow for single and two phase feeders and distribute power at mid to low voltage levels,
therefore a majority of PHV generation systems are connected to the distribution system.
19
Thus unbalanced distribution power flow analysis is most appropriate for performing the
desired studies.
Distribution systems are unbalanced networks which can contain single phase or
two phase feeders and are often characterized by a radial or tree structure. Figure 2.7
shows the basic building block of a distribution power system which interconnects
unbalanced component models for elements such as lines, switches, and transformers to
Each component can have up to three phases therefore the variables in Figure 2.7 are
capacitors can be modeled as current or power injections to the network [36] as shown in
Figure 2.7. Two common methods for solving power flow include backward/forward
sweep techniques for radial structure systems and Newton Raphson for general structured
systems. Each implementation utilizes the multi-phase component modeling in [35] and
each method solves for the steady state voltages at the existing phases concurrently.
sweep and Newton Raphson methods is provided. The two main types of generator
models are constant PQ sources and constant P|V| sources, which will now be discussed
in detail respectively.
synchronous generators are controlled to maintain constant power output and constant
power factor. Some utilities require that a power factor controller must be able to
maintain the power factor within plus or minus one percent [6]. Induction co-generators
are not able to control their power factor as the reactive power will vary with the terminal
simplification based on the assumption of a constant bus voltage [6]. Therefore in this
model, power output of the device is determined completely by its own characteristics
and operations and is independent of the behavior of the utility grid to which it is
connected.
21
Backward/Forward Sweep:
While the power output remains constant the current output of the device is
dependent on the bus voltage magnitude to which it is connected [36]. The current
*
⎛S ⎞
I Gk = ⎜ Gk ⎟ (2.3)
⎝ Vk ⎠
where:
SGk = power supplied by co-generator at bus k
I Gk = current injection due to co-generator at bus k
Newton Raphson:
In the traditional Newton Raphson method load busses are modeled as constant
power PQ busses. It is assumed that the power injection at a load bus is known, which is
key because the mismatch equation for Newton Raphson is defined as the difference
between the known values for power injection and the values for power injection
calculated from the variables at each iteration. Therefore when a PHV generator is
connected to a load bus the power generated is added to the known power consumption
regulate the terminal voltage to a specified value. In this case, the reactive power output
Backward/Forward Sweep:
22
output required to maintain the specified voltage at the given real power output. One
method [26] creates a fictitious node and branch which feeds reactive power to the
specified P|V| node thus maintaining the desired voltage value. Using this technique the
P|V| node can actually be treated as a PQ node in calculations where the Q injection is
⎛ V fict , k − | Vkt |⎞
Qk =| Vkt | ⎜ ⎟⎟ (2.4)
⎜ X
⎝ fic , k ⎠
where:
Qk = specified value of reactive power injection at bus k
Vkt = calculated voltage value in bus k at iteration t
V fict , k = calculated voltage of fictitious node of bus k at iteration t
X fic ,k = fictitious branch impedance of bus k
In the case of generators which are connected to the grid through an inverter the
available injection current is limited. If the Q value determined in (2.4) violates the
current constraint then the inverter will not be able to maintain the specified voltage and
control is switched to current control which is modeled by the constant PQ source model.
Qk ,lim = ± SGk
2
− Pk 2 (2.5)
where:
SGk = power produced by the generator at bus k
Pk = specified real power output of the generator at bus k
23
Newton Raphson:
modeled as constant P|V| busses. The known value for the real power injection is
included in the mismatch equation and the unknown reactive power value is not. The bus
voltage magnitude is specified and thus is not included as a variable. A limit is placed on
the reactive power that may be produced by the generator and after each iteration the
reactive power output is calculated and compared to the limit value. If the constraint is
violated the power flow is considered invalid because no solution exists which satisfies
the both the reactive power limit and the voltage magnitude requirement [11].
Given the concepts reviewed in this chapter, development of a PHV array model
is presented in the following chapter. Integration of the PHV array model with an
This chapter develops a model which calculates the DC power output PGDC , of a
conditions:
The model is intended for use by system planners and operators who will have a limited
amount of data available to them regarding the photovoltaic systems themselves, and the
environmental conditions which determine their output. Inputs corresponding to the solar
modules are limited to the information available on a typical specification sheet, such as
those shown in Appendix D. Inputs corresponding to the size and connection scheme of
conditions are limited to solar irradiance which determines current production and
ambient temperature which most heavily impacts the voltage handling capability. A list
Figure 3.1 shows an I-V curve of a solar module with the three points commonly
provided on specification sheets. In this chapter, the characteristic equation of the non-
ideal photovoltaic cell will be presented first, followed by the method used to scale the
equation to represent an entire array. A step by step summary of the modeling procedure
flow chart of the modeling procedure is then shown which specifies the inputs and output
of each step is shown. Finally the implementation of the PHV array model is described
4.5
4 (0, Isc)
3.5
(VM, IM)
3
DC Amperes
2.5
1.5
0.5
(Voc, 0)
0
0 5 10 15 20 25 30 35 40
DC Volts
Figure 3.1: I-V curve showing the three points given on a typical specification sheet.
26
The circuit model of a photovoltaic cell often used for research purposes is
shown in Figure 3.2. This model was selected due to its use of specification sheet inputs,
and its appearance in several texts regarding photovoltaic devices [5, 20, 29].
In addition to the components of the ideal model, the model shown incorporates a
series and shunt resistance to capture the behavior of a physical solar cell more
accurately. Several elements of the solar cell contain resistive properties such as the
semiconductor material itself, the metal grid which collects current from the
semiconductor material, the collector bus and the internal wiring. It is assumed that these
series losses can be modeled using a lumped resistor Rs. Several shunt resistive losses
occur such as localized shorts at the emitter layer of the semiconductor material and
perimeter shunts at the cell borders. The combined effect of these shunts is modeled by a
lumped parallel resistor Rsh. Equation 3.1 describes the I-V characteristic of this cell
model:
⎛ (VcnkT
+ I c Rs ) q
⎞ V +I R
I c = Il − Io ⎜ e cK
− 1⎟ − c c s (3.1)
⎜ ⎟ Rsh
⎝ ⎠
where:
27
It is shown in [5] that only very small values of Rsh will significantly affect the
power output of the model. Solar cells are designed to reduce shunt losses and therefore
most commercially available solar modules have relatively large shunt resistances. Thus
Rsh = ∞ (3.2)
Also, it is not possible to consistently calculate a value for Rsh given the available
parameters listed in Section 3.3. Rsh is determined by the slope of the I-V curve at the
dI 1
=− (3.3)
dV v = 0 Rsh
28
curves must be available. Therefore the model will be modified according to (3.2) which
may result in a bias that overestimates the power production of the solar array.
⎛ (VcnkT
+ I c Rs ) q
⎞
I c = Il − Io ⎜ e cK
− 1⎟ (3.4)
⎜ ⎟
⎝ ⎠
Figure 3.3 depicts the model of a solar cell neglecting the effects of shunt
resistance. (3.4) describes the electrical behavior of this circuit. This is the circuit model
that will be used to simulate the behavior of a solar cell in this thesis. All of the
parameters of (3.4) can be determined from the input parameters listed. This equation is
the basic building block of the array model just as the solar cell is the building block of
an actual array. The equation must now be modified in order to model the behavior of a
photovoltaic array.
connections of solar cells as shown in Figure 3.4 is utilized. For the purpose of modeling
an array an assumption is made that the current and voltage characteristics of each cell in
the array is uniform (A3). This is important for two reasons: First, it ensures the bypass
29
diodes will be reverse biased and are treated as open circuits and the blocking diode is
forward biased and is treated as a short. Second, it ensures that the exponential
expression (3.4) may be scaled in a linear manner based on the series and parallel
connection of cells because the parameters in the exponent (Vc, Ic, Tck) will be identical
Many solar modules used for grid tie systems are composed of 72 cells connected in
series [10]. This assumption greatly simplifies the modeling procedure and the
characteristic equation that is used as the final model of the array. With this assumption
3.4 where Ns describes the number of cells in a string and Np describes the total number
of strings in the array. While it is true that modules exist which contain parallel cell
connections, these are generally used for low voltage applications such as stand alone DC
systems with battery storage and are not utilized for grid connected photovoltaic
generators.
I A = N p Ic
I scA = N p I sc
(3.5)
VA = N sVc
VocA = N sVoc
where:
N s = number of cells connected in series
N p = number of cells connected in parallel
I scA = short circuit current of the array (A)
VocA = open circuit voltage of the array (V)
Remembering that Il = Isc and substituting these into equation (3.4) results in:
⎛ (VAnN+ I kT
A RsA ) q
⎞
I A = I scA − N p I 0 ⎜ e s cK
− 1⎟ (3.6)
⎜ ⎟
⎝ ⎠
The scheme presented above is a commonly accepted method for scaling the cell
characteristic equation in order to form the array characteristic equation [5]. Inputs to the
model developed here include parameters related to solar modules instead of single cells
31
and thus this scaling method must be modified to account for module inputs. This is
In order to develop the model parameters basic steps are outlined below. Detailed
Step 3) Solve for parameters of the characteristic array equation (Section 3.3.3.).
Step 4) Calculate the I-V curve of the characteristic equation and determine PGDC
(Section 3.3.4.).
The array connection scheme refers to the number of solar modules connected in
series to form a string and the number of parallel strings used to form the array. The
array characteristic equation requires the module connection scheme in order to specify
(Ns, Np), however this information is not available therefore the model determines an
appropriate connection scheme from the desired power rating and equipment
specifications. In many cases the only information a system planner/operator will have
concerning the connection scheme will be the rated power output PrA of the array.
However since the mathematical model is built by scaling the equation of a single solar
following procedure of (3.7) has been developed to determine the probable connection
scheme:
32
where:
ciel () = function that rounds to the next highest integer
VDC = The desired nominal DC voltage (usually 500V)
N sM = Number of modules in series required to achieve VDC
PCol = Power rating of a single string of N sM modules
N pM = number of series strings connected in parallel required to achieve PrA
First the minimum number of series modules, NsM, required to achieve the desired
voltage output at rated operation is determined. Second, the power rating of this string of
modules, PCol, is calculated, and third, the minimum number of strings required to
achieve the desired power, NpM, is determined. Fourth, the actual power rating of the
This scheme builds a PHV array in a discrete manner, as the power rating of the
overall array can only be increased in steps corresponding to the size of the power rating
of a single string of modules. Thus, for an arbitrary desired power rating, this scheme
designs an array with a rating greater than or equal to the rating input by the user. The
method is considered conservative for system studies since the effects of PHV
generation, such as phase imbalance, and overall demand curve changes increase as the
PHV system rating increases. It is noted that the power rating used in the power flow
solution is bounded because the over estimate does not exceed the rated power of a single
string of modules. The size of a single string of modules is limited because it is based on
the input DC voltage range of the power conditioning device. The effect of
33
flows each bus typically represents an aggregate bus such as a pole top transformer which
services a number of loads. Therefore the PHV system on a given bus represents the
aggregate of all the PHV systems serviced by that bus, and for this aggregate system the
scaled up to describe the behavior of the entire array. This is done according to (3.5) and
(3.6) however it is important to note that values for Isc, Voc, and Pr are given at the
module level. Therefore, the procedure is modified to scale appropriately from the
I scA = I scM i N sM
VocA = VocM i N sP (3.8)
PrA = N sM i N sP i PrM
The number of cells in series is the product of the number of series cells in the module,
Ncs, and the number of modules in the string, N sM . The number of parallel connections
N s = N cs i N sM
(3.9)
N p = N sP
34
Once these calculations have been performed the appropriate substitutions can be made in
(3.10). This is the form of the I-V characteristic equation that will be used to model the
photovoltaic array:
⎛ (VAnN+ I kT
A RsA ) q
⎞
I A = I scA − N p I 0 ⎜ e s cK
− 1⎟ (3.10)
⎜ ⎟
⎝ ⎠
• Calculate the array open circuit voltage and short circuit current at the given
environmental conditions
appropriate given assumption A2. While specifications sheets for solar modules do not
provide a value for the series resistance a value for the series resistance can be calculated
from the parameters that are provided, the key parameter being the maximum power
calculate series resistance are (VocA, IscA, PrA). Note that these parameters refer to the
entire array. Thus the series resistance of the entire array will be calculated directly.
In addition, the following calculations will make use of the parameter fill factor
defined as follows:
35
VrA I rA
FFA = (3.11)
VocA I scA
The fill factor of a given array describes the relationship between the rated power output
and the product of the short circuit voltage and open circuit voltage. While the fill factor
is not strictly a measure of efficiency it is indicative of the efficiency of the array. This
measure is useful because it is possible to approximate FF0A defined as the fill factor of
where:
FF0 : Fill Factor of the array without a series resistance
The key to the following derivation is that (VocA, IscA) remain the same in the two cases of
an array with and without series resistance. This allows us to define a relationship
between (3.11) and the empirically determined [5] (3.12) which involves the parameter of
series resistance. The derivation for the value of RsA will now be described:
PrA = VrA I rA
PrA = PrAwoR − I rA2 RsA
⎛ I ⎞
PrA = PrAwoR ⎜1 − rA RsA ⎟ (3.13)
⎝ VrA ⎠
I rA I scA
≈
VrA VocA
36
where:
PrAwoR = Denotes power the array would output if RsA = 0
(VrA , I rA ) = Voltage and current of the array at rated power
The approximation shown in (3.13) is an assumption based on the shape of the I-V
⎛ I ⎞
PrA = PrAwoR ⎜1 − scA RsA ⎟
⎝ VocA ⎠
⎛ I ⎞ (3.14)
PrAwoR ⎜1 − scA RsA ⎟
FF =
PrA
= ⎝ VocA ⎠ = FF ⎛1 − I scA R ⎞
0⎜ sA ⎟
VocA I scA VocA I scA ⎝ VocA ⎠
VocA PrA
RsA = − 2
(3.15)
I scA FF0 A I scA
Alternative methods for the calculation of series resistance do exist [29]. This
method requires the use of many empirically determined I-V characteristics of the solar
module or array and therefore is impractical for use in this algorithm because the detailed
Calculate the array open circuit voltage and short circuit current at the given
environmental conditions:
This section describes how the short circuit current and open circuit voltage of the
array are transformed from rated values (IscAr, VocAr) to the appropriate values given the
environmental state (IscAE, VocAE). IscAE is substituted directly into (3.10) and both (IscAE,
37
VocAE) are used to calculate the saturation current of the diode I0 later in this section.
While the short circuit current and open circuit voltage do not describe operating points
of a solar generator during normal operation, the operating points are determined from
these parameters. Therefore, for purpose of discussion it is appropriate to assume that the
impact environmental conditions have on the short circuit current and open circuit
voltage will be similar to the effect on the operating current and voltage respectively of
the array.
The rated values (IscM, VocM), are determined empirically at standard test
G = 1000 W/m 2
TA = 25°C (3.16)
Atmospheric Spectrum = AM 1.5
The current produced by a solar cell is directly dependant on the solar irradiance incident
upon its surface. The current produced by the array is proportional to the energy input in
the form of solar irradiance. The array output voltage is heavily impacted by the
temperature of the solar cell because the voltage handling capability of the semiconductor
empirically under a separate set of standard test conditions of 800 W/m2, 20ºC, AM 1.5.
NOCT − 20
Tc = Ta + iG (W/m 2 ) (3.17)
800
38
proportional the energy input in the form of solar irradiation. There is a small
⎛ ∂I ⎞
temperature coefficient, ⎜ scA ⎟ , on the order of a few milliamps per degree Celsius to
⎝ ∂Tc ⎠
I scAr ⎛ ∂I ⎞
I scAE = G + ⎜ scA ⎟ (Tc − Tc 0 ) (3.18)
1000 ⎝ ∂Tc ⎠
where:
The open circuit voltage of the array under given environmental conditions is
calculated in (3.19):
⎛ ∂V ⎞ kT ⎛I ⎞
VocAE ≈ VocAr + ⎜ ocA ⎟ (Tc − Tc 0 ) + cK ln ⎜ scAE ⎟ (3.19)
⎝ ∂Tc ⎠ q ⎝ I scAr ⎠
As the temperature of the cell rises, the voltage capability of the semiconductor material
in the cell is diminished and thus the voltage across the cell decreases. This can be
The values for open circuit voltage and short circuit current at the given
environmental conditions are thus determined [5]. These values will now be used to
⎛ (VAnN+ I kT
A RsA ) q
⎞
I A = I scAE − N p I0 ⎜ e s cK
− 1⎟ (3.20)
⎜ ⎟
⎝ ⎠
The parameter I0 is determined by setting the equation to open circuit conditions, and
IA = 0
VA = VocAE (3.21)
I scAE
I0 =
⎛ VocAE q ⎞
N p ⎜ e nN s kTcK − 1⎟
⎜ ⎟
⎝ ⎠
3.3.4. Calculate the I-V Curve of the Characteristic Equation and Determine PGDC
The characteristic equation that is used to model the PHV array is repeated in
(3.22):
40
⎛ (VA + I A RsA ) q ⎞
I A = I scAE − N p I 0 ⎜ e nN s kTcK − 1⎟ (3.22)
⎜ ⎟
⎝ ⎠
The variable IA occurs twice in (3.22), and therefore there is no unique solution to
this equation. In order to find the correct solution a known initial condition is required.
This model uses the open circuit point (0, VocAE) for this purpose. It can be determined by
⎛ nN kT ⎞ ⎛ I scAE ⎞
VocAE = ⎜ s cK ⎟ ⎜
ln ⎜ + 1 ⎟⎟ (3.23)
⎝ q ⎠ ⎝ Io N p ⎠
With (0, VocA) as the initial solution the iterative technique in (3.24) is used to calculate
VA = VocAE ;
I A1 = 0;
while VA > 0
VA = VA − small _ step;
⎛ (VA + I A1RsA ) q ⎞
I A = I scA − N p I 0 ⎜ e nN s kTcK − 1⎟ ;
⎜ ⎟
⎝ ⎠
while abs(I A1 − I A ) > epsilon (3.24)
I A1 = I A1 + ( I A − I A1 ) /10;
⎛ (VA + I A1RsA ) q ⎞
I A = I scA − N p I 0 ⎜ e nN s kTcK − 1⎟ ;
⎜ ⎟
⎝ ⎠
end
I A1 = I A ;
end
41
As can be seen from (3.24) the initial solution for IA is input to the equation as IA1. The
value of VA is reduced by small step and iterations are performed until the values of IA
and IA1 are within a given tolerance epsilon. Once a solution is determined the procedure
is repeated until the short circuit point is reached. I-V curves are thus formed for a solar
A power vector is calculated from the I-V curve by multiplying the stored vectors
of I and V. The DC power output of the array is then defined as the maximum element of
Pˆ = IV
ˆˆ
(3.25)
PGDC = Pmax AE = max( Pˆ );
It is assumed that the PHV array operates at the maximum power point. In the
physical system the output of the array may not be the maximum power point however
the PHV output is fed to the MPPT which assures the maximum power point is fed into
the DC to AC inverter. Therefore the described model accounts for the behavior of both
the PHV array and the MPPT. The power loss in the MPPT is taken into account using
3.4. Flow Diagram of Procedure for Calculating Power Output of PHV Array
The flow diagram shown in Figure 3.5 describes the PHV array model by defining
the equations that are implemented in the model and their input output relationships.
⎛ ∂I scM ⎞ ⎛ ∂VocM ⎞
⎜ ⎟, ⎜ ⎟
⎝ ∂Tc ⎠ ⎝ ∂Tc ⎠
PGDC
Figure 3.5: Flow diagram of PHV array model
43
This model has been implemented in MATLAB in order to interface with the
software developed in [35]. The output of the model for an example PHV array is
presented here in order to describe a typical residential system under a given set of
environmental conditions. Figures 3.6 and 3.7 show a typical PHV array I-V curve and
6
DC Amperes
0
0 100 200 300 400 500 600 700
DC Volts
Figure 3.6: I-V Characteristic of example PHV Array (circle denotes max power point)
44
3500
3000
2500
Watts
2000
1500
1000
500
0
0 100 200 300 400 500 600 700
Volts
Figure 3.7: P-V Characteristic of example PHV Array (circle denotes max power point)
Notice from Figure 3.5 that the operating voltage of the array is ~470 V, which is
within the ideal operating range of the inverter (195-550 V) [7]. The power output of this
array under the given conditions is 3544.3 Watts DC. Power output of a PHV array
varies based on the environmental conditions, and is most often less than the rated output
4. Model of the Power Conditioning Unit and Integration with Power Flow
This chapter will present the conversion of the PHV array output power PGDC to an
AC power injection SGAC to the grid dependant on the source model selected:
where:
SGAC = complex power injection by PHV generator
PGAC = real power injection by PHV generator
QGAC,lim = limit of the reactive power inection by the PHV generator
η = efficiency of the PCU
pf = power factor
As discussed in Chapter 2 there are two control schemes available for the inverter of the
PCU which correlate to two distinct generator models, the PQ source model and the P|V|
source model. If the constant PQ source model is selected the complex power injection
SGAC is completely determined by the characteristics of the PHV model. If the constant
P|V| model is selected the real power injection and voltage magnitude of the output bus
are determined while the reactive power injection is determined by power flow
computations. A reactive power limit is also calculated in order to assure the current
production capabilities of the PHV generator are not exceeded. PHV generators are often
connected at the load site as most PHV generators are owned by individual consumers.
Section 4.2 describes how the calculated power injections are integrated with the model
Most PHV generators utilize self commutated voltage source inverters and the
inverter control scheme used in the PCU of the PHV generator determines the generator
modeled as constant PQ sources and generators which utilize voltage controlled inverters
are modeled as constant P|V| sources. In each case, the efficiency, η, of the PCU is
considered constant and the output power of the PHV system PGDC , is scaled according to
(4.2):
' = η i PG
PGDC DC
(4.2)
The constant PQ and constant P|V| power flow component models are described in the
following sections.
inverters which utilize the current control scheme. In this scheme the phase of the current
to be output by the PCU is controlled to match a voltage reference measured at the output
bus of the inverter. This emphasis on matching the current phase angle to the output bus
ensures a high output power factor for the PHV generator [14]. Most commercially
available PCU’s specify an output power factor close to 1 under normal conditions and
no lower than 0.9 [33]. The generator acts as a current source and does not control the
voltage at its output bus. Thus a constant PQ model is selected for integration with the
power flow module. For this model the real and reactive power injections PGinj and
47
QGinj are functions of the PHV array model under the given environmental conditions and
PGinj = pf i PGDC
'
would incorporate an inverter using the voltage control scheme and thus would act as a
voltage source. As such, commercial sized PHV installations will be modeled utilizing a
For a given environmental condition the apparent power capacity of the generator
SGinj is determined by the PHV array model (4.4) and the desired | V | is specified:
| SGinj |≤ PGDC
' (4.5)
The current capacity of the PHV generator is limited by SGinj therefore it is necessary to
define another parameter in order to determine the constant PGinj injection and the reactive
power limit QGinj,lim . In this case, it is appropriate to define a minimum power factor for the
power output of the array in order to accomplish this. A power factor of 0.9 will be
selected as the minimum power factor because this is stated to be the minimum power
factor for some commercially available PCU’s [33]. Therefore PGinj and QGinj,lim are
calculated in (4.6):
48
The P|V| generator is then integrated with the power flow module in the standard
manner a generator bus treated in the Newton Raphson power flow method. When an
iteration is completed a value for QGinj is calculated and compared to QGinj,lim . If the
constraint is violated the power flow is considered invalid because a solution does not
exist where both the constraint and the voltage magnitude requirement are satisfied.
An unbalanced three phase distribution power flow solver has been developed in
[14] and implemented in MATLAB. This implementation models the steady state
behavior of a three phase distribution system based on information in a case file which
describes the components and topology of the distribution system to be modeled. The
The power flow models single phase and two phase networks, as well as
unbalanced loads and generators. In this implementation load busses often represent
aggregate loads such as a pole top transformer which services a number of residential and
commercial units, or an industrial substation feeding large industrial loads. The PHV
generator model is represented as an injection at the load bus therefore the PHV generator
model is also an aggregate of all the PHV generators connected to the given bus. An
unbalanced PHV generator may represent a situation where the number and capacity of
generators (10>kW) and those modeled as constant P|V| sources are balanced three phase
S kinj = S Lk
inj
+ SGACk (4.4)
where:
Skinj = total power injected at bus k
inj
S Lk = power injected by the load at bus k
The power injection of the PHV generator must also be combined with the load
injection for the constant P|V| case. The real power injection and reactive constraint at
bus k are thus defined in (4.5) and the voltage magnitude | Vk | is specified:
(4.5)
constraint:
inj
QGk ≤ QGk
inj
,lim
where:
PLkinj = total real power injection specified for bus k
Qkinj = total reactive power injection at bus k
calculated from results of the power flow
(PGkinj , QGk
inj
) = real and reactive power injections due to PHV generator
50
For the Newton Raphson implementation presented in [35] the variable, Jacobian,
and mismatch matrices are created based on the network topology before all P|V| busses
are determined. Therefore it is necessary to remove the appropriate rows and columns
corresponding to the voltage magnitude of P|V| busses. If the constraint is violated the
PHV generator model is converted to the constant PQ type with a given power factor, for
example 0.9. In this case, the voltage requirement | Vk | will not be met in the solution.
The PHV array and PCU models have been developed and integrated with
existing unbalanced distribution power flows. The following chapter presents the
The model described in Chapters 3 and 4 has been implemented in MATLAB and
integrated with an existing power flow program in order to perform system studies on
large scale distribution systems. For each power flow computation, a load level and set
of environmental conditions must be selected and input to the system. Then, a 394 bus
test system of a real world power network is used as an example for the following
studies.
The 394 bus test system with 199 load busses that is used for simulation studies in
this work is shown in Figure 5.1. For a simulation to be performed a case file must be
constructed which describes the system conditions. The case file must contain data for
both the electrical and weather conditions in order to fully describe the test system.
Electrical data includes load data as well as the location and ratings of installed PHV
generators. This section describes the construction of case files which include this
information. Cases studies and corresponding result are summarized in Table 5.1
3
4
Power flow data includes network, load and generation parameters. This section
will focus on the two most relevant components to this work which are the loading
conditions and the configuration of installed PHV generators. These will now be
discussed respectively.
A base case loading condition was provided for the 394 bus test system, which
represented peak demand. The loads have been divided into categories of residential,
commercial, and industrial loads and each type of load may be scaled separately to
In order to create 24 hour load profiles from the base case, existing load profiles
may be used to describe demand of the test system for a specific hour of a given load
profile. Seasonal load profiles are available online for free from Itron through their
53
eShapes database [15]. This database contains load profiles for ten geographic regions
for the years 2001-2005, and specifies the type of load which allows for the use of
residential, commercial and industrial example load profiles. These profiles are used to
construct load data for case files according to the procedure described in Appendix C.
With respect to PHV generators, the case file must include data on the location
and rating of the generator. The 394 bus test system has 199 load buses. It is appropriate
to place PHV generators on these busses because of the previously stated trend that most
PHV generators are owned by the consumer and placed at the load site. It is also
studies will use specific schemes to determine the desired locations and capacity for PHV
generators. These schemes will be described in the following sections which outline the
Laboratory [27]. This database is a compilation of data measured during the years 1961-
individual years and concatenating them to form a single year of data. The database was
The PHV generator model uses two parameters which are available in the TMY2
are included in the TMY2 measured data, however the most appropriate for use is that
54
labeled in [27] as the Global Horizontal Radiation (W/m2), defined as the total direct and
diffuse radiation incident upon a horizontal surface. The array of most solar generators is
installed at an angle which maximizes the time at which direct rays from the sun are
normal to the surface of the panels. Therefore use of the irradiance measured on a
horizontal surface as an input will create a bias which underestimates the production
The following sections describe specific simulations and their results. In each
simulation environmental data is matched with appropriate load data from the correct
season.
Single power flow studies are the basic tool to be used in building 24 hour or
longer studies. Thus given a single set of PHV installation locations and ratings,
environmental conditions, network load conditions and network parameters, a power flow
study can be made. Here, arbitrary levels of PHV penetration are considered based on a
percentage of the total substation demand (real power) of the base case (no PHV
generation). Some US state mandates have set a goal of 20% renewable generation and
therefore increments of 5% up to 20% have been performed. In each case the total PHV
generation was spread evenly over 65 of the 199 load busses. This resulted in PQ bus
power flow models of the PHV generators. An arbitrary unbalanced, aggregate PHV
• phase C at 20%
For this study the peak load levels of the original distribution system case file are used.
55
difference between the individual phase apparent powers is determined with respect to
the total apparent power, |S3Φ|, at the substation. For example, between phase a and b, the
abs (| S a | − | Sb |)
| S a −b | % = *100 (5.6)
(| S3φ | / 3)
The per unit difference in voltage between two phases is calculated as:
The results of the power flow at peak loads for this study are shown in Table 1.
Twenty four hour simulations are designed to investigate the impacts the
intermittent nature of PHV generation has on the distribution system. These simulations
use the methods described in section 5.1 to create load profiles which are then matched
distribution system over the course of a 24 hour period. The environmental data provided
are single measurements taken once an hour. Therefore the simulation results are limited
56
in their ability to model system behavior for the entire 24 hour period. The results do not
represent an average of the system behavior over time they represent the system behavior
An example is provided here which studies the behavior of the 394 bus test
system on a peak load day with peak irradiance conditions. The example is similar to
that of the single flow study presented above in that the total PHV generation was spread
evenly over 65 of the 199 load busses, which results in PQ bus power flow models.
Again the arbitrary unbalanced, aggregate PHV installation at each bus was selected
with:
• phase C at 20%
For these simulations loads were categorized and scaled appropriately according
to the procedure described above. The base case which contains no PHV generators and
thus describes the load profile of the distribution system at the substation is shown in
Figure 5.2.
57
30000.00
25000.00
20000.00
P Watts
15000.00
10000.00
5000.00
0.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Hour
Figure 5.2: Real power demand of the 394 bus test case for peak load
geographical proximity to the 394 bus test system located in Elmira, NY. The day
containing the highest irradiance measurement in the TMY2 database was selected for the
environmental input as an appropriate pairing for the peak loading day of the distribution
system. The corresponding irradiance and temperature curves are show in Figures 5.3
1000
900
800
700
G (W/m^2)
600
500
400
300
200
100
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Hour
25
20
Degrees Celcius
15
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Hour
Figure 5.4: TMY2 Ambient temperature profile for Binghamton NY, July 16
The results of the 24 hour simulations are shown in Figure 5.5. As in the single flow
simulation the overall rated capacity of installed PHV generation is varied from 5% to
30000
25000
20000 0%
5%
P Watts
15000 10%
15%
10000 20%
5000
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Hour
Figure 5.5: Real power demand at the substation under varying capacity of PHV
generation
simulate the power output of an example PHV generator over a 24 hour period using an
available environmental profile. Figure 5.6 shows the power output of a 1000W PHV
generator under the same environmental conditions used in the previous section
900
800
700
600
P (Watts)
500
400
300
200
100
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Hour
By comparing Figure 5.6 to Figures 5.3 and 5.4 it can be seen that the power
output of a PHV generator is most heavily impacted by the irradiance incident upon its
surface. This conclusion is in agreement with Chapter 3 which states that the electrical
energy output of a PHV generator is most directly proportional to the energy input in the
Figures 5.3 and 5.5 show one of the potential impacts a high penetration of PHV
generation may have on distribution systems. Solar irradiance and thus PHV generator
production peaks at 1:00pm followed by a sharp drop off while the load demand peaks at
3:00pm and drops off more slowly towards the end of the day. Therefore overall system
demand changes rapidly during this afternoon drop off in solar radiation. This change in
load profile could present a new challenge for distribution system planners and operators.
61
6.1. Conclusions
This thesis provided a review of PHV generators and presented the development
of a mathematical model of a grid connected PHV generator practical for use in large
scale distribution systems studies. The model was implemented and integrated with an
performed using a 394 bus test system with the purpose of identifying and characterizing
The presented PHV generator model was designed specifically for distribution
system studies. Therefore, environmental and generator input parameters were limited to
those readily available to distribution system planners and operators. The PHV generator
model was created using the generally accepted I-V characteristic equation of a PHV cell
as its basic building block. The model accounted for the two most common inverter
control schemes by allowing for integration with distribution power flow as either a
constant PQ or constant P|V| source. The model can be integrated with several methods
of distribution power flow and specific schemes for integration with the Newton
capture the intermittent nature of PHV generation. Hourly load levels were calculated
using test system peak load levels and publicly available distribution load profiles. These
methods were then used along with hourly environmental data to develop case files for 24
hour simulation of distribution systems with installed PHV generation. Simulations were
62
performed with a 394 bus test system using both single flow and 24 hour simulation
generation. Specifically phase balancing, feeder balancing, system demand profiles, and
steady state distribution system modeling. The following contributions to this research
• Practical PHV generator model for systems engineers requiring limited input data
• Matlab based simulation tool which integrates the PHV model with an unbalanced
• Simulation methods, results, and analysis for 24 hour system studies using a 394
This thesis provides an additional component model which increases the breadth of cases
available for steady state distribution system studies, including an example of its
This thesis can be seen as a first step towards the comprehensive study of grid
connected PHV generation, its system impacts and possible control schemes to enhance
levels of grid connected PHV generators increase the behavior of distribution systems
will become increasingly impacted by the intermittent nature, and single phase
characteristics of this renewable energy source. It may be necessary for new schemes to
be developed for applications such as load balancing, capacitor placement and switching,
service restoration, and distribution automation for economic operation. This work
provides engineers with a model which can be used to perform the system studies for
This model could be used as a predictive tool where predictions of load and
environmental data could be used to predict the steady state behavior of a given
distribution system with grid connected PHV generation. Such an application would
require additional investigation regarding the PHV model in order to assure the model
accurately predicts the behavior of a physical system within a certain margin of error.
Such investigations are problematic because they would require a physical PHV
measure environmental inputs and system conditions. The cost of a residential sized
PHV generator is on the order of $10,000 and proper installation requires an appropriate
space with unobstructed southern exposure that is also accessible for measurement.
The model presented in this thesis can be utilized in a multitude of studies and
investigations. It provides engineers with a steady state simulation engine for distribution
64
system studies with grid connected PHV generation. It can be used to simulate and
analyze distribution systems with varied PHV connection schemes and varied levels of
installed PHV capacity only a few of which are included in this work. It can also be used
to test and optimize control schemes designed for the case of distribution systems with
grid connected PHV generation. This work presents only a sample of the applications for
which this model may be used to improve planning and operations for distribution
References
[1] K. Aoki, T. Ichimori and M. Kanezashi, "An efficient algorithm for load balancing of
transformers and feeders by switch operation in large scale distribution systems," IEEE
Trans. Power Del., vol. 3, pp. 1865–1872, Oct. 1988. 1988.
[3] M. E. Baran and F. F. Wu, "Network reconfiguration in distribution system for loss
reduction and load balancing," IEEE Trans. Power Del., vol. 4, pp. 1401–1407, Apr.
1989. 1989.
[5] L. Castaner and S. Silvestre, Modeling Photovoltaic Systems using PSpice. West
Sussex, England: Wiley, 2002,
[7] H. Chihchiang and S. Chihming, "Study of maximum power tracking techniques and
control of DC/DC converters for photovoltaic power system," Power Electronics
Specialists Conference, 1998. PESC 98 Record. 29th Annual IEEE, vol. 1, pp. 86, May
17-22. 1998.
[11] J. Grainger and W. Stevenson, Power System Analysis. New York: McGraw-Hill,
1994, pp. 787.
[12] F. Groppi, "Grid-connected photovoltaic power systems: Power value and capacity
value of PV systems," International Energy Agency, Milano, Italy, Tech. Rep. IEA PVPS
T5-11: 2002, February, 2002.
[20] T. Markvart, Solar Electricity. Chichester, England: John Wiley & Sons, 1994,
[21] R. Messenger and J. Ventre, Photovoltaic Systems Engineering. USA: CRC Press,
2004,
67
[22] K. N. Miu and H. D. Chiang, "Service restoration for unbalanced radial distribution
systems with varying loads: solution algorithm," IEEE Pwr. Eng. Soc. Summer Meeting,
vol. 1, July 1999. 1999.
[25] K. N. Miu, H. D. Chiang, B. Yuan and G. Darling, "Fast service restoration for
large-scale distribution systems with priority customers and constraints," 20th Int. Conf.
on Power Industry Computer Applications, pp. 3-9, 11-16 May 1997. 1997.
[26] S. Naka, T. Genji and Y. Fukuyama, "Practical equipment models for fast
distribution power flow considering interconnection of distributed generators," IEEE
Pwr. Eng. Soc. Summer Meeting, vol. 2, pp. 1007 - 1012, 15-19 July 2001. 2001.
[27] National Renewable Energy Laboratory (NREL), "Typical Mean Year 2 Database,"
http://rredc.nrel.gov/solar/old_data/nsrdb/tmy2/.
[28] Renewable Resource Data Center, "Solar Radiation Resource Information," 2006,
http://rredc.nrel.gov/solar/. 2006.
[32] J. C. Wang, H. D. Chiang, K. N. Miu and G. Darling, "Capacitor placement and real
time control in large-scale unbalanced distribution systems: loss reduction formula,
68
[36] R. D. Zimmerman and H. D. Chiang, "Fast decoupled power flow for unbalanced
radial distribution systems," IEEE Trans. on Power Systems, vol. 10, pp. 2045 - 2052,
Nov. 1995. 1995.
69
PGDC = calculated real power output of the array at given conditions (W)
Pra = rated DC power output of the array (W)
VocM = module open circuit voltage (V)
I scM = module short circuit current (A)
( I mM , VmM )= module maximum power point (A, V)
I A = N p Ic
I scA = N p I sc
VA = N sVc
VocA = N sVoc
N s = number of cells connected in series
N p = number of cells connected in parallel
I scA = short circuit current of the array (A)
VocA = open circuit voltage of the array (V)
4. Model of the Power Conditioning Unit and Integration with Power Flow
It will now be shown how equation (3.19) has been developed. Given the I-V
characteristic equation of the solar array at standard test conditions (1000 W/m2, 25ºC):
⎛ (VArnN+ I kT
Ar RsA ) q
⎞
I Ar = I scAr − N p I0 ⎜ e s cK
− 1⎟ (B.1)
⎜ ⎟
⎝ ⎠
Set the current to zero in order solve for the open circuit voltage:
⎛ nNVocArkTq ⎞
0 = I scAr − N p I 0 ⎜ e s cK − 1⎟ (B.2)
⎜ ⎟
⎝ ⎠
kTcK ⎛ I scAr ⎞
VocAr = ln ⎜1 + ⎟ (B.3)
q ⎝ Io ⎠
⎛ ∂V ⎞ kT ⎛ I ⎞
VocAr + ⎜ ocA ⎟ (Tc − Tc 0 ) = cK ln ⎜ 1 + scAr ⎟ (B.4)
⎝ ∂Tc ⎠ q ⎝ Io ⎠
Similar to equation 6.
kTcK ⎛ I scAE ⎞
VocAE = ln ⎜1 + ⎟ (B.6)
q ⎝ Io ⎠
74
⎛ ∂V ⎞ kT ⎛ I ⎞ kTcK ⎛ I scAr ⎞
VocAE = VocAr + ⎜ ocA ⎟ (Tc − Tc 0 ) + cK ln ⎜1 + scAE ⎟− ln ⎜ 1 + ⎟ (B.7)
⎝ ∂Tc ⎠ q ⎝ Io ⎠ q ⎝ Io ⎠
⎛ I ⎞
⎜ 1 + scAE ⎟
⎛ ∂V ⎞ kT Io
VocAE = VocAr + ⎜ ocA ⎟ (Tc − Tc 0 ) + cK ln ⎜ ⎟ (B.8)
⎝ ∂Tc ⎠ q ⎜ I scAr ⎟
⎜ 1+ I ⎟
⎝ o ⎠
In general unity can be neglected in the numerator and denominator of the log term in
⎛ ∂V ⎞ kT ⎛I ⎞
VocAE ≈ VocAr + ⎜ ocA ⎟ (Tc − Tc 0 ) + cK ln ⎜ scAE ⎟ (B.9)
⎝ ∂Tc ⎠ q ⎝ I scAr ⎠
75
In the case file load data is included for each load bus at conditions of peak
demand. Many combinations are possible for the type of load and model used. Balanced
or unbalanced, and grounded or ungrounded load types are possible and each load can be
modeled using the constant power, constant impedance or constant current load models.
Regardless of the model used however the load data which is input to the model is in the
(S A
P,k , S PB,k , S PC,k ) (C.1)
where:
such as a given hour of a given day of the year it is necessary to scale this peak load in an
appropriate manner to describe the situation which is desired for test. Load scalars are
defined in order to perform this function. Because different types of loads exhibit
different loading profiles three types of loads are considered separately, these are
industrial, commercial and residential loads. Scalars are calculated for each type of load
in order to model the load behavior of the entire system more accurately. Two scalars are
used to calculate the load level for a specific hour of a specific day of the year. The first
scalar Sd d referred to as the day scalar is used to calculate the peak load on a given day
(C.2):
76
| S Pd ,k |=| S P ,k |i Sd d( I ,C , R ) | (C.2)
where:
Sd d = day scalar for day d
( I ,C , R )
= denotes (industrial, commercial, residential) load type
S Pd ,k = peak power consumption on day d on bus k (kVA)
The parameter Sd d is calculated from a given set of loading data. It is not necessary for
the load data to be specific to the distribution system under test, it is only necessary that
the load data be from a distribution system load of the same type (I,C,R). Sd d is
calculated as follows:
| SlPd |
Sd d = (C.3)
| SlP |
where:
SlPd = peak load on day d from given load data
SlP = peak load for the entire year from given load data
Once the peak load on a given day is determined the load for any hour of that day
can be calculated using the scalar Shd , h referred to as the hour scalar, as follows:
where:
Shd , h = hour scalar for day d, hour h
S d ,h ,k = power consuption on day d, hour h, at bus k
The parameter Shd ,h is calculated from load data on the given day in a similar manner as
| Sld , h |
Shd ,h = (C.5)
| SlPd |
where:
Sld ,h = power consumption for day d, hour h, from given load data
In this manner given the necessary load data the power consumption for all load
busses on the 394 bus test system can be determined for any day of the year at any hour
of the day. This describes the ideal case where daily load data is available for the period
of a year. This specific data is not always available, as often load data is grouped by
season where four sets of data are used to describe average days for the four seasons. In
this case the calculations above are valid however it would be appropriate for notation