Project Control
Project Control
PROJECT MANAGEMENT
CONSULTANCY
© Mo. Elsheikh
PMC
Project Controls Scope
Phase 1 (0 - 14 days)
1. Provide a detailed mobilisation programme including a Forty-five-day (45) look-ahead
WORK STAGE DELIVERABLES
schedule.
2. Establish communication, reporting and authorization procedures to operate between the
Client, the Consultant, the Client’s other consultants and contractors through PMIS.
3. Establish Portfolio and Project level Project Execution Plan (PEP) frameworks based on
Client portfolio-level plan (Portfolio Management Plan PMP).
4. Submit a Master strategic programme, including strategic milestones per project for the
purpose of establishing a baseline programme.
Page 1
2024© MO.ELSHEIKH
PMC
Project Controls Scope
requirements.
2. Formulation and Monitoring of Risk Register :
Coordinate the production of a risk register, with input from all parties, to ensure
accountability and tracking of any risks to the project’s success.
3. Start of Construction Works :
A first-month programme, to a per-day level of detail, is to be obtained from the
contractor to ensure that works are commenced on time and are undertaken at
maximum efficacy from the outset.
4. Monitoring of Construction Works :
A. Monitor the progress of works on a continuous basis and undertake various methods
to ensure the works progress is in line with the contract program.
B. In the event of any work slippage by the consultants, the Consultant shall issue
necessary contractual notices to remedy the situation and recover the delays or faults.
C. In the event of any work slippage by the contractors, the Consultant in alignment with
the CSC shall issue any necessary contractual notice and take necessary actions.
D. In the event of any applications for requests for any change, or claims, the Consultant
shall prepare a detailed estimate and evaluation for such work and assist in the
negotiation and dispute resolution.
E. Advising the Client in the event of persistent failure by the Construction Supervision
Consultant(s) and Contractor(s) to comply with the Contract Documents and in the
event of an unsatisfactory rate of progress.
F. Ensure that Construction Supervision Consultant(s) and Contractor(s) KPIs evaluations
are evaluated and validated.
Page 2
2024© MO.ELSHEIKH
PMC
Project Controls Scope
3. Advise and recommend any such additional procedure(s) that the consultant considers
would assist in the timely completion of the work. The content and extent of these
requirements can be modified by the Client, if necessary, to suit the Contract's
requirements.
B. Project Management Delivery System
1. Provide, submit, and get Client approval on the Project Execution Plan (PEP/s) on the basis
of the Client Portfolio Management Plan (PMP) which shall define all processes,
procedures, and responsibility matrix.
2. Perform and manage all tasks as listed in the PMP and project management standards for
the post-contract stages.
3. Prepare and submit a Project Execution Plan (PEP), which should include, but not be limited
to, the Project organizational structure; Project team responsibilities and reporting
relationships; and the Consultant’s strategy for managing the Project, coordinated plans
to collectively define, describe and encompass the Consultant’s proposed, systems
methods, procedures, confirmation processes, sequencing of activities, and the like and
shall show how these combined together demonstrate Client’s requirements.
4. The PEP shall include, among other things: A stakeholder management and
communication plan; an Environmental Management System (EMS); Schedule
management plan; Reporting system; Key performance index; Project master schedule;
Risk and opportunity management plan; QS and cost control system; Change control
management system; Contract administration plan; Claims management plan;
Construction supervision manual; Construction standards and specifications; Defects
liability period management plan; Communications and document management plan;
Quality management plan; Health, safety and security management plan; Environmental
management plan; Sustainability plan; Utility management plan; Traffic consent plan;
Engineering plan; Procurement plan; Public Relation management; Testing and
commissioning management; Operations and maintenance period management plan; and
Project transfer, handover and Consultant’s demobilisation plan.
5. Perform and manage all tasks as listed in PEP and project management standards for the
post-contract stages. PEP may be updated periodically to suit changes to the project
circumstances.
Page 3
2024© MO.ELSHEIKH
PMC
Project Controls Scope
upon the revised schedule, revised resources deployment and revised milestones.
4. Monitor and review, on a weekly basis, the construction progress and performance and
advise the Client accordingly. This shall be done using planning software, Primavera (P6)
version 17.0 or above or other Client-approved software to achieve prompt and accurate
reporting.
5. Validate all types of Project schedules prepared by the Consultants and Contractors and
report to the Client on the overall compliance with milestone objectives and the viability
of the schedules and establish a permit/statutory approval schedule.
6. An interim update of planning documents shall be operated if deemed necessary at the
request of the Client (i.e. weekly, fortnightly, etc.).
D. Reporting
1. Establish a ‘PMWEB’ web-based reporting and information-sharing tool that will provide
web-based reports, analysis, and dashboard metrics to highlight critical data points and
actively share information with all necessary stakeholders.
2. Submit plans and periodic/final (Close-out) reports in-due time as requested by the client),
The report shall be in the format given the Client’s Requirements and Guidelines.
3. Submit an Inception Report after four weeks from the commencement of services. The
Report shall contain a detailed work programme and a brief description of the updated
work methods proposed for carrying out the services in accordance with the Terms of
Reference. The report shall also identify any significant issues and problems likely to be
encountered.
4. Upon request from the Client, the Consultant shall provide the updates for weekly project
dashboard reports in a format to be agreed upon by the Client to clearly detail the status
of all key elements of the Project or a part thereof as directed by the Client.
5. If deemed necessary by Client, other reports and presentations shall be generated by the
Consultant when asked to do so and assist in presentations by Client.
Page 4
2024© MO.ELSHEIKH
PMC
Project Controls Scope
Page 5
2024© MO.ELSHEIKH
PMC
Project Controls Scope
Page 6
2024© MO.ELSHEIKH
PMC
Project Controls Scope
I. Risk Management
1. Prepare a Risk and Opportunity Management framework and submit a complete
Qualitative and Quantitative Risk Register.
2. Manage the project cost and commercial risk during the construction and maintenance
periods.
3. Structure a process for documenting and reporting on the status of identified risks on a
CONSULTANT DELIVERABLES
2024© MO.ELSHEIKH
PMC
Project Controls Scope
L. Meetings
1. Convene/chair all meetings as required, including but not limited to meetings on progress,
CONSULTANT DELIVERABLES
Page 8
2024© MO.ELSHEIKH