Steam Blowing Procedure
Steam Blowing Procedure
SIEMENS LTD.
62OP42654_U1_643010112 -
Responsible Department Take over Department Doc type Folder No. :
IST COE IND TPE IST OPS VAD P BOP TI
Prepared : Checked : Approved : Language :
MS 28.12.2020 BMK 28.12.2020 MP 28.12.2020 EN
Valid for : Derived from : Replaces : E file no.
GP PG IST 643010112.doc
Project Name :
1 x 14MW MARWAR MUNDHWA WHRS PROJECT
Customer :
THYSSENKRUPP INDUSTRIES INDIA PVT. LTD.
End Customer :
LAFARGE HOLCIM LTD.
INDEX
Turbine Requirements
S. No. Document Title Document No. Rev
1.0 Steam Condition
1.1 Steam Purity for Turbine Operation STIM-11.002 F
1.2 Main Steam Parameters Variation 1CYJ470056 -
2.0 Auxiliray System "Lube Oil"
2.1 Turbine Oil Cleaning and Flushing 1CYJ464025 D
2.2 Inservice Monitoring of Mineral Turbine oils for Steam Turbines 1CYJ470058 -
2.3 Lubrication Oil TLV 9013 05 A
3.0 Steam Blowing
3.1 Steam Blowing procedure 2CWN002896 G
4.0 Non Return Valves
4.1 Installation of QCNRV in Steam Line 1CYJ470057 A
5.0 Safety
5.1 Saftey Precautions 1CYJ470059 -
6.0 Piping
6.1 Turbine Piping Guidelines 1CYJ470060 B
6.2 Heater's Drain Piping 1CYJ470061 -
Flushing and Chemical Cleaning of TG Steam, Condensate and Feedwater
6.3 1CYJ464026 A
piping.
Unrestricted
Document type
No.: STIM-11.002
Steam Turbine Information Manual
Revision/Date: F 2014-08-29
EXPORT CONTROLLED
Technology specified in the CCL, AL or ECL
This document is subject to U.S. and/or national export regulations. Unauthorized diversion may be prohibited. In cases of
doubt contact your Export Compliance Department.
Dieses Dokument unterliegt nationalen und/oder U.S. Ausfuhrvorschriften. Die Verbreitung kann eine Genehmigung
benötigen. Im Zweifel wenden Sie sich an Ihre ECC Abteilung.
This document contains the turbine steam purity specification for main and auxiliary steam
condensate from the steam turbine manual, document number 1.1.3-42100-00003.
REVISION SHEET
start-up
Technical Instruction:
Main steam parameters variation
(As per EN ISO 60045-1, formerly IEC45-1)
_________________________________________________________________________________________________________________________________
We reserve the rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly
forbidden. © SIEMENS Ltd.
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
The steam conditions at inlet to the ESV. The limitations placed on variations of initial pressure
and initial temperature in 6.2 a) and 6.2 b) respectively are appropriate for a turbine supplied
with steam from a fossil-fired boiler or other high temperature source.
For a turbine supplied with steam at or near saturated conditions, for example from a nuclear
reactor, waste-heat recovery steam generators, non fossil-fired boilers the limitations to be
placed on initial steam conditions shall be agreed between the purchaser, the reactor supplier
and the turbine supplier.
a) Initial pressure
The average initial pressure at the turbine inlet over any 12 months of operation shall not
exceed the rated pressure. In maintaining this average, the pressure shall not exceed 105% of
the rated pressure. Further accidental swings not exceeding 120 % of the rated pressure are
permitted, provided that the aggregate duration of such swings over any 12 months of
operation does not exceed 12 h (but see note at the end of 6.2). Pressure limits on lower side
from rated value shall be applicable as per SIEMENS recommendation.
The average steam temperature at any inlet to the turbine over any 12 months of operation
shall not exceed the rated temperature.
In maintaining this average, the temperature shall not normally exceed the rated temperature
by more than 8K. if, exceptionally, the temperature exceeds the rated temperature by more
than 8K, the instantaneous value of the temperature may vary between this figure and a value
of 14K in excess of the rated temperature, provided that the total operating time between these
two limits does not exceed 400 h during any 12 months operating period.
Operation between limits of 14K and 28K in excess of the rated temperature may be permitted,
for brief swings of 15 min or less, provided that the total operating time between these two
limits does not exceed 80 h during any 12 months operating period.
In no case shall the temperature exceed the rated temperature by more than 28K.
Temperature limits on lower side from rated value shall be applicable as per SIEMENS
recommendation.
The average exhaust pressure shall not exceed the specified exhaust pressure over any 12
months operating period. In maintaining this average, the exhaust absolute pressure shall not
exceed the rated pressure by more than 10 % nor drop more than 20 % below it.
Exhaust pressure limits (Vacuum) for condensing turbines as per Siemens guidelines.
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
d) Abnormal operation
The purchaser shall clearly specify his requirements if operation is required in any of the
following categories, as a part of contract.
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Document No. Rev.No.
Contents:
_________________________________________________________________________________________________________________________________
We reserve the rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly
forbidden. © SIEMENS Ltd.
As a general rule it shall be observed that no turbo set must ever be started before the oil system has
been flushed in accordance with the present standard.
All prefabricated pipes supplied shall have been as far as possible cleaned and treated with a
preservation agent according to specification (1CYJ464027). If the pipes have not been flushed, they
shall be tagged accordingly and flushed at site.
If the pipes cannot be mounted immediately, they shall be suitably stored to avoid new contamination
(Pipe ends to be covered with a plastic lid; storage not in the vicinity of sand blasting or grinding work).
Pipes, which need not be adjusted or welded any more on site, shall be thoroughly checked for
cleanliness and be cleaned if necessary prior to their installation. Care shall be taken that no dirt particles
are retained due to the preservation agent. Removal of the preservation and dirt shall be done with a cold
cleansing agent followed by blowing out with air (the regulations governing the use of hazardous material
must be observed).
Before starting the work to be done, the areas to be welded of the pipes prepared for welding shall be
cleaned from the preservation by means of a solvent (mind the regulations governing the use of
hazardous material). Inert-gas-shielded welding shall be used for all welds.
Prior to starting oil flushing the oil tank shall be checked for contamination and if required to be cleaned
properly. Same is applicable for Overhead Oil Tank (if applicable), Drain Oil Tank (if applicable) &
Collecting Oil Tank (if applicable) also. Before filling the oil tank with turbine oil for the first time, the oil
tank shall be subjected to an acceptance test and a corresponding report issued. The same procedure
shall be carried out before refilling the turbine oil after flushing.
Oil Filter cartridges to be removed and filter casing to be checked for contamination and if required to be
cleaned properly.
Independent of the flushing procedure, the bearing housings shall be subsequently checked and
thoroughly cleaned.
Remarks!
2. Flushing circuit
2.1. Flushing circuit of the Lube oil system (Refer to Flushing PID)
The flushing oil is bypassed at the bearings by means of bypass connection between bearing inlets and
outlets. The flushing oil is also bypassed around the oil-containing equipment which is susceptible to
functional disturbances in the case of minor oil contaminations.
For flushing the suction and pressure pipes of a shaft driven Main oil pump, the pressure-side non-return
flap valve will be removed and replaced by a spool piece. As the main oil pump is removed, there will be
sufficient space for placing a bypass between the suction pipe and the discharge pipe.
Damage of the auxiliary or emergency oil pump due to dirt particles carried into the tank by the flushing oil
need not be expected. The strainer screens will retain the dirt particles.
The pressure pipes of the emergency oil pump are cleaned by means of the emergency oil pump.
The non-return valve flaps of the Auxiliary and Emergency oil pumps are not dismantled for the flushing
procedure.
Temperature control valve (if applicable) shall be isolated and bypass with the help of the valve provided
with the system.
The Lube oil header pressure regulating valve (if applicable) shall be removed and replaced by a spool
piece.
Remarks!
All necessary bypass connection(s), loop(s), hose(s), spool(s), Screen(s), flanges with necessary
hardware, fittings etc. required for oil flushing shall be provided by “Erection Contractor”
2.2. Flushing circuit of the Control oil system (Refer to Flushing PID)
The bypass of the following components is part of the preparatory work for flushing the Control oil circuit:
- Servomotor(s)
- Current to Pressure convertor / I to H converter
- Safety Block
- Valve Actuator for Emergency Stop Valve
For flushing the orifice provided in the inlet of servomoters shall be removed.
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
4
1CYJ464025 D
In order to avoid that any blind flanges and other flushing facilities remain in place by mistake after
flushing, all modifications made to the system for the purpose of flushing shall be noted down on a special
list. After completion of the flushing procedure, the operating conditions of the system shall be restored
with the help of this list.
3.1.1. General
· The system will be flushed with the help of the auxiliary oil pump(s). If two 3-ph A.C driven pumps are
available, they shall be operated together to increase the effectiveness - Higher flow velocity. The
pump drive motors must be equipped with the normal protection equipment. Care shall be taken not
to exceed the admissible power input indicated on the maker’s name and rating plates of the motors.
· Monitoring of the oil level in the tank must be ensured. (For this purpose, the suction basket length
from the oil tank cover is to be measured and the oil quantity suitably determined to ensure an oil
level, at least 50 – 60% tank level to be maintained during normal flushing operation).
· All adjustable orifices in the oil supply piping shall be fully open to allow maximum flow in the system.
· Setting of the maximum possible oil flow is accomplished by closing the pressure control valve
(tightening the setting screw). Care shall be taken that the oil pressure does not exceed 2.5 Bar (g).
· To fulfill this requirement, pressure switch at oil supply header to be installed at the time of oil
flushing. An interlock also to be provided with the pump in order to avoid pressure beyond specified
limit.
· MCC protection scheme to avoid over pressure of the pump is given in Annexure I.
· A throttling plate with an open cross section of 10 % to 15 % of the inner pipe cross section or
Butterfly valve shall be installed in drain header at the last flange upstream of the oil tank. If the
throttling plate is used, opening must be situated in the bottom area of the pipe. Because of this
throttling plate entire inner cross section of the pipe will be filled with oil during flushing.
· The suction and pressure sides of the main oil pump shall be connected by means of a bypass.
· The non-return flap valve in the pressure pipe shall be removed. After the flushing procedure, the oil
channels shall be cleaned manually and by blowing out with air.
· High point vents to be provided in flushing circuit to ensure proper venting of the trapped air during
flushing startup.
The inlet pipe of the jacking oil pump shall be led direct to the oil tank by means of a bypass connected
upstream of the pump.
Both coolers are completely mounted and connected on their oil and water sides. The oil temperature is
increased by admitting hot water to the cooling water side. The oil can also be heated using the heating
coil in the tank and by using the heating coil of the oil purifier, while the pump is in operation for more than
8 hours.
· The maximum water temperature in case of water heating shall not increase 80 °C. Heating of the
water shall be done carefully and slowly to avoid a temperature shock inside the cooler. The heating
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
5
1CYJ464025 D
water circuit shall incorporate one cooler only so that quick cooling down of the oil is possible
through the second cooler.
· An oil temperature between 60- 70 Deg. C must be maintained while flushing.
· Only new flushing oil shall be used (ISOVG32 or ISOVG46) depending on which oil shall be used
during normal operation. The oil shall be delivered in accordance with Siemens specification &
Technical delivery terms (TLV 9013-05) and amount of oil required shall be as per specification
provided by SIEMENS.
· The flushing oil can be reused as first fill lubrication oil as per technical instruction provided by
SIEMENS (Refer document no. 1CYJ461103E43)
4.1. General
Pipes which are properly ground and pickled are free from scale and weld splatter. Oil flushing is primarily
intended to remove from the oil system any loose foreign particles that are lying in the pipes or dirt
sticking to the wall.
· Efficient oil flushing is only possible if the following requirements are fulfilled:
The oil must flow through the pipes at the highest velocity possible.
Before starting the oil pumps for the first time, the pressure control valve is fully opened. As soon as the
Auxiliary pump is in operation, the control valve is slowly closed while observing the oil flow as well as the
pump capacity (take care that the power consumption of the oil pumps is in accordance with the
admissible rating data of the motors, i.e. that the pumps are not overloaded), in order to achieve
maximum flow velocity in the oil pipes.
· High flow velocities will be achieved if the overall oil system is divided into partial systems. (Please
refer point no. 4.2 for further details)
Particles which are sticking to the inside walls of the pipe are to be loosened by the effect of thermal
shocks (differential expansion).
b) After heating of the oil system and oil pipes, cooling down is achieved by stopping the lube oil pump.
This abbreviates the duration of the flushing procedure and saves time.
Remarks!
· The heating and cooling method described under a) should always be used because this type of
temperature change has the greatest effect.
During flushing, the pipes shall be hammered with a high-frequency pneumatic vibrator fitted with a
copper or hard-rubber top, so that any dirt sticking to the walls is loosened and can be carried more easily
by the lube oil flow to the oil tank strainer. If a pneumatic vibrator is not available, the pipes shall be
hammered by hand with the help of a plastic hammer.
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
6
1CYJ464025 D
Remarks!
· During this, care shall be taken to avoid any damage to the pipes and pipe supports.
The oil is cleaned with the filters or strainers or screens / flushing oil filter installed in the drain header.
· Flushing should be carried out for each lines as per below steps to achieve high flow velocities in oil
lines.
Remarks!
· During the flushing procedure, the flushing oil is circulated by means of the Auxiliary oil pump. In the
oil return line to the tank, screen of 200 microns mesh size has to be installed. Gradually reduce the
screen size to 150, 100, 50 & 30 microns as contamination reduces. Same procedure to be followed
for Step 1, Step 2 & Step 3.
After step 3 when the 30 micron screen in the return oil line is clear, the relatively short pressure pipe of
the Emergency Oil Pump shall be flushed. For this purpose, the pump shall be operated for 2 - 3 hours.
After that 30 micron screen shall be remain in clean condition, if not continue flushing for emergency oil
line until system is clean.
Remarks!
· All other oil pumps shall be shut down during that time.
· All Connections / loops prepared for Step 3 should remain as it is for flushing Emergency oil pump
lines.
After the above cycle & when 30 micron screen in the return line is clear remove the bypass connection to
the bearings of Turbine, Gear unit & driven machine and install lube oil filter elements.
Ensure the level of the oil tank is to 50 - 60 % of the operating oil quantity. Now lube oil is circulated in the
lube oil system with main oil filters.
Start the flushing of system and run for a minimum of 2 hours & ensure that main filter elements are in
clean condition. If the filter differential pressure reaches the value of contamination, clean/replace the
filter elements.
The flushing shall be considered complete when the filter differential pressure remains essentially
unchanged for 4 hours and the solid contamination code conforms to the 19/17/14 contamination code
outlined in ISO 4406.
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
7
1CYJ464025 D
4.2.3. Flushing of the Control oil system
Before terminating the flushing procedure of the lube oil system, the control oil system shall be
incorporated into the flushing circuit. Flushing of the control oil system is completed when the differential
pressure remains essentially unchanged and the service life of the control oil filters (if applicable)
exceeds 24 hours.
Connect the jacking oil supply line(s) to the jacking oil pump(s). All jacking oil pressure lines to be
connected to lube oil return lines with hoses.
Start the lube oil pump and than jacking oil pump. Keep them in operation for at least 4 hours. Shut down
the first jacking oil pump and start the second one (if applicable) and keep them in operation for at least 4
hours.
Reinstall jacking oil piping / tubing and repeat the procedure for turning gear tubing (if applicable)
Remarks!
A high degree of oil purity in the turbine oil system is required in order to prevent damage to bearings (or
jamming), gear transmission and all other oil supplied components, and also for operation of turbine
control system.
The worldwide accepted and up-to-date standard for classifying the oil purity is ISO 4406:1999. According
to this standard, the number of particles of the sizes > 4 µm, > 6 µm and > 14 µm is determined that exist
in a sample of 100 ml of the liquid to be examined. The particles can be counted either microscopically or
with the help of an automatic particle counting device.
ISO class 19 / 17 / 14 says that the following are found in 100 ml of analyzed sample:
250000 - 500000 particle > 4 µm (c)
64000 - 130000 particle > 6 µm (c)
8000 - 16000 particle > 14 µm (c)
· All flushing pipes, bypasses, screens, blind flanges and orifices installed or attached for the purpose
of flushing shall be removed and the "dead ends“ resulting thereof or the fittings and pipe sections
dismantled shall be manually cleaned and re-installed.
· The bearings and oil channels of the bearing housings which are part of the flushing circuit shall be
manually cleaned and mounted together with the upper part of the bearing ready for operation.
· The bypasses at the main oil pumps shall be removed and the “dead ends” resulting thereof or fittings
shall be manually cleaned and re-installed.
· The suction filter of the main oil pump, auxiliary oil pump & emergency oil pump shall be cleaned
internally and re-installed.
· The non-return flap valves in the pressure pipe of the main oil pump shall be re-installed.
Important: Be careful to install the non-return flap valve for operation in the correct direction.
· All filter elements must be checked for cleanliness and thoroughly cleaned prior to assembly. Also
check and clean the filter housing carefully.
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
8
1CYJ464025 D
· After termination of the flushing procedure, the oil tank shall be drained and cleaned. In case the
same lube oil is to be used for later operation, it shall be purified, filtered and returned to the oil tank
via an oil purification system.
Remarks!
· The oil shall be drained in warm condition. Make sure that the heaters are switched off before the oil is
drained. Make also sure that all oil has been drained from pipes, coolers, components low points, etc.
· Before draining the oil tank, it is advisable to allow for a certain settling time of about one day so that
all dirt particles can settle on the oil tank floor.
· Before filling in the filtered turbine oil, the oil tank shall be checked and a corresponding report be
issued.
· All non-return flap valves installed in the oil systems shall be checked for correct installation and
trouble-free operation.
· Any expansion joints (rubber or metal) incorporated in the piping system shall be dismantled and
cleaned.
· By installing pressure gauges at the measuring points downstream of the inlet orifices, it is possible to
check the lube oil flow to the bearing.
6. Check list
For the flushing of the oil system a check list shall be completed which comprises the following pages:
This check list is to demonstrate that the individual points under this factory standard have been properly
complied with.
The check list is allocated to the documentation of new equipment, provided with a corresponding
document number and documented accordingly.
The individual items on the check list will be checked one by one and either be ticked off or completed
with additional information (remarks), as applicable.
The person who has attended to the individual point shall confirm the proper execution of the work by
signing with his name and date at the corresponding place on the check list.
· Reference Documents :
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Annexure I
Auxiliary / Main
oil Pump Motor
Note : The above circuit represents conceptual view and same need to be followed
in project specific MCC circuit.
Document No. Rev.No.
2 1CYJ470046 -
1. Flushing Turbine Oil Systems : Check List
Machine Type :
Step 1 :
Remarks Date Name
Piping System
1) Branches
2) Tapers
3) Gauge connections
1) For Dirt ?
2) Weld seams ?
Step 2 :
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
3 1CYJ470046 -
Step 3 :
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
4 1CYJ470046 -
Step 4 :
Step 5 :
Date Name
Checked
Released
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Document No. Rev.No.
Cleaning Procedure:
2 1CYJ464025 B
This specification aims at the cleaning procedure for carbon steel, stainless steel piping, oil tanks and oil
coolers for oil system.
1) Deburring:
Remove scale and corrosive layer by a wire brush or by sand-blasting method. For smaller sizes
of pipes pull method of wire brush can be adopted.
2) Cleaning :
3) Pressure Testing :
The pressure test of the pipes shall be carried out as mentioned below:
4) Anticorrosive Treatment :
After caring out pressure testing of the pipes, blow hot air through the pipes to remove water
particles.
Apply “RUSTOP-274” or “TECTYL-511” on the inner as well as outer surface of the pipes and blow
compressed air to spread it thoroughly.
All Holes / Openings in the pipes shall be plugged by Plastic / Wooden plugs.
1) Cleaning :
Clean the pipes by a wire brush. For smaller sizes of pipes pull method of wire brush can be
adopted.
2) Wiping :
Clean the interior of the pipes with linen cloth drawn through the pipes.
Prior to cleaning, excessively dirty pipes should be degreased in Neutralising solution which is
prepared by mixing 3 kgs of Caustic Soda with 100 ltrs of water.
_________________________________________________________________________________________________________________________________
_____
Format No.: DDIT3009
REV./Date : A/08.12.2005
Page: Document No. Rev.No.
3 1CYJ464025 B
3) Pressure Testing :
The pressure test of the pipes shall be carried out as mentioned below:
1. All Control Oil pipes to be pressure tested at 12 barg.
2. All Lube Oil pipes to be pressure tested at 4 barg.
3. All Return Oil (Drain) pipes to be pressure tested at 2 barg.
Note
Brush, steel wool and wire rope should not be of Carbon steel material.
Remove scale, corrosion, burrs, metal / weld lumps from tank as well as nozzles & fitment of the
tank.
1. Clean properly weld areas &remove all weld spatters.
2. Perform sand /shot blasting.
2) Cleaning :
1) Deburring:
1. Remove scales, corrosion, burrs, metal lumps etc. from shell as well as holes provided for fitment
of nozzles.
2. Remove scales, corrosion, burrs, metal lumps etc. from both dished ends as well as holes
provided for fitment of nozzles.
3. Clean properly weld area of shell & dished ends & remove all weld spatters.
4. Sand blast shell & dished ends.
CLEANING OF SHELL & DISHED ENDS AFTER WELDING OF FITMENTS BUT BEFORE WELDING
OF TUBE SHEETS WITH SHELL.
1. DEGREASING: Degrease and clean shell and dished ends with detergent water.
2. CLEANING: Take hydrochloric acid of 30-35 % concentration. Mix with water in the ration of 1:10.
Put shell & dished ends in the above solution.
_________________________________________________________________________________________________________________________________
_____
Format No.: DDIT3009
REV./Date : A/08.12.2005
Page: Document No. Rev.No.
4 1CYJ464025 B
Duration – 8 hours approx.
3. WASHING: Wash shell & dished ends with plain normal water. Ensure no trace of HCL is left out.
Take 3 kg of caustic soda and mix it with 100 litres of water. Put shell and dished ends in the
solution. Solution temperature may reach 90 deg. c due to exothermic reaction.
CLOSE OIL INLET& OUT LET NOZZLES WITH DUMMUY FLANGE & GASKET IMMEDIATELY AFTER
WELDING OF TUBE SHEETS WITH SHELL.
2. Dry with hot air. Ensure no water particles are left out inside the cooler.
3. Apply rustop-274 inside & out side surface of cooler as rust preventive. Ensure application of
RUSTOP on inside surface of shell & dished end of the cooler.
4. Close all the nozzles with dummy flange and gasket to avoid dust getting inside.
_________________________________________________________________________________________________________________________________
_____
Format No.: DDIT3009
REV./Date : A/08.12.2005
Document No. Rev.No.
Technical Instruction:
Reusing flushing oil as first fill
_________________________________________________________________________________________________________________________________
We reserve the rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly
forbidden. © SIEMENS Ltd.
2 1CYJ461103E43 -
General:
Lube Oil System shall be flushed before first turbine start as per Flushing of Turbine Systems
(1CYJ464025)
Draining of flushed oil shall be done through centrifuge only. Flushed oil shall be collected
to empty oil drums / drain oil tank (If provided) only.
Centrifuge suction line to be connected to Main oil tank drain line provided at tank bottom &
centrifuge discharge line pipe to be connected to empty oil drum / drain oil tank (If provided)
Before draining the oil tank, it is advisable to allow for a certain settling time of about one
day so that all dirt particles can settle on the oil tank floor.
The oil shall be drained in warm condition. Make sure that the heaters are switched off
before the oil is drained.
Make also sure that all oil has been drained from all pipes, both coolers & filters,
components low points, etc.
Temporary piping / hose pipe to be used for draining oil form all pipes, both coolers & filters,
components low points, etc.
All components to be cleaned after draining of flushed oil as per Flushing of Turbine Systems (1CYJ464025)
Refilling of flushed oil shall be done through centrifuge only, collected in empty oil drums /
drain oil tank (If provided).
Centrifuge suction line to be connected to empty oil drum / drain oil tank (If provided) and
centrifuge discharge line pipe to be connected to main oil tank oil filling line or centrifuge
return line.
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Document No. Rev.No.
Technical Instruction:
In-Service Monitoring of Lube Oil for Steam
Turbines
_______________________________________________________________________________________________________________________________
We reserve the rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is
strictly forbidden. © SIEMENS Ltd.
1CYJ470058 -
1. General:
The guidelines in this document are based on practical experience from SIEMENS Ltd. and
international standards for condition monitoring of lubricating oils.
This document is intended to assist the user to maintain effective lubrication of all parts of the turbine
generator set. It includes information and recommendations regarding lubricating oil quality, sampling
and testing schedules and actions that must be taken if the quality of the lubricating oil is not within
given recommendations.
The document is not universal and cannot be expected to cover all issues that may be connected to
lubricating oil.
Turbine oil is usually paraffin based mineral oil consisting of a mixture of saturated hydrocarbons and
different additives. Additives are added depending on the requirements on the lubricating oil, for
example oxidation inhibitors, rust inhibitors and anti wear agents.
While new turbine oil should exhibit properties fulfilling the material specification, these properties
cannot be expected to remain unchanged during the life of the oil. Lubricating oil experience thermal
and oxidative stresses which gradually deplete the oil’s additive package and also degrade the
chemical composition of the oil’s base stock.
Some deterioration can be tolerated without consequences to the safety or efficiency of the system,
but good monitoring procedures are necessary to determine when and how the properties of the oil
have changed. This helps the user to judge the condition of the oil and decide when actions are
required.
Regardless of the initial quality of the oil, the turbine oil will deteriorate in service. Air, elevated
temperature, metals and water are always present to some extent in turbine oil systems. These
elements promote oil degradation. Deterioration occurs by one or a combination of the processes
mentioned below.
Oxidative degradation – Presence of oxygen causes the oil to degrade chemically in a constant
chain reaction. Additives are added to all modern lubrication oils to act as a buffer against
oxidation and protect the base oil from degradation.
Loss of additives – This can result in more rapid oxidation, premature rusting and formation of
deposits and sludge.
System impurities – Remains of rust protection fluids and cleaning agents can influence the
properties of the turbine oil.
Contaminants – Contaminants arising within the system (for example additive-, corrosion- and
wear products) or entering the system (for example dirt and fluids) can cause lubrication and wear
problems.
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Document No. Rev.
No.
1CYJ470058 -
The deterioration process cannot be stopped but it can be delayed. This can be achieved by using
high quality Lubrication oil, by making sure the system is clean before filling and by minimizing the
possibilities of contamination. Proper maintenance and adequate monitoring of the oil is necessary in
order to achieve a high reliability of the lubricating system.
The main purpose of a monitoring is to ensure a long trouble-free operation of the turbine generator
set. This can be achieved by taking prompt and proper action steps. Such action steps should be
based on correct interpretation of test results and operation experience gathered over a period of
time. Siemens Ltd. developed an oil condition monitoring program for our turbines based on years of
experience and international standards for condition monitoring.
A sample shall be taken after flushing in order to verify the delivered oil quality. The results shall be
used to establish a baseline of oil properties for complete use of a condition monitoring program. The
sample after flushing should be analyzed according to table 1. See table 4 for analysis methods and
standards.
Oil properties
Chemical elements
Viscosity
Total acid number
Water content
Cleanliness
Anti-oxidation additives
Air release
Demulsibility
Foaming (at 50°C)
Oxidation stability
The condition of the oil should be monitored according to the schedule in table 2. See table 3 for
warning levels and actions if these are exceeded and table 4 for analysis methods and standards.
Depending on analysis results it may be necessary to change the frequency of analysis for certain
properties.
Table 2: Recommended analysis frequency during normal operation. See table 4 for analysis methods
and standards.
1CYJ470058 -
Continuous supervision of the oil system ensures optimum efficiency and high availability. The
following actions will help greatly to keep the oil in serviceable condition and to notice coming issues
beforehand.
Samples submitted for examination must be representative of the complete oil volume. To obtain a
representative sample from the lubricating system the sample should be taken from a free flowing line
during oil circulation. If this is impossible the sample can be taken from an agitated tank.
The properties of turbine oil cannot be expected to remain unchanged during the life of the oil. Some
deterioration can be tolerated without consequences to the safety or efficiency of the system but it is
important to know when certain limits have been reached. Recommended warning levels and actions
for certain properties of oil in operation are given in table 3. Actions must be taken in order to restore
the quality of the oil if these warning levels are exceeded.
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Document No. Rev.
No.
1CYJ470058 -
Table 3: Warning levels, possible causes & consequences and recommended actions for deviating analysis
results.
Possible
Property Warning level Possible causes Recommended actions
Consequences
Appearance Hazy, Sudden Contamination of Check water content and
change in color water or dirt. solid impurities.
between samples Deterioration of oil.
Water content Max. 200 mg/kg Water or steam Decreased lubricity. Drain water from bottom of
(ppm) leakage. Increased oil tank if possible. Reduce
deterioration. water by centrifugation.
Damaged pumps, Check Demulsibility.
gears and bearings.
Viscosity ± 10% from initial Contamination or Decreased lubricity. Consider oil change.
value severe oxidation of oil. Increased filter
exchange rate.
Solid impurities
Sediment Max. 10 mg / 100 ml Organic sediment: Increased filter Check type of impurities.
The oil may be exchange rate. Investigate and remedy
deteriorated or Decreased lubricity. sources of contamination if
chemically Increased oil possible.
contaminated. deterioration.
Dirt: Dirt left in the Formation of Check function of filters.
system or entering the deposits in the oil Clean oil by centrifugation
system during system. or filtration.
operation.
Cleanliness Max. 20 / 16 / 13 Wear particles: Damaged pumps,
Defective lubrication. gears and bearings.
Rust particles: Decreased lubricity.
Corrosion of oil Increased oil
system, from for deterioration.
example water in the
system.
Dirt: Dirt left in the
system or entering the
system during
operation.
Chemical elements
Wear metals Continuous or Defective lubrication Damaged gears Check for solid impurities.
Contaminants sudden change. or contamination. and bearings. Check physical properties.
Additives Decreased filter Decreased lubricity.
efficiency. Increased oil
Depletion or deterioration.
deterioration of
additives.
Total Acid Max. increase 0.3- Severe deterioration of Decreased lubricity. Look for signs of increased
Number 0.4 mg KOH/g over oil. Formation of sediments on filters.
(TAN) new oil deposits in the oil
system.
Air release Max. 7 minutes Contamination or Decreased lubricity. Resample and retest. If
deterioration of oil. Increased oil same result, consider oil
deterioration. change.
Foaming Tendency: Contamination or Decreased lubricity. Resample and retest. If
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Document No. Rev.
No.
1CYJ470058 -
(at 24°C) max.450 ml deterioration of oil. Increased oil same result, consider oil
Stability: 0 ml deterioration. change.
Demulsibility 40/37/3 in 30 Contamination or Decreased lubricity. Resample and retest. If
minutes deterioration of oil. Increased oil same result, consider oil
deterioration. change.
Oxidation >3000 h Deterioration of oil. Decreased lubricity. Perform RPVOT test
stability Formation of (Result 750 min)
deposits and Resample and retest. If
sludge same result, consider oil
in the oil system. change.
Table 4: Test methods, standards and general information regarding oil properties and analyses.
1CYJ470058 -
24°C) form foam. Too high foaming or
persistent foam can cause operating
problems.
Demulsibility 1401 6614 Describes the oils ability to separate
water. An important parameter
especially for steam turbines where
there is a higher risk for water entering
the oil system.
Oxidation RPVOT 2272 RPVOT (Rotating Pressurized Vessel
stability Oxidation Test) estimates the working
life of the oil.
The higher the RPVOT the longer the oil
can normally be used
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
2015-07-03; Varma Murali Krishna; Siemens AG, PG SU AP IN EN PEN MECH
Ausdruck unterliegt nicht dem Änderungsdienst
Technische Liefervorschrift September 2010
The printout is not covered by our automatic updating service
TLV-Exportkennzeichnung: TLV-Export-Identification:
AL = N AL = N
ECCN = N ECCN = N
Weitergabe
sowie Verviel- Vertragsverbindlich ist immer die deutsch- The German version of this TLV shall be consid-
fältigung
dieser Unter- sprachige Fassung dieser TLV. ered as the only binding one. The English ver-
lage, Ver- sion is for reference only.
wertung und
Mitteilung
ihres Inhaltes
nicht gestattet
soweit nicht
ausdrücklich 1. Geltungsbereich 1. Scope of Application
zugestanden.
Zuwiderhand- Diese Liefervorschrift (TLV) gilt für die Beschaffung This specification (TPS) is valid for procuring turbine
lungen ver-
pflichten zu von Turbinenölen, die zur Schmierung und teilweise oils used as lubricating oils and particulary as con-
Schadener-
satz. auch zur Steuerung und Regelung von Siemens- trol and governor oils for Siemens steam and gas
Alle Rechte
für den Fall
Dampf- und Gasturbosätzen mit und ohne Getriebe turbosets with and without gearbox.
der Patent- verwendet werden.
erteilung oder
GM-Ein-
tragung
vorbehalten.
2. Mitgeltende Dokumente 2. Referenced Documents
DIN 51 562-1, DIN EN ISO 3104, DIN ISO 2909, DIN 51 562-1, DIN EN ISO 3104, DIN ISO 2909,
DIN ISO 9120, DIN 51 558-1, DIN EN ISO 12937, DIN ISO 9120, DIN 51 558-1, DIN EN ISO 12937,
ISO 6247, DIN 51 589-1, DIN ISO 6614, ISO 6247, DIN 51 589-1, DIN ISO 6614,
___ DIN 51 757, DIN ISO 2592, DIN ISO 3016, DIN 51 757, DIN ISO 2592, DIN ISO 3016,
ISO 4406, DIN EN ISO 2160, DIN ISO 7120, ISO 4406, DIN EN ISO 2160, DIN ISO 7120,
Copying of
this docu-
DIN EN ISO 4263-1, DIN ISO 14635-1, DIN EN ISO 4263-1, DIN ISO 14635-1,
ment, and ASTM D 445, ASTM D 2270, ASTM D 3427, ASTM D 445, ASTM D 2270, ASTM D 3427,
giving it to
others and ASTM D 974, ASTM D 1744, ASTM D 892, ASTM D 974, ASTM D 1744, ASTM D 892,
the use or
commu-
ASTM D 1401, ASTM D 1298, ASTM D 92, ASTM D 1401, ASTM D 1298, ASTM D 92,
nication of ASTM D 97, ASTM D 130, ASTM D 665, ASTM D 97, ASTM D 130, ASTM D 665,
the contents
thereof, are ASTM D 943, ASTM D 5182, ASTM D 2272 ASTM D 943, ASTM D 5182, ASTM D 2272
forbidden
without ex-
press author-
ity.
Offenders 3. Allgemeine Forderungen 3. General Requirements
are liable to
the payment
of damages.
Unter Turbinenöl nach dieser TLV ist ein Mineralöl According to this TPS turbine oil is a mineral oil or a
All rights are oder ein synthetisches Öl mit Wirkstoffen zur Erhö- synthetic oil containing additives to increase corro-
reserved in
the event of hung des Korrosionsschutzes und der Alterungsbe- sion protection and ageing stability.
the grant of a
patent or the ständigkeit zu verstehen.
registration of
utility model
Turbinenöle, die zur Getriebeschmierung eingesetzt Turbine oils used for gear lubrication may additional
or design. werden, können zusätzlich Wirkstoffe zur Erhöhung contain additives to increase the load capacity and
der Belastbarkeit und zur Herabsetzung des Ver- to decrease wear.
schleißes enthalten.
Schutzklasse: Nur für internen Gebrauch / Protection class: For internal use only Copyright © Siemens AG All Rights Reserved
2015-07-03; Varma Murali Krishna; Siemens AG, PG SU AP IN EN PEN MECH
Ausdruck unterliegt nicht dem Änderungsdienst
Seite/ Page 2 The printout is not covered by our automatic updating service
TLV 9013 05: 2 0 1 0 -09
4. Eigenschaften 4. Properties
4.1 Chemische Zusammensetzung 4.1 Chemical Composition
Bei Turbinenöl handelt es sich in der Regel um pa- Usually turbine oil is a paraffin based mineral oil
raffinbasisches Mineralöl, bestehend aus einem consisting of a mixture of saturated hydrocarbons. A
Gemisch gesättigter Kohlenwasserstoffe. Eine defi- defined composition cannot be given on account of
nierte Zusammensetzung kann wegen der Vielzahl the quantity of different components. The criterion of
unterschiedlicher Bestandteile nicht gegeben wer- selection for use as turbine oil is the physical condi-
den. Auswahlkriterium für die Verwendung als Tur- tion.
binenöl ist die physikalische Beschaffenheit.
Die zugemischten Wirkstoffe (Additive) dürfen keine The admixed additives must not have any negative
nachteiligen Auswirkungen auf Werkstoffe des Öl- effects on the materials of the oil system. They must
systems haben. Sie dürfen keine metallorganischen not contain organometallic compounds (e.g. organic
Verbindungen (z.B. organische Zinkverbindungen) zinc compounds).
enthalten.
4.4 Physikalische und chemische Eigenschaften 4.4 Physical and chemical properties
Neutralisationszahl
total acid number ≤ 0.30 mg KOH/g DIN 51 558-1 ASTM D 974
Wassergehalt
water content ≤ 200 mg/kg DIN EN ISO 12937 ASTM D 1744
Demulgiervermögen
demulsibility ≤ 30 min DIN ISO 6614 ASTM D 1401
2015-07-03; Varma Murali Krishna; Siemens AG, PG SU AP IN EN PEN MECH
Ausdruck unterliegt nicht dem Änderungsdienst
The printout is not covered by our automatic updating service Seite/ Page 3
TLV 9013 05: 2 0 1 0 -09
4.4 Physikalische und chemische Eigenschaften 4.4 Physical and chemical properties
(Fortsetzung) (continued)
Reinheitsgrad 2)
cleanliness level 2) ≤ 20/17/14 - ISO 4406 -
2) Der Reinheitsgrad des Öles bezieht sich auf den Anlieferungszustand. Die geforderte Reinheit im System wird sys-
temspezifisch festgelegt und muß durch geeignete Maßnahmen (z.B. Filtrierung, Separierung) sichergestellt werden.
The cleanliness level refers to the oil condition on delivery. The required system cleanliness is dependent upon the
system design. Suitable measures (e.g. filtration, separation) have to be taken to guarantee this cleanliness level.
4.5 Zusätzliche Anforderung an Getriebe- 4.5 Additional requirement on turbine oils for use
turbinenöle in gearboxes
7. Befüllen 7. Filling
Serviceleistungen zur Befüllung sind vom Besteller Services for filling must be stipulated between pur-
mit dem Lieferanten schriftlich zu vereinbaren und chaser and supplier.
im Vertrag festzuhalten.
Technical purchasing specification TLV 9013 05 Die Technische Liefervorschrift TLV 9013 05
is valid for purchasing turbine oils with higher gilt für die Beschaffung von Turbinenölen
thermal stability for Siemens steam and gas mit erhöhter thermischer Stabilität für
turbosets. Siemens Dampf- und Gasturbosätze.
Turbine oils that were tested and approved Turbinenöle, die nach TLV 9013 05 untersucht
according to TLV 9013 05 are shown in the und freigegeben wurden, sind in der folgenden
following approval list. The approval does not Freigabeliste aufgeführt. Die Freigabe entbindet
release the supplier from his responsibility for den Lieferanten nicht von der Verantwortung für
the quality of the product. die Qualität seines Produktes.
Attention: The selection must be made Achtung: Bei der Auswahl eines Öls muss
in consideration of the viscosity class die für den jeweiligen Turbosatz festgelegte
determined for the turbo set. Turbo sets with Viskositätsklasse beachtet werden. Bei
gearboxes need special turbine oils suitable Turbosätzen mit Getriebe muss ein
for gearbox lubrication. Getriebeturbinenöl ausgewählt werden.
Dates about the viscosity class and the suitabi- Die jeweilige Viskositätsklasse und die Angabe,
lity for gearbox turbosets can be found in the ob es sich um ein Getriebeturbinenöl handelt,
following table. Turbine oils for use in turbines finden sich in der folgenden Tabelle. Getriebe-
with gearboxes may also be used for turbosets turbinenöle können auch in Turbinen ohne Ge-
without a gearbox. triebe eingesetzt werden.
ST G WN TUB 051-05-010
Prepared: Checked: Released: Language: Page:
PG I Nbg. / Essen
Contents
1. General ............................................................................................................................... 1
1.1 Danger of Accidents/Noise Prevention ................................................................................ 1
2. Blowing Circulations ............................................................................................................ 2
3. Conditions for Blowing Out .................................................................................................. 2
3.1 Dynamic Pressure Conditions.............................................................................................. 2
3.2 Rating the Blow Out Piping.................................................................................................. 3
3.3 Blowing Gate Valve ............................................................................................................. 4
4. Blowing Out Operation ........................................................................................................ 4
4.1 Duration of a Blast............................................................................................................... 4
4.2 Number of Blasts ................................................................................................................. 4
4.3 Sudden Temperature Drop .................................................................................................. 4
4.4 Procedure When Blowing Out.............................................................................................. 4
5. Cleanliness of the System ................................................................................................... 4
5.1 Assessing the Cleanliness of the System ............................................................................ 4
1. General
This recommendation describes the blowing-out conditions and purity criteria that are required by
manufacturer.
Blowing-out has the purpose of removing rust, scale, coatings dirt and foreign bodies from the inner
surfaces of steam piping to avoid blockages of the steam filter at the turbine inlet or damage to the turbine.
You must never start up a turbine before the boiler and the steam piping to the turbine have been cleaned.
Failure to follow this recommendation and starting the system even though it has not been properly cleaned
is at the customer's own risk. Any damage that occurs due to incorrect blowing out is excluded from the
warranty.
The manufacturer exclusively retains the right to inspect the turbine before acceptance testing the turbo
generator to determine the current status and, if necessary, to take into account corrections to the
guarantee values. Any additional costs that result from this shall be borne by the customer.
If blowing out was not carried out in accordance with this guideline, the customer must be informed in
writing of the facts and the corresponding results.
Official regulations dictate that you must provide noise prevention measures.
Copyright DIN ISO 16016 shall be observed ! The reproduction, distribution and utilization of this document as well as the communication of
its contents to others without explicid authorization is prohibited. Offenders will be held liable for the payment of damages. All rights reserved
in the event of the grant of a patent, utility model or design. © Siemens AG
VD002521
Revision: Language: Page:
G en 2 2CWN002896
To reduce noise pollution due to blowing-out, you can use two procedures:
- utilize a silencer
- divert the steam under water
The supplier of the boiler or the piping must guarantee the provision of noise prevention measures.
2. Blowing Circulations
Blowing out is intended above all to clean the boiler's piping system. In the same way, you must clean all
the steam piping (live steam piping, secondary steam piping) that supplies steam to the turbine. In addition,
the supply lines of by-pass and reduction stations are blown out as well as those of the seal-steam system
and the steam-jet air ejector units.
Normally, you blow out all of the piping until directly in front of the valve casing or close to it.
The provisional blow out pipe is connected to the connection flange of the steam pipe to the quick-action
valve or to a pipe flange close to it.
If you carry out blowing via the quick-action valve, you must dismount it. If constructional reasons dictate
that it is not possible to connect the blow-out line in front of the quick-action valve and the quick-action
valve is welded to the control valve casing, you must carry out blowing via the quick-action valve by means
of a deployment ordered from the manufacturer.
Dismount the provisional blow out pipe and mount the definitive steam piping under conditions that are as
clean as possible.
It is advisable to remove from the blowing circulation sensitive objects such as valve seats, valve shafts,
flow-measuring orifices, etc.
Below, we will use index A for the maximum throughflow in full-load operation and index B for blowing out:
⎛ c2 ⎞ ⎛ c2 ⎞
⎜ ⎟ >⎜ ⎟
⎝ 2v ⎠ B ⎝ 2v ⎠ A
( m²xy v )B > ( m² y v )A
VD002521
Revision: Language: Page:
G en 3 2CWN002896
vA
mB > m A ⋅
vB
Calculation example:
pA = 61 bara mA = 33 kg/s
TA = 450° C vA = 0.051189 m³/kg
vA
mB > m A ⋅
vB
0,051189
mB > 33 ×
0,090526
To ensure that the desired parameters of the mass flow rate are achieved, you should carry out an
estimate of the mass flow rate, if possible, by means of the operational measurement.
If possible, you should measure the pressure and the temperature for the calculation directly by the boiler
outlet.
You should aim to achieve high steam conditions, since experience has shown that steam piping is not
correctly cleaned until high temperatures have been reached.
The following empirical values are used to specify the pressure and temperature for blowing out:
VD002521
Revision: Language: Page:
G en 4 2CWN002896
3.3 Blowing Gate Valve
It is absolutely vital to install a blowing gate valve with a low (30-second) opening time. You should install
the gate valve in the area of the blow-out pipe in front of the mirrors. This gate valve makes it possible to
achieve a reduction in the blow-out time, due to warming of the steam line via water drains, and an
improvement in the level of cleaning.
The supplier of the boiler or the piping will provide the blowing gate valve.
Blowing out is started by running up the boiler to the previously specified blowing parameters and by
warming to piping that is to be blown out.
After this, carry out blowing using the steam data that is necessary to achieve the dynamic pressure
conditions and the temperature. While doing this, you should keep open the blowing gate valve for 1-2
minutes. Carry out blowing two to three times according to this method.
After this, blow down to low pressure and empty the boiler to clean the evaporator.
After this, use the fans to cool down the boiler.
On the day after this, run at full blowing pressure and full temperature.
With the first two or three blasts, no steel mirrors are installed to check cleanliness due to the high levels of
contamination that can be expected.
You must install a mirror at least after every cooling down period of the boiler to allow you to determine the
effectivity of the blowing out operation.
VD002521
Revision: Language: Page:
G en 5 2CWN002896
Material: St 37
ASTM A36
ASTM A516Gr70
Hardness: approximately 110 -120 HB
>10 D
DN L [ mm ] B [ mm ]
100 90 15
150 135 20
200 180 25
250 225 30
300 270 35
350 315 40
400 360 45
VD002521
Revision: Language: Page:
G en 6 2CWN002896
Adequate cleanliness of the steam piping was achieved by complying with the conditions below:
a) Two successive blasts must result in mirror surfaces that have no strikes that are outside the
assessment limits stated below.
b) After a cooling-down period of at least 12 hours, two more successive blasts must result in mirror
surfaces that have strikes that comply with the stated assessment limits.
y Not more than 2 strikes with diameters greater than 0.4 mm per 2500 mm²
y Not more than 10 strikes with diameters greater than 0.2 mm per 2500 mm²
VD002521
Revision: Language: Page:
G en 7 2CWN002896
VD002521
Document No. Rev.No.
Technical Instruction:
INSTALLATION OF QCNRV IN STEAM LINE
2 1CYJ470057 A
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
3 1CYJ470057 A
In case of non conformance to the above distances, Customer suppose to brought the
actual upstream and downstream length of QCNRV to Siemens notice for final
concurrence.
Below Diagrams Indicate Typical Installation of the QCNRV. How ever the Actuator Side (Right
side/Left side) shall be project specific.
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
4 1CYJ470057 A
Inlet Outlet
QCNRV when provided with an internal drain, same must be continuously drained to
atmosphere by means of steam trap assembly as shown is fig 4.
The following instructions shall be followed when planning and implementing non-return valve
drains.
The drain shall be implemented with an orifice and valve in the main line and a drain
trap in the bypass as per fig 4
The drain trap shall be selected under consideration of the pressure parameters in
accordance with Section 3.5 of steam trap and 3.6 of orifice from Turbine drain
guideline, doc no 1CYJ470060.
Unhindered draining of the condensate shall be ensured, although this may be either to
a header or to the atmosphere
Under all circumstances, it must be ensured that there is a pressure gradient of at least
1 bar to the main steam line, where the main steam line has the higher pressure level
Technical Instruction:
SAFETY PRECAUTIONS
2 1CYJ470059 -
Safety precautions
General
This section covers the general safety precautions which must be observed during
operation and periodic maintenance of the Siemens Ltd. Supplied steam turbines.
It includes the most important precautions which, if neglected, can cause personal injury or
death. In addition to this general safety information, there are also some additional safety
information in the operating and maintenance instructions that has to be considered as well,
but which only concerns a specific action or component.
Safety information
Warning
Indicates the presence of danger. Ignoring the sign may lead to
Personal injury or death and/or damage to the equipment.
Caution
Informs you of situations or conditions which, if not adhered to,
may damage machinery or cause additional wear to the equipment.
Note
Additional important information—that should be observed by the operating
or maintenance personnel—are labeled as notes.
Note!
Notes provide you with additional and useful information.
Although less urgent than cautions and warnings, notes are
Important and should not be ignored.
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
3 1CYJ470059 -
Warning
General
Prior to Switch on the CEP, the condenser has to be filled with demin water
until the level indication shows a level of approximately 50 % of the range.
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
4 1CYJ470059 -
Manual synchronizing must only be carried out by authorised
Personnel. The utmost care must be taken to avoid out of phase
Synchronization.
Before start up, make sure that the unit is ready for start-up after
Any maintenance work.
Caution! If there is still power or speed after a turbine trip, close the main
steam line.
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
5 1CYJ470059 -
Vessel and main steam lines have to be blown out before first start-up
and after repair works. Loose particles can lead to damages at valves,
blading or labyrinths.
Too high sealing steam pressure can damage the labyrinth packings!
The sealing steam pressure must not be higher than 1.1 ata.
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
6 1CYJ470059 -
The auxiliary oil pumps may only be switched off after standstill of the
turbines, otherwise it might damage the bearings.
Only use oil of the quality and type as in the specification indicated.
Damages which can be put down to the use of unspecified oil evade our
liability.
The disposal of leak and used oil has to be done in accordance with
local regulations and laws.
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
7 1CYJ470059 -
Prior to the start up of the steam turbine the turning gear is operating for
at least 24 hours.
While the turbines are hot / flange centre temperature is greater than
recommended hot start temperature , the rotor should not be stopped
for longer than 10 minutes. If necessary, turn the turbine rotor each 10
minutes for 90°.
If the turbine rotor was not turned in time and is stuck, in no case use
violence, but let the turbine completely cool down. Before the restart of
the cold turbine try, whether the turbine rotor can be turned free for at
least two turns (no scraping sounds).
After a standstill of the turbine more than one week the turbine rotor
must be turned by hand for at least two turns (no scraping sounds)
before starting the turbine again.
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Document No. Rev.No.
Technical Instruction:
Turbine Piping Guidelines
Unrestricted
_______________________________________________________________________________________________________________________________
We reserve the rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is
strictly forbidden. © SIEMENS Ltd.
2 1CYJ470060 B
Sr.
Contents Page
No.
1.0 Scope of Application 3
2.0 Type of Drains 3
2.1 External Drains 3
2.2 Internal Drains 4
2.3 Function of Drains 5
3.0 General Information on Drain System 6
3.1 Design Notes 6
3.2 Typical Design 7
3.3 Dimensioning 10
3.4 Condensate collection nozzle (Drip leg) 10
3.5 Application of ANSI/ASME TDP-1 standard 11
3.6 Steam Traps 12
3.7 Orifice 12
3.8 Drain Headers 12
3.9 Drain Collecting Tank 13
4.0 Draining of condensing turbine with upward facing exhaust and axial 15
exhaust
5.0 Drainage of condensing turbine with installation at ground floor 15
6.0 Perfect Closure 15
7.0 Live Steam 16
8.0 Extraction Steam 18
9.0 Admission Steam 20
10.0 Exhaust Steam Backpressure 22
11.0 Oil System 22
Unrestricted
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page Document No. Rev. No.
3 1CYJ470060 B
This guideline defines the requirements that SIEMENS AG specifies to the company performing
the work for planning, production and installation of piping systems (e.g. non-automatic
extraction). Adherence to this guideline will help prevent damage to components delivered
by Siemens, thus making a contribution to ensuring smooth,fault-free operation of the turbine
plant.
The document contains essential information about piping arrangement that can strongly
influence safe and reliable operation of steam turbine. Therefore, fulfillment from Customer’s
side has to be verified by Siemens staff on site and is condition for validity of Guarantees.
This design standard is derived to establish piping design criteria for the turbine (SST 150, SST
200, SST 300, and SST 600 (G&V)). Among other benefits, this ensures operating reliability of the
turbine generator unit.
An inadequately designed drain system can result in the following damage or faults in the turbine
unit:
· Uneven cooling of the turbine casing and shaft due to condensate in the lower section of
the casing, with resulting deformation.
· Water hammer in the turbine – damage to blades
· Chugging in piping with consequential damage to piping hangers.
· Accumulation of condensate in the seal and leak-off steam system, with faults in pressure
regulation of the valves
· Corrosion due to condensate.
If there is a possible link between the external drains & the internal drains, e.g. By means of a
common flash tank, the steam from the external piping systems could flow into the turbine and the
condenser and locally heat them, which would lead to damage.
In addition, designer must not route the internal drains into the atmosphere when there is a
vacuum in the turbine and the condenser, since this would result in air being sucked into the
internal system.
4 1CYJ470060 B
· High or low pressure turbine bypass pipes with condensing plant before the bypass
valve.
· Extraction / Bleed lines after the first non-return valve.
· Back pressure line (exhaust steam) after QCNRV
The system carries out internal drainage of the Turbine and the following steam lines (viewed in
the direction of flow):
· Turbine casing and balance piston line drains.
· Lines between the ESV and turbine governing valves.
· Lines after the turbine governing valves.
· Seal steam pipe after the regulating valve.
· Extraction / bleed lines before the first non-return valve.
· Ejector and GSC drains.
· Cross-over or cross-under pipes between various turbine casings.
· Back pressure line (exhaust steam) before QCNRV.
· high or low pressure turbine bypass pipes with condensing plant after the bypass valve
Unrestricted
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page Document No. Rev. No.
5 1CYJ470060 B
Unrestricted
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page Document No. Rev. No.
6 1CYJ470060 B
7 1CYJ470060 B
8 1CYJ470060 B
Fig. 9 Routing and draining of exhaust steam lines with valves, self draining
Fig. 10 Routing and draining of exhaust steam lines with valves, via drain line (I)
Unrestricted
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page Document No. Rev. No.
9 1CYJ470060 B
Fig. 13 Routing and draining of steam lines with expansion joint and orifice
Unrestricted
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page Document No. Rev. No.
10 1CYJ470060 B
3.3 Dimensioning
The dimensions and number of drains are determined by the nominal diameter, length, steam
conditions and steam mass flow rate in the piping section to be drained.
The cross sections of the drain lines shall be compared with the quantities of condensate
occurring in operating conditions.
Unrestricted
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page Document No. Rev. No.
11 1CYJ470060 B
Fig 17 Modified drainage concept according to ANSI/ASME TDP-1 acceptable to turbine internal
drainage
Unrestricted
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page Document No. Rev. No.
12 1CYJ470060 B
3.7 Orifice
The diameter of orifice should be selected based on upstream operating pressure at full load,
according to the table below. Orifice in drain lines should be installed after first rolling of
turbine.
The drains shall be implemented in sequence on the header as a function of pressure, starting with
the highest pressure. The drain at the highest pressure shall be configured the furthest from the
flash box. This prevents drains at higher pressure from compromising the functioning of drains at
lower pressure (isolation processes). Drain lines to be connected to header from top. Connection to
the header at centerline or below is not recommended.
The drain header shall be connected to flash box for water cooled condenser and to drain boot for
air cooled condenser at least 250mm above the maximum condensate level. The Drain Header
must be of minimum possible length and sloped towards terminal point / flash box. (Figure 19 & 20)
A split in the drain header may be necessary depending on the engineering implementation and
local/spatial conditions (Figure 19). The separate sections shall be divided by pressure ranges (HP,
LP), where the pressure-dependent configuration shall also be observed.
Unrestricted
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page Document No. Rev. No.
13 1CYJ470060 B
These provide for separation and discharge of the condensate/steam mixture from the drain
headers. Additional spray attemperation ensures cooling/condensation.
The exhaust steam line for the drain collecting tank shall be dimensioned so as to prevent any
pressure build-up in the tank.
In condensing plants, the collecting tank is connected to the condenser on the steam side (main
condenser, heating condenser or air-cooled condenser).
Unrestricted
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page Document No. Rev. No.
14 1CYJ470060 B
Unrestricted
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page Document No. Rev. No.
15 1CYJ470060 B
4.0 Draining of condensing turbines with upward facing exhaust and axial exhaust
In turbines with upward-facing exhaust steam nozzles and axial exhaust, the condenser is usually
configured next to or above the turbine. The drain header shall be located at a hydrostatic level
which ensures reliable draining at all times.
Fig 21: Draining of condensing turbine with upward facing and axial exhaust
The minimum distance between the lowest drain connection (e.g. turbine casing) and the drain
header is at least 1000 mm. The drain valves shall be configured horizontally if necessary. The
connection to the drain header is vertically upwards.
The minimum height difference between the drain header and the maximum condensate level is
250 mm (Figure 21).
16 1CYJ470060 B
steam leaking from the pressurized piping into the turbine; which is inadmissible for reasons of
safe work on the equipment of the consecutive pressure piping; in case of a long-term outing this
closure eliminates steam penetration into the turbine which would be the reason of either corrosion
of the turbine or local heating of some parts of the turbine and later their deformation.
- Turbine Live steam temperature and pressure measurements have to be located as close as
possible to ESV, maximally 3 m upstream of ESV. If this requirement cannot be met, Siemens
has to be requested for approval
- Dimension of MSIV bypass need to be designed with regard to requirements of live steam line
preheating. Live steam line needs to be preheated by speed 4 °C/min to minimum start-up
Unrestricted
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page Document No. Rev. No.
17 1CYJ470060 B
18 1CYJ470060 B
- Inlet steam line is preheated via open Emergency stop valve to closed turbine control valve.
7.2 Reason of the Main steam isolation valve and its bypass Necessity
- The emergency stop valve cannot be used as isolation valve for long time (more than 1 hour) if
turbine is not operated by corrosion reason. This means – in this case (missing MSIV) steam
system cannot be operated without turbine operation (for example steam heaters, steam
technology consumers, bypass valves, test of boilers etc.)
Unrestricted
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page Document No. Rev. No.
19 1CYJ470060 B
20 1CYJ470060 B
Unrestricted
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page Document No. Rev. No.
21 1CYJ470060 B
Unrestricted
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page Document No. Rev. No.
22 1CYJ470060 B
-Reverse initial heating of the turbine may be required for backpressure turbines. This is
illustrated as appropriate in the P&I diagram. The bypass around the exhaust steam valve MSIV 1
is used for reverse heating. The condensate that accumulates is removed through the turbine
casing internal drains.
Unrestricted
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Document No. Rev.No.
Piping Guidelines:
_______________________________________________________________________________________________________________________________
We reserve the rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is
strictly forbidden. © SIEMENS Ltd.
INDEX
1.0 Guidelines for design of LP heater normal / emergency drain Piping
2.0 Guidelines for design of HP heater normal drain Piping
3.0 Guidelines for design of HP heater emergency drain Piping
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Document No. Rev.
No.
1CYJ470061 -
Piping Guidelines for Termination of heaters drain’s near to Condenser Flash Box
Pipline after Control valve should be connect straight at nozzle elevation of
flash box to avoid accumulation of water inside the pipe. ( Refer Fig.1.1 &
Fig.1.2)
There should not be any riser nor any bends after Control Valve
Line Size after Control Valve should be designed as per Volumetric flow of
fluid ( Mixture of Steam + Water) Refer Calculations below
Fluid downstream of control valve will be “Flash Steam” having very high
velocity & energy, so it is recommended to keep the control valve nearrer &
strainght inline with flash box nozzle
There should not be any bend after control valve to avoid fluid hammering
Do Not Provide Rigid Support near to flash box nozzle, Prefrable to provide
spring support.
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Document No. Rev.
No.
1CYJ470061 -
Fig. 1.1 Piping sketch for control valve outlet to condenser flash box
Fig. 1.2 Piping sketch for control valve outlet to condenser flash box
What is flash steam? When hot condensate or heater water, under pressure, is
released to a lower pressure, part of it gets re-evaporated and become flash
steam.
SL = Sensible heat in the cond. at the lower pressure to which discharge takes
place.
H = Latent heat in the steam at the lower pressure to which the cond. has been
discharged.
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Document No. Rev.
No.
1CYJ470061 -
Piping Guidelines for Termination of heaters drain’s near to Condenser Flash Box
Pipline after Control valve should be connect straight at nozzle elevation of
flash box to avoid accumulation of water inside the pipe. ( Refer Fig.1.1 &
Fig.1.2)
There should not be any riser nor any bends after Control Valve
Line Size after Control Valve should be designed as per Volumetric flow of
fluid ( Mixture of Steam + Water) Refer Calculations below
Fluid downstream of control valve will be “Flash Steam” having very high
velocity & energy, so it is recommended to keep the control valve nearrer &
strainght inline with flash box nozzle
There should not be any bend after control valve to avoid fluid hammering
Do Not Provide Rigid Support near to flash box nozzle, Prefrable to provide
spring support
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Document No. Rev.
No.
1CYJ470061 -
_______________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Document No. Rev
SIEMENS LTD. 1CYJ464026 A
Responsible Department Take over Departm ent Doc- type Folder No. :
Pro jec t Engine ering\BOP\Gene ral\Ere ction do cs\
E P SU PEN E S FS TI Sta ndard doc uments
Prepared : Checked : Released : Language : Page :
-- -- -- Eng 1 of 5
Valid for: Derived from : Replaces : E file no.
E P SU VAD 464026.doc
The objective is to remove dirt, oil, grease, welding slag and mill scale adhering to
the internal surfaces of piping by cold water flushing, hot water flushing & alkali
flushing and preservation of pipes, fittings, valves & pumps to ensure flow of clean
condensate and feed water to the boiler.
The cleaning may be carried out by circulating the specified chemical solutions in the
specified sequence and conditions. Temporary piping, pumps of suitable capacity,
fittings, flanges, tanks, gaskets, heating arrangement, hydrometers, valves, test
coupons, spares, laboratory facilities with all accessories required for conducting
tests during cleaning operation, chemicals and safety accessories for operation per-
sonnel etc., shall be made available at site prior to cleaning operation. Quantity of
chemicals required should be calculated based on the hold-up volume of the circuit.
We reserve the rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties
without express authority is strictly forbidden. © SIEMENS Ltd.
Format No.: IP-Q-F-3009
Rev./Date : C / 31.03.2010
Page Document No. Rev
Customer has to provide DM water & Construcion power and same will be tapped by
contractor by making necessary arrangements. All other activites, processes and
Loop diagram showing details for cleaning shall be done by Erection contractor and
submitted to Owner for review before starting the work. For making the loops refer to
the PID’s for the project.
3.0 Procedure
Preferably each of the steam, condensate, feed water and heater drain systems
shall be flushed separately. It consists of cold water flushing, hot water flushing fol-
lowed by alkali flushing using Trisodium Phosphate, Caustic Soda and Lissopol. Af-
ter Alkali flushing, the system is flushed well with DM water and then preserved
using Hydrazine Hydrate with Ammonia to maintain Ph 10.
System is again filled with DM water and circulated for half an hour in each loop and
drained. Now rinse the system with DM water by continuous filling and draining while
keeping pumps running till effluent is visibly clean and conductivity and oil parame-
ters meet as per completion criteria.
3.4 Preservation:
# Description Concentration
1. Trisodium Phosphate Na 3PO4.12H2O 0.5% by wt.
2. Caustic soda Sodium Hydroxide NaOH 0.3% by wt.
3. Lissopol Patented Chemical 0.02% (200ppm)
4. Hydrazine Hydrate N2H4H2O 200 ppm
5. Ammonia for Ph 10
RECORD SHEET 1
PROJECT:
Start Finish
S No. Activity Remarks
Date Time Date Time
REMARKS:
..................................... .....................................
Signature Signature
(Siemens Limited, Vadodara, India) (Customer :______________ )
RECORD SHEET 2
PROJECT:
UNIT:
Conductiv-
Oil content
S No Date Time ity Micro Remarks
PPM
S/Cm
Preservation
Hydrazine
S No Date Time pH Remarks
PPM
REMARKS :
..................................... .....................................
Signature Signature
(Siemens Limited, Vadodara, India) (Customer :______________ )
Technical Instruction:
Preservation of the Shut-down Turbine plant
(Extract from Turbine O&M Manual )
_________________________________________________________________________________________________________________________________
We reserve the rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly
forbidden. © SIEMENS Ltd.
2 1CYJ461103EXX -
Preservation of the Shut-down Turbine plant
Shut-down turbine plants are exposed to corrosion. Mostly an electro-chemical process is
involved in which iron is converted to rust by the presence of water and air (oxygen). Also the
most disadvantageous, forming of pitting may occur.
Stand still periods can cause damage by corrosion and later consequent faults due to corroded
components. After a stand still period of only a few days with high humidity damage of blading
components is possible. The combination of moisture and salt deposits in the cold turbine
increases the risk of pitting, which may reduce the endurance strength and increase the risk
for high cycle fatigue.
The recommendations as mentioned in this section are for Turbine point of view only.
Customer to refer respective equipment manuals for other plant systems / auxiliaries.
The higher the relative humidity, the thicker the water film and the faster the corrosion will be.
The relation between relative humidity and relative corrosion velocity is shown in the diagram.
This relation has three important zones.
Above 50 % relative humidity, the corrosion velocity increases rapidly with increased
relative humidity
If the relative humidity of the environment is higher than 40 %, the recommend precautions
must be taken immediately in order to prevent corrosion damage. If the stand still period is
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
3 1CYJ461103EXX -
expected to exceed 9 - 12 months, or if the environment is extremely aggressive, a more
extensive conservation procedure than described here in should be considered.
This process begins immediately after the turbine is shut-down and has subsequently cooled-
down. Air temperatures below dew point cause condensation of air moisture on internal
surfaces.
The relative humidity can be reduced by hot-air injection, dry-air injection or inert gas
injection (for example nitrogen). We recommend dry-air injection with dehumidifiers
because it is more reliable and economic than the other methods.
Leak steam, steam back flows and condensate penetration to protected sections should be
prevented first of all.
For short stand still periods, such as a night or a weekend, we recommend that the
gland steam system is left in operation and the main condenser is kept under vacuum.
(Rotor on barring speed)
If there is no possibility to get gland steam during the stand still period, Maintain the
condenser cooling water circulation in order to direct the condensation to the condenser
instead of the turbine.
Turbine
For longer stand still periods the condenser should be drained and a dehumidifier be
connected.
Drain the turbine, and related pipes.
In any case no steam or condensate may leak to the turbine system, because the
conservation would fail and the dehumidifiers would accelerate corrosion.
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
4 1CYJ461103EXX -
Check that there is airflow from the turbine shaft glands. This airflow is very important in
order to prevent corrosion in the glands.
Clean the strainers in the steam traps and check the drain pipes for clogging
Check that there is airflow through turbine and condenser.
Protect turbine against possible entering of leak steam. Do not use the emergency stop
valve as a component of steam lock. It is not protected against corrosion.
Casing and rotor temperatures are kept above dew and freezing point.
Protect against entering steam by fitting blank plates between inlet connecting flanges
(main steam, bleed steam, sealing steam).
Remove measuring instruments and electrical equipment, mark carefully and store
wrapped in oil paper.
Oil System
Every 2 weeks put oil pumps for 1 hour into operation; during this period all control
devices shall be moved once from "completely closed" to "completely open" position.
Turn turbine rotor with turning gear shortly. Most of the commercial turbine oil brands
contain corrosion inhibitors which provide good protection against rusting. Take oil
samples as accustomed.
A slow cooling water flow should be maintained in the coolers all the time. (Both sides
of oil cooler)
To protect turbine plants against corrosion for indefinite periods is rather extensive and
expensive. All measures for preservation should be carried out in connection with an
immediate overall overhaul of the complete turbo set after shut-down. All components are
preserved, packed and stored in dismantled condition. Check the preservation in 2 years
intervals and renew if required. Prior to recommissioning the corrosion inhibitors must be
removed with steam or paraffin.
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
5 1CYJ461103EXX -
Turbine
Dismantle turbine not later than 4 days after shut down and remove rotor. Check and
clean internals.
The relative humidity in the storage environment must be kept below 40%, below 30%
is recommended.
Protective coatings with anti corrosion protection agents can be applied. Checks at
regular intervals are necessary to ensure protection.
Mark carefully the components. Apply TECTYL 506 to all internals, bearings, joints,
auxiliary drives, flange bolts, etc. Bearings and joint surfaces should be additionally
wrapped in oil paper. Apply TECTYL 511M to all inner casing surfaces. Dismantled
components shall be wrapped in foils and stored indoors or stored next to the turbine in
cases.
Lift upper turbine casing, bearing cover, valve block by about 100 mm from the
horizontal joint by means of hardwood distance pieces. Wrap these in oil paper. Plug all
turbine ports with plastic covers well visible for everybody.
Clean and apply TECTYL 506 to all dismantled components like steam strainers,
control and emergency stop valves, valve chests, control components etc. Dismantled
components shall be wrapped in foils and stored indoors or stored next to the turbine in
cases.
Apply TECTYL 506 and preserve base plates, sliding surfaces, keys, guide pins.
Remove measuring instruments and electrical equipment and store them carefully
marked and wrapped in oil paper. Check external coatings, renew if required. Remove
piping and clean, dry the individual sections, seal air-tight and apply a new external
coating. Order and keep on store one set of new sealing rings and gaskets for
recommissioning.
TECTYL 511-M
Properties
TECTYL 511-M is a fluid rust-preventive. The resulting film is light-brown, nearly transparent
and soft. Coverage amounts to 35-45 m2 per litre. TECTYL 511-M is an especially water
displacing and creepable product. The film does not attack any metal surfaces.
This product is very suitable for temporary storage and short time dispatch (metals being
protected by TECTYL 511-M must be covered so that neither rain water nor sunshine can
affect them). It forms a barrier between metals and aggressive mediums protecting steel from
rust and aluminium-magnesium-alloys from efflorescence.
Application
TECTYL 511-M can be applied by spraying, painting or dipping of the parts to be protected.
Removal
TECTYL 511-M can be removed without any difficulties by benzine, petroleum, Diesel oil, wax
solvents and alkali cleaner and steam.
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
6 1CYJ461103EXX -
Flash point DIN 51755 approx. 40°C
TECTYL 506
TECTYL 506 is a rust-preventive especially suitable for export of machines of various types.
When being supplied, product is liquid. The resulting wax film is not affecting any metal
surfaces and does not attack lacquer, plastics and rubber materials. This brown rust-
preventive is resistant against temperatures occurring in packing, which amount to 70-90°C in
some countries. The wax film furthermore has an outstanding adhesion with minus
temperatures. TECTYL 506 with its flexible protective film being tight and adhesive forms a
good barrier between metal surface to be protected and corrosive influences. Coverage
amounts to 6-8 m2 per litre - depending on the film thickness.
Protection Period on Clean Steel Surfaces (Film Thickness Approx. 100 Microns):
Application
TECTYL 506 can be applied by painting or spraying or airless to the parts to be protected
Removal
TECTYL 506 can be removed without difficulties by means of benzine, petroleum, Diesel oil or
wax solvents. In case of big surfaces steam jet cleaning device with special additives can be
used (prior to this use wax remover and wait for its reaction).
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Document No. Rev.No.
Technical Instruction:
2 1CYJ470068 -
In order to get a safe and trouble-free operation with pneumatic actuators, the
instrument
air shall fulfil the demands in either ISO 8573-1 or ANSI/ISA-7.0.01-1996.
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Document No. Rev.No.
Technical Instruction:
FIRE PROTECTION OF TG HALL
2 1CYJ470065 -
It is essential to design the turbine and equipment to minimize the risk for fire. Based on our
experience passive protection has reduced the risk to an acceptable level.
• Welded couplings are used for the high-pressure oil tubing to avoid leakage.
• Shielding Plates are provided near front and rear bearing pads in order to avoid the
exposure to High temperature region of Turbine casing.
• Steam pipes and oil pipes shall be separated on each side of the turbo set in order to
avoid mixture of hot steam pipes and oil pipes. If separation is not possible, separating
plates shall be mounted between the oil- and steam containing parts.
• Sub-atmospheric pressure is present in the lube oil supply unit, return lube oil piping and
part of the bearing bracket in order to reduce the risk for leakage.
• All lube oil piping/oil tubing are routed in such a way that the risk for rupture of
piping/tubing due to mechanical damage is minimized.
If the customer requires or insurance company demands active fire protection, we recommend
the customer to install a water-spray protection.
3 1CYJ470065 -
• The protection should be provided for the following.
Bearing housings
Shaft-driven oil pumps
Control oil systems using mineral oil
Main supply and return oil piping
When there is a sound enclosure on the turbine operating floor, the turbine foundation must be
equipped with necessary floor drainages. This in order to be able to drain the water inside the
sound enclosure if the water-spray system have been activated.
• Operator training to secure the unit so that lube oils pumps can be shut off as quickly and
safely as possible.
• Protection of control rooms, located in turbine buildings in order to provide operators the
opportunity to take action during emergency.
• Protection of critical cable to minimize the possibility of loss of more than one unit and
reduce the chance of uncontrolled loss of lubrication system.
Figure. 1
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Document No. Rev.No.
Technical Instruction:
JOB SITE STORAGE OF GOODS
2 1CYJ470066 -
During storage before and during erection and first start certain precautions must be taken
in order to prevent corrosion damage to the plant equipment.
This instruction primarily covers the equipment leaving Siemens Ltd. workshop in India.
Special attention must be given to the generator, where, for instance, all the heaters must
be connected and activated upon arrival at site. Additional information will be made
available before shipping.
All machinery, electrical and other sensitive parts shall be stored indoors. If the storage
time exceeds 2 - 3 months, the packages shall be opened and a dehumidifier unit
Connected to the storage room in order to keep the relative humidity below 50 %.
Other equipment, such as piping and less sensitive materials, need not to be stored dry
indoors. Instead, rust protection by use of rust preventive agents e.g. Tectyl TM, water-
soluble oils and silica gel inside sealed-off space can be used. Weather protection and
periodic inspections are recommended.
Arrival at site
General parts
Place the crates and boxes, so that they will not be exposed to water (rain, flooding etc.)
and/or physical damage.
Do not open any box or crate until the equipment in that specific box or crate is to be used.
If an opened box or crate is to be stored further, it must be carefully closed and resealed.
At the opening of the different boxes an inventory must take place using the packing list
for each box, in the presence of a Siemens Ltd. representative.
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Page: Document No. Rev.No.
3 1CYJ470066 -
Spare parts
Spare parts are to be placed indoors in a ventilated space in normal room temperature
and preferably low humidity. Rust inhibitors should not be removed until each spare part is
intended to be used.
Control cubicles
Do not remove or damage the plastic film that covers each cubicle.
If an inspection of the cubicles has to be made the moisture absorbent (silica gel) must not
be removed from inside the cubicles. The plastic film should then be hermetically resealed
by welding as soon as possible.
Do not place the cubicles in their final space until the conditions are such that no
Condensation will take place inside the cubicles.
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010
Document No. Rev.No.
Technical Instruction:
GROUTING MATERIAL SPECIFICATION
Unrestricted
_________________________________________________________________________________________________________________________________
We reserve the rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly
forbidden. © SIEMENS Ltd.
2 1CYJ470067 B
GROUTING MATERIAL SPECIFICATION
General
Grouting Material:
Generally any grouting material having expansive characteristics is preferred. The Grout
expands while drying and is non-shrink with high early strength. Providing and laying High
Strength Non-shrink free flow grout below the base-Frame of the turbine, gear box,
alternator, condenser etc. as per the drawing, manufacturer’s specification and instruction of
Engineer in charge.
Volume / Quantity to be decided as per respective equipment drawings.
Table :1 Indicates minimum required Properties of Grouting material.
Unrestricted
_________________________________________________________________________________________________________________________________
Format No.: IP-Q-F-3009/C
Rev.Date : 31.03.2010