Method Statement For Wall & Columns Concreting
Method Statement For Wall & Columns Concreting
11
Page | 1
METHOD STATEMENT TPHL/QMS Document No. 11
CONTENTS
3. Materials required
4. Engineering works
5. Responsibility
6.1 Hazards
7. Sequence of work
7.4 Miscellaneous
8. Documentation
Page | 2
METHOD STATEMENT TPHL/QMS Document No. 11
The method statement involves concreting work procedure for wall & columns specified in the tender
document. It shall be done by experienced workmanship as per the latest and relevant specifications
/drawings and to the full satisfaction of the Engineer-in-charge.
Vibrator Needle dia 40 - 50mm to be used for workable concrete in thin wall & columns.
And needle dia 60mm to be used for workable concrete in thick wall & columns.
No Vibrator shall be used in SCC, only rubber hammer shall be used to vibrate the formwork.
3. Materials required:
3.1 Approved concrete mix (Normal or Self Compacting Concrete) as per IS 10262-2019, IS 4926-
2003
3.2 Drinking water as IS 456-2000
3.3 Ordinary Portland Cement as per IS 269-2015
3.4 PVC/concrete cover blocks
4. Engineering works:
As receipt of drawings the Engineer-in-charge shall review the received drawings and discuss with their
senior for any technical doubts and clarifications.
5. Responsibility:
5.1 The Engineer-in-charge will be responsible for implementing everything in this method statement.
5.2 Safety officer will ensure that all safety procedures and measures are implemented in relation to the
type of work being done according to the project’s HSE plan.
5.3 QA/QC representative will be responsible for the implementation of QA/QC works as spelled out in
the Quality Management Plan.
Page | 3
METHOD STATEMENT TPHL/QMS Document No. 11
Page | 4
METHOD STATEMENT TPHL/QMS Document No. 11
6.3.8 In less serious cases, first aid or clinical aid shall be extended to injured victims if any and the
matter intimated to all concerned. Adequate first aid boxes shall be in place and trained first
aiders provided at site.
7. Sequence of work:
7.1 Preparation for wall & columns concreting:
7.1.1 The Engineer-in-charge will ensure all necessary platforms are made with double handrails to
execute the work.
7.1.2 Required level of concrete shall be marked on the formwork.
7.1.3 Needle vibrator shall be arranged, in working condition with spare needles.
7.1.4 Support to formwork shall be checked properly and shall be ensure tighten and rigid.
7.1.5 Site engineer shall ensure all parameters of works are in place.
7.1.6 The position and arrangement of construction joints shall be as shown in the structural drawings
or as directed by the Engineer-in-charge. The number of these joints should be kept minimum
and shall be kept as straight and shear key must be made as per Drawing.
7.1.7 When the work to be resumed on old concrete surface which has hardened, such surface shall be
roughened, clean and wetted with water thoroughly.
7.1.8 For horizontal joints, the cement mortar slurry shall be poured over existing concrete surface
with a thickness of about 8-10 mm, composed of cement and sand ratio as in the concrete mix,
immediately before placing of the concrete, this will help to avoid the honeycombing at joint
level “in case of normal concrete.”
7.1.9 For horizontal joints, in case of self-compacting concrete no cement mortar slurry is required to
pour prior to pour the concrete in formwork.
7.4 Miscellaneous:
Page | 5
METHOD STATEMENT TPHL/QMS Document No. 11
The completed works shall be inspected and any left out items, minor defects if any, shall be rectified
immediately.
8. Documentation: RFI & checklist shall be maintained by site Engineer for the work.
Page | 6