Chapter 14 (New)
Chapter 14 (New)
►
Global Company Profile:
Wheeled Coach
Dependent Demand
► Dependent Inventory Model
Requirements
PowerPoint presentation to accompany
Heizer and Render ► MRP Structure
Operations Management, Global Edition, Eleventh Edition
Principles of Operations Management, Global Edition, Ninth Edition ► MRP Management
PowerPoint slides by Jeff Heyl
© 2014
© 2014
Pearson
Pearson
Education
Education 14 - 1 © 2014 Pearson Education 14 - 2
1
27/07/2022
© 2014
© 2014
Pearson
Pearson
Education
Education 14 - 7 © 2014 Pearson Education 14 - 8
2
27/07/2022
Figure 14.1
© 2014 Pearson Education 14 - 13 © 2014 Pearson Education 14 - 14
Production Marketing
Finance
Capacity Customer
Cash flow Master production
Inventory demand
schedule
Change
master
production
schedule?
Supply Chain Sales & Operations Material
Procurement Planning Human Resources requirements plan
Supplier Generates an Staff planning
performance aggregate plan
Schedule and
Master production execute plan
schedule
3
27/07/2022
Level Product structure for “Awesome” (A) Level Product structure for “Awesome” (A)
Part B: 2 x number of As = (2)(50) = 100
0 A 0 C:
Part 3 x number of As = A (3)(50) = 150
Part D: 2 x number of Bs
1 B(2) C(3) 1 B(2) + 2 x number of Fs = (2)(100) + (2)(300)
C(3) = 800
Part E: 2 x number of Bs
+ 2 x number of Cs = (2)(100) + (2)(150) = 500
2 E(2) E(2) F(2) Part
2 F: 2 x number
E(2) of Cs = (2)(150) =
E(2) F(2)300
Part G: 1 x number of Fs = (1)(300) = 300
4
27/07/2022
▶ Outstanding purchase orders must of the move, setup, and Lead Times for Awesome
Speaker Kits (As)
assembly or run times
accurately reflect quantities and COMPONENT LEAD TIME
Time-Phased Product
Structure Figure 14.3
MRP Structure
Figure 14.4
Must have D and E Data Files
Start production of D Output Reports
completed here so
production can begin MRP by
on B BOM Master period report
1 week production schedule
2 weeks to
D produce MRP by
date report
B
2 weeks Lead times
E (Item master file) Planned order
A report
2 weeks 1 week
Inventory data
E Purchase advice
2 weeks 1 week Material
requirement
G C planning
3 weeks programs
F (computer and Exception reports
Purchasing data software)
1 week Order early or late
D or not needed
| | | | | | | |
Order quantity too
1 2 3 4 5 6 7 8 small or too large
Time in weeks
© 2014 Pearson Education 14 - 29 © 2014 Pearson Education 14 - 30
5
27/07/2022
appears at only one level in the BOM D. Required date 600 200
Order release date 600 200 1 week
G. Required date 300
Order release date 300 2 weeks
6
27/07/2022
▶ Starts with a production schedule for the end ▶ Following the lead time offset procedure, the
item – 50 units of Item A in week 8 planned order release for Item A is now 40 units
in week 7
▶ Because there are 10 Item As on hand, only
40 are actually required – (net requirement) = ▶ The gross requirement for Item B is now 80 units
(gross requirement – on-hand inventory) in week 7
▶ The planned order receipt for Item A in week ▶ There are 15 units of Item B on hand, so the net
8 is 40 units – 40 = 50 – 10 requirement is 65 units in week 7
▶ A planned order receipt of 65 units in week 7
generates a planned order release of 65 units in
week 5
week 8
▶ This is referred to as the Gross-to-Net
calculation and is the third basic function of the
MRP process Periods 1 2 3 4 5 6 7 8
Therefore, these are
40+10 15+30
Gross requirements: B 10 40 50 20 the gross
=50 =45
requirements for B
© 2014 Pearson Education 14 - 39 © 2014 Pearson Education 14 - 40
Gross + Allocations
requirements
Total requirements
On Scheduled Net
– + = requirements
hand receipts
Figure 14.6
Available inventory
7
27/07/2022
8
27/07/2022
Holding cost = $1/week; Setup cost = $100; Lead time = 1 week Holding cost = $1/week; Setup cost = $100; Lead time = 1 week
Holding cost = $1/week; Setup cost = $100; Lead time = 1 week Holding cost = $1/week; Setup cost = $100; Lead time = 1 week
Average weekly gross requirements = 27; EOQ = 73 units Average weekly gross requirements = 27; EOQ = 73 units
© 2014 Pearson Education 14 - 51 © 2014 Pearson Education 14 - 52
Scheduled Scheduled
receipts receipts
Projected on Projected on
35 35 0 40 0 0 70 30 0 0 55 35 35 0 40 0 0 70 30 0 0 55
hand hand
Net Net
0 30 0 0 10 0 0 55 0 0 30 0 0 10 0 0 55 0
requirements requirements
Planned order Planned order
70 80 0 85 0 70 80 0 85 0
receipts receipts
Planned order Planned order
70 80 85 70 80 85
releases releases
EOQ = 73 units; Average weekly gross requirements = 27; EOQ = 73 units; Average weekly gross requirements = 27;
POQ interval = 73/27 ≅ 3 weeks POQ interval = 73/27 ≅ 3 weeks
© 2014 Pearson Education 14 - 53 © 2014 Pearson Education 14 - 54
9
27/07/2022
10
27/07/2022
OK?
NO Priority Management Capacity Management
requirements for work centers
Develop Master Production
Schedule
Evaluate Resource Availability
(Rough Cut)
▶ Work can be moved between work
OK?
NO OK? YES Planning centers to smooth the load or bring it
Prepare Materials
Requirements Pan
Determine Capacity Availability
within capacity
OK? YES
Execution
Detailed Production Implement Input/Output Control (in repetitive
Activity Control systems JIT
(Shop Scheduling/Dispatching) techniques
are used)
move 2 units to
12 – 12 –
day 1
3 13 13 12 1 Split order: 13 10 – 10 –
move one unit
to day 6 or 8– 8–
request
overtime 6– 6–
4 10 10 12 (2) 12 4– 4–
5 14 14 12 2 Split order: 12 2–
move 2 units to
2–
day 4 0– 0–
61 1 2 3 4 5 1 2 3 4 5
Days Days
(a) (b)
11
27/07/2022
directly linked to demand for other Buffalo Chicken Mac & Cheese
services
▶ These can be treated as dependent
Garnish with Buffalo Chicken Baked Buffalo Chicken Mac
mix, Blue Cheese, Scallions & Cheese
▶ Hotels Grated
Smoked Blue Cooked Mac &
Buffalo Pepper Chopped
Pulled Cheese Elbow Cheese Milk
Sauce Jack Scallions
Chicken Crumbles Macaroni Base
Cheese
12
27/07/2022
Figure 14.10 ERP and MRP Figure 14.10 ERP and MRP
Customer Relationship Management
Figure 14.10 ERP and MRP Figure 14.10 ERP and MRP
Master
Production
Schedule
Inventory Bills of
Management Material
MRP
Work
Orders
Supply-Chain Management
Vendor Communication
(schedules, EDI, advanced shipping notice,
Purchasing Routings e-commerce, etc.)
and and
Lead Times Lead Times
Table 13.6
13
27/07/2022
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or
transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or
otherwise, without the prior written permission of the publisher.
Printed in the United States of America.
14