Lecture 8 - Design Economics
Lecture 8 - Design Economics
1) Client’s Requirements
• Performance
• Time
• Cost
Page2
.:Client’s Requirements:.
Page3
Introduction
The client's requirements for a project might initially include a vision, mission and objectives for
what they wish the project to achieve.
The success of any construction project can be measured against several different criteria.
• Appearance
• Quality
• Function
Performance • Durability
• Maintenance
• Design Length
• Start Date
• Completion Time
• Handover
• Budget
• Estimate
Cost • Tender
• Final Account
• Cost-in-Use
Page4
Performance
• The architect must produce a basic plan concept to meet the client’s requirements in the most
efficient manner.
• The quality of the finished work will have been defined in the specification and the selection of an
experienced contractor and the required supervision throughout the construction on site.
• Inadequate design and detailing and the wrong choice of materials are elementary problems that
will cause obstacles to proper performance.
• Must satisfy that the completed structure meets his needs and requirements in terms of design
and the structure’s function.
• A further important consideration of the future maintenance requirements once the project is in
use.
Page5
Time
• Once the clients decide to build, they are generally in a hurry for their completed projects.
• Although a large amount of time may be spent deliberating over a scheme, once the decision to
build is made, the project becomes of the utmost urgency.
• The design of the project will influence the methods adopted by the contractor for construction,
and these in turn will have an important influence on the length of the contract period.
• One method of measuring the success of a project is whether it is available for commissioning by
the date promised in the contract documents.
Page6
Cost
• Before clients commit themselves to the detailed design of projects, some information on the
expected price is usually required.
• Eventually a tender sum will be accepted, and once the work has been completed, the final
account can be agreed.
• It is also measure cost in terms of initial values and for life cycle cost.
Page7
.:Factors Affecting Economic in Design:.
Page8
Introduction
Page10
Planning and
3 Contour 4 Ground Conditions 5 Building Regulation
• The more steeply sloping • Low load – bearing Ratio off site value of cost of
the site the greater will be capacity of surface soil
the cost of foundations and required piling, raft buildings should always be
earthworks. foundation etc. considered:-
• Large quantity of cut and • Excavation in rock could be • Secure the most profitable
fill required for floor. 5 to 8 times more permitted use
expensive.
• Higher water level will • Obtain maximum site
increase cost if pumping utilization.
throughout construction
period
• Shrinkable clay soil needs
to take foundation at least
1 meter below ground level
• Sandy soil with running
underground water may
course sinkhole
Page11
Building Size
Client A
Height = 4m
• This is an important factor in terms of cost
efficiency.
• Large buildings have lower unit costs than small 68m 68m
size of buildings which offering an equivalent
quality of specification.
30m 30m
• Small projects take a longer time per unit to
design, and this is reflected in the design costs. Client B
Height = 4m
• Large project can be more efficiently managed, 80m
particularly where the size of the project
warrants a resident site manager.
51m
Page 12
Based on:-
The lowest wall to floor area ratio, the more economic will
be design when judged against this criterion.
Page 13
SOLUTIONS
Client A
Height = 4m
Therefore,
GFA for 2 buildings for Client A
= 2040m² + 2040m² = 4080m²
Page 14
SOLUTIONS
Client B
Height = 4m
80m
Therefore,
GFA for 1 building for Client B
= 4080m²
Page 15
WHICH ONE IS ECONOMIC?
Page 16
Plan Shape 20m
Building A Building C
20m Height = 3m Height = 3m
A 20m
10m C
40m
Page 18
Building B
Therefore, Building B
a) GFA
Height = 3m Area 1 = 30m x 10m = 300m²
10m Area 2 = 10m x 10m = 100m²
30m B 10m
b) Perimeter Wall (Girth)
10m = 10m+30m+10m+20m+12m+10m+10m+10m+8m
= 100m
Page 19
WHICH ONE IS ECONOMIC?
10m
20m 8m
0.75
0.6
B 10m
A 20m
10m
10m
0.75
10m C
40m
Page 20
Total Height
• Construction cost increase in the total height of building or number of storey.
• The constructional costs of tall structures are greater than those of low – rise buildings offering
a similar amount of accommodation
• Multi – storey buildings are more expensive than low rise buildings; because of:-
Page 21
Wind load
(e.g Plumbing,
Live load
refuse
disposal/chute) Wind load
Dead load
Fire
protection
Vertical
Structural transportation
Frame (e.g capacity, speed,
cable, car shaft etc)
Foundation
Effect of Increasing Total Height
( load )
Page 22
Storey Height
Page 23
Effect on:-
6 storey 6 storey ⁻ Wall
⁻ Service Pipe
⁻ Lift
2.8m 3.2m
⁻ Staircase
⁻ Roof
⁻ Hoisting of materials and
equipment
⁻ Foundation
⁻ Frame
⁻ Flooring
10.00 m 10.00 m
A B
10.00 m 10.00 m
Wall/Floor Ratio = 1.12 Wall/Floor Ratio = 1.28
Page 24
Grouping of Buildings
• The grouping and arrangement of building on site can have an important influence on the
overall cost of the project.
• Inter link buildings or structure, a saving in costs can usually be achieved often because of a
saving in foundation and external walling costs or other common items of construction.
WHICH
C ONE IS
A B ECONOMIC? D
Page 25
By grouping the buildings, the changes in cost can be examined. The height of the building is 4.00m, the
construction cost of half-brick thick external walls is RM35.00/m². Therefore, identify which building is the
most economic based on construction cost. Each units have the same area, height, and quality.
Broad Fronted
Narrow Fronted
Area (m²) Area (m²)
Party wall 6.67 x 4 = 26.68 Party wall 10 x 4 = 40
External wall 36.67 x 4 = 146.68 External wall 30 x 4 = 120
• Buildability is defined as the extent to which the design of a building facilitates ease of
construction, subject to the overall requirements for the completed building.
• Largely concerned with the work on site and the practicalities of producing a structure from a
design.
• The quality of work should be interpreted not as building quality alone, but also as the
performance of the building throughout its life.
Page 27