Project Methodology
Project Methodology
COLLECTOR
1.0 Pre-Shutdown Phase
1.1 Secure of work permits to responsible permit issuer.
1.2 Hauling and unloading of tools, equipment’s and materials
from BP Industrial Fabrication Shop to worksite.
1.3 Conduct site inspection and validation.
1.4 Adhere to URS requirements for equipment purchase, design, and installation.
1.5 Submit detailed structural design for pipe supports (if applicable).
1.6 Demonstrate all required tools before execution.
1.7 Advance works: Fabricate new SS ducting and pipe supports brackets/base plates.
1.8 Execute line release.
3. 0 Post-Shutdown Phase
3.1 Perform testing to ensure proper functionality.
3.2 Tag the machinery accordingly.
3.3 Disassemble scaffolding.
3.4 Implement 5S principles, environmental release, and demobilization
Prepared by:
MICHAEL SANCHEZ
Project In-charge