List of Holidays-
Jan- 1, 14, 26
Feb- 23
Mar- 10, 11, 27
April- 3, 7, 10
May- 1
Aug- 15, 19, 23
Sept- 3, 21, 28
Oct- 2, 17-21
Dec- 25
EPS
OBS
Execution
General Works Aditya Gujar, Contractor
1.2 Substructure
1.2.1 Foundations
Excavate foundations Backhoe (25)
Excavate elevator pit Backhoe (1)
P.C.C. for all footings Concrete (150 cum)
R.C.C. works for footings and columns Concrete (105 cum)
Prepare and pour concrete for floor Concrete (190 cum)
1.2.2 Basement
Casting of Columns Concrete (90cum)
Casting of Lift wall Concrete (23cum)
Casting of Staircase Concrete (8cum)
Shuttering work for slab Shuttering(1500sqm)
Slab casting Concrete (150 cum)
1.3 Superstructure
1.3.1 Ground Floor
Casting of Columns Concrete (90cum)
Casting of Lift wall Concrete (23cum)
Casting of Staircase Concrete (8cum)
Shuttering work for slab Shuttering(1500sqm)
Slab casting Concrete (150 cum)
1.3.2 First Floor
Casting of Columns Concrete (90cum)
Casting of Lift wall Concrete (23cum)
Casting of Staircase Concrete (8cum)
Shuttering work for slab Shuttering(1500sqm)
Slab casting Concrete (150 cum)
1.3.3 Second floor
Casting of Columns Concrete (90cum)
Casting of Lift wall Concrete (23cum)
Casting of Staircase Concrete (8cum)
Shuttering work for slab Shuttering(1500sqm)
Slab casting Concrete (150 cum)
1.3.4 BRICKWORK, Door frames
Bricks (15,000 nos.) FW door
Basement Qty (58 sqm), Door frames
(Sal wood) (210 Rm)
Bricks (13,000 nos.),FW door
Ground Qty(58 sqm),Door frames(Sal
wood)(210 Rm)
Bricks (12,000 nos.),FW door
First Qty(58 sqm),Door frames(sal
wood)(210 Rm)
Bricks (12,000 nos.), FW door
Second Qty(58 sqm),Door frames(sal
wood)(210 Rm)
1.3.5 Internal Plaster
Cement (145 bags), Sand (50
Basement cum)
Cement (135 bags), Sand (40
Ground cum)
Cement (125 bags), Sand (35
First cum)
Cement (125 bags), Sand (35
Second cum)
1.3.6 External Plaster
Cement (150 bags), Sand (52
Basement cum)
Cement (140 bags), Sand (42
Ground cum)
Cement (130 bags), Sand (38
First cum)
Cement (130 bags), Sand (38
Second cum)
1.3.7 External Painting
Basement Paint (15 lit)
Ground Paint (15 lit
First Paint (15 lit)
Second Paint (15 lit)
1.3.8 Concealed Conduiting & Waterproofing
Toilet s water Proofing (77
Basement sqm)
Toilet s water Proofing (77
Ground sqm)
Toilet s water Proofing (77
First sqm)
Toilet s water Proofing (77
Second sqm)
1.3.9 Aluminium Windows & grills Fixing
Aluminium powder coated
Basement sliding windows (80 sqm)
Aluminium powder coated
Ground sliding windows (80 sqm)
Aluminium powder coated
First sliding windows (80 sqm)
Aluminium powder coated
Second sliding windows (80 sqm)
1.3.10 Toilet Dado
Cermic- Glazed Tiles (340
Basement sqm)
Cermic- Glazed Tiles (340
Ground sqm)
Cermic- Glazed Tiles (340
First sqm)
Cermic- Glazed Tiles (340
Second sqm)
1.3.11 TILING Flooring & Kitchen Dado
Vitrified Tiles Flooring (495
sqm), Vitrified tiles
skirting(566 Rm),Cermic
flooring(143 sqm),Cermic tiles
skirting(199 Rm),Anti-skid
ceramic tiles (165 sqm),black
granite platform in kitchen(21
Basement RM)
Vitrified Tiles Flooring (495
sqm),Vitrified tiles skirting(566
Rm),Cermic flooring(143
sqm),Cermic tiles skirting(199
Rm),Anti-skid ceramic tiles
(165 sqm),black granite
Ground platform in kitchen(21 RM)
Vitrified Tiles Flooring (495
sqm),Vitrified tiles skirting(566
Rm),Cermic flooring(143
sqm),Cermic tiles skirting(199
Rm),Anti-skid ceramic tiles
(165 sqm),black granite
First platform in kitchen(21 RM)
Vitrified Tiles Flooring (495
sqm),Vitrified tiles skirting(566
Rm),Cermic flooring(143
sqm),Cermic tiles skirting(199
Rm),Anti-skid ceramic tiles
(165 sqm),black granite
Second platform in kitchen(21 RM)
1.3.12 Fixing Door Shutters
D1(15 SQM), D2(37
SQM),D3(11 SQM),D4(41
Basement SQM)
D1(15 SQM),D2(37
SQM),D3(11 SQM),D4(41
Ground SQM)
D1(15 SQM),D2(37
SQM),D3(11 SQM),D4(41
First SQM)
D1(15 SQM),D2(37
SQM),D3(11 SQM),D4(41
Second SQM)
1.3.13 Internal Painting
Basement Paint (45 lit)
Ground Paint (45 lit)
First Paint (45 lit)
Second Paint (45 lit)
1.3.14 Sanitary Wares & Electrical Fittings
Sanitary Wares & Electrical
Basement Fittings Building (10156 sqm)
Sanitary Wares & Electrical
Ground Fittings Building (10156 sqm)
Sanitary Wares & Electrical
First Fittings Building (10156 sqm)
Sanitary Wares & Electrical
Second Fittings Building (10156 sqm)
1.3.15 Building Services
Procurement of lift Fixed cost Rs.400000
Lift Installation work Fixed cost Rs.25000
Procurement of DG Fixed cost Rs.300000
Procurement of Transformer Fixed cost Rs.100000
Installation of DG Fixed cost Rs.15000
Installation of Transformer Fixed cost Rs.300000
HT & LT Cabling work Fixed cost Rs.50000
Firefighting system Fixed cost Rs.15000
Finishing Work Helper- 15