Section 5
Section 5
1. GENERAL ...................................................................................................... 2
QCS 2010
QCS 2010 Section 5 Part 1 General Page 2
1. GENERAL
1.1 INTRODUCTION
1.1.1 Scope
1 This Section includes the requirements for concrete work for pipelines, roadworks, runways,
structures, water retaining structures, foundations and bases for structures and equipment.
2 This Part includes relevant standards, definitions, abbreviations, and requirements for testing
facilities, rejected materials, and record keeping.
GSO ISO 1920-1 ....... Testing of concrete —Part 1: Sampling of fresh concrete
GSO ISO 1920-2 ....... Testing of concrete – part 2: properties of fresh concrete
GSO ISO 1920-3 ....... 2007 Testing of concrete – part 3: Making and curing test specimens
QCS 2010
QCS 2010 Section 5 Part 1 General Page 3
1.1.3 Definitions
QCS 2010
QCS 2010 Section 5 Part 1 General Page 4
1.2 PRODUCTS
1.2.1 Approved Products
1.3 IMPLEMENTATION
1.3.1 Approved Installers
1 The Contractor shall carry out the test procedures required by this Section and any other
tests and test procedures as directed by the Engineer from time to time. The test
procedures shall be carried out using the facilities of an approved independent testing
laboratory.
2 Supply, storage, sampling and testing of all materials shall be the responsibility of the
Contractor, unless the Contract specifies others.
3 The Engineer may also require the Contractor to take samples of materials and deliver them
to the Central Materials Laboratory for additional tests to be carried out by the Employer.
Sampling procedures and sample sizes shall conform to the requirements shown in Table
1.1.
4 The minimum equipment required for testing on Site is given in Table 1.2. This equipment
shall be maintained on Site at all times during concreting operations together with the
necessary scoops, buckets, sample containers, and other items required for sampling. The
cube curing tank shall be located in an air-conditioned area as stated in part 06.
1 Any material rejected by the Engineer, in particular cement which has deteriorated or
aggregates which have segregated or become contaminated, shall be immediately removed
from the Site.
1.3.4 Records
1 The Contractor shall maintain on the Site full records of all work carried out accurately
related to the location of the work on site, which shall include:
(a) the time and date when all concrete was poured, formwork removed and when
formwork props were fully removed
2 One copy of all test results shall be sent to the Engineer immediately upon completion of the
tests
QCS 2010
QCS 2010 Section 5 Part 1 General Page 5
Table 1.1
Sampling Procedure and
Minimum Sample Sizes for Central Materials Laboratory
Material Test Min. Sample
Composite sample of 7 kg
Cement Full range of tests
taken from at least 12 bags
Full range of tests 200 kg
Sieve analysis
Chemical analysis
Soundness test
Specific gravity
Aggregate Water absorption 50 kg
Table 1.2
Minimum Testing Equipment for Each Site*
Minimum Number
Test Equipment to be Provided
Required
Slump test BS EN Slump cone with base plate 1
12350-2 Tamping rod 1
Or Trowel 1
GSO ISO 1920-2 300 mm rule 1
or Small scoop 1
ASTM C143
Cube making 150 mm cubical or cylindrical moulds1 6
BS EN 12390-1 and base plate
and Tamping bar square or hemispherical 1
BS EN 12350-1:2000 tip end face
or Set of tools for assembling and 1
GSO ISO 1920-1 stripping moulds -
and Trowel Scoop as for slump test -
GSO ISO 1920-3 Released agent in closed container 1
or ASTM C31 and C39 with brush
Hessian or sacking, impervious sheet lot
Cube curing BS EN Maximum/minimum thermometer 1
12390-2 Waterproof marking crayon/paint or
Or equivalent 1
GSO ISO 1920-3 Curing tank (in air conditioned room) 1
or ASTM C39 Supply of packing materials for sending
cubes to commercial laboratory Lot
ASTM C1064 Concrete thermometer 1
1 As specified by the designer (cube or cylinder, and nominal size d). The use of 100 mm cube
and cylinder moulds are not permitted unless otherwise specified by designer and when the
nominal maximum aggregate size is less than 20mm
END OF PART
QCS 2010
QCS 2010 Section 5 Part 2 Aggregates Page 1
2. AGGREGATES .............................................................................................. 2
QCS 2010
QCS 2010 Section 5 Part 2 Aggregates Page 2
2. AGGREGATES
2.1 GENERAL
2.1.1 Scope
1 This part covers the requirements of aggregates for use in structural concrete.
QCS 2010
QCS 2010 Section 5 Part 2 Aggregates Page 3
BRE Digest 330-2 ----- Alkali-Silica Reaction in Concrete – Detailed Guidance for New
Construction.
BS 812 ------------------- Testing aggregates
BS 8500 part 2 --------- Concrete. Complementary British Standard to BS EN 206-1.
Specification for constituent materials and concrete
BS EN 12620 ----------- Aggregates for concrete
BS EN 1744-1 ---------- Tests for chemical properties of aggregates, Chemical analysis
BS EN 1367-4 ---------- Determination of drying shrinkage
BS EN 933 -------------- Tests for geometrical properties of aggregates
BS EN 1097-6 ---------- Tests for mechanical and physical properties of aggregates.
Determination of particle density and water absorption
BS EN13055-1 --------- Lightweight aggregates. Lightweight aggregates for concrete, mortar
2.1.4 Sampling
1 The Contractor shall provide samples of both fine and course aggregate to the Engineer, in
accordance with the requirements of relevant standards in QCS for sampling, sample
reducing and testing of Aggregates, for testing at least two weeks before beginning
deliveries to the Site.
2 All samples shall be taken in the presence of the Engineer or an approved testing agency
assigned by the Engineer.
QCS 2010
QCS 2010 Section 5 Part 2 Aggregates Page 4
and shall contain no materials likely to cause staining or otherwise disfigure the concrete
surface.
2 Aggregates which shall be obtained from a source approved by the Engineer, shall comply
with the requirements of BS EN 12620 with BS PD 6682, EN 12620, EN 13139 , EN 998-1 ,
EN 998-2, ASTM C33 and relevant EN, ACI and ASTM standards and codes of practice and
subject to Engineer’s acceptance except as modified here under. If required by the Engineer,
and in order to comply with these requirements the aggregates shall be washed with water to
meet with the requirements of part 04.
3 Contractor shall provide all data as specified in QCS
4 Contractor shall ensure that aggregates to be supplied will not be susceptible to alkali
aggregate reaction.
5 Sampling of the aggregates shall be carried out in accordance with the requirements of BS
QCS 2010
QCS 2010 Section 5 Part 2 Aggregates Page 5
Table 2.1
Limits for Physical, Chemical and Mechanical Properties of Aggregates for Normal Concrete
Flakiness index
Used for reinforced concrete 30% max
Elongation index
Used for reinforced concrete 35% max
QCS 2010
QCS 2010 Section 5 Part 2 Aggregates Page 6
Notes:
1- Use of a fine aggregate failing in the test is not prohibited, provided that:
a- The discoloration is due principally to the presence of small quantities of coal, lignite, or
similar discrete particles.
b- When tested for the effect of organic impurities on strength of mortar, the relative strength
at 7 days, calculated in accordance with ASTM C87, is not less than 95 %.
2- Air-cooled blast-furnace slag aggregate shall meet the requirements in BS EN 12620:2002 for
acid-soluble sulfate category AS1,0. In accordance with BS PD 6682-1 and BS EN 12620, air
cooled blast-furnace slag shall be free from dicalcium disintegration and from iron
disintegration when tested in accordance with BS EN 1744-1
3- The limit of 10% fines value (dry condition) is for 20 mm aggregates. Reference BS 812-111.
4- AIV The impact test can be used as an alternative to the Los Angeles test but a correlation
with the Los Angeles test should first be established to avoid double testing and ensure
mutual recognition of results. The Los Angeles test (reference method) should be used in
cases of dispute
5- It is applicable only for 20mm aggregates, for high strength concrete using 10 mm aggregates
the 10% fines value will be at least 100 KN
2 The gradation of fine aggregate for concrete and mortar shall be in accordance with the
gradation designations in EN 12620 with BS PD 6682, EN 13139 , EN 998-1 , EN 998-2,
QCS 2010
QCS 2010 Section 5 Part 2 Aggregates Page 7
relevant ACI and ASTM standards and codes of practice and subject to Engineer’s
acceptance.
3 Each batch of aggregate delivered to the Site shall be kept separate from previous batches,
and shall be stored to allow for inspection and tests to be carried out.
4 The Contractor shall mechanically wash the aggregate to remove salts and other impurities
in order to meet the specified requirements.
5 The storage area for the clean washed sand shall be shaded from the direct rays of the sun
and shall be screened for protection from dust. The area in the neighbourhood of
stockpile/mixing plant shall be watered as necessary, to reduce as far as possible the rising
of dust.
(b) Used only for blocks, block mortar, plasters, soil cement, shotcrete and insulation
concrete.
2 For other types of concrete mixes subject to Engineer's acceptance, coarse aggregate shall
be complying with the relevant EN, ACI and ASTM standards and codes such as EN
guideline and ACI 237 for Self Consolidating Concrete (SCC) and ACI for shotcrete.
3 Aggregates that are deleteriously reactive with the alkalis in cement shall not be used.
4 Exception: Aggregates that have been shown by test or actual service to produce concrete
of adequate strength and durability and approved by the building official.
5 Nominal maximum size of coarse aggregate shall be not larger than: (a) 1/5 the narrowest
dimension between sides of forms, nor (b) 1/3 the depth of slabs, nor (c) 3/4 the minimum
clear spacing between individual reinforcing bars or wires, bundles of bars, individual
tendons, bundled tendons, or ducts.
6 These limitations shall not apply if, in the judgment of the licensed design professional,
workability and methods of consolidation are such that concrete can be placed without
honeycombs or voids.
7 The Contractor shall mechanically wash the aggregates to remove salts and other impurities
in order to meet the requirements specified.
1 The material passing the 0.063 mm sieve shall not exceed 3.0 % of the combined aggregate
(by weight) and not exceeding 3.5% on 0.075mm sieve when used in accordance with ASTM
C117.
2 Combined aggregate gradation used in the work shall be as specified, except when
otherwise approved or directed by the Engineer.
QCS 2010
QCS 2010 Section 5 Part 2 Aggregates Page 8
3 Changes in the approved gradation shall not be made during the progress of the works
unless approved or directed by the Engineer.
5 Organic Impurities (Test Method ASTM C 40): Lightweight aggregates that, upon being
subjected to test for organic impurities, produce a colour darker than the standard shall be
rejected, unless it is demonstrated that the discoloration is due to small quantities of
materials not harmful to the concrete.
6 Staining (Test Method ASTM C 641): An aggregate producing a stain index of 60 or higher
shall be rejected when the deposited stain is found upon chemical analysis to contain an iron
content, expressed as Fe2O3 equal to or greater than 1.5 mg/200 g of sample
7 Loss on ignition (Test Methods ASTM C 114): The loss on ignition of lightweight aggregates
shall not exceed 5 %.
8 The acid soluble sulfate content shall be not more than 1% when measured in accordance
with BS EN 1744-1
2 A representative sample of the RCA or RA is sieved into size fractions. For each size fraction
the particles are sorted by hand into concrete and normal-weight aggregates; masonry;
lightweight block materials; asphalt; other foreign matter.
3 The mass of each of these groups is determined and expressed as a mass fraction (%) of
the sieve size. For each sieve size, tests are carried out on duplicate test portions and the
test result is the average percentage from the two tests. The data for the different sieve sizes
are then manipulated to determine the mass fraction (%) of the combined RCA or RA.
QCS 2010
QCS 2010 Section 5 Part 2 Aggregates Page 9
4 When the composition of coarse RCA and coarse RA is tested in accordance with BS 8500
part 2 Annex B, the test result obtained for each type of particle shall not exceed the
maximum value specified in Table 2.3.
Table 2.3 Requirements for coarse RCA and coarse RA Requirements given as mass fraction (%)
(BS 8500-2)
Requirement 1
1 Where the material to be used is obtained by crushing hardened concrete of known composition
that has not been in use, e.g. surplus precast units or returned fresh concrete, and not
contaminated during storage and processing, the only requirements are those for grading and
maximum fines.
2 Material with a density less than 1 000 kg/m3
3 The provisions for coarse RCA may be applied to mixtures of natural coarse aggregates blended
with the listed constituents.
4 The appropriate limit and test method needs to be determined on a case-by-case basis (see Note
6 to 4.3 of BS 8500-2).
5 Glass aggregates are specifically excluded from BRE Digest 330-2, and recycled aggregates
should be treated as highly reactive aggregate. The alkali contribution from Recycled
concrete aggregate shall be (reference made to BRE Digest 330-2) taken as either:
(b) where the composition of the recycled concrete aggregate is known (e.g. surplus
precast units; fresh concrete returned to the plant, allowed to harden and then
crushed), the alkali content calculated for the original concrete.
7 For manufacturing of masonry concrete blocks the usage of recycled aggregates can reach
100% of coarse aggregates, if applicable then ACI 555 requirements shall be applied.
END OF PART
QCS 2010
QCS 2010 Section 5 Part 3 Cement Page 1
3. CEMENT........................................................................................................ 2
3.1 GENERAL...................................................................................................... 2
3.1.1 Scope 2
3.1.2 References 2
3.2 SOURCE APPROVAL ................................................................................... 2
QCS 2010
QCS 2010 Section 5 Part 3 Cement Page 2
3. CEMENT
3.1 GENERAL
3.1.1 Scope
1 This Part covers the requirements for the testing and use of cement in structural concrete.
3.1.2 References
QCS 2010
QCS 2010 Section 5 Part 3 Cement Page 3
5 Cement manufacture shall label their packaging and delivery documents shall provide,
where applicable, with information on the packing/dispatch date, storage conditions and the
storage period appropriate to maintaining the activity of any reducing agent and to keeping
the content of soluble chromium (VI) below the 2 ppm limit. The Engineer shall has the right
to test the cement for presence of chromium at the contractor charge.
3.3 SAMPLING
1 The methods of obtaining samples of cement for testing shall be carried out as described in
EN 196 or ASTM C183
2 Each delivery of cement to the Site shall be accompanied by the manufacturer's test
certificates. If such certificates are not available, the Contractor shall take representative
samples from different bags or containers of each consignment, or as required by the
Engineer. The samples shall be packed, labelled and sent for testing to an accepted testing
QCS 2010
QCS 2010 Section 5 Part 3 Cement Page 4
2 Cement shall be stored at the site in such a manner, as to prevent its deterioration, intrusion
of moisture and foreign matter. It must be kept dry at all times. Immediately upon arrival at
the Site the Contractor shall store the cement in
(a) bins or silos designed for the purpose. It shall be tight and provide for free movement to
discharge opening, or
(b) dry, weather tight and properly ventilated structures with floors raised a minimum of
450 mm above the ground with adequate provision to prevent absorption of moisture.
QCS 2010
QCS 2010 Section 5 Part 3 Cement Page 5
3 All storage facilities shall be subject to the approval of the Engineer, and shall be such as to
permit easy access for inspection and identification. Prolonged storage of cement at site is to
be avoided.
4 Each consignment of cement shall be kept separately, and the Contractor shall use the
consignments in the order in which they are received.
5 The Contractor shall keep records of the various consignments of cement in store, giving
quantities received and used, and the sections of the work in which the cement has been
used, on a daily basis and make a weekly return to the Engineer accordingly. Cement used
in the Works shall be free flowing and free from lumps.
6 In no case shall bagged cement be stored in stacks more than eight bags high.
8 Different types of cement shall be kept in clearly marked separate storage facilities.
9 Cement delivered to Site in drums or bags by the supplier or manufacturer shall be stored in
the drums or bags until used in the Works.
10 Any cement in drums or bags which have been opened shall be used immediately.
11 Cement that has partially or fully caked in storage will not be permitted in work and shall be
immediately removed from the storage area. Any bag or package or sample of cement which
has been damaged, or rebagged or in any way has deteriorated shall be rejected either as
an individual bag or package or as the whole consignment in which such bag, package or
sample is contained, as advised by the Engineer.
12 Where Site limitations preclude the storage of cement of Site, cement shall be stored at a
central location and shall be delivered daily as required to specific job sites.
13 The Contractor shall provide weighing machines which shall be kept permanently in each
shed for checking the weight of the bags or barrels of cement. The weighing machines shall
be calibrated by an independent agency. The Engineer shall have access at all times to the
cement storage sheds.
14 During transport and storage the cement shall be fully protected from all weather elements.
15 Any consignment of cement not used within two months from the date of manufacture and
cement which in the opinion of the Engineer is of doubtful quality shall not be used in the
Works until it has been retested and test result sheets showing that it complies in all
respects with the specification and relevant standards have been delivered to the Engineer.
16 Cement stored for longer than 28 days shall be tested for “loss on ignition" prior to use to
check for deterioration, and any cement which fails the test shall not be used in the works.
END OF PART
QCS 2010
QCS 2010 Section 5 Part 4 Water Page 1
4. WATER .......................................................................................................... 2
4.1 GENERAL...................................................................................................... 2
4.1.1 Scope 2
4.1.2 References 2
4.2 QUALITY OF WATER.................................................................................... 2
4.2.1 General 2
4.2.2 pH of Water 3
4.2.3 Permissible Temperatures 3
4.2.4 Supply and Storage 3
QCS 2010
QCS 2010 Section 5 Part 4 Water Page 2
4. WATER
4.1 GENERAL
4.1.1 Scope
1 This Part includes water used for concrete mixes, washing of aggregates and equipment,
wetting of surfaces or ponding during curing or for wetting formwork and washing
reinforcement.
4.2.1 General
1 The potable water is suitable for use in concrete, while other water origin such as
underground water, natural surface water, recovered water, as well as municipal treated
water or mixed water shall be tested to prove that its quality shall conform to water quality
requirements of 3.3.1 and as explained in Table 1 and chemical limitations listed in Table 2
& Table 3.
2 In site, where permit is issued for Municipal Treated Effluent use for concrete, the effluent
shall be treated by tertiary treatment stage: Reverse Osmosis (R.O.), and disinfection
(Ultraviolet Radiation, or ozonation).
3 The water shall be examined in accordance with the test procedures stated in Table 1, EN
1008. Water not conforming to one or more of the requirements in Table 1, EN 1008 may be
used only, if it can be shown to be suitable for use in concrete, in accordance with the
physical tests of Table 1 below.
QCS 2010
QCS 2010 Section 5 Part 4 Water Page 3
4 The site health and safety services and Treated Effluent Quality shall fulfill the requirements
of 5.
4.2.2 pH of Water
1 Temperature of water for concrete shall not be less than 5 °C and not more than 40 °C
2 Water may be cooled to not less than 5 °C by the gradual addition of chilled water or ice as
follows:
1 The Contractor shall make his own arrangements and obtain the approval of the Engineer
for the supply of water.
2 Storage of water should be such that contamination is prevented from occurring. Any
measures taken to avoid contamination of the water shall be to the approval of the Engineer.
2 Samples of water of not less than 5 l shall be taken, sealed and sent for testing at an
approved independent laboratory, prior to the approval of any water source, and whenever
the sources of water is changed periodically during the continuance of its use.
3 Water of questionable quality should comply with the physical tests of Table 4.1 and
chemical limitations listed in Table 4.2 & Table 4.3.
4 No source of water shall be used until the required tests have demonstrated its suitability for
concreting.
5 The use of water from a municipal or government supply does not preclude the requirement
for testing.
Table 4.1
Acceptance Criteria and Physical Tests for Mixing Water
QCS 2010
QCS 2010 Section 5 Part 4 Water Page 4
Table 4.2
Chemical Limitations for Mixing Water
Maximum Limit,
Parameter Test Method
mg/l
Table 4.3
Maximum limit of Harmful Contaminants
Maximum Limit,
Parameter Test Method
mg/l
COD SM 5220 B 50
QCS 2010
QCS 2010 Section 5 Part 4 Water Page 5
QCS 2010
QCS 2010 Section 5 Part 4 Water Page 6
1 On site, where a permit is issued for Municipal Treated Water use in construction works, the
effluent should be treated by tertiary treatment stage including filtration and disinfectant
(Chlorine alone, or Ultraviolet Radiation, or ozonation). Furthermore, the following site health
and safety services and the Treated Effluent Quality shall be fulfilled:
(a) Residual chlorine level shall be within the range of 0.5 – 1.0 mg/l. For water
to be used for concrete, the disinfectant shall be Ultraviolet Radiation, or
ozonation.
(b) Coliform level shall fulfil one of the following:
(c) The site shall be facilitated by health and safety guidelines signs, where it is
indicated by Arabic, English, and any other languages where there are 5
workers or more on the site, that “Water not for Human Consumption”
(d) The site shall be facilitated by health and safety equipment, as well as,
personal health and safety protection equipment.
(e) Labour shall follow health and safety guidelines and instructions and use
their health and safety personal protection equibment.
END OF PART
QCS 2010
QCS 2010 Section 5 Part 5 Admixtures Page 1
5. ADMIXTURES ............................................................................................... 2
5.1 GENERAL...................................................................................................... 2
5.1.1 Scope 2
5.1.2 References 2
5.1.3 Definitions 2
5.1.4 Submittals 2
5.2 USE OF ADMIXTURES ................................................................................. 3
5.2.1 General 3
5.2.2 Trials 3
QCS 2010
QCS 2010 Section 5 Part 5 Admixtures Page 2
5. ADMIXTURES
5.1 GENERAL
5.1.1 Scope
1 This Part includes materials added to the concrete materials during mixing.
1 The following standards and other documents are referred to in this Part:
ACI 302 ..................... Guide for Concrete Floor and Slab Construction
ACI 305 ..................... Hot Weather Concreting
ACI 308 ..................... Standard Practice for Curing Concrete
ASTM C311, ............. Test Methods for Sampling and Testing Fly Ash or Natural Pozzolans
for Use in Portland-Cement Concrete
ASTM C494,.............. Standard Specification for Chemical Admixtures for Concrete
ASTM C618............... Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan
for Use in Concrete
ASTM C989............... Specification for Slag Cement for Use in Concrete and Mortars
ASTM G61,................ Test Method for Conducting Cyclic Potentiodynamic Polarization
Measurements for Localized Corrosion Susceptibility of Iron, Nickel, or
Cobalt Based Alloys
ASTM G109,.............. Test Method for Determining the Effects of Chemical Admixtures on
the Corrosion of Embedded Steel Reinforcement in Concrete Exposed
to Chloride Environments
5.1.3 Definitions
Admixtures shall mean materials added to the concrete materials during mixing for the
purpose of altering the properties of the concrete mix.
5.1.4 Submittals
QCS 2010
QCS 2010 Section 5 Part 5 Admixtures Page 3
2 The Concrete supplier shall furnish a series of at least ten trial mixes which clearly indicate
that the use of the admixture has consistently exhibited the specified absorption,
permeability and poring values. The trial mix should be verified by an approved independent
laboratory. The Concrete supplier shall also conduct (with the aforementioned) a trial
showing that a control mix without the admixture does not exhibit a greater density than that
incorporating the admixture.
5.2.1 General
1 Admixtures shall mean materials added to the concrete materials during mixing for the
purpose of altering the properties of the mix.
5 The effects of accidental overdose of the admixture and measure to be taken if an overdose
occurs shall be provided by the Contractor to the Engineer.
7 The use of the admixtures shall be controlled; i.e., strict quality control to ensure correct
dosages as prescribed by the manufacturer and justified by trial mixes to be used. A
calibrated dispenser or flowmeter shall be used to for the addition of the admixture.
5.2.2 Trials
1 In addition to the standard requirements for the approval of materials, approval of admixtures
shall be subject to extensive trials to demonstrate the suitability, adequacy of dosing
arrangements and performance, when a proven history of performance can be provided to
the satisfaction of the Engineer.
2 The concrete supplier shall furnish a series of at least ten trial mixes which clearly indicate
that the use of the admixture has consistently exhibited the specified absorption,
permeability and porosity values. These are to be verified by an approved independent
laboratory. The concrete supplier shall also conduct (with the aforementioned) a trial
showing that a control mix without the admixture does not exhibit a greater density than that
incorporating the admixture.
QCS 2010
QCS 2010 Section 5 Part 5 Admixtures Page 4
1 Ground granulated blastfurnace slag (GGBS) shall comply with the requirements of BS EN
15167 or ASTM C989.
2 The Contractor shall test each batch of GGBS delivered to site in accordance with the
required standard and provide the Engineer with certificates for the following:
(a) moisture content
(b) loss of ignition
(c) specific gravity
(d) fineness
(e) SO3 content
(f) MgO content
4 All GGBS shall be supplied from a single source. Should the Contractor wish to change the
source of supply he shall provide to the Engineer for his approval full test certification
detailing compliance with the requirement of this specification
5 The mix proportion of cement to BS EN 197-1 with that of GGBS to BS EN 15167 ASTM
C989 shall not be less than 30 % GGBS and not greater than 70 % GGBS by total weight
of cementitious material.
1 Pulverised fuel ash (PFA) shall comply with the requirements of BS EN 450, ASTM C311
and ASTM C618.
2 The Contractor shall provide for the approval of the Engineer test results and certificates in
accordance with relevant standard for each batch of PFA delivered to site for the following:
(a) loss of ignition
(b) moisture content
(c) fineness
(d) specific gravity.
3 The specific surface area shall not be less than 450 m2/kg.
4 All PFA shall be supplied from a single source. Should the Contractor wish to change the
source of supply he shall provide to the Engineer for his approval full test certification
detailing compliance with the requirement of this specification
5 The mix proportion of cement to BS EN 197-1 with that of PFA to BS EN 450 ASTM C618
shall not be less than 25 % PFA and not greater than 40 % PFA by total weight of
cementitious material.
1 Densified silica fume shall not exceed 8 % by total weight of cementitious material.
2 Silica Fume shall comply with ASTM C1240 Standard specification for silica fume in
cementitious mixture
3 The Contractor shall notify the Engineer of the intended form of microsilica. No other form of
microsilica, other than slurried shall be used without the written permission of the Engineer.
4 The Contractor shall provide for the approval of the Engineer the following test results and
certificates for each batch of microsilica delivered to site:
QCS 2010
QCS 2010 Section 5 Part 5 Admixtures Page 5
5.4.1 General
1 Hydrophobic pore blocking admixtures shall only be used with the permission of the
5.4.2 Use
1 The admixture is to be added as per Manufacture supplier data sheet at the time of mixing.
An approved lab verification shall be made prior to use,
2 The manufacturer’s representative is to be present for all additions of the hydrophobic pore
blocking compound to ensure the correct dosage rate.
5.5.1 General
1 Non-organic corrosion inhibiting admixtures shall only be used when the advantages of
using such admixtures overweight the disadvantages. This has to be decided by the
engineer depending on the project conditions.
5.6.1 General
1 Where the concrete is deemed to be in a critical area the Contractor may propose the test of
an organic corrosion inhibiting admixture. The admixture shall be based on an aqueous
emulsion of amines and esters and shall be capable of inhibiting chloride penetration
through the capillary pores in addition to forming a protective corrosion resistant film around
the steel reinforcement.
2 The admixture shall have no effect on either the slump or temperature development of the
concrete in its plastic state.
3 In its hardened state the admixture shall not affect strength development or concrete-steel
bond strengths in any way.
4 The corrosion inhibitor shall be capable of effecting protection to the steel where concrete
has cracked and allows access to the elements responsible for corrosion.
5 The corrosion inhibitor is to be added at a rate of five litres per cubic metre at the time of
mixing.
QCS 2010
QCS 2010 Section 5 Part 5 Admixtures Page 6
5.7.1 General
1 This section specifies synthetic fibre reinforcement used as an additive in concrete. Fibres
shall serve as secondary reinforcement for concrete, and to protect concrete from stresses
which cause cracking initially after placement.
5.7.2 Submittals
1 The Contractor shall submit the manufacturer’s product data, installation instructions, use
limitations and recommendations for use.
1 Fibres shall be manufactured by a firm with a minimum of five years experience in the
production of fibres. Manufacturers proposed for use shall submit evidence of their ability to
meet all the requirements specified, and include a list of projects of similar design and
complexity.
2 A preinstallation meeting shall be held two weeks prior to the commencement of field
operations to establish procedures to maintain optimum working conditions and to co-
ordinate this work with related and adjacent work. The agenda for the meeting shall include
concrete and fibre handling, placing, finishing, curing, and joint layout.
3 A representative of the distributor shall be present for project startup during initial concrete
placement. The Engineer may waive this requirement for the distributor’s representative if
the Contractor provides sufficient evidence that the producer and finisher have adequate
experience with fibres.
5.7.4 Materials
1 The fibre concrete additive shall comply with the following requirements:
(a) fibres shall be 12 mm long, manufactured from polypropylene and have a maximum
diameter of 18 microns (3 denier)
(b) the fibres shall have a surface area of at least 225 m² per kg
(c) fibres shall be straight to ensure rapid dispersion during mixing (i.e, they shall not be
crimped)
(d) fibres shall be supplied in cellulose bags which disperse during mixing.
5.7.5 Concrete Mix
1 The application rate shall be 0.6 kg. per cubic metre of concrete unless recommended
otherwise by the manufacturer. For uniform distribution mixing shall take place in the truck at
full mixing speed for a minimum of 5 min after fibre addition. Where possible the fibres shall
be added at the batch plant to ensure proper dispersion.
5.7.6 Examination
1 Conditions that are found to be detrimental to the correct execution of the work shall be
notified to the Engineer.
2 Work shall not proceed until unsatisfactory conditions are corrected to the approval of the
Engineer.
QCS 2010
QCS 2010 Section 5 Part 5 Admixtures Page 7
1 Concrete fibres shall comply with the manufacturer’s recommendations for addition and
mixing requirements.
2 Concrete finishing and curing shall comply with ACI 302, ACI 308, and ACI 305.
5.7.8 Protection
1 Completed work shall be protected from damage and construction operations throughout
finishing and curing operations.
END OF PART
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 1
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 2
6. PROPERTY REQUIREMENTS
6.1 GENERAL
6.1.1 Scope
1 This Part includes Grades 15 MPa and above of concrete to be used in the civil works, with
the requirements for workability, permeability, and drying shrinkage.
ASTM A 820, ...... Specification for Steel Fibers for Fiber-Reinforced Concrete
ASTM C 1018, .... Test Method for Flexural Toughness and First-Crack Strength of Fiber-
Reinforced Concrete
ASTM C 1116, ... Specification for Fiber-Reinforced Concrete
ASTM C 1140, .... Practice for Preparing and Testing Specimens from Shotcrete Test Panels
ASTM C 1231, .... Practice for Use of Unbonded Caps in Determination of Compressive
Strength of Hardened Concrete Cylinders
ASTM C 1240, .... Specification for Silica Fume Used in Cementitious Mixtures
ASTM C 138, ...... Test Method for Density (Unit Weight), Yield, and Air Content (Gravimetric)
of Concrete
ASTM C 1385, .... Practice for Sampling Materials for Shotcrete
ASTM C 1480, .... Specification for Packaged, Pre-Blended, Dry, Combined Materials for Use
in Wet or Dry Shotcrete Application
ASTM C 1550, .... Test Method for Flexural Toughness of Fiber Reinforced Concrete (Using
Centrally Loaded Round Panel)
ASTM C 1611, .... Test Method for Slump Flow of Self-Consolidating Concrete
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 3
ASTM C 1666, .... Specification for Alkali Resistant (AR) Glass Fiber for GFRC and Fiber-
Reinforced Concrete and Cement
ASTM C 172, ...... Practice for Sampling Freshly Mixed Concrete
ASTM C 173, ...... Test Method for Air Content of Freshly Mixed Concrete by the Volumetric
Method
ASTM C 231 ....... Test Method for Air Content of Freshly Mixed Concrete by the Pressure
Method
ASTM C 311, ..... Test Methods for Sampling and Testing Fly Ash or Natural Pozzolans for
Use in Portland-Cement Concrete
ASTM C 387, ...... Specification for Packaged, Dry, Combined Materials for Mortar and
Concrete
ASTM C 39, ........ Test Method for Compressive Strength of Cylindrical Concrete Specimens
ASTM C 42, ........ Test Method for Obtaining and Testing Drilled Cores and Sawed Beams of
Concrete
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 4
ISO 1920-8 ......... Testing of concrete -- Part 8: Determination of drying shrinkage of concrete
for samples prepared in the field or in the laboratory
ISO 1920-9 ......... Testing of concrete -- Part 9: Determination of creep of concrete cylinders
in compression
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 5
ISO 1920-10 ....... Testing of concrete -- Part 10: Determination of static modulus of elasticity
in compression
6.1.3 Definitions:
(a) Class B: Blinding concrete of minimum strength 15 MPa, and minimum strength 10
MPa for concrete Pavement (part 16). For this class, strength is only the requirement.
(c) Class C1’:All internal reinforced concrete in dry condition and protected against
humidity and weather conditions.
(d) Class C1: Low Exposure - All other reinforced concrete in occasionally exposed to
humidity. Concrete surfaces protected against weather or aggressive conditions.
(e) Class C2 Moderate Exposure - Concrete in contact with the ground or below ground,
concrete at roof level and all exposed concrete.Concrete sufaces continuously under
non-aggressive water. Concrete in contact with non-aggressive soil and subject to
moisture condensation.
(f) Class C3: Severe Exposure - Concrete in contact with the ground, alternate wetting
and drying or severe condensation. Exposed to chloride from airborne
(g) Class C 4: Aggressive Exposure – Concrete surfaces exposed to sea water spray or
in sea water tidal zone. Occasionally exposed to sea water spray. Exposed to
corrosive fumes. Exposed to abrasive action. Where chloride corrosion is the main
effect of concrete such as in tidal zone, causeways and structural concrete in contact
with water and chloride from airborne, the contractor shall assign a specialist to verify
and predict the life cycle of concrete. And to follow ASTM E-917 for basic standard
measuring and ACI 365 life-cycle costs of building and building systems
2 "Cementitious Materials": Portland cement in combination with one or more of the following:
blended hydraulic cement, fly ash and other pozzolans, ground granulated blast-furnace
slag, silica fume and Metakoalin; subject to compliance with requirements of this
specification.
3 “Water/Cementitious Ratio” shall mean the ratio between the total weight of water in the
concrete (less the water absorbed by the aggregate) and the weight of cementitious
materials, expressed as a decimal fraction.
4 “Admixtures” shall mean a material other than water, aggregate, cementitious materials or
fiber reinforcement, used as an ingredient of concrete or mortar.
5 “Hot Weather” shall mean any combination of the following conditions that tends to impair
the quality of freshly mixed or hardened concrete by accelerating the rate of moisture loss
and rate of cement hydration, or otherwise causing detrimental results such as: a. High
ambient temperature (when the shade temperature is above 40 deg C on a rising
thermometer, 43 deg C on a falling thermometer), b. High concrete temperature, c. Low
relative humidity, d. High wind speed and e. whenever the rate of evaporation exceeds 0.75
Kg/m2/h
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 6
6 “Mass concrete” is defined as any volume of concrete with dimensions large enough to
require that measures be taken to cope with generation of heat form hydration of the cement
and attendant volume change to minimize cracking. Reinforced Massive concrete structures
include pile caps, transfer plates, and structural members where the least dimension
exceeds 1.5 meters.
7 “Coarse Aggregate” shall be considered as that size passing a 28mm sieve (or larger sieve
size) and predominately retained on a 5mm sieve.
8 “Fine Aggregate” shall be considered as that size predominately passing a 5mm sieve and
predominately retained on a 0.063mm size.
12 “Gap-graded aggregate” shall mean graded aggregate without one or more of the
intermediate sizes.
14 “Target Mean Strength” shall mean the specified strength plus the margin.
15 “Margin” shall mean the difference between the specified strength and the target mean
strength.
18 “All-in” aggregate shall mean the materials composed of a mixture of coarse and fine
aggregates.
6.1.4 Submittals
1 The Contractor shall submit details of mix designs to the Engineer for approval.
2 Material Safety Data Sheet MSDS or equivalent for all products. test results and other
information as required to prove compliance with the specification shall be submitted to the
Engineer for approval according to the relevant sections of QCS on at least the following
products
3 Cement:
(a) Recent independent test results acceptable to the Engineer confirming compliance
with the specified requirements and referenced standards.
(b) Manufacturer's certificates shall also be supplied for each batch of production of
cement or on a weekly basis, whichever is more frequent, certifying compliance with
the relevant standard.
(c) The early compressive strength of each consignment of cement shall conform to the
requirements of QCS part 3 at the independent site laboratory. Deviation of more than
10% from either the previous consignment value or the rolling average shall be
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 7
4 GGBS:
(a) Recent independent test results acceptable to the Engineer confirming compliance
with the specified requirements and referenced standards.
(b) Manufacturer's certificates with all information necessary to verify compliance shall
also be supplied for each consignment of GGBS or on weekly basis, whichever is
more frequent.
(c) The early compressive strength of each consignment of GGBS shall be determined in
accordance with ASTM C989 at the independent site laboratory based on a blend of
5 PFA:
(a) Recent independent test results acceptable to the Engineer confirming compliance
with specified requirements and referenced standards.
(b) Manufacturer's certificates with all information necessary to verify compliance with
internationally recognized standards shall also be supplied with each consignment of
PFA.
(c) The materials shall comply with QCS part 3. Deviation of the strength factor by more
than 5% from either the previous consignment value or the rolling average shall be
immediately reported to the Engineer and the Technical Manager of the premix
company.
6 Silica fume:
(a) Recent independent test results acceptable to the Engineer confirming compliance
with specified requirements and referenced standards.
(b) Manufacturer's certificates with all information necessary to verify compliance with
internationally recognized standards shall also be supplied with each consignment of
silica fume.
(c) 7 day pozzolanic activity test in accordance with ASTM C 1240 on each consignment
of silica fume at the Independent site laboratory. Deviation of the activity index by
more than 5% from either the previous consignment value or the rolling average shall
be immediately reported to the Engineer and the Technical Manager of the premix
company.
7 Aggregates:
(a) Recent independent test results acceptable to the Engineer confirming compliance
with the specified requirements and referenced standards.
8 Water: Recent independent test results acceptable to the Engineer confirming compliance
with the specified requirements and referenced standards.
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 8
10 Mix Designs: Submit concrete mix designs for each type and strength of concrete required at
least sixty (60) days before placing concrete.
12 Submit complete mix design data for each separate mix to be used on the Project in a single
submittal with at least the following information:
(c) Cementitious content* (GGBS, PFA, natural pozzolan, rice husk ash and/or silica
fume).
(o) Bleeding
(r) Initial and final concrete setting time for each mix design
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 9
13 Data shall be from the same production facility that will be used for the Project.
14 Mix Design data shall include but not be limited to the following:
(a) Locations on the Project where each mix design is to be used corresponding to
Structural General Notes on the Drawings.
(b) Design Compressive Strength: As indicated on the Drawings.
(c) Proportions: Concrete constituent materials shall be proportioned to yield 1 m3
(d) Gradation and quality of each type of ingredient including fresh (wet) unit weight,
aggregates sieve analysis.
(e) Water/cementitious material (w/cm) ratio.
(a) Submit mix design for mass concrete elements in conformance with requirements of
ACI 301 Section 8. The use of high early strength cement ASTM C 150 Type III
cement and cement grade with index “R” is prohibited. The concrete mix design shall
not be designed with a high early strength unless otherwise demonstrated by the
Contractor for capability of maintaining proper temperature and approved by the
Engineer.
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 10
(c) Submit analysis of anticipated thermal development within mass concrete elements
with the proposed mix design for these elements. Results of the analysis, using
methods in ACI 207.1R and ACI 207.2R such as the Schmidt model and site specific
data, shall address the maximum differential temperature and the maximum
temperature during curing
(d) Submit proposed number and locations of temperature monitoring devices to record
temperature development between the interior and the exterior of mass concrete
elements.
6.2.1 General
1 Grades of concrete to be used in the Works shall in general be designed as in para 6.2.2.
Where different grades of concrete are required the design of the mix shall follow the
requirements of this specification.
2 The concrete grades shall be designed mixes according to classes set in para 6.1.3 and
shall comply with the requirements set in the table 6.1:
4 Cement contents in excess of 400 kg/m3 shall not be used unless special consideration has
been given to the effect for heat of hydration and reduce thermal stress in the concrete, and
approval has been obtained from the Engineer. The maximum cementitious content shall not
exceed 500kg/m³
5 The proportioning, mixing and placing of the mixture shall be in accordance with Parts 7 and
8 of this Section
(a) Maximum fresh concrete temperature shall not exceed 32°C unless construction
testing to verify a proposed concrete mixture will function satisfactorily at a concrete
temperature greater than 32ºC. No concrete shall be placed if the concrete
temperature is above 35oC
(b) Methods to reduce fresh concrete temperature shall minimize energy consumption in
accordance with the sustainability goals of the project.
(c) The concrete producer shall demonstrate that temperature of concrete due to
hydration particularly in mass concrete structures shall comply with this specification
para 6.2.3.3 with the proposed maximum fresh concrete temperature. The supplier
may use in his demonstration testing heat sensors and simulation technologies which
measure the concrete heat of hydration and its rate versus concrete curing age.
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 11
7 The Contractor is responsible for ensuring that the concrete is able to be fully compacted
within the concrete element regardless of reinforcing density or other limitations. This may
involve reducing the maximum aggregate size, increase the level of concrete workability or
use self compacting concrete. Generally the slump of concrete as delivered to site shall be in
the range of 120mm to 200mm depending on the type/area of application unless otherwise
specified by the Engineer.
Table 6:1a Minimum concrete cube strength grade based on concrete exposure conditions:
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 12
Maximum Chloride
Minimum Maximum
Minimum Cube limit for new
Cylinder Minimum Maximum expansion
Compressive construction, % by
Concrete Grade
(months)
2 2 3 Acid Water
(N/mm ) (N/mm ) (Kg/m ) (W/C) soluble
4
soluble
5
6 12 18
1. The strength requirement is based on the design criteria; conversation of cylinder/cube shall be as
specified in above table or as indicated in QCS Part 05-06 clause 6.4.2.9.b.4.
2. For Prestressed concrete the chloride limits are 0.08 and 0.06 respectively
3. Applicable where concrete is exposed to soils and water and not protected by waterproofing
membrane.
4. Test method according to ASTM C1152 or BS 1881: Part 124.
5. Test method according to ASTM C1218 .
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 13
1
Durability level
No. Durability Requirements
minimum Moderate Moderately
High Level High Level
Level Level
Class 4
Class 3
Class 2 Class 3
1 concrete exposure condition Class 1 Class 2
Class 1 Class 2
Class 1
Class 1
Minimum cube compressive
2 C35 C40 C50 C75
Water Penetration, BS EN
3 25 15 10 5
12390-8 (mm)
Resistance to Chloride ion
4 Penetration (RCP), ASTM C 4000 2000 1000 500
1202 (coulombs)
3
Chloride Migration , NT Build -12 -12 -12
5 2 N.A 5.0 x 10 3.0 x 10 1.0 x 10
492 (m /s)
Water Absorption, BS 1881: 1.2
6 2.5 2.0 1.6
Part 122 (%)
1. The durability level and requirement test or tests shall be applied when requested by the Engineer and
shall be tested at 28 days.
2. Exception will be made for mass concrete structure, or concrete mix containing fly ash, silica fume, or
GGBS , concrete strength grade C50 or more and for Exposure Conditions class 3 or class 4 the
durability requirement shall be requested at 56 days ,or 91 days if approved by the Engineer.
3. Optional requirement.
1 At the start of the construction period, the Contractor shall design a mix for each grade of
concrete as stated hereafter.
4 Where a concrete production facility does not have strength test records meeting
requirements of 6.2.2(3) above, but does have test records not more than 12 months old
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 14
5 To determine the correction factor between cube strength and cylinder strength, the
contractor shall establish at least 30 consecutive strength tests from each proposed mix
design. This correction will remain valid thru the project providing that no change in the
properties of the materials and no change in source occurred.
6 Required average compressive strength (Target Mean Strength) f’cr used as the
basis for selection of concrete proportions shall be determined from Table 6.3
using the sample standard deviation, Ss
Table 6.3: Required Average Compressive Strength (Target Mean Strength) When Data Are Available
To Establish A Sample Standard Deviation
F’c < 35 MPa --- see footnote F’cr = f’c + 1.34Ss ------------------ Eq. 1
F’c > 35 MPa --- see footnote F’cr = f’c + 1.34Ss ------------------ Eq. 1
7 When a concrete production facility does not have field strength test records for
calculation of Ss, Required average strength (Target Mean Strength) f’cr shall be
determined as follow:
(a) F’cr = f’c + 8.5 MPa when 20 < f’c < 35 MPa
(b) F’cr = 1.10f’c + 5 MPa when f’c > 35 MPa
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 15
1 Portland cement concrete shall consist of a mixture of Portland cement, cementitious, fine
aggregate, coarse aggregate, water, and additives (when required). It shall be classified as in
table 6.2.1 unless otherwise stated hereafter and requested by the Engineer.
2 Blinding concrete
(b) The thickness of the blinding concrete shall be as shown on the Drawings, but shall in
no instance be less than 75 mm.
(c) The surface finish to blinding concrete shall be Class U2 as specified in Clause 9.3.1
3 Mass Concrete
(a) The fresh concrete temperature at placing shall not exceed 21oC unless otherwise a
higher temperature can be demonstrate the satisfactory of concrete with crack free
from thermal effect, Delayed Ettringite formation and/or internal sulphate attack. The
maximum allowable differential temperature between the interior and the exterior of
the mass concrete element shall not exceed 25 deg C. The maximum temperature in
any location within the mass concrete structure during curing shall not exceed 70 deg
C. The drop in concrete surface temperature during, and at the conclusion of the
specified curing period, shall not exceed 11 deg C in any 24 hour period. The internal
differential temperature of concrete shall not exceed 20oC for gabbro aggregates and
30oC for limestone aggregates.
(a) General: Self Consolidating Concrete (SCC) is an innovative concrete that does not
require vibration for placing and compaction. It is able to flow under its own weight,
completely filling formwork and achieving full compaction, even in the presence of
congested reinforcement. The hardened concrete is dense, homogeneous and has
the same engineering properties and durability as traditional vibrated, fully compacted
concrete.
(b) Self Consolidating Concrete Supplier: SCC shall be supplied by a competent concrete
producer with a record of successfully producing this type of concrete at considerable
volume and with high consistency.
(c) Constituent Materials, General: The constituent materials for SCC are the same as
those used in traditional vibrated concrete conforming to EN 206-1, as specified in
part 2 of this section.
(d) To achieve these requirements the control of the constituent materials needs to be
increased and the tolerable variations restricted, so that daily production of SCC is
within the conformity criteria without the need to test and/or adjust every batch.
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 16
(f) Concrete specimens shall be moulded in single layer without rodding and tapping
(g) Slump flow and VSI testing shall be performed as outlined in ASTM C 1611/C 1611M
5 Pile Concrete
(a) The cementitious content shall not be less than 370 kg/m3
(c) The concrete mixture shall be designed of high slump not less than 150 mm allowing
proper free fall with excellent homogeneity. When concrete mixture requires slump of
greater than 230 mm, it shall be designed as Self Consolidated Concrete. The
increase in slump shall be made using proper admixtures. The use of chemical
admixture including air-entraining or any other shall be evaluated as it increases the
workability, if needed and approved by the engineer.
(d) The concrete slump shall have adequate retention using approved type of retarder
and shall be submitted in the design mix.
(e) The increase in workability shall not permit any decrease in the specified design
strength
(f) The concrete in a pile shall, if at all possible, be placed in one continuous operation.
6 Underwater concrete shall generally comply with ACI 304 Chp 8 and following
characteristics:
(a) The Cementitious content shall not be less than 390 kg/m3
(c) Fine aggregate contents of 45 to 55% by volume of total aggregate and air contents of
up to approximately 5% are generally specified.
(d) Concrete shall be more cohesive and less prone to washout of cement or fines from
the concrete during placement. Antiwashout admixtures or alternative concrete mix
shall be used for underwater concrete.
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 17
(e) Trial placements shall be conducted to verify that the concrete proportioned with the
antiwashout admixture can maintain adequate slump life and can flow for the required
distance.
(g) The concrete mixture shall be designed of high slump not less than 150 mm allowing
proper free fall with excellent homogeneity. The use of air-entraining admixture shall
be evaluated as it increases the workability. When concrete mixture requires slump of
greater than 230 mm, it shall be designed as Self Consolidated Concrete. The
increase in slump shall be made using proper admixtures.
(h) The concrete slump shall have adequate retention using approved type of retarder
and shall be submitted in the design mix.
(i) The increase in workability shall not permit any decrease in the specified design
(g) The final selection of a concrete mixture shall be based on test placements made
under water in a placement box or in a pit that can be dewatered after the placement.
Test placements shall be examined for concrete surface flatness, amount of laitance
present, quality of concrete at the extreme flow distance of the test, and flow around
embedded items, if appropriate.
7 Shotcrete
(a) The classification of shotcreting shall be in accordance to the process used (wet-mix
or dry-mix) and the size of aggregates used.
(b) All materials shall be as per QCS except for aggregate where gradation shall be as
per ACI 506R and 506.2R
(c) Steel and synthetic fibers will be used to reduce propagation of cracks. Fibers shall be
as per Manufacturer supplier data sheet and shall conform to ASTM A 820 for steel
fibers and ASTM C1116 for synthetic fibers.
(d) The nozzle operator should be certified (refer to ACI CP-60) and have completed at
least one similar application as a nozzle operator on a similar project. The nozzle
operator should also be able to demonstrate, by test, an ability to satisfactorily perform
the required duties and to apply shotcrete as required by specifications
(e) Before shotcreting the surface shall be prepared and maintained before and during
shotcrete application. Surface preparation shall conform to ACI 506 R chap. 5
(f) The cementitious content shall not be less than 360 Kg/m3 where wet-mix is applied
the slump shall be in the range of 40 to 80 mm
(g) Normal testing ages for compressive strength are 7 and 28 days; however, shorter
periods may be required for particular applications or conditions as directed by the
Engineer. Testing shall be on daily production or every 40 m3 whichever is greater.
(h) Sampling and testing, however, should be varied according to the size and complexity
of the project. Sampling should be done in accordance with ASTM C 1385. Making
extra cylinders or panels shall be at the request of Engineer if testing results vary.
(i) Testing for water absorption, drying shrinkage, and resistance to freezing-and-thawing
cycles shall be at the request of the Engineer.
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 18
(j) Fiber-reinforced shotcrete requires fiber washout tests or flexural toughness testing
according to ASTM C 1018.
(k) Acceptance of shotcrete should be based on results obtained from drilled cores or
sawed cubes (ASTM C 42). The use of data from nondestructive testing devices, such
as impact hammers or probes (ASTM C 805, ASTM C 803), ultrasonic equipment
(ASTM C 597), and pull-out devices (ASTM C 900) may be useful in determining the
uniformity and quality of the in-place shotcrete. These tests, however, may not provide
reliable values for compressive strength.
(a) No-fines concrete shall be made using a coarse aggregate conforming QCS section 5
part 3
(b) Proportion of aggregate, cement and water shall be determined by trial mixes by the
Contractor and to be accepted by the Engineer.
(c) All the aggregate particles are to be coated with a film of cement grout.
(g) Three test cubes of no-fines concrete shall be made of each preliminary mix.
(h) Minimum crushing strength of the chosen mix shall be 5 MPa at 28 days.
(i) The porosity of no-fines concrete shall be such that water will pass through a slab
300 mm thick at the rate of not less than 7 l/m2 • s of slab with a constant 100 mm
depth of water on the slab.
(j) Where a slab incorporating vertical weep holes or drain holes is casted above a layer
of no-fines concrete; any polyethylene sheeting shall be pierced below the pipes
forming such drain holes and the edges of the sheeting sealed to the lower end of the
pipe to prevent the ingress of grout and fine particles from the slab concrete into the
no-fines concrete.
(k) The limit for the maximum height of drop while placing is not applicable for no fines
concrete.
(l) Formwork shall remain in place until the no fines concrete has gained adequate
strength to support itself as per the requirements of Part 10 of this Section.
(m) Curing shall be carried out in accordance with the provisions of Part 11 of this Section
(n) The fresh density of Pervious concrete shall be tested as per ASTM C1688 and the
infiltration rate shall be tested as per ASTM C1701 and to follow ACI 522.1R for
testing and quality control scheme.
9 Concrete with recycled aggregates shall be generally approved once the source of recycled
aggregates is identified based on type and approved by the Engineer.
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 19
(a) The recycled aggregates shall be subject for examination as per ASTM C856.
(b) The recycled aggregates shall meet with BS EN 12620 and QCS requirements.
(c) Recycled aggregates shall always be moist above saturation stage at batching plant
(d) The concrete made with recycled aggregates shall be limited to design strength of 20
MPa cube strength; unless otherwise accepted by the Engineer. EN 206, ACI 555 and
BRE digest 433 shall be the code of practice and guide for the usage of recycled
concrete aggregates in concrete.
(e) Concrete made with recycled aggregates shall be tested for shrinkage, modulus of
rupture, carbonation, chloride penetration which they shall meet with design criteria of
the project.
(g) To determine a target mean strength on the basis of a required strength, a higher
standard deviation (increased by 40%) shall be used when designing a concrete with
recycled aggregates of variable quality than when recycled aggregate of uniform
quality or virgin aggregates are used
(h) Specific gravity, unit weight, and absorption of aggregates should be determined
before mixture proportion studies
(i) The mixture proportion should be based on the measured density of the recycled
aggregates intended in the job concrete
(j) Trial mixes shall be made to verify the requirements with project specification and
QCS.
(a) The quality of the aggregates should comply with the requirements of QCS for normal
weight aggregates, ASTM C 637 for heavyweight aggregates and ASTM C638 for
aggregates to be used in radiation-shielding concrete.
(b) When ferrophosphorous aggregates are used, tests shall be made to determine if
gases (nontoxic) might be released during construction.
(c) Aggregates shall be checked for every delivery to ensure that they conform
completely with purchase specifications
(d) Aggregates shall be frequently evaluated for the effects of deleterious substances or
aggregate coatings on concrete strength or the promotion of corrosion in metallic
aggregates or embedment’s
(e) The chemical properties of all high-density aggregates must be provided to the
Engineer for evaluation before use with due consideration given to chemical reactivity,
particularly in highly alkaline environment as found in cement paste.
(f) Tests for alkali-aggregate reactivity shall be determined from each source and
supplier and shall be made every 3 months.
(g) The fresh density of high-density concrete shall be made from each truck
(h) Lead shot concrete shall not be use for structural concrete.
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 20
(i) Thermal conductivity, elastic behaviour and shrinkage, hardened density, strength as
well as other hardened concrete properties shall be tested and verified before the use
of concrete.
11 Fiber-Reinforced Concrete
(a) Classification of fiber-reinforced concrete shall be made based on the material type of
the fiber incorporated:
(iv) Type IV Natural Fiber-Reinforced Concrete— Contains natural fibers for which
documentary evidence can be produced confirming their long-term resistance
to deterioration when in contact with the moisture and alkalis present in cement
paste and the substances present in admixtures. Test Method ASTM D 6942
may be used to determine the susceptibility of these fibers to deterioration as a
result of exposure to alkalis in concrete
(v) When the purchaser chooses to permit the use of fibers other than those
complying with the above classifications, the manufacturer or supplier shall
show evidence satisfactory to the purchaser that the type of fiber proposed for
use shows long-term resistance to deterioration when in contact with the
moisture and alkalis present in cement paste and the substances present in
admixtures
(iii) Slump or time of flow required at the point of delivery, or when appropriate the
point of placement, subject to the tolerances hereinafter specified Slump shall
be specified when it is anticipated to be 50 mm or more, and time of flow shall
be specified when slump is anticipated to be less than 50 mm. Slump or time of
flow shall not be specified for shotcrete placed by the dry process. Time of flow
shall be in general of 8 to 15 seconds.
(c) Air content when air-entrainment is required, based on the air content of samples
taken at the point of discharge, or when appropriate the point of placement, subject to
the tolerances specified in ASTM C1116
(e) Fibers shall be measured by mass. When the fibers are to be measured by mass,
bags, boxes, or like containers are acceptable provided that such like containers are
sealed by the fiber manufacturer and have the mass contained therein clearly marked.
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 21
No fraction of a container delivered unsealed, or left over from previous work, shall be
used unless weighed.
(f) Prepackaged, dry, combined materials, including fibers, shall comply with the
packaging and marking requirements of Specification ASTM C 387 or C 1480 and
shall be accepted for use provided that after addition of water, the resulting fiber
reinforced concrete meets the performance requirements of this specification
(g) Batching plant used for the preparation of continuously mixed fiber-reinforced
concrete shall comply with the applicable requirements of NRMCA. Fiber-reinforced
concrete shall be added directly to the concrete at the time of batching in amounts in
accord with approved submittals for each type of concrete required. Mix concrete in
strict accord with fiber-reinforced concrete manufacturer, instructions and
recommendations
(i) The manufacturer of the fiber-reinforced concrete shall furnish to the purchaser a
delivery ticket or statement of particulars on which is printed, stamped, or written,
information with details of the type, brand, and amount of fibers used.
(j) The contractor shall afford the inspector all reasonable access, without charge, for the
procurement of samples of freshly mixed fiber-reinforced concrete at the time of
placement to determine compliance with the requirements of this specification.
(l) If the measured slumps, time of flow, or air content fall outside the limits permitted by
this specification, make a check test immediately on another portion of the same
sample. If the results again fall outside the permitted limits, the material represented
by the sample fails to meet the requirements of this specification
(m) The following shall apply to all forms of fiber-reinforced concrete except dry-mix
shotcrete. When applicable, the slump shall be in tolerance with this section para
6.4.2.5 (a) and (b).
(ii) When the project specifications for time of flow are not written as a “minimum”
or “not less than” requirement:
Tolerances for time of flow
For specified time of flow Tolerance
8 to 15 s + 3s
More than 15 s + 5s
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 22
(p) Provide fibers for concrete reinforcing capable of achieving a two hour fire resistance
rating when tested under ASTM E 119. Fire tests must be certified.
12 Lightweight concrete
(a) This clause of the specification refers to lightweight concrete with improved insulation
properties where the practical range of densities is between about 300 and 1850
(b) The required density and strength of the lightweight concrete will be specified on the
drawings or directed by the Engineer.
(c) The method of production of lightweight concrete will be shown on the drawings or
directed by the Engineer. The Contractor shall submit full technical details of the
materials and method of production for the lightweight concrete along with a list of
previous projects where the particular system has been used.
(d) After source approval of the material and system the Contractor shall submit a mix
design for the lightweight concrete for the approval of the Engineer. After the review
and approval of the mix theoretical mix design the Contractor shall carry out a trial mix
to check the workability of the fresh concrete and to allow samples to be made for
compressive strength and density.
(e) The Engineer may also instruct that tests are carried out for abrasion resistance and
thermal insulation properties.
(f) Iightweight concrete shall be made with lightweight aggregates as approved in part 2
of section 05 in QCS for its use in concrete
(a) Not less than 50 strength test results as in para 6.2.2 of this specification
(b) The results shall valid by no more than 6 months from the date of approval
2 Batch the field concrete trial mixture within -2°C of the proposed maximum allowable fresh
concrete temperature in a truck-mixer with a minimum batch size of 3 m3.
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 23
3 The concrete mixture shall be held in the mixer for 90 minutes, unless otherwise specified by
the Engineer. During the entire 90-minute period, agitate the mixer at 1 to 6 rpm. At the end
of 90 minutes, mix the concrete mixture at full mixing speed designated by the manufacturer
(6 to 18 rpm) for 2 minutes.
4 For each trial mix, a plant production trial shall be carried out and the slump of the concrete
checked immediately after discharge from the mixer and thereafter at 30 min intervals up to
the maximum time period envisaged for delivery and standing on site. Based on this trial the
mix design shall identify any adjustments to the range of plasticiser for acceptable
workability for different times after batching. Where ready mix concrete is being used, the
above requirement may be waived at the discretion of the Engineer if the Contractor has
documented previous experience of a particular mix design with test results available.
5 The proportions of cement, aggregate and water shall be carefully determined by weight in
6 Each sample shall consist of at least 9 specimens for strength analysis where 3 specimens
for each age will be tested to determine the concrete strength at the required age.
7 If either or both the average value of the strength of the three cubes tested at 28 d is less
than the required strength (target strength) or the difference between the greatest and the
least strengths is more than 20 % of the average strengths, the Contractor shall take
measures as deemed necessary such as:
(a) Propose new mix design
(b) Provide new materials and prepare and test further trial mixes until specified
requirements are achieved.
8 Additionally, the Contractor shall measure the temperature, workability of concrete in each
batch.
9 When requested by engineer, a mock-up of 2x2x2 m3 shall be made at jobsite and full scale
tests of the workability of each trial mix of each grade of concrete shall be made by the
Contractor in the presence of the Engineer. The trial mix of each grade of concrete shall be
batched, mixed and then transported a representative distance in the manner that the
Contractor proposes to batch, mix and transport the concrete to be placed in the Works.
After discarding the first batch so made, the concrete shall be placed and compacted in trial
moulds both for reinforced and mass concrete with dimensions typical of the Works. The
sides of the moulds shall be capable of being stripped without undue disturbance of the
concrete placed therein. The sides of the moulds shall be stripped after the concrete has set
and the workability judged on the compaction obtained. If the workability test shows that the
workability required is not attained for any trial mix for any class of concrete, the trial mix
shall be redesigned by the Contractor and a further full scale workability test shall be
undertaken for that trial mix of concrete.
10 Redesign of the concrete mixes and trial mixes of concrete shall be repeated for each grade
of concrete until the concrete meets the requirements in this specification and it is verified by
full scale mockup test as described above.
11 The Contractor shall use only the approved mix of each grade of concrete in the Works. If at
any time during the construction of the Works the source of cement or aggregate is changed
or the grading of the aggregate alters to such an extent that the fraction of aggregate
retained on any sieve cannot be maintained within two percent of the total quantity of fine
and coarse aggregate when adjusted in accordance with this Clause, then further trial mixes
of concrete shall be made, tested and approved for use.
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 24
12 Approval of the job-mix proportions by the Engineer or his assistance to the Contractor in
establishing those proportions, in no way relieves the Contractor of the responsibility of
producing concrete which meets the requirements of this Specification.
13 The Engineer may also require practical tests to be made on the Site by filling trial moulds to
confirm the suitability of:
(a) mix for the works
(b) type of plant used for mixing
(c) face intended for use in the works
(d) type of form oil
(e) type of protective coatings.
14 All costs connected with the preparations of trial mixes and the design of the job mixes shall
be borne by the Contractor.
16 The Contractor shall declare any change in the source of the material and any changes in
the cement content consumption greater than 20.0kg/m³ from that used in the trial mixes.
6.4.1 General
1 In order to ensure that the quality of materials and mix proportions are maintained
throughout concreting operations, sampling and testing shall be carried out using the
relevant standard procedures and all other relevant codes quoted in this specification in
accordance with a routine testing program that shall be agreed with the Engineer before the
start of concrete work.
2 The Contractor, thru third party approved testing agency, shall supply all necessary tools for
tests, shall cast all concrete specimens, strip and store them in water as stated in standard
procedure. The Contractor shall also arrange for the transport of samples to the place of
testing and shall supply the Engineer with duplicate copies of all test certificates.
1 Unless the Engineer directs otherwise, the program shall include at least the tests specified
below.
4 Slump tests (and VSI testing when applicable) shall be carried out at the rate of one test per
load of concrete delivered to the Site, or one test per 10 m3 whichever is the lesser for the
first 50 m3 of concrete then at a rate of 1 slump test for every 50 m3 if concrete was
consistent during production. In the event of inconsistent slump values, the Engineer may
instruct the Contractor to check the slump test on each truck of concrete at the plant. The
Contractor shall carry out an investigation to establish the cause of the high variation in
slump and shall take any necessary corrective measures. The slump requirements to the
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 25
fresh concrete are to be approved by the Engineer depending on location and exposure and
it shall be recorded on the batch ticket for each delivery.
5 Any variations from approved slumps necessitated by the use of superplactisers or other
admixtures or additives shall be approved by the Engineer. Unless other tolerances are
included in the project specification, the following shall apply:
(a) When the project specifications for slump are written as a “maximum” or “not to
exceed” requirement:
Specified Slump
Minus tolerance* 40 mm 60 mm
(b) When the project specifications for slump are not written as “maximum” or “not to
exceed” requirement:
50 mm and less 20 mm
50 mm to 100 mm 30 mm
6 The adjustment for the slump of concrete to fit the job requirement can be conducted only
one time using a proper additive at jobsite provided that such addition does not increase the
water-cement ratio and setting time above the maximum permitted by the specifications.
This addition will only be made at the approval of Engineer.
7 Concrete shall be available within the permissible range of slump for a period of 30 min
starting either on arrival at the job site or after the initial slump adjustment as permitted
above, whichever is later. The first and last quarter m3 discharged are exempt from this
requirement. If the user is unprepared for discharge of the concrete from the vehicle, the
producer shall not be responsible for the limitation of minimum slump after 30 min have
elapsed starting either on arrival of the vehicle at the prescribed destination or at the
requested delivery time, whichever is later.
8 When air-entrained concrete is desired the purchaser shall specify the total air content of the
concrete. The air content of air-entrained concrete when sampled from the transportation
unit at the point of discharge shall be within a tolerance of +1.0% of the specified value.
(a) Each concrete strength sample shall consist of at least seven specimens, two to be
tested at 7 days, three at 28 days and two to be tested at the discretion of the
Engineer. Additional samples may be prepared as directed by the Engineer to be
tested at the discretion of the Engineer for strength and/or durability.
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 26
(b) When concrete cylinders have been specified, the concrete specimens shall not be
capped using sulphur for environmental effect. The Contractor shall follow one of the
following procedures and as approved by the Engineer:
(i) Cap the specimens in accordance with ASTM C617 using neat cement paste
and/or High-strength gypsum cement paste
(ii) Saw cut and Grind the surface of the concrete to the desired planeness and
perpendicular
(iii) Test the concrete cylinders using Unbonded Caps in accordance with ASTM
C1231
(iv) For field specimens, the contractor has the right to either use the conversation
(c) A minimum of one sample shall be taken of each mix every day the mix is used
(d) Samples shall be taken at the average rate of one sample every 30 m3 of concrete or
fractions thereof for the first 90 m3, then one sample every 100 m3 of concrete or
fraction thereof when continuous concrete production reaches up to 2000 m3 and later
of one sample every 200 m3 of concrete or fraction thereof when concrete production
exceeds 2000 m3.
(e) If the average strength of the three specimens at 7 d indicate that the required
strength at 28 d will not be achieved the Contractor shall immediately:
(i) stop all concreting until checks are made on material and equipment
(ii) rectify any defect which has become apparent as the result of checking.
(f) At Contractor’s option, defective concrete may be removed and replaced without
waiting the 28 d test results.
(g) A test shall be the average of the strength of the specimens tested at the age
specified. If a specimen shows definite evidence other than low strength, of improper
sampling, molding, handling, curing, or testing, it shall be discarded and the strength
of the remaining cylinder shall then be considered the test result. To conform to the
requirements of this specification, strength tests representing each class of concrete
must meet the following requirements:
(i) The average of any three consecutive strength tests shall be equal to, or
greater than, the specified strength, f ‘c, and
(ii) When the specified strength is 35 MPa or less, no individual strength test
(average of at least two specimen tests) shall be more than 3.5 MPa below the
specified strength, f ‘c
(iii) When the specified strength is greater than 35 MPa, no individual strength test
(average of two specimen tests) shall be less than 0.90f ‘c.
(h) If works test specimens fail at 28 days the Contractor shall suspend concreting
operations and shall not proceed further without approval. The Contractor shall carry
out in-situ testing of the suspect concrete in accordance with Part 13 of this Section, in
the presence of the Engineer. All defective work shall be replaced and retested to the
satisfaction of the Engineer.
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 27
(a) When post-crack flexural performance is used as the basis for acceptance of fiber-
reinforced concrete, make, condition, and test sets of test specimens in accordance
with Test Method ASTM C1399, C1550 or C1609/C1609M as specified.
(b) When flexural strength is used as the basis for acceptance, make and test sets of at
least three test specimens in accordance with the requirements for sampling and
conditioning given in Test Method ASTM C1609/C1609M. Test specimens
representing thin sections, as defined in C1609/C1609M, or specimens representing
fiber-reinforced shotcrete of any thickness, shall be tested as cast or placed without
being turned on their sides before placement on the support system. Acceptance shall
not be based on flexural strength alone when post-crack performance is important.
Test Method C1609/C1609M provides for the determination of first peak flexural
(c) When compressive strength is used as part of the basis for acceptance of fiber-
reinforced concrete, make sets of at least two test specimens in accordance with the
applicable requirements of Practices ASTM C31/C31M and C192/C192M and as
specified in this section, or Test Methods C42/C42M or C1604/C1604M and condition
and test in accordance with Test Methods BS EN 12390, C39/C39M, C42/ C42M, or
C1604/C1604M. Acceptance shall not be based on compressive strength alone.
(ii) When fibers are added, subject for approval of the Engineer, at the truck mixer
the tests shall be made for each 20 m3 or fraction thereof, or whenever
significant changes have been made in the proportioning controls. On each day
fiber-reinforced concrete is mixed, at least one test shall be made for each class
of material.
(iii) For Shotcrete: Tests shall be made for each 38 m3 placed using specimens
sawed or cored from the structure or from corresponding test panels prepared
in accordance with Practice ASTM C1604 and C 1140. On each day fiber-
reinforced shotcrete is prepared; at least one test shall be made for each class
of material.
1 The Contractor shall submit a continuous statistical analysis, on a monthly bases, for
strength showing the potential strength of the concrete, variations in measured strength by
determining the standard deviation (margin), batch-to-batch variations of the proportions and
characteristics of the constituent materials in the concrete, the production, delivery, and
handling process, and climatic conditions; and variations in the sampling, specimen
preparation, curing, and testing procedures (within-test).
2 The Contractor shall provide in his analysis the mean strength, calculated standard
deviation, the normal distribution of concrete strength and the frequency histogram. The
Contractor shall draw the upper and lower lines for warning line (Target mean strength + 2 x
standard deviation) and control line (Target mean strength + 3 x standard deviation)
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 28
3 The contractor shall use the methods, of computing standard deviation along with coefficient
of variation and factors for computing within-test standard deviation from range, addressed
in ACI 214
4 This recalculated margin, if adopted by the Engineer, becomes the current margin for the
judgement of compliance with the specified characteristic strength of concrete
5 When standard deviation or coefficient of variation are relatively high that represent low
quality, the Engineer has the right to stop concreting until the Contractor provide corrective
and preventive measures.
For classes C0, C1’, C1 and when strength is equal or less than 35 MPa
Overall variation
General construction testing Below 3.4 MPa 3.4 to 4.8 MPa Above 4.8 MPa
Within-test variation
For classes C2, C3, C4 and when strength is higher than 35 MPa
Overall variation
Within-test variation
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 29
5 When Self Consolidate Concrete is used, the concrete specimens shall not be consolidated
in moulds and it shall be placed in single lift then levelled with minimum manipulation.
6 All samples shall be moulded at jobsite on a levelled surface area to within 20 mm per meter
7 Immediately after moulding and finishing, the specimens shall be stored for a period up to 48
h in a temperature range from 20 to 26oC and in an environment preventing moisture loss
from the specimens
8 Specimens shall not be transported or handled until at least 8 h after final set
9 Transportation time from site to laboratory for final curing and strength testing shall not
exceed 4 hours. Specimens shall be protected direct sun or rapid evaporation and placed on
cushion layer to reduce vibration
1 Concrete mixes shall be rejected if they fail to meet one or more requirements, which
cannot be brought into compliance of visually unsatisfactory as related to any of the
following:
1 A test shall be the average of the strengths of the specimens tested at the age specified. If a
specimen shows definite evidence other than low strength, of improper sampling, molding,
handling, curing, or testing, it shall be discarded and the strength of the remaining
specimens shall then be considered the test result and where the range of the test values is
more than 15 % of the mean, the results shall be disregarded unless an investigation
QCS 2010
QCS 2010 Section 5 Part 6 Property Requirements Page 30
(a) The average of any three consecutive strength tests shall be equal to, or greater than,
the specified strength, f ‘c, and
(b) When the specified strength is 35 MPa or less, no individual strength test (average of at
least two specimen tests) shall be more than 3.5 MPa below the specified strength, f ‘c
(c) When the specified strength is greater than 35 MPa, no individual strength test (average
of two specimen tests) shall be less than 0.90 f ‘c.
2 Should any of the test results be unsatisfactory, the Engineer may order the work to be
3 In the case of the 7-day works cube tests proving unsatisfactory, the work may be stopped
but shall not be liable to rejection pending the result of the 28-day test. If the test results fail
to comply with the requirements, the work represented shall be immediately liable to
rejection. The Contractor may however be given the option of cutting three acceptable
specimens from the completed work and preparing from them test cores according to part 13
of this section. Should the average strength of these specimens attain the minimum 28day
strength the work will be accepted but otherwise the work will remain liable to rejection as
above.
4 The cost of all such cuttings, preparation of specimens, transportation and testing, and of
making good the portions of the structure affected shall be borne by the Contractor.
5 Regardless of satisfactory test cube results, any concrete work which, in the Engineer's
opinion, is excessively honeycombed or in any other way is defective, shall be liable to
rejection. Minor defects apparent on stripping the formwork must be made good at the
Contractor's expense. No such repair work shall be carried out until after inspection by the
Engineer and his acceptance of the proposed treatment has been given. Work which has
not been previously inspected but which shows signs of such treatment shall be liable to
rejection as defective work.
6 The cost of all delays on site due to faulty concrete work shall be met by the Contractor.
END OF PART
QCS 2010
QCS 2010 Section 5 Part 7 Batching and Mixing Page 1
QCS 2010
QCS 2010 Section 5 Part 7 Batching and Mixing Page 2
7.1.1 Scope
1 This Part covers batching and mixing of concrete and ready-mixed concrete.
QCS 2010
QCS 2010 Section 5 Part 7 Batching and Mixing Page 3
GSO ISO 1920-4 ------ Testing of concrete – part 4: strength of hardened concrete.
GSO ISO 1920-5 ------ Testing of concrete – part 5: properties hardened concrete other than
strength.
GSO ISO 1920-6 ------ Testing of concrete – part 6: sampling, preparing and testing of
concrete core.
GSO ISO 1920-7 ------ Testing of concrete – part 7: Non–destructive test on hardened
concrete.
ISO 1920-8-------------- Testing of concrete -- Part 8: Determination of drying shrinkage of
concrete for samples prepared in the field or in the laboratory
ISO 1920-9-------------- Testing of concrete -- Part 9: Determination of creep of concrete
cylinders in compression
7.2 BATCHING
7.2.1 General
2 The coarse aggregate shall be controlled to minimize segregation and undersized material.
Fine aggregate shall be controlled to minimize variations in gradation, giving special
attention to keeping finer fractions uniform and exercising care to avoid excessive removal of
fines during processing
3 Avoid blending two sizes of fine aggregate by placing alternate amounts in bins or stockpiles
or when loading cars or trucks. Satisfactory results are achieved when different size
fractions are blended as they flow into a stream from regulating gates or feeders. A more
reliable method of control for a wide range of plant and job conditions, however, is to
separate storage, handling, and batching of the coarse and fine fractions
4 Stockpiling of coarse aggregate shall be kept to a minimum because fines tend to settle and
accumulate. When stockpiling is necessary use of correct methods minimizes problems with
fines, segregation, aggregate breakage, excessive variation in gradation, and contamination.
Stockpiles shall be built up in horizontal or gently sloping layers, not by end-dumping.
Trucks, loaders, and dozers, or other equipment shall not be operated on the stockpiles
because, in addition to breaking the aggregate, they frequently track dirt onto the piles
6 Sequencing and blending of the ingredients during charging of the mixers shall be carried
out in such a way as to obtain uniformity and homogeneity in the concrete produced as
indicated by such physical properties as unit weight, slump, air content, strength and air-free
mortar content in successive batches of the same mix proportions and as stated in ASTM
C94 Annex A.
7 The mix recipe for the mixes to be produced shall be readily available to the mixer operator.
Only authorised personnel shall be allowed to make changes to the mix design.
8 All cement bags shall be stored in weathertight, properly ventilated structures to prevent
absorption of moisture.
QCS 2010
QCS 2010 Section 5 Part 7 Batching and Mixing Page 4
9 Storage facilities for bulk cement shall include separate compartments for each type of
cement used. The interior of a cement silo shall be smooth, with a minimum bottom slope of
50 degrees from the horizontal for a circular silo and 55 to 60 degrees for a rectangular silo.
Silos shall be equipped with non-clogging air-diffuser flow pads through which small
quantities of dry, oil-free, low-pressure air can be introduced intermittently at approximately 3
to 5 psi (20 to 35 kPa) to loosen cement that has settled tightly in the silos. Storage silos
shall be drawn down frequently, preferably once per month, to prevent cement caking.
10 Each bin compartment from which cement is batched shall include a separate gate, screw
conveyor, air slide, rotary feeder, or other conveyance that effectively allows both constant
flow and precise cutoff to obtain accurate batching of cement
11 Fly ash, ground slag, or other pozzolans shall be handled, conveyed, and stored in the same
manner as cement. The bins, however, shall be completely separate from cement bins
12 All bins and silos shall be properly tagged at silos, bins and near charging hose.
13 Bags of cement should be stacked on pallets or similar platforms to permit proper circulation
of air. For a storage period of less than 60 days, stack the bags no higher than 14 layers,
and for longer periods, no higher than seven layers.
14 The water batcher and the water pipes should be leak-free. If ice is used, the ice facilities,
including the equipment for batching and transporting to the mixer, should be properly
insulated to prevent the ice from melting before it is in the mixer.
1 Manual control batching. Manual plants are acceptable for small jobs having low batching
rate requirements, generally for jobs up to a total concrete quantity of 1000 m3 and 10 m3/h.
2 Semi-automatic control batching. In this system, aggregate bin gates for charging batchers
are opened by manually operated push buttons or switches. Gates are closed automatically
when the designated weight of material has been delivered.
1 Batch plant bins shall be of sufficient size to effectively accommodate the production
capacity of the plant. Compartments in bins separate the various concrete materials, and the
shape and arrangement of aggregate bins shall prevent aggregate segregation and leakage.
2 Weight batchers shall be charged with easy-operating clam shells or undercut radial-type bin
gates.
3 Gates used to charge semi-automatic and fully automatic batchers shall be power operated
and equipped with a suitable in flight correction to obtain the desired weighing accuracy.
They shall be calibrated by the plant supplier for the types of aggregate used at the standard
range of moisture contents.
4 Weigh batchers shall be accessible for obtaining representative samples, and they shall be
arranged to obtain the proper sequencing and blending of aggregates during charging of the
mixer.
5 The amount of concrete mixed in any one batch shall not exceed the rated capacity of the
mixer.
QCS 2010
QCS 2010 Section 5 Part 7 Batching and Mixing Page 5
6 All mixing and batching plants shall be maintained free of set concrete or cement and shall
be clean before commencing mixing.
7 For each different type of cement at use at the plant a separate silo shall be provided.
1 Scales for weighing concrete ingredients shall be accurate when in use within ±3 % and
±1.5 % for additives. Standard test weights shall be available to permit the checking of scale
accuracy.
2 Testing of the weighers shall be at three-month intervals. If water is dispensed by flow meter
the frequency of testing shall be at three-month intervals. Such testing shall be undertaken
1 Operation of batching equipment shall be such that the concrete ingredients are consistently
measured within the following tolerances. The plant shall have the ability to flag values that
are outside these limits. The operator shall make manual adjustments to the batching and
the final weights shall be within the given limits stated in table 7.1. Any adjustments shall be
displayed on the batch weight printouts.
3 Aggregate shall be measured by mass. Batch mass measurements shall be based on dry
materials and shall be the required masses of dry materials plus the total mass of moisture
(both absorbed and surface) contained in the aggregate
4 Mixing water shall consist of water added to the batch, ice added to the batch, water
occurring as surface moisture on the aggregates, and water introduced in the form of
admixtures. The added water shall be measured by weight or volume.
5 Added ice shall be measured by weight. In the case of truck mixers, any wash water retained
in the drum for use in the next batch of concrete shall be accurately measured; if this proves
impractical or impossible the wash water shall be discharged prior to loading the next batch
of concrete
QCS 2010
QCS 2010 Section 5 Part 7 Batching and Mixing Page 6
7 Cement supplied in bags shall be placed directly from the bag into the intake of the mixing
plant and each batch must contain one or more complete bags of cement. No mixer having
a rated capacity of less than a one-bag batch shall be used and the mixer shall not be
charged in excess of its rated capacity.
1 Each batch shall be so charged into the mixer that some of the water will enter in advance of
the cement and aggregates. Controls shall be provided to prevent batched ingredients from
entering the mixer before the previous batch has been completely discharged.
2 The first batch of concrete through the mixer shall contain an excess of cement to allow for
coating of the inside of the mixing drum without reducing the required mortar content of the
mix.
3 Mixing plant that has been out of action for more than 30 minutes shall be thoroughly
cleaned before any fresh concrete is mixed in it.
4 When a change of mix is made to one using a different type of cement, the mixing plant shall
be thoroughly cleaned of all traces of the previously used cement, whatever is the time
interval between successive mixes.
7.3 MIXING
1 Water shall enter the mixer first with continuous flow while other ingredients are entering the
mixer. Water charging pipes must be of the proper design and of sufficient size so that water
enters at a point well inside the mixer and charging is completed within the first 25% of the
prescribed mixing time and where concrete uniformity shall be verified by approved
inspector.
QCS 2010
QCS 2010 Section 5 Part 7 Batching and Mixing Page 7
2 Admixtures shall be charged to the mixer in accordance with the instructions of the
manufacturer. Automatic dispensers shall be used.
1 The mixing time required shall be based upon the ability of the mixer to produce uniform,
homogeneous, consistent mixture throughout the batch and from batch to batch.
2 Final mixing times shall be based on the results of mixer performance tests made at the start
of the project and the time fixed unless a change is authorised by the Engineer. The time
shall however not be less than 60 Sec unless otherwise verified as stated hereafter. Where
no mixer performance tests are made, the acceptable mixing time for mixers having
capacities of 0.75 m3 or less shall be not less than 1 min. For mixers of greater capacity, this
minimum shall be increased 15 s for each cubic meter or fraction thereof of additional
3 Where mixer performance tests have been made on given concrete mixtures in accordance
with the testing program ASTM C94 Annex A and NRMCA certification, and the mixers have
been charged to their rated capacity, the acceptable mixing time is permitted to be reduced
for those particular circumstances to a point at which satisfactory mixing defined in ASTM
C94 and NRMCA certification for central mixing plants shall have been accomplished. When
the mixing time is so reduced the maximum time of mixing shall not exceed this reduced
time by more than 60 s for air-entrained concrete. The mixing time shall be measured from
the time all ingredients are in the mixer.
4 Batch mixers with audible indicators used in combination with interlocks which prevent mixer
discharge prior to completion of a preset mixing time shall be provided on automatic plants
and are also desirable on manual plants.
5 The mixer shall be designed for starting and stopping under full load.
7.3.3 Mixing
2 The plant shall be complete with suitable water chilling or ice making facilities, or both, to
ensure concrete temperatures are maintained as specified in Parts 6 and 15 of this Section.
3 Concrete shall be mixed in batches in plant capable of combining the aggregates, cement
and water (including admixtures, if any) into a mixture of uniform colour and consistency and
of discharging the mixture without segregation.
4 Automatic moisture content probes, set in the hoppers shall be used to continuously
determine the moisture content of the aggregates.
5 Contractor shall make due allowance for the water contained in the aggregates when
determining the quantity of water to be added to each mix.
6 The amount of water added to each mix shall be adjusted to maintain the constant approved
water:cement ratio of the mixed concrete.
1 No concrete shall exceed the water:cement ratio as given in Part 6 of this Section.
QCS 2010
QCS 2010 Section 5 Part 7 Batching and Mixing Page 8
2 The quantity of water used in mixing shall be the least amount that will produce a workable
homogeneous plastic mixture which can be worked into the forms and around the
reinforcement.
3 Excess water over the maximum allowed by the mix design shall not be permitted and any
batch containing such excess will be rejected.
7.4.1 General
1 The manufacture of readymix concrete for use in government projects may only be carried
out in batching plants that have an approval certificate issued by the Central Materials
4 Every additional facility, including but not limited to testing equipment, labour, laboratory
facilities and transport, which the Engineer or persons authorised by him may require for the
supervision and inspection of the batching, mixing, testing and transporting to Site of ready-
mixed concrete shall be provided by the Contractor at no extra cost.
5 Copies of all delivery notes shall be submitted to the Engineer in duplicate, on computer
generated forms and shall include at least the following information.
(a) name of supplier, serial number of ticket and date
(b) truck number
(c) name of Contractor
(d) name of Contract and location of office
(e) grade of concrete
(f) specified workability
(g) type and source of cement
(h) source of aggregate
(i) nominal maximum size of aggregate
(j) quantity of each concrete ingredient
(k) type of admixture and quantity
(l) water content
(m) time of loading and departure from ready-mix plant
(n) arrival and departure times of truck
(o) time of completion of discharge
(p) notations to indicate equipment was checked and found to be free of contaminants
prior to batching.
6 A copy of the delivery note shall be given to the Engineer's site representative for each load.
7 Unless approved otherwise in advance of batching all concrete of single design mix for any
one day's pour shall be from a single batch plant of a single supplier.
QCS 2010
QCS 2010 Section 5 Part 7 Batching and Mixing Page 9
9 Transit mixers equipped with automatic devices for recording the number of revolutions of
the drum shall be used.
10 Excess water over the maximum allowed by the mix design shall not be added.
11 Each mixer truck shall arrive at the job site with its water container full.
12 In the event that a container is not full or concrete tests give a greater slump than
acceptable, the load shall be rejected.
13 Shade temperature and concrete temperature shall be recorded at the point of discharge of
the mixer and at placement for each load of concrete delivered to site.
14 Maximum and minimum temperatures and wet bulb temperatures shall be recorded daily.
END OF PART
QCS 2010
QCS 2010 Section 5 Part 8 Transportation and Placing of Concrete Page 1
QCS 2010
QCS 2010 Section 5 Part 8 Transportation and Placing of Concrete Page 2
1 This part deals with the transportation, placing and compaction of concrete.
1 Should the Contractor propose to use concrete pumps for the transportation and placing of
concrete, he shall submit details of the equipment and operating techniques he proposes to
use for the approval of the Engineer.
2 A method statement shall be submitted for approval for major concrete placements, which
shall address
(a) the planned rate of placing
(b) number of batching plants
(c) number of trucks
(d) number and positioning of pumps
(e) pour sequence
(f) quality control measures
(g) spare equipment
(h) any other factors that might affect the placing of concrete.
The method statement should be submitted at least three days in advance of the planned
pour. If required by the Engineer or any other concerned party a prepour planning meeting
may be arranged with representatives from the ready-mix supplier, Contractor and Engineer.
3 The Contractor shall submit to the Engineer for approval details of his proposed operations
and standby equipment.
8.2 TRANSPORTATION
8.2.1 General
2 Concrete shall be conveyed from the mixer to its place in the Works as rapidly as possible
by methods which will prevent segregation or drying out and ensure that the concrete is of
the required workability at the point and time of placing.
QCS 2010
QCS 2010 Section 5 Part 8 Transportation and Placing of Concrete Page 3
3 Should segregation occur in the concrete then the materials shall be remixed to the
satisfaction of the Engineer or discarded. Furthermore the cause of the segregation shall be
determined and further occurrences prevented.
4 The Contractor shall ensure that the time between placing of different lifts or layers of
concrete is short enough to prevent the formation of cold joints. The Contractor shall ensure
that there is a back up plant that can be used in the event of a breakdown, and that
adequate provision has been made for the number of delivery trucks.
5 The concrete shall be transported to the site in an approved type of truck mixer or agitator
truck which apart from the cab and chassis shall be painted white and kept clean at all times.
The discharge chute and other dirty areas shall be washed down after delivery to prevent
spillage on the roads.
7 All trucks shall be rotated 30 revolutions at mixing speed before discharging concrete to
assure uniformity.
8 The insides of concrete mix trucks shall be inspected periodically, and any build up of
concrete removed that may impair the efficiency of the mixing action. All trucks shall be
NRMCA certified or any equivalent certification
9 Discharge of the concrete shall be completed within 90 min, or before the drum has revolved
300 revolutions, whichever comes first, after the introduction of the mixing water to the
cement and aggregates or the introduction of the cement to the aggregates. These
limitations are permitted to be waived by the purchaser if the concrete is of such slump or
slump flow after the 90 min time or 300-revolution limit has been reached that it can be
placed, without the addition of water, to the batch. In hot weather, or under conditions
contributing to quick stiffening of the concrete, a time less than 90 min is permitted to be
specified by the Engineer
1 Access for the pump shall be checked prior to the pour. If access cannot be assured, the
Contractor shall not continue with concreting operations.
2 If approval is obtained for pumped concrete, the Contractor shall ensure that shock is not
transferred from the pipeline to the formwork and previously laid concrete.
3 During placing concrete by pumping the end hose must never reach into the concrete. All
measures shall be taken to avoid blockage of the delivery hose system. The Compaction of
concrete shall be carried out as per standard practice procedures.
4 Grout shall be pumped through the concrete pump to provide initial lubrication. The initial
discharge of any pumped concrete shall not be incorporated in the permanent works.
5 Where concrete is conveyed by chuting or pumping the plant shall be of a size and design to
ensure continuous flow in the chute or pipe. The slope of the chute or the pressure of the
pump shall allow the concrete to flow without the use of any water additional to that
approved by the Engineer to produce the required consistency and without segregation of
the ingredients. The delivery end of the chute or pipe shall be thoroughly flushed with water
before and after each working period and kept clean. The water used for this purpose shall
be discharged outside and away from any permanent works.
QCS 2010
QCS 2010 Section 5 Part 8 Transportation and Placing of Concrete Page 4
8.2.3 Records
Within 24 h of delivery, the Contractor shall provide the Engineer with delivery notes giving
the information required under Paragraph 7.4.1.5 of this Section.
8.3 PLACING CONCRETE
8.3.1 General
1 The Contractor shall obtain the approval of the Engineer to his proposed arrangements
before beginning concreting.
2 All placing and compacting of concrete shall be carried out under the direct supervision of a
competent member of the Contractor’s staff with a minimum of five years of experience in
3 For night concreting operations, the Contractor shall arrange adequate suitable lighting.
4 The Contractor shall provide safe secure access for all personnel on concreting operations.
5 Where the thickness of the concrete section exceeds 600 mm the Contractor shall adopt
special precautions, to be approved by the Engineer, to avoid thermal cracking due to
external and core temperature differentials.
6 Concrete shall not be placed in adverse weather conditions such as dust storms or heavy
rain.
8.3.2 Preparation
1 No concrete shall be placed until the Engineer has inspected and approved in writing the
surfaces upon which the concrete is to be placed, the formwork, and reinforcing steel. The
Contractor shall give the Engineer at least 24 hours notice to enable this inspection to be
carried out. If concrete is not placed within 24 hours of approval being given, approval shall
be obtained again before concreting. An inspection shall be made immediately prior to
concreting to check the cleanliness of the forms.
2 Wood forms, unless lined, shall be oiled or wetted with water in advance of placing concrete
so that joints will tighten and prevent seepage of cement grout from the mix.
3 The reinforcement shall be sprayed with a small amount of water prior to starting the pour.
Reinforcement shall be secured in position, inspected, and accepted by the Engineer before
placing the concrete.
4 All inserts, anchor bolts, sleeves and other embedded items shall be accurately located,
using templates where appropriate, and held securely to prevent displacement during the
placing of the concrete. Aluminium items shall be completely covered and protected when
embedded in the concrete.
5 Except where shown on the drawings, no fixtures shall be attached to the concrete by shot
fixing or drilling without acceptance by the Engineer. Notwithstanding any such
authorisation, the Contractor shall be responsible for all damage so caused to the concrete
and make good at his own expense.
6 Water shall be removed from excavations before concrete is deposited. Any flow of water
shall be diverted through proper side drains and shall be removed without washing over
freshly deposited concrete. All dewatering works shall be continued as long as required.
Hardened concrete, debris, and foreign materials shall be removed from interior of forms
and from inner surfaces of mixing and conveying equipment.
QCS 2010
QCS 2010 Section 5 Part 8 Transportation and Placing of Concrete Page 5
7 Runways or other means accepted by the Engineer shall be provided for wheeled equipment
to convey the concrete to the points of deposit. Equipment used to deposit concrete shall not
be wheeled over reinforcement nor shall runways be supported on reinforcement.
8 Before depositing new concrete on or against concrete that has set, existing surfaces shall
be thoroughly roughened and cleaned of laitance, foreign matter and loose particles. Forms
shall be re-tightened and existing surfaces slushed with a grout coat of mortar consisting of
cement and fine aggregate in the same proportion in the mix, but not leaner than one (1) part
cement to two (2) parts fine aggregate, after the existing surface has been moistened. New
concrete shall be placed before the grout has attained initial set. Horizontal construction
joints shall be given a brush coat of grout consisting of cement and fine aggregate in the
same proportion as concrete to be placed, followed by approximately 75mm of concrete of
regular mix, except that the proportion of coarse aggregate shall be reduced 50%.
8.3.3 Placing
1 Concrete shall be placed in its final position before initial set has commenced and shall not
be subsequently disturbed. All concrete shall be placed within 15 min of mixing unless
carried in purpose made agitators.
2 Concrete shall be carefully placed in horizontal layers which shall be kept at an even height
throughout the work. The depth of layers and time between placement of layers shall be
such that each layer can be properly merged into the preceding layer before initial set takes
place, the depth of layer shall be determined from the type of plant the Contractor proposes
to use.
3 Concrete shall be allowed to slide or flow down sloping surfaces directly into its final position
from skips, down pipes or other placing machines or devices or, if this is not practical, it
should be shovelled into position, care being taken to avoid separation of the constituent
materials.
4 Concrete placed in horizontal slabs from barrows or other tipping vehicles shall be tipped
into the face of the previously placed concrete.
5 Concrete dropped into place shall be dropped vertically. It shall not strike the formwork
between the point of its discharge and its final place in the Work, and except by approval of
the Engineer it shall not be dropped freely through a height greater than 1.5 m. Chutes and
conveyor belts shall be also designed so that there is no segregation or loss of mortar and
shall be provided with a vertical tapered down pipe, or other device, to ensure that concrete
is discharged vertically into place.
7 Concrete that has attained its initial set or has contained its water content for more than 1.5
hours or 300 drum revolutions, whichever comes first, shall not be deposited in the work.
8 Cold weather concreting shall be in accordance with EN 1992-1-1 or CIRIA Report 67 and
ACI 306.
10 Special care shall be taken to protect new concrete from the harmful effects of drying winds.
QCS 2010
QCS 2010 Section 5 Part 8 Transportation and Placing of Concrete Page 6
11 During wet weather, the concrete shall be adequately protected as soon as it is in position.
12 No concreting shall be carried out during periods of continuous heavy rain unless it is
completely covered during mixing, transporting and placing.
14 Underwater placing of concrete is allowed only for unreinforced components, the placing
being effected exclusively with stationary tremies or with a bottom-opening watertight boxes
and shall be in accordance with the requirements of design or equivalent as accepted.
16 All work connected with the placing of concrete under water shall be designed, directed and
inspected with due regard to local circumstances and purposes. Work shall not proceed until
all phases and methods to be used in the placing operations have been accepted by the
Engineer.
17 Stops in concrete, at the end of a period of work, shall be made only at construction joint
locations shown on the drawings and/or positions accepted. Where the positions of
construction joints are not indicated on the drawings, these may be assumed, for estimating
purposes, to occur at 5 metre intervals in foundations and retaining walls and at one-third to
one-quarter of span in slabs and beams subject to a maximum spacing of approximately 9
metres.
18 At construction joint location the surface of the completed concrete shall be prepared by
spraying, wire brushing or chipping so that it is free from all laitance, scum and loose
material and shows a slightly roughened texture and tips of the coarse aggregate exposed.
Before continuing concreting the exposed concrete face shall be thoroughly wetted.
19 In the ground floor slab (where ground bearing), construction joints, crack inducer joints,
contraction joints and expansion joints shall be incorporated into the work as appropriate.
The spacing of construction joints, crack induced joints, contraction joints and expansion
joints in water retaining structures shall be shown on the design drawings
20 Where the positions or type of joints are not indicated on the drawings in the ground floor
slab, the slab shall be cast in strips not more than 4.0 metres wide, in alternating sequence,
across the width of the building. A minimum of 3 days shall elapse between the casting of
adjacent strips. Within each strip, crack induced joints shall be provided at not more than
5.0 metre spacing, and contraction joints shall be provided at not more than 15.0m spacing.
Across the width of the building, construction joint shall be provided between adjacent strips
with contraction joint at every 4th construction joint.
22 Engineer’s acceptance shall be obtained by the Contractor, prior to start of work, on the
casting sequence and the layout of joints.
QCS 2010
QCS 2010 Section 5 Part 8 Transportation and Placing of Concrete Page 7
24 The type of waterbar to be used shall suit the joint and purpose according to water bar
manufacturers recommendations
8.3.4 Compaction
1 Concrete shall be thoroughly compacted by vibration during the operation of placing and
thoroughly worked around the reinforcement, around embedded fixtures and into corners or
the formwork to form a solid mass free from voids.
2 When vibrators are used to compact the concrete, vibration shall be applied continuously
during the placing of each batch of concrete until the expulsion of air has practically ceased
3 Immersion type vibrators shall be capable of producing not less than 10000 cycles per
minute, and external vibrators not less than 3000 cycles per minute.
4 A sufficient number of vibrators in serviceable condition shall be on site to ensure that spare
equipment is always available in the event of breakdown.
5 Immersion type vibrators shall be inserted into the uncompacted concrete vertically and at
regular intervals. Where the uncompacted concrete is in a layer above freshly compacted
concrete the vibrator shall penetrate vertically for about 100 mm into the previous layer.
Vibrators shall not come into contact with the reinforcement or the formwork. They shall be
drawn back slowly from the mass concrete so as to leave no voids. Internal type vibrators
shall not be placed in the concrete in a random or haphazard manner nor shall concrete be
moved from one part of the work to another by means of the vibrators.
6 Operators shall be trained in the use of vibrators. Foremen shall have a minimum of five
years of experience in the supervision of placing concrete
8 Compaction shall commence as soon as there is sufficient concrete to immerse the vibrator
and continue during the placing operations so that at no time shall there be a large volume of
uncompacted concrete in the formwork.
9 The duration of vibration shall be limited to that required to produce satisfactory compaction
without causing segregation. Vibration shall on no account be continued after water or
excess grout has appeared on the surface.
10 During the placing of all reinforced concrete, a competent steel fixer and a competent
carpenter shall be in attendance on each concreting gang. They shall ensure the
reinforcement embedded fittings and forms are kept in position as work proceeds.
1 Whenever instructed by the Engineer, the Contractor shall carry out the work in such a
manner that the placing of the concrete in any particular section of the structure shall be
executed without any interruption whatsoever from the beginning to the end of the operation.
2 Casting of concrete shall not begin until a sufficient quantity of approved material is at hand
to ensure continuity of operation, nor shall work begin until there is sufficient equipment in
reserve in case of breakdown.
END OF PART
QCS 2010
QCS 2010 Section 5 Part 9 Formwork Page 1
9. FORMWORK ................................................................................................. 2
9.1 GENERAL...................................................................................................... 2
9.1.1 Scope 2
9.1.2 References 2
9.1.3 Submittals 2
9.1.4 Quality Assurance 3
9.2 FORMWORK MATERIALS ............................................................................ 4
9.2.1 General 4
9.3 CLASS OF FINISH AND MATERIALS:.......................................................... 4
QCS 2010
QCS 2010 Section 5 Part 9 Formwork Page 2
9. FORMWORK
9.1 GENERAL
9.1.1 Scope
1 This Part includes permanent forms, temporary formwork, and falsework for structural and
architectural cast-in-place concrete including form liners, coatings, and accessories.
1 The following standards and other document are referred to in this Part:
ACI Committee 117... “Standard Tolerances for Concrete Construction and Materials” (ACI
117-90), American Concrete Institute, Detroit, 22 pp.
ACI Manual of Concrete Practice, Parts 2 and 5.
1 Shop drawings shall include plans and sections, giving the following minimum information for
each level:
(a) details of individual panels
(b) position, size and spacing of adjustable steel shores
(c) position, size and spacing of joists, soldiers, ties
(d) details of formwork for columns, beams, parapets, slab and kickers
(e) details of construction joints and movement joints
(f) details of retaining walls and deep beams showing the position and size of ties, joints,
soldiers and sheeting, together with detailed information on erection and casting
sequences and construction joints
(g) general assembly details
(h) full calculation sheets
(i) proposals at all penetrations through the concrete
(j) proposed sequence of shoring and reshoring beams and slabs for different spans and
floor heights and number of floors shored, and the stripping time for supported and
suspended structural elements, clearly identifying the supported element and
suspended element.
2 Scales of shop drawings shall be as follows:
(a) details: 1:1, 1:5, 1:10, 1:20
(b) construction: 1:50, 1:100
(c) layout and Site Plan: 1:100 or 1:200
QCS 2010
QCS 2010 Section 5 Part 9 Formwork Page 3
3 The Contractor shall submit samples of all proposed formwork materials and samples of ties
proposed for use in general situations above the water table and for fair faced concrete.
4 The Contractor shall allow 14 days for Engineer’s review of submittals or samples.
5 Supply and delivery of built-in pipework should be clearly shown on the detailed construction
program to be submitted by the Contractor.
2 The erection of formwork and associated falsework shall be executed and supervised by
fully qualified personnel having a minimum of five years experience.
4 Formwork design shall be carried out in accordance with the Concrete Society Technical
Report No. 13.
5 The erected formwork shall be watertight from the ingress of external liquids and the egress
of internal liquids. Adjustable steel supports and shores shall allow formboards and
framework to be accurately adjusted to line and level. The Contractor shall ensure that
adequate ground support for falsework is available, and if not shall take measures to make
them suitable.
6 Formwork shall be designed to be sufficiently rigid to maintain the correct position, shape
and profile so that the final concrete structure is within the dimensional tolerances specified
Subpart 9.7 of this Part.
8 Soffit formwork, properly supported on shores only, shall be capable of being retained in
position during the concrete maturing period.
9 The design shall allow free movement and accessibility under the formwork.
QCS 2010
QCS 2010 Section 5 Part 9 Formwork Page 4
(i) self-weight
(ii) formwork forces
(iii) reinforcement weight
(iv) wet concrete weight
(v) construction loads
(vi) wind loads, based on a design wind speed of 45 m/s according
to CP3 chapter V-2: 1972
(vii) incidental dynamic effects caused by placing, vibrating and compacting
concrete
(viii) the use of externally applied vibrators
9.2.1 General
4 Form oil and form sealer shall be of quality as acceptable to the Engineer.
QCS 2010
QCS 2010 Section 5 Part 9 Formwork Page 5
(iv) Non-slip Finish - Concrete surfaces described on the drawings as having a non-
slip finish shall be treated with carborundum dust, evenly sprinkled on whilst the
concrete is still green, at a rate of 1½ kg/m² and lightly trowelled in before final
finishing. Alternatively, the carborundum dust may be incorporated into the
finish by means of a mechanical power float.
(v) Hardened Finish - Where a hardened finish is required to the floor slabs these
shall be treated with three coats of accepted material. Each coat shall be
applied with a soft brush on a clean and dry surface in accordance with the
manufacturer's printed instructions.
(vi) Finishing Unformed Surfaces - Finishing unformed surfaces shall be tamped,
floated, trowelled or brushed as defined below and shown on the drawings.
(a) Type T - Tamped surfaces shall be formed by levelling and tamping the
concrete to produce a uniform plain or ridged surface, surplus concrete
being struck off by a straight edge immediately after compaction. It is
3 Initial finishing of unformed surfaces shall commence immediately after the placing and
compaction have taken place.
4 Suitable access boards or platforms shall be provided to allow access to all parts of
unformed surfaces to be finished.
6 Brush to finish shall be obtained by carrying out a steel trial finish and then using a suitable
stiff nylon brush dragged lightly across the surface.
7 The addition of small quantities of water to the finishing trowel will be permitted to aid
finishing.
1 Finishes to formed surfaces of concrete shall be classified as F1, F2 and F3, or such other
special finish as may be designated.
QCS 2010
QCS 2010 Section 5 Part 9 Formwork Page 6
(c) where surfaces are to be tanked by covering with paint or sheeting, the formwork
shall be capable of achieving a finish suitable for the proposed tanking as directed by
the Engineer.
9.3.3 Formwork Materials
1 Formwork for Class F3 finish shall be lined with as large panels as possible of non-staining
material with a smooth unblemished surface such as sanded plywood or hard compressed
fibre board, arranged in a uniform approved pattern and fixed to back formwork by oval nails.
(a) the same type of lining shall be used throughout any one structure
(b) unfaced wrought boarding or standard steel panels shall not be permitted.
2 Formwork for Class F2 finish shall be faced with wrought tongued and grooved boards or
plywood arranged in a uniform approved pattern free from defects likely to detract from the
3 Formwork for Class F1 finish shall be constructed of timber, or of any suitable materials
which will prevent loss of grout when the concrete is vibrated.
2 Care shall be taken to ensure that the finish to the exposed concrete on the external and
internal surfaces are of the highest quality to produce a smooth concrete surface of uniform
texture and appearance without visible imprint of grains, steppings or ridges.
3 The resulting concreting shall be free from honeycombing, stains, fins, lipping, nail and
screw marks, raised grain marks or any other imperfections and shall be of a uniform
surface texture and colour. Only very minor surface blemishes caused by entrapped air or
water will be accepted provided that they do not exceed 0.5% by area of each square metre
considered separately and in addition they shall not be concentrated in a manner such that
they are noticeable.
6 Grooves in exposed concrete shall be formed by attaching tapered planed timber battens
accurately aligned to the face of formwork.
1 Form coatings shall be commercial formulation form-coating compounds that will not bond
with, stain, nor adversely affect concrete surfaces requiring bond or adhesion, nor impede
QCS 2010
QCS 2010 Section 5 Part 9 Formwork Page 7
the wetting of surfaces to be cured, shall be used. The use of form coatings shall be strictly
in accordance with the manufacturer instructions.
2 Formwork in contact with the concrete shall be treated with a suitable non-staining mould oil
to prevent adherence of the concrete.
3 Forms for exposed surfaces shall be coated with oil before reinforcement is placed. Forms
for unexposed surfaces may be thoroughly wetted with water in lieu of oiling, immediately
before placing of concrete except during freezing weather.
4 Excessive oiling of the forms shall not be permitted in order to prevent discoloration of the
cement plaster. Where concrete surface is to be painted, the form-oil must not affect the
bond between concrete and paint.
6 Release agents shall not be used where concrete surfaces receive special finishes or
applied coatings which may be affected by the agent, unless approved by the Engineer.
7 Fillet and chamfer strips shall be PVC or timber to the approval of the Engineer.
8 Tapes to be used to seal joints of formwork panels for smooth finish concrete shall be plastic
faced adhesive tape to the approval of the Engineer.
9.4.1 General
1 Where formwork to external faces will be permanently exposed, all horizontal and vertical
formwork joints shall be so arranged that joint lines will form a uniform pattern on the face of
the concrete.
2 Where the Contractor proposes to make up the formwork from standard sized manufactured
formwork panels, the size of such panels shall be approved by the Engineer before they are
used in the construction of the Works.
3 The finished appearance of the entire elevation of the structure and adjoining structures
shall be considered when planning the pattern of joint lines caused by the formwork and by
the construction joints to ensure continuity of horizontal and vertical lines.
4 Masonry nails or similar items shall not be used to fix formwork of the like to permanent
concrete works.
1 The trial panels shall comprise surfaces that have unformed surfaces and formed surfaces
F1, F2 and F3.
2 The concrete cast from the job mock-up shall be used to assess the acceptability of the
Contractor’s workmanship for finishing.
3 If the finishing is deemed unacceptable by the Engineer, the Contractor shall prepare a
further mock-up with a particular class of finish.
QCS 2010
QCS 2010 Section 5 Part 9 Formwork Page 8
4 The job mock-ups shall be retained during the course of the works to allow comparative
inspection, with production concreting and finishing and for the purpose of colour
comparison to ensure colour consistency.
1 Faces of formwork in contact with concrete shall be free from adhering foreign matter,
projecting nails and the like, splits or other defects, and all formwork shall be clean and free
from standing water, dirt, shavings, chippings or other deleterious matter.
2 Joints between forms and tie holes shall be watertight to prevent the escape of mortar or the
formation of fins or other blemishes on the face of the concrete.
3 The Contractor shall verify lines, levels and measurement before proceeding with formwork
1 Formwork shall be provided for the top surfaces of sloping work where the slope exceeds
15 ° from the horizontal (except where any such top surface is specified as a spaded finish).
2 The formwork shall be anchored to enable the concrete to be properly compacted and to
prevent flotation.
3 Care shall be taken to prevent air being trapped under the sloping formwork.
1 The Contractor shall provide temporary openings for inspection of the inside of the formwork
and for the removal of water used for washing down. The openings shall be formed as to be
easily closed before placing concrete.
1 The Contractor shall provide windows in forms wherever directed by the Engineer or
necessary for access for concrete placement and vibration.
2 The windows shall be of a size adequate for tremies and vibrators spaced at maximum
1.8 m centres horizontally.
3 Any windows shall be tightly closed and sealed before proceeding to place concrete at a
higher level.
9.4.7 Co-ordination
1 The Contractor shall ensure that the work of other trades in forming and setting openings,
slots recesses, chases, sleeves, bolts, anchors and other inserts is fully co-ordinated.
9.4.8 Conduits
1 Conduits or pipes shall be located so as not to reduce the strength of the construction.
2 In no case shall pipes other than conduits be placed in a slab 125 mm or less in thickness.
3 Conduits embedded in a concrete slab shall not have an outside diameter greater than
one-third the thickness of the slab nor be placed below the bottom reinforcing steel or over
the top reinforcing steel.
QCS 2010
QCS 2010 Section 5 Part 9 Formwork Page 9
4 Conduits may be embedded in walls provided they are not larger in outside diameter than
one-third the thickness of the wall, are not spaced closer than three diameters on centre,
and do not impair the strength of the structure.
5 Embedded pipes and conduits shall be supported independently from reinforcing steel in a
manner to prevent metallic contact and thereby prevent electrolytic deterioration.
6 Pipes and conduits where embedded shall be placed as nearly as possible to the centre line
of the concrete section.
7 Conduits, piping, and other wall penetrations or reinforcements shall be subject to the
Engineer’s review and approval.
2 Ties, bolts or other devices shall not be built into the concrete for the purpose of supporting
formwork without the prior approval of the Engineer. The whole or part of any such supports
shall be capable of removal so that no part remaining embedded in the concrete shall be
nearer to the surface than the cover required for reinforcement.
9.4.10 Chamfers
1 Chamfer moulding strips shall be positioned on the exposed corners of columns and beams.
9.4.11 Cambers
2 The depth of beams at all points in the span, where cambers are used, shall be as
shown on the Drawings.
3 Allowance shall be made for compression and settlement of the formwork on line and level.
1 All exterior angles to concrete exposed to view in the completed structure shall be cast to the
true angles evenly throughout the length.
2 Care shall be taken to ensure that no waviness occurs along the angle and that no spalling
occurs to the concrete on removal of the formwork.
1 Surface retarders shall not be used on any formwork surface in contact with concrete unless
expressly authorised by the Engineer.
1 Devices of telltale type shall be installed on supported forms and elsewhere as required to
detect formwork movements and deflection during concrete placement.
2 Where required slab and beam cambers shall be checked and correctly maintained as
concrete loads are applied on forms.
QCS 2010
QCS 2010 Section 5 Part 9 Formwork Page 10
3 Workmen shall be assigned to check forms during concrete placement and to promptly seal
all mortar leaks.
1 Pipes and pipe specials through concrete walls and floors shall as far as possible be
positioned and built in during construction. They shall be located exactly in the positions
shown on the Drawings and shall be true to line and level.
2 The Contractor shall take particular care to ensure that fully compacted concrete is in
contact with the pipe at all points.
3 Where it is not practicable to cast pipes and specials in the concrete, boxholes shall be
formed in the shuttering.
5 When the pipe is later fixed, the remaining hole shall be reshuttered and filled with
non-shrink epoxy grout or non-shrink concrete. In the case of water retaining structures, the
Contractor shall ensure that the measures adopted shall provide a finished joint which is
resistant against and free from leakage.
1 The Engineer shall be notified in writing before the removal of any formwork.
2 The Contractor, under no circumstances, shall strike the formwork until the concrete has
attained adequate strength to resist damage, in particular to arises and features.
3 Concrete shall be thoroughly wetted as soon as the forms are first loosened and shall be
kept wet during the removal operations and until the curing media is applied.
4 A potable water supply with hoses having fine fog spray attachments shall be ready at each
removal location before operations are commenced.
1 The period of time elapsing between the placing of the concrete and the striking of the
formwork shall be approved by the Engineer after consideration of the loads likely to be
imposed on the concrete and shall in any case be not less than the periods shown in
Table 9.1
2 Stripping of the formwork within the time limits listed above does not relieve the Contractor
from successfully crushing test cubes and achieving the specified compressive strength
results.
3 Notwithstanding the foregoing the Contractor shall be held responsible for any damage
arising from removal of formwork before the structure is capable of carrying its own weight
and any incidental loading.
4 Where finished surfaces have re-entrant angles, the formwork shall be removed as early as
possible, within the time limits set above, to avoid shrinkage cracks.
QCS 2010
QCS 2010 Section 5 Part 9 Formwork Page 11
5 The formwork shall be carefully stripped to avoid sudden shocks from the removal of
wedges, or vibration which might cause damage to the concrete.
6 Reshoring to beams and slabs shall be placed immediately after stripping formwork.
Table 9.1
Stripping Times of Formworks
1 Holes formed in concrete surfaces by formwork supports or the like shall be filled neatly with
non-shrink grout.
2 The Contractor shall clean and scarify any hole that is to be filled with non-shrink grout.
1 Where the concrete surface has been damaged, the Contractor shall break out any loose,
broken or cracked concrete or aggregate.
2 The concrete surrounding the hole shall be then be thoroughly soaked after which the
surface shall be dried so as to leave a small amount of free water on the surface. The
surface shall then be dusted with ordinary Portland cement by means of a small dry brush
until the whole surface that will come into contact with the dry-pack mortar has been covered
and darkened by absorption of the free water by the cement. Any dry cement in the hole
shall be removed
3 Dry-pack material shall then be placed and packed in layers having a compacted thickness
in accordance with the manufacturer’s instructions. Compaction shall be carried out by the
use of a hardwood stick and a hammer and shall extend over the full area of the layer,
particular care being taken to compact the dry-pack against the side of the hole. After
compaction the surface of each layer shall be scratched before further loose material is
added
4 The hole shall not be over-filled and the surface shall be finished by layering a hardwood
block against the dry-pack fill and striking the block several times. Steel finishing tools shall
not be used and water shall not be added to facilitate finishing.
5 The surface of the concrete shall be rubbed down smooth with carborundum and water in an
approved manner within three days of removing the formwork. Holes left after removal of
such supports shall be neatly filled with non-shrink grout of a suitable consistency and
matching colour.
QCS 2010
QCS 2010 Section 5 Part 9 Formwork Page 12
1 The delivery of formwork materials shall be done in such a manner that damage can be
prevented.
9.6.2 Storage
1 Formwork should be stored, after cleaning and preparing for reuse if used before, in such a
manner that access to all different materials is available.
2 While propping through two floors, the Contractor shall ensure, that the props beneath the
floor last constructed are released over its full extent as soon as the concrete has achieved
sufficient strength to support itself plus any superimposed loading, but not sooner than the
periods given in Table 9.1. The props shall then be re-tightened so that these may be used
to share the construction loading from the floor above.
QCS 2010
QCS 2010 Section 5 Part 9 Formwork Page 13
3 Not withstanding the requirements of this Section for the removal times for formwork, the
following provisions shall apply to early loading of concrete.
4 Concrete shall at no time be subject to loading including its own weight which will induce a
compressive stress in excess of 0.33 of the actual compressive strength of the concrete at
the time of loading or 0.33 of the specified 28 d characteristic strength whichever is the
lower. For the purpose of this clause the assessment of the strength of the concrete and the
stress produced by the loads shall be subject to the agreement of the Engineer.
5 If, due to his method of construction, the Contractor wishes to place an imposed load on the
structure, he shall arrange for additional cubes to be cast at the point of the structure to be
loaded and these cubes will be crushed to monitor the compressive strength in accordance
with BS EN 12390-3 Compressive strength of test specimens. The Contractor shall submit
calculations showing the stresses induced by any proposed temporary loads to be placed on
6 No superstructure load shall be placed upon finished piers or abutments until the Engineer
has given his approval in writing and in no case shall any load be placed until the curing
period is complete.
7 Deck slabs of bridges shall only be opened to traffic or construction equipment and plant
when authorised by the Engineer and in no case until the curing period is complete.
END OF PART
QCS 2010
QCS 2010 Section 5 Part 10 Curing Page 1
QCS 2010
QCS 2010 Section 5 Part 10 Curing Page 2
10. CURING
10.1 GENERAL
10.1.1 Scope
1 The Contractor shall submit to the Engineer the proposed method of curing for approval.
1 The Contractor shall submit to the Engineer for approval the details of proposed curing
media, if any. Details shall include chemical tests for the product in accordance with
BS 7542 and details of quality assurance procedures, including ISO 9001 certificates if held.
10.1.5 Storage
10.2 CURING
10.2.1 General
1 The Contractor shall ensure that curing is provided for 24 hours per day including holidays
and that all related necessary plant and labour resources are also available.
2 Special attention shall be given to the curing of vertical and overhanging surfaces to ensure
satisfactory curing.
3 The Contractor shall adopt curing measures that preclude the possibility of thermal shock to
the concrete during curing. This may be achieved by ensuring that the temperature of the
water used for curing does not differ from that of the concrete by more than 15 °C.
4 Curing shall continue for at least 7 days and until it attains an in-place compressive strength
of the concrete of at least 70% of the specified compressive or flexural strength, whichever
period is longer. Curing shall not stop unless otherwise approved by the Engineer.
5 When low W/C is used, the concrete shall be preferably cured by water.
QCS 2010
QCS 2010 Section 5 Part 10 Curing Page 3
1 Water used for any curing purposes shall conform to the requirements of Part 4 of this
Section.
1 Freshly placed concrete shall be protected from sun, wind, exposure and excessive drying
out.
2 All fresh concrete shall be cured by liquid membrane curing compound or equivalent as soon
as possible, provided that the surface water has evaporated. The liquid membrane curing
shall not be applied if bleed water is forming or is present on the concrete surface.
4 All concrete shall be cured for a period of time required to obtain the full specified strength,
but not less than seven consecutive days. The method of curing shall be by water for the first
seven days and by water or membrane until the concrete has reached the full specified
strength.
5 For mixtures with a low to zero bleeding rate, or in the case of aggressively evaporative
environments, or both, the curing shall start at early anytime between placement and final
finishing of the concrete. The curing shall be by reducing the moisture loss from surface
using fogging systems and the use of evaporation reducers such as monomolecular water
curing compound.
6 Exposed surfaces shall be protected from air blown contamination until 28 d after the
concrete is placed.
7 The method of curing shall ensure that sufficient moisture is present to complete the
hydration of the cement, and shall be to the approval of the Engineer. The method of curing
shall not:
(a) disfigure permanently exposed surfaces
(b) affect bonding of subsequent coatings
(c) increase the temperature of the concrete.
8 During the curing period, exposed concrete surface shall be protected from the direct rays of
the sun.
1 Formed surfaces, including the underside of beams, girders, supported slabs and the like, by
moist curing with the forms in place for the full curing period, or until the forms are removed.
QCS 2010
QCS 2010 Section 5 Part 10 Curing Page 4
(d) Burlap, cotton mats, and other absorbent materials can be used to hold water on
horizontal or vertical surfaces.
(e) Wet straw or hay can be used for wet-curing small areas, but there is the danger that
wind might displace it unless it is held down with screen wire, burlap, or other means
2 Where method (a) is employed, the bunds used shall not be made from fill from excavations
or any other areas where there is the possibility of chloride contamination.
1 The concrete surface shall be covered with a suitable absorptive covering, such as hessian.
2 The absorptive covering shall be overlaid with a 1000 gauge polythene sheet.
5 Any penetrations or tear in the covering shall be shall be repaired with the same material
and waterproof tape.
1 Liquid membrane curing shall be in accordance with the requirements of ASTM C 309 or
C1315 when tested at the rate of coverage use on the job.
2 ASTM C 156 shall be used as a test method to evaluate water-retention capability of liquid
membrane forming compounds. ASTM C 1151 provides an alternative laboratory test for
determining the efficiency of liquid membrane-forming compounds.
4 Membrane forming curing compounds shall not be used on surfaces against which
additional concrete or other material is to be bonded unless:
(a) it is proven that the curing compound will not prevent bond, or
(b) positive measures are taken to remove it completely from those areas which are to
receive bonded applications
1 An enclosure shall be formed around the concrete using tarpaulin or other suitable means.
2 Application of steam shall not be commenced until at least 2 h after final placement of
concrete.
4 Excessive rates of heating and cooling shall be prevented during steam curing and
temperatures in the enclosure shall not be allowed to increase or decrease by more than
22 °C per hour.
5 The maximum steam temperature shall be maintained in the enclosure until concrete has
reached its specified strength.
QCS 2010
QCS 2010 Section 5 Part 10 Curing Page 5
1 Curing shall ensure that no plastic shrinkage crack will occur, this can be done by protective
measures such as sun shields, wind breaks, evaporation reducers, or fog spraying should
be initiated immediately to reduce evaporation.
2 Mats used for curing can either be left in place and kept saturated for completion of the
curing, or can be subsequently replaced by a liquid membrane-forming curing compound,
plastic sheeting, reinforced paper, straw, or water
3 Care shall be taken to prevent thermal shock and cracks when using water that is
significantly cooler than the concrete surface. Curing water should not be more than about
11oC cooler than the concrete.
4 Immediately following form removal, the surfaces shall be kept continuously wet by a water
spray or water-saturated fabric or until the membrane-forming curing compound is applied.
Curing
1 Mass concrete is often cured with water for the additional cooling benefit in warm weather;
however, this can be counterproductive when the temperature gradient between the warmer
interior and the cooler surface generates stress in the concrete.
3 For vertical and other formed surfaces, after the concrete has hardened and the forms are
still in place, the form ties may be loosened and water supplied to run down the inside of the
form to keep the concrete wet
4 Care shall be taken to prevent thermal shock and cracks when using water that is
significantly cooler than the concrete surface. Curing water should not be more than about
11oC cooler than the concrete.
5 Curing shall start as soon as the concrete has hardened sufficiently to prevent surface
damage.
6 For unreinforced massive sections not containing ground granulated blast-furnace slag or
pozzolan, curing shall be continued for not less than 2 weeks. Where ground granulated
blast-furnace slag or pozzolan is included in the concrete, the minimum time for curing shall
be not less than 3 weeks.
7 For reinforced mass concrete, curing shall be continuous for a minimum of 7 days or until
70% of the specified compressive strength is obtained, if strength is the key concrete
performance criterion. For construction joints, curing shall be continued until resumption of
concrete placement or until the required curing period is completed.
8 Curing shall not stop until favourable differential temperature is attained and at the approval
of the Engineer.
END OF PART
QCS 2010
QCS 2010 Section 5 Part 11 Reinforcement Page 1
11. REINFORCEMENT........................................................................................ 2
11.1 GENERAL...................................................................................................... 2
11.1.1 Scope 2
11.1.2 References 2
11.1.3 Submittals 2
11.1.4 Quality Assurance 2
11.1.5 Delivery Storage and Handling 3
11.2 REINFORCING MATERIALS......................................................................... 3
11.2.1 Reinforcing Bars 3
QCS 2010
QCS 2010 Section 5 Part 11 Reinforcement Page 2
11. REINFORCEMENT
11.1 GENERAL
11.1.1 Scope
1 This Part includes tension, compression, and temperature reinforcing steel, including welded
wire fabric, and epoxy coated reinforcing. The work includes furnishing, fabrication, and
placement of reinforcement for cast-in-place concrete, including bars, welded wire fabric,
ties, and supports.
BS 4449 : 2005............. Specification for Carbon steel bars for the reinforcement of concrete
BS 8666,....................... Specification for scheduling, dimensioning, bending and cutting of
steel reinforcement for concrete
BS 4482: 2005,............. Specification for Cold reduced steel wire for the
reinforcement of concrete
BS 4483: 2005.............. Steel fabric for the reinforcement of concrete
QS ISO 6935-1:2007,... Steel for the reinforcement of concrete -Part 1: Plain bars
QS ISO 6935-2:2007.... Steel for the reinforcement of concrete Part 2: Ribbed bars
QS ISO 6935-3:2007.... Steel for the reinforcement of concrete Part 3: Welded fabric
11.1.3 Submittals
1 Product data including the manufacturer’s specification and installation instructions for
proprietary materials and reinforcement accessories shall be provided.
2 The Contractor shall submit, the manufacturer’s records of chemical and physical properties
of each batch of billet steel bars and a certificate that the respective material furnished
meets the requirements for the steel reinforcement specified. The manufacturer’s records
shall include certificates of mill as well as analysis, tensile and bend tests of the
reinforcement.
3 Three copies of the steel test report shall be furnished with each consignment of steel
reinforcement. The steel shall be tagged and cross-referenced with mill certificates.
11.1.4 Quality Assurance
1 The Contractor shall submit to the Engineer for source approval details of the proposed
source of supply of the reinforcement. Details shall include chemical and physical tests for
QCS 2010
QCS 2010 Section 5 Part 11 Reinforcement Page 3
the past six months production and any independent test results for this period. Details of
quality assurance procedures, including ISO 9000 certificate if held, shall also be given.
2 The Contractor shall furnish the Engineer with a certificate of compliance for each shipment
of epoxy coated bars. The certificate of compliance shall state that representative samples of
the epoxy coated bars have been tested and that the test results comply with the
requirements herein specified. Test results shall be retained by the Contractor for seven
years. A complete set of test results shall also be handed to the client at the completion of
reinforcement works, and shall be made available to the Engineer upon request.
11.1.5 Delivery Storage and Handling
1 On delivery, bars in each lot shall be legibly tagged by the manufacturer. The tag shall show
the manufacturer’s test number and lot number and other applicable data that will identify the
material with the certificate issued for that lot of steel. The fabricator shall furnish three
QCS 2010
QCS 2010 Section 5 Part 11 Reinforcement Page 4
QCS 2010
QCS 2010 Section 5 Part 11 Reinforcement Page 5
6 Test results for each bar size shall be submitted to the Engineer three weeks before
concrete work commences on Site.
7 Full testing shall be required if the source of supply of reinforcement changes, in which case
the cost of such extra testing will be borne by the Contractor.
8 When any test results do not conform to the relevant standard the reinforcement steel shall
be removed from the Site and all costs resulting therefrom shall be borne by the Contractor.
11.4 CUTTING AND BENDING OF REINFORCEMENT
1 Cutting and bending of reinforcement shall be in accordance with ISO 3766 or BS 8666 and
shall be done without the application of heat. Bends shall have a substantially constant
curvature. For epoxy coated steel the provisions of Clause 11.6.1 of this Part shall apply
2 Shall the Contractor decide to use pre-bent steel reinforcement from his supplier as an
QCS 2010
QCS 2010 Section 5 Part 11 Reinforcement Page 6
5 The length of run deposited in a single pass shall not exceed five times the bar diameter. If a
longer welded length is required, the weld shall be divided into sections with the space
between runs made not less than five times the bar diameter.
6 Butt welds shall be formed by flash butt welding or metal-arc welding. Other methods may
be approved, subject to their satisfactory performance in trial joints.
7 Metal-arc welding or electrical resistance welding may be used for fixing suitable steels or
for lapped joints.
8 Flash butt welding shall be executed with the correct combination of flashing, heating,
upsetting and annealing, using only machines which automatically control this cycle of
operations.
9 Metal-arc welding shall comply with EN 1011 and the recommendations of the reinforcement
manufacturer.
QCS 2010
QCS 2010 Section 5 Part 11 Reinforcement Page 7
Table 11.1
Minimum Cover to Reinforcement
QCS 2010
QCS 2010 Section 5 Part 11 Reinforcement Page 8
2 Protect projecting reinforcement from the weather where rust staining of exposed concrete
surfaces may occur.
3 At the time of concreting, all reinforcement steel shall have been thoroughly cleaned and
freed from all mud, oil or any other coatings that might destroy or reduce the bond:
(a) clean all set or partially set concrete which may have been deposited thereon during
the placing of a previous lift of concrete
(b) all uncoated rust bars shall be again sand blasted and pressure washed.
4 Immediately before concrete placing the reinforcing steel shall be washed thoroughly with
high pressure potable water jets to remove any deposited salts.
11.6 PROTECTIVE COATINGS TO REINFORCEMENT
QCS 2010
QCS 2010 Section 5 Part 11 Reinforcement Page 9
14 A holiday detector shall be used in accordance with the manufacturer's instruction to check
the epoxy coating for holidays. A 67.5 V detector such as the Tinker and Rasor Model M-
1 or its approved equivalent shall be used.
15 Patching of holidays is not required if there are less than three holidays per 300 mm length.
Bars having three or more holidays per 300 mm shall be cleaned and recoated or replaced
as directed by the Engineer.
Epoxy coating film shall be cured and/or post cured to a fully cured condition. A
representative proportion of each production lot shall be checked by the epoxy coating
applicator, using the method most effective for measuring cure to ensure that the entire
production lot of epoxy coating is supplied in the fully cured condition.
16 Contractor shall repair all coating damaged by fixtures used to handle or support the bars in
the coating process as follows:
QCS 2010
QCS 2010 Section 5 Part 11 Reinforcement Page 10
6 Bend test shall be conducted at a room temperature of between 20 °C and 30 °C after the
specimen has been exposed to room temperature for a sufficient time to ensure that it has
reached thermal equilibrium.
7 No cracking of the epoxy coating shall be visible to the naked eye on the outside radius of
the bent bar.
Table 11.2
10 79
12 95
13 103
14 111
16 127
18 143
20 159
22 175
24 191
25 198
26 206
28 222
30 238
32 254
34 270
36 286
END OF PART
QCS 2010
QCS 2010 Section 5 Part 12 Joints Page 1
QCS 2010
QCS 2010 Section 5 Part 12 Joints Page 2
12. JOINTS
12.1 GENERAL
12.1.1 Scope
1 This part deals with movement and construction joints, slip bearings, waterstops and
associated sealants and filler materials.
12.1.3 Submittals
1 The Contractor shall submit for approval by the Engineer as soon as practicable after
acceptance of his Tender and not less than three weeks before commencement of
concreting, drawings showing his proposals for the position of construction joints having due
regard to any that may be shown on the Contract Drawings.
2 For slide bearings the Contractor shall provide at least three samples of the proposed
material, together with the manufacturer's technical specifications and recommendations in
respect of application and performance.
3 For slip joints the Contractor shall provide at least three samples of materials proposed,
together with manufacturer's technical specifications and recommendations in respect of
application and performance.
4 For waterstops the Contractor shall provide at least three samples of proposed types,
including prefabricated joints and junctions, if applicable. If joints are to be made up on site,
provide worked samples, including samples for each make of waterstop, where samples
from different manufacturers are provided.
QCS 2010
QCS 2010 Section 5 Part 12 Joints Page 3
5 The Contractor must supply a certificate of compliance for the joint sealant, stating that it
meets the requirements of the specification. The Contractor shall also supply the
Manufacturer’s technical and installation data for the proposed material. The Contractor shall
provide details of previous installations of the product, with the client name, structure name,
type of joint and value of contract.
6 The Contractor shall prepare shop drawings that show the layout of the waterstops, specials
and joints.
1 The joint sealant, including primers and debonding materials shall be compatible with each
other and shall be supplied from a manufacturer operating the ISO 9001 or 9002 Quality
Assurance Scheme.
1 Construction Joint: The surface where two successive placements of concrete meet, across
which it is desirable to develop and maintain bond between the two concrete placements,
and through which any reinforcement which may be present is not interrupted.
5 Joints Fillers: Materials that are used to fill space within movement joints during
construction. They may provide support to a sealant applied subsequently.
12.2.1 General
1 Where construction joints are required in slabs or beams (designed by Direct Design Method
DDM) they shall be located within the middle third of their spans, and at one-third to one-
quarter of span in slabs and beams subject to a maximum spacing of approximately 9
metres. Where slabs are supported by beams then the beams and slabs shall be
constructed in one operation.
2 In all cases vertical stop boards of a form to be approved by the Engineer shall be provided
by at the end of each section of work which is to be concreted in one operation and the
concrete shall be thoroughly compacted against these stop boards.
3 Where slabs, beams and walls incorporate construction joints, panels shall generally be
constructed consecutively. Where this is not possible a gap not exceeding one metre shall
be formed between adjacent panels. This gap shall not be concreted until a minimum
interval of 7 d has expired since the casting of the most recent panel.
4 The size of bays for reinforced floors, walls and roofs shall be as shown on the drawings but
in no event shall they exceed 7.5 m in either direction and 6 m when unreinforced or with
nominal reinforcement.
QCS 2010
QCS 2010 Section 5 Part 12 Joints Page 4
5 Horizontal construction joints in walls will only be permitted when the wall is continuous with
the floor slab. Walls shall be keyed on cast kickers 150 mm high or on the tops of walls
meeting the soffits of suspended members.
6 Construction joints in monolithic structures shall be aligned with each other whenever
practicable.
7 Before placing new concrete against concrete which has already set the latter shall be
treated to expose the aggregate over the full section and leave a sound irregular surface.
This shall be done while the concrete is still fresh by means of water spray and light brushing
or other means approved by the Engineer.
8 Immediately before the new concrete is placed all foreign matter shall be cleaned away and
the surface moistened.
1 The floor may be designed as fully restrained against shrinkage and thermal contraction and
should be cast directly onto the blinding concrete.
2 In large structures, the floor shall be designed as a series of continuous strips with
transverse induced contraction joints provided to ensure that cracking occurs in
predetermined positions. Longitudinal joints between the strips should form contraction
joints.
3 Waterstops shall be incorporated into construction joints, crack induced joints, contraction
joints and expansion joints in water retaining structures. The Contractor shall ensure that all
such joints are watertight and any joints which may leak or weep shall be rectified by the
Contractor to the Engineer’s satisfaction.
4 The spacing of construction joints, crack induced joints, contraction joints and expansion
joints in water retaining structures shall be shown on the design drawings.
5 Where the positions or type of joints are not indicated on the drawings, the spacing of
construction joints or crack induced joints in water retaining structures shall not exceed 5 m.
6 Where the positions or type of joints are not indicated on the drawings in the ground floor
slab, construction joints, crack induced joints, contraction joints and expansion joints shall be
incorporated into the works as appropriate. for slabs on grade, construction joints or crack
induced joints should be provided at areas where differences in subgrade and slab support
may cause cracks. The slab shall be cast in strips not more than 15 metres wide across the
width of the building. Within each strip for both directions, crack induced joints shall be
provided at areas where cracks are expected and not more than 5.0 metre spacing, and
construction or contraction joints shall be provided at not more than 15.0m spacing.
8 Waterstops of a type acceptable to the Engineer shall be embedded in the concrete. The
waterstop should be made of a high quality material, which must retain its resilience through
the service life of the structure for the double function of movement and sealing. The
surface of waterstops should be carefully rounded to ensure tightness of the joint even under
heavy water pressure. To ensure a good tightness with or without movement of the joints,
the waterstop should be provided with anchor parts. The cross-section of the waterstops
should be determined in accordance with the presumed maximum water pressure and joint
QCS 2010
QCS 2010 Section 5 Part 12 Joints Page 5
movements. The complete works of fixed and welded connections must be carried out
strictly in accordance with the manufacturer’s instructions.
9 Engineer’s acceptance shall be obtained by the Contractor, prior to start of work, on the
casting sequence and the layout of joints.
12.3.1 General
1 Movement joints for expansion and contraction shall be constructed in accordance with the
details and to the dimension shown on the Drawings or where otherwise ordered by the
Engineer and shall be formed of the elements specified.
3 The Contractor shall pay particular attention to the effects of climatic extremes on any
material which he may desire to use on any movement joint and shall submit for approval by
the Engineer his proposals for the proper storage, handling and use of the said materials
having due regard for any recommendations made by the manufacturer in this connection.
1 Joint fillers shall conform to the requirements of BS 6093 or ASTM D1751 or equivalent if
they are bituminous type or to the requirements of ASTM D3575 or BS EN ISO 7214 or
equivalent if they are polymer foam type.
2 The joint filler shall be fixed to the required dimensions of the joint cross-section and shall
provide a firm base for the joint sealer.
3 When required between two concrete surfaces as a resilient movement joint, the filler shall
be an approved granulated cork bound with insoluble synthetic resin.
4 When required between blockwork and concrete as a low density movement joint filler or for
building details it shall be an approved bitumen impregnated fibreboard or preformed closed
cell polyethylene.
1 All joints to be sealed shall be formed and the groove grit blasted to remove all traces of
deleterious materials such as form oil or curing compounds and also to remove any surface
laitance from the sides of the joint. The joint shall be dry prior the application of priming.
Where the use of grit blasting is not possible the Contractor may propose alternative
methods subject to the approval of the Engineer.
2 The back of the joint shall receive a debonding tape or polyethylene foam backer cord in
order to provide the correct depth to width ratio and prevent three sided adhesion.
3 The areas adjacent to the joint shall be protected using masking tape.
4 The sides of the joint shall be primed with the relevant primer as recommended by the
sealant manufacturer and the sealant material applied in accordance with the manufacturers
instructions.
QCS 2010
QCS 2010 Section 5 Part 12 Joints Page 6
including epoxy-polyurethane, rubber bitumen and acrylic, subject to the requirements of the
specification and the approval of the Engineer.
6 Where the joint sealant is to be in contact with a protective coating the Contractor shall
satisfy the Engineer that the sealant and protective coating are compatible
9 All surface preparation, priming, mixing and application shall be carried out in strict
accordance with the manufacturer’s instructions.
10 The sealant shall have a proven track record of no less than ten years under similar local
conditions.
12.4.1 General
1 Slip bearings shall be preformed low friction bearing strips to form a thin sliding joint.
2 They shall be extruded from specially formulated polyethylene to form a durable lamina
resistant to sewage, mineral acids and alkalis, solvents and weathering.
3 Slip bearings shall be applied in two layers with the bottom layer bonded to the substrate
with a high quality solvent borne adhesive based on polychloroprene rubber. The substrate
shall be clean and free from deleterious materials such as form oil or curing compounds and
surface laitance. The surface shall be level and even along the full length of the joint
4 The applied loads for slip bearings shall not exceed 0.7 MPa.
12.5 WATERSTOPS
12.5.1 General
2 PVC waterstops shall be suitable for storage, handling, installation and service within a
range of 15 °C to 65 °C.
12.5.2 Waterstops
1 The waterstop shall be a high performance system forming a continuous network as shown
on the Drawings.
2 Site jointing is to be limited to butt joints and shall be performed strictly in accordance with
the manufacturer’s instructions.
QCS 2010
QCS 2010 Section 5 Part 12 Joints Page 7
3 Centrally placed waterstops shall employ centre bulbs/shutter stop with ribs on the web
sections.
4 Externally placed waterstops shall have ribs on either side of the centre of the waterstop.
The water bar used at the location of expansion joints shall have a bulb in the centre to
accommodate the movements.
6 The minimum test performance data for PVC waterstops shall be as follows:
Tensile strength >12 MPa
Elongation at break 300 %
Hardness Shore ‘A’ 80 to 90
1 Butyl rubber waterstops shall have the properties stated in Table 12.1 when tested in
accordance with BS 903.
Table 12.1
2 Butyl rubber waterstops shall be suitable for storage, handling, installation and service within
a temperature of 0 °C to 40 °C
1 Where active sealing is required for critical areas, waterstops shall be hydrophilic polymer
modified chloroprene rubber strips. The rubber strips shall conform to the following
properties as applicable:
(a) Water pressure resistance : 5 Bar (50 m)
(b) Expansion in contact with water : 2 x original SRE
(c) : Reversible
(d) Application Temperatures : - 30 to + 70 °C
END OF PART
QCS 2010
QCS 2010 Section 5 Part 13 Inspection and Testing of Page 1
Hardened Concrete
13. INSPECTION AND TESTING OF HARDENED CONCRETE ........................ 2
QCS 2010
QCS 2010 Section 5 Part 13 Inspection and Testing of Page 2
Hardened Concrete
13. INSPECTION AND TESTING OF HARDENED CONCRETE
13.1 GENERAL
13.1.1 Scope
1 This Part of the specification covers the inspection, sampling and testing of hardened
concrete.
13.1.3 Submittals
1 The Contractor shall submit to the Engineer his quality assurance procedures for the
particular parts of the testing work that will be carried out.
2 The Contractor shall submit for the Engineer’s approval the curriculum vitae (CV) of the
supervisor proposed for the work.
3 The Contractor shall through testing agency prepare a factual report that identifies the test
methods used and the test results. The report shall also identify any unusual results or
pertinent information relating to the testing. The report shall be presented in hard and
electronic copies.
4 For each of the test results the Contractor shall identify the precision or repeatability of the
particular sampling and testing method. This shall be as given from experience of the
particular test by the laboratory or as expected from information in the particular test
standard.
5 In-place tests will be valid only if the tests have been conducted using properly calibrated
equipment in accordance with recognized standard procedures and acceptable correlation
QCS 2010
QCS 2010 Section 5 Part 13 Inspection and Testing of Page 3
Hardened Concrete
between test results and concrete compressive strength has been established and is
submitted.
6 Non-destructive tests shall not be used as the sole basis for accepting or rejecting concrete,
but they may be used to “evaluate” concrete when the standard-cured strengths fail to meet
the specified strength criteria
1 All field and laboratory testing of concrete shall be carried out by an independent laboratory
approved by the Engineer.
1 If the 28 d works test cubes as defined in clause 6.6 of this Section fail to meet the minimum
criteria, the Engineer shall direct the Contractor to carry out in-place methods to estimate the
concrete strength by non-destructive testing, in-situ drilling of concrete cores or load testing.
2 The parts or elements of the structure made from the defective batch or batches of concrete
as represented by the works test cubes shall be identified by the Engineer and based on this
information the Engineer shall instruct the Contractor on the required number and position of
concrete cores.
3 The Engineer shall review the concrete core test results in conjunction with BS EN 13791 or
ACI 318 whichever is applicable to the structural design.
4 Based on this assessment the Engineer shall decide the acceptability of the concrete in the
structural element and may either:
(a) accept the concrete
(b) instruct that certain remedial works are carried out
(c) instruct that the element is replaced.
13.1.6 General Fieldwork Requirements
1 The Contractor shall make all arrangements to provide safe stable access to testing
locations.
2 When gaining access to testing locations and whilst testing the Contractor shall take care
not to damage the structure or leave it in an untidy or unclean state.
3 The Contractor shall take precautions to ensure that cooling water from concrete
coring/other operations is discharged such as not to cause a mess or damage the interior or
exterior parts of the structure.
4 The Contractor shall be responsible for arranging the water supply required for testing.
5 The Contractor shall arrange for a suitable power supplies. Where testing is being carried
out on an occupied structure a power supply from the building services may not available
and the Contractor shall make arrangements for power supply and extension leads of
adequate length.
QCS 2010
QCS 2010 Section 5 Part 13 Inspection and Testing of Page 4
Hardened Concrete
6 The Contractor shall appoint a qualified field supervisor to co-ordinate and manage the field
work. The supervisor shall have not less than five years experience of such work.
7 Before starting the work, the Engineer with the Contractor’s supervisor will mark the
positions where field testing is to be carried out. A unique referencing system to identify each
sample or testing location will be adopted, and this will either be referenced on sketch plans
or drawings or by a detailed description used throughout the report to identify test locations.
8 If testing is being carried out on an occupied structure the Contractor shall co-ordinate with
the owner or operator of the structure to arrange the detailed programme for the works and
gain access to the various parts of the structure.
9 As soon as laboratory test results are available these shall be submitted by hand or faxed to
the Engineer in draft form. The testing laboratory, or technical bureau assigned by the
10 All core holes, dust sample holes and exploratory investigation areas shall be reinstated with
a proprietary non shrink cementitious repair mortar. The preparation of the hole or area
before reinstatement shall be carried out as per the recommendation of the repair mortar
supplier.
11 Before filling any core holes, dust sample holes or exploratory investigation areas, the
Contractor shall allow the Engineer time to inspect these areas and obtain written
confirmation from the Engineer before filling.
13.2.1 General
1 The drilling and testing of cores shall be carried out in accordance with BS EN 13791 & BS
EN 12504-1, or GSO ISO 1920-6 or ASTM C42 and ACI 214.4 whichever is applicable to the
structural design.
2 All of the supplementary information listed by the relevant standards shall be included in the
test report with photographs of the cores.
3 An assessment of in-situ compressive strength for a particular test region shall be based on
at least 3 cores. Consideration shall be given to any structural implications resulting from
taking cores. The diameter of concrete core shall be at least 100 mm for strength evaluation
unless clear spacing of reinforcement is less than 100 mm and approved by Engineer.
4 The preferred minimum core diameter is three times the nominal maximum size of the
coarse aggregate, but it shall be at least two times the nominal maximum size of the coarse
aggregate
5 The Engineer will advise the required number and locations of cores. If the results of the
initial coring are inconclusive, the Engineer may instruct that further cores be taken at certain
locations.
6 Unless otherwise directed by the Engineer, the Contractor shall ensure that coring does not
cut through any reinforcing steel. The required diameter and depth of concrete cores shall
be as stated in table 13.1
QCS 2010
QCS 2010 Section 5 Part 13 Inspection and Testing of Page 5
Hardened Concrete
Table 13.1 Minimum Depth of Sampling of Concrete for Testing Purposes1 (ASTM C823)
1 The requirements of table 13.2.1 may not provide the quantities or dimensions of samples
that are required for all tests, in that case, the necessary additional quantity of concrete in
pieces of appropriate minimum size should be taken at each sampling location.
2 When suspended slabs are cored, it is desirable to leave the lower 25 mm uncored, so as
not to lose the core by its falling from the barrel and to make it easier to patch the core hole.
1 Before beginning coring operations the Contractor shall use a proprietary cover meter to
identify the position of steel reinforcing bars at the testing location.
2 The Engineer may instruct that the core is taken through the concrete without hitting any
reinforcement or the Engineer may instruct that the core is taken in a position where it is
expected reinforcement will be cut in order to provide a sample of the reinforcement to check
its condition. The locations of all drilling points shall be chosen so that the core contains no
steel parallel to its length.
3 Before capping, the core shall have a length of at least 95 % of its diameter. Once prepared
for test the core shall have a length at least equal to the diameter and not more than 1.2
times its diameter.
4 Cores of both 100 mm and 150 mm nominal diameters may be tested provided that the
aggregate size does not exceed 20 mm and 40 mm respectively. Where possible 150 mm
cores should be taken to reduce the variability due to drilling and increase the reliability of
the testing, unless reinforcement is congested and the use of 100 mm cores will reduce the
possibility that the core will contain steel or it is necessary to restrict the sampling to a length
of less than 150 mm.
5 Where the size of the section precludes the use of 100 mm or 150 mm cores, smaller cores
may be used with the permission of the Engineer.
6 During drilling operations, a log of observations that may affect the interpretation of core
samples shall be prepared.
7 If instructed by the Engineer, immediately after the core has been cut and removed and the
structure a carbonation test will be carried out by using a 1 or 2 % solution of
phenolphthalein poured over the cut surface. A photograph shall be taken of the cut core
with the phenolphthalein solution applied to provide a record of the test.
QCS 2010
QCS 2010 Section 5 Part 13 Inspection and Testing of Page 6
Hardened Concrete
8 If during the drilling of the core, the core collapses due to weak honeycombed or defective
concrete, the Contractor shall stop the drilling operation and carry out testing at an adjacent
location as advised by the Engineer. If when testing at the second location, the core again
breaks due to honeycombed or defective concrete the freshly cut core shall be retained for
reference and a note made of the condition.
1 The compressive strength of field concrete cores shall be assessed in accordance with BS
EN 13791.
2 The details of the concrete core in accordance with BS EN 13791 shall be recorded and two
photographs on either side of the core taken.
4 Before carrying out the compressive strength testing of the cores, the Contractor shall inform
the Engineer to allow him to witness the testing if required.
5 Crushed core samples shall be retained by the laboratory and only disposed of after written
approval by the Engineer.
1 The estimated in-situ strength of the concrete shall be calculated from the core result using
BS EN 13791, ACI 214.4 or ACI 318 whichever is applicable by the structural design.
2 The locations for checking cover and the spacing between measurements shall be advised
by the Engineer based on the objective of the investigation. The Contractor shall carry out
calibrations of the electric magnetic device for a particular bar size to allow the bar diameter
to be measured.
4 The electromagnetic device shall incorporate scale or digital display range and shall be
calibrated in accordance with BS 1881 Part 204. When calibrated in this manner the
indicated cover to steel reinforcement shall be accurate to within ±5 % or ±2 mm which ever
is the greater over the working range given by the manufacturer.
5 The cover meter shall be used in accordance with the manufacturers instructions and
checks on the zero carried out as specified.
6 The search head shall be traversed systematically across the concrete, and, where
reinforcement is located, rotated until the maximum disturbance with electromagnetic field is
indicated by the meter.
7 The cover to the reinforcement shall be noted along with the axis of the reinforcement. The
cover shall also be recorded on the concrete surface with chalk or a suitable non-permanent
marking pen.
QCS 2010
QCS 2010 Section 5 Part 13 Inspection and Testing of Page 7
Hardened Concrete
8 Care should be taken to avoid interference from other metallic sources or magnetic material.
9 The cover meter checks shall be carried out by an operator with five years experience.
13.4.1 General
1 The ultrasonic velocity test equipment shall be capable of measuring the transit time of a
pulse vibration through concrete. The length of the pulse part between the transducer
equipment shall be measured, and the pulse velocity calculated.
2 Ultrasonic pulse velocity testing shall be carried out in accordance with the provisions of BS
EN 12504-4.
1 Wherever possible direct transmission arrangements shall be used. The transducers shall
be mounted on a specially formed moulded surface.
2 The minimum path length shall be 100 mm for concrete in which the nominal maximum size
of aggregate is 20 mm or less and 150 mm for concrete in which the nominal maximum size
of aggregate is between 20 mm and 40 mm. but the path length shall not be longer than
required to detect small regions of bad concrete.
3 Where concrete contains steel the pulse velocity shall be adjusted in accordance with the
requirement of BS EN 12504-4.
4 Locations that contain reinforcement directly along or close to the pulse paths shall be
avoided.
1 Positions chosen for the test locations shall be clearly and accurately marked on the surface
of the concrete.
2 The surface of the concrete shall be shall be cleaned and free from grit and dust. Path
lengths shall be determined to an accuracy of ±1 % and a suitable couplant (such as grease)
applied to each of the test points.
QCS 2010
QCS 2010 Section 5 Part 13 Inspection and Testing of Page 8
Hardened Concrete
3 Pulse transit times shall be measured by a skilled operator, with a minimum of five years
experience in the use of the equipment.
5 Test results shall be examined and any unusual readings repeated carefully for verification
or amendment.
1 A correlation shall be established between the cube crushing strength of the particular mix
used in the structure and the pulse velocity.
13.5.1 General
1 Testing of concrete surfaces for hardness using rebound hammers shall be carried out in
accordance with BS EN 12504-2.
2 The rebound hammer shall only be used for estimation of concrete strength where a specific
correlation is carried out of the concrete from the structure being tested; this shall be from
works test cubes or cores taken from the structure.
3 The correlation between concrete strength and the rebound number shall be carried out in
accordance with BS EN 12504-2. The precision of the correlation curve between the mean
rebound number and strength shall be stated and this shall be used when reporting any
strength interpretations from surface hardness readings. The use of general manufacturers’
correlation or calibration curve for strength shall not be used.
4 It should be noted that the rebound hammer number only provides information on a surface
layer of approximately 30 mm in depth of the concrete and that this should be quoted in the
test report.
5 The rebound hammer maybe used to establish the uniformity of the finish products or similar
elements in a structure at a constant age, temperature, maturity and moisture condition.
2 The reading shall be on a regular grid between 20 mm to 50 mm spacing over an area not
exceeding 300 mm by 300 mm.
QCS 2010
QCS 2010 Section 5 Part 13 Inspection and Testing of Page 9
Hardened Concrete
3 The mean of each set of readings shall be calculated including abnormally high and
abnormally low results unless there is good reason to doubt the validity of a particular
reading.
4 The coefficient of variation and the standard deviation of the readings shall be reported.
13.5.3 Equipment
1 The rebound hammer shall be a proprietary type that has been used successfully and
serviced for a minimum of five years.
2 The hammer shall comprise of a mass propelled by a spring that strikes a plunger in contact
with the surface.
13.5.4 Reporting
1 The test report shall affirm that the hardness was determined in accordance with BS EN
12504-2 and shall provide the following information:
(a) date time and place of test
(b) description of structure and location of test
(c) details of concrete
(d) type of cement
(e) cement content
(f) type of aggregate
(g) type of curing
(h) age of concrete
(i) type of compaction of concrete
(j) forming of surface
(k) moisture condition of the surface
(l) carbonation state of surface
(m) any suspected movement of the concrete under test
(n) direction of test
(o) any other factors that are considered significant in influencing the hardness readings.
2 The details of the rebound hammer correlation with strength including the mean, range,
standard deviation and coefficient and variation of each reading shall also be included.
13.6.1 Sampling
1 The Engineer shall instruct the depth increments over which the dust samples are to be
taken, the types of chemical testing to be carried out and the quantity of sample required.
2 The depth of sample shall not be less than the concrete cover to the reinforcement and at
least 50 mm from the surface of concrete. In presence of reinforcement, the chemical
content shall be tested at least at two levels before and after the depth of reinforcement from
the surface of concrete.
3 To provide uniform samples of cement matrix and aggregate, three separate holes shall be
drilled at one location. The diameter of the holes shall be between 12 and 20 mm.
4 Care shall be taken to discard the material from any render or finish unless this is specifically
required under the investigation.
5 Care shall be taken to ensure that dust increments are accurately measured by marking the
drill bit.
QCS 2010
QCS 2010 Section 5 Part 13 Inspection and Testing of Page 10
Hardened Concrete
6 The dust samples increments shall be carefully transferred to plastic bags and sealed to
avoid contamination. Each sealed bag shall be uniquely identified by the sample
identification and depth increment.
1 Residual split samples of dust from the field investigation shall be retained until the Engineer
has reviewed the chloride test results. The Engineer may instruct that repeat tests are
carried out on certain samples.
2 Chloride testing of concrete dust samples shall be by an acid soluble method in accordance
with BS 1881 Part 124. The results shall be reported to two decimal places.
3 Sulphate testing of concrete dust samples shall be in accordance with BS 1881 Part 124,
END OF PART
QCS 2010
QCS 2010 Section 5 Part 14 Protective Treatments for Concrete Page 1
QCS 2010
QCS 2010 Section 5 Part 14 Protective Treatments for Concrete Page 2
QCS 2010
QCS 2010 Section 5 Part 14 Protective Treatments for Concrete Page 3
14.1.1 Scope
1 This Part covers the materials and application requirements for coatings for concrete
surfaces including epoxy coatings, waterproof membranes, penetrative primers, protective
coatings, and coatings and treatments for specialist applications where there is a harsh
environment.
ASTM C97 ................. Standard Test Methods for Absorption and Bulk Specific Gravity of
Dimension Stone
ASTM C501 ............... Standard Test Method for Relative Resistance to Wear of Unglazed
Ceramic Tile by the Taber Abraser
ASTM C836 ............... Standard Specification for High Solids Content, Cold Liquid-Applied
Elastomeric Waterproofing Membrane for Use with Separate Wearing
Course
ASTM D412 ............... Test Methods for Vulcanized Rubbers and Thermoplastic Elastomers
Tension
ASTM D543 ............... Test Method for Resistance of Plastics to Chemical Reagents
ASTM D570 ............... Test Method for Water Absorption of Plastics
ASTM D638 ............... Test Method for Tensile Properties of Plastics (Metric)
ASTM D746 ............... Test Method for Brittleness Temperature of Plastics and Elastomers
by Impact
ASTM D882 ............... Test Methods for Tensile Properties of Thin Plastic Sheeting
ASTM D1000 ............. Test Method for Pressure Sensitive Adhesive Coated Tapes Used for
Electrical and Electronic Applications
ASTM D1004 ............. Test Method for Initial Tear Resistance of Plastic Film and Sheeting
ASTM D4541 ............. Test Method for Pull Off Strength of Coatings Using Portable
Adhesion Testers
ASTM E96 ................. Test Methods for Water Vapor Transmission of Materials
ASTM E154 ............... Test Methods for Water Vapor Retarders Used in Contact with Earth
Under Concrete Slabs, on Walls, or as Ground Cover
QCS 2010
QCS 2010 Section 5 Part 14 Protective Treatments for Concrete Page 4
14.1.3 Submittals
1 The Contractor shall submit manufacturers' specifications, installation instructions and other
data to show compliance with the requirements of this part of the specification and the
Contract Documents.
2 The Contractor shall submit samples of all materials to be used in the works before delivery
of material to Site. Samples of membrane waterproofing shall be 300 mm square. Samples
of liquid components shall be a minimum of one litre.
3 The Contractor shall submit comprehensive test results for the protective coating system as
per the tests in the specification which shall clearly indicate whether the values are mean
values measured in current production or minimum values which the property does not fall
below.
5 In addition to the test methods identified in this clause of this specification, the Engineer may
require the Contractor to carry out further tests to different standards.
6 If the Contractor wishes to propose a material which has been tested to alternative
standards, the Contractor shall submit correlation tests showing the comparable values of
the two test methods. These test results shall be comprehensive giving full details of the
sample conditioning, preparation, method of test, criteria for assessment etc.
8 The Contractor shall submit a guaranty for the protective coating system and the
workmanship. The guaranty shall be worded to reflect the required performance of the
material and shall be approved by the Engineer. The guaranty shall be worded to include the
phrase ‘the Contractor shall, at the convenience of the Employer, effect all repairs and
replacements necessary to remedy defects all to the complete satisfaction of the Engineer’.
Unless stated otherwise in the contract specific documentation, the performance guaranty
shall be for a period of ten years except for the penetrative primer which shall be for a period
of five years.
9 The use of alternatives may be considered by the Engineer. If the Contractor wishes to
propose such systems, a technical submission shall be made which shall include a
comprehensive justification giving an explanation of why the proposed system is equivalent
or superior to the one designated.
1 The protective coating system shall be supplied by a manufacturer who is certified to the
ISO 9000 series of quality standards. The Contractor shall submit to the Engineer a copy of
the ISO 9000 series certificate that clearly states the scope of the certification.
2 The protective coating system shall be supplied by a manufacturer who provides technical
assistance on the suitability for the application and installation for the material. For the initial
use of the material on Site, the Contractor shall arrange for the technical representative of
the manufacturer to be present to demonstrate the correct use of the material.
QCS 2010
QCS 2010 Section 5 Part 14 Protective Treatments for Concrete Page 5
the Engineer may permit the use of an applicator who is not certified to ISO 9000 if the
applicator works to a quality system that is approved by the Engineer.
1 After approval of all materials and before installation, a prework conference with the
Engineer shall be held at the Site. The meeting shall be attended by representatives of the
Engineer, Contractor, subcontractor, and manufacturer.
1 Materials shall be delivered in their original, tightly sealed containers or unopened packages,
all clearly labelled with the manufacturer's name, brand name, and number and batch
number of the material where appropriate. Materials and equipment shall be stored as
directed in a neat and safe manner.
2 Storage areas shall comply with the manufacturers requirements with regard to shade,
ventilation and temperature limits and shall be located away from all sources of excess heat,
sparks or open flame. Containers of liquid material shall not be left open at any time in the
storage area.
3 Materials not conforming to these requirements will be rejected by the Engineer and shall be
removed from the Site and replaced with approved materials.
4 The Contractor shall deliver materials to Site in ample time to avoid delay in job progress
and at such times as to permit proper co-ordination of the various parts.
14.1.7 Protection
1 The Contractor shall protect the protection system installation from damage during the
construction period so that it will be without any indication of abuse, defects or damage at
the time of completion.
2 The Contractor shall protect the building/structure from damage resulting from spillage,
dripping and dropping of materials.
3 The Contractor shall prevent any materials from running into and clogging drains.
4 Materials and plant shall not be stored on any newly constructed floor without the permission
of the Engineer.
5 Impervious membranes shall be laid as protection to all concrete surfaces in contact with the
soil and shall consist of tanking or similar accepted material, based on soil investigation
report.
QCS 2010
QCS 2010 Section 5 Part 14 Protective Treatments for Concrete Page 6
6 All foundations shall be provided with protection such as epoxy coatings or similar other
accepted equivalents so that concrete is not exposed to harmful effects of soil, chlorides etc.
2 All protective coating systems to be used shall be applied strictly in accordance with the
manufacturers recommendations.
3 The Contractor shall take all necessary precautions against fire and other hazards during
delivery, storage and installation of flammable materials specified herein and comply any
regulations imposed by the Civil Defence Department of the Ministry of the Interior in respect
4 The Engineer shall specify the required final colour of the coating and the Contractor shall
submit samples showing the colour before ordering the materials.
5 Where multiple coatings are required, each shall be clearly distinguishable by colour from
adjacent coats or by any alternative way approved by Engineer.
6 Protective coatings for wastewater applications shall effectively seal the concrete surfaces
against hydrogen sulphide and its derivatives, and chlorine attack. Additionally they shall
provide reduced permeability to oxygen, carbon dioxide and water vapour. Materials shall
be applied in such coats as is necessary to produce absorption rates as measured by the
Initial Surface Absorption Test (ISAT) in accordance with BS 1881-122 of less than the
following (Table 14.0).
Table 14.0
Absorption Rate
Time after ISAT value
starting test 2
(min) (l/m /s)
10 0.25
30 0.17
60 0.10
2
ISAT value for existing concrete surfaces in the splash zone shall be taken as 0.5 ml/m /s.
14.2.1 General
1 The coating shall be a decorative flexible high solids, epoxy polyurethane coating applied in
two coats to a dry film thickness of 400 µm minimum.
QCS 2010
QCS 2010 Section 5 Part 14 Protective Treatments for Concrete Page 7
1 The surface of the concrete shall be free from oil, grease, loose particles, decayed matter,
moss or algae growth and general curing compounds. All surface contamination and surface
laitance shall be removed by high pressure water jetting or sweep blasting.
2 Blow holes and areas of substantial pitting shall then be filled with a solvent free thixotropic
epoxy resin fairing coat. The mixing and application of this coat shall be in accordance with
the product manufacturer’s recommendations.
14.2.3 Materials
1 External above ground coating materials shall provide protection against chlorides and
carbonation, and be UV and abrasion resistant.
2 The above ground coating shall be applied over the below ground coating and shall continue
for a minimum of 150 mm above the ground level.
4 The finished coating shall be pinhole free and have a total minimum dry film thickness of
400 µm.
5 The materials used in the coating system shall comply with the following requirements or
equivalent testing standards:
14.2.4 Application
1 Where required by the Engineer, trial areas not exposed in the finished work shall first be
treated using the selected materials.
2 The exposed concrete surfaces as defined in the documents or as agreed with the Engineer
shall be treated with the material.
3 The coating shall be applied by spray, roller or brush to achieve a finish acceptable to the
Engineer.
4 In all operations of storage, mixing and application, the Contractor is to comply with the
health and safety recommendations of the manufacturer and governing authorities.
QCS 2010
QCS 2010 Section 5 Part 14 Protective Treatments for Concrete Page 8
14.3.1 General
1 This Subpart covers the use of waterproof membrane for general protection to buried
concrete.
2 Where indicated on the Drawings or directed by the Engineer, concrete in contact with the
ground shall be protected by a preformed flexible self-adhesive bituminous type membrane.
3 The laying, lapping and sealing of the membrane shall be in accordance with the
manufacturer’s instructions.
2 Primer for Sheet Membrane: As recommended by the manufacture of the sheet membrane.
1 The material shall be suitable for use in the Gulf region the compound shall be specially
formulated for hot climates and shall have proven experience in the Middle East.
2 The waterproofing material shall conform to the standards detailed in Table 14.1
Table 14.1
Waterproof Membrane Property Requirements
14.3.4 Application
QCS 2010
QCS 2010 Section 5 Part 14 Protective Treatments for Concrete Page 9
2 Boards shall be bonded onto position with high quality solvent borne contact adhesive based
on polychloroprene rubber.
3 The Contractor shall co-ordinate the installation of waterproofing membrane with floor
drains, equipment bases and other adjacent work and mask adjacent work to prevent soil
marks.
4 Areas where waterproofing is applied shall be protected from all traffic and where necessary
backfilling. All damage to finished portions of the waterproofing membrane shall be either
repaired or replaced, or both, in a manner acceptable to the Engineer.
1 The system shall be a penetrating hydrophobic treatment that protects concrete from both
water and chloride intrusion, while permitting water vapour transmission.
2 The treatment shall significantly reduce the absorption of water and water borne salts but
allow the transmission of water vapour from the substrate.
3 The treatment shall not produce any discoloration of the substrate and shall have excellent
resistance to weathering.
14.4.2 Material
1 The material shall be a low viscosity silane-siloxane system which penetrates deeply into a
porous substrate and reacts to produce a bonded hydrophobic lining to the pores.
2 The material shall be resistant to petrol, oil, and atmospheric contaminants such as car
exhaust fumes and industrial exhausts.
3 The water absorption shall not be more than 1 % when tested to ASTM C97 or equivalent.
1 The surface shall be dry, free from oil and grease, loose particles, decayed matter, algae
growth and curing compounds.
2 If the concrete surface is newly cast and has a very smooth finish, the surface shall be
roughened by sand or grit blasting, water blasting or some mechanical means. The Engineer
shall decide if this means of preparation is required.
3 Moss or algae growth on the surface shall be removed using a proprietary fungicidal wash in
accordance with the manufacturer’s recommendations.
4 Concrete finishing required shall be completed before the application of the treatment.
5 Cracks of width greater than 0.2 mm shall be filled in accordance with the manufacturer’s
recommendations.
14.4.4 Application
1 Unless directed otherwise by the Engineer the treatment shall be applied a minimum period
of 24 h after the wet curing period, and shall be surface dry.
2 The Contractor shall carry out tests to verify the depth of penetration of the material. These
tests shall be carried out on specimens of the actual mix design and shall use coloured dyes
to trace the penetration of the material.
QCS 2010
QCS 2010 Section 5 Part 14 Protective Treatments for Concrete Page 10
3 Where fine cracking has occurred in the concrete (at a width not greater than 0.3 mm for
reinforced concrete and 0.2 mm for water retaining structures) an additional four 'stripe
coats' of the treatment shall be applied before the main treatment.
4 The application of the material on surfaces shall be by a low pressure spray direct from the
can. Under no circumstances should thinning of the material be carried out.
5 The rate of application shall ensure that the surface is completely saturated. The
impregnated coating shall be applied to two or more flood coats each flood coat shall be a
minimum of 0.4 l/m2.
6 The material shall be applied strictly in accordance with the manufacturers instructions and
as follows:
14.5.1 General
1 The coating system shall be used for the protection of new or existing reinforced concrete
structures against carbonation or chloride induced corrosion.
2 The system shall comprise of a penetrating, reactive primer and an acrylic polymer top coat
system to minimise ingress of acidic gases, chlorides and water.
1 Before application, all surfaces must be dry and free from oil, grease, loose particles,
decayed matter, moss or algae growth and general curing compounds.
2 All such contamination and laitence must be removed by the use of grit blasting, high
pressure water jetting or equivalent mechanical means.
3 Before proceeding to apply the protective coatings, all surfaces which are not to be coated
but which may be affected by the application of the coating shall be fully masked and, in
particular, flora and fauna shall be protected.
4 Blow holes and areas of pitting shall be made good with a one part modified cementitious
material and allowed to cure in accordance with the manufacturer's recommendations. In
particular, the application shall be in accordance with the manufacturer's recommendations,
with respect to the maximum application thickness.
1 The materials are required to provide in-depth protection against carbonation and chloride
penetration whilst permitting water vapour transmission from the concrete.
QCS 2010
QCS 2010 Section 5 Part 14 Protective Treatments for Concrete Page 11
2 The primer shall be a low viscosity silane-siloxane system which penetrates deeply into a
porous substrate and reacts to produce a bonded hydrophobic lining to the pores.
3 The material employed for the coating shall comply with the following requirements or
equivalent testing standards:
4 Where test methods are not specified, the procedure for establishing compliance with the
above criteria shall be agreed with the Engineer.
1 The coating system shall be two components polyamide coal tar epoxy with excellent
chemical resistance properties.
2 The material shall comply with the following requirements or equivalent testing standards:
3 Where test methods are not specified, the procedure for establishing compliance with the
above criteria shall be agreed with the Engineer.
QCS 2010
QCS 2010 Section 5 Part 14 Protective Treatments for Concrete Page 12
1 The coating system shall be two components high build, non-toxic, solvent free, epoxy
coating.
2 The material shall comply with the following requirements or equivalent testing standards:
3 Where test methods are not specified, the procedure for establishing compliance with the
above criteria shall be agreed with the Engineer.
14.5.6 Application
1 Where required by the Engineer, trial areas not exposed in the finished work shall first be
treated using the selected materials. These trial areas shall be noted on the Drawings and
shall be carried out using the type of materials, mixing procedures and applications that will
be used on the contract and shall be approved by the Engineer before the Contractor
commences with the general work.
2 The exposed concrete surfaces as defined in the documents or as agreed with the Engineer
shall be conditioned by the application of a penetrating hydrophobic treatment. The primer
shall be allowed to dry in accordance with the manufacturer's requirements.
3 The Contractor shall then apply two coats of pigmented topcoat in accordance with the
manufacturer's instructions. The finished coating shall be pinhole free and have a total
minimum dry film thickness of 150 µm. The colour and finish is to be as agreed with the
Engineer.
4 The coating shall be applied by spray, roller or brush to achieve a finish acceptable to the
Engineer.
5 In all operations of storage, mixing and application the Contractor shall comply with the
health and safety recommendations of the manufacturer and governing authorities.
14.6.1 General
1 This Subpart covers the supply and installation of sheet liners in reinforced concrete
structures.
2 The liner must be continuous and free of pinholes both across the joints and in the liner
itself.
3 All work for and in connection with the installation of the lining in concrete pipe and structure,
and the field sealing and welding of joints, will be done in strict conformity with all applicable
specifications, instructions, and recommendations of the lining manufacturer.
QCS 2010
QCS 2010 Section 5 Part 14 Protective Treatments for Concrete Page 13
1 The Contractor shall submit to the Engineer for approval the following:
(a) liner schedule
(b) material certifications
(c) test results
(d) material samples
(e) the manufacturer of the lining will submit an affidavit attesting to the successful use
of its material as a lining for sewer pipes and structures for a minimum period of
five years in service conditions recognised as corrosive or otherwise detrimental to
concrete.
14.6.3 Liner Material Requirements
3 All plastic sheets including locking extensions, all joints and welding strips shall be free of
cracks, asperities and other defects that may affect the protective properties of the material.
1 Except at shop welds, all plastic sheet liners and strips shall have the properties shown in
Table 14.3 when tested at 25 °C.
Table 14.3
Properties of Plastic Sheet Liner Strips
Property Requirement
Tensile strength 15 MPa
Elongation at break 200 %
1 s 50 - 60 ±5 (with respect to 10 s
Shore Durometer
35 - 50 ±5)
Weight change ±1.5 %
QCS 2010
QCS 2010 Section 5 Part 14 Protective Treatments for Concrete Page 14
Table 14.4
Plastic Sheet Liner Minimum Dimensions
1 Locking extensions (T-shaped) shall be of the same materials as that of the liner and shall
be integrally extruded with the sheet.
3 Sheets not used for shop fabrication into larger sheets shall be shop tested for pinholes
using an electrical spark tester set at 9000 V per 1.0 mm thickness of lining minimum. Holes
shall be repaired and retested.
14.6.7 Installation
1 Installation of the lining, including preheating of sheets in cold weather and the welding of all
joints, shall be performed in accordance with the recommendations of the manufacturer.
2 The lining to be held snugly in place against inner forms by means of steel banding straps or
other means recommended by the manufacturer.
3 Concrete that is to be poured against the lining shall be vibrated, spaded, or compacted in a
careful manner to protect the lining and produce a dense, homogenous concrete, securely
anchoring the locking extensions into the concrete.
4 In removing forms care shall be taken to protect the lining from damage. In particular:
(a) sharp instruments not to be used to pry forms from lined surfaces.
(b) when forms are removed, any nails that remain in the lining to be pulled, without
tearing the lining, and the resulting holes clearly marked.
(c) form tie holes to be marked before ties are broken off and all areas of serious
abrasion or damage shall be marked.
5 All nail and tie holes and all cut, torn, and seriously abraded areas in the lining shall be
patched as follows:
(a) patches made entirely with welding strip to be fused to the liner over the entire patch
area
(b) larger patches may consist of smooth liner sheet applied over the damaged area with
adhesive
(c) all edges must be covered with welding strip fused to the patch and the sound lining
adjoining the damaged area.
6 Hot joint compounds, such as coal tar, shall not be poured or applied to the lining.
7 The Contractor shall take all necessary measures to prevent damage to the installed lining
from equipment and materials used in or taken through the work.
QCS 2010
QCS 2010 Section 5 Part 14 Protective Treatments for Concrete Page 15
1 Samples taken from sheets, joints or weld strips shall be tested to determine material
properties. Determination of tensile strength and elongation shall be in accordance with
ASTM D 412 using Die B. Determination of indentation hardness shall be in accordance with
ASTM D 2240 using a Type D Durometer, except that a single thickness of material and
indentation hardness shall be made on 25 mm by 75 mm specimens. Thickness of
specimens shall be the thickness of the sheet or strip.
2 The measurement of initial physical properties for tensile strength, weight, elongation and
indentation hardness shall be determined before chemical resistance tests.
3 Chemical resistance tests shall be carried out to determine the physical properties of the
specimens after exposure to chemical solutions. Test specimens shall be conditioned to
5 Pull test for locking extensions: Liner locking extensions embedded in concrete shall
withstand a test pull of at least 18 kN/m, applied perpendicularly to the concrete surface for a
period of 1 min, without rupture of the locking extensions or withdrawal from embedment.
This test shall be made at a temperature between 21 °C to 27 °C inclusive.
6 Shop-welded joints: Shop-welded joints, used to fuse individual sections of liner together,
shall be a least equal to the minimum requirements of the liner for thickness, corrosion
resistance and impermeability. Welds shall show no cracks or separations and shall be
tested for tensile strength. Tensile strength measured across the welded joint in accordance
with ASTM D 412 using Die B shall be at least 15 MPa. Test temperature shall be 25 ± 3 °C
and the measured minimum width and thickness of the reduced section shall be used.
7 Spark test: All liner shall be shop tested for holes with a spark tester set to provide from
15 000 to 20 000 V. Sheets having holes shall be satisfactorily repaired in the shop before
shipment from the manufacturer’s plant.
8 The Contractor shall provide the Engineer with certified copies of test reports before the
shipment of the product to the Site.
Table 14.5
Chemical Resistance Tests
QCS 2010
QCS 2010 Section 5 Part 14 Protective Treatments for Concrete Page 16
1 Liner sheets to be closely fitted and properly secured to the inner forms.
(a) sheets that are to be cut to fit curved and warped surfaces shall use a minimum
number of separate pieces
(b) a 50 mm wide water resistant tape or welding strip shall be welded on the back of butt
joints to prevent wet concrete from flowing around the edges.
2 Unless otherwise shown on the Drawings, the lining will be returned at least 75 mm at the
surfaces of contact between the concrete structure and items not of concrete and
(a) the same procedure will be followed at joints where the type of protective lining is
changed or the new work is built to join existing unlined concrete
(b) at each return, the returned liner will be sealed to the item in contact with the plastic
1 Field joints and Lining at joints shall be free of all mortar and other foreign material and shall
be clean and dry before joints are made.
2 All welding is to be in strict conformance with the specifications of the lining manufacturer.
1 All surfaces covered with lining, including welds, will be tested with an approved electrical
holiday detector with the instrument set at 9000 V per 1.0 mm of lining minimum:
(a) all welds shall be physically tested by a non-destructive probing method
(b) all patches over holes, or repairs to the liner wherever damage has occurred.
2 Each transverse welding strip which extends to a lower edge of the liner will be tested by an
approved testing agency at the cost of the Contractor.
(a) the welding strips will extend 50 mm below the liner to provide a tab.
(b) a 5 kg pull will be applied to each tab. The force will be applied normal to the face of
the structure by means of a spring balance
(c) liner adjoining the welding strip will be held against the concrete during application of
the force
(d) the 5 kg pull will be maintained if a weld failure develops until no further separation
occurs.
(e) defective welds will be retested after repairs have been made
(f) tabs shall be trimmed away neatly by the installer of the liner after the welding strip
has passed inspection.
(g) inspection will be made within two days after joints has been completed in order to
prevent tearing the projecting weld strip and consequent damage to the liner from
equipment and materials used in or taken through the work.
QCS 2010
QCS 2010 Section 5 Part 14 Protective Treatments for Concrete Page 17
2 Surface preparation:
(a) Concrete Condition: Concrete surfaces shall be structurally sound and cured at least
0
14 days at 20 C and 50% relative humidity or equivalent before coating.
(b) Surface Contamination: Any form release waxes or oils, curing agents, concrete
hardeners or other contaminants shall be completely removed prior to coating.
Solvent cleaning may be required to remove visible deposits of oil, grease or other
contaminants. The surface shall be sweep blasted to remove any laitance, glaze or
loose concrete.
(c) Surface Profile: The surface shall be sweep blasted to a 50-micron profile.
(d) Blowholes and Pits: Blowholes and pits shall be filled with an approved patching
(e) Moisture Content: The concrete surface shall have a moisture content not exceeding
20% on the “wood” scale of a Delmhorst Model BDOF moisture meter. Note, this does
not correspond to concrete with a 20% moisture content.
(f) Surface Preparation Inspection: The Contractor shall call the Engineer’s
Representative to inspect prepared surfaces before the start of coating application. All
surfaces to be coated shall be completed dry, free of moisture, dust, grit, oil or any
other deleterious substances at the time the coating is applied.
3 Application:
(a) Equipment: Coatings shall be applied by a two component, 1:1 mix ratio, heated,
airless spray unit.
(b) Ambient Conditions: Coatings shall not be applied if the substrate temperature is less
than 30C above the dew point temperature, or if the relative humidity exceeds 80%.
(c) Preparing the Coating Materials: Thinning or mixing of the resins shall not be
undertaken. Resins shall be stored between 100 C and 350 C at all times under
conditions and temperatures recommended by the manufacturer.
(e) Dry Film Thickness: Coatings shall be applied up to a minimum thickness of 3000
microns.
(f) Non-slip finish: The top surface of benching and platforms shall incorporate silica sand
to form a non-slip surface.
(g) Recoating: Recoating shall be permitted provided the coating has cured for less than
the maximum time for recoating recommended by the coating manufacturer. Where
the coating has cured for more than the recoat time, the coating surface shall be
brush-blasted or thoroughly sanded, followed by dry cleaning such as vacuuming, use
of (dry) air hose or sweeping to remove dirt. All surfaces to be recoated must show a
surface profile sufficient to provide adequate mechanical bond.
(h) Curing: Coated surfaces shall be permitted as long a curing time as practical. The
minimum cure times recommended by the manufacturer shall be met before the
coated surfaces are put into service
(i) Coating Inspection: The Contractor shall call the Engineer’s Representative to inspect
coated surfaces. The finished coating shall be generally smooth and free of sharp
protuberances. Minor sags, dimpling and curtaining shall not be considered cause for
rejection.
(j) Holiday Testing: The Contractor shall demonstrate the continuity of the coating by
testing the whole coated surface with a low pulse electronic holiday detector with a
QCS 2010
QCS 2010 Section 5 Part 14 Protective Treatments for Concrete Page 18
maximum voltage set at 3125 volts per mm of coating thickness. All holidays shall be
marked, repaired and satisfactorily retested.
(k) Repair and Touch-up: The Contractor shall repair all holidays and damage to the
coating due to handling or construction operations. Repair coats shall be applied
strictly in accordance with the manufacturer’s recommendations.
5 Guarantee: The Contractor shall provide the Engineer with a 7-year unconditional guarantee
1. Polyurethane coating materials for use as an internal lining of concrete shall comply with the
following specification.
2. Coating materials shall be delivered to the site in sealed containers that plainly show the
contents, batch number, colour, date of manufacture, and name of manufacturer. Materials
shall be stored on site in enclosures, out of direct sunlight in a ventilated dry area. Care
shall be taken in handling of coating materials to prevent puncture, inappropriate opening or
other action, which may lead to product contamination.
3. The coating material shall be an ASTM-D16 Type V system urethane coating comprising a
polisocyanate resin and a polyol resin mixed in a 1:1 ratio by volume at the time of
application.
5. The polyisocyanate and polyol resins shall have balanced viscosities in their liquid state.
Resins shall not require agitation during use.
(a) Conversion to solids by volume: After mixing the resins, the liquid polyurethanes shall
convert to a cured solid on a 100% basis.
(b) Temperature Resistance: The cured coating shall retain its properties between 00 C
and 600 C.
(c) Adhesion to concrete: The cured coating, when applied without a primer to concrete
which has been abrasive sweep blasted to achieve a profile of 50 microns or greater
will have an adhesion greater than the cohesive strength of the concrete.
(d) Tack-free time: The tack-free time for the coating shall not exceed 5 minutes at 200 C.
(e) Cure Time: The coating shall achieve full cure within 48 hours at 200 C.
(f) Specific Gravity: The polyisocyanate resin shall have a specific gravity of no more
than 1.20. The polyol resin shall have a specific gravity of no more than 1.15.
(g) Tensile Strength: The coating shall have a tensile strength of not less than 13.8 Mpa.
(i) Water Vapour Permeability: The water vapour permeability shall not exceed 0.002
perms as performed according to ASTM E-96B at 375 microns.
QCS 2010
QCS 2010 Section 5 Part 14 Protective Treatments for Concrete Page 19
(j) Flexibility Resistance: The coating must have a flexibility capable of passing the 1800
bend test as described by ASTM D-522 using a 25mm mandrel.
7. All coating components shall be packaged in standard containers so as to ensure that within
a period of one year from the date of manufacture they will not gel, liver or thicken
deleteriously or form gas in the closed containers. Each container of separately packaged
component shall be clearly and durably labelled to indicate the date of manufacture,
manufacturer’s batch number, quantity, colour, component identification and designated
name or formula specification number of the coating together with special instructions.
8. Coating repair and touch-up materials shall be obtained from the same manufacturer as the
primary coating and shall be totally compatible with that coating.
END OF PART
QCS 2010
QCS 2010 Section 5 Part 15 Hot Weather Concreting Page 1
15.1 GENERAL...................................................................................................... 2
15.1.1 Scope 2
15.1.2 References 2
15.1.3 Definition of Hot Weather 2
15.1.4 System Description 2
15.1.5 Submittals 3
15.2 PLACING TEMPERATURE ........................................................................... 3
QCS 2010
QCS 2010 Section 5 Part 15 Hot Weather Concreting Page 2
1 This Part covers the precautions to be taken for hot weather concreting for all structural
concrete except blinding concrete, where a minimum compressive strength is specified.
BS EN 1992-1-1 ........ Eurocode 2, Design of concrete structures. General rules and rules for
buildings
BS EN 480................. Admixtures for concrete, mortar and grout. Test methods
BS EN 934................. Admixtures for concrete, mortar and grout
1 The requirements of the following clauses of the specification are applicable during the hot
weather period in Qatar.
2 The hot weather period shall be defined as starting when the maximum ambient air shade
temperature on the Site exceeds 35 °C for three consecutive days. The end of the hot
weather period shall be defined as the period when the maximum air shade temperature is
below 35 °C on three consecutive days.
3 The Contractor shall establish a thermometer on Site that records the ambient air shade
temperature. The thermometer shall be established at a position to provide representative air
temperature for the Site conditions. If requested by the Engineer the Contractor shall
arrange for the calibration of the Site thermometer.
4 Hot weather conditions include the existence of one or more of the following conditions:
(a) high ambient air temperature
(b) low humidity
(c) high solar radiation
(d) high wind speeds.
(e) Calculations or experiments showing that the dry bulb temperature of the placed
concrete, taking into consideration the heat of hydration of cement, exceeds 38ºC and
that the rate of water evaporation exceeds 980 g/m2 per hour.
15.1.4 System Description
1 The Contractor shall undertake hot weather concreting procedures that are effective in
controlling the following potential problems associated with concreting in hot weather:
(a) increased water demand of the mix
(b) increased rate of slump loss
(c) increased rate of setting
(d) increased tendency for plastic shrinkage cracking
(e) decreased long-term strength
QCS 2010
QCS 2010 Section 5 Part 15 Hot Weather Concreting Page 3
1 The Contractor shall prepare weekly in advance his proposed concreting programme
showing the quantities to be placed and the anticipated placing hours.
2 At least one month before the start of the hot weather period the Contractor shall submit his
specific proposals for the control of the concrete temperature for the constituent materials;
cement, water aggregates.
3 Where required the Contractor shall submit to the Engineer his proposals for the use of
2 The maximum temperature of concrete at the point of placing shall not be more than 32 °C.
4 The temperature of each truck of concrete shall be measured using either a glass, dial type
or electronic thermometer, just before the placing of the concrete and the temperature
recorded on the delivery ticket. The maximum temperature at placing shall apply to the
entire load of concrete in the truck or conveyer.
5 The Contractor shall allow for the increase in concrete temperature in the period from
dispatch from the plant while in transportation or whilst awaiting placement on Site and take
adequate measures to ensure the maximum temperature is not exceeded.
2 The Contractor shall arrange concrete pours such that the programme of works can be
achieved without concreting during the period from 10:00 hours to 17:00 hours.
3 The Contractor shall nominate one member of his staff to be the co-ordinator for the supply
of concrete. The co-ordinator’s responsibilities shall include ensuring the batched rate
matches that of delivery and placement and the preparations needed before commencing a
concrete pour.
3 Under no circumstances will the addition of extra water that increases the water cement ratio
be permitted during hotter weather.
QCS 2010
QCS 2010 Section 5 Part 15 Hot Weather Concreting Page 4
4 All concrete materials and proportions used in periods of hot weather shall be those that
have a satisfactory record of use in such conditions.
15.5.1 General
1 The Contractor’s specific proposals for the control of the concrete temperature shall include
extent and type of shading of aggregates, method of chilling mix water and procedures for
batching and mixing, transportation, placing and finishing, curing and protection.
2 These shall include calculations in accordance with ACI 305R, clause 3.1 “estimating
concrete temperature”. The Contractor shall calculate the temperature of freshly produced
15.5.2 Aggregates
1 All practical means shall be employed to keep the aggregates as cool as possible.
2 Stockpiles of aggregates shall be shaded from direct sunlight. Shades shall extend beyond
the edge of aggregate storage areas and stockpile layouts shall be such that direct sunlight
is not incident on the aggregates. Shades shall be constructed to allow access for
mechanical shovels or means of conveyance. Shades and stockpiles shall be constructed so
as to permit the free flow of air over the aggregates. Embedded cooling pipes may also be
used to cool the aggregate.
15.5.3 Water
1 Mix Water shall be cooled by storing in underground tanks or insulated tanks above ground.
2 The water shall be chilled by the use of proprietary chillers or the addition of ice to the water
tank. Measures shall be taken to ensure that ice pieces are not inadvertently deposited
directly into the mixer.
4 Tanks, pipes or trucks used for the storage or transportation of water shall be insulated and
painted white.
5 The mechanical refrigeration equipment and insulated water storage shall be adequate for
the anticipated hourly and daily production rates of concrete during the hot weather period.
6 Mixing water may also be chilled by injection of liquid nitrogen into an insulated holding tank,
such procedures shall be to the approval of the Engineer.
7 Ice shall be completely melted in mixing water prior to adding water to the mixer.
15.5.4 Cement
1 The use of freshly ground cement at very high temperatures is not permitted.
QCS 2010
QCS 2010 Section 5 Part 15 Hot Weather Concreting Page 5
2 The cement shall be kept below the temperature which there is a tendency of false set.
3 Under no conditions shall the temperature of the cement exceed 75 °C when it enters the
mixture.
4 The Contractor shall make arrangements for storage on Site to allow cooling of freshly
ground and delivered cement.
1 Crushed shaved or chipped ice can be used as part of the mixing water for reducing the
concrete temperature.
2 The maximum nominal size of ice particles shall be 10 mm and all the ice must be melted
4 Crushed ice shall be stored at a temperature that will prevent lumps from forming by
refreezing of particles.
5 The batching plant shall incorporate a mechanical system for correctly proportioning and
weighing the ice to be added to the mixture.
6 The quantity of ice shall be deducted from the total batch water.
7 The Contractor shall ensure there are adequate quantities of ice in suitable refrigerated
storage on the Site at the plant to meet the anticipated daily and hourly production rates of
concrete during the hot weather period.
2 Care shall be taken to ensure that the concrete directly adjacent the injection nozzle is not
frozen.
3 The use of liquid nitrogen for cooling concrete shall include a nitrogen supply vessel and
injection facility for the batching plant or one or more injection stations for truck mixers.
4 The system may be set up at the Site for injection just before placing.
5 Proper safety precautions as advised by the supplier of the liquid nitrogen shall be used.
2 Where a truck mixer has been left standing in the sun, the empty drum shall be sprayed with
water and the drum flushed out with cold water before batching. Care shall be taken to
ensure all water is removed from the drum before batching.
3 The temperature of the concrete shall be checked after discharge from the mixer and written
on the delivery ticket. Temperature check shall be carried out at the plant on the concrete
floor for every 50 m3 produced or every hour which ever is the minimum.
QCS 2010
QCS 2010 Section 5 Part 15 Hot Weather Concreting Page 6
15.7 TRANSPORTATION
1 The transportation, placing, compaction and finishing of concrete shall be at the fastest
possible rate. Delivery of concrete to the Site shall be properly scheduled to match the rate
of placement and compaction.
3 However, no further concreting pours shall take place until the Contractor has submitted
revised calculations, in accordance with ACI 305R clause 3.1 to demonstrate that the
maximum temperature will not be exceeded in the future. Before beginning new pours the
temperature of the concrete constituent materials shall be monitored to verify that they meet
the assumptions of the calculations.
2 Evaporation shall be minimised, particularly during the first few hours subsequent to placing
concrete, by suitable means such as applying moisture by fog spraying or any other means
acceptable to the Engineer.
3 All concrete test specimens for strength or other purposes shall be carefully protected and
cured.
5 Specimens shall be kept moist by the addition of water or covering by suitable curing
materials.
6 The exact time of preparation of the specimen on Site shall be noted and the time when it is
transferred to the laboratory. These times shall be written on the test report.
END OF PART
QCS 2010
QCS 2010 Section 5 Part 16 Miscellaneous Page 1
16. MISCELLANEOUS......................................................................................... 2
QCS 2010
QCS 2010 Section 5 Part 16 Miscellaneous Page 2
16. MISCELLANEOUS
16.1 GENERAL
16.1.1 Scope
1 This Part deals with miscellaneous items related to concrete works including pavement
quality concrete, cementitious grout, screeds and repair of concrete.
ASTM C109 ........ Standard Test Method for Compressive Strength of Hydraulic Cement
Mortars (Using 2-in. or [50-mm] Cube Specimens)
ASTM C827 ........ Standard Test Method for Change in Height at Early Ages of Cylindrical
Specimens of Cementitious Mixtures
ASTM C989 ........ Standard Specification for Slag Cement for Use in Concrete and Mortars
ASTM D638 ........ Standard Test Method for Tensile Properties of Plastics
ASTM D2240 ...... Standard Test Method for Rubber Property—Durometer Hardness
BS EN 197-1 ...... Cement. Composition, specifications and conformity criteria for common
cements
BS EN 197-4 ...... Cement. Composition, specifications and conformity criteria for low early
strength blastfurnace cements
BS EN 206-1 ...... Concrete Specification, performance, production and conformity
BS EN 480.......... Admixtures for concrete, mortar and grout
BS EN 934.......... Admixtures for concrete, mortar and grout
BS EN 998.......... Specification for mortar for masonry
QCS 2010
QCS 2010 Section 5 Part 16 Miscellaneous Page 3
16.2.1 Scope
1 This Subpart covers the mix design for concrete used for aircraft aprons and roadworks as
surface slabs, continuously reinforced concrete roadbase, and wet lean mix except cement
bound granular material used as a roadbase or sub-base or as a backfill material for
excavations.
1 Concrete in rigid or composite pavements shall be one of the grades given in Table 16.1
below, in accordance, with the pavement design shown on the Drawings or as directed by
the Engineer.
2 All concrete for use in pavements shall be designed mixes or equivalent standard mixes in
accordance with the relevant clauses of BS 8500 and BS EN 206-1, except where otherwise
specified.
3 Prescribed mixes may be used for rapid construction with the approval of the Engineer
(Table 16.1).
Table 16.1
Pavement Grades
BS 8500 and
Pavement Layer
BS EN 206-1 strength class
Surface Slabs C40
Unreinforced Concrete C40
Jointed Reinforced Concrete C40
Continuously Reinforced Concrete Pavement (CRCP) C40
Continuously Reinforced Concrete Roadbase (CRCR) C40
Ground Beam Anchorages C30
QCS 2010
QCS 2010 Section 5 Part 16 Miscellaneous Page 4
16.2.3 Cement
1 The general term 'cement' in this Part means the materials shown below.
3 The use of a combination of Portland cement and pulverised fuel ash (PFA) is permitted
subject to the approval of the Engineer. In such cases, the Engineer will stipulate the
minimum combined cementitious material content required for the mix. PFA shall be in
accordance with BS 3892.
4 The use of microsilica in the mix designs will be permitted if approved by the Engineer. In
such cases the proportion of microsilica shall be 10 ± 1 % of the Portland cement content.
5 The Engineer will stipulate the minimum combined cementitious material content required for
the mix where PFA or GGBFS are used.
6 The maximum proportion of ground granulated blastfurnace slag with Portland cement shall
be not greater than 65 % of the total cement content for grades up to C30, and 50 % for
C40.
7 In combination with Portland cement, the proportion of PFA by mass to the total cement and
the minimum Portland cement content of the blend shall be advised by the Engineer.
The limit of chloride content of the concrete shall be as stated in BS 8500 and BS EN 206-1.
8 In each cubic metre of fully compacted concrete the minimum cement content shall be
(Table 16.2):
Table 16.2
C40 335
C30 300
C20 (B20) strength is the only requirement
C15 (B15) strength is the only requirement
C10 (B10) strength is the only requirement
16.2.4 Water
1 Water for use in the making and curing of concrete shall conform to the requirements of Part
4 of Section 5.
QCS 2010
QCS 2010 Section 5 Part 16 Miscellaneous Page 5
2 The water content shall be the minimum required to provide the agreed workability for full
compaction of the concrete to the required density, as determined by trial mixes or other
means approved by the Engineer, and the maximum free water:cement ratio shall be 0.45
for grade C40 and 0.5 W/C for grade C30.
16.2.5 Aggregates
2 Aggregates for all pavement concrete shall be natural material complying with BS EN 12620
or aggregate which when crushed complies with the quality and grading requirements of BS
EN 12620.
3 Alternatively coarse aggregate may be crushed air-cooled blastfurnace slag complying with
4 Once the appropriate gradings have been determined and approved they shall not be varied
without the permission of the Engineer.
5 If requested by the Engineer, the aggregate at source shall be tested in accordance with
BS 812 Part 121 and shall have a soundness value greater than 75. Thereafter for routine
testing of such aggregates, the water absorption value of the coarse aggregate shall be
determined as in BS 812 Part 2 or BS EN 1097-3. If the absorption value of the coarse
aggregate is greater than 2 %, the soundness test shall be carried out on the material
delivered to Site.
6 The nominal size of coarse aggregate shall not exceed 40 mm. When the spacing between
longitudinal reinforcement is less than 90 mm, the nominal size of coarse aggregate shall not
exceed 20 mm.
7 The chloride ion content of the aggregate to be used in concrete with embedded metal,
determined in accordance with BS EN 1744-1, clause 7 shall satisfy the requirements of BS
EN 12620.
9 If requested by the Engineer, the Contractor shall carry out tests on the proposed aggregate
combination to check for the possibility of alkali silica reaction. Such tests shall be carried
out in accordance with the procedure laid down in Part 2 of this Section.
16.2.6 Admixtures
1 Plasticisers or water reducing admixtures shall comply with BS 5075, BS EN 480 and BS EN
934. Admixtures containing calcium chloride shall not be used.
2 Other chloride free admixtures may be used with the approval of the Engineer.
1 The total quantity of air in air-entrained concrete as a percentage of the volume of the mix
shall be 5 ± 1.5 % for mixes of nominal aggregate size 20 and be 4 ± 1.5 % for mixes of
nominal aggregate size 40.
2 The air content shall be determined at the point of delivery to the paving plant by a pressure
type air meter in accordance with BS EN 12350-7 or EN 12350-7, at the rate of one
determination per 300 m2 of slab or at least six times per day whichever is the greater, in
conjunction with tests for workability and strength. For areas less than 300 m2, the rate shall
be at least one determination to each 20 m length of slab or less constructed at one time or
QCS 2010
QCS 2010 Section 5 Part 16 Miscellaneous Page 6
at least three times per day. If the air content is outside the specified limits, a further
determination shall be made immediately on the next available load of concrete before
discharging. If the air content is still outside the limit, the Contractor shall immediately adjust
the air content of the concrete to improve its uniformity, before further concrete is used in the
Works.
3 The air-entraining agent shall be added at the mixer, by an apparatus capable of dispensing
the correct dose within the tolerance for admixtures given in BS EN 206-1, and so as to
ensure uniform distribution of the agent throughout the batch during mixing.
16.2.8 Density
1 The density of concrete Grades greater than C30 shall be such that without air-entrainment
the total air voids are not more than 3 %. With air entrainment, the total air voids shall be not
2 The density of concrete Grades C20 (B20) or below shall be at least 95 %, of the theoretical
maximum dry density.
16.3.1 General
1 This Subpart covers a general purpose non-shrink cementitious grout. The grout shall be
used to where it is necessary to eliminate shrinkage when filling the void between a base
plate and a substrate such as in the grouting of stanchion bases, anchorage fixings,
including masts, anchor bolts and fence posts.
2 The grout shall be supplied by a reputable construction chemical company as a single pack
prepackaged cement based product which is chloride free.
3 For a particular application, the Contractor shall submit a method statement detailing how
the formwork will be placed and the points where the grout will be poured.
4 Before beginning work on large repetitive works, the Contractor shall arrange for a site trial
of the materials and methods with the suppliers representative being present to train the
Contractor’s personnel in the correct use of the material.
16.3.2 Material
1 The grout shall be suitable for filling gaps of thickness up to 100 mm and shall be free
flowing and non shrink.
2 Positive volumetric expansion shall take place in the plastic and harden stage by means of
gaseous (nitrogen or equivalent) expansion system to avoid shrinkage and cracking.
3 The compressive strength of the grout when tested in accordance with BS EN 12390-3 or
ASTM C109 shall be a minimum of 15 MPa at 3 d, 40 MPa at 7 d and 50 MPa at 28 d.
4 The flexural strength of the grout when tested in accordance with BS 6319 or equivalent
shall be a minimum of 2 MPa at 3 d, 7 MPa at 7 d and 9 MPa at 28 d.
5 The grout shall exhibit a high early strength gain yet not be subject to cracking or other
detrimental effects.
6 At ambient temperatures above 35 °C, cool water shall be used for mixing the grout before
placing.
QCS 2010
QCS 2010 Section 5 Part 16 Miscellaneous Page 7
16.3.3 Workmanship
1 The storage handling and pouring of the grout shall be in strict accordance with the
manufacturer’s instructions.
2 The substrate surface shall be free from oil grease or loose or partially bonded material.
3 If the concrete surface is defective or has laitance it shall be cut back to a sound base.
4 Bolt holes and fixing pockets shall be blown clean of dirt or debris.
5 The substrate shall be soaked with fresh potable water before grouting, although
immediately before grouting, free water shall be removed and blown out of bolt holes or
pockets.
7 Base plates and metallic items shall be clean and free from oil, grease, or scale.
8 Vent holes shall be provided to allow the release of air from isolated spots.
9 Formwork shall be made leak proof by the use of form rubber strip or mastic sealant
between the constructive formwork and joints. Formwork shall extend above the required
pour height and if necessary shall be extended to allow a hydrostatic head to aid placement.
10 The grout shall be mixed mechanically with a slow speed drill fitted with a high-shear mixer.
11 The quantity of water to be added to the preweighed bags shall be enough to give the
desirable consistency as trowelable or flowable.
13 The grout shall be placed within the time limit specified by the manufacturer depending on
the actual application temperature.
14 Grout shall be poured from one side and it shall be verified that the grout has flowed under
all of the base plate with no voids. Pouring from several sides shall not be permitted.
15 Exposed areas of grout shall be thoroughly cured in accordance with Part 10 of this Section.
16.4 SCREEDS
16.4.1 Scope
1 This Subpart covers screeds that provide by means of a layer of mortar a level surface in
flooring applications and to provide falls on flat concrete roofs.
16.4.2 General
2 The screeds shall be suitable for receiving surface finishes which may arrange from thin
flexible sheeting to ceramic tiling. The screed is not intended to be the final wearing surface.
3 Screed mortars shall generally comprise sand and cement modified by additives or
substituted by other materials such as polymers in order to provide specific performance
requirements.
QCS 2010
QCS 2010 Section 5 Part 16 Miscellaneous Page 8
5 Aggregates used for screeds shall not contain deleterious materials such as coal or iron
particles which may affect the finish the surface of the screed.
6 Admixtures for mortar screeds shall assist workability or alter rates of setting and hardening
and shall comply with the appropriate part of BS EN 480 and BS EN 934.
7 Polymer based additives may be used to improve adhesion and strength of thin or featured
screeds, these shall be based on polyvinyl acetate (PVA) styrene bituene rubber (SPR) or
acrylic polymers.
8 Ready to use sand cement screeds shall comply with the material requirements BS EN 998.
10 The interface of the screed in the concrete substrate shall be specified as one of the
following options by the Engineer:
(a) Monolithic with the concrete base: The screed shall be applied within 3 hours of
placing the concrete base.
(b) Bonded to the concrete base: Screed shall be laid onto a concrete base which is
hardened and is subsequently been prepared to receive the screed, the minimum
thickness of the screed shall be 25 mm and the maximum thickness 40 mm.
(c) As an unbonded screed: The screed shall be laid on a separating layer.
(d) As a floating screed: The screed shall be laid on an insulating material.
11 The cement and sand screed mix shall have the minimum amount of water added to give
sufficient workability and allow the material to be thoroughly compacted.
12 Pan type mixes shall be used to ensure efficient mixing of materials, the cement to
aggregate ratio shall be between 1 to 3 and 1 to 4.5 by weight. The mixing of the sand
cement, water and admixtures shall ensure a thorough homogeneous mixture with no balling
up of the cement.
13 Screeds shall be laid either between carefully levelled and trued batons or between strips of
screed laid and compacted to a finished level.
14 For bonded screed where a high degree of bond is required the surface laitance of the
concrete base shall be mechanically removed to expose the coarse aggregate. A thin layer
of neat cement grout shall be applied to the prewetted or dampened concrete and the
screed applied and compacted while the grout is wet.
15 Screeds shall be fully compacted by heavy hand or mechanical tamping. The screed at joints
around the perimeter shall be particularly well compacted to avoid breaking out and curling.
16 Screeds thicker than 50 mm shall be laid in two approximately equal layers; screed shall be
kept protected by waterproof sheeting for at least 7 days after laying.
17 Sheet and non ceramic tiling finishes shall only be applied after the screed has cured and
necessary strength achieved.
18 If requested by the Engineer the Contractor shall carry out a soundness and impact test in
accordance with BS 8203.
QCS 2010
QCS 2010 Section 5 Part 16 Miscellaneous Page 9
19 Screeds shall be laid in bays of a size to minimise thermal moisture contraction. Contraction
or movement joints shall be provided as appropriate, where shown on the drawings or as
directed by the Engineer. Bays shall be laid alternatively.
20 Bay sizes shall be approximately 15 m2 for 100 mm thick screed and 12 m2 for 75 mm thick
screed.
2 CC offer more thermal insulation and a substantially higher fire-rating than conventional
concrete.
4 The required density and strength of the CC shall be specified on the drawings and
approved by the Engineer.
5 The method of production of Cellular Concrete shall be shown on the drawings or directed
by the Engineer. The Contractor shall submit full technical details of the materials and
method of production for the CC along with a list of previous projects where the particular
system has been used.
6 After source approval of the material and system the Contractor shall submit a mix design for
the CLC for the approval of the Engineer. After the review and approval of the mix theoretical
mix design the Contractor shall carry out a trial mix to check the workability of the fresh
concrete and to allow samples to be made for compressive strength and density.
7 The Engineer may also instruct that tests are carried out for abrasion resistance and thermal
insulation properties.
16.6.1 General
1 The extent and nature of the defects in concrete shall be established in accordance with Part
15 of Section 5. Based on these results the Engineer shall confirm the acceptability of the
work and whether remedial works are required.
2 If remedial works are required the Contractor shall submit a detailed method statement
identifying the specific materials to be used and the sequence of activities for the repair.
3 Only proprietary proven materials that form part of a standard repair system shall be used.
2 All areas which are to be topped with epoxy coating shall be repaired using epoxy resin
repair mortar.
QCS 2010
QCS 2010 Section 5 Part 16 Miscellaneous Page 10
1 All large repair areas shall be repaired using high strength free flowing micro-concrete.
BS EN 12390-3 or ASTM
Compressive strength 50 MPa
C109 @ 28 d
Flexural strength BS 4551 or BS 6319 @ 28 d 10 MPa
Anchorage bond BS EN 1992-1-1, BS 8666 Passes
Water penetration DIN 1048 < 10 mm
1 All small repair areas shall be repaired using high build, high strength patching polymer
modified cementitious repair mortar and shall possess the requirements in table 16.4.
Table 16.4
1 The areas of repair shall be marked out and agreed with the Engineer.
2 All honeycombed, loose, cracked or friable concrete in these areas shall be removed until
sound concrete is reached. Due account shall be taken of propping or other instructions
given by the Engineer regarding sequences of removal and repair.
3 The equipment and methods used to break out the concrete shall be such that no reinforcing
steel or other embedded items such as conduits, lifting sockets, or other inserts are
loosened or damaged unless so directed by the Engineer.
QCS 2010
QCS 2010 Section 5 Part 16 Miscellaneous Page 11
5 The prepared void shall be profiled so that entrapment of air is avoided during the repair
process using fluid micro-concrete.
6 The minimum depth of repair shall be 40 mm throughout. The perimeter of the area to be
repaired shall first be cut to a depth of 10 mm using a suitable tool. Feather edges will not be
accepted.
7 The prepared concrete surface shall be sound and clean and free of loose particles, dust
and debris.
9 Reinforcement damaged during the removal of concrete or the preparation process shall, if
required by the Engineer, be repaired or replaced.
10 Adequate formwork shall be provided in accordance with of Part 9 of this Section. This shall
be securely fixed to withstand the hydraulic pressures of the fluid micro-concrete repair
material without distortion or movement during placement.
11 The formwork shall be watertight at all joints between panels and between the formwork and
the existing concrete surface so as to prevent grout leakage.
12 The formwork shall be constructed from appropriate materials as agreed with the Engineer
to achieve the required finish.
13 Formwork surfaces that are to be in contact with the repair micro-concrete shall be treated
with a suitable mould release agent. This shall be used in accordance with the
manufacturer's recommendations.
14 The entry point of the feed pipe into the form shall be at the lowest point of the void.
Sufficient hydrostatic head or pumping pressure shall be maintained to ensure that the void
is filled completely and no air remains entrapped.
15 Where necessary, provision shall be made for controllable bleed points to prevent air
entrapment and enable the extent of flow of the repair material to be assessed.
16 The formwork shall be inspected by the Engineer and, if approved, filled with clean water
which demonstrates that the formwork is grout-tight and saturates the prepared concrete
surfaces. The formwork shall be then be completely drained and resealed
17 In situations where the completed repair will be subjected to constant immersion an epoxy
bonding agent shall be applied in accordance with the manufacturers’ instructions.
18 Both the Compressive strength and Flexural strength shall be at a water:powder ratio of 0.18
and tested at 20 oC
19 The thermal conductivity and the elastic modulus of the repair material shall be compatible
with the host concrete.
20 If requested by the Engineer, recent test results of the material for the following properties
shall be submitted:
(a) thermal conductivity
(b) elastic modulus, BS 1881
(c) expansion characteristics, ASTM C 827, CRD 621-82A
(d) flow characteristic, UK DOT BD 27/86 paragraph 4.6 B.
QCS 2010
QCS 2010 Section 5 Part 16 Miscellaneous Page 12
21 The micro-concrete shall be mixed and placed in accordance with the manufacturer's
recommendations, particularly with regard to water content, mixing equipment and placing
time.
22 As far as possible the placing of the micro-concrete shall be continuous. The mixing
operation shall be timed so that there is minimal interruption in the material flow. If, however,
placing is interrupted, the operation shall recommence as soon as possible while the repair
material retains its flow characteristics.
23 The formwork shall not be removed until the repair micro-concrete has achieved a
compressive strength of at least 10 MPa or as directed by the Engineer.
24 Immediately after removal of the formwork the repair area shall be cured in accordance with
Part 10 of Section 5.
1 This clause of the specification covers non-active cracks within concrete elements caused
by shrinkage or other structural movement. Non-active cracks shall be injected with a low-
viscosity epoxy resin to fill and seal the crack and restore the structural integrity.
2 Before to starting the injection operation it shall be established by testing and investigation
work that cracks manifest within concrete elements due to either or both shrinkage or
structural movement are non-active.
3 The extent of the cracks to be filled will be as directed by the Engineer. The cracks to be
filled shall be marked out in detail on the concrete elements by the Contractor and agreed
with the Engineer before proceeding.
4 The extent of the work may be adjusted by the Engineer as the project proceeds, according
to the conditions found.
5 Grease, oil or other contaminants shall be removed. Algae and other biological growth shall
also be removed by scrubbing with bactericide or detergent and clean water. If necessary,
wire brushes shall be used.
6 Loose or spalling areas of concrete, laitance, traces of paint or other coating materials within
the marked out scope of the work shall be removed.
7 All cracks shall be thoroughly cleaned out using clean, oil-free compressed air. Both the
concrete surface and the cracks shall be allowed to dry thoroughly before continuing.
8 The injection nipples shall be fixed at intervals along the length of each crack. The distance
between each nipple will depend on the width and depth of the crack.
9 Spacing shall be close enough to ensure that the resin will penetrate along the crack to the
next point of injection. This will normally be between 200 mm and 100 mm.
10 Each nipple shall be firmly bonded to the concrete surface by using a sealant. The sealant
shall be supplied in two pans (liquid base and hardener system). The two components shall
be thoroughly mixed together for 3 to 4 min until a putty-like consistency is achieved.
11 The mixed sealant shall be applied to the metal base of each surface-fixed nipple. They shall
be pressed firmly into place and held for several seconds until secure. The mixed sealant
shall be applied around each embedded nipple, ensuring a complete seal is made. In this
way, all the nipples shall be fixed along the length of the crack.
12 In the case of a wall or slab which is cracked all the way through, nipples shall be located on
both sides with those at the back placed at midway points between those it the front.
13 The surface of the cracks between the nipples shall be sealed with a band of sealant 30 to
40 mm wide and 2 to 3 mm thick. Both sides if cracks which go all the way through a wall or
slab shall be sealed in this way.
QCS 2010
QCS 2010 Section 5 Part 16 Miscellaneous Page 13
14 The prepared cracks shall be allowed to cure for 12 to 24 h. At low ambient temperatures
(5 °C to 12 °C) the curing time will be extended and the Contractor shall ensure that the
surface sealant has adequately cured before continuing.
15 One end of the injection hose shall be attached to the lowest nipple on vertical cracks or to
either end of horizontal cracks.
16 Each crack shall be treated in a single, continuous operation. Sufficient material shall
therefore be made ready before the commencement of the work.
17 The Contractor shall to ensure that sufficient cracks are prepared to provide effective use of
the mixed material.
18 The preparation, mixing and application of the materials shall be undertaken in strict
accordance with the manufacturer's recommendations. The Contractor is to ensure that all
necessary tools and equipment are on Site.
Table 16.5
Property Requirement for Epoxy Crack Injection Material
27 Wet cracks shall be injected with a polyurethane foaming crack injection resin to stop the
water flow, followed by the injection of permanent flexible polyurethane injection material.
28 The reaction time between the foaming polyurethane material and the water shall be less
than 30 seconds @ 25oC.
29 The polyurethane injection material shall comply with the following requirements (Table
16.6).
QCS 2010
QCS 2010 Section 5 Part 16 Miscellaneous Page 14
Table 16.6
Property Requirement for Polyurethane Injection Material
QCS 2010
QCS 2010 Section 5 Part 17 Structural Precast Concrete Page 1
QCS 2010
QCS 2010 Section 5 Part 17 Structural Precast Concrete Page 2
1 The work included in this Section comprises furnishing all plant, labour, equipment,
appliances and materials and performing all operations in connection with Structural Precast
Concrete Work.
1 The following standards and other documents are referred to in this Part:
ACI 523.2R ................ Guide for Precast Cellular Concrete Floor, Roof, and Wall Units
ACI 533R ................... Guide for Precast Concrete Wall Panels
ACI 533.1R ................ Design Responsibility for Architectural Precast-Concrete Projects
ACI 543R ................... Design, Manufacture, and Installation of Concrete Piles
ACI 550.1R-09 .......... Guide to Emulating Cast-in-Place Detailing for Seismic Design of
Precast Concrete Structures
17.1.3 Submittals
1 Manufacturer's Literature:
(a) the Contractor shall provide copies of manufacturer's specifications and installation
instructions for each item of proprietary material to be used, showing compliance with
this specification. Information on equipment, embedded items and other accessories
shall also be provided.
QCS 2010
QCS 2010 Section 5 Part 17 Structural Precast Concrete Page 3
2 Design Mixes:
(a) copies of mix designs with support material
(b) the requirements of the mix design shall be in accordance with Parts 6 and 7 of this
Section.
3 Product Design Criteria:
(a) loadings for design:
(i) initial handling and erection stresses
(ii) all dead and live loads as specified on the contract drawings or as required
(iii) all other loads specified for the member where they are applicable.
4 Product Design Calculations:
(a) the design calculations shall be performed by a Structural Engineer experienced in
QCS 2010
QCS 2010 Section 5 Part 17 Structural Precast Concrete Page 4
2 The Contractor may execute this work himself if he can satisfy the Engineer that he has
sufficient experience and expertise in this field. As a minimum the Contractor shall:
(a) provide satisfactory evidence that his tradesmen and their supervisory personnel
engaged in such work have successful experience with work comparable to that
shown and specified
(b) provide details of organised quality control and testing procedures.
17.1.5 Quality Assurance
1 The precast concrete supplier shall have a quality assurance scheme that meets ISO 9000
or equivalent.
2 All work shall be performed to secure for the project homogeneous concrete having the
required strength, surface finish, materials, durability, and weathering resistance, without
planes of weakness or other structural defects, and free of honeycombs, air pockets, voids,
projections, offset of plane and other defacements of concrete.
4 The Contractor shall supervise and co-ordinate all phases of the structural precast concrete
construction process and be responsible for the complete manufacturing process.
5 All methods of manufacture and practices of handling raw materials and manufactured
concrete shall be reviewed by the Engineer before execution of the structural precast
concrete work, at least 14 days before the beginning of precasting work.
7 All materials shall be properly selected, reviewed and approved by the Engineer before use,
and maintained during shipment, storage and use.
8 Construction systems and techniques shall be properly selected, reviewed and approved by
the Engineer before use, and maintained throughout the complete structural precast
concrete construction phase.
9 Adequate spare equipment, parts, additional components and repair facilities shall be
available for all tools and equipment.
QCS 2010
QCS 2010 Section 5 Part 17 Structural Precast Concrete Page 5
10 Regardless of approvals by the Engineer, the Contractor shall be responsible for all
materials and methods of structural precast concrete work.
11 If work does not meet the specified requirements, the Contractor shall at no additional cost
to the Employer:
(a) implement removal, replacement or remedial work
(b) revise procedures or materials to prevent recurrence of unacceptable work.
1 The Contractor shall prepare and provide his quality control programme for structural
precast concrete work with particular attention to details, pre-checking processes,
procedures and close supervision, and in particular the Contractor shall:
4 The Contractor's quality control personnel shall also verify the quality of the structural
precast concrete work and guide the production of results which will be within acceptable
physical tolerances
17.1.7 Testing
4 The Contractor shall station a qualified technician at the casting site to continuously test,
inspect and report on the following:
QCS 2010
QCS 2010 Section 5 Part 17 Structural Precast Concrete Page 6
(a) that concrete testing is being carried out in accordance with the requirements of
Part 6 of this Section
(b) check the following and verify conformance with specified requirements and approved
shop drawings:
(i) all reinforcing bars
(ii) all embedded items
(iii) all formwork
(c) check all openings and provisions for co-ordination with all trades in the Contract as
shown on approved shop drawings.
5 The Contractor shall provide facilities and equipment for the conducting of all tests specified
herein except for the strength test which should be carried out by an approved independent
testing agency.
1 The structural precast elements shall be removed from the form without damaging or over
stressing and stored or placed for transportation on a stable bed that will not allow distortion
of the member.
3 Mark each member with an identifying reference or piece mark, and the date of casting.
4 All piece marks are to be correlated with test reports and plan layouts or erection drawings.
5 The structural precast element shall be transported with sufficient battens, bracing, and
supports so as to prevent over-stress by vibration or impact loadings. The Contractor shall
submit his proposed method of transportation to the Engineer for approval.
6 Structural precast units shall be stored, handled and transported in a manner that will avoid
undue strains, hair cracks, staining, or other damage.
7 The Contractor shall deliver the units from the casting site to the project Site in accordance
with schedule and proper setting sequence.
8 Structural precast units shall be stored free of the ground and protected from wind or rain
splashes.
9 The units shall be covered and protected from dust, dirt or other staining materials.
10 During fabrication, construction and after erection, the Contractor shall protect the castings
to avoid the possibility of damage.
1 The provisions of this Clause shall apply if the Contractor is responsible for the design of the
structural precast units.
2 The precast elements shall be designed to withstand all loading conditions against which
strength and serviceability must be measured.
3 Vertical loads shall include the self-weight of precast elements, floor coverings and live loads
as indicated on the contract drawings.
4 The wind loads shall be calculated in accordance with BS EN 1991-1-4 using mean hourly
wind speed of not less than 30 m/s.
5 Account shall be taken of the loads and deformation caused by temperature and time
dependent deformations. For such purpose 55 °C temperature variation and 90 % relative
QCS 2010
QCS 2010 Section 5 Part 17 Structural Precast Concrete Page 7
humidity should be considered for all members, except exterior elements and facade
elements shall consider 85 oC.
7 Nominal cover to steel including links must meet the durability requirement of severe
condition of exposure and to meet requirement for 2 h period of fire resistance, as provided
for in BS EN 1992-1-1 or relevant ACI code.
8 Total deflection of precast elements should be limited to 1/350 of the span of this element.
9 Plan and design for openings for building services, where required or necessary.
17.2.1 General
1 The Contractor shall obtain cement, aggregates and water from a single source, sufficient to
complete the entire structural precast concrete work to assure regularity of appearance and
uniformity of colour.
2 The Contractor shall provide all materials in accordance with and meet all applicable
requirements of this section.
17.3 FORMING
17.3.1 General
1 Forms and casting beds are to be firmly seated so as not to deflect or be displaced under
concreting or tensioning loads.
3 For member penetrations larger than 150 mm, coring or field cutting is not permitted unless
approved by the Engineer.
4 Clean and coat forms with release agent before installation or reinforcing or embedments.
QCS 2010
QCS 2010 Section 5 Part 17 Structural Precast Concrete Page 8
17.3.2 Tolerances
1 Permissible deviations of formed surfaces are not to exceed tolerances outlined in PCI
Manual 116, with items as summarised or modified in Table 17.1
Table 17.1 Tolerances for Structural Precast Concrete
Description Tolerance
Dimensions
Length: ±5 mm
Width: ±3 mm
Thickness: Stem ±3 mm; Flange ±2.0 mm.
17.4 INSTALLATION
17.4.1 General
1 The Contractor’s erection responsibilities include the safe and proper placing, aligning, and
levelling of the structural precast elements on the accepted bearing surfaces and affecting
their proper fastening.
17.4.2 Survey
1 Before placement of the structural precast elements the Contractor shall survey and
maintain all temporary supports shown or required to control alignment, and deflection.
2 Temporary supports shall be retained until framing elements braced thereby have attained
integral stability in accordance with the design.
1 The Contractor shall install in proper sequence and maintain all temporary supports shown
or required to control alignment, deflection and stress levels.
2 Temporary supports shall be retained until framing elements braced thereby have attained
integral stability in accordance with the design.
1 The Contractor shall compensate and correct for the misaligning affect of temperature, draw
from welding, bolting or erection sequence or grouting.
1 The following erection tolerances shall apply unless otherwise specified in the Contract:
Variations from plumb 6 mm in 6 m run;
12 mm total in a12 m or longer run
Variation from level or elevation 6 mm in runs;
12 mm in 12 m run; maximum 12 mm at
single locations
Variation from position in plan ±12 mm maximum.
Offsets in alignment of adjacent
members at joints 1.5 mm in 3 m run, 6 mm maximum.
QCS 2010
QCS 2010 Section 5 Part 17 Structural Precast Concrete Page 9
17.4.6 Welding
1 Where permission for welding is given by the Engineer, the following shall apply:
(a) welding shall not take place until all adjacent elements to be connected have been
aligned, firmly seated and braced
(b) control of heat build-up by limiting voltage, electrode size, and rate
(c) spalled or heat damaged concrete around weldments shall not be acceptable.
17.4.7 Grouting
1 Joints, gaps and connections shall be filled with grout as shown on the Drawings and as
approved by the Engineer.
2 The maximum hole size shall be 150 mm diameter or as limited by member size or strand
location
3 Any cracks, spalls and sharp corners created by field cutting are to be ground, eased, and
patched with epoxy type bonding and patching compounds.
END OF PART
QCS 2010
QCS 2010 Section 5 Part 18 Prestressed Concrete Page 1
18.1 GENERAL...................................................................................................... 2
18.1.1 Scope 2
18.1.2 References 2
18.1.3 Submittals 2
18.1.4 Storage and Handling 3
18.2 PRESTRESSING ........................................................................................... 3
18.2.1 General 3
18.2.2 Wires and Strands 3
QCS 2010
QCS 2010 Section 5 Part 18 Prestressed Concrete Page 2
1 This section describes the requirements for prestressed post-tensioned concrete, including
materials and procedures for installation, stressing and grouting.
ASTM A881/A881M -10 ............Standard Specification for Steel Wire, Deformed, Stress-
Relieved or Low-Relaxation for Prestressed Concrete Railroad Ties
ASTM A882/A882M-04a(2010).Standard Specification for Filled Epoxy-Coated Seven-Wire
Prestressing Steel Strand
ASTM A416/A416M-10 Standard Specification for Steel Strand, Uncoated Seven-Wire for
Prestressed Concrete
18.1.3 Submittals
1 Samples
(a) a 1 m length sample of strand shall be taken from every 1000 m of strand to be
installed in the works with a minimum of one sample of strand per reel, on Site in the
presence of the Engineer for strength test at an independent laboratory approved by
the Engineer. A reel shall only be accepted if both the breaking load and the 0.1 %
proof load of the sample exceed the characteristic load given in BS 5896 Table 6
(b) a minimum of three samples of strand shall be taken at random from each reel of
prestressing steel on Site in the presence of the Engineer. The reels on Site shall only
QCS 2010
QCS 2010 Section 5 Part 18 Prestressed Concrete Page 3
be accepted if the relaxation values determined by the tests are equal to or lower than
the specified relaxation class of BS 5896.
2 Technical details of the proposed materials and equipment shall be submitted. Details of the
jack type and size shall be submitted to allow for clearances to be checked.
1 Prestressing steel shall be stored on palettes at least 300 mm above the ground, and be
protected from contamination by wind blown sand or rain.
2 Prestressing steel shall be in coils of sufficiently large diameter to ensure that the strand
pays off straight.
18.2 PRESTRESSING
18.2.1 General
1 Prestressing operation shall be carried out only under the direction of an experienced and
competent supervisor and all personnel operating the stressing equipment shall have been
properly trained in its use.
2 In addition to the normal precautions against accident, which should be taken at all times for
the whole of the Works, special care shall be taken when working with or near tendons
which have been tensioned or are in the process of being tensioned.
3 The system of prestressing used shall be a system approved by the Engineer. Such system
shall be used strictly in accordance with the recommendations of the system manufacturer.
4 Under no circumstances shall equipment or fittings designed for use with one system of
prestressing be used in conjunction with equipment and fittings designed for use with
another system.
5 Prestressing components shall be stored in clean dry conditions. They shall be clean and
free form loose rust and lose mill scale at the time of fixing in position and subsequent
concreting. Slight rusting of the steel, which can be removed by moderate rubbing, is
acceptable, but the surface shall not show signs of pitting.
1 All prestressing strands shall be seven-wire super stabilised low relaxation strands with a
Guaranteed Ultimate Tensile Strength (GUTS) of not less than 1770 MPa, complying with
BS 5896 or relevant ASTM standards.
2 All wires or strands to be stressed at the same time shall be taken from the same parcel.
The coil numbers of the steel used for each tendon shall be recorded.
QCS 2010
QCS 2010 Section 5 Part 18 Prestressed Concrete Page 4
4 All cutting of strands shall be carried out using a high-speed abrasive cutting wheel or
friction saw at not less than one diameter from the anchor. Cutting shall take place only after
the Contractor has submitted the stressing records and the Engineer has approved them in
writing. Flame cutting will not be permitted.
5 Tendons shall be built into the Works strictly in accordance with the system which is being
employed.
6 Sufficient strand shall project from the anchorage to allow jacking to take place at either end
of the tendon.
7 The cable or individual strands comprising the cable shall not be kinked or bent. No strand
1 Sheaths shall be accurately located both vertically and horizontally as described in the
Specific Project Specification. Unless otherwise described in the Specific Project
Specification the tolerance in the location of the centre line of the sheath shall be within
±5 mm.
2 All sheaths and cores shall be maintained in their correct positions during the placing of the
concrete. Unless otherwise agreed with the Engineer, sheaths shall be rigidly supported at
points not less than 50 mm and not more than 500 mm apart. The method of support shall
be to the approval of the Engineer.
3 Where sheaths are used, the number of joints shall be kept to a minimum and sleeve
connectors shall be used for jointing. Each joint shall be adequately sealed against the
ingress of material. Joints in adjacent sheaths shall be staggered by at least 300 mm
4 Sheaths shall be kept free of matter detrimental to the bond between the grout and the
sheath and, except for material sealing a sheath joint, between the sheath and concrete.
5 Within 24 hours of the concrete being placed the Contractor shall satisfy the Engineer that
the tendons are free to move if they are in ducts or that the ducts are free from obstruction.
6 The number and position of grout vents for entry and outlet points and for checking that the
entire length of duct has been adequately grouted, shall be agreed with the Engineer before
the ducts are formed.
7 Vents shall be provided at low points in the tendon profile to allow the disposal of water that
may have collected as a result of rain or curing, for example. The vents shall be sealed
before grouting operations beginning.
18.2.4 Anchorages
1 Anchorages, end blocks and plates shall be positioned and maintained in position during
concreting so that the centre line of the duct passes axially through the anchorage assembly.
1 All jacking equipment used for stressing operations shall be of the type applicable to the
system adopted.
QCS 2010
QCS 2010 Section 5 Part 18 Prestressed Concrete Page 5
2 Jack and pumps shall be calibrated at an independent facility, in the presence of the
Engineer, before beginning stressing operations. Calibration of the equipment shall take
place at six-month intervals for equipment permanently present on Site. Whenever new
equipment is brought to the Site, or equipment is removed and returned, or serviced,
recalibration of the equipment as described will be required.
3 All gauges, load cells, dynamometers and other devices used for measurement shall have a
reading accuracy of within ±2 %.
18.2.6 Tensioning
1 The Contractor shall submit details of the proposed stressing loads and stressing sequence
to the Engineer for approval.
3 The Contractor shall ensure that personnel carrying out the stressing are provided with
particulars of the required tendon loads, order of stressing and extensions.
4 Immediately before tensioning, the Contractor shall prove that all tendons are free to move
between jacking points.
5 Unless otherwise permitted in the Contract, concrete shall not be stressed until it has
reached at least the age at which two test cubes taken from it attain the specified transfer
strength. The cubes shall be made and tested as described in BS 1881 , BS EN 12350, BS
EN 12390 or GSO ISO 1920. They shall be cured in similar conditions to the concrete to
which they relate to, and in a manner approved by the Engineer.
6 The friction factors assumed for the calculation of tendon extension shall be verified by on
Site measurement of the force-extension relationship of a typical sample of installed
tendons.
7 The Contractor shall establish the datum point for measuring extension and jack pressure to
the satisfaction of the Engineer.
8 The tendons shall be stressed at a gradual and steady rate until they attain the force
required.
9 The maximum force exerted on the shall not exceed 75 % of the GUTS of the strand. For the
purposes of cable detensioning, where the installed strand is to be discarded the jacking
force may be increased to 80 % GUTS.
10 The force in the tendons shall be obtained from the readings on a load cell or pressure
gauge and the extension of the tendons measured. The two readings shall conform to the
limits set by the Engineer but in all cases the force in the tendon as computed from the
extension measurement shall be within +5 % to -2 % of the force indicated by the gauging
system.
11 When stressing from one end only the pull in at the dead end shall be accurately measured
and the appropriate allowance made in the measured extension at the live end.
12 If the calculated and measured extensions vary from each other by more than ±6 % then
corrective action shall be taken. This may involve detensioning and retensioning of the
tendons if required by the Engineer.
13 When the required force, including overloads of short duration, has been applied to the
satisfaction of the Engineer, the tendons shall be anchored. The jack pressure shall then be
relieved in such a way as to avoid shock to the anchorage or tendons.
QCS 2010
QCS 2010 Section 5 Part 18 Prestressed Concrete Page 6
14 If the pull-in of tendons at the completion of anchoring is greater than that acceptable to the
Engineer, the tendons shall be detensioned and the tendon tensioned again.
15 The Engineer may direct that the force in any tendon be tested by rejacking. This will only be
instructed if there is doubt that the calibration of tensioning equipment is accurate. Care shall
be exercised by the Contractor during the retensioning to ensure that the jacking load does
not exceed more than 80 % of the GUTS of the strand.
16 If it is necessary to crop the tendons to enable the ducts to be grouted, this shall be delayed
as long as is practicable up to the time of grouting. In all other cases, unless otherwise
agreed with the Engineer, the tendons shall not be cropped less than three days after
grouting.
17 The Contractor shall keep full records of all tensioning operations, including the measured
18.2.7 Grouting
1 Grouting shall take place only with the written approval of the Engineer.
2 All ducts shall be thoroughly cleaned by means of compressed air and all anchorages shall
be sealed before grouting.
3 Ducts shall be grouted as soon as practicable after the tendons in them have been stressed
and the Engineer’s written permission to commence has been obtained. Grout shall be
injected in one continuous operation and allowed to flow from the vents until the consistency
is equivalent to that being injected. The maximum time between mixing and injection shall
not exceed 30 min.
5 Vents shall be sealed consecutively in the direction of flow and the injection tube sealed
under pressure until the grout has set. The filled ducts shall be protected to the satisfaction
of the Engineer to ensure that they are not subject to shock or vibration for one day.
6 Two days after grouting, the level of grout in the injection and vent tubes shall be inspected
and made good if necessary.
7 The Contractor shall keep full records of grouting including the date each duct was grouted,
the proportions of the grout and admixtures used, the pressure, details of interruptions and
topping up required. Copies of these records shall be supplied to the Engineer within three
days of grouting.
1 The grout mixer shall produce a grout of colloidal consistency. The grout injector shall be
capable of continuous operation with a sensibly constant pressure up to 0.7 MPa and shall
include a system of circulating or agitating the grout whilst the actual grouting is not in
progress. All baffles to the pump shall be fitted with sieve strainers size BS 14.
2 The equipment shall be capable of maintaining pressure on completely grouted ducts and
shall be fitted with a nozzle which can be locked off without loss of pressure in the duct.
3 The pressure gauges shall be calibrated before they are first used in the Works and
thereafter as required by the Engineer. All equipment shall be thoroughly washed with clean
water at least once every three hours during grouting operations and at the end of use for
each day.
QCS 2010
QCS 2010 Section 5 Part 18 Prestressed Concrete Page 7
4 The Contractor shall ensure that standby grouting equipment is available in the event of a
breakdown.
1 The Contractor shall carry out grouting trails to the satisfaction of the Engineer before actual
grouting taking place.
2 Unless otherwise directed or agreed as a result of grouting trials, the grout shall:
(a) consist only of ordinary Portland cement, water and an approved expansion agent
(b) have a water:cement ratio as low as possible consistent with the necessary
workability. Under no circumstances shall the water:cement ratio exceed 0.4
(c) not be subject to bleeding in excess of 2 % after 3 h or 4 % maximum when measured
4 The grout shall be mixed for a minimum of 2 minutes and until a uniform consistency is
obtained.
END OF PART
QCS 2010
QCS 2010 Section 5 Part 19 Testing of Water Retaining Structures Page 1
19.1 GENERAL...................................................................................................... 2
19.1.1 Scope 2
19.1.2 References 2
19.1.3 Submittals 2
19.1.4 General 2
19.2 TESTING ....................................................................................................... 2
19.2.1 General 2
19.2.2 Cleaning 3
QCS 2010
QCS 2010 Section 5 Part 19 Testing of Water Retaining Structures Page 2
1 This Part of the specification applies to the testing of structures that are designed with the
intention of retaining water.
1 The Contractor shall record and submit to the Engineer within 24 hours the results of the
watertightness tests carried out.
19.1.4 General
19.2 TESTING
19.2.1 General
1 The Contractor shall test watertightness of water retaining structures including storage
reservoirs and other miscellaneous structures that require to be watertight.
2 All water used for testing shall be potable or irrigation water and the Contractor shall make
arrangements for the supply and disposal of this water.
3 Water retaining structures shall be tested for watertightness after completion, in accordance
with the following method or as directed by the Engineer:
(a) the structure shall be filled with potable or irrigation water in stages not exceeding 1 m
in 24 h held at each water level for such time as the Engineer may require. Should
dampness or leakage occur, the water shall be drawn off and the defects remedied to
the satisfaction of the Engineer
(b) in the case of structures which are subdivided into individual tanks, each individual
tank shall be tested separately. In the case of underground or partially underground
structures, the testing shall take place before application of water proofing membrane,
liner material or perimeter drain, filter material or backfilling is placed against the walls
(c) in the case of hopper bottomed tanks, this shall be taken to mean that no material is
placed against the vertical external walls of the tank, the sloping walls of the hopper
bottoms of the tanks being assumed built directly against the excavation apart from
the blinding concrete
(d) no placing of material against the walls shall take place until the Engineer has given
his written approval and acceptance of the water retaining structures as watertight
(e) filling shall not take place earlier than 28 d after the casting of the final sections of the
structure which will be stressed by the filling of the structure.
QCS 2010
QCS 2010 Section 5 Part 19 Testing of Water Retaining Structures Page 3
(f) testing shall not be undertaken until the structure to be tested has been; completed
structurally including roof, if any, and has been passed by the Engineer in writing as
satisfactory in all respects other than watertightness, especially in regard to the final
finish of the work
(g) not withstanding the satisfactory completion of the seven day test, leakage, cracks,
and damp patches and sweating visible on the outside faces of the structure shall be
rectified from the water face by an injection system to the approval of the Engineer
(h) repair making the outer face only watertight wall not be accepted, this applies to
bobbin holes also
(i) the structure shall be retested until the watertightness is approved by the Engineer.
(j) should the structure fail a test in the above respects, the Contractor shall immediately
take such steps as may be necessary to:
(i) ascertain the nature and positions of defects or leakage's
(ii) empty the structure
1 All water retaining structures shall, on completion, be carefully cleaned of all debris, to the
complete satisfaction of the Engineer as follows:
(a) shall be brushed down on all internal faces with a stiff broom while still dry
(b) all resulting debris removed
(c) all associated reservoir pipe work shall be cleaned in accordance with the specified
requirements
(d) the structure shall then be flooded with approximately 75 mm of clean water
(e) whole of internal faces shall be carefully brushed down with stiff brooms using the
water continuously until all faces are clean
(f) water shall then be drained off
(g) walls and floors hosed and flushed with clean water until perfectly clean.
19.3.1 Walls
1 After completion and cleaning of the structure and all associated pipe work, if any, the
Contractor shall fill the structure up to the top water level and leave for a stabilising period of
21 d in order to allow for absorption and autogenous healing to take place.
2 Water shall be added over this period to maintain the top water level.
3 The Contractor shall ensure that all pipes and specials are available in ample time ahead of
testing.
4 Two sets of evaporation trays shall be provided along with two sets of rain gauges.
5 Levels in the trays and structure shall be made and recorded by a hook gauge with vernier
attachments.
6 Before and during testing, flows in the structure under drainage, if any, shall be monitored,
measured and recorded.
7 Each under drain shall be numbered and observations reported by under drain number to
facilitate analysis of the data.
QCS 2010
QCS 2010 Section 5 Part 19 Testing of Water Retaining Structures Page 4
9 On the twenty-second day, two shallow watertight evaporation trays of area 0.4 m2 shall be
filled with 75 mm of water and placed to float in the structure.
10 The water level in the structure shall be recorded and the test commenced and carried out
over the next 7 d.
11 Readings of water levels in the structure and trays shall be made and recorded every 24 h
over this period.
12 If the water level in the tank falls by more than indicated by the evaporation trays, or other
sign of leakage occurs by the end of the test period then the Contractor shall search and
mark all areas of defect.
14 After completion of remedial measures the structure shall be refilled and the test repeated.
15 This process shall be repeated until the structure is watertight to the satisfaction of the
Engineer.
16 The fall of water level in the structure over the test period of 7 d, minus the fall accounted for
by evaporation and rainfall shall not exceed 1/500 of the average water depth of the full
structure or 10 mm whichever is less.
19.3.2 Roofs
1 The roofs of structures shall be tested for watertightness before laying of roof membrane.
2 Roof and fittings shall be hosed down vigorously and this shall be repeated in such a way as
to keep the roof wet for three successive days.
3 Roof and fittings shall be deemed satisfactory for watertightness if no discernible leaks or
damp patches show in the soffit.
1 The Contractor shall provide suitable means for disposal of water used for testing, such that
no damage results to facilities, structures or property.
2 These means shall be subject to the approval of the Engineer and local authorities.
4 The Contractor shall be responsible for damage caused by his filling, testing, flushing and
wastewater disposal operations.
END OF PART
QCS 2010