PP 01 77 00

Uploaded by

Mike
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
25 views15 pages

PP 01 77 00

Uploaded by

Mike
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 15

SECTION 01 77 00 - PROJECT CLOSE-OUT PROCEDURES

PART 1 - GENERAL

1.1. RELATED DOCUMENTS

1.1.1. The Contractor's attention is specifically directed, but not limited, to the Uniform General and
Supplementary General Conditions for University of Texas System Building Construction
Contracts (UGC) for other requirements.

1.2. SUMMARY

1.2.1. The following Project Close-Out procedures are addressed in this Section:

1.2.1.1. Requirements for Substantial Completion

1.2.1.2. Provisions for Release of Retainage

1.2.1.3. Requirements for Final Acceptance

1.2.1.4. Requirements for Record Documents

1.2.1.5. Requirements for Record Submittals and Samples

1.2.1.6. Requirements for Operating and Maintenance Manuals

1.2.1.7. Requirements for Commissioning and Close-out Manual

1.2.1.8. Requirements for Close-Out Document Submission

1.2.1.9. Project Cleaning

1.3. DEFINITIONS

1.3.1. The term “Project Close-Out” is hereby defined to include requirements near the end of the
Contract Time, in preparation for Substantial Completion acceptance, occupancy by Owner,
release of retainage, final acceptance, Final Payment, and similar actions evidencing
completion of the Work. Specific additional requirements for individual units of work are
specified in the Technical Specifications.

1.3.2. The term “Time” of Close-Out is directly related to completion and acceptance, and therefore
may be either a single time period for the entire Project, or a series of time periods for
individual portions or phases of the Project that have been certified as substantially complete
at different dates.

1.3.3. Refer to the UGC for Definitions used throughout the Contract Documents.

1.4. REQUIREMENTS FOR SUBSTANTIAL COMPLETION

1.4.1. In addition to items identified in the UGC, prior to requesting a Substantial Completion
inspection (for either the entire Work or portions thereof as agreed to by the Owner and
Contractor), Contractor shall complete and/or submit the following to the Owner and list
known exceptions in the request.

1.4.1.1. Contractor’s Application for Payment that is coincident with the period of time
anticipated for Substantial Completion shall reflect a minimum of 95%
completion for all applicable Work.

The University of Texas PROJECT CLOSE-OUT PROCEDURES


MD Anderson Cancer Center 01 77 00
MS083012 1 OF 15
1.4.1.2. Owner’s acceptance of all building system installations. If Owner’s Construction
Inspectors are assigned to the Project, acceptance may be in the form of
building system final inspection reports.

1.4.1.3. Record Documents: Up-to-date, marked-up drawings and specifications that


record all changes made during construction.

1.4.1.4. Record Submittals and Samples.

1.4.1.5. Operating and Maintenance Manual(s).

1.4.1.6. Commissioning and Close-out Manual.

1.4.1.7. Completed Punchlists.

1.4.1.8. Certification statement that no asbestos containing materials have been used or
incorporated into the Project.

1.4.1.9. Releases enabling Owner's full and unrestricted use of the Project and access to
services and utilities, including (where applicable) operating certificates, and
similar releases.

1.4.1.10. Deliver tools, spare parts, extra stock of materials, Samples, and similar physical
items to Owner.

1.4.2. If Owner intends to occupy Project upon Substantial Completion acceptance, Contractor shall
make provisions for final changeover of locks with the Owner's personnel. Upon written
directive from Owner and for the convenience of the Contractor in completing Punchlist
activity, Owner may waive the final changeover of locks until final acceptance.

1.4.3. Contractor shall complete instructing and training Owner's personnel for all systems and
equipment serving the areas claimed as substantially complete, for which Owner training was
not completed in association with system demonstrations and inspections. Refer also to
Section 01 91 00 – General Commissioning Requirements.

1.4.4. Contractor shall complete the initial clean-up requirements as described in Part 3 of this
Section for the entire portion of the Project claimed as substantially complete. Contractor
shall touch-up and otherwise repair and restore marred exposed finishes.

1.4.5. SUBSTANTIAL COMPLETION INSPECTION PROCEDURE

1.4.5.1. Refer to the UGC and Section 01 45 00 – Project Quality Control.

1.4.5.2. The Contractor shall ensure the Work is ready for inspection and/or reinspection.
If the Work is found not to be as stated in the Contractor’s Punchlist or the items
have not been substantially corrected and/or completed, the inspection will be
terminated. All costs incurred by the Owner and Architect/Engineer for
scheduling and attending the terminated inspection(s) shall be the responsibility
of the Contractor and excluded from the Cost of Work.

1.5. PROVISIONS FOR RELEASE OF RETAINAGE

1.5.1. Refer to the UGC.

1.5.2. Release of any retainage, or reduction in amount of retainage withheld, is strictly at the
discretion of the Owner, regardless of Contractor compliance with requirements. All of the
requirements noted for Substantial Completion acceptance must be completed prior to

The University of Texas PROJECT CLOSE-OUT PROCEDURES


MD Anderson Cancer Center 01 77 00
MS083012 2 OF 15
application for final release of Contract retainage. In addition, Contractor shall meet the
following requirements:

1.5.2.1. Submit affidavits of final release of claim and lien from each subcontractor and
supplier who provided materials and/or labor to the Project.

1.5.2.2. Submit affidavit that all bills for the Project have been paid, or will be paid within
thirty (30) days of Contractor’s receipt of payment.

1.5.2.3. Submit Consent of Surety to Release of Retainage.

1.6. REQUIREMENTS FOR FINAL ACCEPTANCE

1.6.1. In addition to items identified in the UGC, prior to requesting a Final Completion inspection
(for either the entire Work or portions thereof as agreed to by the Owner and Contractor),
Contractor shall complete and/or submit the following to the Owner and list known exceptions
in the request:

1.6.1.1. Draft Application for Final Payment showing 100% completion for each line item
on the Schedule of Values. Contractor must submit with this draft, the final
releases and supporting documentation not previously submitted and accepted.
Contractor must include Certificates of Insurance when applicable. The Final
Payment, including final release of retainage, will not be released until all Work
(including Punchlist items) has been completed, all requirements met, a Project
Close-Out audit performed (if deemed necessary) and a Final Change Order has
been processed if required to resolve final cost or close-out audit issues,
including deletion of any remaining Contract allowances.

1.6.1.2. Copy of Architect/Engineer's Substantial Completion Punchlist including


evidence that each item has been completed or otherwise resolved.

1.6.1.3. Final meter readings for utilities, and similar data as of time of Substantial
Completion or when Owner took possession of and responsibility for
corresponding elements of the Work.

1.6.1.4. Final Record Documents, all approved record submittals, record Samples, and
Operating and Maintenance Manuals as described later in this Section. This
includes specific warranties, maintenance agreements, product certifications and
similar documents. The Architect/Engineer and Owner must approve Record
Documents in writing prior to issuance of Final Payment.

1.6.1.5. Completed Commissioning and Close-Out Manual, acknowledging receipt of all


attic stock, training/demonstration, test reports, and any other requirements of
the Contract Documents.

1.6.1.6. Complete final cleaning requirements including touch-up of marred surfaces.

1.6.1.7. Evidence of final and continuing insurance coverage complying with applicable
insurance requirements.

1.6.2. FINAL ACCEPTANCE INSPECTION PROCEDURE

1.6.2.1. When the Contractor has completed the Work required in the Final Completion
inspection Punchlist and has complied with the Close-Out requirements in this
Section and elsewhere in the Contract Documents, then the Contractor shall
provide a minimum of ten (10) days written notice to the Architect/Engineer and

The University of Texas PROJECT CLOSE-OUT PROCEDURES


MD Anderson Cancer Center 01 77 00
MS083012 3 OF 15
Owner that the Project is ready for a final acceptance inspection for Final
Completion. Refer to the UGC for additional requirements.

1.6.2.2. All Owner and Architect/Engineer costs for travel and time for additional
inspections at either Substantial Completion or Final Acceptance which are
required either by failure of the Contractor to complete the noted Punchlist items,
or by erroneous notices that the Work is ready for such inspections, shall be the
responsibility of the Contractor. Owner may issue a unilateral deductive Change
Order for these costs.

1.6.3. FINAL PAYMENT REQUEST

1.6.3.1. Contractor shall submit the following documentation with the Application for Final
Payment:

1.6.3.1.1. Final Release of Liens and Claims.

1.6.3.1.2. Affidavit of Payment of Debts and Claims.

1.6.3.1.3. Consent of Surety.

1.6.3.1.4. Completed SWPPP Documents and Notice of Termination.

1.6.3.1.5. Final Historically Underutilized Business Plan.

1.6.3.1.6. Completed and Signed Notice of Termination.

1.6.3.1.7. Signed Final Completion Certificate.

PART 2 - PRODUCTS

2.1. REQUIREMENTS FOR RECORD DOCUMENTS

2.1.1. During progress of the Work, Contractor shall maintain a set of Construction Documents and
Shop Drawings at the Site. Contractor must update these documents weekly, at a minimum,
with mark-ups of actual installations that vary from the work as originally shown. Contractor
shall include all drawings issued as addenda, clarifications, and/or change orders.

2.1.2. Contractor shall maintain and have available for review in conjunction with Project Progress
Meetings, a current set of the marked-up record drawings and specifications. Availability for
review and acceptability of both the format and content is a prerequisite condition for
certification of the monthly pay requests by the Owner and Architect/Engineer.

2.1.3. Contractor shall not use Record Documents for construction purposes. Contractor must
protect Record Documents from deterioration and loss in a secure location.

2.1.4. Record Documents shall include marked-up copies of Construction Documents that indicate
all changed conditions issued through addenda and/or change orders. Record Documents
include newly prepared drawings submitted as an RFI, Change Order/Request for Proposal,
Field Change, Red Line, Supplemental Document, Revision/ASI, or Addendum and Shop
Drawings defined herein as supplemental drawings. Include marked-up product submittals,
field records for variable and concealed conditions such as excavations and foundations, and
miscellaneous record information on Work that was recorded only schematically or not
recorded at all.

The University of Texas PROJECT CLOSE-OUT PROCEDURES


MD Anderson Cancer Center 01 77 00
MS083012 4 OF 15
2.1.5. RECORD DOCUMENTS EDIT LOG

2.1.5.1. During progress of the Work, Contractor shall maintain a Record Documents Edit Log
at the Site to track changes and edits to the Construction Documents. Contractor shall
update the log each time changes are made to the Record Documents and shall
review the log with the Owner prior to each monthly Application for Payment.

2.1.5.2. The “Record Documents Edit Log” should include the following information as a
minimum, as indicated in Owner’s template. Refer to Attachment No. 1 for an example
of the Record Documents Edit Log Template. Download an electronic version of the
Record Document Edit Log in Microsoft Word format to use as a template for submittal
purposes at the following Internet website:

http://www2.mdanderson.org/depts/cpm/standards/supp.html#templates

2.1.5.2.1. Date Edited.

2.1.5.2.2. Name and Company of Person Making Edit.

2.1.5.2.3. Edit Type: RFI, Change Order/Request for Proposal, Field Change, Red
Line, Supplemental Document, Revision/ASI, or Addendum.

2.1.5.2.4. Reference: name and number of the source document if applicable, such as
Change Order or RFI number.

2.1.5.2.5. Sheet(s) Edited.

2.1.5.2.6. Description of Edit, unless documented by an RFI, Change Order, or Field


Change.

2.1.6. RECORD DRAWINGS

2.1.6.1. Contractor must mark-up whatever drawing is most compatible for showing actual
physical condition, fully and accurately and must reference all other appearances of
this work to the updated sheet. Contractor must include cross-references to the official
change number on the updated sheet and all additional sheets where the work is
shown.

2.1.6.1.1. Contractor must mark-up with erasable colored pencil in a legible and
professional manner, using separate colors where feasible to distinguish
between changes for different categories of work at the same general
location.

2.1.6.1.2. Contractor must mark-up important additional information, which was either
shown schematically only or omitted from the Construction Documents.
Contractor must give particular attention to information on concealed work
that would be difficult to identify or measure and record at a later date.

2.1.6.1.3. Contractor must require each person preparing mark-ups to initial and date
the mark-ups and indicate the name of their firm.

2.1.6.2. In association with Contractor’s request for Substantial Completion inspection,


Contractor must submit one (1) copy of the marked-up record drawings to the
Architect/Engineer and one (1) copy to the Owner for review. Drawings may be
scanned in Adobe PDF format. Upon Architect/Engineer’s and Owner’s acceptance
that the marked-up information is accurate and complete, the Contractor shall proceed
with preparation of “final” record drawings.

The University of Texas PROJECT CLOSE-OUT PROCEDURES


MD Anderson Cancer Center 01 77 00
MS083012 5 OF 15
2.1.6.3. Contractor shall bear all costs associated with obtaining the Architect/Engineer's
original drawings to draft marked-up information.

2.1.6.3.1. Contractor shall ensure that all drawing changes are of good drafting quality,
performed by a person skilled in drafting and knowledgeable of the
conventions of the trades involved.

2.1.6.3.2. Contractor may utilize Contractor’s staff or seek outside assistance, including
the Architect/Engineer, for this drafting work provided the contractual
requirements pertaining to quality, format, and content are met.

2.1.6.4. All final record drawings shall bear the official Project name and number. Each record
drawing, including supplemental drawings, shall be noted as "Record Document" along
with the Contractor's certification that such is an accurate reflection of actual as-
constructed conditions. Contractor shall sign and date each certification in a format
that is acceptable to the Owner.

2.1.6.5. All drawings issued as addenda, clarifications and/or change orders shall be
incorporated into the final record drawings. If supplemental drawings are used,
Contractor must follow the requirements below for supplemental drawings.

2.1.6.6. Contractor shall submit final record drawings to Owner per Owner’s native software
requirements and within sixty (60) days after Final Completion.

2.1.6.7. SUPPLEMENTAL DRAWINGS

2.1.6.7.1. The use of Shop Drawings as supplements to the final record drawings is
required for all items in which the larger scale employed on the Shop
Drawings is needed to show the work in sufficient detail for Owner’s future
use. Examples of supplemental drawings include, but are not limited to:
HVAC ductwork, hydronic and plumbing piping, sprinkler piping, switchgear,
and custom air handling units. When marked-up Shop Drawings are included
in the Record Documents, Contractor must mark-up and cross-reference on
the Contract Drawings at the corresponding location.

2.1.6.7.2. During preparation of the final record drawings, the applicable supplemental
sheet must be placed in the set directly behind the Contract Drawing which it
supplements, with appropriate reference notes on both the applicable
Contract Drawing and all other affected drawings.

2.1.6.7.3. The supplemental document must be identified as a Record Document and


must be numbered with an extension to the Contract Drawing it supplements
in a manner acceptable to the Owner.

2.1.7. RECORD SPECIFICATIONS

2.1.7.1. It is mandatory that all changes to specified materials, installation, warranty, etc. be
clearly and fully marked within the applicable specification section in a manner
acceptable to the Architect/Engineer and the Owner. Contractor shall review with the
Owner and document an acceptable procedure early in the construction phase.

2.1.7.2. Contractor must give particular attention to substitutions, selection of options, and
similar information on work where the exact products used are not clearly identified or
readily discernable in the original specifications. When applicable, Contractor must
cross-reference related record drawing information and product data.

The University of Texas PROJECT CLOSE-OUT PROCEDURES


MD Anderson Cancer Center 01 77 00
MS083012 6 OF 15
2.1.7.3. Contractor must neatly transcribe and post all marked-up information to a "clean" copy
of the Project Specifications, ensuring that similar types of information are annotated in
like fashion throughout the Project Specifications.

2.1.7.4. In association with Contractor’s request for Substantial Completion inspection,


Contractor must submit the marked-up Site copy of the specifications to the
Architect/Engineer and Owner for review. Upon the Architect/Engineer’s acceptance
that the marked-up information is accurate and complete, the Architect/Engineer will
proceed with preparation of final record specifications.

2.2. REQUIREMENTS FOR RECORD SUBMITTALS AND SAMPLES

2.2.1. RECORD SUBMITTALS

2.2.1.1. During progress of the Work, Contractor shall maintain copies of each approved
product submittal and Shop Drawing, including documentation of all Architect/Engineer
and Owner comments. Contractor shall include variations in product as delivered to
the Site and variations from manufacturer's instructions and recommendations for
installation.

2.2.1.1.1. Contractor shall give particular attention to concealed products and portions
of the Work that are not clearly identified in the original submittal or cannot
otherwise be readily discerned at a later date by direct observation.
Contractor shall cross reference to change orders and record drawings and
specifications.

2.2.1.2. Contractor shall include a complete table of contents of record submittals transmitted
to Owner.

2.2.1.3. These record submittal requirements are in addition to inclusion of similar material as
supplemental drawings or data for Operating and Maintenance Manuals.

2.2.2. RECORD SAMPLES

2.2.2.1. Prior to date(s) of Substantial Completion, Contractor shall arrange for


Architect/Engineer and Owner's representative to meet with Contractor at the Site to
determine which (if any) of the submitted Samples or mock-ups maintained by
Contractor during progress of the Work are to be transmitted to Owner for record
purposes.

2.2.2.2. Contractor shall comply with Architect/Engineer's and/or Owner’s instructions for
packaging, identification marking, and delivery to Owner's designated location at the
Site or other location as directed by Owner.

2.2.2.2.1. Furnish two (2) binders of all record finishes Samples, bound in heavy-duty,
3-ring vinyl-covered binders including pocket folders for any folded sheet
information. Binder content shall be divided with plastic-covered tabs for
each section of each binder. Provide labels to identify binder content on
both the front and spine of each binder.

2.2.2.2.2. Samples shall be mounted to paper or heavy stock depending on type of


sample, organized by finish type, with the following information: Type,
Manufacturer, Product Number, Finish/Color, Description, Installed Location.

2.2.2.2.3. Finishes Samples include, but are not limited to, the following as applicable
to the Work: tile, VCT, terrazzo, stone, sheet vinyl, carpet, base, wall

The University of Texas PROJECT CLOSE-OUT PROCEDURES


MD Anderson Cancer Center 01 77 00
MS083012 7 OF 15
coverings, laminates, solid surface materials, decorative glass, paint, and
wood.

2.2.2.3. Contractor shall dispose of other Samples in the manner specified for disposal of
surplus and waste materials, unless otherwise indicated or directed by
Architect/Engineer and/or Owner.

2.3. REQUIREMENTS FOR OPERATING AND MAINTENANCE MANUALS

2.3.1. Within thirty (30) days of the Notice to Proceed with Construction, Contractor shall submit to
Owner the proposed format, content and organizational structure for Operating and
Maintenance Manuals for Owner’s review and approval. The organizational structure shall
follow Owner’s format for maintenance management; confirm structure with Owner.

2.3.2. Contractor shall make revisions and corrections to format and content as reasonably
requested by Owner. After the Owner approves the proposed format, content, and
organizational structure, Contractor shall create the file structure and update Operating and
Maintenance Manual content as the Work progresses.

2.3.3. Product submittals, owner’s manuals, manufacturer’s printed instructions, parts lists, and
other submittals required by other Sections of the Specifications shall be included in the
Operating and Maintenance Manuals provided that they are approved and are formatted in a
manner consistent with the requirements of this Section.

2.3.4. Test data and commissioning data included in the Operating and Maintenance Manuals need
not be duplicated in the Commissioning and Close-Out Manual and vice versa. Test data not
pertaining to a particular device or piece of equipment (such as domestic water pipe pressure
test reports) must be inserted in the Commissioning and Close-Out Manual.

2.3.4.1. Equipment is defined as any mechanism, mechanical, electrical or electronic device, or


any combination thereof, which is made up of two (2) or more working parts to perform
a particular function.

2.3.4.2. When an item of equipment is a packaged unit furnished by one manufacturer and the
package as furnished contains proprietary items of equipment obtained from other
sources, Contractor shall include copies of equipment data for each item of such
equipment as if each item of equipment had been separately furnished.

2.3.5. Manufacturers’ standard printed data shall include only sheets pertinent to the product or
component installed. Mark each sheet to identify each product or component incorporated
into the Work. Prepare supplementary text if manufacturers’ standard printed data are not
available and where the information is necessary for proper operation and maintenance of
equipment or systems.

2.3.6. Refer to individual Technical Specification Sections for additional operating and maintenance
requirements.

2.3.7. Examples of equipment, material, and systems for which operating and maintenance data is
required includes, but is not limited to, the following:

Architectural / HVAC / Plumbing Electrical / Life Safety


Miscellaneous
Doors and Windows Piping, Valves, and Cable, Wire, and
Fittings Connectors, 600 Volt
Overhead Coiling Doors Motors Wiring Devices
and Grilles
Automatic Door Openers Fire Protection Systems Motor Control Centers

The University of Texas PROJECT CLOSE-OUT PROCEDURES


MD Anderson Cancer Center 01 77 00
MS083012 8 OF 15
Architectural / HVAC / Plumbing Electrical / Life Safety
Miscellaneous
Door Hardware Plumbing Equipment Distribution Panelboards
Wall Coverings Plumbing Specialties Panelboards
Paint Liquid Nitrogen System Emergency Generator
Paralleling Switchgear
Floor Coverings and Base Gas Systems Packaged Engine
Generator Systems
Stone and Terrazzo Fuel Oil Systems Automatic Transfer
Switches
Tile Reverse Osmosis Standby Power
System Generator Switchgear
Acoustical Ceiling Tile Hydronic Specialties Fuses
Decorative Glass Steam and Steam Switchgear
Condensate Specialties
Access Flooring HVAC Pumps Power Factor Correction
Equipment
Demountable Partitions Chemical Treatment Transformers
Systems
Folding Operable Chillers Busway – 600 Volt and
Partitions Below
Loading Dock Equipment Boilers Surge Protective Devices
Laboratory Casework DX Air-Conditioning Motor Starters
Systems
Fume Hoods Heat Exchangers Power Status and
Monitoring System
Biological Safety Cabinets Humidifiers Lighting Fixtures
Environmental Rooms Terminal Heat Transfer Lighting Control Systems
Units
Sterilizers, Washers and Modular Air Handling UPS Equipment
Dryers Units
Audio-Visual Equipment Custom Air Handling Fire Alarm System
Units
Window Treatment Fans Communication Systems
Radiation Protection Filters Security System
Conveying Systems Ductwork
Irrigation Systems Air Terminal Units
Window Washing Air Outlets and Inlets
Systems
Pneumatic Tube Systems Variable Speed Drives
Building Automation
System

2.3.8. OPERATING AND MAINTENANCE DATA

2.3.8.1. Contractor shall furnish the following equipment data content to be Included in
Operating and Maintenance Manuals:

2.3.8.1.1. Description of Equipment. Completed Equipment Matrix; refer to the


Equipment Matrix requirements of Section 01 91 00 – General
Commissioning Requirements.

2.3.8.1.2. Record Product Submittals. Clearly identify all options and accessories of
actual installed product and variations in the actual Work in comparison with
submitted information.

The University of Texas PROJECT CLOSE-OUT PROCEDURES


MD Anderson Cancer Center 01 77 00
MS083012 9 OF 15
2.3.8.1.3. Parts List. Clearly identify every part in the item of equipment with the proper
manufacturer’s name, part nomenclature and number, local source, and list
price.

2.3.8.1.4. Recommended Spare Parts List. For each equipment item that Owner will
likely need within a 12-month period to support and operate that item of
equipment. The quantities of spare parts recommended must be based upon
the quantity of like equipment items installed under the Contract Documents.

2.3.8.1.5. Normal Operating Instructions. Detailed information to permit a journeyman


mechanic to adjust, start-up, operate, and shut down the equipment. Special
start-up precautions shall be noted as well as other action items required
before the equipment is put into service.

2.3.8.1.6. Emergency Operating Procedures. Detailed description of the sequence of


action to be taken in the event of a malfunction of the unit, either to permit a
short period of continued operation or emergency shutdown to prevent
further damage to the unit and to the system in which it is installed.

2.3.8.1.7. Preventive Maintenance. Detailed information to cover routine and special


inspection requirements, including but not limited to, field adjustments,
inspections for wear, adjustment changes, packing wear, lubrication points,
frequency and specific lubrication type required, cleaning of the unit and type
solvent to use, and such other measures as are applicable to preventive
maintenance program.

2.3.8.1.8. Calibration. Detailed data on what to calibrate, how to calibrate, when to


calibrate and procedures to enable checking the equipment for reliability or
indications as well as data for test equipment, special tools and the location
of test points.

2.3.8.1.9. Scale and Corrosion Control. Detailed information covering the prevention of
and removal of scale and corrosion.

2.3.8.1.10. Trouble Shooting Procedures. Detailed information and procedures for


detecting and isolating malfunctions and detailed information concerning
probable causes and applicable remedies.

2.3.8.1.11. Removal and Installation Instructions. Detailed information concerning the


logical sequence of steps required to remove and install the item including
instructions for the use of special tools and equipment.

2.3.8.1.12. Disassembly and Assembly Instructions. Detailed illustrations and text to


show the logical procedure and provide the instructions necessary to
disassemble and assemble the unit properly. The text shall include all
checks and special precautions as well as the use of special tools and
equipment required to perform the assembly or disassembly.

2.3.8.1.13. Repair Instructions. Detailed repair procedures to bring the equipment up to


the required operating standard including instruction for examining
equipment and parts for needed repairs and adjustments, and tests or
inspections required to determine whether old parts may be reused or must
be replaced.

2.3.8.1.14. Special Tools and Test Equipment. Detailed list of the special tools and test
equipment needed to perform repair and maintenance for each equipment
item. The list shall contain the special tool and test equipment part number,

The University of Texas PROJECT CLOSE-OUT PROCEDURES


MD Anderson Cancer Center 01 77 00
MS083012 10 OF 15
size, quantity, price, manufacturer’s name and address, and local supplier’s
name and address.

2.3.8.1.15. System Drawings. Contractor shall furnish detailed drawings, where


applicable, that clearly show wiring diagrams, utility service diagrams, control
diagrams, system schematics, pneumatic and fluid flow diagrams, etc., which
pertain to the unit function. System drawings must show major pieces of
equipment, such as chillers, boilers, heat exchangers, pumps, air handlers,
tanks, switchgear, etc., as meaningful to the Project. Fluid flow and direction
and valves with their valve tag identification numbers must be clearly noted
on drawings. Drawings must show modifications to another manufacturer's
standard unit when it is incorporated into the assembly or package unit.

2.3.9. WARRANTIES AND GUARANTEES

2.3.9.1. Contractor shall include, within the Operating and Maintenance Manual organizational
structure for each system, equipment item, or material, an executed copy of the
specified warranty/guarantee with warranty effective dates covering that particular
system, equipment item, or material. Contractor shall include the manufacturer’s
warranty as specified and the installing subcontractor’s and supplier’s guarantee for
workmanship and system operation.

2.4. REQUIREMENTS FOR COMMISSIONING AND CLOSE-OUT MANUAL

2.4.1. The Contractor shall incorporate all Commissioning and Close-Out documentation and/or
verification documents not included in the Operating and Maintenance Manuals, into a
separate Commissioning and Close-Out Manual for transmittal to the Owner at the
conclusion of the Project. The Commissioning and Close-Out Manual is intended to be a
consolidation of documentation/verification for the Project commissioning and close-out
process. Update the Commissioning and Close-Out Manual throughout the Project, so that
the documentation process can be expedited and monitored.

2.4.2. The Owner may provide a preliminary handbook with sample forms for use by the Contractor
in development of the Commissioning and Close-Out Manual. Each Project may require the
Contractor to revise and/or create forms for Project specific equipment. The Contractor shall
review each form for approval with the Owner before using the Contractor’s form.

2.4.3. The Commissioning and Close-Out Manual is not intended to impose duplication of Close-
Out Documents. Those items and/or data that are incorporated into the Operating and
Maintenance Manuals need not be included in the Commissioning and Close-Out Manual.

2.4.4. The Commissioning and Close-Out Manual shall include, but is not limited to, the following.

2.4.4.1. Commissioning documentation as described in Section 01 91 00 - General


Commissioning Requirements.

2.4.4.2. Final air balance reports produced by the Test, Adjust, and Balance Firm.

2.4.4.3. Completed Valve Schedule and Fire, Fire/Smoke and Smoke Damper Schedule per
Specification Section 20 05 53.

2.4.4.4. Owner Demonstration / Training Reports: Contractor shall furnish Training Plan and
documentation of Owner’s personnel training regarding operation of systems per
Section 01 91 00 – General Commissioning Requirements and Technical Specification
Sections. Contractor shall include identification of parties receiving training and
date(s) of such training.

The University of Texas PROJECT CLOSE-OUT PROCEDURES


MD Anderson Cancer Center 01 77 00
MS083012 11 OF 15
2.4.4.5. Paint/Finish Schedule: All paints, flooring, finishes, door hardware, used on the
Project. Provide manufacturer, model number, color formula, location on Project,
purchase source, and any other information helpful to the Owner’s maintenance
personnel.

2.4.4.6. Attic Stock and Keys Checklists. Attic stock shall be referenced to the Owner’s
Mainsaver Asset Number.

2.4.4.7. Elevator Checklist.

2.4.4.8. Electrical Test Reports (including factory tests and settings).

2.4.4.9. Miscellaneous Equipment Test Reports (including factory tests and settings).

2.4.4.10. HVAC Calibration Reports (including duct testing reports).

2.4.4.11. Fire Alarm Test Reports.

2.4.4.12. Piping Test Reports.

2.4.4.13. Sewer Video Log.

2.4.4.14. Code-required Certifications as described within Technical Specifications.

2.4.4.15. Material Safety Data Sheets (MSDS) for any and all products incorporated into the
Project.

2.4.4.16. Miscellaneous Close-out Documents. Contractor shall provide categories of


requirements resulting in miscellaneous work records including, but not be limited to,
the following:

2.4.4.16.1. Required field records on excavations, foundations, underground


construction, wells and similar work.

2.4.4.16.2. Accurate survey showing locations and elevations of underground lines,


including invert elevations of drainage piping.

2.4.4.16.3. Surveys establishing lines and levels of building.

2.4.4.16.4. Planting material treatment records (wood, soil, etc).

2.4.4.16.5. Certifications received in lieu of labels on products and similar record


documentation.

2.4.4.16.6. Concrete batch mixing and bulk delivery records.

2.4.4.16.7. Testing and qualification of tradesmen.

2.4.4.16.8. Documented qualification of installation firms.

2.4.4.16.9. Materials testing reports.

2.4.4.16.10. Final inspection Punchlist and deficiency corrections.

2.4.4.16.11. All original, signed Project warranties and guarantees.

The University of Texas PROJECT CLOSE-OUT PROCEDURES


MD Anderson Cancer Center 01 77 00
MS083012 12 OF 15
PART 3 - EXECUTION

3.1. REQUIREMENTS FOR CLOSE-OUT DOCUMENT SUBMISSION

3.1.1. Recording: Maintain one (1) copy of each Close-out Document during the construction
period. Post changes and modifications to Close-out Documents as they occur to facilitate
Owner inspections and review for Contractor’s Application for Payment. Provide access to
Close-out Documents for Owner and Architect/Engineer review during normal working hours.

3.1.2. All final Record Documents (drawings and specifications) and Close-out Documents shall be
submitted in Adobe PDF format with the file structure bookmarked by content organization
and text searchable by keyword. Organize content into sets of manageable size.

3.1.2.1. Verify that all pages on every document have been scanned. All documents shall be
scanned with optical character recognition (OCR) technology. Review each page to
ensure that the scan captures original detail. If images appear too dark or too light, or
smudged, rescan the page to ensure proper image quality and legibility. Color charts
or other documents where color is required to convey full information shall be scanned
in color.

3.1.3. Record drawings shall be submitted using the Owner’s electronic file naming convention to
enable each sheet to be readily searchable. Submit record drawings and specifications in
Owner’s native software.

3.1.4. In addition to electronic files, furnish two (2) paper hardcopies to Owner of all Close-out
Documents, bound in heavy-duty, 3-ring vinyl-covered binders including pocket folders for
folded sheet information. Binder content shall be divided with plastic-covered tabs for each
section of each manual. Contractor shall mark identification on both the front and spine of
each binder.

3.2. PROJECT CLEANING AT SUBSTANTIAL COMPLETION

3.2.1. The Contractor shall maintain the Project and the Site in a clean and orderly condition
throughout the course of construction. In addition to continuous Project cleaning, the
following requirements are related to Project Close-Out. Special cleaning for specific units of
Work may also be specified in other Sections of Project Specifications.

3.2.2. Contractor shall perform an initial cleaning of the Work consisting of cleaning each surface or
unit of Work to normal "clean" condition expected for a first-class building cleaning and
maintenance program.

3.2.3. Contractor shall comply with manufacturer's instructions for cleaning of all system
components, equipment, and materials incorporated into the Project.

3.2.4. Contractor shall perform the following "initial" final cleaning immediately prior to the time the
Contractor requests Substantial Completion inspection.

3.2.4.1. Remove labels that are not required as permanent labels.

3.2.4.2. Clean, according to manufacturer’s recommendations, exposed hard-surfaced finishes,


including glass, metals, stone, concrete, painted surfaces, plastics, tile, wood, special
coatings, and similar surfaces, to a dirt-free condition, free of dust, stains, films and
similar noticeable distracting substances. Restore reflective surfaces to original
condition.

3.2.4.3. Remove debris and surface dust from limited-access spaces including plenums, shafts,
and similar spaces.

The University of Texas PROJECT CLOSE-OUT PROCEDURES


MD Anderson Cancer Center 01 77 00
MS083012 13 OF 15
3.2.4.4. Clean concrete floors in non-occupied spaces, wet-mop and broom clean.

3.2.4.5. Clean fixtures of all dust and debris. Replace lamps in accordance with Technical
Specifications after final Project cleaning.

3.2.4.6. Remove crates, cartons and other flammable waste materials or trash from the Site.
Provide Owner with a finished Project that is free of concealed garbage, trash and
rodent infestation. If concealed garbage, trash and rodent infestation are revealed, or
odors from them occur, Contractor shall remove and correct at the Contractor’s
expense. Restore property to its original condition where no improvements are shown.

3.2.4.7. Clean spaces such as elevator shafts, equipment rooms, pipe and duct chases, furred
spaces, and other similar unfurnished space to leave free from rubbish, loose plaster,
mortar drippings, extraneous construction materials, dirt, and dust.

3.2.4.8. Remove rubbish by way of chutes, taken down on hoists, or lowered in receptacles.
Contractor shall not remove rubbish or waste by dropping or throwing from one level to
another within or outside the building(s).

3.2.5. Contractor shall not mark, soil or otherwise deface finished surfaces. If Contractor marks,
soils, or otherwise defaces finished surfaces, Contractor shall bear all costs for cleaning and
restoring such surfaces to their originally intended condition.

3.3. PROJECT CLEANING AT FINAL ACCEPTANCE

3.3.1. Contractor shall complete the following "final" cleaning immediately prior requesting a Final
Completion inspection:

3.3.1.1. Clean transparent materials, including mirrors and window/door glass, to a polished
condition, removing substances that are noticeable as vision-obscuring materials.

3.3.1.2. Turn the work over in immaculate condition inside and outside the premises.

3.3.1.3. Clean all work on the premises including walks, drives, curbs, paving, fences, grounds
and walls. Provide a clean shine on slick surfaces. Remove smudges, marks, stains,
fingerprints, soil, dirt, paint, dust, lint, labels, discolorations and other foreign materials.

3.3.1.4. Clean all finished surfaces on interior and exterior of Project including floors, walls,
ceilings, windows, glass, doors, fixtures, hardware and equipment. Final wax and
polish all natural finish metal on interior or exterior surfaces. Clean and apply finish
(including wax) to all floors as recommended by the manufacturer and accepted by
Owner.

3.3.2. In addition to the cleaning specified above and more specific cleaning required in the various
technical Specifications, Contractor shall prepare the building(s) for occupancy by a thorough
cleaning throughout, including washing (or cleaning by approved methods) surfaces on which
dirt or dust has collected, and by washing glass on both sides leaving a smear-free shine.
Contractor shall wash exterior glass using a window-cleaning contractor specializing in such
work.

3.3.3. Contractor shall remove temporary buildings and structures, fences, scaffolding, surplus
materials and rubbish of every kind from the Site. Contractor shall repair these areas to be
compatible with the surrounding construction finished condition.

END OF SECTION 01 77 00

The University of Texas PROJECT CLOSE-OUT PROCEDURES


MD Anderson Cancer Center 01 77 00
MS083012 14 OF 15
Attachment No. 1 – Record Documents Edit Log
Download an Electronic Version of the Record Documents Edit Log template at the following Internet Address
http://www2.mdanderson.org/depts/cpm/standards/supp.html#templates

The University of Texas PROJECT CLOSE-OUT PROCEDURES


MD Anderson Cancer Center 01 77 00 – ATTACHMENT NO. 1
MS083012 15 OF 15