General Specifications
General Specifications
CONTENTS
GENERAL 1
EARTHWORK 2
CONCRETE 3
STONEWORK 4
BIULDING WORK 5
GENERAL
The drawings of the Tender Documents and any other modifications to those drawings and any
other drawings that may be prepared by the Contractor and approved by the Supervisor engineer
shall subsequently become the Contract Drawings.
For the purpose of carrying out the Contract, the Contractor will be provided with 2 sets of the
Contract Documents and Contract Drawings.
For convenience and in order to establish the necessary standards of quality, reference has been
made to specifications issued by national or other widely recognised bodies. Such specifications
shall be referred to as ‘Standard Specifications’ and shall be the latest editions of such Standard
Specifications issued prior to the issue of these Tender documents together with such additions
or amendments as may have been issued prior to the same date.
BS British Standard
ISO International Organisation for Standardisation
ASTM American Society for Testing and Materials
ASA American Standards Association
IGTS Iraqi general technical specification.
NCCL National centre for construction laboratories.
All drawings, calculations, plans, reports, instruction manuals, pamphlets, data and all other
documents required to be submitted by the Contractor under the Contract shall be clear and
readable.
All the drawings and calculation to substantiate the design shall be checked, signed and
approved by the Contractor prior to submission.
The Contractor shall be obliged to attend all meetings at the appointed time. The discussions of
such meetings shall include but not be limited to the progress of work and problems having direct
bearing on the immediate and long term activities (construction, procurement, transport, labour
etc.).
The Supervisor engineer shall invite the Employer for such meetings.
1.7 Records
The Contractor shall take photographs of the Facility and the Depots before starting construction
and keep detailed records as specified below and as directed by the Supervisor engineer, and
submit them at least once a week to the Engineer for his approval.
1.8 Reports
The Contractor shall submit from time to time to the Supervisor engineer reports, notices and other
documents as specified in the Specifications and as directed by the Supervisor engineer. The
reports and notices shall include, but not be limited to the following:
The following documents shall be submitted to the Supervisor engineer in a separate volume
from paragraph (1) above:
(1) Number and classifications of labour engaged in the Works on daily basis,
(2) Erection and job site processing equipment and materials used, and
(3) Any problem and solution.
The Contractor shall furnish to the Supervisor engineer at the completion of the Works the
reports and documents as described in the Clause 1.18.
(a) The drawings provided in the book of drawings issued for Tender
(b) Such other drawings and/or sketches as are issued from time to time by the Engineer to
deal with design modifications in response to on-site conditions.
(c) Where shop drawings are to be used, the Contractor, unless otherwise specified, shall
submit not later than seven (7) days before the beginning of a trade work to the
Supervisor engineer for his approval three (3) copies of all shop and setting-out drawings
and schedules required for its work. No work shall be commenced before approval of the
Supervisor engineer for such drawings and schedules.
The survey control points and benchmarks shown on the drawings shall be handed over to the
Contractor as basis for surveying and setting out of Works.
Before using the control points and bench marks for setting out of the Works, the Contractor shall
carry out a check survey thereon and satisfy himself as to their accuracy. The Employer shall
bear no responsibility for the accuracy of any control point or benchmark.
The Contractor may establish additional temporary bench marks for his own convenience but
each temporary bench mark shall be of a design and in a location approved by the Supervisor
engineer and shall be accurate in relation to the bench marks established by the Supervisor
engineer.
The Contractor shall protect the reference points and level bench marks and in the event of any
damage he shall re-survey and re-establish the points and bench marks.
The Contractor shall appoint and employ the necessary qualified and experienced staff to set out
the Works accurately. The Contractor shall establish and locate all lines and levels and be
responsible for the correct location of all Works.
Where directed by the Supervisor engineer, the Contractor shall take such levels and dimensions
as may be required for the purposes of measurements prior to disturbance of the ground. These
shall be agreed between the Contractor and the Supervisor engineer in writing before any surface
is disturbed or covered up.
The Contractor shall be solely responsible for and shall provide all labour, tools, lifting tackle and
other equipment required for the construction and checking of the Works.
No operatives shall be allowed to execute any type of work, which is normally carried out by a
skilled tradesman, unless the operative is thoroughly experienced and proficient in the trade
concerned. Supervisors and operatives may be required to demonstrate their proficiency or
produce certificate of competence to the satisfaction of the Supervisor engineer.
As each part of the work is carried out it shall be subject to the approval by the Supervisor
engineer.
The Contractor will be required to maintain a competent supervising Site Agent and staff on site
throughout the construction period until completion of the Works, and thereafter as may be
required during the defects liability period. The Supervisor engineer shall give prior approval to
the appointment of this supervising Site Agent and key staff and shall have authority to withdraw
the approval at any time in accordance with the Conditions of Contract.
All staff and labour employed on the Works shall be employed in accordance with the local labour
and employment laws and regulations.
The Employer of GIZ reserves the right to execute, on the site, works not included under this
Contract and to employ for this purpose either his own employees or other contractors whose
contracts may be either a sub-contract under this Contract, or an entirely separate contract. The
Contractor shall ensure that neither his own operations nor trespass by his employees shall
interfere with the operations of the Employer, or his contractors employed on such works and the
same obligations shall be imposed on the Employer or other contractors in respect of work being
executed under this Contract.
The Employer shall provide, free of charge, areas of land where the Contractor shall establish the
store. The location of stores shall be to the approval of the Supervisor engineer.
The Employer reserves the right to allocate areas of land less than the Contractor may require.
In such case, the Contractor shall make his own arrangement for obtaining the use of the
additional areas that he requires.
The Site shall include all those areas of land which, being public or private:
(a) Are being provided by the Employer for the purpose of constructing the permanent works.
The lands and other places outside the Site which are the property of or under the control of the
Employer shall not be used except with the approval of the Supervisor engineer.
The Supervisor engineer shall at any time remove any vehicle or vessel or any other obstruction
under his control that may be required to be removed by the Engineer for any purpose. The
Contractor shall move such obstruction promptly on instruction being given.
The Supervisor engineer shall maintain access for the inspection, operation and maintenance of
any of the Employer's works which lies within the Site.
The Contractor shall not use any portion of the Site for any purpose not connected with the
Works unless the written permission of the Supervisor engineer has been obtained.
The Contractor shall restrict his activities to those areas of the Site adjacent to the works being
executed and shall avoid any encroachment upon lands outside the areas for which possession has
been given. Any trespass or damage or any claim arising from such encroachment shall be the
Contractor's sole responsibility and he shall hold the Employer indemnified against all claims arising
from such trespass or damage.
The Contractor shall not interfere in any way with any existing works, whether the property of the
Employer or of a third party, whether or not the position of such works is indicated to the Contractor
by the Engineer, except where such interference is specifically described as part of the Works,
either in the Contract or in an instruction from the Supervisor engineer.
The Contractor shall secure all the permits, except for the Building permission undertaken by the
Employer, the licenses necessary for progress of the Works, and negotiate to obtain permission
with the authorities concerned.
All material shall comply with appropriate Standard Specifications unless otherwise required
hereinafter.
The Contractor shall, before placing any order of materials, manufactured articles or machinery
for incorporation in the Works, submit for the approval of the Supervisor engineer the names of
the suppliers from whom he proposes to obtain such materials, manufactured articles or
machinery, together with a list of the same, giving the origin, quality, weight, strength, description
and other relevant details. No materials, manufactured articles or machinery shall be ordered or
obtained from any suppliers which the Supervisor engineer has not approved in writing.
All materials shall be delivered to the Site a sufficient period of time before they are required for
use in the Works, to enable the Supervisor engineer to take such samples as he may wish for
testing and approval.
Notwithstanding the fact that approval has been given to the source of supply, the Supervisor
engineer may forbid the use of any materials if, upon delivery, they are found to be defective, or
he considers them unsuitable for incorporation in the Works. Such rejected materials shall be
removed from the site forthwith.
The Contractor may propose alternative materials of equivalent quality to those specified, and
subject to the approval, such materials may be used in the Works.
The Contractor shall have no claim against the Employer in respect of any financial loss which he
may suffer as a result of the rejection of any such materials, and he shall also bear the cost of
removing them from the Site.
The Supervisor engineer shall have the right to inspect materials and plant for the permanent
works during the course of manufacture. The Contractor shall arrange for the right of access to
manufacturing premises for the Supervisor engineer and his staff during normal working hours.
The Supervisor engineer shall be given sufficient notice by the Contractor to allow him to observe
the testing of any materials for the works at the place of manufacture. The Supervisor engineer
If requested by the Supervisor engineer, the Contractor shall provide to the Engineer copies of
orders for the supply of goods or materials required in connection with the works.
Materials or work which, in the opinion of the Engineer, do not comply with the Specification, shall
be classified as rejected materials or defective work, and shall be cut out and removed from the
Works and replaced as directed by the Supervisor engineer.
The Contractor shall acquaint himself with the positions of all existing works and services
including water mains, storm water drains, cables and service poles before any excavation is
commenced.
The Contractor will be held responsible for any damage, however caused, in the course of the
execution of the Works, to such existing works and services.
Such existing works and services, where exposed by the execution of the works, shall be
properly shored, hung-up and supported to the satisfaction of the Supervisor engineer and of the
authority concerned.
Poles supporting cables and the like adjacent to the Works shall be kept securely in place until
the Works are completed and shall then be made as safe and permanent as before.
Notwithstanding the foregoing requirements and without lessening the Contractor's responsibility,
the Contractor shall inform the Supervisor engineer immediately any existing works have been
exposed and shall comply with any requirements of the authority concerned.
Only when and as directed by the Supervisor engineer shall the position of existing works or
services be changed by the Contractor to meet the requirements of the proposed work.
The laying of pipework, ducts, drains, and the like shall be arranged so as to cause as little
interference as possible with the smooth operation of existing works.
When breaking out and making good existing structures, the Contractor shall disturb the existing
structures as little as possible. All structures shall be made good with materials similar to those
used in the existing works, or such materials which are considered by the Supervisor engineer to
be of similar appearance and suitable in all other respects.
The Contractor shall be solely responsible for the location, procurement and maintenance of a
water supply adequate in quality and quantity to meet his obligations under the Contract.
The Contractor shall make his own arrangements for power supplies and shall be solely
responsible for the location, procurement and maintenance of a power supply, adequate to meet
his obligations under the Contract.
The Engineer will give the Contractor due notice of his intention to carry out any inspection during
the defects liability period. The Contractor shall, upon receipt of such notice, arrange for a
responsible representative to be present at the times and dates named by the Supervisor
engineer. This representative shall render all necessary assistance and shall take note of all
matters and things to which his attention is directed by the Supervisor engineer.
The Contractor shall provide and maintain in first class working order, for the sole use of the
Engineer and his staff for the duration of the Contract, the minimum survey instruments complete
with all accessories, tapes, poles, staves, stagings, moulds, templates, profiles, and requisites
necessary for checking and setting out, and measurement of the Works. The equipment shall
revert to the Contractor at the end of the Contract period.
The Contractor shall keep the whole of the Works free from water and shall be deemed to have
included in his Contract Sum all costs for pumping, shoring, temporary drains, sumps and other
measures and provisions necessary for such purposes and for clearing away and making good to
the satisfaction of the Supervisor engineer any damage caused thereby.
The Contractor is advised that, at all times, it is necessary to guard against fires starting within
the Site or in the environs thereof, particularly as the result of the Works or from the actions of his
employees. The Contractor shall have available, at all times; a trained fire-fighting team provided
with adequate fire-fighting equipment and shall deal with all fires on the Site howsoever caused.
The Contractor shall be responsible for maintaining qualified fire fighting crew on the Site at all
times as well as maintaining an efficient fire alarm system.
The Contractor shall comply with laws and regulations regarding fires and with respect to the
prevention of fires. No fire may be lit in the dry season without written permission from the
Supervisor engineer and/ or the relevant Authority.
The Contractor shall take all necessary precautions against risks of loss of life or of injury to any
person employed on the Works or to employees of the Employer and to the Supervisor engineer
or to visitors or to persons having good and sufficient reasons to be about the Works, and to this
end he shall properly safeguard the Works to the satisfaction of the Engineer.
The Contractor shall at all times comply with any accident prevention regulations and any safety
regulations peculiar to the various trades employed on the Works, and any safety regulations
published by the Government.
The Contractor shall report promptly to the Supervisor engineer all accidents involving the death
of or serious injury to any person on the Site or resulting from the Contractor’s operations.
The Contractor shall, at his own expense, educate all his employees on safety precautions based
on good practice on site. This shall be done in both English and the local languages. Safety
instructions shall deal with all safety measures including but not be limited to the following;
protective clothing, helmets and footwear, use of lifting equipment, precautions against electrical
shock, welding, routine procedures in case of accidents, fires, etc., watchmen, warning notices
and barriers, use of drilling equipment and dust suppression and use and storage of explosive.
The Contractor shall make arrangements to transport, store and handle explosives and fuels in a
safe manner for protecting the public in accordance with the laws and security regulations in
force.
The Contractor shall obtain all necessary licenses and shall pay all fees and charges in respect of
the same as may be necessary for the purpose of moving explosives and fuels from place to
place and storing the same, and shall make all applications and obtain approvals from the
relevant authorities of the Government.
During thunderstorms and other electrical disturbances, no charging and firing will be permitted.
The Contractor shall employ competent watchmen to guard the Works both by day and night.
Any excavations, material dumps, spoil dumps or other obstructions likely to cause injury to any
person or thing shall be suitably fenced off and at night marked by red warning lights.
During the performance of the work the Contractor shall carry out proper and efficient measures
wherever and as often as necessary to reduce the dust nuisance resulting from his operations.
All work shall be carried out without unreasonable noise. Compressors used on site shall be
silenced either by using only full silenced models or fitted with effective exhaust silencers and
properly lined and scaled acoustic covers all to the design of the manufacturers of the
compressor or by the use of effective acoustic screens to enclose the noise source. Pneumatic
percussion tools used on Site shall be fitted with silencers of a type recommended by the
manufacturers of the tools. Compressors, silencers or other equipment shall be maintained in
good and efficient working order.
No separate payment will be made for noise suppression measures and the costs thereof shall
be included in the unit rates and the Contract Sum.
1.34 Sanitation
The toilet facilities provided at the site by the Contractor shall be made available, free of charge,
to the employees of the Contractor and any of his subcontractors.
The Contractor shall warn his employees and sub-contractors that any employee found fouling
the site shall be removed from the site immediately in accordance with the Conditions of
Contract.
The Contractor shall remove all rubbish and to this end shall provide adequate number of
covered garbage bins/containers placed at convenient points around the site establishments.
The Contractor shall institute and maintain a regular garbage collection and disposal system.
Garbage shall be disposed of by burial or by other means approved by the Supervisor engineer.
No separate payment will be made for such sanitary arrangements and all such costs will be
deemed to be included in the unit rates and Contract Sum.
The Contractor shall provide and maintain all equipment necessary to render First Aid in case of
accidents, snakebites or other emergencies. The Contractor shall ensure that there are persons
available to all such places with knowledge of simple First Aid procedures and able to administer
snakebite treatment.
On completion of the Works, the Contractor shall clear the site; the whole of the site shall be left
in a clean and tidy condition.
The following abbreviations have been used for units and for other words or phrases as indicated.
mm millimetre
Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH
11
Building Construction: August 2020
m meter
km kilometre
sq.m,m2 square metre
ha hectare
cu m,m3 cubic metre
sec,s second
hr hour
min minute
wk week
l litre
gm gram
kg kilogram
t tonne
No Number
nr Number (in bill of quantities)
dia diameter
max maximum
min minimum
AD above datum (levels in metres)
ch chainage (distance in metres)
eo extra over
e exceeding
ne not exceeding
PQ Provisional Quantity
PS Provincial Sum
Do Ditto
fob free on board
cif cost, insurance, freight
wt weight
% percent
mh manhole
ic inspection chamber
HYS high yield steel
PCC precast concrete
uPVC uplasticised polyvinylchloride
GMS galvanised mild steel
DI ductile iron
SV sluice valve
ISO International Standards Organisation
KS Kenyan Standard
BS British Standard
KShs. Kenya Shillings
2 EARTHWORKS
General clearance and site preparation is defined as the clearing, grubbing, removal and disposal
of all vegetation, grass in outside facilities of the school, and backfilling of holes left by the
removal of stumps and roots.
The widths and length over which site clearance is to be carried out shall be instructed by the
Engineer. If termite moulds are excavated, the whole of the mould shall be removed.
After the area of any section of the Works has been cleared and after trees have been felled,
stumps removed and termite moulds excavated to the satisfaction of the Engineer, but before any
other work is commenced, surface levels of the ground shall be taken. The levels shall be taken
at spacing’s agreed with the Supervisor engineer. Levels shall similarly be taken on the surface
of the ground after the removal of unsuitable overburden prior to placing fill and at the interface
between natural ground, rock or artificial hard material layers. The levels shall be agreed with the
Supervisor engineer. The Contractor shall prepare plans and sections which shall, when finally,
and mutually agreed, be signed by the Engineer and Contractor as truly representing the
configurations of the areas in question at the commencement of excavation or fill construction.
Excavation shall be carried out with the allowances for working space given in the Method of
Measurement to the Bill of Quantities, unless otherwise shown as lines, levels and profiles on the
Drawings or to such other lines, levels and profiles as the Supervisor engineer may direct or
approve in writing. The work shall be carried out by the Contractor in such a way as to avoid
disturbance to the surrounding ground. Particular care shall be taken to maintain stability when
excavating in close proximity to existing works.
The Contractor shall dispose of all material arising from excavations to outside of the
municipalities border
The Contractor shall be responsible for keeping all excavations free from water from whatever
cause arising and shall provide such pumping capacity and other measures as may be necessary
for this purpose. The Contractor shall make good any damage that may result from his failure to
keep the excavations free from water.
All excavation shall be carried out with care and the method and Contractor’s equipment to be
used in execution thereof shall be to the satisfaction of the Engineer. The Contractor shall be
responsible for the safety and security of all excavations at all times during the execution of the
contract
The Contractor will be permitted, subject to the approval of the Supervisor engineer, to adjust
side slopes of excavations in soft materials which are to remain open temporarily in preference to
shoring or strutting. However, no payment shall be made for extra excavation volume as a result
of these measures.
The Contractor shall notify the Supervisor engineer without delay of any permeable strata,
fissures or unusual ground encountered during excavation.
When excavations have been taken out accurately to the profiles or dimensions required for the
work the Contractor shall inform the Engineer who shall carry out an inspection of the excavation.
If, after his inspection the Supervisor engineer requires additional excavation to be carried out,
the Contractor shall do so to such new profiles or dimensions as the Supervisor engineer may
direct.
Open excavation to form a foundation for a structure shall be carried out to the lines necessary to
permit the proper construction of the structure to the approval of the Supervisor engineer.
Where a structure is to be founded on soft ground, the excavation shall be taken down until the
required formation is exposed and prepared to the approval of the Supervisor engineer. Where
concrete has to be placed on a soft foundation, the Supervisor engineer may direct that a blinding
layer of lean concrete be placed beneath the structural concrete immediately after completion
and approval of the excavation, or require the Contractor to remove the last 100 mm of
excavation immediately prior to placing the concrete. If foundation conditions are very soft the
Supervisor engineer may instruct that additional material be excavated and replaced with
compacted gravel or hardcore.
Where a structure is required to be founded on rock but is not required to penetrate into it, all soft
overburden shall be removed and the surface of the rock cleared of any loose material by barring
and wedging. Where the foundation is required to penetrate into the rock, excavation of the rock
may be carried out by blasting but in such a manner as to prevent the shattering of the rock which
is to remain. The Supervisor engineer may direct that the last 300 mm of rock be left and be
removed by barring and wedging or by the use of approved pneumatic tools so that the exposed
surface is sound.
The Contractor shall report to the Supervisor engineer whenever excavations are ready to
receive concrete. No concrete shall be placed in the foundations until the Contractor has
obtained the Supervisor’s engineer agreement that a secure foundation has been reached and
that the excavation has been carried out to the lines and levels required.
Foundations for embankments shall be excavated to the depths or to the soil or rock grade
indicated on the Drawings or described in the Specification. The suitability of each part of the
foundation for placing fill thereon shall be determined by the Supervisor engineer. No fill shall be
placed before acceptance of the foundation by the Supervisor engineer and recording of the
geology.
Where specified in the Drawings or Specification or directed by the Supervisor engineer, seams
and other defects below the general level of the foundations shall be excavated and filled or
covered with materials including mortar and concrete to the satisfaction of the Supervisor
engineer before fill is placed thereon.
Where embankments are to be constructed on sloping ground, and where shown on the
Drawings, benches shall be e
\xcavated in the foundations to the dimensions shown on the Drawings.
Except where specifically permitted by the Supervisor engineer all foundations for fill shall be kept
free of water when placing fill thereon.
Trench excavation shall be performed by the use of hand tools and approved mechanical
equipment, in such manner as to minimise disturbance of the sides and bottom of the excavation.
Trenches for pipes shall be excavated to a sufficient depth to enable the pipe and the specified
joint, bedding, haunching and surround to be accommodated. Unless otherwise stated, the width
of the trench shall be equal to the nominal diameter of the pipe plus 600 mm.
The Contractor shall fill any over excavation beneath the pipe or bedding at his own cost with well
rammed selected general excavation material as per requirement of this Specification. The
Contractor shall dispose of surplus excavated material not required for backfill to spoil tips.
The sides of trenches shall be adequately supported at all times. Alternatively, where the
Contractor has to excavate the trenches in open cut the Contractor shall ensure that the side
slopes of the excavation are sufficient for stability.
Where rock or boulders are present in the sides or base of a trench in which a pipe is to be
installed, the trench shall be trimmed so that when the pipeline is laid, no projection of rock
comes within 200 mm of the outside of the pipe at any point. The over excavated portion shall be
backfilled as set out in this Specification with approved granular material at the Contractor’s
expense.
The Contractor shall be entirely responsible for the sufficiency of all temporary supports and side
slopes to the excavations. The excavation shall be carried out in such a way as to maintain the
stability of all roads and other adjacent structures or works.
The excavation of all channels shall be executed in such a manner as to ensure that the stability
of side slopes is not endangered. Should slips or undercutting occur for reasons attributable to
the Contractor's negligence or method of working, the Supervisor engineer will give instructions
for remedial works to be carried out by the Contractor at the expense of the Contractor.
Where channels are to be reshaped, cleared and trimmed, the width, depth, side slopes and
centre line radius shall be as shown on the Drawings. The Contractor shall clear all weeds and
growth from existing channels and grade the beds to required levels. The area of waterway
shown is the minimum required and sides of channels shall be trimmed to the required slope so
as to provide widths not less than those shown on the Drawings.
Any channels, streams, drains or pipes taking water to or from cultivated land shall be diverted so
as to maintain their flow before being moved or broken into unless express permission to the
contrary is given by the Supervisor engineer. All diversions and their subsequent reinstatement
are to be carried out to the satisfaction of the Supervisor engineer. The Contractor shall be
deemed to have included the cost of dealing with this in his rates.
Side banks of channels shall be trimmed to a neat appearance and even surface.
In the construction of channels and embankments a local balance of cut and fill shall be
maintained as far as possible unless the cut is unsuitable material or is specified in the drawings
that the fill should be imported. A deficiency of fill material shall be made up by bed borrow or
gleaning. Surplus material, if suitable and approved by the Supervisor engineer may be used for
Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH
15
Building Construction: August 2020
an increased width of embankment otherwise it may be spread at the toe of the embankment or
placed on spoil tips as directed by the Supervisor engineer.
Where required the Contractor shall control the rates of filling and draw-down of water in
channels so as not to endanger the stability of earthworks.
All material not suitable for embankments or other filling shall, unless otherwise directed by the
Supervisor engineer, be taken to disposal outside of municipality border.
The cost of disposal of shall be deemed to be included in the respective unit rates for the
excavation work and the Contract Sum.
Backfilling of structural excavations shall be carried out with excavated material selected or
approved by the Supervisor engineer. The material shall be placed in layers not exceeding 250
mm compacted thickness or such other thickness as the Supervisor engineer may approve or
direct.
When material is filled up to or over any structure, the filling shall be brought up equally on each
side or as otherwise agreed by the Supervisor engineer so that no unequal pressures likely to
cause damage to the structure are applied.
The material to be used as filling under raised foundations shall consist of suitable material
obtained from adjacent excavations or approved borrow sources, and shall be placed in layers
not exceeding 150 mm compacted thickness.
3 CONCRETE
Concrete shall consist of cement, graded aggregate and water carefully proportioned, thoroughly
mixed, placed and compacted as specified.
The Contractor shall obtain formal approval from the Supervisor engineer before pouring any
concrete for the permanent works. The Supervisor engineer shall allow concreting after
ascertaining the required lines and levels, suitability of formwork, availability of required
equipment and labour, proper fabrication and spacing of the steel bars and quality and quantity of
cement and aggregates.
3.2 Cement
All cements shall be certified by the manufacturers as complying with the requirements of the
specification. Before orders are placed the Contractor shall submit details of the proposed
supplier(s) together with such information on the proposed methods of transport, storage and
certification so that the Supervisor engineer may satisfy himself that the quantity and quality
required can be supplied and maintained throughout the construction period. Where necessary
the Supervisor engineer may require representative samples of the proposed cement to be taken
and forwarded to a nominated laboratory for analysis and testing before the source is approved.
No cement shall be used in the Works until deemed satisfactory by the Supervisor engineer.
Cement shall be obtained from one manufacturer unless otherwise authorised by the
Engineer. Should the use of cement from different manufacturers be authorised, the
different supplies of cement shall be stored separately and shall not be mixed.
The Contractor shall supply to the Engineer copies of the manufacturer's test certificates
certifying that each consignment of cement has been tested and analysed, and that the
results comply in all respects with the above standards. Each certificate shall state clearly
the date of despatch and the number of bags despatched in each consignment.
Bagged cement shall be delivered in sealed 50 kilogrammes sacks. Each bag shall be
marked with the parcel number of the cement contained. Bagged cement shall be
transported so that at no time is it exposed to damp and so that moisture cannot be
absorbed from the atmosphere. Cement in bulk shall be transported in totally enclosed
water tight and sealed containers.
The Contractor shall provide sufficient storage capacity on Site to ensure that his anticipated
programme of work is not interrupted due to lack of cement. Factors outside the
Contractor's control such as transport, weather conditions, holidays and breakdowns shall be
taken into account.
Cement delivered to the Site in bulk shall be stored in dry, well ventilated weather proof silos
or bins which shall be self clearing. Cement delivered to the Site in bags shall be stored in
dry, weather-proof sheds which shall have floors of damp proof construction raised at least
150 mm above the surrounding ground.
Cement of different consignments shall be stored separately and consignments shall be used
in the same order as they are delivered to the site. No cement shall be stored on the site for
longer than three months from the date of despatch by the manufacturer. If not used within
that period, the cement shall be removed from the site.
Cement shall be tested by the manufacturer. If the manufacturer's test certificate is not made
available, representative samples shall be taken from different bags or containers of each
consignment. They shall be suitably packed and sent to an approved laboratory for testing to prove
the cement's compliance with the specified standards.
The Supervisor engineer may require cement to be tested after its delivery to the site. Any cement
which has been in store at the site for longer than one month shall be re-tested.
The Supervisor engineer may take samples of cement from cement bins or bagged cement, from a
parcel of cement after its delivery to the site, or from a parcel of cement which has been stored at
the site for longer than one month.
In addition to the manufacturer's tests the Supervisor engineer may require the following tests to be
carried out to BS EN 196-3:
Any cement which fails to meet the specified requirements shall not be used in the Permanent
Works.
3.6.1 General
Aggregates for concrete shall comply with BS EN 12620, and shall be obtained from a source or
sources approved by the Supervisor engineer and shall be transported and stored in such a
manner as will prevent:
(a) Contamination of the aggregates from the ground, rubbish, vegetation, dust or any other
foreign material.
(b) Segregation.
(c) Intermixing of aggregates of differing characteristics.
Before aggregates from each source are approved for use in the Permanent Works, tests shall be
carried out at an approved testing laboratory on representative samples submitted by the
Contractor to check that the aggregates comply with the requirements of the Specification.
During concreting operations, tests shall be carried out to check that aggregates delivered for use in
the Permanent Works comply with the requirements of the Specification.
Moisture contents of aggregates shall be determined as the moisture content of the aggregate
compared with that of the aggregate in the saturated surface-dry condition. Specific gravities of
aggregate shall be determined on aggregate in the saturated surface-dry condition.
Aggregates shall be stored on a clean, free draining surface. The various types and sizes of
aggregates shall be kept separate from each other and each stockpile shall be kept as large as
possible to maintain a reasonably uniform content in the aggregate.
Fine aggregates shall be clean and durable and shall be natural sand, crushed gravel sand or
crushed rock sand complying with BS EN 12620. All the material shall pass through a 5 mm BS
Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH
18
Building Construction: August 2020
sieve. In order to achieve an acceptable grading, it may be necessary to blend materials from more
than one source.
As an alternative, fine aggregate for mortar only shall comply with BS 1199 and 1200.
The fine aggregate shall not contain iron pyrites or iron oxides. It shall not contain mica, shale, coal
or other laminar, soft or porous materials unless the Contractor can show by tests on finished
concrete as set out in BS EN 12390 that the presence of such materials does not adversely affect
the properties of the concrete.
The proportion of clay, silt and other impurities passing a 75 microns BS sieve shall not exceed
three per cent for natural or crushed gravel sand or 15 per cent for crushed rock sand. The shell
content shall not exceed 15 per cent by weight.
Chlorides soluble in a 10 per cent solution by weight of nitric acid shall not exceed 0.05 per cent by
weight expressed as chloride ion when tested as set out in BS 812, subject to the further restriction
given in the note on total chloride content in sub-clause 3.5.5.
Soundness: After five cycles of the test set out in ASTM C88-76, the aggregate shall not show a
weight loss of more than 10 per cent.
Samples taken from the fine aggregate shall pass the colour test for organic impurities described in
sub-clause 3.6.4.
Tests on fine aggregates shall be carried out daily or as required by the Supervisor engineer on site
during concreting operations as follows:
(b) Moisture content. An approved "rapid" test may be used for this test.
(c) Percentage of material passing a 75 microns BS sieve by the Field Settling Test, checked
when necessary by the Decantation Method.
The Contractor shall arrange to carry out the following tests when requested by the Engineer:
When tested in accordance with ASTM C289, the aggregate shall be non-reactive.
Soundness: After 5 cycles of the test set out in ASTM C88-76, the aggregate shall not show a
weight loss of more than 12 per cent.
Flakiness Index: When tested in accordance with BS 812 shall be as set out hereunder:
If the flakiness index of the coarse aggregate varies more than five units from the average value of
the aggregate used in the approved trial mix, a new set of trial mixes shall be carried out in the
workability of the mixes have been adversely affected by such variation.
Impact Value: Not more than 45 per cent when tested in accordance with BS 812.
Ten per cent fines value: Not less than 50 kN when tested in accordance with BS 812.
Shrinkage: When mixed with other ingredients in the approved proportions for concrete and tested
as set out in BS 1881, the shrinkage factor shall not exceed 0.05 per cent.
Water absorption: The aggregate shall not have a water absorption of more than 2.5 per cent when
tested as described in BS 812.
Tests on coarse aggregate shall be carried out daily or as required by the Engineer on site during
concreting operations as follows:
The Contractor shall arrange to carry out the following tests when requested by the Engineer:
Aggregates shall be tested for organic impurities by means of discoloration of a sodium hydroxide
solution as follows:
A 340 ml graduated prescribed bottle shall be filled to the 123 ml mark with a sample of the
aggregate to be tested. A 3 per cent solution of sodium hydroxide in water shall be added until the
volume of the aggregate and liquid after shaking gives a total volume of 194 ml. The bottle shall be
stoppered, shaken thoroughly and allowed to stand for 24 hours. Should the liquid then be darker
than the standard colour solution the aggregate shall not be used for making concrete.
The standard colour solution shall be prepared in a 340 ml prescription bottle as follows:
2.5 ml of a 2 per cent solution of tannic acid in 10 per cent alcohol shall be added to 97.5 ml of a 3
per cent solution of sodium hydroxide in water. The mixture shall be shaken and allowed to stand
for 24 hours.
A glass of the standard colour may be used in place of the standard solution.
The total chloride content arising from all ingredients in a mix, expressed as chloride ions as a
percentage of the weight of cement in a mix, shall not exceed 0.5 per cent in any one sample nor
0.3 per cent in 95 per cent of the samples tested. For pre-stressed concrete, steam cured concrete
or concrete containing sulphate resisting cement or super sulphated cement, the total chloride
content shall not exceed 0.5 per cent of the weight of cement in the mix.
The total sulphate content arising from all ingredients in a mix shall not exceed 0.4 per cent by
weight of the aggregates or 4 per cent of the weight of cement in the mix, whichever is less. For
this purpose, the sulphate contents shall be expressed as SO3 and shall be calculated from the
sulphate contents of the cement, aggregates and any admixtures. Where applicable, sulphate
contents shall be determined in accordance with tests described in BS 1047 and 3892.
Pulverised fuel ash shall not be used in conjunction with a cement complying with the requirements
of BS 4027 in concrete required to be resistant to sulphates.
3.7 Admixtures
Admixtures for improving workability, accelerating or retarding setting of concrete, or for any other
purpose, shall comply with BS EN 934 and only be used with the Supervisor’s engineer written
approval. Calcium chloride or admixture containing chlorides will, however, not be approved.
The Contractor shall submit samples of the admixtures he proposes to use to the Supervisor
engineer for testing. If an admixture is approved for use it shall be obtained from an approved
supplier and the Contractor's arrangement for measuring, mixing and adding the admixture to the
concrete batch shall be strictly in accordance with the manufacturer's instructions or
recommendations and subject to the approval of the Supervisor engineer.
The proportions of the concrete mixes and water/cement ratio shall be adjusted to the satisfaction of
the Supervisor engineer so that the strength of the concrete with admixture is at least equal to the
strength of the equivalent concrete without admixture.
Clean fresh water complying with BS EN 1008 is to be used for the mixing of all concrete and
mortar, and is to be from a source approved by the Supervisor engineer.
The design of concrete mixes shall be the sole responsibility of the Contractor, but may be
undertaken in conjunction with the Supervisor engineer. Concrete mixes shall be designed mixes
in accordance with the requirements of BS 5328 having the characteristics specified in Table 3.1 of
this Specification. Concrete for use in water retaining structures shall comply with BS 8007.
Evidence shall be submitted to the Supervisor engineer, for all classes of concrete to be used,
showing that at the intended workability the proposed mix proportions and production methods will
produce concrete of the required quality.
The following information shall be provided before any designed mix is supplied:
No change in the approved mix design will be permitted, unless the Contractor carries out trials on
the proposed mix design to show that compliance with this Specification can be maintained.
Mix design shall in all cases be subject to the approval of the Supervisor engineer, but such
approval shall in no way relieve the Contractor of his responsibility for the design and production of
concrete in compliance with this Specification.
At least six (6) weeks before commencing the placing of any concrete in the works, trial mixes shall
be prepared for each class of concrete to be used on the works. Three (3) batches of each class of
concrete shall be made using materials typical of the proposed supply and under full scale
production conditions.
The workability of each of the trial batches shall be determined and three (3) cubes made from each
batch for testing at 28 days. A further three (3) cubes made from each batch may be made for tests
at an earlier age if required.
The trial mix proportions shall be approved if the average compressive strength of the nine (9)
cubes tested at 28 days exceeds the specified characteristic strength by 3 Newtons per square
millimetre, or if nine tests at an earlier age indicate that it is likely to be exceeded by this amount.
To demonstrate that the maximum free water/cement ratio is not exceeded, two batches of concrete
shall be made in a laboratory with cement and surface-dry aggregate known from past records of
the supplier of the material to be typical. The proposed mix proportions will not be accepted unless
both batches have the cement content specified and free water/cement ratio below the maximum
specified in Table 3.1.
A, B and C denote exposure conditions for the finished concrete as defined in BS 8007.
3.11.1 General
All concrete shall be sampled and tested in accordance with the requirements of BS EN 12350 and
BS EN 12390 unless otherwise stated in this Specification or instructed by the Supervisor engineer.
The Contractor shall allow for all the necessary labour, materials, and equipment necessary for the
regular sampling and testing of concrete to be placed in the Works.
Tests shall be carried out as required by the Supervisor engineer to determine the cement content
of the mix. The cement content of any batch of concrete shall not be less than the specified
minimum value minus 5 per cent of that value nor more than the specified maximum value plus 5
per cent of that value.
3.11.3 Workability
The workability of the concrete shall be measured as required by the Supervisor engineer by slump
tests or compaction factor tests and shall be within the following limits:
The required value shall be that which has been accepted under Clause 3.8 of this Specification.
The water/cement ratio shall be determined as required by the Supervisor engineer and shall not
exceed the specified maximum value by more than 5 per cent of that value.
Samples of concrete shall be taken for compressive strength at a rate of one sample per 15 m 3 of
concrete placed or 15 batches of concrete placed whichever is the lesser volume. A greater
frequency of sampling may be instructed by the Supervisor engineer until compliance with specified
strength requirements has been confirmed for each class of concrete used in the Works.
Two test specimens shall be prepared from each sample and shall be cured for 28 days, or by any
other method approved by the Supervisor engineer that enables the prediction of 28-day strength
at an earlier time.
On completion of curing, the two test specimens shall be tested. Provided the difference between
the two results does not exceed 14 per cent of the mean of the two results, the mean shall be taken
as the test result. Where the difference between the two results exceeds 14 per cent of their mean,
the lower of the two results shall be taken as the test result.
Compliance with the specified strength may be assumed if the conditions given in both (a) and (b)
below are satisfied.
(a) The average compressive strength determined from any one group of four consecutive 28-
day test results exceeds the specified characteristic strength by not less than 3 N/mm2 for
classes of concrete C20, C25 and C30 and not less than 2 N/mm2 for class C15 concrete.
(b) Each individual 28-day test results are greater than the specified characteristic strength
minus 3 N/mm2 for classes of concrete C20, C25 and C30 or 2 N/mm2 for class C15
concrete.
If only one tests result fails to meet the second requirement, then that result may be considered to
represent only the particular batch of concrete from which that sample was taken provided the
average strength of the group satisfies the first requirement.
If more than one result in a group fails to meet the second requirement or if the average strength of
any group of four consecutive test results fails to meet the first requirement, then all the concrete in
all the batches represented by all such results shall be deemed not to comply with the strength
requirements. For the purposes of this Clause, the batches of concrete represented by a group of
four consecutive test results shall include the batches from which samples were taken to make the
first and the last tests in the group of four, together with all the intervening batches.
Failure of concrete to comply with the specified requirements will result in it being classified as
defective work. Immediately on notification by the Supervisor engineer that concrete work is
defective, the Contractor shall take all measures necessary to improve concrete quality before
further concrete is placed in the Works. If required by the Supervisor engineer, the rate of sampling
of concrete shall be increased until adequate control is again established. Tests shall be carried out
on the defective concrete or test cores taken from it to establish its in-situ strength. If the results of
these tests satisfy the Supervisor engineer that the defective concrete will fulfil its design function,
then it may be accepted. If not, the Contractor shall propose strengthening or remedial work where
possible or shall remove the defective concrete from the Works.
The Contractor shall send weekly to the Supervisor engineer a return showing the quantities of
cement and the number of mixings of each class of concrete used in each section of the Works.
Records shall be kept by the Contractor of the positions in the Works of all batches of concrete,
of their class and of all test cubes or other specimens taken from them. Copies of these records
shall be supplied to the Supervisor engineer.
The design, layout, installation and operation of equipment for processing, handling,
transporting, storing and proportioning concrete ingredients and for mixing, transporting
and placing concrete shall be to the satisfaction of the Supervisor engineer. Before the
equipment is ordered or delivered to site, the Contractor shall submit to the Supervisor
engineer drawings showing the proposed arrangements of the equipment together with
detailed descriptions of the equipment proposed.
3.15 Batching
The aggregates and cement shall be proportioned by means of efficient weigh batching machines
except when the Supervisor engineer has approved the use of volume batching. The machines
shall be carefully maintained and cleaned and they shall be provided with simple and convenient
means of checking the accuracy of the weighing mechanism, and they shall be checked when
required by the Supervisor engineer.
Where the concrete is to be mixed in machines, these shall be of the batch mixing or other
approved type. The machines shall ensure that all the concreting materials including the water
are thoroughly mixed together before any portion of the mixture is discharged. The mixing time
shall not be less than thirty seconds per cubic foot (30 sec/cft) of concrete, with a minimum of
three minutes (3 min) mixing time per batch. The machines must be capable of discharging their
contents while running.
Where it is not possible to employ machine mixing and approval has been obtained from the
Engineer, concrete shall be mixed by hand as near as practicable to the site where it is to be
deposited. Clean mixing bankers or platforms of sufficient area for the proper execution of the
work shall be provided. These platforms if constructed of timber shall consist of planks closely
jointed so as to avoid the loss of any grout or liquid from the wet concrete. The whole of the
aggregate and cement shall be turned over on the banker in a dry state at least twice. The water
shall then be added gradually through a rose head, after which the materials shall again be
entirely turned over in a wet state at least three times.
Foundations which are to receive concrete shall be properly drained and dewatered so that
no water runs over or stands on a surface on which concrete is being placed. If required by
the Engineer drains provided through or beneath concrete for the temporary conveyance of
water shall afterwards be completely sealed to the Engineer's approval.
Before deposition of concrete against rock, the rock surface shall be thoroughly wetted and
cleaned by the application of water, or of water and air, under pressure. No concrete shall be
deposited until the surface has been cleaned and passed as satisfactory by the Supervisor
engineer.
Faults or seams in the rock shall be cleaned to a depth satisfactory to the Supervisor engineer
and if necessary stemmed with cement mortar of an approved mix.
Before any steel reinforcement is embedded in the concrete any loose mill scale, loose rust and
any oil, grease or other deleterious matter shall be removed. Partially set concrete which may
adhere to the exposed bars during concreting operations shall likewise be removed.
The Contractor shall give the Supervisor engineer at least 24 hours notice of his intention to
place concrete in a particular section of the Works. Before concrete is placed the Contractor
shall apply to the Supervisor engineer for approval of the cleanliness, alignment and
suitability of surfaces against which the new concrete is to be placed and of the fixing of
formwork, reinforcement, embedded parts and the like and he shall obtain written
permission from the Supervisor engineer to proceed with concreting.
The Contractor shall carefully plan his concreting operation to ensure, where possible, that
these operations are completed within the normal working day.
Unless otherwise approved by the Supervisor engineer concrete shall be cast in one operation
between external faces of concrete and joints shown on the Drawings or between
construction joints or both.
The Contractor shall submit and obtain the Supervisor’s engineer approval to a detailed
concreting programme and his proposals for the location of construction joints.
Concrete shall be transported and deposited in such manner as to prevent segregation, loss
of materials or contamination with foreign matter. The means of transport of concrete shall
be subject to the approval of the Supervisor engineer. The containers for conveying the
concrete shall be thoroughly cleaned immediately after use and sides dampened before work
is started or restarted to prevent cement and fine material in the first batch adhering to the
sides. Adequate precautions shall be taken to protect the concrete against wetting or drying
out through exposure to the weather and to prevent segregation and consolidation of the
mix due to prolonged jolting of the concrete. Concrete shall be placed in its final position
and fully compacted before the onset of initial set. Wherever possible, concrete shall be
Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH
26
Building Construction: August 2020
deposited vertically in the final position required and shall not be dropped through a greater
height than 1.5 m. Where necessary, bins, drop chutes, downpipes or baffles shall be
provided to prevent segregation of the material. Drying out of fresh concrete before
deposition shall be prevented by the provision where necessary of suitable covers. Loss of
slump during transport and deposition of the concrete shall not exceed 25 mm.
Concrete shall not be placed in standing or running water unless so specified. Where
concrete has to be placed under water, the Contractor shall submit to the Engineer his
proposals indicating the methods and equipment to be employed. The concrete shall be
deposited by bottom discharging watertight containers or through funnel shaped tremies
which are kept continuously full with concrete up to a level above the water and which shall
have the discharging bottoms immersed in the concrete in order to reduce to a minimum the
contact of the concrete with the water. Special care shall be taken to avoid segregation and
additional cement of about 25% must be added.
Concrete shall be placed in layers not exceeding 500 mm in depth approximately parallel to
the horizontal or inclined construction joint planes. These layers shall be deposited from one
face to the other until the full height of the lift is reached. Each layer shall be deposited on
the previous one before the latter has taken its initial set and the exposed area of fresh
concrete shall be maintained to the practical minimum. In order to accomplish this timing a
new layer may be started before the previous layer is completed.
The face from which placing of concrete is to commence shall be selected so that if an
emergency should occur which prevents the layer being completed the vertical construction
joint will be formed in a structurally acceptable position.
Concrete shall not be placed during rain sufficiently heavy or prolonged to wash mortar form
coarse aggregate on the exposed sloping faces of fresh concrete unless adequate shelter is
provided.
Concrete shall not be placed against any surface (including formwork, reinforcement,
embedded steelwork, adjacent concrete or rock) which during hot weather is not adequately
dampened to prevent excessive absorption of water from the fresh concrete.
Freshly placed concrete shall be protected from rainfall and from water running over the surface
until it is sufficiently hard to resist damage from this cause.
No traffic shall be allowed on any concrete surface until such time as it is hard enough to resist
damage by such traffic.
If the Contractor desires to impose structural loads on newly placed concrete, he shall make at least
three test cubes and cure them in the same conditions as the concrete they represent. These
cubes shall be tested singly at suitable intervals in order to estimate the time at which the nominal
strength is reached.
All concrete must be placed and compacted in its final position within thirty minutes (30 min) of
discharge from the mixer unless otherwise approved. No partially set material shall be used in
this work.
3.25 Concreting in Adverse Weather
No concreting will be allowed to take place in the open during storms or heavy rains. Where
strong winds are likely to be experienced additional precautions to ensure protection from driving
rain and dust shall also be taken.
The Engineer may withhold approval of commencement of concreting until he is satisfied that full
and adequate arrangements have been made.
Where approval has been given to carry out concreting operations at night or in places where
daylight is excluded, the Contractor is to provide adequate lighting at all points where mixing,
transportation and placing of concrete are in progress.
Where the ambient temperature exceeds thirty-two degrees Celsius (32oC), the Contractor shall
take special measures in the mixing, placing and curing of concrete. The temperature of the
concrete when deposited shall not exceed thirty degrees Celsius (30 oC). The Contractor shall
carry out all necessary special measures to ensure that the maximum concrete temperature after
placing shall not exceed fifty degrees Celsius (50 oC) or thirty degrees Celsius (30oC) above the
concrete temperature at the time of placing, whichever is lower.
During placing suitable means shall be provided to prevent premature stiffening of the concrete
placed in contact with hot surfaces.
The Contractor shall not mix and place concrete when the ambient temperature falls below three
degrees Celsius (3oC).
Concrete shall be protected during the first stage of hardening from the harmful effects of
sunshine, drying winds, cold, rain or running water. The Contractor shall pay particular attention
to the need to protect concrete immediately after the finishing operation and prior to its final set
and shall submit their proposals to achieve this protection for the Supervisor’s engineer approval.
Protection of concrete which has achieved its final set shall consist of one or more of the
following:
The use of saline water for curing purposes will not be permitted.
3.29.1 Materials
Unless otherwise directed or otherwise shown on the Drawings, hot rolled high yield
reinforcement shall be used throughout the works.
Where required, mild steel reinforcement, medium tensile steel reinforcement and high
tensile steel reinforcement shall comply with BS 4449. Cold twisted steel wire for the
reinforcement of concrete shall comply with BS 4482.
Before any steel reinforcement is embedded in the concrete any loose mill scale, loose rust and
any oil, grease or other deleterious matter shall be removed. Partially set concrete which may
adhere to the exposed bars during concreting operations shall likewise be removed.
Bar reinforcements shall be bent to the shapes shown on the Drawings and bending
schedules. All bars shall be bent cold, unless otherwise permitted by the Engineer. All
hooks, bends, and the like, unless otherwise shown on the Drawings, shall be to BS 4666.
The Contractor shall satisfy himself as to the accuracy of any bar bending schedules supplied
and shall provide all reinforcement in accordance with the Drawing. Bar reinforcement shall
be bundled and each bundle of steel shall be tagged with identifying tags, showing the size
and mark of the bar. The bundles shall be stacked clear of the ground in easily accessible
positions that do not in any way hinder the progress of work and shall be kept clean.
When placed in the work reinforcement shall be free from coatings or dirt, detrimental scale,
paint, oil or other foreign substances. When steel has on its surface rust, loose scale and
dust which is easily removable, it may be cleaned by a method approved by the Supervisor
engineer.
All reinforcing bars, ties, links and fabric shall be fixed in the positions shown on the
Drawings within the tolerances specified in BS 8666. In no case shall the cover specified on
the Drawings be increased by more than 5 mm.
Spacers shall be used to maintain the cover to all steel and shall be made of dense cement
mortar of one-part cement and two parts sand.
Spacers shall be triangular in section and only one acute edge shall bear against the
formwork, the flat side shall bear against the steel. Wire cast into the blocks to fix them to
the reinforcement shall be 1.6 mm diameter soft annealed iron. Spacers shall not be used on
the wet face of water retaining or water excluding structures. Chairs, stools, etc. shall be
used to maintain clearance between two or more layers of reinforcement.
Nothing shall be allowed to interfere with the specified position of reinforcement. The fixing
of reinforcement shall be checked before and during concreting, and particular attention shall
be given to the position of top steel in cantilever sections. During concrete placing a
competent steel fixer shall be in attendance to adjust and correct the position of any
reinforcement which may be displaced.
All reinforcement shall be provided in full lengths as indicated on the Drawings or bending
schedules. Splicing of bars, except where shown on the Drawings, shall not be permitted
without the written approval of the Supervisor engineer. Splices shall be staggered as far as
possible. Bar reinforcement shall not be welded without the Engineer's written permission.
In lapped splices, the bars shall be placed in contact and wired together in such manner as to
maintain a clearance between bars of not less than 50 mm.
Mesh or bar reinforcement shall overlap sufficiently to maintain a uniform strength and shall
be securely fastened at ends and edges. The edge lap shall not be less than 40 diameters of
the mesh reinforcement bar or two mesh widths whichever is greater.
The concrete cover to reinforcement shall be 50 mm unless otherwise shown on the Drawings.
The Contractor shall provide any necessary concrete pads for ensuring the cover is attained and
in no case shall timber packing be used.
3.31 Formwork
3.31.1 Definitions
Forms, formwork or shuttering shall mean all temporary moulds forming the concrete to the
required shape together with any special lining that may be required to produce the concrete
finish specified.
False work or centring shall mean the furnishing, placing and removal of all temporary
construction such as framing, props and struts required for the support of forms.
3.31.2 Materials
The formwork may be of seasoned, planed, tongued and grooved timber, plywood farefaced
blackboard, tempered hardboard, steel or as specified on the Drawings.
3.31.3 Forms
All forms shall be of wood or metal and shall be built grout-tight and of sufficient rigidity to
prevent distortion due to the pressure of the concrete and other loads incidental to the
construction operations. Forms shall be constructed and maintained so as to prevent
warping and the openings of joints due to shrinkage of the timber.
The forms shall be substantial and unyielding and shall be so designed that the finished
concrete will conform to the proper dimensions and contours. The design of the forms shall
take into account the effect of vibration of concrete as it is placed.
A grout check formed from 25 mm square hardwood timber shall be incorporated in the
formwork to provide a clean, level, horizontal joint on exposed concrete surfaces at the top of
each lift.
All joints in the formwork shall be either horizontal or vertical. End formwork shall be square
across the mass of concrete.
Where concrete is to be deposited to a slope steeper than 20 degrees to the horizontal, top
formwork shall be used to enable the concrete to be properly compacted unless the
Supervisor engineer agrees otherwise.
Openings for the inspection and cleaning of the inside of formwork for walls, piers and
columns shall be formed in such a way that they can be closed conveniently before
commencing to place concrete.
Form clamps, tie bolts and anchors shall be used to fasten forms. The use of wire ties to
hold forms in position during placing of concrete will not be permitted. Tie bolts and clamps
shall be positive in action and of sufficient strength and number to prevent spreading or
springing of the forms. They shall be of such type that no metal part shall be left within the
specified concrete cover. For water retaining sections, methods of fixing the forms which
result in holes through the concrete section when the formwork is removed shall not be used
and built-in wall ties shall be fitted with water baffles.
All forms for outside surfaces shall be constructed with stiff wales at right angles to the studs
and all form clamps shall extend through and fasten such wales.
The shape, strength, rigidity, grout tightness and surface smoothness of forms which are re-
used shall be maintained at all times. Any warped, bulged or otherwise damaged timber
shall be replaced. Forms which are unsatisfactory shall not be re-used. If the surface finish
on the formed concrete deteriorates as a result of deterioration of the faces of the forms, the
Supervisor engineer shall instruct that forms be resurfaced, or discarded.
All forms shall be treated with approved mould or similar oil or be soaked with water
immediately before placing concrete to prevent adherence of concrete. Any materials which
adhere to or discolour concrete shall not be used.
All forms shall be set and maintained true to the line designated until the concrete is
sufficiently hardened. Forms shall remain in place for periods which shall be as specified in
Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH
31
Building Construction: August 2020
Clause 3.26. When forms appear to be unsatisfactory in any way, either before or during the
placing of concrete, the Engineer shall order the work stopped until the defects have been
corrected.
All formwork shall be approved by the Supervisor engineer before concrete is placed within it.
The Contractor shall, if required by the Supervisor engineer, provide copies of calculations of
the strength and stability of the formwork and falsework. Notwithstanding the Supervisor’s
engineer approval of these calculations, the Contractor shall be held responsible for the
safety and adequacy of formwork.
Detailed plans for a falsework or centering shall be supplied by the Contractor to the
Supervisor engineer at least 14 days in advance of the time the Contractor begins
construction of the falsework. Notwithstanding the approval of the Supervisor engineer of
any designs for falsework submitted by the Contractor, the Contractor shall be solely
responsible for the strength, safety and adequacy of the falsework or centering.
All falsework shall be designed and constructed to provide the necessary rigidity and to
support the loads from the weight of green concrete and shuttering and incidental
construction loads.
Falsework or centering shall be founded upon a solid footing safe against undermining and
protected from softening. Falsework which cannot be founded on satisfactory footings shall
be supported on piling which shall be spaced, driven and removed in a manner approved by
the Engineer. The Supervisor engineer may require the Contractor to employ screw jacks, or
hard wood wedges to take up any settlement in the formwork either before or during the
placing of concrete.
Falsework shall be set to give the finished structure the required grade and camber shown
on the Drawings.
Where reinforcement or waterstops pass through the face of a joint the stopping off board
shall be drilled so that the bars or waterstop can pass through, or the board shall be made in
sections with a half round indentation in the joint faces for each bar so that when placed the
board is neat and accurate fit and no grout leaks from the concrete through the bar holes,
joints or around the waterstop.
Only approved chemical release agents, mould creams (emulsions of water in oil) or oils
containing a proportion of surfactant not exceeding 2 percent will be permitted. Water
soluble emulsions and oils without surfactant shall not be used. Oil based release agents
shall be applied at a rate of 7 square metres per litre one day in advance of concreting,
preferably by spray or roller. Chemical release agents shall be applied in accordance with
the manufacturer's recommendations.
New timber face work shall be given three coats of release agent before use on the work to
ensure uniformity of porosity on the surface.
On no account shall the release agent come into contact with the reinforcement.
The minimum periods which shall elapse between completion of placing concrete and
removal of forms are given in the following Table 3.2, and apply to ambient temperatures
higher than 10oC. At lower temperatures or if cements other than ordinary Portland are
involved, the Supervisor engineer may instruct longer periods.
Compliance with these requirements shall not relieve the Contractor of his obligation to
delay removal of formwork until such removal can be completed without damage to the
concrete.
3.33.1 General
After removal of the formwork no treatment of any kind other than that required for curing
the concrete shall be applied to the concrete faces until after inspection by the Supervisor
engineer. All honeycombed areas, deformed surfaces or other defective surfaces shall then
be repaired at the direction of the Supervisor engineer. Immediately following the
Supervisor’s engineer inspection of surface finish, all tie bolt cavities shall be filled with sand
cement mortar and the surface left smooth, sound, even and uniform in colour.
Should the finishes surface either as-stuck or after repair exhibit a non uniform colour or
texture, the Engineer shall have the right to order that the surface be given a skim coat and
then painted.
All joints between panels shall be vertical and horizontal unless otherwise directed. Suitable
joints shall be provided between sheets to maintain accurate alignment in the plane of the
sheets.
For warped surfaces, facings shall be built up of laminated splines cut to make a tight surface
which shall then be dressed and sanded to the required curvature.
Type F1: This finish is for surfaces against which backfill or further concrete will be
placed. Formwork shall consist of sawn boards, sheet metal or any other
suitable material which will prevent the loss of grout when the concrete is being
placed.
Type F3: This finish is for surfaces which will be in contact with water flowing at high
velocity and for surfaces permanently exposed to view where good appearance
and alignment are of importance. To achieve this finish, which shall be free of
boardmarks, the formwork shall be faced with plywood complying with BS 1088
or equivalent material in large sheets. The sheets shall be arranged in an
approved, uniform pattern. Wherever possible, joints between sheets shall be
arranged to coincide with architectural features or changes in direction of the
surface. Suitable joints shall be provided between sheets to maintain accurate
alignment in the place of the sheets. Unfaced wrought boarding or standard
steel panels will not be permitted for Type F3 finish. The Contractor shall ensure
that the surface is protected from rust marks, spillages and stains of all kinds.
Type F4: This finish is similar to that required for type F3 but is used in places where a
first class alignment and a dense surface free from airholes and other defects is
required, suitable for the application of decorative finishes, in very high velocity
water channels and in other similar circumstances.
Type U1: This is screed finish for surfaces of roads of foundations, beds, slabs, and
structural members to be covered by backfill, subsequent stages of construction,
bonded concrete topping or cement mortar beds to receive pavings, and on
exposed surfaces of paving where a superior finish is not required. It is also the
first stage of Type U2 and U3 finishes. The finishing operations shall consist of
levelling and screeding the concrete to produce a uniform, plane or ridged
surface, surplus concrete being struck off by a straight edge immediately after
compaction.
Type U2: This is a floated finish for exposed surfaces where a hard smooth steel trowelled
surface is not required. Floating shall be done only after the concrete has
hardened sufficiently, and may be by hand or machine. Care should be taken
that the concrete is worked no more than is necessary to produce a uniform
surface free from float marks.
Type U3: This is a hard smooth steel trowelled finish for surfaces exposed to water
flowing at high velocity. Trowelling shall not commence until the moisture film
has disappeared and the concrete has hardened sufficiently to prevent excess
laitance from being worked to the surface. The surface shall be trowelled under
firm pressure and left free from trowel marks.
Type U4: This finish is similar to Type U3 finish but the permissible tolerances are smaller.
All parts of concrete surfaces shall be in the positions shown on the Drawings within the
tolerances set out in Table 3.3 or Table 3.4.
Where precast units have been set to a specified tolerance, further adjustments shall be
made as necessary to provide a satisfactory straight or curved line. When the Supervisor
engineer has approved the alignment, the Contractor shall fix the units so that there is no
possibility of further movement.
Note 1:
Note 2:
Abrupt irregularities are not permitted in a Type F4 finish. Any residual irregularities which
remain after removal of formwork shall be removed by grinding to achieve a transition of 1
in 50 between the surfaces adjacent to the irregularity.
Notes:
D is the maximum allowable value of any sudden change of level in the surface.
E is the maximum allowable value of any gradual irregularity of the surface, as
indicated by the gap between the surface and a 3 m long straight edge or correctly
shaped template placed on the surface.
F is the maximum allowable value of the difference in level or position between a
straight edge or correctly shaped template placed on the surface and the specified
level or position of that surface.
Conduits shall be placed as near the centres of members as possible and sufficient space
shall be provided between adjacent conduits to prevent difficulties in the placing of concrete.
Box-outs, holes, grooves, apertures and the like shall be accurately set out in the formwork
prior to placing the concrete. Fixing blocks, ends of brackets, bolts and, where possible, built
in parts shall be cast into the concrete at the time of placing. No part of the concrete works
shall be cut out for any such item, or for any other reason, without the Supervisor’s engineer
permission.
The Contractor shall ensure that all sub-contractors are informed of his programme for the
structural works at the commencement of the Contract and that such sub-contractor's
requirements relating to concrete members are approved well in advance. The Contractor
shall obtain from all such sub-contractors complete information of their requirements
regarding conduits, pipes, fixing blocks, ducts, holes and any other items to be cast into or
formed in the concrete members. Failure of a sub-contractor to sub-contractor to supply
such information shall not be allowed to delay the progress of the Works.
Concreting shall be carried out continuously up to construction joints, the position and
arrangement of which shall be as indicated on the Drawings or as previously approved by the
Engineer. The Contractor is to allow for working beyond the ordinary working hours where
necessary in order that each section of concrete may be completed without any lapse while the
work is in hand. All construction joints are to be formed square to the work.
Where vertical construction joints are required, the joint face of the first stage concrete shall be
finished against a stopping-off board, or vertical end shutter, suitably notched to pass the
reinforcement. When the concrete is hard and the shutter is removed, the whole joint surface
shall be thoroughly hacked and roughened or scabbled with suitable tools so that no smooth skin
of concrete is visible and that all aggregates and solid matrix around them is exposed.
For horizontal or slightly inclined construction joints, the surfaces shall preferably be prepared
when the concrete has set but not hardened by jetting with a fine spray of water and brushing
with a stiff brush to remove the smooth skin and expose the aggregate without disturbing it.
Where this treatment is impractical and work is resumed after the concrete surface has hardened,
a similar procedure shall be adopted as on vertical joints.
If, in the opinion of the Supervisor engineer, any deleterious material has come into contact with
the concrete of the construction joint or if the concrete is honeycombed or unsound for any
reason, the concrete shall be cut back to such a depth as the Supervisor engineer shall order and
the roughened surfaces shall be thoroughly cleaned by compressed air and water jets or other
approved means.
Immediately before concreting is resumed, the roughened joint surface shall be thoroughly
cleaned with compressed air and water jets and slightly wetted and cement grout placed The
Contractor shall take precaution to avoid segregation of the concrete along the joint plane and to
obtain thorough compaction.
Precast concrete units shall be made in accordance with the provisions of this Specification
covering concrete work. Precast concrete units shall be manufactured under shed roofs and
protected from the weather. The units shall remain in the moulds for seven days and shall
remain protected for a further seven days, during which periods the concrete shall be
shielded by sacking or other approved material which shall be kept wet. The units shall then
be moved from the sheds and stacked in the open for at least a further seven days to season
before being set in position.
Precast concrete work shall be tested as directed by the Supervisor engineer and work failing
to meet the requirements of the Specification shall be rejected. Precast units that become
damaged during handling shall likewise be rejected.
The Contractor shall, when required, make arrangements with his supplier for access to the
supplier's work for the Supervisor engineer to inspect and carry out tests on precast concrete
units.
All precast units shall be marked with individual identification. Lifting hooks are to be
attached only to those positions shown on the Drawings or detailed by the Supervisor
engineer. The Contractor shall be deemed to have included in their rates for all measures
required to handle and stack units safely and without undue stressing.
Well in advance of the commencement of the work the Contractor shall seek the approval of
the Engineer regarding the proposed method of breaking out existing concrete or blockwork
in the positions shown on the Drawings or as directed by the Supervisor engineer.
Cement grout for general purposes shall consist of Portland cement and water mixed in the
proportion of one (1) part by volume of cement and one and a half (1.5) parts by volume of water.
The grout shall be used within one hour (1hr) of mixing.
Cement mortar shall be machine mixed and unless otherwise specified, consist of three (3) parts
of sand to one (1) part of Ordinary Portland cement mixed and thoroughly incorporated together.
Just enough water will be added to give a workability appropriate to its use. The above
proportions are by volume. Mortar shall be used whilst freshly mixed and no softening or
retempering will be allowed.
3.40.1 Material
Cement, water and fine aggregate shall conform to the requirements specified in the concrete
works. Mesh reinforcement shall be plain diamond expanded steel lathing to BS 1369 where
specified. Lime shall be to BS 980 and shall be mixed with water and allowed to stand prior to
use according to the manufacturer’s recommendations.
Lime putty may be mixed in mortar for finishing coat at 10% of sand by volume.
Waterproof mortar shall be made by mixing a waterproof agent into ordinary cement mortar. The
Contractor shall be responsible for selection and quality of the waterproof agent and this shall be
approved by the Engineer before use. The mixing and application shall be in accordance with the
manufacturer’s instructions.
3.40.3 Application
The surface which are to receive a rendering coat shall be free from all laitance, scum, loose
carbonate scale, loose aggregate dirt and other foreign matters. Concrete block, brick or stone
surfaces shall be sufficiently and uniformly damped immediately before application of mortar.
Concrete surfaces shall be kept thoroughly wet for 24 hours prior to the application of mortar.
Where shown on the drawings or directed by the Supervisor engineer, steel wire lath shall be
fixed to the brick, concrete block or concrete walls before applying cement mortar plaster.
Cement mortar shall be used within 30 minutes from the time of mixing. Retempering shall not be
permitted.
The total thickness of rendering plus finishing coat shall be 30 mm for the floors and 20 mm for
wall. Cement mortar finish shall be trowel finished unless otherwise specified. When the
finishing coat is applied, the entire surface of floor or wall shall be finished in one operation in
order to minimise joint marks.
When expansion and control joints exist in the base structure, provision shall be made to prevent
cracking of the mortar by inserting metal expansion beads within the coating thickness in a
manner approved by the Supervisor engineer.
The finished surface shall be perfectly plumb or level as the case may be except where otherwise
specified without any bulging, runs, bruises or stains.
After application of the finishing coat, the surfaces shall be kept continuously damp for not less
than 48 hours and then allowed to become thoroughly dry. Moistening shall be started as soon
as the surface has hardened sufficiently not to cause displacement or damage.
In situ concrete chambers shall be constructed generally in accordance with Section 3 of this
Specification.
Covers and slabs shall be the type, size and weight shown in the drawings. Care shall be taken
to see that slabs are even so that the cover can seat without rocking.
Covers and frames shall be provided as shown on the drawings. The tops of the covers shall be
flush at all points with the surrounding surface of paved areas or as directed in unpaved areas.
Any slight adjustment of the slab level which may be necessary to accomplish this shall be
effected by topping the side walls with concrete.
4 STONEWORK
Masonry shall be built to the lines and levels shown on the Drawings.
For face work the stones shall show a face of not less than 0.025 m2 and not more than 0.1 m2 in
area and none shall be less than 100 mm in depth; they shall be laid to give a uniformly random
appearance and shall be selected in laying so as to present an even distribution of large and
small stones on the face.
For the arises, stones shall be roughly squared, quarry split and of a size to give outbands
varying from 300 mm to 500 mm in length and inbands from 150 mm to 250 mm. The alignment
of arises shall be set true to the required lines.
The stones shall be set in mortar with their natural bedding plane (if any) as near normal as
possible to the face or normal to the line of thrust in the case of load bearing structures.
Particular care must be given to obtaining a sound bond both longitudinally and transversely and
there shall be at least one bonder, or length not less than two-thirds of the wall thickness, in each
square yard of wall face.
The mortar, unless otherwise specified, shall be machine mixed cement and sand in the
proportion of one part to three (1:3) parts generally as described in the specification. Mortar shall
completely fill all interstices between the stones.
The face joints in rubble masonry may vary in thickness from 10 mm to 20 mm. They shall be
finished as a neat weathered joint with mortar while the work proceeds where the masonry is
specified to be "unpointed". Where pointing is specified, the joints in each day's work shall be
raked out to a depth of not less than 25 mm before the mortar has set. Subsequently the joint
shall be filled with mortar and finished in accordance with Clause 4.6. The face of the masonry is
to be kept wet while the pointing is proceeding. Provision shall be made to clean all exposed
faces both as work proceeds and on completion so that they are left in a neat, tidy and clean
condition.
Building of masonry will not be allowed in heavy rain without the written consent of the Supervisor
engineer. Building shall only proceed when suitable precautions to the satisfaction of the
Engineer shall be taken against the action of rain on newly placed mortar. If for any reason of
urgency, the consent of the Supervisor engineer should be desired to a departure from these
provisions, the Contractor shall submit to the Engineer for approval their proposals for protecting
the materials and work from the weather.
The arrangement of the stones on the exposed face or faces of the masonry shall be as
described below according to which type is called for on the Drawings.
(a) Random rubble uncoursed masonry shall be built with stones of irregular shapes taken
generally as they come from the quarry, preparation being limited to the removal of
inconvenient corners and excrescences. They shall be selected as the work proceeds to
give a uniformly random appearance and no attempt shall be made to form courses.
(b) Random rubble masonry brought to courses shall be generally as the preceding type
except that it shall be levelled up to courses between 300 mm to 400 mm in depth and
coinciding with the quoin stones.
(c) Squared rubble coursed masonry shall be built in courses between 100 mm to 250 mm in
depth of stones squared to rectangular shapes and selected so that all stones in one
course are of approximately the same height.
Unless otherwise directed by the Supervisor engineer, all masonry stones, when incorporated in
the Works shall be laid on its natural bed, except in the case of arches where the natural bed
shall be radial.
Special stonework shall consist of approved stones dressed to the shapes and dimensions and
with the faces tooled, all as shown on the Drawings. All stones shall be laid true to line and
centre with mortar joints as shown on the Drawings.
Unless otherwise shown on the Drawings, pointing to masonry joints shall be flush and shall be
formed by raking the joint clean and then filling it with pointing consistency mortar which shall be
given a flush face with a steel trowel.
Hand placed rubble filling shall consist of stones individually selected and placed by hand firmly in
place in bearing contact with each other or with the sides of the space to be filled; the voids shall
be carefully filled with small rocks and spalls wedged together to form a compact mass. The
sides of stones shall be roughly trimmed if necessary with a spalling hammer to obtain a
reasonably close fit. On the exposed face the stones shall be placed with their flattened sides
uppermost and in the plane of the face.
5 BUILDING WORKS
5.1 Masonry
Building stone for masonry walls shall be cut to true rectangular shape 225 mm x 225 mm and be
of minimum length from a source approved by the Engineer.
Dressed stone for masonry tanks shall not exceed 300 mm in length and shall be soaked in water
for 24 hours, prior to being laid.
Precast concrete blocks shall conform to B.S.6073 Parts 1 and 2. Blocks shall be solid or hollow,
of the sizes required and shall be made in approved moulds of metal construction of sufficient
strength to ensure the manufacture of dead square blocks of even size and shape.
Concrete blocks for general walling shall be 450 mm x 200 mm. Purpose-made half or three-
quarter length blocks shall be used where required for bonding, and cutting of blocks to obtain
bond will only be permitted where expressly allowed by the Engineer.
5.3 Blockwork
The blocks for walling shall be properly bonded together in such a manner that no vertical joint in
any one course shall be within 100 mm of a similar vertical joint in the course immediately above
or below.
Alternative courses of walling at all angles and intersections shall be carried through the full
thickness of the adjoining wall. All perpends, reveals and other angles of walling shall be built
strictly true and square.
The blocks shall be bedded and jointed in cement mortar 1:3 with beds and joints not more than
20 mm or less than 12 mm thick, all flushed up and grouted solid as the work proceeds. All
walling shall be properly protected as the mortar is setting.
Ends of lintels, cills, joints, roof trusses etc., are to be pinned up to the under side of concrete
beams and slabs with cement mortar.
Timber frames are to be built in with holdfasts and bedded solid and pointed both sides in cement
mortar. Lugs of window, door and louvre frames are to be built in or cut and pinned to blockwork.
Frames are to be bedded solid in mortar and pointed in approved mastic applied externally.
Paving Slabs shall not be less than 50 mm thick and shall be of precast concrete with basalt or
phonolite aggregate. They shall comply in all respects with: -
B.S. 368 for "Precast Concrete Flags". They shall have minimum side dimensions of 600 mm
and shall be hydraulically pressed during manufacture.
Sills to windows shall comply with B.S. 5642 Part 1. They shall measure 105 mm deep, showing
70 mm at the front edge, by 175 mm wide and be of appropriate length as indicated on the
Drawings. All sills shall be cast with a recessed throating under the front edge and shall bear 150
mm on supports.
Lintels to windows, louvre and door openings where these are separate from the reinforced
concrete ring beam shall be of precast concrete complying in all respects with B.S.1239. They
shall bear 300 mm on supports and shall be cast with a recessed throating under the front edge.
Design calculations for lintels shall be submitted to the Supervisor engineer for approval before
casting is commenced.
Airbricks shall be as shown on the drawings and be of an approved type and manufacture. They
shall be supplied complete with a fine copper mesh woven wire fly proof screening fixed to the
back face. Openings through walls shall be formed to the net size required and rendered smooth
in cement mortar. Where openings occur in cavity walls the walls shall be built solid all round the
openings.
a) Plastering
Internal plastering is to be carried out in accordance with B.S. Code of Practice C.P.211
or equivalent approved.
All joints in walling, etc., are to be raked clean for not less than 10 mm deep before any
plaster or rendering is applied.
All concrete surfaces which are to be plastered are to be hacked or otherwise suitably
roughened to provide a key.
All surfaces to receive plaster are to have the suction correctly adjusted by the
application of clean water.
All arises shall be finished true and slightly rounded except where otherwise stated.
The Contractor shall cut out and make good all cracks blisters and other defects and
leave the whole of the plaster work perfect on completion. On no account shall plaster of
paris be used to effect repairs.
Where plastering or rendering is applied over a joint between block walling and concrete,
the plaster or render is to be vee grooved 10 mm deep to coincide with the joint.
b) Cement Rendering
Cement rendering shall be applied in one coat of 10 mm thickness and shall be in the
ratio of 1 part of cement to 3 parts of sand, finished with a wood float, with use of SBR of
200 gr per M2.
c) Roughcast Finish
Roughcast finish, where ordered, shall be to the same consistency as cement rendering,
and shall be applied by means of an approved paddle-gun onto a partly set base coat of
cement rendering. Roughcast finish shall terminate in well defined and straight vertical
and horizontal edges, and shall stand proud of any surrounding rendered finish by at
least 5 mm.
Water proof paper shall comply in all respects with B.S. 1521 for Waterproof Building Paper,
Class B, and shall contain fibrous reinforcement.
Polythene sheeting shall comply with B.S.4646 "High Density polythene sheet for general
purposes".
Steel door frames are to be fixed in accordance with the manufacturers recommendations.
Steel doors and frames shall comply with the requirements of BS 6510
Timber door frames are to be fixed with holdfasts screwed to the frames one end and built into
blockwork or concrete at the other end. Door frames shall have three holdfasts at each side.
The holdfasts shall be of 6 mm x 25 mm galvanised wrought iron 200 mm long, one end turned
up, twice drilled and countersunk for screwing to frames with stout screws and other end formed
swallowtail for building into brickwork etc.
All timber is to be sound, straight, of matured growth, square edge and free from whitewood,
shakes, large loose or dead knots, cracks, waves edges or other defects and blemishes except to
the extent to which the Engineer considers that the timber is not rendered unsuitable for its
intended use.
5.10 Paint
All paint used in the Works shall be of approved manufacture, type and colour delivered to the
Site in sealed containers from the manufacturers.
All materials are to be supplied in containers clearly marked with the manufacturer's name or
trademark and a description of the contents. All materials for multiple coat work, e.g. priming,
under coat and finishing coat shall be supplied by the same manufacturer and are to be those
recommended by the manufacturer as suitable for using together. Undercoats are to be tinted
different shades, to suit the finishing coat, and are to be readily distinguishable. Samples of paint
to be used shall be supplied to the Supervisor engineer for his approval.
Door, and door frames, shall be knotted, stopped, primed and painted with three coats of paint as
directed by the Supervisor engineer.
5.11 Painting
The type of paint, etc., to be used, the number of coats applied and any special process or
treatment required shall be as specified herein.
Paint may be applied by paint rollers on concrete or over surfaces where a light stipple is required
with the permission of the Supervisor engineer.
Rubbing down prior to final coat shall be done by the wet process with pumice stone or
waterproof glass paper. Preliminary coats of paint shall be lightly rubbed down with fine
sandpaper before the next coat is applied.
No external paintwork shall be carried out during wet weather, or upon surfaces that are not
thoroughly dry.
Primed or undercoated work shall not be left in an exposed or unsuitable situation for an undue
period before completing the painting process.
All metal fittings and fastenings are to be removed before the preparatory processes are
commenced, and shall not be refixed in position until after the finishing coat has hardened.
Except for the application of first coat priming, spray painting with approved machines shall be
permitted only with the consent of the Supervisor engineer and must be carried out in accordance
with directions to be supplied by the manufacturers of the material which shall be specially
prepared for this method of application.
All paintwork shall be cleaned down on completion and all marks due to spill removed. All
painted finishes shall be left to the complete satisfaction of the Supervisor engineer.
All undercoating and finishing used on the same work are to be those recommended by the
manufacturer for using together.
Where directed by the Supervisor engineer, the Contractor is to prepare panels showing the
colour schemes proposed for the work for final approval of the Supervisor engineer.
All brushes, tools, pots, kettles etc., used in carrying out the work shall be clean and free from
foreign matter, and are to be thoroughly cleaned out before being used for a different type of
class or material.
Before painting, lacquering, varnishing or enamelling is started, every possible precaution must
be taken to keep down dust.
An ample supply of clean dust sheets to protect the work during its progress are to be at hand.
No dilution of painting materials shall be allowed except strictly as detailed by the Manufacturer in
directions to be supplied or by special permission of the Supervisor engineer. The mixing of
paints of different types shall not be permitted.
All materials are to be thoroughly stirred and mixed when the containers, etc. are opened and
when transferring to painters' kettles. Where necessary the paints are to be strained to remove
all skin, etc. before application. All containers shall be kept securely covered with tight fitting lids
when not in use.
Primers and subsequent coats shall be applied by brush and allowed a minimum period in which
to dry and thoroughly harden in accordance with directions to be supplied by the manufacturer of
the materials.
No paint shall be applied to surfaces structurally or superficially damp and all surfaces must be
ascertained to be free from condensation, dust, oil, etc., before the application of each coat.
Preparation: clean down with a stiff brush to remove loose dust, efflorescence, etc. and
leave work to dry out thoroughly. The surface shall be left as long as possible to ensure
that no further efflorescence will appear.
Finish: apply two coats plastic emulsion paint by brush, roller or other means, as directed
by the Engineer.
Preparation: Metal work delivered unprimed shall be chipped, scraped and wire brushed
to remove all rust and loose scale and cleaned to remove all dirt and grease.
Metal work delivered primed shall be thoroughly washed down to remove all dirt and
grease. All defective paint, blistered, crazed or not firmly adhering, etc., shall be
removed by scraping back to a firm edge or, if necessary, the surface shall be completely
stripped back to clean metal.
Priming:
ii) Surfaces exposed and which are to be painted with finishing coats: 1 coat
approved red lead primer.
Finish
c) Woodwork
Preparation: All timber used for grounds or battens or any purpose which precludes
inspection and maintenance is to be treated with one coat of aluminium wood primer.
All new and unprimed woodwork is to be free from dirt and grease and to be examined
for defects. Any large or loose knots are to be cut out and neatly plugged. Smaller knots
are to be treated with two thin coats of knotting.
Woodwork to be painted shall be well rubbed down and primed with aluminium wood
primer well brushed into the wood. All knots shall be covered with good shellac knotting
before priming and all defects shall be filled with hard stopping after priming. Plywood
shall be filled over the entire surface with an approved brush filler.
Finish: Two coats of exterior grade undercoat shall be applied followed by one coat of
exterior or interior grade high gloss finish as appropriate.
The general arrangement of the drainage system shall be to the Supervisor’s engineer approval.
Bituminous roofing felt shall be in accordance with CP 144, type 2E, suitable for tropical
conditions. Each layer shall be applied to the roof surface strictly in accordance to the
manufacturers instructions. A protective layer of light coloured chippings shall be applied to the
finished surface with an approved adhesive.
6.1 GENERAL
SAMPLES
The sample needs the approval of the Supervisor engineer
PREPARATION
EXISTING BACKGROUNDS/BASES GENERALLY:
Efflorescence, laitance, dirt and other loose material: Remove.
Deposits of oil, grease and other materials incompatible with the bedding: Remove.
Tile, paint and other nonporous surfaces: Clean.
Wet backgrounds: Dry before tiling.
NEW PLASTER
Plaster: Dry, solidly bedded, free from dust and friable matter.
Plaster primer: Apply if recommended by adhesive manufacturer.
6.2 FIXING
FIXING GENERALLY
Colour/ shade: Unintended variations within tiles for use in each area/ room are not permitted.
Variegated tiles: Mix thoroughly.
Adhesive: Compatible with background/ base. Prime if recommended by adhesive
manufacturer.
Use of admixtures with cementitious adhesives: Only admixtures approved by adhesive
manufacturer.
Cut tiles: Neat and accurate.
Fixing: Provide adhesion over entire background/ base and tile backs.
Final appearance: Before bedding material sets, make adjustments necessary to give true,
regular appearance to tiles and joints when viewed under final lighting conditions.
Surplus bedding material: Clean from joints and face of tiles without disturbing tiles
SETTING OUT
Joints: True to line, continuous and without steps.
Joints on walls: Horizontal, vertical and aligned round corners.
Joints in floors: Parallel to the main axis of the space or specified features.
Cut tiles: Minimize number, maximize size and locate unobtrusively.
Joints in adjoining floors and walls: Align.
Joints in adjoining floors and skirtings: Align.
Movement joints: Where locations are not indicated, submit proposals.
GROUTING
Sequence: Grout when bed/adhesive has set sufficient to prevent disturbance of tiles.
Joints: 6 mm deep (or depth of tile if less). Free from dust and debris.
Grouting: Fill joints completely, tool to profile, clean off surface. Leave free from blemishes.
Profile: Flush.
Polishing: When grout is hard, polish tiling with a dry cloth.